Professional Documents
Culture Documents
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Sand (including 5% wastage) cum 1.05 425.00 446.25
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 285.00 57.00
Grand Total 2087.25
BLD-CSTN-1-7 7 Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement kg. 240.00 5.50 1320.00
Sand (including 5% wastage) cum 1.05 425.00 446.25
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 285.00 57.00
Grand Total 1823.25
BLD-CSTN-1-8 8 Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement kg. 180.00 5.50 990.00
Sand (including 5% wastage) cum 1.05 425.00 446.25
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 285.00 57.00
Grand Total 1493.25
CONCRETE, DAMP PROOF COURSE &
BLD-CSTN-2
REINFORCEMENT
BLD-CSTN-2-1 9 Plain Cement concrete Grade M20 - Nominal Mix
using 20mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement Kg 400.00 5.50 2200.00
Coarse aggregate 20mm cum 0.90 1175.00 1057.50 M-053
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
B. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 2.36 215.00 507.40
Water (including for curing) kl 1.20 77.00 92.40
Grand Total 4077.05
Note : For Nominal Mix : Considering table 9 IS 456 : 2000, the
10 quantityCement
Plain of cement neededGrade
concrete is 405M10
kgs /- cum. Hence
Nominal proposed
Mix
BLD-CSTN-2-2 400 kgs of cement
upto Plinth level for cum of CC M20
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 220.00 5.50 1210.00
Coarse aggregate 40mm cum 0.90 745.00 670.50 M-055
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 77.00 92.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 1.39 215.00 298.85
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Grand Total 2834.00
11 PCC Grade M15 - Nominal mix 1:2.5:5 (Hand mixing)
BLD-CSTN-2-3
Unit = 1cum
A) Material
Cement kg 275.00 5.50 1512.50
Coarse sand cum 0.48 325.00 156.00
40 mm aggregate cum 0.54 745.00 402.30
20 mm aggregate cum 0.27 1175.00 317.25
10 mm aggregate cum 0.09 820.00 73.80 M-051
Water (including for curing) kl 1.20 77.00 92.40
B) Labour
Mason (1st Class) day 0.10 285.00 28.50
Mazdoor (Unskilled) day 2.36 215.00 507.40
Grand Total 3090.15
12 Plain Cement concrete (1:4:8) using 40 mm metal
BLD-CSTN-2-4
with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 5.50 891.00
Coarse aggregate 40 mm cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 77.00 92.40
B. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 2.36 215.00 507.40
Grand Total 2381.05
13 Plain Cement concrete (1:4:8) using 40 mm metal
BLD-CSTN-2-5 with concrete mixture. All work upto plinth
level.
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 5.50 891.00
Coarse aggregate 40 mm cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 77.00 92.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 1.39 215.00 298.85
Water Charges 1% - 25.15
Grand Total 2540.15
14 Plain Cement concrete (1:5:10) using 40 mm metal
BLD-CSTN-2-6
with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 5.50 712.80
Coarse aggregate 40 mm cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 77.00 92.40
B. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 2.36 215.00 507.40
Grand Total 2202.85
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
15 Plain Cement concrete (1:5:10) using 40 mm metal
BLD-CSTN-2-7 with Concrete mixture. All work upto plinth level.
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 5.50 712.80
Coarse aggregate 40 mm cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 77.00 92.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 1.39 215.00 298.85
Grand Total 2336.80
16 Plain Cement concrete (1:6:10) using 40 mm metal
BLD-CSTN-2-8
with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 5.50 712.80
Coarse aggregate 40 mm cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.54 425.00 229.50
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.54
Water (including for curing) kl 1.20 77.00 92.40
B. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 2.36 215.00 507.40
Grand Total 2241.10
17 Plain Cement concrete (1:6:10) using 40 mm metal
BLD-CSTN-2-9
with Concrete mixture upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 5.50 712.80
Coarse aggregate 40 mm cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.54 425.00 229.50
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.54
Water (including for curing) kl 1.20 77.00 92.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 1.39 215.00 298.85
Grand Total 2375.05
BLD-CSTN-2-10 18 Plain Cement concrete - Nominal Mix (1:3:6)
using 40mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement Kg 220.00 5.50 1210.00
Coarse aggregate 40mm cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 77.00 92.40
B. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 2.36 215.00 507.40
Grand Total 2700.05
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
19 Plain Cement concrete (M 20) Nominal Mix using
BLD-CSTN-2-11
40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 330.00 5.50 1815.00
Coarse aggregate 40mm graded cum 0.90 745.00 670.50
Fine aggregate (Sand) cum 0.45 425.00 191.25
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20 77.00 92.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 1.39 215.00 298.85
Grand Total 3439.00
20 Plain Cement concrete (M 15) Nominal Mix 1:2.5:5
BLD-CSTN-2-12
A. MATERIALS:
20mm HBG graded metal cum 0.900 1175.00 1057.50
Sand cum 0.450 425.00 191.25
Cement Kgs 400.000 5.50 2200.00
B. LABOUR:
1st Class Mason day 0.133 285.00 37.91
2nd Class Mason day 0.267 260.00 69.42
Mazdoor (Both Men and Women) day 3.600 215.00 774.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 342.50 342.50
Cost of Diesel for Miller Liters 0.133 45.00 5.99
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Cost of Petrol for Vibrator Liters 0.667 75.00 50.03
Water (including for curing) kl 1.200 77.00 92.40
BASIC COST per 1 cum 4820.99
B COLUMNS, LINTELS, WATER TANKS, RCC WALLS
IN BUILDINGS
A. MATERIALS:
20mm HBG graded metal cum 0.900 1175.00 1057.50
Sand cum 0.450 425.00 191.25
Cement Kgs 400.000 5.50 2200.00
B. LABOUR:
1st Class Mason day 0.167 285.00 47.60
2nd Class Mason day 0.167 260.00 43.42
Mazdoor (Both Men and Women) day 4.700 215.00 1010.50
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 342.50 342.50
Water (including for curing) kl 1.200 77.00 92.40
BASIC COST per 1 cum 4985.17
C RCC SLABS, BEAMS
A. MATERIALS:
20mm HBG graded metal cum 0.900 1175.00 1057.50
Sand cum 0.450 425.00 191.25
Cement Kgs 400.000 5.50 2200.00
B. LABOUR:
1st Class Mason day 0.067 285.00 19.10
2nd Class Mason day 0.133 260.00 34.58
Mazdoor (Both Men and Women) day 2.500 215.00 537.50
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 0.267 342.50 91.45
Water (including for curing) kl 1.200 77.00 92.40
BASIC COST per 1 cum 4223.77
24 Damp proof course 40mm thick with cement
concrete (1:2:4 Nominal mix), using 12mm hard
broken stone aggregate including cost of all
materials, seigniorage charges, excluding
BLD-CSTN-2-16 conveyance charges of materials, including the cost
of machinery, labour charges, mixing, placing in
position, leveling, vibrating, curing etc. complete for
finished item of work. (Using concrete mixer)
Unit = 25 sqm
A. MATERIALS:
Cement kgs 320.00 5.50 1760.00
Coarse aggregate 12mm cum 0.90 980.00 882.00 M-052
Fine aggregate (sand) cum 0.45 425.00 191.25
Seigniorage charges of coarse aggregate cum 0.90
Seigniorage charges of sand cum 0.45
Form work L.S. 1200.00 1200.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.1 285.00 28.50
Mazdoor (unskilled) day 1.98 215.00 425.70
D. Grand Total for 25 sqm 4829.95
Rate per Sqm = D/25 193.20
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
25 Damp proof course 50mm thick with 1:2:4 cement
concrete Nominal mix, using 12mm hard broken
stone aggregate including cost of all materials,
seigniorage charges, excluding conveyance charges
BLD-CSTN-2-17 of materials including the cost of machinery, labour
charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished item of
work. (Using concrete mixer)
Unit = 20 sqm
A. MATERIALS:
Cement kgs 320.00 5.50 1760.00
Coarse aggregate 12mm cum 0.90 980.00 882.00
Fine aggregate (sand) cum 0.45 425.00 191.25
Seigniorage charges of coarse aggregate cum 0.90
Seigniorage charges of sand cum 0.45
Form work L.S. 1200.00 1200.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.1 285.00 28.50
Mazdoor (unskilled) day 1.98 215.00 425.70
D. Grand Total for 20 sqm 4829.95
Rate per Sqm = D/20 241.50
26 Supplying, fitting and placing HYSD bar
11.7 reinforcement in foundation complete as per
BLD-CSTN-2-18 drawings and technical specifications for Bars below
36 mm dia including over laps and wastage, where
they are not welded
1000 Unit = t
& (a) Material
1200 HYSD bars including 5 per cent for overlaps and t 1.05 44000.00 46200.00
wastage
Binding wire kg 6.00 55.00 330.00
(b) Labour for cutting, bending, shifting to site, tying 0.00
and placing in position
Blacksmith / Bar bender day 2.00 285.00 570.00
Mazdoor (Unskilled) day 6.40 215.00 1376.00
Sundries on Material 33.00 33.00
Rate per t = a+b+c+d 48509.00
A Supplying, fitting and placing HYSD bar
reinforcement in foundation complete including
wastage, as per drawings and technical
specifications Clauses 1000 and 1202 MORD & 1100,
1600 MORTH for Bars 36 mm dia and above, where
welding required to be done compulsorily.
1000 Unit = t
& (a) Material
1200 HYSD bars including 2.5 per cent for wastage t 1.025 44000.00 45100.00
Welding Electrodes @ 5 per joint (14 joints / ton) each 70.000 12.00 840.00
Welding Charges (Hire charges of Welding Machine) Hr 10.00 12.90 129.00
Binding wire kg 6.00 55.00 330.00
(b) Labour for cutting, bending, shifting to site, tying
and placing in position
Welder day 2.50 285.00 712.50
Blacksmith day 2.00 285.00 570.00
Mazdoor (Unskilled) day 6.40 215.00 1376.00
Rate per t = a+b+c+d 49057.50
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
27 Supplying, fitting and placingTMT bar reinforcement
11.8 in foundation complete as per drawings and
BLD-CSTN-2-19 technical specifications for Bars below 36 mm dia
including over laps and wastage, where they are not
welded.
1000 Unit = t
& (a) Material
1200 TMT bars including 5 per cent for overlaps and wastage t 1.05 44000.00 46200.00
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage t 1.025 44000.00 45100.00
Welding Electrodes @ 5 per joint (14 joints / ton) each 70.000 12.00 840.00
Welding Charges (Hire charges of Welding Machine) Hr 10.00 12.90 129.00
Binding wire kg 6.00 55.00 330.00
(b) Labour for cutting, bending, shifting to site, tying
and placing in position
Welder day 2.50 285.00 712.50
Blacksmith day 2.00 285.00 570.00
Mazdoor (Unskilled) day 6.40 215.00 1376.00
Rate per t = a+b+c+d 49057.50
28 Supplying, fitting and placing MS bar reinforcement
11.9 in foundation complete as per drawings and
BLD-CSTN-2-20 technical specifications for Bars below 36 mm dia
including over laps and wastage, where they are not
welded
1000 Unit = t
& (a) Material
1200 MS bars including 5 per cent for overlaps and wastage t 1.05 44000.00 46200.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 2858.64
Note : For Bricks 2.4 % wastage taken.
ii Brick Masonry in CM (1:4) with Bricks traditional size
23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 72.00 5.50 396.00
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 3.10 1587.20
Wastage of bricks @ 2.40% 38.09
Fine aggregate (Sand) cum 0.20 425.00 85.00
Seigniorage charges for F.A cum 0.20
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 2726.64
iii Brick Masonry in CM (1:5) with Bricks traditional size
23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 57.60 5.50 316.80
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 3.10 1587.20
Wastage of bricks @ 2.40% 38.09
Fine aggregate (Sand) cum 0.20 425.00 85.00
Seigniorage charges for F.A cum 0.20
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 2647.44
iv Brick Masonry in CM (1:6) with 2nd class Bricks
traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement kg 48.00 5.50 264.00
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 3.10 1587.20
Wastage of bricks @ 2.40% 38.09
Fine aggregate (Sand) cum 0.20 425.00 85.00
Seigniorage charges for F.A cum 0.20
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 2594.64
v Brick Masonry in CM (1:8) with Bricks traditional size
23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement kg 36.00 5.50 198.00
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 3.10 1587.20
Wastage of bricks @ 2.40% 38.09
Fine aggregate (Sand) cum 0.20 425.00 85.00
Seigniorage charges for F.A cum 0.20
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 2528.64
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
b Brick Masonry in CM (1:3) with Bricks traditional
size 23 x 11 x 7 cms 1st Class
Unit = 1cum
A. MATERIALS:
Cement kg 96.00 5.50 528.00
Bricks1st Class traditional size 23 x 11 x 7 cms Nos 512.00 3.10 1587.20
Wastage of bricks @ 2.40% 38.09
Fine aggregate (Sand) cum 0.20 425.00 85.00
Seigniorage charges for F.A cum 0.20
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2 class
nd
day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 2858.64
Note : 1. When Mortar mix is changed as CM 1:4, 1:5, 1:6 and
1:8, proportionate
2. When quantity
First class of cement
Modular hasused
Bricks are to beprovide
substituted. No
570 nos
30 changeMasonry
bricks
Brick ofinsize
other
19data.
x 9CM
in x 9(1:3)
cms.with Modular Bricks 19 x 9
BLD-CSTN-3-2
x 9 cms 2nd class
i Unit = 1cum
A. MATERIALS:
Cement kg 100.60 5.50 553.30
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 4.19 2178.80
Wastage of bricks @ 2.40% 52.29
Fine aggregate (Sand) cum 0.21 425.00 89.25
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2 class
nd
day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 3493.99
ii Brick Masonry in CM (1:4) with Modular Bricks 19 x 9
x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 75.60 5.50 415.80
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 4.19 2178.80
Wastage of bricks @ 2.40% 52.29
Fine aggregate (Sand) cum 0.21 425.00 89.25
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 3356.49
iii Brick Masonry in CM (1:5) with Modular Bricks 19 x 9
x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 60.48 5.50 332.64
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 4.19 2178.80
Wastage of bricks @ 2.40% 52.29
Fine aggregate (Sand) cum 0.21 425.00 89.25
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 3273.33
iv Brick Masonry in CM (1:6) with Modular Bricks 19 x 9
x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Cement kg 50.40 5.50 277.20
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 4.19 2178.80
Wastage of bricks @ 2.40% 52.29
Fine aggregate (Sand) cum 0.21 425.00 89.25
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 3217.89
iv Brick Masonry in CM (1:8) with Modular Bricks 19 x 9
x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 37.80 5.50 207.90
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 4.19 2178.80
Wastage of bricks @ 2.40% 52.29
Fine aggregate (Sand) cum 0.21 425.00 89.25
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 1st class day 0.24 285.00 68.40
Mason 2nd class day 0.56 260.00 145.60
Mazdoor (unskilled) day 1.89 215.00 406.35
Grand Total 3148.59
31 11.5 cm wide Brick masonry for super-structure on
ground floor in cm (1:3) using second class
traditional size bricks including cost of all materials,
seigniorage charges, labour and all operations for
BLD-CSTN-3-3 constructing half brick masonry, mixing cement
mortar, curing etc., complete for finished item of
work, but excluding conveyance charges of
materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size 23x11x7cm nos 565.000 3.10 1751.50
Ground Floor :
A. MATERIALS:
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
II Class Bricks cum 512.000 4.19 2145.28
C.M.(1:6) cum 0.200 1823.25 364.65
B. LABOUR:
Mason 1st class day 0.600 285.00 171.00
Mason 2nd class day 0.600 260.00 156.00
Mazdoor (unskilled) day 2.750 215.00 591.25
Grand Total 3428.18
33 Exposed brick masonry for super structure on
ground floor in cm (1:6) using wire cut bricks or
moulded bricks including making horizontal and
vertical grooves 10mm Wide 12mm deep, cost of all
BLD-CSTN-3-5 materials, seigniorage charges, labour and all
operations, mixing cement mortar, curing etc.,
complete for finished item of work, but excluding
conveyance charges of materials
unit:1cum
A. MATERIALS:
Wire cut bricks or moulded bricks size 19x9x9cm nos 520.000 4.19 2178.80
Cement kg. 48.00 5.50 264.00
Sand cum 0.20 425.00 85.00
Seigniorage charges for sand cum 0.20
B. LABOUR:
Mason 1st class day 0.57 285.00 162.45
Mason 2nd class day 0.57 260.00 148.20
Mazdoor (unskilled) day 2.54 215.00 546.10
Add water charges 1% 1.00% 33.85
Grand Total 3418.40
Note : Compressive strength of individual Brick shall not
be less than 70 kg / cm2
34 Brickwork in arches in cement mortar 1:4 complete
including centering and shuttering excluding
BLD-CSTN-3-6 pointing and plastering as per drawing and technical
specifications Clauses 606 and 1205.1 MORD
Unit = cum
a) Material
Brick 1st class Nos. 525.00 4.19 2199.75
Cement mortar (1:4) cum 0.24 2483.25 595.98
b) Labour
Mazdoor (Unskilled) day 1.88 215.00 404.20
Mason (1st Class) day 2.00 285.00 570.00
c) Add for centering and shuttering @ 110% of (a+b) 4146.92
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Brick 2nd class 23 x 11 x 7 Nos. 750.00 3.10 2325.00
Cement mortar (1:5) cum 0.67 2087.25 1398.46
b) Labour
Mazdoor (Unskilled) day 6.60 215.00 1419.00
Mason (1st Class) day 2.41 285.00 686.85
Mason (2nd Class) day 6.21 260.00 1614.60
White Washing 2 Coats LS LS 0.00
Grand Total 7443.91
36 Honey Comb work with Bricks of Modular Size and
BLD-CSTN-3-8 Plastered One Coat 10 mm. thick Cement Mortar 1:5
including White Washing 2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9 Nos. 790.00 4.19 3310.10
Cement mortar (1:5) cum 0.67 2087.25 1398.46
b) Labour
Mazdoor (Unskilled) day 6.60 215.00 1419.00
Mason (1st Class) day 2.41 285.00 686.85
Mason (2nd Class) day 6.21 260.00 1614.60
White Washing 2 Coats LS LS
Grand Total 8429.01
STONE MASONRY, DAMP PROOF COURSE, DRY
BLD-CSTN-4 STONE PACKING, QUARRY RUBBISH & GRAVEL
BACKING
BLD-CSTN-4-1 37 Cut Stone Masonry in CM 1:2
Unit = 1cum
A. MATERIALS:
Cement kg 115.20 5.50 633.60
Cut Stone Roughly dressed to shape at quarry cum 0.89 50.00 44.50
Bond Stones cum 0.16 45.00 7.20
Fine aggregate (Sand) cum 0.16 425.00 68.00
Seigniorage charges for F.A cum 0.16
B. LABOUR:
Mason 1st class day 1.05 285.00 299.25
Mason 2nd class day 2.45 260.00 637.00
Man mazdoor day 3.50 215.00 752.50
Woman mazdoor day 2.80 215.00 602.00
Grand Total 3044.05
Note : When Mortar mix is changed as CM 1:3, 1:4, 1:5, 1:6 and
BLD-CSTN-4-2 38 1:8,
CRSproportionate
Masonry in CM quantity of cement
(1:2) 1st Sort has to be substituted. No
i change in other data.
Unit = 1cum
A. MATERIALS:
Cement kg 201.60 5.50 1108.80
Coursed Rubble Stone cum 0.94 18.00 16.92
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 224.00 35.84
Fine aggregate (Sand) cum 0.28 425.00 119.00
Seigniorage charges for F.A cum 0.28
Seigniorage charges for Stone cum 1.10
B. LABOUR:
Mason 1st class day 2.50 285.00 712.50
Mazdoor (unskilled) day 2.32 215.00 498.80
Grand Total 2491.86
ii CRS Masonry in CM (1:3) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement kg 134.40 5.50 739.20
Coursed Rubble Stone cum 0.94 18.00 16.92
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 224.00 35.84
Fine aggregate (Sand) cum 0.28 425.00 119.00
Seigniorage charges for F.A cum 0.28
Seigniorage charges for Stone cum 1.10
B. LABOUR:
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Mason 1st class day 2.50 285.00 712.50
Mazdoor (unskilled) day 2.32 215.00 498.80
Grand Total 2122.26
iii CRS Masonry in CM (1:4) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement kg 100.80 5.50 554.40
Coursed Rubble Stone cum 0.94 18.00 16.92
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 224.00 35.84
Fine aggregate (Sand) cum 0.28 425.00 119.00
Seigniorage charges for F.A cum 0.28
Seigniorage charges for Stone cum 1.10
B. LABOUR:
Mason 1st class day 2.50 285.00 712.50
Mazdoor (unskilled) day 2.32 215.00 498.80
Grand Total 1937.46
iv CRS Masonry in CM (1:6) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement kg 67.20 5.50 369.60
Coursed Rubble Stone cum 0.94 18.00 16.92
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 224.00 35.84
Fine aggregate (Sand) cum 0.28 425.00 119.00
Seigniorage charges for F.A cum 0.28
Seigniorage charges for Stone cum 1.10
B. LABOUR:
Mason 1st class day 2.50 285.00 712.50
Mazdoor (unskilled) day 2.32 215.00 498.80
Grand Total 1752.66
BLD-CSTN-4-3 39 CRS Masonry in CM (1:6) 2nd Sort
Unit = 1cum
A. MATERIALS:
Cement kg 76.80 5.50 422.40
Coursed Rubble Stone cum 0.94 18.00 16.92
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 224.00 35.84
Fine aggregate (Sand) cum 0.32 425.00 136.00
Seigniorage charges for F.A cum 0.32
Seigniorage charges for Stone cum 1.10
B. LABOUR:
Mason 1st class day 1.50 285.00 427.50
Mazdoor (unskilled) day 2.32 215.00 498.80
Grand Total 1537.46
Note : When Mortar mix is changed proportionate quantity of
40 cement hasrubble
Coursed to be substituted. No change
stone masonry archin (Ist
othersort)
data. in
cement mortar (1:4) complete including centering
BLD-CSTN-4-4 etc. complete as per drawing and technical
specifications Clauses 706 and 1205.1
Unit = cum
A. Material
Stone for CR masonry 1st sort cum 0.94 1937.46 1821.21
Through and bond stone (7 Nos 0.24x0.24x0.39 = 0.16 Nos. 0.16 224.00 35.84
cum)
Cement mortar (Rate as in item 11.5 II) cum 0.30 2483.25 744.98
B. Labour
Mason (1st Class) day 3.00 285.00 855.00
Mazdoor (Unskilled) day 2.43 215.00 522.45
C. Add for centering and shuttering @ 100 % of (a+b) 3979.48
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Unit = 1cum
A. MATERIALS:
Cement kg 57.60 5.50 316.80
Cut Stone Roughly dressed to shape at quarry cum 0.89 50.00 44.50
Bond Stones of Cutstone quality 0.16 45.00 7.20
Fine aggregate (Sand) cum 0.16 425.00 68.00
Seigniorage charges for F.A cum 0.16 0.16
B. LABOUR:
Mason 1st class day 5.05 285.00 1439.25
Mason 2nd class day 2.45 260.00 637.00
Mazdoor (unskilled) day 6.30 215.00 1354.50
Centering Charges LS 1609.00
Grand Total 5476.41
BLD-CSTN-4-6 42 Rubble Arch Work in Cement Mortar (1:4)
Unit = 1cum
A. MATERIALS:
Cement kg 100.80 5.50 554.40
Seleted Stone of sizes as per specification (including cum 1.15 45.00 51.75
Bond Stones)
Fine aggregate (Sand) cum 0.28 425.00 119.00
Seigniorage charges for F.A cum 0.28 0.28
B. LABOUR:
Mason 1st class day 0.90 285.00 256.50
Mason 2nd class day 2.10 260.00 546.00
Mazdoor (unskilled) day 2.43 215.00 522.45
Centering Charges LS 1609.00
Grand Total 3659.38
43 Providing & Laying reinforced cement concrete arch
complete including centering and shuttering
BLD-CSTN-4-7 excluding reinforcement as per drawings and
technical specifications Clauses 800, 900 and 1205.1
Unit = cum
I RCC grade M20 nominal mix
a) Material
Cement t 0.40 5500.00 2200.00
Coarse sand cum 0.45 325.00 146.25
20 mm aggregate cum 0.54 1175.00 634.50
10 mm aggregate cum 0.36 820.00 295.20
b) Labour
Mason (1st Class) day 0.20 285.00 57.00
Mazdoor (Unskilled) day 2.15 215.00 462.25
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 248.40 99.36
d) Add for cost of centering and shuttering @ 50 per 1947.28
cent of (a+b) per sqm of surface of arch soffit
Grand Total 5841.84
II RCC Grade M 25 (Design mix)
a) Material
Cement t 0.38 5500.00 2090.00
Coarse sand cum 0.45 325.00 146.25
20 mm aggregate cum 0.54 1175.00 634.50
10 mm aggregate cum 0.36 820.00 295.20
b) Labour
Mason (1st Class) day 0.20 285.00 57.00
Mazdoor (Unskilled) day 2.15 215.00 462.25
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 248.40 99.36
d) Add for cost of centering and shuttering @ 50 per 1892.28
cent of (a+b) per sqm of surface of arch soffit
Grand Total 5676.84
Note : The additional cost of centering and shuttering @ 50 per
cent of cost of material and labour shall hold good for arch spans
of 6 m and above. For lesser length of spans, the corresponding
Andhra Pradesh Standard Data 15 of 264
additional cost can be taken as 40 per cent for spans above 4 m
SSR 2011-12
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
BLD-CSTN-4-8 44 RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement kg 79.20 5.50 435.60
CR Stone cum 0.44 1752.66 771.17
Rough Stone cum 0.50 50.00 25.00
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 224.00 35.84
Fine aggregate (Sand) cum 0.33 425.00 140.25
Seigniorage charges for F.A cum 0.33
Seigniorage charges for Stone cum 1.10
B. LABOUR:
Mason 1st class day 1.20 285.00 342.00
Mazdoor (unskilled) day 2.00 215.00 430.00
Grand Total 2179.86
BLD-CSTN-4-9 45 RR Masonry in CM (1:8)
Unit = 1cum
A. MATERIALS:
Cement kg 59.40 5.50 326.70 .
CR Stone cum 0.44 1752.66 771.17
Rough Stone cum 0.50 50.00 25.00
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 224.00 35.84
Fine aggregate (Sand) cum 0.33 425.00 140.25
Seigniorage charges for F.A cum 0.33
Seigniorage charges for Stone cum 1.10
B. LABOUR:
Mason 1st class day 1.20 285.00 342.00
Mazdoor (unskilled) day 2.00 215.00 430.00
Grand Total 2070.96
Note : When Mortar mix is changed proportionate quantity of
BLD-CSTN-4-10 46 cement hasMasonry
Dry Stone to be substituted. No change
for Retaining Walls in other data
Unit = 1cum
A. MATERIALS:
Rough Stone cum 1.04 50.00 52.00
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 224.00 35.84
Seigniorage charges for Stone cum 1.20
B. LABOUR:
Mason 1st class day 0.33 285.00 94.05
Mason 2 class
nd
day 0.77 260.00 200.20
Mazdoor (unskilled) day 1.10 215.00 236.50
Grand Total 618.59
BLD-CSTN-4-11 47 Dry Stone Masonry for Well steining
Unit = 1cum
A. MATERIALS:
Rough Stone cum 1.04 50.00 52.00
Bond Stones cum 0.16 224.00 35.84
Seigniorage charges for Stone cum 1.20
B. LABOUR:
Mason 1st class day 0.45 285.00 128.25
Mason 2nd class day 1.05 260.00 273.00
Mazdoor (unskilled) day 1.10 215.00 236.50
Grand Total 725.59
48 Damp Proof, Course Damp Proof (or anti Proof)
BLD-CSTN-4-12 Course with Cuddapah / Shabad slabs 50 mm. thick
in CM (1:3) (Unit - 10 sqm)
A. MATERIALS:
Cuddapah / Shabad slabs 50 mm. thick sqm 10.50 86.00 903.00 BMT-
B.02
Cement Mortar 1:3 cum 0.15 3143.25 471.49
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class day 0.90 285.00 256.50
Mason 2nd class day 2.10 260.00 546.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Mazdoor (unskilled) day 2.00 215.00 430.00
Grand Total 2606.99
Rate per 1 Sq.m 260.70
BLD-CSTN-5 POINTING
49 Flush Pointing with CM (1:3) to Brick / CRS Masonry
BLD-CSTN-5-1
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40 86.00 1238.40
Fine aggregate (Sand) cum 0.03 425.00 12.75
Seigniorage charges for F.A cum 0.03
B. LABOUR:
Mason 2nd class day 0.50 285.00 142.50
Mazdoor (unskilled) day 0.74 260.00 192.40
Grand Total 1586.05
Rate per 1 Sq.m 158.61
BLD-CSTN-5-2 50 Flush Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40 86.00 1238.40
Fine aggregate (Sand) cum 0.03 425.00 12.75
Seigniorage charges for F.A cum 0.03
B. LABOUR:
Mason 2nd class day 0.50 285.00 142.50
Mazdoor (unskilled) day 0.74 260.00 192.40
Grand Total 1586.05
Rate per 1 Sq.m 158.61
BLD-CSTN-5-3 51 Raised Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 28.80 86.00 2476.80
Fine aggregate (Sand) cum 0.06 425.00 25.50
Seigniorage charges for F.A cum 0.06
B. LABOUR:
Mason 2nd class day 0.50 285.00 142.50
Mazdoor (unskilled) day 0.74 260.00 192.40
Grand Total 2837.20
Rate per 1 Sq.m 283.72
52 Raised and cut pointing on coursed or Ashlar stone
BLD-CSTN-5-4 masonry or concrete block walling in white cement
mortar 1 : 3 (1 white cement : 3 marble dust).
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.038 2483.25 94.36
Labour :—
Mason llnd class day 1.460 260.00 379.60
Mazdoor (unskilled) day 2.260 215.00 485.90
Add for water charges @ 1 % 9.60
Cost for 10 sq.m. 969.46
Cost per sq.m 96.95
Note : When Mortar mix is changed as CM 1:4 proportionate
BLD-CSTN-6 quantity of cement has to be substituted. No change in other
PLASTERING
BLD-CSTN-6-1 53 data.
Plastering with CM (1:3), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15 3143.25 471.49
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.60 285.00 171.00
Mazdoor (unskilled) day 0.96 215.00 206.40
Grand Total 848.89
Cost per sq.m 84.89
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
BLD-CSTN-6-2 54 Plastering with CM (1:4), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.15 2483.25 372.49
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.60 285.00 171.00
Mazdoor (unskilled) day 0.96 215.00 206.40
Grand Total 749.89
Cost per sq.m 74.99
BLD-CSTN-6-3 55 Plastering with CM (1:5), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5) cum 0.150 2087.25 313.09
Seigniorage charges for F.A cum 0.150
B. LABOUR:
Mason 1st class day 0.60 285.00 171.00
Mazdoor (unskilled) day 0.96 215.00 206.40
Grand Total 690.49
Cost per sq.m 69.05
BLD-CSTN-6-4 56 Plastering with CM (1:6), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:6) cum 0.15 1823.25 273.49
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.60 285.00 171.00
Mazdoor (unskilled) day 0.96 215.00 206.40
Grand Total 650.89
Cost per sq.m 65.09
BLD-CSTN-6-5 57 Plastering with CM (1:8), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5) cum 0.15 1493.25 223.99
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.60 285.00 171.00
Mazdoor (unskilled) day 0.96 215.00 206.40
Grand Total 601.39
Cost per sq.m 60.14
BLD-CSTN-6-6 58 Plastering with CM (1:4), 15 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.19 2483.25 471.82
Seigniorage charges for F.A cum 0.19
B. LABOUR:
Mason 2nd class day 0.60 260.00 156.00
Mazdoor (unskilled) day 0.96 215.00 206.40
Grand Total 834.22
Cost per sq.m 83.42
BLD-CSTN-6-7 59 Plastering with CM (1:4), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.210 2483.25 521.48
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 2nd class day 0.94 260.00 244.40
Mazdoor (unskilled) day 1.60 215.00 344.00
Grand Total 1109.88
Cost per sq.m 110.99
BLD-CSTN-6-8 60 Plastering with CM (1:3), 20 mm thick
Unit = 10 sqm
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
A. MATERIALS:
Cement Mortar (1:3) cum 0.210 3143.25 660.08
Seigniorage charges for F.A cum 0.21
B. LABOUR:
Mason 2nd class day 0.94 260.00 244.40
Mazdoor (unskilled) day 1.60 215.00 344.00
Grand Total 1248.48
Cost per sq.m 124.85
Note : When Mortar mix is changed proportionate quantity of
61 cement haswith
Plastering to beCM
substituted
2 coats, 20 mm thick, base coat in .
