Category Barriers
Area (e.g. IND, RES, GU) RES Project # 8193 Location Haii Al Jaar
Is it Compliant?
No. Item Addressed
1: Yes 2: No 3: N/A
1 Are all gaps where the hazard of a fall, no matter the distance, protected with barricades?
2 Are protective barricades, floor & wall covers capable of supporting 200 pounds (90.7 kg) of force, and secured in place?
3 Are protective barricades of excavations and for preventing falls from height, where possible, a distance of 1.8m from the edge?
4 Is edge protection complete with top and mid-rail, toe-board ?
5 Have barricades with signage been set up at the base of scaffolds to protect persons on the ground from falling materials?
6 Has the work area surrounding lifting operations / man-lifts been cordoned off using barricades & signage?
7 Are all covers (of holes in floors) secured in place and clearly marked "caution - hole below" in the language of the workers?
Are all covers (of holes in floors) made of a minimum 3/4" (19mm) exterior plywood, extending a minimum of 4" (102mm) from
8 the edge of the hole and fixed in-place?
Are wall openings, service ducts, elevator shafts, risers etc. barricaded with guardrails (top & mid) and orange mesh, or covered
9 with exterior plywood?
10 When minor hazards are expected to last more than 24 hours, are physical barriers erected [instead of hazard warning tape]?
Details of SWO / IN issued: