You are on page 1of 4

DP World Dakar

Port d'Ndayane - Advance Works


MEASUREMENT SHEET
Date: 20.06.2023
BOQ Item Number : 3.3
BOQ DESCRIPTION Construction of Fencing & Gates Work
Substructure works Fencing Foundation (Formwork Quantity )

Description Nr Area (m2) L W H QTY Gridline (x) Gridline (y) Level Drawing Nr. Revision Remarks

Quantity of Formwork As per Drawing

1- Fence Foundation 1,212.53 1.00 2.40 1.00 0.55 1,600.54

123.49 1.00 2.40 1.00 0.55 163.00

Gate Foundation 2.00 1.00 1.60 1.00 1.30 4.16


2.00 1.00 1.20 1.00 1.30 3.12

1,770.82 m2
1- Quantity of Formwork for 20 no. Foundations pouring together (500*500*550mm)
A- Ply Wood (2440*1220*18mm) 20.00 1.00 1.00 1.00 0.55 11.00 Total No. of Foundation 1,336.02
No. of sets as per 20 foundation 66.80
2.00 1.00 12.66 1.00 0.55 13.93 Quantity for 20 foundations (m2) 24.93
TOTAL 1665.34

24.93 m2 Formwork (repetitions : 6 times) 277.56 M2 93

B- White Wood 22.00 2.00 0.55 1.00 1.00 24.20 Total No. of Foundation 1,336.02
(100 x 100 x 3000mm) No. of sets as per 20 foundation 66.80
Quantity for 20 foundations (m) 24.20
TOTAL 1616.58

24.20 M Formwork (repetitions : 6 times) 269.43 M 90

C- White Wood 3.00 2.00 12.66 1.00 1.00 75.96 Total No. of Foundation 1,336.02
(100 x 50 x 3000mm) 3.00 2.00 0.55 1.00 1.00 3.30 No. of sets as per 20 foundation 66.80
Quantity for 20 foundations (m) 79.26
TOTAL 5294.63

79.26 M Formwork (repetitions : 6 times) 882.44 M 294

D- Form Oil Formwork quantity (m2) 1,665.34 m2


Covering area/ Liter (m2) 35.00

Total Form Oil (Liter) 47.58 Liter 48

E- Nails Total No. of Foundation 1,665.34 m2


Required Quantity (Kg)/M2 0.28
Total Nails Qty. (kg) 457.97 Kg 458
2- Quantity of Formwork for Gate Foundations pouring together (600*600*1300 mm)

A- Ply Wood (2440*1220*18mm) 2.00 1.00 1.60 1.00 1.30 4.16


2.00 1.00 1.20 1.00 1.30 3.12

7.28 m2 7.28 M2 2.45

B- White Wood 2.00 8 1.30 1.00 1.00 20.80


(100 x 100 x 3000mm)

20.80 M 20.80 M 7

C- White Wood 2.00 8.00 0.60 1.00 1.00 9.60


(100 x 50 x 3000mm) 2.00 8.00 0.80 1.00 1.00 12.80
2.00 12.00 1.00 1.00 1.30 31.20

53.60 M 53.60 M 18

D- Form Oil Formwork quantity (m2) 7.28 m2


Covering area/ Liter (m2) 35.00

Total Form Oil (Liter) 0.21 Liter 0.21

E- Nails Total No. of Foundation 7.28 m2


Required Quantity (kg)/M2 0.28

Total Nails Qty. (kg) 2.00 Kg 2.00


Summary for Fencing formwork Material

Req. Description Quantity Unit MRF Size

Plywood (Waterproof) 284.84 M2 (1220 x2440 x18mm)

White Wood 290.23 M (100x 100x 3000mm)

White Wood 936.04 M (100 x 50 x 3000mm)

Form Oil 1,672.62 M2


Nails and 1,672.62 M2
consumables
Actual MRF Quantity
Unit
Quantity With 10% Extra

96 105 No.

97 106 No.

312 343 No.

48 53 Liter

460 506 Kg