BLD-CSTN-6-9 CM (1:6), 16mm thick and top coat in CM (1:4), 4mm
thick with Dubara sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement kg 43.00 5.50 236.50
Fine aggregate (Sand) cum 0.18 425.00 76.50
Top Coat in CM(1:4), 4 mm thick
Cement kg 14.50 5.50 79.75
Fine aggregate (Sand) cum 0.04 425.00 17.00
Seigniorage charges for F.A cum 0.22
B. LABOUR:
Mason 1st class day 0.63 285.00 179.55
Mason 2 class
nd
day 1.47 260.00 382.20
Mazdoor (unskilled) day 3.90 215.00 838.50
Grand Total 1810.00
Cost per sq.m 181.00
Note : When Mortar mix is changed proportionate quantity of
62 cement haswith
Plastering to beCM
substituted
2 coats, 12 mm thick, base coat in
BLD-CSTN-6-10 CM (1:5), 8mm thick and top coat in CM (1:3), 4mm
thick with sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement kg 31.70 5.50 174.35
Fine aggregate (Sand) cum 0.11 425.00 46.75
Top Coat in CM(1:3), 4 mm thick
Cement kg 19.20 5.50 105.60
Fine aggregate (Sand) cum 0.04 425.00 17.00
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.63 285.00 179.55
Mason 2nd class day 1.47 260.00 382.20
Mazdoor (unskilled) day 3.90 215.00 838.50
Grand Total 1743.95
Cost per sq.m 174.40
Note : When Mortar mix is changed proportionate quantity of
cement
RCM FACIAhas toWORKS
be substituted
63 RCM facia 5cm thick in CM (1:3) for drop walls, fins with
rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara sponge finishing,
including cost & conveyance of all materials to site,
seigniorage charges, sales & other taxes on all
materials, operational & incidental, cost and conveyance
BLD-CSTN-6-11 of cement, wire mesh, water to work site, centering,
scaffolding and form work, lift charges etc., complete for
finished items of work but excluding cost of steel & its
fabrication charges, for finished item of work. (APSS
No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop) sqm 13.30 12.00 159.60
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Cement Mortar 1:3 for 25 mm thick cum 0.25 3143.25 785.81
Dry Cement for making Lumps kg 50.00 5.50 275.00
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides sqm 21.80 74.99 1634.75
Excluding HYSD Steel/ Mild steel & Binding wire
B) LABOUR CHARGES
1st Class Mason day 8.00 285.00 2280.00
Miller Operator day 1.00 260.00 260.00
Mazdoor (unskilled) day 10.00 215.00 2150.00
c) Machinery
Machine Mixing Mortar with Miller - Hire charges Hrs 2.00 41.20 82.40
BASIC COST per 10 sqm 7627.57
Cost per sq.m 762.76
64 20 mm thick rough cast exterior cement plaster on walls
upto height of 10 metres above ground level consisting
of 10 mm thick backing coat of 1 : 3 cement mortar (1
cement : 3 sand) and 10 mm thick finishing coat of 1 : 3
BLD-CSTN-6-12 cement mortar (1 cement : 3 coarse aggregate of size 6
mm to 10 mm) including arrises, chamfers and/or
rounded angles not exceeding 80 mm in girth.
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Mazdoo (unskilled) day 3.270 215.00 703.05
Add labour for dashing crushed stone
Mason 1st class day 0.500 285.00 142.50
Mazdoo (unskilled) day 1.000 215.00 215.00
Add for water charges @ 1 % 23.03
Cost for 10 sq.m. 2326.29
Cost per sq.m 232.63
(b) Dark coloured finish using ordinary cement and
pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item () 2326.29
Add cost of colour kg 6.000 60.00 232.63 BMT-J.02
Materials :-
Cement mortar 1 :4 cum 0.023 2483.25 57.11
Labour :—
Mason llnd class day 0.300 260.00 78.00
Mazdoor (unskilled) day 0.350 215.00 75.25
Add for water charges @ 1 % 2.10
Cost for 10 metres long and 10 cm wide band 212.47
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Cost per cm width x metre long
b) Sunk band :-
Details of cost for 10 metres long and 10 cm wide band
Materials :-
Cement mortar 1 :4 cum 0.023 2483.25 57.11
Labour :—
Mason llnd class day 0.300 260.00 78.00
Mazdoor (unskilled) day 0.350 215.00 75.25
Add for water charges @ 1 % 2.10
Cost for 10 metres long and 10 cm wide band 212.47
Cost per cm width x metre long
C) Raised Band :-
Materials :-
Cement mortar 1 :4 cum 0.023 2483.25 57.11
Labour :—
Mason llnd class day 0.380 260.00 98.80
Mazdoor (unskilled) day 0.430 215.00 92.45
Add for water charges @ 1 % 2.48
Cost for 10 metres long and 10 cm wide band 250.85
Cost per cm width x metre long
68 20 mm thick plain cement mortar bands in cement mortar
BLD-CSTN-6-16
1:4(1 cement: 4 sand) above 300 mm in width
(A) Flush Band :-
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.224 2483.25 556.25
Labour :—
Mason llnd class day 2.200 260.00 572.00
Mazdoor (unskilled) day 2.700 215.00 580.50
Add for water charges @ 1 % 17.09
Cost for 10 sq.m. 1725.84
Cost per sq.m 172.58
(B) Sunk band :-
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.224 2483.25 556.25
Labour :—
Mason llnd class day 2.500 260.00 650.00
Mazdoor (unskilled) day 3.000 215.00 645.00
Add for water charges @ 1 % 18.51
Cost for 10 sq.m. 1869.76
Cost per sq.m 186.98
(C) Raised band
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.224 2483.25 556.25
Labour :—
Mason llnd class day 3.000 260.00 780.00
Mazdoor (unskilled) day 3.500 215.00 752.50
Add for water charges @ 1 % 20.89
Cost for 10 sq.m. 2109.64
Cost per sq.m 210.96
Moulded Cement Mortar Bands 15 mm
69 15 mm thick moulded cement mortar band in cement
BLD-CSTN-6-17
mortar 1 : 4 (1cement: 4 sand)
Details of cost for 10 metres long and 10 cm wide band
Materials :-
Cement mortar 1 :4 cum 0.023 2483.25 57.11
Labour :—
Mason llnd class day 0.870 260.00 226.20
Mazdoor (unskilled) day 0.920 215.00 197.80
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Add for water charges @ 1 % 4.81
Cost for 10 metres long and 10 cm wide band 485.93
Cost per cm width x metre long
70 Masonry work in CM (1:8) prop with Flyash Cement
solid blocks of size 290 x 225 x 140 mm for
manufacturing of flyash solid blocks using flyash of
80 kgs, cement of 15 kgs. Gypsum of 5 kgs. and
stone dust including cost and conveyance of all
BLD-CSTN-6-18 materials, labour charges, seiniorage charges,
scaffolding and curing etc., cpomplete with a
compresive streangth not lessthan 50 kg/sqm for
walls for Superstructure Walls.
Ground Floor
Unit = 1 cum
A. MATERIALS:
No of blocks required for one cum of Masonry day 110.000 3.10 341.00
Cost of Cement Mortar (1:6) cum 0.100 1823.25 182.33
B. LABOUR
Mason 1st class day 0.420 285.00 119.70
Mason 2nd class day 0.920 260.00 239.20
Man Mazdoor day 0.700 215.00 150.50
Woman Mazdoor day 2.100 215.00 451.50
Total 1484.23
BLD-CSTN-7 FLOORING
71 Flooring with 25mm thick polished shabad stones
set over base coat of CM (1:8) over already laid CC
bed / RCC Roof Slab, including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm. &
Jointed with neat cement to full depth including cost
of all materials like cement, sand, and water and
BLD-CSTN-7-1 flooring stones etc., complete, including seigniorage
charges, labour charges for dressing of flooring
stones etc., complete for finished item of work, but
excluding the cost of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Polished Shahbad Stone (White) (0.457 x 0.457m) SSR sqm 11.00 75.00 825.00 BMT-
item No. (36) B.03
Cement for CM (1:8) proportion for base coat kg. 21.60 5.50 118.80
Cement for slurry kg. 33.00 5.50 181.50
Cement for jointing kg. 20.00 5.50 110.00
Sand for CM (1:8) proportion cum 0.12 425.00 51.00
Seigniorage charges of sand cum 0.12
B. LABOUR:
Mason 1st class day 3.10 285.00 883.50
Mason 2nd class day 1.10 260.00 286.00
Mazdoor (unskilled) day 0.86 215.00 184.90
Add water charges 1% 26.41
Grand Total 2667.11
Rate per 1 Sq.m 266.71
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
72 Flooring with 40 mm thick Rough Cuddapah/Shabad
stones, set over base coat of cement mortar (1 : 8) 12
mm thick over CC bed already laid or RCC roof slab,
including pointing with cement mortar 1:3 duly filling
joints nearly, including cost of all materials like
flooring stone, cement, sand, and water etc.,
BLD-CSTN-7-2 complete, including seigniorage charges, labour
charges for dressing of flooring stones etc.,
complete for finished item of work, but excluding the
cost of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm thick) (0.457 x sqm 10.50 96.80 1016.40
0.457 m)
Cement for CM (1:8) proportion for base coat kg. 21.60 5.50 118.80
Cement for CM 1:3 proportion for pointing kg. 9.60 5.50 52.80
Sand for CM (1:8) proportion cum 0.12 425.00 51.00
Sand for CM (1:3) proportion cum 0.02 425.00 8.50
Seigniorage charges of sand cum 0.14
B. LABOUR:
Mason 1st class day 0.960 285.00 273.60
Mason 2nd class day 2.240 260.00 582.40
Mazdoor (unskilled) day 3.30 215.00 709.50
Add water charges 1% 28.13
Grand Total 2841.13
Rate per 1 Sq.m 284.11
73 Flooring with polished marble slab 20 mm thick set
over base coat of cement mortar (1:6) 20 mm thick
(joints of stone must be flushed) over CC bed
already laid or RCC roof slab, including near cement
slurry of honey like consistency spread @ 3.30 kgs
per sqm. Jointed with neat cement to full depth
mixed with pigment of matching shade, including
BLD-CSTN-7-3 cost of all materials like flooring slab, cement, sand,
and water etc., complete, including seigniorage
charges, labour charges for dressing, rubbing and
polishing of flooring stones etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Marble slab of size 0.305 M x 0.305 M sqm 10.10 460.00 4646.00 BMT-
B.13
Cement for CM (1:6) proportion for base coat kg. 48.00 5.50 264.00
Cement for slurry for bedding kg. 33.00 5.50 181.50
White Cement for pointing kg. 5.00 25.00 125.00 BMS-
W.68
Sand for CM (1:6) cum 0.20 425.00 85.00
Seigniorage charges of sand cum 0.20
B. Machinery
Machine for rubbing of floor day 1.00 1800.00 1800.00 BMC-
X.01
C. LABOUR:
Mason 1st class day 2.10 285.00 598.50
Mason 2nd class day 3.00 260.00 780.00
Mazdoor (unskilled) day 5.00 215.00 1075.00
Add water charges 1% 95.55
Grand Total 9650.55
Rate per 1 Sq.m 965.06
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
74 Flooring with chequrred terrazzo tiles of 22 mm thick
(medium shade) set over base coat of cement mortar
(1:6) 12 mm thick over CC bed already laid or RCC
roof slab, including near cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed with
neat cement to full depth mixed with pigment of
BLD-CSTN-7-4 matching shade including cost of all materials like
cement, sand water and tiles etc., complete,
including seigniorage charges, complete for finished
item of work, but excluding the cost of conveyance
of all materials.
Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick (medium sqm 10.05 229.00 2301.45 BMT-
shade) D.01
Cement for CM (1:6) proportion for base coat kg. 28.80 5.50 158.40
Cement for slurry kg. 33.00 5.50 181.50
Cement for jointing & pointing kg. 6.00 5.50 33.00
Pigment kg.
Sand for CM (1:6) proportion cum 0.12 425.00 51.00
Seigniorage charges of sand cum 0.12
B. MACHINERY
Nill
C. LABOUR
Mason 2nd class day 0.960 260.00 249.60
Man mazdoor day 2.240 215.00 481.60
Mazdoor (unskiled) day 3.30 215.00 709.50
Add water charges 1% 41.66
Grand Total 4207.71
Rate per 1 Sq.m 420.77
75 Flooring with vitrified tiles of 1st quality, set over
base coat of cement mortar (1:8), 12 mm thick over
CC bed already laid or RCC roof slab, including neat
cement slurry of honey like consistency spread @
3.3.kgs per sqm & jointed neatly with white cement
paste to full depth mixed with pigment of matching
BLD-CSTN-7-5 shade, including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for finished item
of work, but excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size sqm 10.10 1024.00 10342.40 BMT-
C.13
Cement for CM (1:8) for base coat kg. 21.60 5.50 118.80
Cement for slurry kg. 33.00 5.50 181.50
Cement for Pointing with CM (1:3) kg. 6.000 5.50 33.00
Sand for CM (1:8) cum 0.12 425.00 51.00
Sand for pointing cum 0.020 425.00 8.50
Seigniorage charges of sand cum 0.140
B. LABOUR
Mason 1st class day 0.96 285.00 273.60
Mason 2nd class day 2.24 260.00 582.40
Mazdoor (unskiled) day 3.30 215.00 709.50
Add water charges 1% 1.00% 123.01
Grand Total 12423.71
Rate per 1 Sq.m 1242.37
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
76 Flooring with ceramic tiles, set over base coat of
cement mortar (1:8), 12 mm thick over CC bed
already laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @ 3.3.kgs
per sqm & jointed neatly with white cement paste to
full depth mixed with pigment of matching shade,
BLD-CSTN-7-6 including cost of all materials like cement, sand
water and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of work, but
excluding the cost of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles sqm 10.10 450.00 4545.00 BMT-
C.02
Cement for CM (1:8) for base coat kg. 21.60 5.50 118.80
Cement for slurry kg. 33.00 5.50 181.50
White cement kg. 2.00 25.00 50.00
Sand for CM (1:8) cum 0.12 425.00 51.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason 1st class day 0.96 285.00 273.60
Mason 2nd class day 2.24 260.00 582.40
Mazdoor (unskiled) day 3.30 215.00 709.50
Add water charges 1% 1.00% 65.12
Grand Total 6576.92
Rate per 1 Sq.m 657.69
77 Flooring with high polished granite 16 to 18 mm mm
thick slabs other than black set over base coat of
cement mortar (1:8), 20 mm thick over CC bed
already laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @ 3.3.kgs
per sqm & jointed neatly with white cement paste
mixed with pigment of matching shade to full depth,
BLD-CSTN-7-7 including cost of all materials like cement, sand
water and tilesetc., complete, including seigniorage
charges, labour charges for dressing of tilesetc.,
complete for finished item of work, but excluding the
cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
High polished granite 16 to 18 mm thick slab other than sqm 10.10 2000.00 20200.00 BMT-
black B.10
Cement for CM (1:8) for base coat kg. 36.00 5.50 198.00
Cement for slurry kg. 33.00 5.50 181.50
White cement for jointing & pointing kg. 6.00 25.00 150.00
Cement for jointing kg.
Sand for CM (1:8) cum 0.20 425.00 85.00
Seigniorage charges of sand cum 0.20
B. LABOUR
Mason 1st class day 3.00 285.00 855.00
Mason 2nd class day 1.00 260.00 260.00
Mazdoor (unskiled) day 8.00 215.00 1720.00
Add water charges 1% 1.00% 236.50
Grand Total 23886.00
Rate per 1 Sq.m 2388.60
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
78 Flooring with marble tiles polished 8 mm thick set
over base coat of cement mortar (1:8), 12 mm thick
over CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency spread
@ 3.3.kgs per sqm & jointed neatly with white
cement paste mixed with pigment of matching shade
BLD-CSTN-7-8 to full depth, including cost of all materials like
cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Marble tiles polished 8 mm thick sqm 10.10 371.00 3747.10 BMT-
B.15
Cement for CM (1:8) for base coat kg. 36.00 5.50 198.00
Cement for slurry kg. 33.00 5.50 181.50
White cement for jointing & pointing kg. 5.00 25.00 125.00
Sand for CM (1:8) cum 0.20 425.00 85.00
Seigniorage charges of sand cum 0.20
B. LABOUR (including for polishing & rubbing)
Mason 1st class day 4.00 285.00 1140.00
Mazdoor (unskiled) day 8.00 215.00 1720.00
Add water charges 1% 1.00% 71.97
Grand Total 7268.57
Rate per 1 Sq.m 726.86
79 Flooring with granite stone tiles 8 mm thick (mirror
polished of all shades) set over base coat of cement
mortar (1:6), 12 mm thick over CC bed already laid or
RCC roof slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm & jointed
neatly with white cement paste mixed with pigment
of matching shade to full depth, including cost of all
BLD-CSTN-7-9 materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work, but excluding the
cost of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Granite stone tiles 8 mm thick (mirror polished of all sqm 10.10 780.00 7878.00
shades)
Cement for CM (1:6) for base coat kg. 48.00 5.50 264.00
Sand for CM (1:6) cum 0.20 425.00 85.00
Seigniorage charges of sand cum 0.20
B. LABOUR
Mason 1st class day 4.00 285.00 1140.00
Mazdoor (unskiled) day 8.00 215.00 1720.00
Add water charges 1% 1.00% 110.87
Grand Total 11197.87
Rate per 1 Sq.m 1119.79
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
80 Flooring with decorated white back ground glazed
tiles, set over base coat of cement mortar (1:6), 12
mm thick over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed
neatly with white cement paste mixed with pigment
of matching shade to full depth, including cost of all
BLD-CSTN-7-10 materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work, but excluding the
cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Decorated white back ground glazed tiles sqm 10.10 459.00 4635.90 BMT-
C.03
Cement for CM (1:6) for base coat kg. 28.80 5.50 158.40
Cement for slurry kg. 33.00 5.50 181.50
White cement for jointing & pointing kg. 6.00 25.00 150.00
Sand for CM (1:6) cum 0.12 425.00 51.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason 1st class day 0.96 285.00 273.60
Mason 2nd class day 2.24 260.00 582.40
Mazdoor (unskiled) day 3.30 215.00 709.50
Add water charges 1% 1.00% 67.42
Grand Total 6809.72
Rate per 1 Sq.m 680.97
83 Gronolithie Concrete Flooring 20 mm thick with
(1:1:2), using 6mm to 12 mm size hard granite
machine crushed metal laid over CC bed already laid
or RCC roof slab, in alternate panels of size not
exceeding 1.50 m x 1.50 m and finishing the top
surface to required smoothness and slopes and
BLD-CSTN-7-13 thread lining including cost of all materials like
cement, metal, sand and water etc., complete,
including seigniorage charges, etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine crushed) cum 0.17 805.00 136.85 M-043
Cement kg 120.00 5.50 660.00
Sand cum 0.085 425.00 36.13
Seigniorage charges of sand cum 0.085
B. LABOUR
Mason 1st class day 1.25 285.00 356.25
Mason 2nd class day 0.06 260.00 15.60
Mazdoor (unskiled) day 3.00 215.00 645.00
Add water charges 1% 1.00% 18.50
Grand Total 1868.32
Rate per 1 Sq.m 186.83
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
88 Providing skirting to internal walls to 15 cm
height/risers of steps with ceramic tiles 7.30 mm
thick length equal to flooring stones, set over base
coat of CM (1:3) 12 mm thick with cement slurry of
honey like consistency spread at the rate of 3.30 kgs
per sqm and jointed with white cement paste mixed
with pigment of matching shade to full depth,
BLD-CSTN-7-18 including cost of all materials like tiles, cement, sand
and water etc., complete including seigniorage
charges, etc., complete for finished item of work, but
excluding the cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick sqm 10.00 374.00 3740.00 BMT-
C.01
Sand for cm 1:3 base coat cum 0.12 425.00 51.00
Cement for cm 1:3 base coat kgs 57.60 5.50 316.80
Cement for slurry kgs 33.00 5.50 181.50
White cement for jointing & pointing kgs 6.00 25.00 150.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason 1st class day 0.77 285.00 219.45
Mazdoor (unskiled) day 0.80 215.00 172.00
Grand Total 4830.75
Rate per 1 Sq.m 483.08
89 Providing skirting to internal walls to 15 cm
height/risers of steps with marble slab……..mm
thickness, length equal to flooring stones, set over
base coat of CM (1:3) 12 mm thick with cement slurry
of honey like consistency spread at the rate of 3.30
kgs per sqm and jointed with white cement paste
mixed with pigment of matching shade to full depth,
BLD-CSTN-7-19 including cost of all materials like marble slab,
cement, sand and water etc., complete including
seigniorage charges, etc., complete for finished item
of work, but excluding the cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
Marble slab………mm thickness sqm 10.10 570.00 5757.00 BMT-
B.12
Sand for base coat cum 0.12 425.00 51.00
Cement for base coat kg 57.60 5.50 316.80
Cement for slurry kg 33.00 5.50 181.50
White cement for jointing & pointing kg 5.00 25.00 125.00
Flate nosing charges RM 66.67 10.00 666.70 BMM-
V.13
Machine cutting charges RM 67.67 10.00 676.70 BMM-
V.12
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 2.10 285.00 598.50
Man mazdoor (Beldar) day 4.90 215.00 1053.50
Man mazdoor (Beldar) for polishing & rubbing day 4.00 215.00 860.00
Woman mazdoor day 4.00 215.00 860.00
Grand Total 11146.70
Rate per 1 Sq.m 1114.67
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
90 Providing skirting to internal walls to 15 cm
height/risers of steps with vitrified tiles length equal
to flooring stones, set over base coat of CM (1:5) 12
mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm
and jointed with white cement paste mixed with
BLD-CSTN-7-20 pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges,
etc., complete for finished item of work, but
excluding the cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles polished 1st quality sqm 10.10 1500.00 15150.00 BMT-
C.50
Sand for cm 1:5 base coat cum 0.12 425.00 51.00
Cement for cm 1:5 base coat kgs 34.56 5.50 190.08
Cement for slurry kgs 33.00 5.50 181.50
White cement for jointing & pointing kgs 2.00 25.00 50.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 0.96 285.00 273.60
Mason 2nd class day 2.24 260.00 582.40
Mazdoor (unskilled) day 3.30 215.00 709.50
Add water charges 1% 1.00% 171.88
Grand Total 17359.96
Rate per 1 Sq.m 1736.00
91 Providing skirting to internal walls to 15 cm
height/risers of steps with 8 mm thick mirror
polished granite tiles length equal to flooring stones,
set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread at
the rate of 3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of matching shade
BLD-CSTN-7-21 to full depth, including cost of all materials like tiles,
cement, sand and water etc., complete including
seigniorage charges, etc., complete for finished item
of work, but excluding the cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles sqm 10.10 780.00 7878.00 BMT-
B.16
Sand for cm 1:3 base coat cum 0.12 425.00 51.00
Cement for cm 1:3 base coat kgs 57.60 5.50 316.80
Cement for slurry kgs 33.00 5.50 181.50
White cement for jointing & pointing kgs 5.00 25.00 125.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 2.10 285.00 598.50
Mazdoor (unskiled) day 0.80 215.00 172.00
Mason 2nd class 4.90 260.00 1274.00
Add water charges 1% 1.00% 105.97
Grand Total 10702.77
Rate per 1 Sq.m 1070.28
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
92 Providing skirting to internal walls to 15 cm
height/risers of steps with 25 mm thick polished
Cuddapah stone length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with cement
slurry of honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white cement
paste mixed with pigment of matching shade to full
BLD-CSTN-7-22 depth, including cost of all materials like Cuddapah
stone, cement, sand and water etc., complete
including seigniorage charges, etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Cuddapah stone sqm 10.10 107.60 1086.76 BMT-
B.06
Sand for cm 1:3 base coat cum 0.12 425.00 51.00
Cement for cm 1:3 base coat kgs 57.60 5.50 316.80
Cement for slurry kgs 33.00 5.50 181.50
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 0.96 285.00 582.40
Mason 2nd class day 2.24 260.00 666.50
Mazdoor (unskiled) day 3.10 215.00 0.01
Add water charges 1% 1.00% 28.85
Grand Total 2913.82
Rate per 1 Sq.m 291.38
93 Providing skirting to internal walls to 15 cm
height/risers of steps with 25 mm thick polished
Shahabad stone length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with cement
slurry of honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white cement
paste mixed with pigment of matching shade to full
BLD-CSTN-7-23 depth, including cost of all materials like Shahabad
stone, cement, sand and water etc., complete
including seigniorage charges, etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Shahabad stone (White) sqm 10.10 75.00 757.50 BMT-
B.03
Sand for cm 1:3 base coat cum 0.12 425.00 51.00
Cement for cm 1:3 base coat kgs 57.60 5.50 316.80
Cement for slurry kgs 33.00 5.50 181.50
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 0.96 285.00 273.60
Mason 2nd class 2.24 260.00 582.40
Mazdoor (unskiled) day 3.10 215.00 666.50
Add water charges 1% 1.00% 28.29
Grand Total 2857.59
Rate per 1 Sq.m 285.76
Note : When Mortar mix is changed proportionate quantity of
94 cement has to be
Teak Wood substituted
Flooring for allThick
40mm. Skirting Items. and
Tongued
BLD-CSTN-7-24 Grooved Planks, including cost of all materials,
labour etc., complete
Unit = 10 sqm
A. MATERIALS:
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Teak Wood Planks 40mm thick cum 0.44 102414.00 45062.16 BMT-
E.04
75 mm Long Screws 100 3.00 118.80 356.40 ELEC-
Nos 1.4.39
B. LABOUR
Carpenters 1st Class day 1.95 285.00 555.75
Carpenters 2nd Class day 4.55 260.00 1183.00
Man mazdoor day 5.40 215.00 1161.00
Note : Deduct 4.3 Nos Carpenters if plank rate is for tongued
and
Grandgrooved
Total ready planned. 48318.31
Rate per 1 Sq.m 4831.83
95 Flooring with Gravel 150 mm thick including cost of
BLD-CSTN-7-25 all materials, labour, watering etc., complete
Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage) cum 1.53 80.00 122.40
B. LABOUR
Man mazdoor day 1.10 215.00 236.50
Woman mazdoor day 0.50 215.00 107.50
Grand Total 466.40
Rate per 1 Sq.m 46.64
BLD-CSTN-8 ROOFING & CEILING
96 Roofing with corrugated G.I sheets 0.80mm thick
fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen
& G.I limpet washers filled with white lead &
including a coat of approved steel primer and two
coats of approved paint on over lapping of sheets
BLD-CSTN-8-1
complete (up to a pitch of 600) and seigniorage
charges, etc., complete, excluding the cost of
purlins, rafters, trusses & cost of conveyance of all
materials
Limpet washers (for scam & ‘J’ bolts) 884 + 810 = nos 91.82 0.25 22.95 BMS-
1694 W.66
Bitumen washers nos 91.82 0.20 18.36 BMS-
W.67
Zinc cromate yellow paint litre 0.14 130.00 17.83 BMT-J.04
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Add for Standard specification 1mm. Thick ridging and LS
1.25 mm thick sheet vallyes when such are required for a
particular work. Average allowance for 10 sqm roofing.
B. LABOUR M-058
For roofing
Carpenter II class day 0.84 260.00 218.43
Man mazdoor (beldar) day 0.91 215.00 195.77
For premier painting one coat
Painter day 0.06 285.00 17.46
Mazdoor (coolie) day 0.06 215.00 13.17
For two coats of painting to over laps
Painter day 0.14 285.00 39.08
Mazdor (coolie) day 0.14 215.00 29.48
Grand Total 7524.77
Rate per 1 Sq.m 40.78
98 Roofing with corrugated G.I sheets 1.25mm thick
fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen
& G.I limpet washers filled with white lead &
including a coat of approved steel primer and two
coats of approved paint on over lapping of sheets
BLD-CSTN-8-3
complete (upto a pitch of 600) and seigniorage
charges, turnover tax etc., complete, excluding the
cost of purlins, rafters, trusses & cost of conveyance
of all materials
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Bitumen washers nos 91.82 0.20 18.36 BMS-
W.66
Zinc cromate yellow paint litre 0.14 130.00 17.83 BMS-
W.67
Ready mixed paint litre 0.20 285.00 57.93 BMT-J.04
B. LABOUR M-058
For roofing
Carpenter II class day 0.84 260.00 218.43
Man mazdoor (beldar) day 0.91 215.00 195.77
For premier painting one coat
Painter day 0.06 285.00 17.46
Mazdoor (coolie) day 0.06 215.00 13.17
For two coats of painting to over laps
Painter day 0.14 285.00 39.08
Mazdor (coolie) day 0.14 215.00 29.48
Grand Total 8961.08
Rate per 1 Sq.m 48.56
99 Roofing with 6 mm thick corrugated asbestos
cement sheets, fixing with G.I ‘J’ bolts & nuts 8 mm
dia G.I plain washers complete including seigniorage
BLD-CSTN-8-4 charges etc., complete for finished item of work, but
excluding the cost of purlins, rafters, trusses & cost
of conveyance of all materials – upto 600 pitch.
8 mm dia G.I ‘J’ bolts & nuts nos 22.03 8.00 176.21 BMS-
W.64
G.I washers nos 22.03 0.50 11.01 BMS-
W.65
Bitumen washers nos 22.03 0.20 4.41 BMS-
W.67
B. LABOUR
Carpenter II class day 0.43 260.00 112.37
Man mazdoor day 0.54 215.00 116.21
Sundries including 50 x 6 mm iron wind ties white lead LS
etc.
Add for Standard specification 1mm. Thick ridging and LS
1.25 mm thick sheet vallyes when such are required for a
particular work. Average allowance for 10 sqm roofing.
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 cum 0.210 3143.25 660.08
Water proof compound kg 2.000 58.00 116.00
B. LABOUR
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Mason 1st class day 0.660 285.00 188.10
Mason 2nd class day 1.540 260.00 400.40
Mazdoor (unskiled) day 3.70 215.00 795.50
Grand Total 2160.08
Rate per 1 Sq.m 216.01
121 Providing & fixing insulating board ceiling of
approved quality with nails etc., complete, excluding
BLD-CSTN-8-26 the cost of frame work for base and cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
12 mm thick insulating board sqm 11.00 177.00 1947.00 BMT-
K.25
B. LABOUR
Carpenter Ist class day 2.50 285.00 712.50
Man mazdoor day 2.00 215.00 430.00
Grand Total 3089.50
Rate per 1 Sq.m 308.95
122 Providing & fixing hard board sheet ceiling of
approved quality with nails etc., complete, excluding
BLD-CSTN-8-27 the cost of frame work for base and cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
3 mm thick standard quality of hard board sqm 11.00 215.00 2365.00 BMT-
M.02
B. LABOUR
Carpenter Ist class day 2.50 285.00 712.50
Man mazdoor day 2.00 215.00 430.00
Grand Total 3507.50
Rate per 1 Sq.m 350.75
123 Providing & fixing flat pressed 3 layer medium
density particle board sheet with necessary nails
BLD-CSTN-8-28 etc., complete, excluding the cost of frame work for
base and cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Standard quality of flat pressed 3 layer medium density sqm 11.00 215.00 2365.00
board sheet 4.50 mm thick
B. LABOUR
Carpenter Ist class day 2.50 285.00 712.50
Man mazdoor day 2.00 215.00 430.00
Grand Total 3507.50
124 Providing & fixing plain AC sheet ceiling of approved 350.75
quality with necessary nails etc., complete,
BLD-CSTN-8-29 excluding the cost of frame work for base and cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Plain AC sheet for ceiling sqm 11.00 800.00 8800.00 M-061
B. LABOUR
Carpenter Ist class day 2.50 285.00 712.50
Man mazdoor day 2.00 215.00 430.00
Grand Total 9942.50
Rate per 1 Sq.m 994.25
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
125 Providing 10 mm thick plaster of paris (Gypsum
anhydrous) ceiling upto a height of 5 m above floor
level over first class BT wood strips 25 x 6 mm with
BLD-CSTN-8-30 10 mm gap in between and reinforced with rabbit
wire mesh fixed to wooden frame excluding cost of
wooden frame for base & cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Wooden strips 1st class BT wood 25 x 6 mm size cum 0.05 1000.00 47.50 M-195
Nails kg 0.75 45.00 33.75 BMT-
F.02
Rabbit wire mesh sqm 10.20 12.00 122.40 BMT-
F.28
Plaster of paris kg 219.76 15.00 3296.40 BMT-
H.91
B. LABOUR
for Jointing the wooden strips including fixing the
rabbit mesh
Carpenter Ist class day 2.60 285.00 741.00
Man mazdoor (beldar) day 1.60 215.00 344.00
For doing plaster of paris over wooden strips
Mason Ist class day 2.62 285.00 745.28
Mason IInd class day 1.62 260.00 419.90
Mazdoor (unskilled) day 3.77 215.00 810.55
Grand Total 6560.78
Rate per 1 Sq.m 656.08
Gypboard Suspended false ceiling
126 Supplying and fixing Gyp Board Suspended regular
single layer false ceiling (GS-MFSC-4.1 as per India
Gypsum) using 12.5 mm thick Gyp Board conforming to
IS 2095 - 1982 fixing to Gyp steel GI perimeter channels
of size 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick
along the perimeter of ceiling screw fixed to brick work/
partition at 610 mm c/c and suspending the frame work
using Intermediate channels (45 mm x 15mm x 15mm x
0.9 mm) from soffit at 1220 mm c/c with ceiling angle (25
mm x 10 mm x 0.55 mm) fixed with GI Cleat and steel
expansion fasteners & connecting clip to the ceiling
channels (with knurled web of 51.5 mm x 26 mm x 10.5
BLD-CSTN-8-31 mm x 0.55 mm) fixed in direction perpendicular to the
intermediate channel at 457 mm c/c and fixing the 12.5
mm tapered edge Gypboard with 25 mm drywall screws
at 230 mm c/c & jointing and finishing using joint
compound and paper tape to have a flush look including
filling the tapered & square edges with jointing
compound, two coats of drywall topcoat complete for
finished item of work as per Idia Gypsum Ltd
specification.
