BLDG6241– Building Information Modeling in Construction

Construction Progress Monitoring


Dr. Jong Won Ma
Assistant Professor

Department of Building, Civil and Environmental Engineering


Concordia University

1
Timeline
Date Week Topics Assignment Due
Jan. 11 1 Lecture 1: Course Introduction & Lecture 2: Introduction to BIM

Lecture 3: Setting Up a Project for Success & Lab 1: Hands-on 3D Modeling (Autodesk Revit
Jan. 18 2
Architecture)
Jan. 25 3 Lecture 4: Model-based Cost Estimating & Lab 2: Hands-on Model-based Cost Estimating

Feb. 1 4 Quiz 1 & Teams to work on HW1 in class

Group Presentations: HW 1 (presenting groups 1-4) & Quiz 1 Re-visit HW1


Feb. 8 5
Lecture 5: Project Scheduling and 4D Simulation & Lab 3: Hands-on 4D Simulation
Feb. 15 6 Quiz 2 & Teams to work on HW2 in class
Group Presentations: HW 2 (presenting groups 5-8)
Feb. 22 7 HW2
Lecture 6: Design Coordination & Lab 4: Hands-on Design Coordination
Mar. 1 8 No class - Mid-term break
Quiz 3 & Teams to work on HW3 in class Synthesis Report
Mar. 8 9
Outline
Group Presentations: HW 3 (presenting groups 9-12) HW3
Mar. 15 10 Lecture 7: Construction Progress Monitoring Technologies & Lab 5: Hands-on As-built Modeling and
Documentation
Mar. 22 11 Guest Lecture (Austin Commercial) & Lab 5: Hands-on As-built Modeling and Documentation

Guest Lecture (Autodesk) & Lecture 8: Last lecture


Mar. 29 12
Teams to work on HW4 in class
Quiz 4 HW4, Synthesis
Apr. 5 13
Group Presentations: HW 4 (presenting groups 13-15) Report

2
Project Timeline
Project
Monitoring
Design &
Planning
&
Control

Construction
Design Development
QTO & Cost Estimation
(HW1)
Geometric validation Commissioning
- Design plans & & Hand-over
specifications
4D Scheduling Schedule tracking
(HW2) - Construction schedules
Design Operation
Equipment/Material
Coordination tracking
(HW3)
3
Project Monitoring & Control
• Project Monitoring: To track the progress, identify and
detect any deviations from BUDGET ($) / SCHEDULE (T) /
QUALITY
• Project Control: To correct the project to be on track. Bring
project performance (BUDGET, SCHEDULE, QUALITY) back
to the plans OR revise the plans
4
Project Monitoring
Construction

How?
Budget
Document the
jobsite VS Schedule

Quality

https://www.clearpointstrategy.com/dashboards/budget-vs-actual-dashboard
https://vertexeng.com/insights/as-planned-versus-as-built-method/ 5
BIM-based Project Monitoring
Construction

How?
Budget
As-
As-built
SCAN
VS Schedule planned
BIM
Quality

6
As-built Scanning Technologies

• Images (Ground & Aerial)


• Videos
• 3D Scans (Ground & Aerial)

7
As-built Scanning Technologies
Images (Ground) – Matterport Indoor 3D Modeling

https://youtu.be/WxPa5qUG6rY

8
As-built Scanning Technologies
Images (Aerial) – DJI Mavic Pro & DroneDeploy https://youtu.be/NS8WLnoFqyE

9
As-built Scanning Technologies
Videos – time-lapse

<Concordia’s pop-up building: 80% of the Learning Square was


https://www.wcctv.com/products/#type=TimeLapseVideo/
https://evercam.io/ assembled in a single weekend> https://youtu.be/7xs-3UTd_Ng

10
As-built Scanning Technologies
Manual 3D Scans (Ground) – Laser Scanners
Leica’s BLK360

FARO’s M70

https://youtu.be/7INzgIahleg

11
As-built Scanning Technologies
Automated 3D Scans (Ground)

Laser scanner (e.g.,


Leica) mounted on
autonomous robot
(e.g., Boston
Dynamic’s Spot)

https://youtu.be/aq5SHrw6WSk

12
BIM-based Project Monitoring
D4AR: 2D Images -> 3D Point Clouds VS As-planned BIM

Golparvar-Fard, M., Peña-Mora, F., & Savarese, S. (2009). D4AR–a 4-dimensional augmented reality model for
automating construction progress monitoring data collection, processing and communication. Journal of information
technology in construction, 14(13), 129-153.

13
BIM-based Project Monitoring
Cyclone 3DR: Laser scanned 3D Point Clouds VS As-planned BIM

https://youtu.be/onkk5rwpZLY

14
BIM-based Project Monitoring
Doxel: Laser scanning using robot + Artificial Intelligence (Detection)

https://youtu.be/0369vlp_fjg

15
BIM-based Project Monitoring
Augmented Reality

https://youtu.be/hxbyEzs_pHE

16
Project Timeline
Design &
Planning

Construction

As-built Scan Commissioning


& Hand-over
VS
As-planned BIM Operation

17
Project Timeline
As-built Scan
Design &
Planning VS
As-built BIM
Construction

As-built Scan Commissioning


& Hand-over
VS
As-planned BIM Operation

18
As-built BIM
What?
• Creating a digital representation of an existing facility with its physical and functional
characteristics ensuring HIGH accuracies of geometric information
• A Building Information Model of an existing facility
Why?
• As-built documentation
• The only reliable resource/baseline for operation & management (O&M)
• Enabling an accurate digital twin by providing as-built 3D model
How?
• Scan-to-BIM

19
As-built BIM Generation

20
As-built BIM Generation

21
As-built BIM Generation

22
As-built BIM-based O&M
Digital Twin for the entire campus

https://youtu.be/iZJN5RzOJEA

23
Important note
• Challenges:
Trusting the technologies
Right knowledge - Understand the outputs & how it works (3D model
from images vs 3D scans)
Garbage in, garbage out
Cost – Training personnel / Hardware / Software
• Start with the end in mind
• Decision-makers are always needed
24
Next class
• Guest lecture
• Lab 5 & HW 4

25
Q&A

26