February 21, 2020
Date MT.STELLAR LILAC / Voyage No.2004
Name Of Vessel PCL 1: 5,000 MT / RBD PALM OIL
Quantity/Commodity
PCL 2: 1,500 MT / PALM FATTY ACID DISTILLATE
PCL 3 : 500 MT / PALM FATTY ACID DISTILLATE
Port of Loading BELITUNG ,INDONESIA
Port of Discharge PORT KLANG , MALAYSIA
Shipper ASTRA KLK
Cleint
Neste Singapore Pte Ltd
Dear Sirs,
Please find below Loading status regarding loading operation of the above-mentioned vessel:
Vessel Arrival Pilot Station February 18, 2020 At 21.30 Hrs
Vessel Notice of Tendered on February 18, 2020 At 22.12 Hrs
Sea Pilot On Board on February 21, 2020 At 11.40 Hrs
Drop Anchorage on February 21, 2020 At 11.18 Hrs
Free Pratique Granted on February 21, 2020 At 13.00 Hrs
Pilot on board for berthing on February 21, 2020 At 11.40 Hrs
First line on shore February 21, 2020 At 12.06 Hrs
Berthed – All fast at SWP Jetty February 21, 2020 At 12.12 Hrs
Gangway down February 21, 2020 At 12.30 Hrs
Surveyor on board on February 21, 2020 At 13.50 Hrs
Key Meeting February 21, 2020 At 13.50-14.20 Hrs
Commenced Tanks inspected February 21, 2020 At 14.20 Hrs
Completed Tanks Inspection February 21, 2020 At 15.20 Hrs
NOR. Accepted February 21, 2020 At 15.20 Hrs
Commenced Ullage / Sounding (RBDPO) February XX,2020 At XX.XX Hrs
Completed Ullage / Sounding (RBDPO) February XX,2020 At XX.XX Hrs
Cargo calculation completed (RBDPO) February XX,2020 At XX.XX Hrs
Commenced Ullage / Sounding (PFAD) February XX,2020 At XX.XX Hrs
Completed Ullage / Sounding (PFAD) February XX,2020 At XX.XX Hrs
Cargo calculation completed (PFAD) February XX,2020 At XX.XX Hrs
Document On Board February XX,2020 At XX.XX Hrs
Vessel sailing etd February XX,2020 At XX.XX Hrs
This report refflect our finding at time and place of inspectionand does not refer to any other matter. this report is issued without prejudice and on the understanding
that it does not relieveparties from their contractual obligations. All inspection covered in this reporthave been carried out to do best of our knowledge and ability and
in accordance with practice and standard generally accepted in trade. Our responsibilityis limited to the exercise of reasonable care and due diligence.
This report is issued under our General Terms and Condition, copy of which is available upon request or may be accessed at www.ptsi.co.id
Fl. 1 de 5
LIQUIDS REPORT
Place, date and time of inspection: Belitung, Indonesia Port at SWP Jetty On February 21, 2020 at 14.20 – 15.20
Hrs (Local Time).
This report refflect our finding at time and place of inspectionand does not refer to any other matter. this report is issued without prejudice and on the understanding
that it does not relieveparties from their contractual obligations. All inspection covered in this reporthave been carried out to do best of our knowledge and ability and
in accordance with practice and standard generally accepted in trade. Our responsibilityis limited to the exercise of reasonable care and due diligence.
This report is issued under our General Terms and Condition, copy of which is available upon request or may be accessed at www.ptsi.co.id
Fl. 2 de 5
LIQUIDS REPORT
Tank Last Cargo 2ndLast Cargo 3rd Last Cargo Coating
No
PALM FATTY ACID STAINLESS
3S CRUDE PALM OIL MONOTHYLENE GLYCOL
DISTILLATE STEEL
PALM FATTY ACID STAINLESS
4P BUTHYL CELLOSOLVE CRUDE PALM OIL
DISTILLATE STEEL
PALM FATTY ACID SPENT BLEACHING EARTH STAINLESS
5P LMO SLACK WAX
DISTILLATE OIL STEEL
PALM FATTY ACID VINYL ACETATE STAINLESS
5S CRUDE PALM OIL
DISTILLATE MONOMER STEEL
PALM FATTY ACID STAINLESS
6P CRUDE PALM OIL MONOTHYLENE GLYCOL
DISTILLATE STEEL
PALM FATTY ACID PALM FATTY ACID STAINLESS
6S LMO SLACK WAX
DISTILLATE DISTILLATE STEEL
PALM FATTY ACID STAINLESS
7P ACETON CRUDE PALM OIL
DISTILLATE STEEL
PALM FATTY ACID STAINLESS
7S SPO SLACK WAX BENZENE
DISTILLATE STEEL
Heating Coils Tested : ( x ) Yes ( ) No
Heating System : Heating Coils by Steam
Tank coating Stainless steel
Tank cleaning method COT 4P,5S,7P & 7S :
The quantity shipped was ascertained by measurement of shore tank before and after loading at SWP Jetty Port of
Belitung, Indonesia with the following results:
Condition of shorelines before loading: EMPTY / after loading EMPTY
BR-1
BR-3
Total Delivered :
Weather Condition: Drizzling or Raining / Normal & Fine
This report refflect our finding at time and place of inspectionand does not refer to any other matter. this report is issued without prejudice and on the understanding
that it does not relieveparties from their contractual obligations. All inspection covered in this reporthave been carried out to do best of our knowledge and ability and
in accordance with practice and standard generally accepted in trade. Our responsibilityis limited to the exercise of reasonable care and due diligence.
This report is issued under our General Terms and Condition, copy of which is available upon request or may be accessed at www.ptsi.co.id
Fl. 3 de 5
LIQUIDS REPORT
PCL 2. 1500 MT / PALM FATTY ACID DISTILLATE
Quantity Quantity
Tank Sounding Temp Liters Density Density Weight MT Weight MT
o
. C loaded (In loaded (In
Nr. (M) (M3) (In Air) (In Vac) (In Air) (In Vac) Air) Vac)
BF-1
BF-2
Total Delivered :
BF-2
Total Delivered :
Weather Condition: Drizzling or Raining / Normal & Fine
This report refflect our finding at time and place of inspectionand does not refer to any other matter. this report is issued without prejudice and on the understanding
that it does not relieveparties from their contractual obligations. All inspection covered in this reporthave been carried out to do best of our knowledge and ability and
in accordance with practice and standard generally accepted in trade. Our responsibilityis limited to the exercise of reasonable care and due diligence.
This report is issued under our General Terms and Condition, copy of which is available upon request or may be accessed at www.ptsi.co.id
Fl. 4 de 5
LIQUIDS REPORT
FINAL DRAFT : - FWD : M - AFT : M - TRIM : M - LIST : NIL
Notes :
- Vessel delay berthing due to a waiting port occupied by MV. NASCHIO 08 she sail at 11.30/21
- ETC on 22/02/2020 at late AM
Best Regards
This report refflect our finding at time and place of inspectionand does not refer to any other matter. this report is issued without prejudice and on the understanding
that it does not relieveparties from their contractual obligations. All inspection covered in this reporthave been carried out to do best of our knowledge and ability and
in accordance with practice and standard generally accepted in trade. Our responsibilityis limited to the exercise of reasonable care and due diligence.
This report is issued under our General Terms and Condition, copy of which is available upon request or may be accessed at www.ptsi.co.id
Fl. 5 de 5