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards sqm 1.03 200.00 205.12 BMT-
M.03
Ceiling Angle
25 mm x 10 mm x 0.55 mm RM 0.64 65.00 41.60 BMT-
M.04
Connecting Clips Nos 1.84 2.00 3.68 BMT-
M.17
Ceiling Section
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick RM 2.30 74.00 170.20 BMT-
M.05
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm RM 0.84 73.00 61.32 BMT-
M.06
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm thick RM 0.40 65.00 26.00 BMT-
M.07
Rawl Plug Nos 0.64 1.50 0.96 BMT-
M.18
Soffit Cleats Nos 0.64 1.50 0.96 BMT-
M.20
Drywall Screws - 25 mm Nos 18.00 1.50 27.00 BMT-
M.21
Jointing Compound Kgs 0.55 25.00 13.75 BMT-
M.22
Jointing Paper Tape RM 1.46 5.00 7.30 BMT-
M.23
Drywall Top Coat Lits 0.15 125.00 18.75 BMT-
M.24
B) LABOUR CHARGES
1st Class Carpenter day 0.40 285.00 114.00
2nd Class Carpenter day 0.40 260.00 104.00
1st Class Painter day 0.08 285.00 22.80
2nd Class Painter day 0.08 260.00 20.80
Power Saw Cutter - Hand Operated - Operator day 0.04 285.00 11.40
Power Drill - Hand Operated - Operator day 0.08 285.00 22.80
Unskilled Mazdoor day 0.24 215.00 51.60
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 105.00 33.60 BMC-
X.02
Power Drill - Hand Operated - Hire Charges Hrs 0.64 97.00 62.08 BMC-
X.03
Scaffolding charges 1% 10.20
BASIC COST per 1 sqm 1029.92
Gyp Board Fine Line Grid false ceiling
127 Supplying and fixing Gyp Board Fine Line Grid false
ceiling (GS-FLC-4.6 as per India Gypsum) in size 600
mm x 600 mm using 12.5 mm thick/ 9.5 mm thick Gyp
Board sheet tiles of size 595 mm x 595 mm or 595 mm x
1195 mm conforming to IS 2095 - 1982 fixing to Gyp
steel precoated GI wall angle of size 25 mm x 25 mm x
of 0.70 mm thick along the perimeter of ceiling screw
fixed to brick work/ partition at 610 mm c/c and
suspending the frame work using precoated GI Tee
section (24 mm x 38 mm x 0.7 mm) from soffit at 1220
mm c/c fixed with GI Soffit Cleat, rawl plugs and steel
BLD-CSTN-8-32 expansion fasteners & connecting clip to the GI T section
with 4 mm dia GI Rod with galvanised spring steel level
clip of PVC unversal holding clips system at 1200 mm c/c
and fixing the 12.5 mm / 9.5 mm Gypboard Sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195 mm and
finishing two coats of drywall topcoat complete for
finished item of work as per Idia Gypsum Ltd
specification.
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm - sqm 1.00 220.00 220.42 BMT-
M.01
Or - 595 mm x 1195 mm -
GI Angle - Precoated
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
25 mm x 25 mm x 0.7 mm RM 0.40 65.00 26.00
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick RM 1.60 47.00 75.20 BMT-
M.10
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick RM 1.60 47.00 75.20
GI Rod - 4 mm Dia
Connecting Rod RM 1.28 10.00 12.80 BMT-
M.26
Rawl Plug Nos 1.28 1.50 1.92 BMT-
M.18
Soffit Cleats Nos 1.28 1.50 1.92
Unversal Holding Clips Nos 5.36 2.50 13.40 BMT-
M.25
Drywall Top Coat Lits 0.15 125.00 18.75 BMT-
M.24
B) LABOUR CHARGES 0.00
1st Class Carpenter day 0.40 285.00 114.00
2nd Class Carpenter day 0.40 260.00 104.00
1st Class Painter day 0.08 285.00 22.80
2nd Class Painter day 0.08 260.00 20.80
Power Saw Cutter - Hand Operated - Operator day 0.04 285.00 11.40
Power Drill - Hand Operated - Operator day 0.04 285.00 11.40
Unskilled Mazdoor day 0.24 215.00 51.60
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 105.00 33.60
Power Drill - Hand Operated - Hire Charges Hrs 0.32 97.00 31.04
Scaffolding charges 1% 8.46
BASIC COST per 1 sqm 854.71
Armstrong False ceiling
128 Providing and fixing in true horizontal level 600 mm x
600 mm 15 mm thick Arm strong false ceiling system
manufactured by M/s Arm strong world Industries using
hot dipped Galvanised Steel section exposed surface
with pre-coated capping, main Tee of size 24 x 32 mm at
every 1200 mm c/c maximum and rotary stiched cross
tee of size 24 x 27 mm at evry 600 mm c/c and sub-cross
tee of size 24 mm x 25 mm at 1200 mm c/c and wall
angle of size 19 x 19 mm fixed to periphery of the wall
and the above grid is suspended at every 1200 mm c/c
in both directions using 2.0 mm thick pre-straightened GI
BLD-CSTN-8-33 Wire laying fine fissured butt edge ceiling tiles of 15 mm
thick mineral fiber Board manufactured by M/s Arm
Strong World Industries Ltd., having RH 99% and for
finished of size 600 x 600 mm including Cost
&conveyance of all materials and labour charges such as
cutting , fixing of standing of frame work exposing roof
making complete for finished item of work
UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x 600 sqm 1.00 450.00 450.86 BMT-
M.29
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm RM 0.40 35.00 14.00 BMT-
M.11
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross Tee) RM 1.60 44.00 70.40 BMT-
M.12
Polyster painted GI - T Section - 300 mm
24 mm x 27 mm RM 1.60 40.00 64.00 BMT-
M.14
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod RM 1.28 10.00 12.80 BMT-
M.26
6 mm Nylon Rawl Plug Nos 1.28 2.50 3.20 BMT-
M.19
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter day 0.40 285.00 114.00
2nd Class Carpenter day 0.40 260.00 104.00
1st Class Painter day 0.08 285.00 22.80
2nd Class Painter day 0.08 260.00 20.80
Power Saw Cutter - Hand Operated - Operator day 0.04 285.00 11.40
Power Drill - Hand Operated - Operator day 0.04 285.00 11.40
Unskilled Mazdoor day 0.24 215.00 51.60
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 105.00 33.60
Power Drill - Hand Operated - Hire Charges Hrs 0.32 97.00 31.04
Scaffolding charges 1% 10.16
BASIC COST per 1 sqm 1026.05
Thermocole False ceiling
129 Providing and fixing Thermocole False ceiling in true
horizontal level 600 mm x 600 mm using 15 mm/ 19 mm
thick Thermocole sheet anodised Aluminium Tee
sections of size 24.50 mm x 24.0 mm x 2.4 mm in grid
with cross tee of size 24 x 24.5 mm at every 600 mm c/c
and anodised aluminium wall angle of size 24 x 24 mm
fixed to periphery of the wall and the above grid is
BLD-CSTN-8-34 suspended at every 1200 mm c/c in both directions using
2.0 mm thick GI Wire for finished of size 600 x 600 mm
including Cost &conveyance of all materials and labour
charges such as cutting , fixing of standing of frame work
exposing roof making complete for finished item of work
UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600 sqm 1.00 40.00 40.08 BMT-
M.38
Alumninium Angle
24 mm x 24 mm RM 0.40 23.00 9.20 BMT-
M.15
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm RM 3.20 30.00 96.00 BMT-
M.16
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod Nos 1.28 10.00 12.80 BMT-
M.26
Rawl Plugs Nos 1.28 1.50 1.92 BMT-
M.18
B) LABOUR CHARGES
1st Class Carpenter day 0.36 285.00 102.60
2nd Class Carpenter day 0.36 260.00 93.60
1st Class Painter day 0.00 285.00 0.00
2nd Class Painter day 0.00 260.00 0.00
Power Saw Cutter - Hand Operated - Operator day 0.02 285.00 5.70
Power Drill - Hand Operated - Operator day 0.04 285.00 11.40
Unskilled Mazdoor day 0.20 215.00 43.00
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges Hrs 0.16 105.00 16.80
Power Drill - Hand Operated - Hire Charges Hrs 0.32 97.00 31.04
Scaffolding charges 1% 4.64
BASIC COST per 1 sqm 468.78
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
WHITE WASHING, COLOUR WASHING &
BLD-CSTN-9
DISTEMPERING
133 White washing one coat with whiting of approved
quality to give an even shade after thoroughly
brushing the surface to remove all dirt and remains with
of loose powdered materials including cost of all White
BLD-CSTN-9-4 materials, labour charges and incidental such as Cement
scaffolding, lift charges etc., complete for finished Grade II
item of work, but excluding conveyance charges of
materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 1.20 25.00 30.00
kg
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.11 285.00 31.35
Mazdoor (unskilled) day 0.22 215.00 47.30
Sundries including brushes, ladders, etc., 0.50% 0.39
Total cost for 10 sqm 109.04
Rate per 1 Sq.m 10.90
134 White washing two coats with whiting of approved
quality to give an even shade after thoroughly
brushing the surface to remove all dirt and remains
of loose powdered materials including cost of all
BLD-CSTN-9-5 materials, labour charges and incidental such as
scaffolding, lift charges etc., complete for finished
item of work, but excluding conveyance charges of
materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 2.00 25.00 50.00
kg
Gum, conjee water, or prickly pear juice including L.S
necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.210 285.00 59.85
Mazdoor (unskilled) day 0.320 215.00 68.80
Sundries including brushes, ladders, etc., 1.00% 1.29
Total cost for 10 sqm 179.94
Rate per 1 Sq.m 17.99
135 White washing three coats with whiting of approved
quality to give an even shade after thoroughly
brushing the surface to remove all dirt and remains
of loose powdered materials including cost of all
BLD-CSTN-9-6 materials, labour charges and incidental such as
scaffolding, lift charges etc., complete for finished
item of work, but excluding conveyance charges of
materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 2.800 25.00 70.00
kg
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.300 285.00 85.50
Mazdoor (unskilled) day 0.430 215.00 92.45
Total cost for 10 sqm 247.95
Rate per 1 Sq.m 24.79
138 Distempering, 2 Coats with Water Bound Distemper
BLD-CSTN-9-9
256
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Unit: 10 sqm
A. MATERIALS :
Distemper kg 1.340 60.00 80.40 BMT-J.21
B. LABOUR
Painter day 0.500 285.00 142.50
Mazdoor (unskilled) day 1.300 215.00 279.50
Sundries including brushes, ladders, etc., 1.000% 4.22
Total cost for 10 sqm 506.62
Rate per 1 Sq.m 50.66
PRIMARY COAT:
Cost of Primer kg 0.50 60.00 30.00
Painter I st class Nos 0.08 285.00 22.80
Pianter Iind class Nos 0.19 260.00 49.40
Cost of washable Oil Bound Distemper Kg 1.70 60.00 102.00 BMT-J.21
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soaps, putty etc., 0.500% 1.00
Total cost for 10 sqm 300.50
Rate per 1 Sq.m 30.05
142 Painting Walls with Snowcem or other equal and
BLD-CSTN-10-3 284 approved Water Proof Cement Paint over Priming
Coat, One Coat (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg kg 2.000 100.00 200.00
B. LABOUR
Painter day 0.300 285.00 85.50
Mazdoor (unskilled) day 1.500 215.00 322.50
Sundries including brushes, etc., 1.000% 1.61
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Total cost for 10 sqm 409.61
Rate per 1 Sq.m 40.96
143 Painting Walls with Snowcem or other equal and
BLD-CSTN-10-4 285 approved Water Proof Cement Paint over Priming
Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg kg 3.500 100.00 350.00
B. LABOUR
Painter day 0.500 285.00 142.50
Mazdoor (unskilled) day 1.500 215.00 322.50
Sundries including brushes, etc., 1.000% 1.61
Total cost for 10 sqm 466.61
Rate per 1 Sq.m 46.66
144 Painting to new walls with 2 coats of water proof cement
paint of apporved brand and shade over a base coat of
approved cement primer grade I making making 3 coats
in all to give an even shade after thourughly brushing the
surface to remove all dirt and remains of loose powdered
BLD-CSTN-10-5 materials, including cost and conveyance of all materials
to work site and all operational, incidental, labour
charges etc. complete for finished item of work as per SS
912 for internal walls
B. LABOUR
Painter day 0.70 285.00 199.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 295.50
Rate per 1 Sq.m 29.55
BLD-CSTN-10-8 147 Varnishing to Wood Work, One Coat
281 Unit: 10 sqm
A. MATERIALS :
Varnish L 0.800 100.00 80.00 BMT-J.09
B. LABOUR
Painter day 0.700 285.00 199.50
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Man Mazdoor day 0.700 215.00 150.50
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm 454.00
Rate per 1 Sq.m 45.40
BLD-CSTN-10-9 148 Varnishing to Wood Work, Two Coats
282 Unit: 10 sqm
A. MATERIALS :
Varnish L 1.200 100.00 120.00
Linseed Oil - boiled L 1.100 40.00 44.00
B. LABOUR
Painter day 1.100 285.00 313.50
Man Mazdoor day 1.100 215.00 236.50
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm 714.00
Rate per 1 Sq.m 71.40
BLD-CSTN-10-10 149 Painting with Ready mixed oil paint (all colours)
256 i. One Coat - New Wood Work :
to Unit: 10 sqm
265 A. MATERIALS :
Ready mixed paint kg 1.600 100.00 160.00
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm 359.50
Rate per 1 Sq.m 35.95
ii Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 2.800 100.00 280.00
B. LABOUR
Painter day 1.200 285.00 342.00
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm 622.00
Rate per 1 Sq.m 62.20
iii One Coat - Old Wood Work & New Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 1.500 100.00 150.00
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm 349.50
Rate per 1 Sq.m 34.95
iv Two Coats - Old Wood Work & New Iron Work:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 2.400 100.00 240.00
B. LABOUR
Painter day 1.200 285.00 342.00
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm 582.00
Rate per 1 Sq.m 58.20
v One Coat - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 1.200 100.00 120.00
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm 319.50
Rate per 1 Sq.m 31.95
vi Two Coats - Old Iron Work :
Unit: 10 sqm
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
A. MATERIALS :
Ready mixed paint kg 2.100 100.00 210.00
B. LABOUR
Painter day 1.100 285.00 313.50
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm 523.50
Rate per 1 Sq.m 52.35
vii Three Coats - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 3.400 100.00 340.00
B. LABOUR
Painter day 1.500 285.00 427.50
Sundries including brushes, soap, putty etc., LS
Total cost for 10 sqm 767.50
Rate per 1 Sq.m 76.75
viii Three Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint kg 3.900 100.00 390.00
B. LABOUR
Painter day 1.600 285.00 456.00
Sundries including brushes, soap, putty etc., LS 33.00
Total cost for 10 sqm 879.00
Rate per 1 Sq.m 87.90
BLD-CSTN-10-11 150 Painting with :
266 i. Plastic Emulsion paint Grade I - One Coat for New
Wood Work, Old Wood Work & New Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 0.500 180.00 90.00 BMT-J.22
Paints (I) Ltd.
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 322.50
Rate per 1 Sq.m 32.25
ii Plastic Emulsion paints - One Coat for Old Iron
Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 0.400 180.00 72.00
Paints (I) Ltd.
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 304.50
Rate per 1 Sq.m 30.45
iii Plastic Emulsion paints - Two Coats for New Wood
Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 0.900 180.00 162.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.200 285.00 342.00
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 537.00
Rate per 1 Sq.m 53.70
iv Plastic Emulsion paints - Two Coats for Old Wood
Work & New Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 0.800 180.00 144.00
Paints (I) Ltd.
B. LABOUR
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Painter day 1.200 285.00 342.00
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 519.00
Rate per 1 Sq.m 51.90
v Plastic Emulsion paints - Two Coats for New Iron
Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 0.800 180.00 144.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.100 285.00 313.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 490.50
Rate per 1 Sq.m 49.05
vi Plastic Emulsion paints - Two Coats for Old Iron
Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 0.700 180.00 126.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.100 285.00 313.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 472.50
Rate per 1 Sq.m 47.25
vii Plastic Emulsion paints - Three Coats for New Wood
Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 1.200 180.00 216.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.600 285.00 456.00
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 705.00
Rate per 1 Sq.m 70.50
viii Plastic Emulsion paints - Three Coats for Old Iron
Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per British L 1.100 180.00 198.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.500 285.00 427.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 658.50
Rate per 1 Sq.m 65.85
151 Painting with Synthetic Enamel paints - One Coat -
BLD-CSTN-10-12 i for New Wood Work, Old Wood Work & New Iron
Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 0.700 170.00 119.00 BMT-J.30
Paints (I) Ltd.
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm 318.50
Rate per 1 Sq.m 31.85
ii Painting with Synthetic Enamel paints - One Coat -
For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 0.500 170.00 85.00
Paints (I) Ltd.
B. LABOUR
Painter day 0.700 285.00 199.50
Sundries including brushes, soap, putty etc., 33.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Total cost for 10 sqm 317.50
Rate per 1 Sq.m 31.75
iii Painting with Synthetic Enamel paints - Two Coats -
for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 1.200 170.00 204.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.200 285.00 342.00
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 579.00
Rate per 1 Sq.m 57.90
iv Painting with Synthetic Enamel paints - Two Coats -
For Old Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 1.100 170.00 187.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.200 285.00 342.00
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 562.00
Rate per 1 Sq.m 56.20
v Painting with Synthetic Enamel paints - Two Coats -
For New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 1.100 170.00 187.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.100 285.00 313.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 533.50
Rate per 1 Sq.m 53.35
vi Painting with Synthetic Enamel paints - Two Coats -
For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 0.900 170.00 153.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.100 285.00 313.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 499.50
Rate per 1 Sq.m 49.95
vii Painting with Synthetic Enamel paints - Three Coats -
for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 1.700 170.00 289.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.600 285.00 456.00
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 778.00
Rate per 1 Sq.m 77.80
viii Painting with Synthetic Enamel paints - Three Coats -
For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per British L 1.600 170.00 272.00
Paints (I) Ltd.
B. LABOUR
Painter day 1.500 285.00 427.50
Sundries including brushes, soap, putty etc., 33.00
Total cost for 10 sqm 732.50
Rate per 1 Sq.m 73.25
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
152 Polishing on wood work with readymade wax polish
BLD-CSTN-10-13
of approved brand and manufacture
New Work :
A. MATERIALS :
Readymade wax polish kg 0.500 400.00 200.00 BMT-J.15
B. LABOUR
Painter day 0.800 285.00 228.00
Healper day 0.800 215.00 172.00
Sundries including brushes, soap, cloth etc., LS 33.00
Total cost for 10 sqm 633.00
Rate per 1 Sq.m 63.30
153 Melamine polishing on wood work (one or more coat)
BLD-CSTN-10-14
New Work :
A. MATERIALS :
Melamine polish L 0.650 221.00 143.65
B. LABOUR
Painter day 0.800 285.00 228.00
Healper day 0.800 215.00 172.00
Sundries for Spraying Machine etc., LS 33.00
Total cost for 10 sqm 576.65
Rate per 1 Sq.m 57.67
154 French Spirit polishing Two or more coats on new
BLD-CSTN-10-15
works including a coat of wood filler.
A. MATERIALS :
Shellac kg 0.228 70.00 15.96 BMT-J.10
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and below 3 m in cum 1.000 81225.00 81225.00 BMT-
length E.06
Labour :—
Carpenter day 17.700 285.00 5044.50
Man Mazdoor day 8.800 215.00 1892.00
Sundries including nails, screws etc., LS 33.00
Cost per cum 88194.50
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
157 Best Teak Wood wrought and put up in large
BLD-CSTN-11-3 scantling of over 3 metres in length (Schedule Item
No 288)
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and below 3 m in cum 1.000 84756.00 84756.00 BMT-
length E.07
Labour :—
Carpenter day 17.700 285.00 5044.50
Man Mazdoor day 8.800 215.00 1892.00
Sundries including nails, screws etc., LS 33.00
Cost per cum 91725.50
158 Best Teak Wood wrought and put up for trusses
BLD-CSTN-11-4 including straps and all iron work (Schedule Item No
289)
Unit = 1 cum
Materials :—
Teak wood large scantlings cum 1.000 54738.00 54738.00
Iron Work (average) kg 112.000 50.00 5600.00
Labour :—
Carpenter day 26.500 285.00 7552.50
Man Mazdoor day 8.800 215.00 1892.00
Sundries including nails, screws etc., LS 33.00
Cost per cum 69815.50
159 Fully Panelled doors - External or Internal - Moulded
BLD-CSTN-11-5
panels (Schedule Item No 290)
A Single Shutter
i 800 x 2000 mm
*Teak wood cum 0.083 54738.00 4543.25 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 1.600 230.00 368.00 BMM-
V.23
Sundries inclusive of holdfasts and all wind appliances LS 33.00
(Vide relevant standard specification)
Total for each door 4944.25
ii 900 x 2000 mm
*Teak wood cum 0.088 54738.00 4816.94
Labour, wrought and putup in position frame & shutters sqm 1.800 230.00 414.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
vi 1500 x 2400 mm
*Teak wood cum 0.159 54738.00 8703.34
Labour, wrought and putup in position frame & shutters sqm 3.600 230.00 828.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Sundries inclusive of holdfasts and all wind appliances LS 33.00
(Vide relevant standard specification)
Total for each door 8267.52
iv 1300 x 2200 mm
*Teak wood cum 0.106 54738.00 5802.23
Five - Ply - Ply - Wood brich sqm 1.390 1587.00 2205.93
Labour, wrought and putup in position frame & shutters sqm 2.860 365.00 1043.90
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Labour, wrought and putup in position frame & shutters sqm 3.600 365.00 1314.00
A Single Shutter
i 800 x 2000 mm
*Teak wood cum 0.072 54738.00 3941.14 BMT-
E.01
Glass sqm 0.470 713.00 335.11 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.600 365.00 584.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 4893.25
ii 900 x 2000 mm
*Teak wood cum 0.076 54738.00 4160.09 BMT-
E.01
Glass sqm 0.560 713.00 399.28 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.800 365.00 657.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 5249.37
iii 1200 x 2100 mm
*Teak wood cum 0.106 54738.00 5802.23 BMT-
E.01
Glass sqm 0.760 713.00 541.88 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 2.520 365.00 919.80 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 7296.91
iv 1300 x 2200 mm
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
*Teak wood cum 0.115 54738.00 6294.87 BMT-
E.01
Glass sqm 0.870 713.00 620.31 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 2.860 365.00 1043.90 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 7992.08
B Double Shutter
i 900 x 2000 mm
*Teak wood cum 0.087 54738.00 4762.21 BMT-
E.01
Glass sqm 0.420 713.00 299.46 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.800 365.00 657.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 5751.67
ii 1000 x 2000 mm
*Teak wood cum 0.092 54738.00 5035.90 BMT-
E.01
Glass sqm 0.510 713.00 363.63 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 2.000 365.00 730.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 6162.53
iii 1100 x 2000 mm
*Teak wood cum 0.096 54738.00 5254.85 BMT-
E.01
Glass sqm 0.600 713.00 427.80 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 2.200 365.00 803.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 6518.65
iv 1400 x 2300 mm
*Teak wood cum 0.123 54738.00 6732.77 BMT-
E.01
Glass sqm 1.060 713.00 755.78 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 3.220 365.00 1175.30 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 8696.85
v 1500 x 2400 mm
*Teak wood cum 0.130 54738.00 7115.94 BMT-
E.01
Glass sqm 1.280 713.00 912.64 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 3.600 365.00 1314.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and all wind LS 33.00
appliances (Vide relevant standard specification)
Total for each door 9375.58
* Note : Average rate for respective size scantlings and
rough planks.
164 Furniture - Same as for Fully Panelled Doors External
BLD-CSTN-11-10
(Schedule Item No. 295)
Total for each door
165 Framed and Planked Doors (Schedule Item No. 296)
BLD-CSTN-11-11
i 1000 x 2000 mm
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
*Teak wood cum 0.107 54738.00 5856.97 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 2.000 365.00 730.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind LS 33.00
appliances and screws for planks (Vide standard
specification)
Total for each door 6619.97
ii 1200 x 2100 mm
*Teak wood cum 0.127 54738.00 6951.73 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 2.520 365.00 919.80 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind LS 33.00
appliances and screws for planks (Vide standard
specification)
Total for each door 7904.53
* Note : Average rate for respective size scantlings and
rough planks.
166 Country wood Framed and Planked Doors (Schedule
BLD-CSTN-11-12
Item No. 297)
Single Shutter :
i 1000 x 2000 mm
Country wood cum 0.107 54738.00 5856.97 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 2.000 365.00 730.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind LS 33.00
appliances and screws for planks (Vide standard
specification)
Total for each door 6619.97
ii 1200 x 2100 mm
Country wood cum 0.127 54738.00 6951.73 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 2.520 365.00 919.80 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind LS 33.00
appliances and screws for planks (Vide standard
specification)
Total for each door 7904.53
167 Furniture - 6 Butt Hings - 1 Top and 2 Bottom Tower
BLD-CSTN-11-13 Bolts and One Wrought steel safety Hasp L.S.
(Schedule Item No. 298)
Each Door
168 Ledged Braced and Planked Doors (Schedule Item
BLD-CSTN-11-14
No. 299)
Single Shutter :
i 800 x 2000 mm
*Teak wood cum 0.083 54738.00 4543.25 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 1.600 365.00 584.00 BMM-
V.07
Sundries inclusive of hold fasts and wind appliances and LS 33.00
nails for planks (Vide standard specification)
** Furniture - 3 Nos T - hinges - Vide SS for size - 2 Nos LS
Chain and slopes country make.
Total for each door 5160.25
ii 1000 x 2100 mm
*Teak wood cum 0.100 54738.00 5473.80
Labour, wrought and putup in position frame & shutters sqm 2.100 365.00 766.50
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
** Furniture - 3 Nos T - hinges - Vide SS for size - 2 Nos LS
Chain and slopes country make.
Total for each door 6273.30
Note : * Average rate for respective size scantlings and
rough planks.
** Note that for this type of door the furniture will be
supplied and fixed by the contractor.
169 * Country wood Ledged Braced and Planked Doors
BLD-CSTN-11-15
(Schedule Item No. 300)
i 800 x 2000 mm
Country wood cum 0.083 54738.00 4543.25
Labour, wrought and putup in position frame & shutters sqm 1.600 365.00 584.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Labour, wrought and putup in position frame & shutters sqm 0.720 365.00 262.80 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 2106.53
ii 800 x 1200 mm
*Teak wood cum 0.037 54738.00 2025.31 BMT-
E.01
Glass sqm 0.500 713.00 356.50 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 0.960 365.00 350.40 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 2765.21
B Double Shutter :
i 1000 x 1200 mm
*Teak wood cum 0.041 54738.00 2244.26 BMT-
E.01
Glass sqm 0.700 713.00 499.10 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.200 365.00 438.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 3214.36
ii 1200 x 1200 mm
*Teak wood cum 0.061 54738.00 3339.02 BMT-
E.01
Glass sqm 0.710 713.00 506.23 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.440 365.00 525.60 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 4403.85
iii 1500 x 1200 mm (3 Pannels)
*Teak wood cum 0.072 54738.00 3941.14 BMT-
E.01
Glass sqm 0.920 713.00 655.96 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.800 365.00 657.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 5287.10
iv 1000 x 1700 mm (2 Pannels)
*Teak wood cum 0.059 54738.00 3229.54 BMT-
E.01
Glass sqm 0.970 713.00 691.61 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.700 365.00 620.50 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 4574.65
*Note : Average rate for respective size scantlings.
172 Furniture for Double Leaf Windows Glazed With Top
BLD-CSTN-11-18
Lights (Schedule Item No. 303)
Banel Bolts 100 mm long each 2 76.00 152.00 BMT-
G.01
Top tower bolts 150 mm long each 2 112.00 224.00 BMT-
G.02
Bottom bolts 150 mm long each 2 112.00 224.00 BMT-
G.02
Parliament hinges each 4 166.00 664.00 BMT-
G.22
1264.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
173 Furniture for Double Leaf Windows Glazed without LS
BLD-CSTN-11-19
Top Lights (Schedule Item No. 304)
Top tower bolts 150 mm long each 2 112.00 224.00
Bottom bolts 150 mm long each 2 112.00 224.00
Parliament hinges each 4 166.00 664.00
Same for all such windows 1112.00
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Sundries inclusive of hold fasts and wind appliances 33.00
(Vide standard specification)
Total for each window 3492.53
**Note : Average rate for respective size scantlings and
rough planks.
176 Windows Panelled & Glazed (Schedule Item No. 307)
BLD-CSTN-11-22
A Single Shutter
600 x 1200 mm
**Teak wood cum 0.036 54738.00 1970.57 BMT-
E.01
Glass sqm 0.070 713.00 49.91 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 0.720 365.00 262.80 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 2316.28
B Double Shutter
i 900 x 1200 mm
**Teak wood cum 0.052 54738.00 2846.38 BMT-
E.01
Glass sqm 0.100 713.00 71.30 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.080 365.00 394.20 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 3344.88
ii 1200 x 1200 mm
**Teak wood cum 0.077 54738.00 4214.83 BMT-
E.01
Glass sqm 0.120 713.00 85.56 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.440 365.00 525.60 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 4858.99
C 1500 x 1200 mm (3 Pannels)
**Teak wood cum 0.094 54738.00 5145.37 BMT-
E.01
Glass sqm 0.150 713.00 106.95 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 1.800 365.00 657.00 BMM-
V.07
Sundries inclusive of putty, brads, hold fasts and wind 33.00
appliances (Vide standard specification)
Total for each window 5942.32
**Note : Average rate for respective size scantlings and
rough planks.
177 Furniture for Windows Panelled : Single Leaf with
half Shutters (Schedule Item No. 308)
Cabin hooks and eyes 200 mm long each 2 312.00 624.00 BMT-
G.59
Butt hinges 75 mm size each 4 32.00 128.00 BMT-
G.19
Top tower bolts 150 mm long each 1 112.00 112.00 BMT-
G.02
Bottom bolts 150 mm long each 1 112.00 112.00 BMT-
G.02
Same for all such windows 976.00
178 Furniture for Windows Panelled : Double Leaf with
BLD-CSTN-11-23
half Shutters (Schedule Item No. 309)
Cabin hooks and eyes 200 mm long each 4 312.00 1248.00 BMT-
G.59
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Butt hinges 75 mm size each 8 32.00 256.00 BMT-
G.19
Top tower bolts 150 mm long each 2 112.00 224.00 BMT-
G.02
Bottom bolts 150 mm long each 2 112.00 224.00 BMT-
G.02
Same for all such windows 1952.00
179 Teak Wood Windows - Ledged Braced and Planked
BLD-CSTN-11-24
(Schedule Item No. 310)
i 600 x 1200 mm (half Shutters)
*Teak wood cum 0.034 54738.00 1861.09 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 0.720 365.00 262.80 BMM-
V.07
Sundries inclusive of all furniture and fitting in LS 33.00
accordance with relevant standard specification
Total for each window 2156.89
ii 800 x 1200 mm (half Shutters)
*Teak wood cum 0.048 54738.00 2627.42 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 0.960 365.00 350.40 BMM-
V.07
Sundries inclusive of all furniture and fitting in LS 33.00
accordance with relevant standard specification
Total for each window 3010.82
iii 900 x 1200 mm (half Shutters)
*Teak wood cum 0.052 54738.00 2846.38 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 1.080 365.00 394.20 BMM-
V.07
Sundries inclusive of all furniture and fitting in LS 33.00
accordance with relevant standard specification
Total for each window 3273.58
iv 1000 x 1200 mm (half Shutters)
*Teak wood cum 0.052 54738.00 2846.38 BMT-
E.01
Labour, wrought and putup in position frame & shutters sqm 1.200 365.00 438.00 BMM-
V.07
Sundries inclusive of all furniture and fitting in LS 33.00
accordance with relevant standard specification
Total for each window 3317.38
*Note : Average rate for respective size scantlings and
rough planks.
180 Ventilators Glazed - Fixed Double Frame and with
BLD-CSTN-11-25
Wire Netting (Schedule Item No. 312)
i 800 x 500 mm
*Teak wood cum 0.012 54738.00 656.86 BMT-
E.01
Glass sqm 0.240 713.00 171.12 BMT-I.04
Wire netting sqm 0.190 12.00 2.28 BMT-
F.28
Labour, wrought and putup in position sqm 0.400 365.00 146.00 BMM-
V.07
Sundries inclusive of putty brads and iron hold fasts LS 33.00
where such are necessary say in 30 cm wall.
Total for each Ventilator 1009.26
ii 1000 x 500 mm
*Teak wood cum 0.014 54738.00 766.33 BMT-
E.01
Glass sqm 0.310 713.00 221.03 BMT-I.04
Wire netting sqm 0.240 12.00 2.88 BMT-
F.28
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Labour, wrought and putup in position sqm 0.500 365.00 182.50 BMM-
V.07
Sundries inclusive of putty brads and iron hold fasts LS 33.00
where such are necessary say in 30 cm wall.
Total for each Ventilator 1205.74
iii 1200 x 600 mm
*Teak wood cum 0.018 54738.00 985.28 BMT-
E.01
Glass sqm 0.480 713.00 342.24 BMT-I.04
Wire netting sqm 0.290 12.00 3.48 BMT-
F.28
Labour, wrought and putup in position sqm 0.720 365.00 262.80 BMM-
V.07
Sundries inclusive of putty brads and iron hold fasts LS 33.00
where such are necessary say in 30 cm wall.
Total for each Ventilator 1626.80
*Note : Average rate for respective size scantlings
181 Swing Ventilators - Glazed (Schedule Item No. 313)
BLD-CSTN-11-26
i 800 x 500 mm
*Teak wood cum 0.021 54738.00 1149.50 BMT-
E.01
Glass sqm 0.190 713.00 135.47 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 0.400 365.00 146.00 BMM-
V.07
Sundries inclusive of putty brads sash centres brass ring LS 33.00
iron cleats and window card - vide relevant standard
specifications.
Total for each Ventilator 1463.97
ii 1000 x 500 mm
*Teak wood cum 0.025 54738.00 1368.45 BMT-
E.01
Glass sqm 0.024 713.00 17.11 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 0.500 365.00 182.50 BMM-
V.07
Sundries inclusive of putty brads sash centres brass ring LS 33.00
iron cleats and window card - vide relevant standard
specifications.
Total for each Ventilator 1601.06
iii 1200 x 600 mm
*Teak wood cum 0.030 54738.00 1642.14 BMT-
E.01
Glass sqm 0.390 713.00 278.07 BMT-I.04
Labour, wrought and putup in position frame & shutters sqm 0.720 365.00 262.80 BMM-
V.07
Sundries inclusive of putty brads sash centres brass ring LS 33.00
iron cleats and window card - vide relevant standard
specifications.
Total for each Ventilator 2216.01
*Note : Average rate for respective size scantlings and
rough planks.
187 Removing white wash or colour wash by steel wire
brushing and/or scraping; sand papering and preparing
BLD-CSTN-11-32 the wall surface smooth including necessary repairs to
scratches complete
Details of cost for 10 sq.m
Labour :—
White washer / Mason 2nd Class day 0.010 260.00 2.60
Mazdoor (unskilled) day 0.170 215.00 36.55
Sundries such as sand paper and scraper etc. 33.00
Scaffolding 11.54
Add for water charges @ 1 % 0.84
Cost for 10 sq.m. 84.53
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Cost per sq.m 8.45
188 Removing white wash or colour wash by steel wire
brushing and/or scraping; sand papering and preparing
BLD-CSTN-11-33 the ceiling and/or sloping roofs surface smooth including
necessary repairs to scratches complete
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
White washer / Mason 2nd Class day 0.010 260.00 2.60
Mazdoor (unskilled) day 0.170 215.00 36.55
Sundries, such as chemical etc. 33.00
Add for water charges @ 1 % 0.72
Cost for 10 sq.m. 72.87
Cost per sq.m 7.29
BLD-CSTN-12 DISMANTLING & DEMOLITION
194 Demolishing and disposal of unserviceable materials
BLD-CSTN-12-1
within 100 metres lead
i Lime concrete.
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 1.220 215.00 262.30
Sundries 33.00
Add for water charges @ 1 % 2.95
Cost per cu m 298.25
ii Unreinforced cement concrete upto 15 cm thicknes
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
197 Dismantling doors, windows and clear storey windows,
ventilators etc.; (wood or steel) shutters including
BLD-CSTN-12-4 chowkhats, architraves, hold fasts and other attachments
etc., complete and stacking them within 100 metre lead
i
Not exceeding 3 sq.m. in area:
Details of cost per each
Labour :-
Mason, II class day 0.100 260.00 26.00
Mazdoor (male) day 0.200 215.00 43.00
Blacksmith II class day 0.050 260.00 13.00
Sundries 33.00
Add for water charges @ 1 % 1.15
Cost per each 116.15
ii Exceeding 3 sq.m. in area
Details of cost per each
Labour :-
Mason, II class day 0.130 260.00 33.80
Mazdoor (male) day 0.270 215.00 58.05
Blacksmith II class day 0.070 260.00 18.20
Sundries 33.00
Add for water charges @ 1 % 1.43
Cost per each 144.48
198 Taking out doors, windows and clearestorey window
BLD-CSTN-12-5 shutters (steel or wood) including stacking within 100
metres lead
i
Not exceeding 3 sq.m. in area:
Details of cost per each
Labour :-
Carpenter II class day 0.060 260.00 15.60
Mazdoor (male) day 0.120 215.00 25.80
Sundries 33.00
Add for water charges @ 1 % 0.74
Cost per each 75.14
ii Exceeding 3 sq.m. in area
Details of cost per each
Labour :-
Carpenter II class day 0.080 260.00 20.80
Mazdoor (male) day 0.160 215.00 34.40
Sundries 33.00
Add for water charges @ 1 % 0.88
Cost per each 89.08
BLD-CSTN-13 MISCELLANEOUS BUILDING ITEMS
204 Providing and fixing 1.80 metre long RCC fencing posts
with 6 mm bar bibs as per design in plate No. 22/2/2.
BLD-CSTN-13-6 (earth work & concrete to be paid for separately)
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Carriage of R.C.C. posts
6 mm bar bibs
Sundries
Labour for fixing posts in line
Mason, 1st Class day 0.120 285.00 34.20
Mason, 2nd Class day 0.120 260.00 31.20
Mazdoor (Male) day 0.250 215.00 53.75
Add Water charges on A @ 1% 459.81
Cost for 10 posts 46441.08
Cost per post 4644.11
Sub Analysis :
Plastering with CM 1:3, 12 mm thick 10 1.000 848.89 848.89
sqm
Deduct - CM 1:3 cum 0.025 3143.25 78.58
Add - Cement (720-480 x .125) cum 30.000 30.00 900.00 BMT-
T.02
1670.31
Annexure - 'X'
Details of quantities for RCC posts
Concrete quantity
Area of bottom A, =15+12.5/2 x 8.75+1/2 x 22/7 (6.25) =
120.31+61.38=181.69 Sq.m.
Area of top A2= 10+7.5/1 x 6.25 + 1/2 x 22 x (3.75)2/ 7=
54.69+22.10=76.79 Sq.Cm.
Av A2 = 118.12 Sq. Cm.
Volume = h/3(A, + A2 + VA,A2)
A2+A2+A, A2=0.V03766 Sq.m
Volume = 1.05/3 * 0.03766 = 0.0131810 Cu.m. =0.0132
Cu.m.
Volume of lower square portion =0.165x0.165x0.75
=0.0204 Cu.m
Total volume = 0.0336 Cu. m
Quantity for 10 posts = 0.336 Cu.m
Quantity of centring & shuttering 0.2770* 1.05=0.2908
Sq.m.
3x0.165x0.75=0.3712
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.6992 Sq.m..
For ten posts=10 x 0.6992 = 6.992 Sq.m.
Quantity of surface plaster area 12.50+7.60+7.60=27.70
Cm.
xr=3.1416x5=15.71Cm./43.41Cm 0.434 x 1.05=0.4560
Sq.m.
4x0.165x0.75=0.4950
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.9882 Sq.m. For 10 posts =
10 x 0.9882=9.88 Sq.m.
205 Supplying and fixing galvanised steel barbed wire (IS :
278-1962 Type I) weighing 9.38 Kg per 100 metres
(min.), Straining and fixing to any type of standard, rails,
straining bolts, including securing with and provision of
BLD-CSTN-13-7 galvanised mild steel wire, stapples or steel pins, etc., as
directed (Posts and struts of wood, concrete, steel, etc.)
and straining bolts shall be paid for separately).
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
For fixing & stretching wire
Blacksmith, 1st Class day 0.150 285.00 42.75
Blacksmith, 2nd Class day 0.150 260.00 39.00
Mazdoor (male). day 0.300 215.00 64.50
Sundries. 33.00
Add water charges @ 1 % 8.66
Cost for 100 metres day line of wire 874.99
Rate per m 8.75
BLD-CSTN-14 ANTE-TERMITE TREATMENT
207 Providing Antitermite treatment as per IS 6315 (Part - 2)
2001 (Pre-constructional chemical treatment measures)
along the internal & external vertical faces of the
columns, plinth beams, basement and top surface of the
basement filling below flooring bed as per the specified
procedure conforming to IS 6315 (Part-2) 2001 and other
relevant approved specification duly using Chlorpyriphos/
Lindane emulsifiable concentrate 20% with 1%
concentration @ 7.5 Liters/ sqm of the vertical surface &
@ 5.0 Liters/ sqm of the horizontal surface of the
BLD-CSTN-14-1 substructure to a depth of 500 mm around columns &
300 mm deep around plinth beams, basements & floor
filling area including excavation channel along the wall &
rodding etc & cost & conveyance of all materials to the
site, cost of labour for spraying, rodding etc complete for
finished item of work as per the approval of the
Engineer-in-Charge
Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable concentrate
of 20%
1 liter : 19 Parts water Therefore: 868.55 L /20 Lit 4.100 200.00 820.00 BMS-
W.09
Add 12%wastage Liters 0.41 98.40
Total Quantity 4.51 918.40
B) Add Water Charges @ 1% 1% 9.18
C) Labour Charges
Man Mazdoor day 3.0 215.00 645.00
Sprayer day 0.22 260.00 57.20
D) Hire charges
Sprayer, drilling machine etc 10% 162.98
sundries & contingencies 3% 48.89
Water charges & electricity 1.50% 24.45
BASIC COST per 1 sqm 1866.10
BLD-CSTN-15 CENTERING, FORM WORK etc.
208 Providing traditional centering, shuttering and scaffolding
using Cashewrina balli props and bracings supporting
wooden brackets, wooden wall plates, wooden runners
and steel plate form work as per the approved plan and
BLD-CSTN-15-1 other accessories as per the standard trade practice
including hire charges for ballies, runners, wooden
members and cost and conveyance of all other
consumable accessories, taxes etc complete for finished
item of work
UNIT 1 sqm
(I) Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 2.40 60.00 144.00 BMC-
X.05
Wall Plate Brackets / beam bottom supports Nos 1.44 170.00 244.80 BMC-
X.07
Wedge Plate fixture Nos 1.44 8.00 11.52 BMC-
X.08
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Runner beams of approximately 4" x 4" size RM 16.00 350.00 5600.00 BMC-
X.09
Steel Plate - form work plates - sqm 1.86 1200.00 2232.48 BMC-
X.10
B) LABOUR CHARGES
1st Class Carpenter day 0.16 285.00 45.60
2nd Class Carpenter day 0.28 260.00 72.80
Unskilled Mazdoor day 0.48 215.00 103.20
Consumables like Rope, Nails, de-shuttering oil 1% 84.54
Tape, cover plates 1% 84.54
Tools like Hammers etc., 1% 84.54
BASIC COST per 1 sqm 8708.03
(II) Unsupported Roof Height up to - 4.60 M (15'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 4.32 60.00 259.20 BMC-
X.05
Wall Plate Brackets / beam bottom supports Nos 1.44 170.00 244.80 BMC-
X.07
Wedge Plate fixture Nos 1.44 8.00 11.52 BMC-
X.08
Runner beams of approximately 4" x 4" size RM 16.00 350.00 5600.00 BMC-
X.09
Steel Plate - form work plates - sqm 1.86 1200.00 2232.48 BMC-
X.10
B) LABOUR CHARGES
1st Class Carpenter Nos 0.20 285.00 57.00
2nd Class Carpenter Nos 0.36 260.00 93.60
Unskilled Mazdoor Nos 0.68 215.00 146.20
Consumables like Rope, Nails, de-shuttering oil 1% 86.45
Tape, cover plates 1% 86.45
Tools like Hammers etc., 1% 86.45
BASIC COST per 1 sqm 8904.14
(III) Unsupported Roof Height up to - 7.30 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 5.76 60.00 345.60 BMC-
X.05
Wall Plate Brackets / beam bottom supports Nos 1.44 170.00 244.80 BMC-
X.07
Wedge Plate fixture Nos 1.44 8.00 11.52 BMC-
X.08
Runner beams of approximately 4" x 4" size RM 16.00 350.00 5600.00 BMC-
X.09
Steel Plate - form work plates - sqm 1.86 1200.00 2232.48 BMC-
X.10
B) LABOUR CHARGES
1st Class Carpenter Nos 0.28 285.00 79.80
2nd Class Carpenter Nos 0.52 260.00 135.20
Unskilled Mazdoor Nos 1.08 215.00 232.20
Consumables like Rope, Nails, de-shuttering oil 1% 88.82
Tape, cover plates 1% 88.82
Tools like Hammers etc., 1% 88.82
BASIC COST per 1 sqm 9148.05
209 Providing rigid Steel centering, shuttering and scaffolding
using steel pipes, adjustable Jack screw props, acro
spans, couplers, tie rods, bracings members, supporting
brackets, acro span beams and steel plate/ ply-wood
form work as per the approved shuttering designs & plan
and other accessories as per the IS Norms and stability
BLD-CSTN-15-2 calculations including hire charges for jack pipes, acro
spans, runners, wooden members and cost and
conveyance of all other consumable accessories, taxes
etc complete for finished item of work
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
UNIT 1 sqm
(I) Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class Pipes
B) LABOUR CHARGES
1st Class Carpenter day 0.22 285.00 62.70
2nd Class Carpenter day 0.38 260.00 98.80
Unskilled Mazdoor day 0.72 215.00 154.80
Supervision Charges day 0.04 59.43
Consumables like Rope, Nails, de-shuttering oil 1% 60.02
Tape, cover plates 1% 60.02
Tools like Hammers etc., 1% 60.02
BASIC COST per 1 sqm 6182.05
(II) Unsupported Roof Height up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Span Beams - 2.4 M Long (Acro Spans) - Approximtely
B) LABOUR CHARGES
1st Class Carpenter day 0.32 285.00 91.20
2nd Class Carpenter day 0.52 260.00 135.20
Unskilled Mazdoor day 1.28 215.00 275.20
Supervision Charges day 0.06 0.00
Consumables like Rope, Nails, de-shuttering oil 1% 106.39
Tape, cover plates 1% 106.39
Tools like Hammers etc., 1% 106.39
BASIC COST per 1 sqm 10957.91
Note : Cost of Centering charges with different centering
& scaffolding materials for different structures may be
calculated as per the guidelines given Below
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
RCC
UNIT STRUCT
CENTERING COST OF URE
TYPE OF STRUCTURE
AREA CENTERI UNIT
NG MEASUR
EMENT
A B C
A FOOTINGS 3.88 sqm per 1
cum
B PEDESTALS 6.17 sqm per 1
cum
C PLINTH BEAMS 9.35 sqm per 1
cum
D LINTELS 7.94 sqm per 1
cum
E CHAJJAS - SUNSHADES 1.22 sqm per 1
sqm
F COLUMNS 11.15 sqm per 1
cum
G BEAMS 9.35 sqm per 1
cum
H SLABS - Up to 150 mm thick 1.05 sqm per 1
sqm
I SLABS - above 150 mm - Up to 300 mm thick 1.09 sqm per 1
sqm
J SLABS - above 300 mm thick 1.14 sqm per 1
sqm
K WAFFLE - (GRID) SLABS (Rib Beams with Slabs) 3.85 sqm per 1
sqm
L PERGOLA SLABS (Only Rib Beams) 2.70 sqm per 1
sqm
M ARCHE BEAMS - up to 1.5 M Span 10.63 sqm per 1
cum
N ARCHE BEAMS - above 1.5 M Span 10.78 sqm per 1
cum
O DOME SLABS 17.19 sqm per 1
cum
P HELICAL STAIRCASES 1.31 sqm per 1
sqm
For calculating centering charges of RCC Structures,
using either cashewrina balli scaffolding or steel pipe
scaffolding, the respective cost may be arrived by taking
the above values.
Therefore, Centering charges for any structure:C= A x B
UNIT 1 sqm
(I) Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 2.40 60.00 144.00
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" Nos 2.70 100.00 270.00
long
B) LABOUR CHARGES
1st Class Carpenter day 0.04 285.00 11.40
2nd Class Carpenter day 0.30 260.00 78.00
Unskilled Mazdoor day 0.48 215.00 103.20
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Supervision Charges day 0.04 6.07
Consumables like Rope, Nails, de-shuttering oil 1% 6.07
Tape, cover plates 1% 6.07
Tools like Hammers etc., 1% 87.47
BASIC COST per 1 sqm - PLAN AREA 712.27
(II) Unsupported Roof Height up to - 4.60 M (15'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 4.32 60.00 259.20
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" Nos 2.70 100.00 270.00
long
B) LABOUR CHARGES
1st Class Carpenter day 0.08 285.00 22.80
2nd Class Carpenter day 0.38 260.00 98.80
Unskilled Mazdoor day 0.68 215.00 146.20
Consumables like Rope, Nails, de-shuttering oil 1% 7.97
Tape, cover plates 1% 7.97
Tools like Hammers etc., 1% 7.97
BASIC COST per 1 sqm - PLAN AREA 820.91
(III) Unsupported Roof Height up to - 7.30 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 5.76 60.00 345.60
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" Nos 2.70 100.00 270.00
long
B) LABOUR CHARGES
1st Class Carpenter day 0.12 285.00 34.20
2nd Class Carpenter day 0.54 260.00 140.40
Unskilled Mazdoor day 1.08 215.00 232.20
Consumables like Rope, Nails, de-shuttering oil 1% 10.22
Tape, cover plates 1% 10.22
Tools like Hammers etc., 1% 10.22
BASIC COST per 1 sqm - PLAN AREA 1053.07
211 Providing ACCESS SCAFFOLD using Cashewrina balli
props and bracings supporting wooden brackets,
wooden stage scaffold boards including hire charges for
BLD-CSTN-15-4 cashewrina ballies, wooden baords, scaffolds etc., and
cost and conveyance of all other consumable
accessories, taxes etc complete for finished item of work
for ELEVATION AREA
UNIT 1 sqm
(I) Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 1.74 60.00 104.40
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" Nos 0.72 100.00 72.00
long
B) LABOUR CHARGES
1st Class Carpenter day 0.07 285.00 19.95
2nd Class Carpenter day 0.11 260.00 28.60
Unskilled Mazdoor day 0.2 215.00 43.00
Consumables like Rope, Nails, de-shuttering oil 1% 2.68
Tape, cover plates 1% 2.68
Tools like Hammers etc., 1% 2.68
BASIC COST per 1 sqm - VERTICAL ELEVATION 275.99
AREA
(II) Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 1.74 60.00 104.40
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" Nos 0.38 100.00 38.00
long
B) LABOUR CHARGES
1st Class Carpenter day 0.12 285.00 34.20
2nd Class Carpenter day 0.22 260.00 57.20
Unskilled Mazdoor day 0.36 215.00 77.40
Consumables like Rope, Nails,de-shuttering oil 1% 3.11
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
Tape, cover plates 1% 3.11
Tools like Hammers etc., 1% 3.11
BASIC COST per 1 sqm - VERTICAL ELEVATION 320.54
AREA
212 Providing STAGE SCAFFOLD using Steel Scaffolding
Pipe Frames made of 40 mmd ia MS Pipes and bracings
with scaffold boards including hire charges for MS Pipe
BLD-CSTN-15-5 Frames scaffolds boards etc., and cost and conveyance
of all other consumable accessories, taxes etc complete
for finished item of work for PLAN AREA
UNIT 1 sqm
(I) Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class Pipes
UNIT 1 sqm
(I) Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 19.7496 90.00 1777.46
Amount
Index-code S.No Description Unit Quantity Rate Rs. Remarks
Rs.
1 2 3 4 5 6 7
B) LABOUR CHARGES
1st Class Carpenter day 0.07 285.00 19.95
2nd Class Carpenter day 0.11 260.00 28.60
Unskilled Mazdoor day 0.24 215.00 51.60
Consumables like Rope, Nails, de-shuttering oil 1% 18.78
Tape, cover plates 1% 18.78
Tools like Hammers etc., 1% 18.78
BASIC COST per 1 sqm - VERTICAL ELEVATION 1933.94
AREA
(II) Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 19.14 90.00 1722.38
B) LABOUR CHARGES
1st Class Carpenter day 0.12 285.00 34.20
2nd Class Carpenter day 0.22 260.00 57.20
Unskilled Mazdoor day 0.44 215.00 94.60
Consumables like Rope, Nails, de-shuttering oil 1% 19.08
Tape, cover plates 1% 19.08
Tools like Hammers etc., 1% 19.08
BASIC COST per 1 sqm - VERTICAL ELEVATION 1965.64
AREA
For Design mix concrete, allow Cement as follows (for estimate Grade Kgs
purpose only) :
M 20 350
M 25 380
M 30 400
M 35 420
M 40 430
BLD-CSTN- 23 Supply and placing of the Ready Mix (RMC) Standard Design Mix Concrete grade as per IS 4926-2003 with minimum cement content as per IS code 456-2000 using 20 mm graded metal, from standard suppliers approved by the department
2-15 including pumping, laying concrete, vibrating, curing etc. complete but excluding cots of steel and its fabrication charges, centering, shuttering for finished item of work.
Assumtion 10 m
200 mm dia CI pipes 5m long (class ‘A’)
Weight = 2 x 257 kgs = 514 kgs = 5.14 quintal
(a) LABOUR:
Plumber 1st class day 0.102 285.00 29.07
Plumber 2nd class day 0.238 260.00 61.88
Man mazdoor day 1.330 260.00 345.80
(b) Cost for 10 metres 436.75
Rate per metre = b/10 43.68
Rate for 1 kg = b/514 0.85
1 Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with
s/s ends carefully into trenches and laying them true to alignment
PHE-LCIS- and gradient including all sundries but excluding cost and
1 conveyance of pipes from source of supply (Ref to specifications.
BIS No.3114/1994)
Note : The Labour charges for cost of Lowering & Laying per 1 kg
weight shall be as per sub-analysis made for 200 mm dia CI Pipes
S/s ends.
Details of cost for 5m
i 80 mm dia pipe
Weight of 5m length = (79 +85.5 + 92)/3 = 85.5 kgs
(a) Labour charges for laying kgs 85.500 0.850 72.68
(b) Overheads & Contractors Profit 10.17
(c) Cost for 5 metres = a+b 82.85
Rate per metre = c/5 16.57
ii 100 mm dia pipe
Weight of 5m length = (100+109+117)/3 = 108.67 kgs
(a) Labour charges for laying kgs 108.670 0.850 92.37
(b) Overheads & Contractors Profit 12.93
(c) Cost for 5 metres = a+b 105.30
Rate per metre = c/5 21.06
iii 125 mm dia pipe
Weight of 5m length = (130+141+153)/3 = 141.33 kgs
(a) Labour charges for laying kgs 141.330 0.850 120.13
(b) Overheads & Contractors Profit 16.82
(c) Cost for 5 metres = a+b 136.95
Rate per metre = c/5 27.39
iv 150mm dia pipe
Weight of 5m length = (162+178+191)/3 = 177 kgs
(a) Labour charges for laying kgs 177.000 0.850 150.45
(b) Overheads & Contractors Profit 21.06
(c) Cost for 5 metres = a+b 171.51
Rate per metre = c/5 34.30
v 200 mm dia pipe
Weight of 5m length = (237+257+278)/3 = 257.33 kgs
(a) Labour charges for laying kgs 257.330 0.850 218.73
(b) Overheads & Contractors Profit 30.62
(c) Cost for 5 metres = a+b 249.35
Rate per metre = c/5 49.87
vi 250 mm dia pipe
Weight of 5m length = (319+348+376)/3 = 347.67 kgs
(a) Labour charges for laying kgs 347.670 0.850 295.52
Note : The cost of lowering and laying is taken as per sub analysis
made for S/S ends.
Details of cost for 10m
i 80 mm dia pipe
Weight of 1m length = 19.8+(2x3.7)/2.75 = 22.49 kgs
(a) Labour charges for laying kgs 22.490 0.850 19.12
(b) Overheads & Contractors Profit 2.68
Rate per metre 21.79
ii 100 mm dia pipe
Weight of 1m length = 25.4+(2x4.2)/2.75 = 28.45 kgs
(a) Labour charges for laying kgs 28.450 0.850 24.18
(b) Overheads & Contractors Profit 3.39
Rate per metre 27.57
iii 125 mm dia pipe
Weight of 1m length = 33.1+(2x5.3)/2.75 = 36.95 kgs
(a) Labour charges for laying kgs 36.950 0.850 31.41
(b) Overheads & Contractors Profit 4.40
Rate per metre 35.80
iv 150mm dia pipe
Weight of 1m length = 41.6+(2x6.7)/2.75 = 46.47 kgs
(a) Labour charges for laying kgs 46.470 0.850 39.50
(b) Overheads & Contractors Profit 5.53
Rate per metre 45.03
v 200 mm dia pipe
Weight of 1m length = 60.1+(2x9.3)/2.75 = 66.86 kgs
(a) Labour charges for laying kgs 66.860 0.850 56.83
(b) Overheads & Contractors Profit 7.96
Rate per metre 64.79
vi 250 mm dia pipe
Weight of 1m length = 81.8+(2x12)/2.75 = 90.53 kgs
(a) Labour charges for laying kgs 90.530 0.850 76.95
(b) Overheads & Contractors Profit 10.77
Rate per metre 87.72
vii 300 mm dia pipe
Weight of 1m length = 106.1+(2x14.8)/2.75 = 116.86 kgs
(a) Labour charges for laying kgs 116.860 0.850 99.33
(b) Overheads & Contractors Profit 13.91
Rate per metre 113.24
viii 350 mm dia pipe
Weight of 1m length = 133.5+(2x19)/2.75 = 147.32 kgs
(a) Labour charges for laying kgs 147.320 0.850 125.22
(b) Overheads & Contractors Profit 17.53
Rate per metre 142.75
ix 400 mm dia pipe
Weight of 1m length = 162.6+(2x23.4)/2.75 = 179.62 kgs
(a) Labour charges for laying kgs 179.620 0.850 152.68
(b) Overheads & Contractors Profit 21.37
Rate per metre 174.05
x 450mm dia pipe
Materials
Pressure guage Nos 0.050 960.00 48.00
3/4" G.I. Pipe (20 mm) RM 3.000 207.00 621.00
Specials Ls 13.00
Dummies No. 0.100 30.00 3.00 BMW-I.52
Diesel (2 Lts. / Hr) 30 Hrs. Lts. 60.000 45.00 2700.00
(T) Total Rate per 500 Mts. 8620.00
(r) Rate per 1 Rmt for 450 mm dia 17.24
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
Note : Proportionate Testing Charges may be arrived,
keeping the diametre of pipe based on this analysis, for an
varities of pipes for various Dia Pipes.
3 Jointing CI /DI pipes & fittings with s/s ends including cost of pig
lead, hemp yarn and sundries such as cost of fuel for melting
PHE-JCIS- lead, filling with water with lead up to 500m and testing to required
3 pressure complete. (Reference to specifications. BIS
No.3114/94/12288:1997)
a) Labour
Plumber 1st class day 3.000 260.00 780.00
Plumber 2 class
nd
day 6.000 260.00 1560.00
Foreman (work inspector) Non technical day 0.750 260.00 195.00
b) Material
Rubber gasket each
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 50.000 17.24 862.00
Specification including filling with water with a water lead upto 500
M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
Unit= 1 rmt
Taking out put 100 rmt
i 80 mm dia
a) Labour
Mason 1st class day 0.780 285.00 222.30
Mason 2 class
nd
day 1.800 260.00 468.00
Man mazdoor day 5.000 260.00 1300.00
Woman mazdoor(water carrier) day 1.300 215.00 279.50
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000 20.00 1000.00
c) Testing
Materials
Pressure guage Nos 0.05 960.00 48.00
3/4" G.I. Pipe Mts 3 207.00 621.00
Specials Ls 13.00
Dummies No. 0.1 30.00 3.00 BMW-I.52
Diesel (2 Lts. / Hr) 30 Hrs. Lts. 60 45.00 2700.00
(T) Total Rate per 500 Mts. 6985.00
(r) Rate per 1 Rmt for 450 mm dia 13.97
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
i 80 mm dia meter pipe
(a) Labour
Plumber 1st class day 0.180 285.00 51.30
Plumber 2nd class day 0.420 260.00 109.20
Man mazdoor day 1.600 260.00 416.00
Total
(b) Machinery for Testing of Pipelines with required pressure rm 40.000 13.97 558.80
as per relevant IS Specification including hire charges of
testing equipment, labour and transportation of water upto
500 M lead Materials needed for testing (as per Sub Analysis
11 A)
(c) Add for water charges @ 1% on Labour & Testing Charges 11.35
(c) Add for water charges @ 1% on Labour & Testing Charges 13.46
(c) Add for water charges @ 1% on Labour & Testing Charges 13.46
(c) Add for water charges @ 1% on Labour & Testing Charges 14.52
(c) Add for water charges @ 1% on Labour & Testing Charges 14.52
(c) Add for water charges @ 1% on Labour & Testing Charges 16.63
(c) Add for water charges @ 1% on Labour & Testing Charges 18.74
(c) Add for water charges @ 1% on Labour & Testing Charges 18.74
(c) Add for water charges @ 1% on Labour & Testing Charges 20.85
(c) Add for water charges @ 1% on Labour & Testing Charges 20.85
(c) Add for water charges @ 1% on Labour & Testing Charges 22.96
Total 10415.00
(b) Material
Add for Water charges at 1% on Labour & Testing Lt 104.15
(c) Overheads & Contractors Profit 1472.68
(d) Total (a+b+c) 11991.83
Rate per RM =d/500 23.98
Rate per 10 mm / 1rm
A All Classes pipes :
i 63 mm dia pipe
Weight of 1m length = (0.468+0.666+1.01)/3 =0.715 kgs
(a) Labour charges for laying, jointing & testing rm 6.300 23.98 151.10
(b) Overheads & Contractors Profit 21.15
Rate per metre a+b 172.25
ii 75 mm dia pipe
Weight of 1m length = (0.655+0.923+1.439)/3 =1.005 kgs
(a) Labour charges for laying, jointing & testing rm 7.500 23.98 179.88
(b) Overheads & Contractors Profit 25.18
Rate per metre a+b 205.06
iii 90 mm dia pipe
Weight of 1m length = (0.924+1.321+2.032)/3 =1.426 kgs
(a) Labour charges for laying, jointing & testing rm 9.000 23.98 215.85
(b) Overheads & Contractors Profit 30.22
Rate per metre a+b 246.07
iv 110 mm dia pipe
Weight of 1m length = (1.323+1.902+3.062)/3 =2.096 kgs
(a) Labour charges for laying, jointing & testing rm 11.000 23.98 263.82
(b) Overheads & Contractors Profit 36.93
Rate per metre a+b 300.76
v 125 mm dia pipe
Weight of 1m length = (1.722+2.511+3.929)/3 =2.72 kgs
(a) Labour charges for laying, jointing & testing rm 12.500 23.98 299.80
(b) Overheads & Contractors Profit 41.97
Rate per metre a+b 341.77
vi 140 mm dia pipe
Weight of 1m length = (2.144+3.116+4.905)/3 =3.388 kgs
(a) Labour charges for laying, jointing & testing rm 14.000 23.98 335.77
(b) Overheads & Contractors Profit 47.01
Rate per metre a+b 382.78
vii 160 mm dia pipe
Weight of 1m length = (2.799+4.012+6.414)/3 =4.408 kgs
(a) Labour charges for laying, jointing & testing rm 16.000 23.98 383.74
(b) Overheads & Contractors Profit 53.72
Rate per metre a+b 437.46
viii 180 mm dia pipe
Weight of 1m length = (3.581+5.134+8.092)/3 =5.602 kgs
(a) Labour charges for laying, jointing & testing rm 18.000 23.98 431.71
(b) Overheads & Contractors Profit 60.44
Rate per metre a+b 492.14
ix 200 mm dia pipe
Weight of 1m length = (4.331+6.351+10.001)/3 =6.894 kgs
(a) Labour charges for laying, jointing & testing rm 20.000 23.98 479.67
(b) Overheads & Contractors Profit 67.15
Rate per metre a+b 546.83
x 225 mm dia pipe
Weight of 1m length = (5.511+7.975+12.675)/3 =8.72 kgs
(a) Labour charges for laying, jointing & testing rm 25.000 23.98 599.59
(b) Overheads & Contractors Profit 83.94
Rate per metre a+b 683.53
xii 280 mm dia pipe
Weight of 1m length = (8.453+12.404+19.616)/3 =13.491 kgs
(a) Labour charges for laying, jointing & testing rm 28.000 23.98 671.54
(b) Overheads & Contractors Profit 94.02
Rate per metre a+b 765.56
xiii 315 mm dia pipe
Weight of 1m length = (10.682+15.723+24.732)/3 =17.046 kgs
(a) Labour charges for laying, jointing & testing rm 31.500 23.98 755.49
(b) Overheads & Contractors Profit 105.77
Rate per metre a+b 861.25
12 Laying and jointing of HDPE pipes by butt fusion welding as per
PHE- IS:7634 – part-II/1975 as amended from time to time to the
LJHE-12 alignment and gradient and testing the pipeline to the required
pressure.
(c) Material
Kerosene Lt 4.000 225.000 900.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 75.000 75.00
Overheads & Contractors Profit 2889.88
(d) Total (a+b+c) 23531.88
Rate per RM =d/456 51.61
iii 90 mm Dia
Taking output : Length - 432 m ; Joints - 36 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 5.000 260.000 1300.00
Jointing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 5.000 225.000 1125.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 98.000 98.00
Overheads & Contractors Profit 2961.00
(d) Total (a+b+c) 24111.00
Rate per RM =d/432 55.81
iv 110 mm Dia
Taking output : Length - 384 m ; Joints - 32 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 6.000 260.000 1560.00
Jointing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 6.000 225.000 1350.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 135.000 135.00
Overheads & Contractors Profit 3034.08
(d) Total (a+b+c) 24706.08
Rate per RM =d/384 64.34
(c) Material
Kerosene Lt 7.000 225.000 1575.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 242.000 242.00
Overheads & Contractors Profit 3193.26
(d) Total (a+b+c) 26002.26
Rate per RM =d/348 74.72
vi 140 mm Dia
Taking output : Length - 300 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 7.000 260.000 1820.00
Jointing
Fitter day 2.000 285.000 570.00
Mazdoor day 3.000 260.000 780.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 8.000 225.000 1800.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 245.000 245.00
Overheads & Contractors Profit 3225.18
(d) Total (a+b+c) 26262.18
Rate per RM =d/300 87.54
vii 160 mm Dia
Taking output : Length - 303 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 7.000 260.000 1820.00
Jointing
Fitter day 2.000 285.000 570.00
Mazdoor day 4.000 260.000 1040.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
(c) Material
Kerosene Lt 9.000 225.000 2025.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 341.000 341.00
Overheads & Contractors Profit 3306.52
(d) Total (a+b+c) 26924.52
Rate per RM =d/303 88.86
viii 180 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 8.000 260.000 2080.00
Jointing
Fitter day 2.000 285.000 570.00
Mazdoor day 4.000 260.000 1040.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total Labour
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 10.000 225.000 2250.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 484.000 484.00
Overheads & Contractors Profit 3394.44
(d) Total (a+b+c) 27640.44
Rate per RM =d/240 115.17
ix 200 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 10.000 260.000 2600.00
Jointing
Fitter day 2.000 285.000 570.00
Mazdoor day 6.000 260.000 1560.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 11.000 225.000 2475.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 623.000 623.00
Overheads & Contractors Profit 3591.00
(d) Total (a+b+c) 29241.00
Rate per RM =d/240 121.84
x 225 mm Dia
Taking output : Length - 216 m ; Joints -18 Nos
(a) Labour
For lowering / sub surface transport
(c) Material
Kerosene Lt 12.000 225.000 2700.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 714.000 714.00
Overheads & Contractors Profit 3635.24
(d) Total (a+b+c) 29601.24
Rate per RM =d/216 137.04
xi 250 mm Dia
Taking output : Length - 216 m ; Joints - 18 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 11.000 260.000 2860.00
Jointing
Fitter day 2.000 285.000 570.00
Mazdoor day 6.000 260.000 1560.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 13.000 225.000 2925.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 836.000 836.00
Overheads & Contractors Profit 3720.22
(d) Total (a+b+c) 30293.22
Rate per RM =d/216 140.25
xii 280 mm Dia
Taking output : Length - 192 m ; Joints - 16 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 12.000 260.000 3120.00
Jointing
Fitter day 2.000 285.000 570.00
Mazdoor day 6.000 260.000 1560.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 14.000 225.000 3150.00
(c) Material
Kerosene Lt 15.000 225.000 3375.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 1078.000 1078.00
Overheads & Contractors Profit 3853.50
(d) Total (a+b+c) 31378.50
Rate per RM =d/180 174.33
xiv 355 mm Dia
Taking output : Length - 144 m ; Joints - 12 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 14.000 260.000 3640.00
Jointing
Fitter day 2.000 285.000 570.00
Mazdoor day 8.000 260.000 2080.00
Testing
Fitter day 1.000 285.000 285.00
Mazdoor day 2.000 260.000 520.00
Supervisor day 1.000 260.000 260.00
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000 14880.000 14880.00
(c) Material
Kerosene Lt 16.000 225.000 3600.00
Diesel Lt 8.000 225.00 1800.00
Water for Testing Lt 77.00
Transport day 1.000 2252.000 2252.00
Overheads & Contractors Profit 4194.96
(d) Total (a+b+c) 34158.96
Rate per RM =d/144 237.22
13 Lowering and laying in ready made trench true to alignment and
gradient, jointing, and testing of stone ware pipes including cost of
PHE-
jointing material such as cement mortar (1:1) proportion and
LJSW-13 hemp yarn but excluding cost and conveyance of pipe. (Reference
to specifications BIS No. 6530/72)
Unit each
i 40 mm dia
(a) Labour
Lowering charges for air valve kgs 27.000 121.00 3267.00
Boring main & threding etc
Plumber 2nd class day 0.140 260.00 36.40
Man mazdoor day 0.140 260.00 36.40
Overheads & Contractors Profit 467.57
Rate per each valve 3807.37
ii 25 mm dia
(a) Labour
Lowering charges for air valve kgs 20.000 106.00 2120.00
Boring main & threding etc
Plumber 2nd class day 0.110 260.00 28.60
Man mazdoor day 0.110 260.00 28.60
Overheads & Contractors Profit 304.81
Rate per each valve 2482.01
17 Providing and fixing spindle fire hydrant with 65 mm outlet.
PHE- Complete with bolts, nuts, and rubber insertion etc. complete but
SFHD-17
excluding cost of Materials.
Details of cost for 1fire hydrants
i 65 mm dia
(a) Labour
Plumber 1st class day 0.750 285.00 213.75
Plumber 2nd class day 1.750 260.00 455.00
Man mazdoor day 4.000 260.00 1040.00
Overheads & Contractors Profit 239.23
Rate per each fire hydrant 1947.98
Note : For other sizes proportionately allow the Data.
PHE- 18 Dismantling of spindle fire hydrant including stacking of useful
DSFH-18 materials within 50m lead
Details of cost for 10 Nos
65 mm dia
(a) Labour
Fitter 1st class day 0.750 285.00 213.75
Fitter 2nd class day 1.750 260.00 455.00
Man mazdoor day 4.000 260.00 1040.00
Overheads & Contractors Profit 239.23
(b) Labour
Man mazdoor day 0.500 260.00 130.00
(c) Sundries for Coir rope, nails, @ 1% 19.78
(d) Sundries for lighting and watching etc at 1% 19.78
Overheads & Contractors Profit 282.46
Cost for 3rmt (a+b+c+d) 2300.02
Rate per each rmt = (a+b+c+d)/3 766.67
1 Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead BLD-CSTN-2
of 10m including all operational, incidental, labour charges such as shoring ,sheeting, planking,
strutting, etc. complete for finished item of work including seigniorage excluding dewatering
charges etc as per SS - 20 B (APSS 308).
Ordinary soil
Mechanical Means
Upto 3 m depth
Unit = cum
Taking output = 210 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 8.32 215.00 1788.80
b) Machinery
Hydraulic Excavator 1 cum bucket capacity hour 6.00 2009.50 12057.00
c&d) Overheads & Contractors Profit 1938.41
Cost for 240 cum = a+b+c+d 15784.21
Rate per cum = (a+b+c+d)/210 75.16
2 Hard Soil
(B) Mechanical Means
a) Labour
Mate day -
Mazdoor for dressing sides, bottom and back filling day 2.08 215.00
(Unskilled) 447.20
b) Machinery
Hydraulic Excavator 1 cum bucket capacity @ 60 cum / hour hour 0.17 2009.50
341.62
Tipper 5.5 cum capacity, 4 trips per hour hour 0.45 696.40 313.38
c) Material
Selected earth for refilling cum 5.00 72.00 360.00 M-163
d&e) Overheads & Contractors Profit 204.71
Cost for 10 cum = a+b+c+d+e 1666.90
Rate per cum = a+b+c+d+e)/10 166.69
3 Ordinary rock (not requiring blasting)
(B) Mechanical Means
Upto 3 m depth
Unit = cum
Taking output = 180 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 6.24 215.00 1341.60
b) Machinery
Hydraulic Excavator 1 cum bucket capacity hour 6.00 2009.50 12057.00
c&d) Overheads & Contractors Profit 1875.80
Cost for 180 cum = a+b+c+d 15274.40
Rate per cum = (a+b+c+d)/180 84.86
Sl. Description Unit Quantity Rate Rs. Amount Remarks
No Rs.
1 2 3 4 5 6 7
4 Filling available excavated earth (excluding rock) in sides of foundations upto plinth in layer not
exceeding 20 cms. In depth, compacting each deposited layer by ramming after watering with lead
upto 50 m. and lift upto 1.5m. Inluding cost of all labour complete as per speicifications.
Unit = cum
Taking output = 6 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.12 215.00 670.80
b&c) Overheads & Contractors Profit 93.91
Cost for 180 cum = a+b+c 764.71
Rate per cum = (a+b+c)/6 127.45
8 Providing and laying in position plain cement concrete of nominal mix M 7.5 with OPC cement
@180kgs, with 40 mm & down side graded granite coarce aggeregate @ 0.85 Cum & fine
ggeregate@ 0.57 Cum machine mixed, machine mixed, concrete laid in layer not exceeding 15
cms, thick , well compacted in foundation & plinth.including cost of all material, labour HOM
Machinary , curing complete as per specification.
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 5.50 891.00
Coarse aggregate 40 mm (including Seignorage Charges) cum 0.90 975.00
877.50
Fine aggregate (Sand) (including Seignorage Charges) cum 0.45 425.00 191.25
Water (including for curing) kl 1.20 77.00 92.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 342.50 342.50
C. LABOUR:
Mason 1st class day 0.10 285.00 28.50
Mazdoor (unskilled) day 1.39 215.00 298.85
Water Charges 1% - 0.92
b&c) Overheads & Contractors Profit 381.21
Grand Total 3104.13
9 Providing and laying in position plain cement concrete of nominal mix M 15 with OPC cement
@180kgs, with 40 mm & down side graded granite coarce aggeregate @ 0.85 Cum & fine
ggeregate@ 0.57 Cum machine mixed, machine mixed, concrete laid in layer not exceeding 15
cms, thick , well compacted in foundation & plinth.including cost of all material, labour HOM
Machinary , curing complete as per specification.
Unit : 1cum
A. MATERIALS:
Cement Kg 275.000 5.50 1512.50
Coarse aggregate 40mm cum 0.540 975.00 526.50
Coarse aggregate 20mm cum 0.270 1025.00 276.75
Coarse aggregate 10mm cum 0.090 750.00 67.50
Fine aggregate (Sand) cum 0.480 425.00 204.00
Water (including for curing) kl 1.20 77.00 92.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 342.50 342.50
C. LABOUR:
Sl. Description Unit Quantity Rate Rs. Amount Remarks
No Rs.
1 2 3 4 5 6 7
Mason 1 class
st
day 0.100 285.00 28.50
Mazdoor (unskilled) day 1.390 215.00 298.85
D&E) Overheads & Contractors Profit 468.93
Grand Total 3818.43
10 Providing and laying cement concrete by pumping using 20mm and down size granite jelly of
ready mixed concrete (RMC) for RCC works laid in 15cms thcik layers and well compacted
vibrating, curing, finishing with necessary cement mortar, with all lead and lifts etc., complete
(exclusive of cost of steel and fabrication charges)
UNIT 1 sqm
(I) Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class Pipes
for vertical props placed @ 3'0" c/c in bothways
Approximately 33'-0" x 33'-0" roof area
Span Beams - 2.4 M Long (Acro Spans) - Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates - 9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates - Appx Kgs 62.51 90.00 5626.26
B) LABOUR CHARGES
1st Class Carpenter day 0.22 285.00 62.70
2nd Class Carpenter day 0.38 260.00 98.80
Unskilled Mazdoor day 0.72 215.00 154.80
Supervision Charges day 0.04 59.43
Consumables like Rope, Nails, de-shuttering oil 1% 60.02
Tape, cover plates 1% 60.02
Tools like Hammers etc., 1% 60.02
D&E) Overheads & Contractors Profit 865.49
BASIC COST per 1 sqm 7047.54
(II) Unsupported Roof Height up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD Towers)
Span Beams - 2.4 M Long (Acro Spans) - Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates - 9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Sl. Description Unit Quantity Rate Rs. Amount Remarks
No Rs.
1 2 3 4 5 6 7
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates - Appx - kgs 112.635 90.00 10137.15
B) LABOUR CHARGES
1st Class Carpenter day 0.32 285.00 91.20
2nd Class Carpenter day 0.52 260.00 135.20
Unskilled Mazdoor day 1.28 215.00 275.20
Supervision Charges day 0.06 0.00
Consumables like Rope, Nails, de-shuttering oil 1% 106.39
Tape, cover plates 1% 106.39
Tools like Hammers etc., 1% 106.39
D&E) Overheads & Contractors Profit 1534.11
BASIC COST per 1 sqm 12492.02
210 Providing STAGE SCAFFOLD with staging using Cashewrina balli props and bracings supporting
wooden brackets, wooden stage scaffold boards including hire charges for cashewrina ballies,
wooden baords, scaffolds etc., and cost and conveyance of all other consumable accessories, taxes
etc complete for finished item of work for PLAN AREA
UNIT 1 sqm
(I) Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 2.40 60.00 144.00
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 2.70 100.00 270.00
B) LABOUR CHARGES
1st Class Carpenter day 0.04 285.00 11.40
2nd Class Carpenter day 0.30 260.00 78.00
Unskilled Mazdoor day 0.48 215.00 103.20
Consumables like Rope, Nails, de-shuttering oil 1% 6.07
Tape, cover plates 1% 6.07
Tools like Hammers etc., 1% 6.07
D&E) Overheads & Contractors Profit 87.47
BASIC COST per 1 sqm - PLAN AREA 712.27
(II) Unsupported Roof Height up to - 4.60 M (15'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 4.32 60.00 259.20
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 2.70 100.00 270.00
B) LABOUR CHARGES
1st Class Carpenter day 0.08 285.00 22.80
2nd Class Carpenter day 0.38 260.00 98.80
Unskilled Mazdoor day 0.68 215.00 146.20
Consumables like Rope, Nails, de-shuttering oil 1% 7.97
Tape, cover plates 1% 7.97
Tools like Hammers etc., 1% 7.97
D&E) Overheads & Contractors Profit 114.93
BASIC COST per 1 sqm - PLAN AREA 935.84
Sl. Description Unit Quantity Rate Rs. Amount Remarks
No Rs.
1 2 3 4 5 6 7
(III) Unsupported Roof Height up to - 7.30 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 5.76 60.00 345.60
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 2.70 100.00 270.00
B) LABOUR CHARGES
1st Class Carpenter day 0.12 285.00 34.20
2nd Class Carpenter day 0.54 260.00 140.40
Unskilled Mazdoor day 1.08 215.00 232.20
Consumables like Rope, Nails, de-shuttering oil 1% 10.22
Tape, cover plates 1% 10.22
Tools like Hammers etc., 1% 10.22
D&E) Overheads & Contractors Profit 147.43
BASIC COST per 1 sqm - PLAN AREA 1200.50
211 Providing ACCESS SCAFFOLD using Cashewrina balli props and bracings supporting wooden
brackets, wooden stage scaffold boards including hire charges for cashewrina ballies, wooden
baords, scaffolds etc., and cost and conveyance of all other consumable accessories, taxes etc
complete for finished item of work for ELEVATION AREA
UNIT 1 sqm
(I) Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 1.74 60.00 104.40
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 0.72 100.00 72.00
B) LABOUR CHARGES
1st Class Carpenter day 0.07 285.00 19.95
2nd Class Carpenter day 0.11 260.00 28.60
Unskilled Mazdoor day 0.2 215.00 43.00
Consumables like Rope, Nails, de-shuttering oil 1% 2.68
Tape, cover plates 1% 2.68
Tools like Hammers etc., 1% 2.68
38.64
BASIC COST per 1 sqm - VERTICAL ELEVATION AREA 314.63
(II) Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 1.74 60.00 104.40
Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 0.38 100.00 38.00
B) LABOUR CHARGES
1st Class Carpenter day 0.12 285.00 34.20
2nd Class Carpenter day 0.22 260.00 57.20
Unskilled Mazdoor day 0.36 215.00 77.40
Consumables like Rope, Nails,de-shuttering oil 1% 3.11
Tape, cover plates 1% 3.11
Tools like Hammers etc., 1% 3.11
44.88
BASIC COST per 1 sqm - VERTICAL ELEVATION AREA 365.41
Sl. Description Unit Quantity Rate Rs. Amount Remarks
No Rs.
1 2 3 4 5 6 7
212 Providing STAGE SCAFFOLD using Steel Scaffolding Pipe Frames made of 40 mmd ia MS Pipes and
bracings with scaffold boards including hire charges for MS Pipe Frames scaffolds boards etc., and
cost and conveyance of all other consumable accessories, taxes etc complete for finished item of
work for PLAN AREA
UNIT 1 sqm
(I) Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class Pipes
for vertical props placed @ 3'0" c/c in bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 39.26 90.00 3533.31
B) LABOUR CHARGES
1st Class Carpenter day 0.04 285.00 11.40
2nd Class Carpenter day 0.34 260.00 88.40
Unskilled Mazdoor day 0.60 215.00 129.00
Consumables like Rope, Nails, de-shuttering oil 1% 37.62
Tape, cover plates 1% 37.62
Tools like Hammers etc., 1% 37.62
542.50
BASIC COST per 1 sqm - PLAN AREA 4417.47
(II) Unsupported Roof Height up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD Towers)
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 112.635 90.00 10137.15
B) LABOUR CHARGES
1st Class Carpenter day 0.12 285.00 34.20
2nd Class Carpenter day 0.58 260.00 150.80
Unskilled Mazdoor day 1.20 215.00 258.00
Consumables like Rope, Nails, de-shuttering oil 1% 105.80
Tape, cover plates 1% 105.80
Tools like Hammers etc., 1% 105.80
1525.66
BASIC COST per 1 sqm - PLAN AREA 12423.21
213 Providing ACCESS SCAFFOLD using Steel Scaffolding Pipe Frames made of 40 mmd ia MS Pipes and
bracings with scaffold boards including hire charges for MS Pipe Frames scaffolds boards etc., and
cost and conveyance of all other consumable accessories, taxes etc complete for finished item of
work for ELEVATION AREA
UNIT 1 sqm
(I) Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
Sl. Description Unit Quantity Rate Rs. Amount Remarks
No Rs.
1 2 3 4 5 6 7
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 19.7496 90.00 1777.46
B) LABOUR CHARGES
1st Class Carpenter day 0.07 285.00 19.95
2nd Class Carpenter day 0.11 260.00 28.60
Unskilled Mazdoor day 0.24 215.00 51.60
Consumables like Rope, Nails, de-shuttering oil 1% 18.78
Tape, cover plates 1% 18.78
Tools like Hammers etc., 1% 18.78
270.75
BASIC COST per 1 sqm - VERTICAL ELEVATION AREA 2204.69
(II) Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 19.14 90.00 1722.38
B) LABOUR CHARGES
1st Class Carpenter day 0.12 285.00 34.20
2nd Class Carpenter day 0.22 260.00 57.20
Unskilled Mazdoor day 0.44 215.00 94.60
Consumables like Rope, Nails, de-shuttering oil 1% 19.08
Tape, cover plates 1% 19.08
Tools like Hammers etc., 1% 19.08
275.19
BASIC COST per 1 sqm - VERTICAL ELEVATION AREA 2240.82
19 Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending,
hooking, placing in position, lapping and / or welding wherever required, tying with binding wire
and achoring to the adjoining members wherever necessary complete as per design (laps, hooks
and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery
complete as per specifications.
Unit = tonns
(a) Material
TMT bars including 2.5 per cent for wastage t 1.025 42000.00 43050.00
Welding Electrodes @ 5 per joint (14 joints / ton) each 70.000 9.00 630.00
Welding Charges (Hire charges of Welding Machine) Hr 10.00 12.90 129.00
Binding wire kg 6.00 55.00 330.00
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
Welder day 2.50 285.00 712.50
Blacksmith day 2.00 285.00 570.00
Mazdoor (Unskilled) day 6.40 215.00 1376.00
(c&d)Overhead Charges and Contractor’s profit on (a+b+c) 467.97
30 Providing Ceramic tiles of approved make, shade and size for flooring, treads of steps and landings
laid on a bed of 12mm thick, cement mortar 1:3 mix, flush pointing with white cement using
colour pigment, including cost of materials, labour, curing, complete as per specifications. for
Ceramic Tiles of size 30x30cms.
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick sqm 10.00 374.00 3740.00
Sand for cm 1:3 base coat cum 0.12 325.00 39.00
Cement for cm 1:3 base coat kgs 57.60 5.50 316.80
Cement for slurry kgs 33.00 5.50 181.50
White cement for jointing & pointing kgs 6.00 25.00 150.00
B. LABOUR
Mason 1st class day 0.77 285.00 219.45
Mazdoor (unskiled) day 0.80 215.00 172.00
(c&d)Overhead Charges and Contractor’s profit on (a+b+c) 674.63
38 KSRB 15-3.12: Providing 20mm thick cement plaster in single coat with cement mortar 1:,6 to
stone masonry & concrete surface including rounding off corners wherever required smooth
rendering, Providing and removing scaffolding, including cost of materials, labour, curing
complete as per specifications.
39 KSRB 15-3.14: Providing 12mm thick cement plaster in single coat with cement mortar 1:4 to
ceiling inclunding & rounded off corners wherever required smooth rendering Providing &
removing scaffolding including cost of materials, labour curing complete as per specification
41 KSRB 15-5.2: Providing rough cement plastering 15mm thick in single coat with cement mortor 1:6
to brick masonry for base of dadooing works with sand of approved quality, providing and
removing scaffolding, including cost of materials, labour, curing complete as per specifications.
1 2 3 4 5 6
BUILDING ITEMS
MORTARS
1 Cement Mortar (1 : 1) Cu.m 8423.25 1179.26 9602.51
2 Cement Mortar (1 : 1.5) Cu.m 5783.25 809.66 6592.91
3 Cement Mortar (1 : 2) Cu.m 4463.25 624.86 5088.11
4 Cement Mortar (1 : 3) Cu.m 3143.25 440.06 3583.31
5 Cement Mortar (1 : 4) Cu.m 2483.25 347.66 2830.91
6 Cement Mortar (1 : 5) Cu.m 2087.25 292.22 2379.47
7 Cement Mortar (1 : 6) Cu.m 1823.25 255.26 2078.51
8 Cement Mortar (1 : 8) Cu.m 1493.25 209.06 1702.31
CONCRETE, DAMP PROOF COURSE & REINFORCEMENT
9 Plain Cement concrete Grade M20 - Nominal Mix Cu.m 4077.05 570.79 4647.84
10 Plain Cement concrete Grade M10 - Nominal Mix upto Plinth level Cu.m 2834.00 396.76 3230.76
11 PCC Grade M15 - Nominal mix 1:2.5:5 (Hand mixing) Cu.m 3090.15 432.62 3522.77
Plain Cement concrete (1:4:8) using 40 mm metal with hand mixing upto Plinth level Cu.m 2381.05 333.35 2714.40
12
Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture. All work upto plinth level. Cu.m 2540.15 355.62 2895.77
13
Plain Cement concrete (1:5:10) using 40 mm metal with hand mixing upto Plinth level Cu.m 2202.85 308.40 2511.25
14
Plain Cement concrete (1:5:10) using 40 mm metal with Concrete mixture. All work upto plinth level. Cu.m 2336.80 327.15 2663.95
15
Plain Cement concrete (1:6:10) using 40 mm metal with hand mixing upto Plinth level Cu.m 2241.10 313.75 2554.85
16
Plain Cement concrete (1:6:10) using 40 mm metal with Concrete mixture upto Plinth level Cu.m 2375.05 332.51 2707.56
17
18 Plain Cement concrete - Nominal Mix (1:3:6) Cu.m 2700.05 378.01 3078.06
Plain Cement concrete (M 20) Nominal Mix using 40mm metal using concrete mixer Cu.m 3439.00 481.46 3920.46
19
20 Plain Cement concrete (M 15) Nominal Mix 1:2.5:5 Cu.m 3272.10 458.09 3730.19
R.C.C. M-20 Nominal Mix
RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to Table 9 of IS
456 using 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work,
but excluding centering, shuttering.
Damp proof course 50mm thick with 1:2:4 cement concrete Nominal mix, using 12mm hard broken Sq.m 241.50 33.81 275.31
stone aggregate including cost of all materials, seigniorage charges, excluding conveyance charges of
materials including the cost of machinery, labour charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished item of work. (Using concrete mixer)
25
Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and M.Tonns 48509.00 6791.26 55300.26
technical specifications for Bars below 36 mm dia including over laps and wastage, where they are not
26
welded
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 71 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Supplying, fitting and placing HYSD bar reinforcement in foundation complete including wastage, as M.Tonns 49057.50 6868.05 55925.55
per drawings and technical specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for
27 Bars 36 mm dia and above, where welding required to be done compulsorily.
Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and M.Tonns 48476.00 6786.64 55262.64
technical specifications for Bars below 36 mm dia including over laps and wastage, where they are not
28
welded.
Supplying, fitting and placingTMT bar reinforcement in foundation complete including wastage, as M.Tonns 49057.50 6868.05 55925.55
per drawings and technical specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for
29 Bars 36 mm dia and above, where welding required to be done compulsorily.
Supplying, fitting and placing MS bar reinforcement in foundation complete as per drawings and M.Tonns 48476.00 6786.64 55262.64
technical specifications for Bars below 36 mm dia including over laps and wastage, where they are not
30
welded
32 Brick Masonry in CM (1:4) with Bricks traditional size 23 x 11 x 7 cms 2nd class Cu.m 2726.64 381.73 3108.37
33 Brick Masonry in CM (1:5) with Bricks traditional size 23 x 11 x 7 cms 2nd class Cu.m 2647.44 370.64 3018.08
34 Brick Masonry in CM (1:6) with 2nd class Bricks traditional size 23 x 11 x 7 cms Cu.m 2594.64 363.25 2957.89
35 Brick Masonry in CM (1:8) with Bricks traditional size 23 x 11 x 7 cms 2nd Class Cu.m 2528.64 354.01 2882.65
36 Brick Masonry in CM (1:3) with Bricks traditional size 23 x 11 x 7 cms 1st Class Cu.m 2858.64 400.21 3258.85
37 Brick Masonry in CM (1:3) with Modular Bricks 19 x 9 x 9 cms 2nd class Cu.m 3493.99 489.16 3983.15
38 Brick Masonry in CM (1:4) with Modular Bricks 19 x 9 x 9 cms 2nd class Cu.m 3356.49 469.91 3826.40
39 Brick Masonry in CM (1:5) with Modular Bricks 19 x 9 x 9 cms 2nd class Cu.m 3273.33 458.27 3731.60
40 Brick Masonry in CM (1:6) with Modular Bricks 19 x 9 x 9 cms 2nd class Cu.m 3217.89 450.50 3668.40
41 Brick Masonry in CM (1:8) with Modular Bricks 19 x 9 x 9 cms 2nd class Cu.m 3148.59 440.80 3589.39
11.5 cm wide Brick masonry for super-structure on ground floor in cm (1:3) using second class Sq.m 342.22 47.91 390.13
traditional size bricks including cost of all materials, seigniorage charges, labour and all operations for
constructing half brick masonry, mixing cement mortar, curing etc., complete for finished item of
42 work, but excluding conveyance charges of materials.
Reinforced Brick Masonary walls of 11.5cm in CM(1:6) using FlyAsh bricks having a crushing Sq.m 3428.18 479.95 3908.13
strength of not less than 35.00kg/cm2 and using two mild steel bars of 6m dia in every third layer of
brick masory, with free joints of the main block work including cost and seignorage charges and
conveyance of all materials and water from approved sources to work site and all operational,
incidental, labour charges such as scaffolding mixing mortor constructing masonary lift charges,
curing etc. complete but excluding the cost of steel and its fabrication charges for finished item of
43 work as per SS 509
Exposed brick masonry for super structure on ground floor in cm (1:6) using wire cut bricks or Cu.m 3418.40 478.58 3896.97
moulded bricks including making horizontal and vertical grooves 10mm Wide 12mm deep, cost of all
materials, seigniorage charges, labour and all operations, mixing cement mortar, curing etc., complete
44 for finished item of work, but excluding conveyance charges of materials
Brickwork in arches in cement mortar 1:4 complete including centering and shuttering excluding Cu.m 7916.85 1108.36 9025.21
pointing and plastering as per drawing and technical specifications Clauses 606 and 1205.1 MORD
45
Honey Comb work with Bricks of traditional Size and Plastered One Coat 10 mm. thick Cement Cu.m 7443.91 1042.15 8486.05
46 Mortar 1:5 including White Washing 2 Coats
Honey Comb work with Bricks of Modular Size and Plastered One Coat 10 mm. thick Cement Mortar Cu.m 8429.01 1180.06 9609.07
47 1:5 including White Washing 2 Coats
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 72 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Coursed rubble stone masonry arch (Ist sort) in cement mortar (1:4) complete including centering etc. Cu.m 7958.95 1114.25 9073.21
complete as per drawing and technical specifications Clauses 706 and 1205.1
54
55 Ashlar Arch Work in Cement Mortar (1:4) Cu.m 5476.41 766.70 6243.11
56 Rubble Arch Work in Cement Mortar (1:4) Cu.m 3659.38 512.31 4171.69
Providing & Laying reinforced cement concrete arch complete including centering and shuttering Cu.m 5841.84 817.86 6659.70
excluding reinforcement as per drawings and technical specifications Clauses 800, 900 and 1205.1
57
64 Flush Pointing with CM (1:3) to Brick / CRS Masonry Sq.m 158.61 22.20 180.81
65 Flush Pointing with CM (1:3) to RR Masonry Sq.m 158.61 22.20 180.81
66 Raised Pointing with CM (1:3) to RR Masonry Sq.m 283.72 39.72 323.44
Raised and cut pointing on coursed or Ashlar stone masonry or concrete block walling in white cement Sq.m 96.95 13.57 110.52
67 mortar 1 : 3 (1 white cement : 3 marble dust).
PLASTERING
68 Plastering with CM (1:3), 12 mm thick Sq.m 84.89 11.88 96.77
69 Plastering with CM (1:4), 12 mm thick Sq.m 74.99 10.50 85.49
70 Plastering with CM (1:5), 12 mm thick Sq.m 69.05 9.67 78.72
71 Plastering with CM (1:6), 12 mm thick Sq.m 65.09 9.11 74.20
72 Plastering with CM (1:8), 12 mm thick Sq.m 60.14 8.42 68.56
73 Plastering with CM (1:4), 15 mm thick Sq.m 83.42 11.68 95.10
74 Plastering with CM (1:4), 20 mm thick Sq.m 110.99 15.54 126.53
75 Plastering with CM (1:3), 20 mm thick Sq.m 124.85 17.48 142.33
Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:6), 16mm thick and top coat in CM Sq.m 181.00 25.34 206.34
76 (1:4), 4mm thick with Dubara sponze finishing.
Plastering with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8mm thick and top coat in CM (1:3), Sq.m 174.40 24.42 198.81
77 4mm thick with sponze finishing.
20 mm thick rough cast exterior cement plaster on walls upto height of 10 metres above ground level Sq.m 200.93 28.13 229.05
consisting of 10 mm thick backing coat of 1 : 3 cement mortar (1 cement : 3 sand) and 10 mm thick
finishing coat of 1 : 3 cement mortar (1 cement : 3 coarse aggregate of size 6 mm to 10 mm) including
arrises, chamfers and/or rounded angles not exceeding 80 mm in girth.
79
Rough cast exterior cement plaster on walls upto a height of 10 metres above ground level with a
mixture of sand and gravel or crushed stone graded from 6 mm to 10 mm nominal size dashed
over and including fresh plaster in two coats, backing coat 10 mm cement plaster 1 : 3 (1 cemen"
: 3 sand) and finishing coat 10 mm cement plaster with cement mortar 1:3 (1 cement: 3 sand)
mixed with 10% finely grounded hydrated lime by volume of cement including arrises, chamfers
and/or rounded angles not exceeding 80 mm in girth.
80 (a) Natural cement finish using ordinary cement. 232.63 32.57 265.20
81 (b) Dark coloured finish using ordinary cement and pigment 258.45 36.18 294.63
82 (c) Light coloured finish using white cement and pigment 261.06 36.55 297.61
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 73 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Pebble dash exterior plaster on walls upto a height of 10 metres above ground level with a mixture of 222.90 31.21 254.10
washed pebble or crushed stone graded from 6 mm to 12 mm nominal size dashed over and including
fresh cement plaster in two coats, backing coat 10 mm cement plaster 1 : 3 (1 cement : 3 sand) and
finishing coat 10 mm cement plaster 1 : 3 (1 cement : 3 sand) mixed with 10% finely grounded
83 hydrated lime by volume of cement including arrises, chamfers and/or rounded angles not exceeding
80 mm in girth
Masonry work in CM (1:8) prop with Flyash Cement solid blocks of size 290 x 225 x 140 mm for Cu.m 1484.23 207.79 1692.02
manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs. Gypsum of 5 kgs. and
stone dust including cost and conveyance of all materials, labour charges, seiniorage charges,
scaffolding and curing etc., cpomplete with a compresive streangth not lessthan 50 kg/sqm for walls
91 for Superstructure Walls.
FLOORING
Flooring with 25mm thick polished shabad stones set over base coat of CM (1:8) over already laid CC Sq.m 266.71 37.34 304.05
bed / RCC Roof Slab, including neat cement slurry of honey like consistency spread @ 3.3 kgs per
sqm. & Jointed with neat cement to full depth including cost of all materials like cement, sand, and
water and flooring stones etc., complete, including seigniorage charges, labour charges for dressing of
92 flooring stones etc., complete for finished item of work, but excluding the cost of conveyance of all
materials.
Flooring with 40 mm thick Rough Cuddapah/Shabad stones, set over base coat of cement mortar (1 : Sq.m 284.11 39.78 323.89
8) 12 mm thick over CC bed already laid or RCC roof slab, including pointing with cement mortar 1:3
duly filling joints nearly, including cost of all materials like flooring stone, cement, sand, and water
etc., complete, including seigniorage charges, labour charges for dressing of flooring stones etc.,
93 complete for finished item of work, but excluding the cost of conveyance of all materials.
Flooring with polished marble slab 20 mm thick set over base coat of cement mortar (1:6) 20 mm thick Sq.m 965.06 135.11 1100.16
(joints of stone must be flushed) over CC bed already laid or RCC roof slab, including near cement
slurry of honey like consistency spread @ 3.30 kgs per sqm. Jointed with neat cement to full depth
mixed with pigment of matching shade, including cost of all materials like flooring slab, cement, sand,
and water etc., complete, including seigniorage charges, labour charges for dressing, rubbing and
polishing of flooring stones etc., complete for finished item of work, but excluding the cost of
94 conveyance of all materials.
Flooring with chequrred terrazzo tiles of 22 mm thick (medium shade) set over base coat of cement Sq.m 420.77 58.91 479.68
mortar (1:6) 12 mm thick over CC bed already laid or RCC roof slab, including near cement slurry of
honey like consistency spread @ 3.3.kgs per sqm & jointed with neat cement to full depth mixed with
pigment of matching shade including cost of all materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, complete for finished item of work, but excluding the cost of
95 conveyance of all materials.
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 74 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Flooring with vitrified tiles of 1st quality, set over base coat of cement mortar (1:8), 12 mm thick over Sq.m 1242.37 173.93 1416.30
CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread
@ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete for finished item of work, but excluding the cost of
96 conveyance of all materials.
Flooring with ceramic tiles, set over base coat of cement mortar (1:8), 12 mm thick over CC bed Sq.m 657.69 92.08 749.77
already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @
3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement, sand water and tiles etc., complete,
97 including seigniorage charges, etc., complete for finished item of work, but excluding the cost of
conveyance of all materials.
Flooring with high polished granite 16 to 18 mm mm thick slabs other than black set over base coat of Sq.m 2388.60 334.40 2723.00
cement mortar (1:8), 20 mm thick over CC bed already laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste
mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand
water and tilesetc., complete, including seigniorage charges, labour charges for dressing of tilesetc.,
98 complete for finished item of work, but excluding the cost of conveyance of all materials
Flooring with marble tiles polished 8 mm thick set over base coat of cement mortar (1:8), 12 mm thick Sq.m 726.86 101.76 828.62
over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly with white cement paste mixed with pigment of matching
shade to full depth, including cost of all materials like cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete for finished item of work, but excluding the cost of
99 conveyance of all materials
Flooring with granite stone tiles 8 mm thick (mirror polished of all shades) set over base coat of Sq.m 1119.79 156.77 1276.56
cement mortar (1:6), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste
mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand
water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work,
100 but excluding the cost of conveyance of all materials.
Flooring with decorated white back ground glazed tiles, set over base coat of cement mortar (1:6), 12 Sq.m 680.97 95.34 776.31
mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste mixed with pigment
of matching shade to full depth, including cost of all materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc., complete for finished item of work, but excluding the
101 cost of conveyance of all materials
Gronolithie Concrete Flooring 20 mm thick with (1:1:2), using 6mm to 12 mm size hard granite Sq.m 186.83 26.16 212.99
machine crushed metal laid over CC bed already laid or RCC roof slab, in alternate panels of size not
exceeding 1.50 m x 1.50 m and finishing the top surface to required smoothness and slopes and thread
lining including cost of all materials like cement, metal, sand and water etc., complete, including
102 seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of
all materials
Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles 7.30 mm thick Sq.m 483.08 67.63 550.71
length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of
honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste
mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement,
sand and water etc., complete including seigniorage charges, etc., complete for finished item of work,
103 but excluding the cost of conveyance of all materials
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 75 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Providing skirting to internal walls to 15 cm height/risers of steps with marble slab……..mm Sq.m 1114.67 156.05 1270.72
thickness, length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement
slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement
paste mixed with pigment of matching shade to full depth, including cost of all materials like marble
slab, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished
104 item of work, but excluding the cost of conveyance of all materials
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to Sq.m 1736.00 243.04 1979.04
flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with
pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges, etc., complete for finished item of work, but
105 excluding the cost of conveyance of all materials
Providing skirting to internal walls to 15 cm height/risers of steps with 8 mm thick mirror polished Sq.m 1070.28 149.84 1220.12
granite tiles length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement
slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement
paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles,
cement, sand and water etc., complete including seigniorage charges, etc., complete for finished item
106 of work, but excluding the cost of conveyance of all materials
Providing skirting to internal walls to 15 cm height/risers of steps with 25 mm thick polished Sq.m 291.38 40.79 332.18
Cuddapah stone length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of matching shade to full depth, including cost of all materials like
Cuddapah stone, cement, sand and water etc., complete including seigniorage charges, etc., complete
107 for finished item of work, but excluding the cost of conveyance of all materials
Providing skirting to internal walls to 15 cm height/risers of steps with 25 mm thick polished Sq.m 285.76 40.01 325.77
Shahabad stone length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of matching shade to full depth, including cost of all materials like
Shahabad stone, cement, sand and water etc., complete including seigniorage charges, etc., complete
108 for finished item of work, but excluding the cost of conveyance of all materials
Teak Wood Flooring 40mm. Thick Tongued and Grooved Planks, including cost of all materials, Sq.m 4831.83 676.46 5508.29
109 labour etc., complete
Flooring with Gravel 150 mm thick including cost of all materials, labour, watering etc., complete Sq.m 46.64 6.53 53.17
110
Roofing with corrugated G.I sheets 1.00mm thick fixed with G.I ‘J’ bolts & nuts 8 mm dia with Sq.m 40.78 5.71 46.49
bitumen & G.I limpet washers filled with white lead & including a coat of approved steel primer and
two coats of approved paint on over lapping of sheets complete (upto a pitch of 60 0) and seigniorage
charges, turnover tax etc., complete, excluding the cost of purlins, rafters, trusses & cost of
112 conveyance of all materials
Roofing with corrugated G.I sheets 1.25mm thick fixed with G.I ‘J’ bolts & nuts 8 mm dia with Sq.m 48.56 6.80 55.36
bitumen & G.I limpet washers filled with white lead & including a coat of approved steel primer and
two coats of approved paint on over lapping of sheets complete (upto a pitch of 60 0) and seigniorage
charges, turnover tax etc., complete, excluding the cost of purlins, rafters, trusses & cost of
113 conveyance of all materials
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 76 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Roofing with 6 mm thick corrugated asbestos cement sheets, fixing with G.I ‘J’ bolts & nuts 8 mm dia Sq.m 2.07 0.29 2.36
G.I plain washers complete including seigniorage charges etc., complete for finished item of work, but
114 excluding the cost of purlins, rafters, trusses & cost of conveyance of all materials – upto 60 0 pitch.
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of Sq.m 216.01 30.24 246.25
water proof compound per bag of cement laid over roof when it is green including cost of all
materials, seigniorage charges, excluding conveyance charges of materials and including all
operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread
115 lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work
Providing & fixing insulating board ceiling of approved quality with nails etc., complete, excluding Sq.m 308.95 43.25 352.20
the cost of frame work for base and cost of conveyance of all materials
116
Providing & fixing hard board sheet ceiling of approved quality with nails etc., complete, excluding Sq.m 350.75 49.11 399.86
the cost of frame work for base and cost of conveyance of all materials
117
Providing & fixing flat pressed 3 layer medium density particle board sheet with necessary nails etc., Sq.m 350.75 49.11 399.86
complete, excluding the cost of frame work for base and cost of conveyance of all materials
118
Providing & fixing plain AC sheet ceiling of approved quality with necessary nails etc., complete, Sq.m 994.25 139.20 1133.45
excluding the cost of frame work for base and cost of conveyance of all materials
119
Providing 10 mm thick plaster of paris (Gypsum anhydrous) ceiling upto a height of 5 m above floor Sq.m 656.08 91.85 747.93
level over first class BT wood strips 25 x 6 mm with 10 mm gap in between and reinforced with rabbit
wire mesh fixed to wooden frame excluding cost of wooden frame for base & cost of conveyance of
120 all materials.
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 77 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Providing and fixing in true horizontal level 600 mm x 600 mm 15 mm thick Arm strong false ceiling Sq.m 1026.05 143.65 1169.70
system manufactured by M/s Arm strong world Industries using hot dipped Galvanised Steel section
exposed surface with pre-coated capping, main Tee of size 24 x 32 mm at every 1200 mm c/c
maximum and rotary stiched cross tee of size 24 x 27 mm at evry 600 mm c/c and sub-cross tee of size
24 mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and
the above grid is suspended at every 1200 mm c/c in both directions using 2.0 mm thick pre-
straightened GI Wire laying fine fissured butt edge ceiling tiles of 15 mm thick mineral fiber Board
manufactured by M/s Arm Strong World Industries Ltd., having RH 99% and for finished of size 600
x 600 mm including Cost &conveyance of all materials and labour charges such as cutting , fixing of
123 standing of frame work exposing roof making complete for finished item of work
White washing two coats with whiting of approved quality to give an even shade after thoroughly Sq.m 17.99 2.52 20.51
brushing the surface to remove all dirt and remains of loose powdered materials including cost of all
materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished
126 item of work, but excluding conveyance charges of materials
White washing three coats with whiting of approved quality to give an even shade after thoroughly Sq.m 24.79 3.47 28.27
brushing the surface to remove all dirt and remains of loose powdered materials including cost of all
materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished
127 item of work, but excluding conveyance charges of materials
128 Distempering, 2 Coats with Water Bound Distemper Sq.m 50.66 7.09 57.75
129 Distempering, 2 Coats with Oil Bound Distemper Sq.m 44.74 6.26 51.01
PAINTING & VARNISHING
Painting to new walls with 2 coats of water proof cement paint of apporved brand and shade over a Sq.m 576.59 80.72 657.31
base coat of approved cement primer grade I making making 3 coats in all to give an even shade after
thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including
cost and conveyance of all materials to work site and all operational, incidental, labour charges etc.
130 complete for finished item of work as per SS 912 for internal walls
131 Painting, Priming Coat on New Wood Work Sq.m 27.24 3.81 31.05
132 Painting, Priming Coat on New Iron Work Sq.m 29.55 4.14 33.69
133 Varnishing to Wood Work, One Coat Sq.m 45.40 6.36 51.76
134 Varnishing to Wood Work, Two Coats Sq.m 71.40 10.00 81.40
Painting with Ready mixed oil paint (all colours)
135 i. One Coat - New Wood Work : Sq.m 35.95 5.03 40.98
136 Two Coats - New Wood Work : Sq.m 62.20 8.71 70.91
137 One Coat - Old Wood Work & New Iron Work : Sq.m 34.95 4.89 39.84
138 Two Coats - Old Wood Work & New Iron Work: Sq.m 58.20 8.15 66.35
139 One Coat - Old Iron Work : Sq.m 31.95 4.47 36.42
140 Two Coats - Old Iron Work : Sq.m 52.35 7.33 59.68
141 Three Coats - Old Iron Work : Sq.m 76.75 10.75 87.50
142 Three Coats - New Wood Work : Sq.m 87.90 12.31 100.21
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 78 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Painting with :
i. Plastic Emulsion paint Grade I - One Coat for New Wood Work, Old Wood Work & New Iron Sq.m 32.25 4.52 36.77
143 Work :
144 Plastic Emulsion paints - One Coat for Old Iron Work : Sq.m 30.45 4.26 34.71
145 Plastic Emulsion paints - Two Coats for New Wood Work : Sq.m 53.70 7.52 61.22
146 Plastic Emulsion paints - Two Coats for Old Wood Work & New Iron Work : Sq.m 51.90 7.27 59.17
147 Plastic Emulsion paints - Two Coats for New Iron Work : Sq.m 49.05 6.87 55.92
148 Plastic Emulsion paints - Two Coats for Old Iron Work : Sq.m 47.25 6.62 53.87
149 Plastic Emulsion paints - Three Coats for New Wood Work : Sq.m 70.50 9.87 80.37
150 Plastic Emulsion paints - Three Coats for Old Iron Work : Sq.m 65.85 9.22 75.07
Painting with Synthetic Enamel paints - One Coat - for New Wood Work, Old Wood Work & New Sq.m 31.85 4.46 36.31
151 Iron Work
152 Painting with Synthetic Enamel paints - One Coat - For Old Iron Work Sq.m 31.75 4.45 36.20
153 Painting with Synthetic Enamel paints - Two Coats - for New Wood Work Sq.m 57.90 8.11 66.01
154 Painting with Synthetic Enamel paints - Two Coats - For Old Wood Work Sq.m 56.20 7.87 64.07
155 Painting with Synthetic Enamel paints - Two Coats - For New Iron Work Sq.m 53.35 7.47 60.82
156 Painting with Synthetic Enamel paints - Two Coats - For Old Iron Work Sq.m 49.95 6.99 56.94
157 Painting with Synthetic Enamel paints - Three Coats - for New Wood Work Sq.m 77.80 10.89 88.69
158 Painting with Synthetic Enamel paints - Three Coats - For Old Iron Work Sq.m 73.25 10.26 83.51
Polishing on wood work with readymade wax polish of approved brand and manufacture Sq.m 63.30 8.86 72.16
159
160 Melamine polishing on wood work (one or more coat) Sq.m 57.67 8.07 65.74
French Spirit polishing Two or more coats on new works including a coat of wood filler. Sq.m 107.51 15.05 122.56
161
Best Teak Wood wrought and put up in large scantling of over 3 metres in length (Schedule Item No Sq.m 91725.50 12841.57 104567.07
164 288)
Best Teak Wood wrought and put up for trusses including straps and all iron work (Schedule Item No Sq.m 69815.50 9774.17 79589.67
165 289)
Fully Panelled doors - External or Internal - Moulded panels (Schedule Item No 290)
Single Shutter
166 800 x 2000 mm Sq.m 4944.25 692.20 5636.45
167 900 x 2000 mm Sq.m 5263.94 736.95 6000.90
168 1100 x 2000 mm Sq.m 6505.44 910.76 7416.20
169 1200 x 2100 mm Sq.m 7345.37 1028.35 8373.73
170 900 x 2100 mm Sq.m 5613.07 785.83 6398.90
171 1500 x 2400 mm Sq.m 9564.34 1339.01 10903.35
Double Shutter
172 900 x 2000 mm Sq.m 5701.85 798.26 6500.11
173 1000 x 2000 mm Sq.m 6185.75 866.01 7051.76
174 1300 x 2200 mm Sq.m 8025.69 1123.60 9149.29
175 1400 x 2300 mm Sq.m 8820.09 1234.81 10054.90
Fully Panelled doors - Internal Five Ply - Ply-wood Panels (Schedule Item No 291)
Single Shutter
176 800 x 2000 mm Sq.m 5481.82 767.46 6249.28
177 900 x 2000 mm Sq.m 5957.09 833.99 6791.08
178 1200 x 2100 mm Sq.m 8267.52 1157.45 9424.97
179 1300 x 2200 mm Sq.m 9085.06 1271.91 10356.97
180 900 x 2100 mm Sq.m 6334.24 886.79 7221.03
181 1000 x 2100 mm Sq.m 7177.22 1004.81 8182.03
Double Shutter
182 900 x 2000 mm Sq.m 6305.29 882.74 7188.03
183 1000 x 2000 mm Sq.m 6881.28 963.38 7844.66
184 1100 x 2000 mm Sq.m 7254.20 1015.59 8269.79
185 1400 x 2300 mm Sq.m 11095.07 1553.31 12648.38
186 1500 x 2400 mm Sq.m 10494.30 1469.20 11963.50
187 Furniture - Iron - for External doors (Schedule Item 292) Sq.m 2122.00 297.08 2419.08
188 Furniture - Iron - Internal doors (Schedule Item 293) Sq.m 1335.00 186.90 1521.90
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 79 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Glazed and Panelled doors (Schedule Item No. 294)
Single Shutter
189 800 x 2000 mm Sq.m 4893.25 685.05 5578.30
190 900 x 2000 mm Sq.m 5249.37 734.91 5984.28
191 1200 x 2100 mm Sq.m 7296.91 1021.57 8318.48
192 1300 x 2200 mm Sq.m 7992.08 1118.89 9110.97
Double Shutter
193 900 x 2000 mm Sq.m 5751.67 805.23 6556.90
194 1000 x 2000 mm Sq.m 6162.53 862.75 7025.28
195 1100 x 2000 mm Sq.m 6518.65 912.61 7431.26
196 1400 x 2300 mm Sq.m 8696.85 1217.56 9914.41
197 1500 x 2400 mm Sq.m 9375.58 1312.58 10688.16
Framed and Planked Doors (Schedule Item No. 296)
198 1000 x 2000 mm Sq.m 6619.97 926.80 7546.76
199 1200 x 2100 mm Sq.m 7904.53 1106.63 9011.16
Country wood Framed and Planked Doors (Schedule Item No. 297)
Single Shutter :
200 1000 x 2000 mm Sq.m 6619.97 926.80 7546.76
201 1200 x 2100 mm Sq.m 7904.53 1106.63 9011.16
Ledged Braced and Planked Doors (Schedule Item No. 299)
Single Shutter :
202 800 x 2000 mm Sq.m 5160.25 722.44 5882.69
203 1000 x 2100 mm Sq.m 6273.30 878.26 7151.56
Country wood Ledged Braced and Planked Doors (Schedule Item No. 300)
204 800 x 2000 mm Sq.m 5160.25 722.44 5882.69
205 1000 x 2100 mm Sq.m 6273.30 878.26 7151.56
Flush type Doors with 35mm Thick Flush Shutters with Bondwood solied Block Board Type
Faced on Both the sides with Commercial Type Plywood (Schedule Item No. 301.)
Single Shutter :
206 900 x 2000 mm Sq.m 4596.36 643.49 5239.85
207 1000 x 2100 mm Sq.m 5192.63 726.97 5919.59
Windows Glazed (Schedule Item No. 302)
Single Shutter :
208 600 x 1200 mm Sq.m 2106.53 294.91 2401.45
209 800 x 1200 mm Sq.m 2765.21 387.13 3152.33
Double Shutter :
210 1000 x 1200 mm Sq.m 3214.36 450.01 3664.37
211 1200 x 1200 mm Sq.m 4403.85 616.54 5020.39
212 1500 x 1200 mm (3 Pannels) Sq.m 5287.10 740.19 6027.29
213 1000 x 1700 mm (2 Pannels) Sq.m 4574.65 640.45 5215.10
Furniture for Double Leaf Windows Glazed With Top Lights (Schedule Item No. 303) Sq.m 1264.00 176.96 1440.96
214
Furniture for Double Leaf Windows Glazed without Top Lights (Schedule Item No. 304) Sq.m 1112.00 155.68 1267.68
215
Furniture for Single Leaf Windows Glazed without Top Lights (Schedule Item No. 305) Sq.m 556.00 77.84 633.84
216
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 80 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Furniture for Windows Panelled : Single Leaf with half Shutters (Schedule Item No. 308) Sq.m 976.00 136.64 1112.64
227
Furniture for Windows Panelled : Double Leaf with half Shutters (Schedule Item No. 309) Sq.m 1952.00 273.28 2225.28
228
Teak Wood Windows - Ledged Braced and Planked (Schedule Item No. 310)
229 600 x 1200 mm (half Shutters) Sq.m 2156.89 301.96 2458.86
230 800 x 1200 mm (half Shutters) Sq.m 3010.82 421.52 3432.34
231 900 x 1200 mm (half Shutters) Sq.m 3273.58 458.30 3731.88
232 1000 x 1200 mm (half Shutters) Sq.m 3317.38 464.43 3781.81
Ventilators Glazed - Fixed Double Frame and with Wire Netting (Schedule Item No. 312)
Removing white wash or colour wash by steel wire brushing and/or scraping; sand papering and Sq.m 9.30 1.30 10.60
preparing the ceiling and/or sloping roofs surface smooth including necessary repairs to scratches
240
complete
Removing white wash or colour wash by steel wire brushing and/or scraping; sand papering and Sq.m 13.61 1.91 15.51
preparing the wall surface smooth including necessary repairs to scratches complete for the wall
241
surface spoiled by smoke soot
Removing white wash or colour wash by steel wire brushing and/or scraping; sand papering and Sq.m 10.23 1.43 11.66
preparing the ceiling and/or sloping roofs surface smooth including necessary repairs to scratches
242 complete for the ceiling surface spoiled by smoke soot
243 Washing and cleaning of decorated wall surfaces with soap, soda and water Sq.m 7.29 1.02 8.31
Washing and cleaning of the old plastered ceiling and/or sloping roofs with soap, soda and water Sq.m 8.02 1.12 9.14
244
Washing and cleaning of oil and grease spots on decorated wall surface by suitable chemical Sq.m 7.29 1.02 8.31
245
Dismantling doors, windows and clear storey windows, ventilators etc.; (wood or steel) shutters
including chowkhats, architraves, hold fasts and other attachments etc., complete and stacking
them within 100 metre lead
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 81 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Supplying and fixing galvanised steel barbed wire (IS : 278-1962 Type I) weighing 9.38 Kg per 100 Rmt's 8.75 1.22 9.97
metres (min.), Straining and fixing to any type of standard, rails, straining bolts, including securing
with and provision of galvanised mild steel wire, stapples or steel pins, etc., as directed (Posts and
struts of wood, concrete, steel, etc.) and straining bolts shall be paid for separately).
257
ANTE-TERMITE TREATMENT
Providing Antitermite treatment as per IS 6315 (Part - 2) 2001 (Pre-constructional chemical treatment Sq.m 5077.71 710.88 5788.59
measures) along the internal & external vertical faces of the columns, plinth beams, basement and top
surface of the basement filling below flooring bed as per the specified procedure conforming to IS
6315 (Part-2) 2001 and other relevant approved specification duly using Chlorpyriphos/ Lindane
emulsifiable concentrate 20% with 1% concentration @ 7.5 Liters/ sqm of the vertical surface & @ 5.0
Liters/ sqm of the horizontal surface of the substructure to a depth of 500 mm around columns & 300
mm deep around plinth beams, basements & floor filling area including excavation channel along the
wall & rodding etc & cost & conveyance of all materials to the site, cost of labour for spraying,
rodding etc complete for finished item of work as per the approval of the Engineer-in-Charge
258
259 Unsupported Roof Height up to - 3.66 M (12'0") Sq.m 8708.03 1219.12 9927.16
260 Unsupported Roof Height up to - 4.60 M (15'0") Sq.m 8904.14 1246.58 10150.72
261 Unsupported Roof Height up to - 7.30 M (24'0") Sq.m 9148.05 1280.73 10428.77
Providing rigid Steel centering, shuttering and scaffolding using steel pipes, adjustable Jack screw
props, acro spans, couplers, tie rods, bracings members, supporting brackets, acro span beams and
steel plate/ ply-wood form work as per the approved shuttering designs & plan and other accessories as
per the IS Norms and stability calculations including hire charges for jack pipes, acro spans, runners,
wooden members and cost and conveyance of all other consumable accessories, taxes etc complete for
finished item of work
262 Unsupported Roof Height up to - 3.66 M (12'0") Sq.m 6182.05 865.49 7047.54
263 Unsupported Roof Height up to - 7.32 M (24'0") Sq.m 10957.91 1534.11 12492.02
Providing STAGE SCAFFOLD with staging using Cashewrina balli props and bracings supporting
wooden brackets, wooden stage scaffold boards including hire charges for cashewrina ballies, wooden
baords, scaffolds etc., and cost and conveyance of all other consumable accessories, taxes etc complete
for finished item of work for PLAN AREA
264 Unsupported Roof Height up to - 3.66 M (12'0") Sq.m 712.27 99.72 811.99
265 Unsupported Roof Height up to - 4.60 M (15'0") Sq.m 820.91 114.93 935.84
266 Unsupported Roof Height up to - 7.30 M (24'0") Sq.m 1053.07 147.43 1200.50
Providing ACCESS SCAFFOLD using Cashewrina balli props and bracings supporting wooden
brackets, wooden stage scaffold boards including hire charges for cashewrina ballies, wooden baords,
scaffolds etc., and cost and conveyance of all other consumable accessories, taxes etc complete for
finished item of work for ELEVATION AREA
269 Unsupported Roof Height up to - 3.66 M (12'0") Sq.m 3874.98 542.50 4417.47
270 Unsupported Roof Height up to - 7.32 M (24'0") Sq.m 10897.55 1525.66 12423.21
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 82 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Providing ACCESS SCAFFOLD using Steel Scaffolding Pipe Frames made of 40 mmd ia MS Pipes
and bracings with scaffold boards including hire charges for MS Pipe Frames scaffolds boards etc.,
and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of
work for ELEVATION AREA
Supply and placing of the Design Mix Concrete corresponding to IS 456 using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges,
sales & other taxes on all materials including all operational, incidental and labour charges such
as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No. 402)with minimum cement
content as per IS code from standard suppliers approved by the department including pumping,
centering, shuttering, laying concrete, vibrating, curing etc. complete but excluding cost of steel
and its fabrication charges for finished item of work.
Supply and placing of the Ready Mix (RMC) Standard Design Mix Concrete grade as per IS
4926-2003 with minimum cement content as per IS code 456-2000 using 20 mm graded metal,
from standard suppliers approved by the department including pumping, laying concrete,
vibrating, curing etc. complete but excluding cots of steel and its fabrication charges, centering,
shuttering for finished item of work.
FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)
288 Grade M 20 Cu.m 3895.11 545.32 4440.43
289 Grade M 25 Cu.m 4060.11 568.42 4628.53
290 Grade M 30 Cu.m 4170.11 583.82 4753.93
291 Grade M 35 Cu.m 4280.11 599.22 4879.33
292 Grade M 40 Cu.m 4335.11 606.92 4942.03
COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS
293 Grade M 20 Cu.m 4631.37 648.39 5279.76
294 Grade M 25 Cu.m 4796.37 671.49 5467.86
295 Grade M 30 Cu.m 4906.3694 686.89 5593.26
296 Grade M 35 Cu.m 5016.3694 702.29 5718.66
297 Grade M 40 Cu.m 5071.3694 709.99 5781.36
RCC SLABS, BEAMS
298 Grade M 20 Cu.m 3570.86 499.92 4070.78
299 Grade M 25 Cu.m 3735.86 523.02 4258.88
300 Grade M 30 Cu.m 3845.8558 538.42 4384.28
301 Grade M 35 Cu.m 3955.8558 553.82 4509.68
302 Grade M 40 Cu.m 4010.8558 561.52 4572.38
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 83 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
RATE INCLUDING OVER HEAD CHARGES AND CONTRACTORS PROFIT
Earthwork excavation for foundation of buildings, culverts, water supply, sanitary lines and
electrical conduits either in pits or in trenches 1.5m.and above in widthi,n ordinary soil
notexceeding 1.5m.in depth including dressing the bottom and sides of pits and trenches,
stacking the excavated soil clear from edges of excavation with lead upto 50 m. after breaking of
clods complete as per specifications.
303 Ordinary soil Cu.m 65.77 -- 65.77
304 Hard Soil Cu.m 166.69 -- 166.69
305 Ordinary rock (not requiring blasting) Cu.m 84.86 -- 84.86
Cu.m 127.45 -- 127.45
306 Filling available excavated earth (excluding rock) in sides of foundations upto plinth in layer not
exceeding 20 cms. In depth, compacting each deposited layer by ramming after watering with
lead upto 50 m. and lift upto 1.5m. Inluding cost of all labour complete as per speicifications.
Sq.m 549.34 -- 549.34
307 Providing Ceramic tiles of approved make, shade and size for flooring, treads of steps and landings
laid on a bed of 12mm thick, cement mortar 1:3 mix, flush pointing with white cement using colour
pigment, including cost of materials, labour, curing, complete as per specifications. for Ceramic Tiles
of size 30x30cms.
Sq.m 129.73 -- 129.73
308 Providing 20mm thick cement plaster in single coat with cement mortar 1:,6 to stone masonry &
concrete surface including rounding off corners wherever required smooth rendering, Providing and
removing scaffolding, including cost of materials, labour, curing complete as per specifications.
Sq.m 100.16 -- 100.16
309 Providing 12mm thick cement plaster in single coat with cement mortar 1:4 to ceiling inclunding &
rounded off corners wherever required smooth rendering Providing & removing scaffolding including
cost of materials, labour curing complete as per specification
Sq.m 96.67 -- 96.67
310 Providing rough cement plastering 15mm thick in single coat with cement mortor 1:6 to brick masonry
for base of dadooing works with sand of approved quality, providing and removing scaffolding,
including cost of materials, labour, curing complete as per specifications.
Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with s/s ends carefully into trenches and
laying them true to alignment and gradient including all sundries but excluding cost and conveyance of
pipes from source of supply (Ref to specifications. BIS No.3114/1994)
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 84 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
330 125 mm dia pipe Rmt's 35.80 -- 35.80
331 150mm dia pipe Rmt's 45.03 -- 45.03
332 200 mm dia pipe Rmt's 64.79 -- 64.79
333 250 mm dia pipe Rmt's 87.72 -- 87.72
334 300 mm dia pipe Rmt's 113.24 -- 113.24
335 350 mm dia pipe Rmt's 142.75 -- 142.75
336 400 mm dia pipe Rmt's 174.05 -- 174.05
337 450mm dia pipe Rmt's 209.57 -- 209.57
338 500 mm dia pipe Rmt's 244.82 -- 244.82
339 600 mm dia pipe Rmt's 328.01 -- 328.01
340 700mm dia pipe s/s for 5m Rmt's 424.29 -- 424.29
341 750 mm dia pipe Rmt's 479.16 -- 479.16
Jointing CI /DI pipes & fittings with s/s ends including cost of pig lead, hemp yarn and sundries such
as cost of fuel for melting lead, filling with water with lead up to 500m and testing to required
pressure complete. (Reference to specifications. BIS No.3114/94/12288:1997)
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 85 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
381 300 mm dia pipe Each 630.33 -- 630.33
382 350 mm dia pipe Each 898.30 -- 898.30
383 400 mm dia pipe Each 1429.01 -- 1429.01
384 450 mm dia pipe Each 1660.42 -- 1660.42
385 500 mm dia pipe Each 1921.97 -- 1921.97
386 600 mm dia pipe Each 2675.05 -- 2675.05
387 700 mm dia pipe Each 3405.07 -- 3405.07
388 750 mm dia pipe Each 3656.52 -- 3656.52
Lowering the RCC S/S pipes carefully into the trenches laying them true to alignment and gradient,
jointing with rubber rings and testing including filling with water with a water lead upto 500 meters
including cost of rubber rings as per BIS No. 783/1985
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 86 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
427 200 mm dia pipe Rmt's 35.30 -- 35.30
428 250 mm dia pipe Rmt's 44.97 -- 44.97
429 300 mm dia pipe Rmt's 64.03 -- 64.03
430 350 mm dia pipe Rmt's 74.04 -- 74.04
431 400 mm dia pipe Rmt's 100.99 -- 100.99
432 450 mm dia pipe Rmt's 121.47 -- 121.47
433 500 mm dia pipe Rmt's 149.03 -- 149.03
434 600 mm dia pipe Rmt's 212.61 -- 212.61
Jointing A.C. pressure pipes with A.C. coupling or C.I. detachable joints complete with rubber rings
including filling with water, with a water lead up to 500m and testing to required pressure etc.,
complete but excluding cost of jointing materials and conveyance of pipe from source of supply.
Reference to specifications BIS No.6530/72 (Labour Charges Only)
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 87 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
Lowering and laying in ready made trench true to alignment and gradient, jointing, and testing of stone
ware pipes including cost of jointing material such as cement mortar (1:1) proportion and hemp yarn
but excluding cost and conveyance of pipe. (Reference to specifications BIS No. 6530/72)
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 88 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
514 225mm dia Rmt's 33.91 -- 33.91
515 300mm dia Rmt's 36.85 -- 36.85
Uprooting of old S.W. pipes including breaking of joints and bed concrete stacking of useful materials
near the site with in 50m lead and disposal of un serviceable materials in to municipal dumps
excluding the cost of earth work excavation. (Reference to specifications BIS No.)
Providing RCC spun vent shaft with cowl 140 mm and 200 mm internal and external dia respectively No's 4499.92 -- 4499.92
at top, 300 and 450 mm internal and external dia respectively at bottom and 9.10m overall length.
Bottom 1.25 m below ground level fixed in a pit 90cmx90cm x150 cm with cement concrete 1:4:8,
25cm in bed and minimum 20cm all-round with top 15cm in cement concrete 1:2:4. Junction of vent
shaft and concrete grouted with cement mortar 1:1 including making connection with sewer manhole
with 150 mm dia metre cement concrete pipe of required length complete as per standard design
545
Well Sinking
Well sinking in sandy and other loose soils under water either by manual labour, divers or dredgers
weighting the top of staining to assist sinking etc., including dewatering and other incidental charges
such as hire charges for mechanical equipment etc., complete upto 4.0 m dia (For non perennial
rivers)
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 89 of 264
Add Overhead
Sl.No Description of Item Unit Rate Charges and Total Amount
Contractor Profit
1 2 3 4 5 6
549 6.0 to 8.0 m below G.L. : Rmt's 51623.42 -- 51623.42
550 8.0 to 10.0 m below G.L. : Rmt's 58485.19 -- 58485.19
Sinking of RCC 12 m dia well in sandy soils, soft disintegrated rock, loamy and clayey soils etc; under
water by manual or mechanical means including dewatering until the completion of sinking of the well
to the required depth, the dummies of the weep holes pipes are opened for seepage of water into well,
including all hire charges complete as per SS and as directed by the departmental officers (Open well
excavation)
559 C.I Pipes and Specials (load per truck =6.50 T) Rmt's 138.17 -- 138.17
560 RCC Pipes and Collars (load per truck =7.205 T) Rmt's 124.65 -- 124.65
561 AC Pipes and Collars (load per truck = 5.40 T) Rmt's 166.31 -- 166.31
562 Stone ware pipes (load per truck = 5.40 T) Rmt's 166.31 -- 166.31
Loading or unloading materials such as C.I / D.I. Pipes, stone ware pipes, R.C.C. pipes, A.C. Pressure
pipes and specials from 300 mm to 600 mm dia upto 4 mts in length including stacking.
563 C.I. / D.I. Pipes (load per truck = 5.5 T) M.tonns 163.29 -- 163.29
564 RCC Pipes and Collars (load per truck =5.75 T) M.tonns 156.19 -- 156.19
565 AC Pipes M.tonns 209.55 -- 209.55
566 Stone ware pipes M.tonns 209.55 -- 209.55
Loading or unloading materials such as CI / DI Pipes, A.C. pressure pipes less than 300 mm dia above
4.00 M in length including stacking
567 C.I. / D.I. Pipes (load per truck = 8.46 T) M.tonns 212.55 -- 212.55
568 AC Pipes (load per truck = 3.78 T) M.tonns 236.50 -- 236.50
Loading or Unloading materials such as C.I / D.I. Pipes, A.C. Pressure pipes from 300 to 600mm dia
above 4.00 m including stacking
571 For R.C.C. Elevated Service Reservoir of Staging upto 40 Ft. below G.W.L. Sq.m 134.63 -- 134.63
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 90 of 264
TANDARD DATA ( Asper SSR 2011-12 )
STRACT SHEET
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 91 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 92 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 93 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 94 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 95 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 96 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 97 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 98 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 99 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 100 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 101 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 102 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 103 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 104 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 105 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 106 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 107 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 108 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 109 of 264
Remarks
Andhra Pradesh Standard Data Asper SSR 2011-12 Page No. 110 of 264
Standard Data - Electrical Items For Buildings
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
BLD-ELEC-1 Conduit Laying
BLD-ELEC-1 1 MS / PVC / Trunks Coduit Laying
BLD-ELEC-1-1 1.1 M.S.CONDUIT (Surface)
1.1.1 Supply and Fixing of 20mm dia 16 SWG (ISI Mark) MS Surface conduit Note for All
pipe duly threading at Joints with all required accessories fixing on T.W. Items for
Separators with chromium plated base saddles and No.18 SWG MS box Coduit Laying
for light, fan and separate plug points including cost of Cement, all
materials, accessories and all labour charges etc., complete.
Unit = 1Metre
Taking Output = 100 M
a) Material
32mm dia 16 SWG MS conduit 100 M 1.00 11340.00 11340.00 ELEC-1.1.3
T.W seperators 100 Nos 1.50 150.00 225.00 ELEC-8.1.8
38mm Screws No.8 100 Nos 1.50 86.40 129.60 ELEC-1.4.37
Rawal Plugs 100 Nos 1.50 16.00 24.00 ELEC-8.1.9
12mm Screws 100 Nos 3.00 54.00 162.00 ELEC-1.4.34
32mm Saddles MS 100 Nos 1.50 329.40 494.10 ELEC-1.1.36
32mm 1,2,3 & 4 way Junction box Dozen 0.50 674.40 337.20 ELEC-1.1.8
32mm dia HG bends Dozen 1.00 596.40 596.40 ELEC-1.1.16
Cement (As per civil SSR) kg 12.50 5.50 68.75
b) Labour charges :
Skilled Electrician day 3.00 297.00 891.00
Semi skilled Electrician day 3.00 260.00 780.00
Helpers day 3.00 260.00 780.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Sundries 33.00
C) Cost for 100 RM 15861.05
Rate per Metre = C/100 158.61
BLD-ELEC-1-2 1.2 MS Conduit Concealed
1.2.1 Supply and Fixing of 20mm dia 16 SWG (ISI Mark) MS concealed conduit,
duly threadig at Joints, on wall with required accessories including
chiselling the wall for light, Fan and separate plug point including
necessary sheet metal deep boxes, masonsary work and all labour
charges etc. complete.
1 2 3 4 5 6 7
35mm Screws 100 Nos 2.00 86.40 172.80 ELEC-1.4.37
Chromium Plated saddles with base Each 200.00 191.20 38240.00 ELEC-1.1.34
20mm 1,2,3, & 4 way Junction boxes Each 12.00 21.60 259.20 ELEC-1.1.6
20mm PVC Bends Each 12.00 4.40 52.80 ELEC-1.2.43
8" x10" Decolam Board Each 3.00 66.00 198.00 ELEC-1.4.26
Cement kg 25.00 5.50 137.50
b) Labour charges :
Skilled Electrician day 2.00 297.00 594.00
Semi skilled Electrician day 2.00 260.00 520.00
Helpers day 2.00 260.00 520.00
Sundries 33.00
C) Cost for 100 RM 42409.30
Rate per Metre = C/100 424.09
1.3.2 Supply and Fixing of 25mm dia 1.5mm thick surface P.V.C. pipe (ISI
MARK) with all accessories fixing on chromium plated metallic base
saddles including all labour charges etc., complete for run of mains.
1 2 3 4 5 6 7
1.3.5 Supply and Fixing of 50mm dia 2mm thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium plated metallic base saddles
including all labour charges etc., complete for run of mains.
1 2 3 4 5 6 7
Skilled Electrician day 2.00 297.00 594.00
Semi skilled Electrician day 2.00 260.00 520.00
Helpers day 2.00 260.00 520.00
Mason Ist class day 2.00 297.00 594.00
Sundries 33.00
C) Cost for 100 RM 5691.20
Rate per Metre = C/100 56.91
(b) Supply and Fixing of 25mm dia 1.5mm thick PVC pipe (ISI MARK)
concealed in wall with all required accessories including masonary work
and labour charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 1.5mm thick PVC pipe 100 M 1.00 2200.00 2200.00 ELEC-1.2.3
U' Links 100 Nos 2.00 40.00 80.00 ELEC-8.1.10
25mm dia 1,2,3 & 4 way deep Junction Box Each 12.00 21.60 259.20 ELEC-1.1.7
25mm PVC bends Each 12.00 5.50 66.00 ELEC-1.2.44
Cement kg 50.00 5.50 275.00
b) Labour charges :
Skilled Electrician day 2.00 297.00 594.00
Semi skilled Electrician day 2.00 260.00 520.00
Helpers day 2.00 260.00 520.00
Mason Ist class day 2.00 297.00 594.00
Sundries 33.00
C) Cost for 100 RM 5141.20
Rate per Metre = C/100 51.41
Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI MARK)
concealed in Roof Slabs with all required accessories including masonary
work and labour charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 2mm thick PVC pipe 100 M 1.00 2750.00 2750.00 ELEC-1.2.4
25mm dia 1,2,3 & 4 way deep Junction Box Each 12.00 21.60 259.20 ELEC-1.1.7
25mm PVC bends Each 12.00 5.50 66.00 ELEC-1.2.44
b) Labour charges :
Skilled Electrician day 2.00 297.00 594.00
Semi skilled Electrician day 2.00 260.00 520.00
Helpers day 2.00 260.00 520.00
Sundries 33.00
C) Cost for 100 RM 4742.20
Rate per Metre = C/100 47.42
Note : 1. If 25mm dia PVC / MS pipes are used for light / fan point, add
the cost of sheet metal / well seasoned wooden board / box.
1 2 3 4 5 6 7
C) Cost for 100 RM 3860.00
Rate per Metre = C/100 38.60
1.5.3 Supply and Laying of P.V.C casing and caping (ISI MARK) with double
locking arrangments with groover trunking of size not below 12.5mm
height 31/32mm size with all accessories, duly sealed at points and
erected on Wall / Ceiling including cost of all materials and labour charges
complete.
1 2 3 4 5 6 7
2.1.3 Wiring with 2 of 14/0.3mm (1.0 Sq.mm) P.V.C. insulated F.R. flexible
copper cable (ISI MARK) in existing pipe with 6A switch control and 3/2
pin sockets fixing on separate board including all labour charges etc.,
complete.
Taking Output = 15 Points
a) Material
14/0.3mm PVC FR flexible copper wire 100 M 1.00 1001.00 1001.00 ELEC-1.5.1
6A switches @16/each each 15.00 16.00 240.00
6A 3 pin / 2 Pin Socket each 15.00 27.00 405.00 ELEC-1.7.4
b) Labour charges :
Skilled Electrician day 1.50 297.00 445.50
Semi skilled Electrician day 1.50 260.00 390.00
Helpers day 1.50 260.00 390.00
C) Cost for 15 Points 2871.50
Rate per Points = C/15 191.43
2.1.4 Supply and fixing of 6A 3 pin wall plug socket with 6A switch control on a
common switch board with earth continuity including wire leads, earth
connections along with all labour charges etc., complete.
2.1.5 Supply and fixing of 16A 3pin / 6A 3pin plug socket with indicator lamp
and 16Amps fuse unit and 16 Amps switch control (5 in one) on decolam
sheet covered board including earth connection and all labour charges
etc., complete on wall.
Taking Output = each
a) Material
20 x 15 cms (8" x6") Decolam sheet covered board each 1.00 39.60 39.60 ELEC-1.4.25
16A 3 pin / 6A 3pin Plug socket with indicator lamp, fuse unit (5 in 1) each 1.00 146.00 146.00 ELEC-1.7.11
b) Labour charges :
Skilled Electrician day 0.10 297.00 29.70
Helpers day 0.10 260.00 26.00
Rate per each 241.30
Note : Labour Charges proposed for 1point considering 10 per day
2.1.6 Supply and Fixing of 16A 3pin and 6A 3pin plug socket with indicator lamp
and 16A fuse unit and 16A switch control (5 in 1) duly recessed in wall
with wooden deep box of 6" x8" x2 1/2" size covered with hylam sheet
including earth connections and all labour charges etc., complete.
1 2 3 4 5 6 7
2.1.8 Supply and fixing of batten holder / angle holder on existing block, but
without bulb including all connections etc., complete (For replacement).
1 2 3 4 5 6 7
Skilled Electrician day 0.06 260.00 16.12
Helpers day 0.06 260.00 16.12
Rate per each 157.34
NOTE : Labour Charges proposed for 16 jobs per day
2.1.14 Supply and fixing of Electronic musical bell on 150 x 200 mm (6"x8")
decolam block including giving connections cost of all accessories and all
labour charges etc., complete.
Taking Output = each
a) Material
Electronic Musical bell Nos 1.00 240.00 240.00 ELEC-1.7.25
150 x 200 mm (6"x8") Decolam block Nos 1.00 39.60 39.60 ELEC-1.4.25
b) Labour charges :
Skilled Electrician day 0.06 260.00 16.12
Helpers day 0.06 260.00 16.12
Rate per each 311.84
NOTE : Labour Charges proposed for 16 jobs per day
BLD-ELEC-3 3 RUN OF MAINS
BLD-ELEC-3-1 3.1 Wiring with F.R P.V.C. insulated flexible copper cable
3.1.1 Supply and run of 2 of 14/0.3mm (1.0 Sq.mm) F.R P.V.C. insulated
flexible copper cable in existing pipe for mains inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire 100 M 2.00 1001.00 2002.00 ELEC-1.5.1
b) Labour charges :
Skilled Electrician day 0.67 297.00 198.99
Semi Skilled Electrician day 2.00 260.00 520.00
Helpers day 0.67 260.00 174.20
Sundries 33.00
C) Cost for 100 RM 2928.19
Rate per Metre = C/100 29.28
Note : Labour Charges considered for 150 M / day
3.1.2 Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C. insulated
flexible copper cable in existing pipe for earth continuity including all
labour charges etc., complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire 100 M 1.00 1001.00 1001.00 ELEC-1.5.1
b) Labour charges :
Skilled Electrician day 0.34 297.00 100.98
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 0.34 260.00 88.40
Sundries 33.00
C) Cost for 100 RM 1483.38
Rate per Metre = C/100 14.83
Note : Labour Charges considered for 150 M / day
3.1.3 Supply and run of 2 of 22/0.3mm (1.5 Sq.mm) F.R P.V.C. insulated
flexible copper cable in existing pipe for mains inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
22/0.3mm FR PVC copper wire 100 M 2.00 1480.60 2961.20 ELEC-1.5.2
b) Labour charges :
Skilled Electrician day 0.67 297.00 198.99
Semi Skilled Electrician day 2.00 260.00 520.00
Helpers day 0.67 260.00 174.20
Sundries 33.00
C) Cost for 100 RM 3887.39
Rate per Metre = C/100 38.87
Note : Labour Charges considered for 150 M / day
3.1.4 Supply and run of 2 of 36/0.3mm (2.5 Sq.mm) F.R P.V.C. insulated
flexible copper cable in existing pipe for mains inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper wire 100 M 2.00 2389.20 4778.40 ELEC-1.5.3
b) Labour charges :
Skilled Electrician day 0.67 297.00 198.99
Semi Skilled Electrician day 2.00 260.00 520.00
Helpers day 0.67 260.00 174.20
Sundries 33.00
C) Cost for 100 RM 5704.59
Rate per Metre = C/100 57.05
Note : Labour Charges considered for 150 M / day
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
3.1.4 Supply and run of 1 of 36/0.3mm (2.5 Sq.mm) F.R P.V.C. insulated
(a) flexible copper cable in existing pipe for earth continuity inlcuding all
labour charges etc., complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper wire 100 M 1.00 2389.20 2389.20 ELEC-1.5.3
b) Labour charges :
Skilled Electrician day 0.34 297.00 100.98
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 0.34 260.00 88.40
Sundries 33.00
C) Cost for 100 RM 2871.58
Rate per Metre = C/100 28.72
Note : Labour Charges considered for 150 M / day
3.1.5 Supply and run of 2 of 56/0.3mm (4 Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
56 /0.3mm (4 sqmm)FR PVC flexible copper wire. 100 M 2.00 3478.20 6956.40 ELEC-1.5.4
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 3.00 260.00 780.00
Helpers day 1.00 260.00 260.00
Sundries 33.00
C) Cost for 100 RM 8326.40
Rate per Metre = C/100 83.26
Note : Labour Charges considered for 100 M / day
3.1.6 Supply and run of 2 of 84/0.3mm (6.0 Sq.mm) FR P.V.C. insulated
flexible copper cable in existing pipe for mains inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
84 /0.3mm (6 Sq.mm) FR PVC flexible copper wire. 100 M 2.00 5291.00 10582.00 ELEC-1.5.5
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 3.00 260.00 780.00
Helpers day 1.00 260.00 260.00
Sundries 33.00
C) Cost for 100 RM 11952.00
Rate per Metre = C/100 119.52
Note : Labour Charges considered for 100 M / day
3.3.7 Supply and run of 2 of 140 /0.3mm (10 Sq.mm) F.R PVC insulated flexible
copper cable in existing pipe for mains including all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
140/0.3 (10 Sq.mm) FR PVC flexible copper wire 100 M 2.00 8223.60 16447.20 ELEC-1.5.6
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 3.00 260.00 780.00
Helpers day 1.00 260.00 260.00
Sundries 33.00
C) Cost for 100 RM 17817.20
Rate per Metre = C/100 178.17
Note : Labour Charges considered for 100 M / day
3.3.8 Supply and run of 2 of 126 /0.4mm (16 Sq.mm) F.R PVC insulated flexible
copper cable in existing pipe for mains including all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
126/0.4mm (16 Sq.mm) FR PVC flexible copper wire 100 M 2.00 13145.00 26290.00 ELEC-1.5.6
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 3.00 260.00 780.00
Helpers day 1.00 260.00 260.00
Sundries 33.00
C) Cost for 100 RM 27660.00
Rate per Metre = C/100 276.60
Note : Labour Charges considered for 100 M / day
BLD-ELEC-4 4 SWITCH GEAR & MCB DISTRIBUTION BOARDS.
4.1 Panel Mounting Cubical type SDF
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
4.1.1 Supply and erection of Panel mounting cubical type 30 / 32A TPN 415V,
50 Hz. switch disconnector fuse unit complete with front drive mechanism
with door inter lock, padlocking arrangement etc., complete with fuse links
on existing control panel.
Taking Output = each
a) Material
30 / 32A TPN 415V, 50 Hz. switchs Disconnector fuse unit with HRC each 1.00 49.50 49.50 ELEC-2.5.1
fuses.
b) Labour charges :
Skilled Electrician day 0.17 297.00 49.60
Semi Skilled Electrician day 0.17 260.00 43.42
Helpers day 0.33 260.00 86.58
Sundries such as hardware etc., LS 33.00
Rate per each 262.10
Note : Labour Charges considered for 6 jobs / day
4.1.2 Supply and erection of Panel mounting cubical type 60 / 63A TPN 415V,
50 Hz. switch disconnector fuse unit complete with front drive mechanism
with door inter lock, padlocking arrangement etc., complete with fuse links
on existing control panel.
Taking Output = each
a) Material
60 / 63A TPN 415V, 50 Hz. switchs Disconnector fuse unit with HRC each 1.00 77.00 77.00 ELEC-2.5.2
fuses.
b) Labour charges :
Skilled Electrician day 0.17 297.00 49.60
Semi Skilled Electrician day 0.17 260.00 43.42
Helpers day 0.33 260.00 86.58
Sundries such as hardware etc., LS 33.00
Rate per each 289.60
Note : Labour Charges considered for 6 jobs / day
4.1.3 Supply and erection of Panel mounting cubical type 125A TPN 415V, 50
Hz. switch disconnector fuse unit complete with front drive mechanism
with door inter lock, padlocking arrangement etc., complete with fuse links
on existing control panel.
Taking Output = each
a) Material
125A TPN 415V, 50 Hz. switchs Disconnector fuse unit with HRC fuses. each 1.00 247.50 247.50 ELEC-2.5.3
b) Labour charges :
Skilled Electrician day 0.17 297.00 49.60
Semi Skilled Electrician day 0.17 260.00 43.42
Helpers day 0.33 260.00 86.58
Sundries such as hardware etc., LS 33.00
Rate per each 460.10
Note : Labour Charges considered for 6 jobs / day
4.1.4 Supply and erection of Panel mounting cubical type 200A TPN 415V, 50
Hz. switch disconnector fuse unit complete with front drive mechanism
with door inter lock, padlocking arrangement etc., complete with fuse links
on existing control panel.
Taking Output = each
a) Material
200A TPN 415V, 50 Hz. switchs Disconnector fuse unit with HRC fuses. each 1.00 247.50 247.50 ELEC-2.5.3
b) Labour charges :
Skilled Electrician day 0.20 297.00 59.40
Semi Skilled Electrician day 0.40 260.00 104.00
Helpers day 0.40 260.00 104.00
Sundries such as hardware etc., LS 33.00
Rate per each 547.90
Note : Labour Charges considered for 5 jobs / day
4.1.5 Supply and erection of Panel mounting cubical type 250A TPN 415V, 50
Hz. switch disconnector fuse unit complete with front drive mechanism
with door inter lock, padlocking arrangement etc., complete with fuse links
on existing control panel.
Taking Output = each
a) Material
250A TPN 415V, 50 Hz. switchs Disconnector fuse unit with HRC fuses. each 1.00 363.00 363.00 ELEC-2.5.4
b) Labour charges :
Skilled Electrician day 0.20 297.00 59.40
Semi Skilled Electrician day 0.40 260.00 104.00
Helpers day 0.40 260.00 104.00
Sundries such as hardware etc., LS 33.00
Rate per each 663.40
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Note : Labour Charges considered for 5 jobs / day
4.1.6 Supply and erection of Panel mounting cubical type 400A TPN 415V, 50
Hz. switch disconnector fuse unit complete with front drive mechanism
with door inter lock, padlocking arrangement etc., complete with fuse links
on existing control panel.
Taking Output = each
a) Material
400A TPN 415V, 50 Hz. switchs Disconnector fuse unit with HRC fuses. each 1.00 704.00 704.00 ELEC-2.5.5
b) Labour charges :
Skilled Electrician day 0.25 297.00 74.25
Semi Skilled Electrician day 0.50 260.00 130.00
Helpers day 0.50 260.00 130.00
Sundries such as hardware etc., LS 33.00
Rate per each 1071.25
Note : Labour Charges considered for 4 jobs / day
4.1.7 Supply and erection of Panel mounting cubical type 630A TPN 415V, 50
Hz. switch disconnector fuse unit complete with front drive mechanism
with door inter lock, padlocking arrangement etc., complete with fuse links
on existing control panel.
Taking Output = each
a) Material
630A TPN 415V, 50 Hz. switchs Disconnector fuse unit with HRC fuses. each 1.00 1424.50 1424.50 ELEC-2.5.6
b) Labour charges :
Skilled Electrician day 0.25 297.00 74.25
Semi Skilled Electrician day 0.50 260.00 130.00
Helpers day 0.50 260.00 130.00
Sundries such as hardware etc., LS 33.00
Rate per each 1791.75
Note : Labour Charges considered for 4 jobs / day
4.2 Panel Mounting Cubical type, 4pole onload change over switch
BLD-ELEC-4-2
confirming to IS 13947-3-1993.
4.2.1 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 60 / 63A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
60 / 63A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 4134.90 4134.90 ELEC-2.2.1
b) Labour charges :
Skilled Electrician day 0.17 297.00 49.60
Semi Skilled Electrician day 0.17 260.00 43.42
Helpers day 0.33 260.00 86.58
Sundries such as hardware etc., LS 33.00
Rate per each 4347.50
Note : Labour Charges considered for 6 jobs / day
4.2.2 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 125A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
125A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 7827.80 7827.80 ELEC-2.2.2
b) Labour charges :
Skilled Electrician day 0.17 297.00 49.60
Semi Skilled Electrician day 0.17 260.00 43.42
Helpers day 0.33 260.00 86.58
Sundries such as hardware etc., LS 33.00
Rate per each 8040.40
Note : Labour Charges considered for 6 jobs / day
4.2.3 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 200A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
200A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 10473.80 10473.80 ELEC-2.2.2
b) Labour charges :
Skilled Electrician day 0.20 297.00 59.40
Semi Skilled Electrician day 0.40 260.00 104.00
Helpers day 0.40 260.00 104.00
Sundries such as hardware etc., LS 33.00
Rate per each 10774.20
Note : Labour Charges considered for 5 jobs / day
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
4.2.4 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 250A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
250A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 14883.80 14883.80 ELEC-2.2.4
b) Labour charges :
Skilled Electrician day 0.20 297.00 59.40
Semi Skilled Electrician day 0.40 260.00 104.00
Helpers day 0.40 260.00 104.00
Sundries such as hardware etc., LS 33.00
Rate per each 15184.20
Note : Labour Charges considered for 5 jobs / day
4.2.5 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 400A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
400A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 22711.50 22711.50 ELEC-2.2.5
b) Labour charges :
Skilled Electrician day 0.25 297.00 74.25
Semi Skilled Electrician day 0.50 260.00 130.00
Helpers day 0.50 260.00 130.00
Sundries such as hardware etc., LS 33.00
Rate per each 23078.75
Note : Labour Charges considered for 4 jobs / day
4.2.6 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 630A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
630A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 27011.30 27011.30 ELEC-2.2.6
b) Labour charges :
Skilled Electrician day 0.25 297.00 74.25
Semi Skilled Electrician day 0.50 260.00 130.00
Helpers day 0.50 260.00 130.00
Sundries such as hardware etc., LS 33.00
Rate per each 27378.55
Note : Labour Charges considered for 4 jobs / day
4.2.7 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 800A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
800A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 39138.80 39138.80 ELEC-2.2.7
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Sundries such as hardware etc., LS 33.00
Rate per each 39988.80
4.2.8 Supply and erection of Panel mounting cubical type L.T heavy duty ON
LOAD change over switch of 1060A, 4 pole, 415V, 50 Hz. with all
accessories etc., complete on existing control panel.
Taking Output = each
a) Material
1060A, 4 Pole, 415V, 50 Hz. On load cubical type C.O.S each 1.00 64496.30 64496.30 ELEC-2.2.8
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Sundries such as hardware etc., LS 33.00
Rate per each 65346.30
BLD-ELEC-4-3 4.3 Panel Mounting Moulded Case Circute Breakers (MCCBs)
4.3.1 Supply and erection of Panel mounting 60 / 63A, 3 Pole, 10 /16kA, MCCB
with thermal magnetic setting / Microprocessor based release
arrangement with all connections etc., complete on existing panel.
1 2 3 4 5 6 7
Helpers day 0.33
Sundries such as hardware etc., LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
4.3.2 Supply and erection of Panel mounting 60 / 63A, 4 Pole, 10 / 16kA, MCCB
with thermal magnetic setting / Microprocessor based release
arrangement with all connections etc., complete on existing panel.
1 2 3 4 5 6 7
BLD-ELEC-4-4 4.4 DISTRIBUTION BOARDS
4.4.1 Supply and fixing SPN Distribution board with IP-20 protection suitable for
single phase Earth Leakage Circute Braker (ELCB) / Residual Current
Circute Braker (RCCB) / Double Pole (DP) Isolator as incomer and 10kA
SP MCBs as out going including internal connections and labour charges
for surface / flush mounting etc., complete.
1 2 3 4 5 6 7
Taking Output = each
a) Material
SPN 8 way D.B with IP-42 Protection (MD) suitable for single phase each 1.00 1225.80 1225.80 ELEC-2.12.7
ECCB / RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB each 1.00 366.20 366.20 ELEC-2.10.2
10 kA - 6-32A range SP MCBs each 6.00 200.60 1203.60 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 0.50 297.00 148.50
Semi Skilled Electrician day 0.50 260.00 130.00
Helpers day 1.00 260.00 260.00
Sundries such as hardware, cement etc, LS 33.00
Rate per each 3367.10
Note : Labour Charges considered for 2 jobs / day
C 40A DP Isolator/ RCCB / ELCB - 1 No for incomer, 6-32A SP MCBs -
8 Nos for outgoing.
Taking Output = each
a) Material
SPN 12 way D.B with IP-42 Protection (MD) suitable for single phase each 1.00 1477.40 1477.40 ELEC-2.12.8
ECCB / RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB each 1.00 366.20 366.20 ELEC-2.10.2
10 kA - 6-32A range SP MCBs each 8.00 200.60 1604.80 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 0.50 297.00 148.50
Semi Skilled Electrician day 0.50 260.00 130.00
Helpers day 1.00 260.00 260.00
Sundries such as hardware, cement etc, LS 33.00
Rate per each 4019.90
Note : Labour Charges considered for 2 jobs / day
4.4.3 Supply and fixing TPN Distribution board with IP-20 protection suitable for
3 phase ELCB / RCCB / FP Isolator as incomer and 10kA SP MCBs as
outing going including internal connection and labour charges for surface /
flush mounting etc., complete.
A 40A FP Isolator/ RCCB / ELCB - 1 No for incomer, 10kA-6-32A SP
MCBs - 12Nos for outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection suitable for 3 phase ELCB / RCCB/ each 1.00 1398.60 1398.60 ELEC-2.12.21
FP Isolator as incommer.
40A, 4 Pole Isolator / ELCB / RCCB each 1.00 366.20 366.20 ELEC-2.10.2
10kA - 6-32A range SP MCBs each 12.00 200.60 2407.20 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 0.50 297.00 148.50
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Sundries such as TW Plugs, Screws Cement etc, LS 33.00
Rate per each 4873.50
Note : Labour Charges considered for 2 jobs / day
B 63A FP Isolator - 1 No for incomer, 10kA- 6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection suitable for 3 phase ELCB / RCCB/ each 1.00 1398.60 1398.60 ELEC-2.12.21
FP Isolator as incommer.
63A, 4 Pole Isolator / ELCB / RCCB each 1.00 889.40 889.40 ELEC-2.10.7
10kA - 6-32A range SP MCBs each 12.00 200.60 2407.20 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 0.50 297.00 148.50
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Sundries such as TW Plugs, Screws Cement etc, LS 33.00
Rate per each 5396.70
Note : Labour Charges considered for 2 jobs / day
C 80A FP Isolator - 1 No for incomer, 10kA- 6-32A SP MCBs - 18Nos
for outgoing.
Taking Output = each
a) Material
6 way TPN, D.B with IP-20 Protection suitable for 3 phase ELCB / RCCB/ each 1.00 3373.90 3373.90 ELEC-2.12.66
FP Isolator as incommer.
80A, 4 Pole Isolator / ELCB / RCCB each 1.00 940.70 940.70 ELEC-2.10.8
10kA - 6-32A range SP MCBs each 18.00 200.60 3610.80 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 0.50 297.00 148.50
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Sundries such as TW Plugs, Screws Cement etc, LS 33.00
Rate per each 8626.90
Note : Labour Charges considered for 2 jobs / day
4.4.4 Supply and fixing TPN Distribution board with IP-42 protection (Metal
Door) suitable for 3 phase ELCB / RCCB / FP Isolator as incomer and
10kA SP MCBs as outing going including internal connection and labour
charges for surface / flush mounting etc., complete.
1 2 3 4 5 6 7
B Incomer : 80A FP Isolator / ELCB / RCCB
Outgoing : 32A TP MCBs 4 Nos and 6-32A SP MCBs 12Nos
a) Material
8way TPN - Vertical type DB with IP-20 protection suitable for 3 Phase Nos 1.00 6321.20 6321.20 ELEC-2.12.28
ELCB / RCCB / 4 Pole Isolator as in commer and TP / SP MCBs as
outgoing with Bus-bar arrangment etc.,
80 Apms, 4 Pole Isolator / ELCB / RCCB Nos 1.00 940.70 940.70 ELEC-2.10.8
32A TP MCBs Nos 4.00 817.50 3270.00 ELEC-2.9.13
10kA -6-32A SP MCBs Nos 8.00 200.60 1604.80 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 0.50 297.00 148.50
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Sundries, suchas T.W plugs, Screws, Cement etc, LS 33.00
Rate per each 12838.20
Note : Labour Charges considered for 2 jobs / day
4.4.6 Supply and fixing TPN - Vertical type Distribution board with IP - 42
Protection (Metal Door) suitable for 3 phase ELCB / RCCB / FP Isolator
as incomer and 10 kA TP / SP MCBs as outing going including internal
connection and labour charges for surface / flush mounting etc., complete.
63A, 4 Pole Isolator / ELCB / RCCB . Nos 1.00 889.40 889.40 ELEC-2.10.7
40A DP Isolator Nos 3.00 366.20 1098.60 ELEC-2.10.2
6-32 Amps range SP MCBs. Nos 12.00 200.60 2407.20 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 0.50 297.00 148.50
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Sundries such as T.W. Plugs, Screws, Cement etc., LS 33.00
Rate per each 10966.50
Note : Labour Charges considered for 2 jobs / day
B Incomer : 80A FP Isolator/ ELCB / RCCB
Phase Control : 63A DP Isolator 3 Nos
Outgoing : 10kA-6-32A SP MCBs 24 Nos
a) Material
7 Segment, TPN Distribution 8 Way DB with IP-42 (Metal Door) protection Nos 1.00 7386.10 7386.10 ELEC-2.12.35
with phase segregation and seperation between incomming an outgoing.
80A, 4 Pole Isolator / ELCB / RCCB . Nos 1.00 940.70 940.70 ELEC-2.10.8
63A DP Isolator Nos 3.00 487.20 1461.60 ELEC-2.10.3
6-32 Amps range SP MCBs. Nos 12.00 200.60 2407.20 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Sundries such as T.W. Plugs, Screws, Cement etc., LS 33.00
Rate per each 13045.60
Note : Labour Charges considered for 2 jobs / day
4.4.8 Supply and fixing TPN - Vertical type Distribution board with IP -42
Protection (Metal Door) with 125A, 4Pole 25 kA MCCB as incomer with
4Nos 32A TP MCBs and 12 Nos. 10 kA SPMCBs as outgoing including
internal connection and labour charges for surface / flush mounting etc.,
complete.
a) Material
8 Way TPN Vertical DB with IP -42 (Metal door) protection suitable for Nos 1.00 7527.60 7527.60 ELEC-2.12.32
125A, 4 Pole, 16kA MCCB as incomer.
125 Amps, 4 Pole , 25 kA MCCB Nos 1.00 9822.60 9822.60 ELEC-2.12.37
10 kA, 32A TP MCBs: Nos 4.00 817.50 3270.00 ELEC-2.9.13
10kA, 6 to 32A SP MCBs: Rs.119 / Each Nos 12.00 200.60 2407.20 ELEC-2.9.1
b) Labour charges :
Skilled Electrician day 1.00 297.00 297.00
Semi Skilled Electrician day 1.00 260.00 260.00
Helpers day 1.00 260.00 260.00
Sundries such as T.W. Plugs, Screws, Cement etc., LS 33.00
Rate per each 23877.40
Note : 1. Labour Charges considered for 2 jobs / day
2. If the Distribution Boards from Item No. 4.4.1 to 4.4.8 proposed for
concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
4.4.9 Supply and fixing Distribution board with 20A single phase plug and
Socket, in sheet steel enclosure with 10/16/20A SP MCB including
internal connection and labour charges for surface / flush mounting etc.,
complete
a) Material
1 Phase Distribution board with 20A plug and socket. Nos 1.00 900.70 900.70 ELEC-2.12.38
10/16/20A SP MCB Nos 1.00 200.60 200.60 ELEC-2.9.1
b) Labour charges :
Skilled Electrician Nos 0.25 297.00 74.25
Semi skilled Electrician Nos 0.25 260.00 65.00
Helpers Nos 0.25 260.00 65.00
Sundries such as Cement, Sand, T.W. Plugs, Screws etc., LS 33.00
Rate per each 1338.55
Note : 1. Labour Charges considered for 4 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
4.4.10 Supply and fixing Distribution board with 20A 3 phase plug and Socket, in
sheet steel enclosure with 16/20A TP MCB including internal connection
and labour charges for surface / flush mounting etc., complete.
a) Material
Distribution board with 3 Ph. 20A Plug and Socket . Each 1.00 900.70 900.70 ELEC-2.12.38
32A TP MCB, 10 kA Each 1.00 954.80 954.80 ELEC-2.9.5
b) Labour charges :
Skilled Electrician Nos 0.33 297.00 98.01
Semi skilled Electrician Nos 0.33 260.00 85.80
Helpers Nos 0.33 260.00 85.80
Sundries such as Cement, T.W. Plugs, Screws etc., 33.00
Rate per each 2158.11
Note : 1. Labour Charges considered for 3 jobs / day
2. For concealing, add the following:
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a 1No. Semi skilled mason
b 1/4 bag cement
BLD-ELEC-5 5 EARTHING
BLD-ELEC-5-1 5.1 EARTHING
5.1.1 Providing independent earthling by excavating a trench to a depth of 2.1
M in all soils, as per size specified in the Data, using 40mm dia 'B' class
GI pipe of 2.5 Mtrs length with necessary accessories with hume pipe ring
duly providing staggered holes including filling with equal proportion of
Salt and Charcoal in layers and all labour charges etc., complete for small
quarters.
a) Material
Earth Work Excavation of Hard gravel Soil with small boulder for trench cum 0.85 166.69 141.69
1st step of size 1.5 x 0.6 x 0.9 m (5'x2'x3')
Excavation of Hard disteggrated rocks and boulders for trench 2nd Step of cum 0.90 84.86 76.37
size 1.2 x 0.6 x 1.2 m (Civil SSR) (4'x2'x4')
25% extra for narrow trench & pit and back filling with Sand, Coke, Salt 54.52
etc., and leveling
40mm dia 'B' Class G.I pipe Mtr 2.50 189.00 472.50 ELEC-8.1.62
25 x 6 mm (1"X 1/4") G.I Flat duly drilled 12mm holes (4 Nos) of 200 mm Each 1.00 170.00 170.00 M-101
(8") length
Drilling of 16 Nos through holes of 12mm dia to G.I pipe Each 16.00 50.00 800.00 ELEC-8.1.63
G.I Nuts, Bolts an Washers Set 4.00 10.00 40.00 ELEC-8.1.64
18" dia hume pipe ring Each 1.00 200.00 200.00 ELEC-8.1.65
Hard Coke Kg 40.00 8.00 320.00 ELEC-8.1.16
Salt Kg 20.00 4.00 80.00 ELEC-8.1.17
b) labour charges for fixing pipe ring and connections
Semi skilled Electrician Nos 0.50 297.00 148.50
Helpers Nos 0.50 260.00 130.00
Sundries 33.00
Rate per each 2666.58
5.1.2 Providing independent earthing for Important equipment with 40mm dia 'B'
class 2.5m long G.I pipe and 19mm dia 'B' class G.I pipe of 0.3mtr. long
connected with reducer providing G.I funnel with mesh enclosed in
C.C.Chamber of 400m x 400m x 400mm with R.C.C. Slab cover duly
providing staggered holes filling with salt and charcoal from the bottom of
the pipe giving earth connection from electrode through G.I strip of 25 x
6mm x 200mm length with all accessories and labour charges complete,
as per IS specifications 732/1982 (Part II)
a) Material
Earth work excavation of hard gravel soil with small boulders for trench cum 1.27 166.69 211.70
1st step of size 1.5 x 0.9 x 0.9 m (5'x3'x3')
Earth work hard disintegrated rock and boulders for trench 2nd Step of cum 1.87 84.86 158.69
size 1.2 x 0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')
25% extra for trenches and narrow Pit, back filling and blending. 92.60
Laying C.C bed in Cement mortar with 1: 2:4 with 20 mm HBG Stone cum 0.90 3669.35
Metal (Civil SSR). 4077.05
Masonary through with brick Masonry with CM 1:3 cum 0.23 2858.64 657.49
Cement plastering inside through with 1:3 Cement mortar, 12 mm thick sqm 2.09 177.42
(Civil SSR). 84.89
40mm dia G.I pipe Class 'B' (Civil SSR) Mtr 2.50 189.00 472.50
19mm dia G.I pipe Mtr 0.30 0.30
40mm x 19mm reducer Each 1.00 1.00
G.I Funel covered with wire mesh Each 1.00 1.00
25mm x 6mm x 200 mm length G.I Strip (Flat) with 4 Nos. Holes of 12mm Each 1.00 1.00
dia.
Drilling of staggered holes of 12mm dia to G.I pipe. Each 16.00 16.00
G.I Bolts, Nuts and Washers. Set 4.00 4.00
Hard Coke. kg 4.00 4.00
Salt. kg 20.00 20.00
Cost Iron cover 400 mm x 400mm x 50mm. L.S
b) labour charges for fixing pipe
Skilled Electrician Nos 1.00 1.00
Sundries such as Lugs and Saddles 33.00
Rate per each 5521.03
5.1.3 Providing independent earthing for Sophisticated Electronic equipment
with 600mm x 600mm x 3.15mm thick copper plate rigidly fixed to 40mm
dia G.I Pipe of 0.3mtr. length connected with reducer providing G.I funnel
with wiremesh as per National Electric Code including C.C.Chamber of
size 400m x 400m x 400mm covered with R.C.C. Slab filling with salt and
charcoal giving earth connection from electrode G.I strip of 25mm x 6mm
x 200mm length with all accessories and labour charges complete as per
IS specification 732/1982 (Part II).
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
Earth work excavation of hard gravel soil with small boulders for trench cum 1.27
1st step of size 1.5 x 0.9 x 0.9 m (5'x3'x3')
Earth work hard disintegrated rock and boulders for trench 2nd Step of cum 1.87
size 1.2 x 0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')
25% extra for trenches and narrow Pit, back filling and blending.
Laying C.C bed in Cement mortar with 1: 2:4 with 20 mm HBG Stone cum 0.90
Metal (Civil SSR).
Masonary through with brick Masonry with CM 1:3 cum 0.23
Cement plastering inside through with 1:3 Cement mortar, 12 mm thick sqm 2.09
(Civil SSR).
40mm dia G.I pipe Class 'B' (Civil SSR) Mtr 2.50
19mm dia G.I pipe Mtr 0.30
40mm x 19mm reducer Each 1.00
G.I Funel covered with wire mesh Each 1.00
25mm x 6mm x 200 mm length G.I Strip (Flat) with 4 Nos. Holes of 12mm Each 1.00
dia.
600mm x600mm x 3.15mm thick copper plate kg 10.00
Drilling of staggered holes of 12mm dia to G.I pipe. Each 16.00
G.I Bolts, Nuts and Washers. Set 4.00
Hard Coke. kg 4.00
Salt. kg 20.00
Cost Iron cover 400 mm x 400mm x 50mm. L.S
b) labour charges for fixing pipe
Skilled Electrician Nos 1.00
Sundries such as Lugs and Saddles
Rate per each
BLD-ELEC-5-2 5.2 G.I Wire and Strip
5.2.1 Supply and Run of No.8 SWG G.I wire including cost of all accessories
and labour charges etc., complete.
a) Material
No.8 SWG G.I wire 100 M Length (0.104 Kg / Mtr) Kg 10.40 549.90 5718.96 ELEC-8.1.41
U' Nails 100Nos 1.50 40.00 60.00
b) labour charges
Helpers day 2.00 260.00 520.00
Sundries. 33.00
C) Cost for 100 M 6331.96
Rate per mtr c/100 63.32
5.2.2 Supply and Run of No.10 SWG G.I wire including cost of all accessories
and labour charges etc., complete.
a) Material
No.10 SWG G.I wire 100 M Length (0.067 Kg / Mtr) Kg 6.70 549.90 3684.33
U' Nails 100Nos 1.50 40.00 60.00
b) labour charges
Helpers day 2.00 260.00 520.00
Sundries. 33.00
C) Cost for 100 M 4297.33
Rate per mtr c/100 42.97
5.2.3 Supply and Run of No.12 SWG G.I wire including cost of all accessories
and labour charges etc., complete.
a) Material
No.12 SWG G.I wire 100 M Length (0.044 Kg / Mtr) Kg 4.40 549.90 2419.56
U' Nails 100Nos 1.50 40.00 60.00
b) labour charges
Helpers day 2.00 260.00 520.00
Sundries. 33.00
C) Cost for 100 M 3032.56
Rate per mtr c/100 30.33
5.2.4 Supply and Run of No.14 SWG G.I wire including cost of all accessories
and labour charges etc., complete.
a) Material
No.14 SWG G.I wire 100 M Length (0.026 Kg / Mtr) Kg 2.60 549.90 1429.74
U' Nails 100Nos 1.50 40.00 60.00
b) labour charges
Helpers day 2.00 260.00 520.00
Sundries. 33.00
C) Cost for 100 M 2042.74
Rate per mtr c/100 20.43
5.2.5 Supply and Run of 25mm x 6mm G.I Strip including cost of all
accessories and labour charges etc., complete.
a) Material
25mm x 6mm G.I Strip 100 M Length (1.18 Kg / Mtr) kg 118.00
b) labour charges
Skilled Electrician Nos 2.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Helper Nos 2.00
Sundries such as T&P.
C) Cost for 100 M
Rate per mtr c/100
5.2.6 Supply and Run of 40mm x 6mm G.I Strip including cost of all accessories
and labour charges etc., complete
a) Material
40mm x 6mm G.I Strip 100 M Length (1.88 Kg / Mtr) kg 188.00
b) labour charges
Skilled Electrician Nos 2.00
Helper Nos 2.00
Sundries such as T&P.
C) Cost for 100 M
Rate per mtr c/100
5.2.7 Supply and Run of 50mm x 6mm G.I Strip including cost of all
accessories and labour charges etc., complete.
a) Material
50mm x 6mm G.I Strip 100 M Length (2.36 Kg / Mtr) kg 236.00
b) labour charges
Skilled Electrician Nos 2.00
Helper Nos 2.00
Sundries such as T&P.
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-5-3 5.3 Copper wire and Strip
5.3.1 Supply and Run of Zero gauge copper wire including cost of all
accessories and labour charges etc., complete
a) Material
O' SWG Copper wire (0.455 Kg/Mtr.) 100 M Length Kg 45.50
b) labour charges
Skilled Electrician Nos 1.00
Semi skilled Electrician Nos 1.00
Helper Nos 1.00
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.2 Supply and Run of No. 8 SWG copper wire including cost of all
accessories and labour charges etc., complete.
a) Material
8 SWG Copper wire (0.1155 Kg/Mtr.) 100 M Length Kg 11.55
b) labour charges
Skilled Electrician Nos 1.00
Semi skilled Electrician Nos 1.00
Helper Nos 1.00
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.3 Supply and Run of No. 14 SWG copper wire including cost of all
accessories and labour charges etc., complete
a) Material
14 SWG Copper wire (0.028 Kg/Mtr.) 100 M Length Kg 2.80
b) labour charges
Skilled Electrician Nos 1.00
Semi skilled Electrician Nos 1.00
Helper Nos 1.00
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.4 Supply and Run of 25mm x 3mm copper strip including cost of all
accessories and labour charges etc., complete.
a) Material
25mmx 3mm Copper strip (0.663 Kg / Mtr) 100 M Length Kg 66.30
b) labour charges
Skilled Electrician Nos 2.00
Helper Nos 2.00
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.5 Supply and Run of 32mm x 6mm copper strip including cost of all LS
accessories and labour charges etc., complete.
a) Material
32mmx 6mm Copper strip (1.697 Kg / Mtr) 100 M Length Kg 169.70
b) labour charges
Skilled Electrician Nos 2.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Helper Nos 2.00
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-6 6 SERVICE MAINS & LTOH Lines
BLD-ELEC-6-1 6.1 WPSC (Weather Prrof Single Core) (PVC Cleats)
6.1.1 Supply and Run of 2 of 2.5 Sq.mm WPSC (Whether Proof Single Core)
Aluminium cable along with No.10 SWG G.I bearer wire through PVC
cleats with all accessories including labour charges etc., complete for
service mains.
a) Material
2.5 Sq.mm WPSC Aluminium cable 100 M 2.00
No.10 SWG G.I wire. (0.026 Kg / Mtr) Length 100 RM kg 6.70
PVC Cleats 100 Nos 1.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries such as insulation tapes and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.2 Supply and Run of 2 of 6 Sq.mm WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete for service mains.
a) Material
6 Sq.mm WPSC Aluminium cable 100 M 2.00
No.10 SWG G.I wire. (0.026 Kg / Mtr) Length 100 RM kg 6.70
PVC Cleats 100 Nos 1.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries such as insulation tapes and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.3 Supply and Run of 2 of 10 Sq.mm WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable 100 M 2.00
No.10 SWG G.I wire. (0.026 Kg / Mtr )Length 100 RM kg 6.70
PVC Cleats 100 Nos 1.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries such as insulation tapes and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.4 Supply and Run of 4 of 6 Sq.mm WPSC Aluminium cable along with
No.10 SWG G.I bearer wire on both sides through PVC cleats with all
accessories including labour charges etc., complete for service mains.
a) Material
6 Sq.mm WPSC Aluminium cable 100 M 4.00
No.10 SWG GI Wire (6.7kg x 2) Length 200 RM kg 13.40
Binding wire kg 0.25
PVC Cleats / Separters 4 W. 100 Nos 1.00
b) labour charges
Skilled Electrician day 2.00
Semi skilled day 2.00
Helper day 2.00
Sundries such as insulation tapes and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.5 Supply and Run of 4 of 10 Sq.mm WPSC Aluminium cable along with
No.10 SWG G.I bearer wire on both sides through PVC cleats with all
accessories including labour charges etc., complete for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable 100 M 4.00
No.10 SWG GI Wire (6.7kg x 2) Length 200 RM kg 13.40
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Binding wire kg 0.25
PVC Cleats / Separters 4 W. 100 Nos 1.00
b) labour charges
Skilled Electrician day 2.00
Semi skilled day 2.00
Helper day 2.00
Sundries such as insulation tapes and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.6 Supply and Run of 4 of 16 Sq.mm WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete for service mains.
a) Material
16 Sq.mm WPSC Aluminium cable 100 M 4.00
No.10 SWG GI Wire (6.7kg x 2) Length 200 RM kg 13.40
Binding wire kg 0.25
PVC Cleats / Separters 4 W. 100 Nos 1.00
b) labour charges
Skilled Electrician day 2.00
Semi skilled day 2.00
Helper day 2.00
Sundries such as insulation tapes and rounding off
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-6-2 6.2 WPTC (Weather Prrof Twin Core) Cable
6.2.1 Supply and Run of 1 of 6 Sq.mm WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete.
a) Material
6 Sq.mm (7/18) wptc Aluminium cable 100 M 1.00
No.10 G.I wire. Length 100 RM kg 6.70
Insulation tapes each 2.00
Aluminium link clips box 2.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.2.2 Supply and Run of 1 of 10 Sq.mm WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete.
a) Material
10 Sq.mm (7/18) wptc Aluminium cable 100 M 1.00
No.10 G.I wire. Length 100 RM kg 6.70
Insulation tapes each 2.00
Aluminium link clips box 2.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.2.3 Supply and Run of 2 of 6 Sq.mm WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete.
a) Material
6 Sq.mm (7/18) wptc Aluminium cable 100 M 2.00
No.10 G.I wire. Length 100 RM kg 6.70
PVC insulation tapes each 4.00
Link clips box 2.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.2.4 Supply and Run of 2 of 10 Sq.mm WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
10 Sq.mm (7/18) wptc Aluminium cable 100 M 2.00
No.10 G.I wire. Length 100 RM kg 6.70
PVC insulation tapes each 4.00
Link clips box 2.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.2.5 Supply and Run of 2 of 16 Sq.mm WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through PVC cleats with all accessories
including labour charges etc., complete.
a) Material
16 Sq.mm (7/18) wptc Aluminium cable 100 M 2.00
No.10 G.I wire. Length 100 RM kg 6.70
PVC insulation tapes each 4.00
Link clips box 2.00
b) labour charges
Skilled Electrician day 1.00
Semi skilled day 1.00
Helper day 1.00
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-6-3 6.3 L.T.O.H. Lines
6.3.1 Supply and fixing of 3 phase, 4 wire angle iron cross arm with 3 Nos
shackle / pin insulators for phases and C.I knob for neutral including cost
and conveyance of all materials.
a) Material
Angle Iron 38 x 38 x 6 mm (1.5"x1.5"x1/4") kg 4.27
Drilling Holes each 6.00
M.S Clamp 25mm x 6mm with bolts and nuts each 1.00
Pin insulators 100 x 80 mm (4"x3 1/2") each 3.00
C.I Nob each 1.00
Cutting of angle Iron and Welding including cost of flat Iron etc., LS
b) labour charges
Skilled Electrician day 0.13
Semi skilled day 0.13
Rate per Each
Note : 1. Labour Charges considered for 8 jobs / day
6.3.2 Supply and fixing of single phase, 2 wire angle iron cross arm with 1 Nos
shackle / pin insulators for phases and C.I knob for neutral including cost
and conveyance of all materials.
a) Material
Angle Iron 38 x 38 x 6 mm (1.5"x1.5"x1/4" (0.61 mt)) kg 2.13
Drilling Holes each 4.00
M.S Clamp 25mm x 6mm with bolts and nuts each 1.00
Pin insulators 100 x 80 mm (4"x3 1/2") each 1.00
C.I Knob each 1.00
Cutting of angle Iron and Welding including cost of flat Iron sundires. LS
b) labour charges
Skilled Electrician day 0.10
Semi skilled day 0.10
Rate per Each
Note : 1. Labour Charges considered for 10 jobs / day
6.3.3 Supply and fixing of stayset with 7/8 SWG (10to 15m long) guy insulator
with concreting 1:3:6 incluidng excavation of pit and back filling including
cost and conveyance of all materials and labolur charges etc., complete.
a) Material
Stay rod of 16mm dia (7/8 SWG) 1560mm length with bolts and nuts with each 1.00
switch plate.
Stay tight set (Jum Bracket 300mm) pair 1.00
Stay wire 7/20 weighing 4kgs each 1.00
Cement Concrete 1:3:6 (As per Civil SSR) cum 0.14
Excavation of pit and back filling 1.5 x 0.75 x 0.6 m (5'x2.5'x2') cum 0.68
Stay clamp with bolts and nuts set 1.00
L.T guy insulator each 1.00
b) labour charges
Skilled Electrician. day 0.50
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Man Mazdoor day 1.00
Rate per Each
Note : 1. Labour Charges considered for 2 jobs / day
6.3.4 Supply and fixing of over head line horizontal type safety device with
angle iron cross arm of size 50 x 50 x 6 mm, 1.52m length projection from
pole with 38 x 38 x 6 mm (1 1/2"x1 1/2" x 1/4") angle iron arm including
G.I wire for earth continuity and cost of all accessories labour charges
etc., complete.
a) Material
50 x 50 x 6 mm (2"x2"x1/4") Angle Iron of 1.52 Mtr length kg 5.32
38 x 38 x 6 mm (1.5"x1.5"x1/4") Angle Iron of 0.45 Mtr kg 1.57
Special Flat Iron Clamp 25x6mm with bolts and nuts each 1.00
No.8 SWG G.I wire 8m Length kg 0.80
b) labour charges
Skilled Electrician day 0.25
Semi skilled day 0.25
Helper day 0.50
Sundires such as bolts, nuts including soldering.
Rate per Each
Note : 1. Labour Charges considered for 4 jobs / day
6.3.5 OH Conductors
6.3.5 Supply and erecting 7/2.00 AAAC (All Aluminium Annealed Conductor) /
(a) Squirrel (20 Sq.mm) conductor for Overhead line with stringing, binding
and suitable size of clamps for Jumpering etc., complete
a) Material
7/2.0 AAAC (Squirrel) km 1.00
7/2.0 AAAC for binding and Jumpering. km 0.10
Aluminium Clamps each 10.00
b) labour charges
Skilled Electrician day 2.00
Helper day 8.00
For special T&P LS
Sundires and rounding off
Rate per km
6.3.5 Supply and erecting 7/2.50 AAAC / Weasel (34 Sq.mm) conductor for
(b) Overhead line with stringing, binding and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/2.5 AAAC / Weasel (34 Sq.mm) km 1.00
7/2.5 AAAC for binding and Jumpering. km 0.10
Aluminium Clamps each 10.00
b) labour charges
Skilled Electrician day 2.00
Helper day 8.00
For special T&P LS
Sundires and rounding off
Rate per km
6.3.5 Supply and erecting 7/3.15 AAAC / Rabbit (55 Sq.mm) conductor for
(c) Overhead line with stringing, binding and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/3.15 AAAC / Rabbit (55 Sq.mm) km 1.00
7/3.15 AAAC for binding and Jumpering. km 0.10
Aluminium Clamps each 10.00
b) labour charges
Skilled Electrician day 2.00
Helper day 8.00
For special T&P LS
Sundires and rounding off
Rate per km
6.3.6 Supply and erecting of fibre / PVC spacers for L.T Overhead line of 3 to 5
conductors.
a) Material
PVC spacer suitable for 3 to 5 conductos. each 1.00
b) labour charges
Helper day 0.20
Special T&P. LS
Rate per km
Note : 1. Labour Charges considered for 5 jobs / day
6.3.7 Excavation of hard rock or Bituminous road (BT) by chiselling for
preparing pit for poles / stay / earth plates / laying pipes, including
clearing the site by removing debris and making the site to original
position.
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
Cutting B.T road surface (As per Civil SSR) cum 1.00
Excavation of WBM under B.T cum 1.00
6.3.9 Supply Transportation and unloading the 9.1mtr long PSCC poles with
(b) 280kg working load at site in good condition for H.T. / L.T. lines support
including cost and conveyance of all materials and labour charges etc.,
complete.
a) Material
9.1 Mtr PSCC pole of 280 Kg working load each 1.00
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.50
Rate per each
Note : 1. Unloading Charges considered for 12 jobs / 6 Helpers / day
6.3.9 Supply Transportation and unloading the 8.0mtr long PSCC poles with
(c) 200kg working load at site in good condition for H.T. / L.T. lines support
including cost and conveyance of all materials and labour charges etc.,
complete.
a) Material
8 Mtr PSCC pole of 200 Kg working load each 1.00
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.50
Rate per each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Note : 1. Unloading Charges considered for 12 jobs / 6 Helpers / day
6.3.9 Supply, Transportation and unloading the 8.0mtr long PSCC poles with
(d) 140kg working load at site in good condition for H.T. / L.T. lines support
including cost and conveyance of all materials and labour charges etc.,
complete.
a) Material
8 Mtr PSCC pole of 140 Kg working load each 1.00
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.50
Rate per each
Note : 1. Unloading Charges considered for 12 jobs / 6 Helpers / day
6.3.10 Supply Transportation and unloading the RS Joist of 9.0 mtr long 175mm
(a) x 85mm size at site in good condition for H.T. / L.T. lines support including
cost and conveyance of all materials and labour charges etc., complete.
a) Material
175mm x 85mm, 9.0 Mtr long R.S.Joist (1mt = 19.6 Kg) kg 176.40
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.33
Rate per each
Note : 1. Unloading Charges considered for 20 jobs / 6 Helpers / day
6.3.10 Supply Transportation and unloading the RS Joist of 8.0 mtr long 150mm
(b) x 75mm size at site in good condition for H.T. / L.T. lines support including
cost and conveyance of all materials and labour charges etc., complete.
a) Material
150mm x 75mm, 8.0 Mtr long R.S.Joist (1mt = 15.0 Kg) kg 120.00
Transportation Charges @ 5% of Cost
Helper for Unloading day 0.33
Rate per each
Note : 1. Unloading Charges considered for 20 jobs / 6 Helpers / day
a) Material
1x40W WP flourscent street light fitting. each 1.00
Lamp cost of 40W each 1.00
Sundries and rounding off
Rate per each
7.1.2 Supply of 2x11W CFL (Compacted Flourescent Lamp), Street light fitting
with all standard accessories and 2 Nos 11W CFL, Lamp etc., complete.
a) Material
2x11W CFL street light fitting. each 1.00
Cost of 11W CFL each 1.00
Sundries and rounding off
Rate per each
7.1.3 Supply of 1x18W CFL, Street light fitting with all standard accessories
and 1 No 18W CFL lamp etc., complete.
a) Material
1x18W CFL street light flourscent fitting. each 1.00
Lamp cost of 1x18W CFL each 1.00
Sundries and rounding off
Rate per each
BLD-ELEC-7-2 7.2 Mercury Vapour (M.V.) LUMINAIRE
7.2.1 Supply of single piece die cast Aluminium body with 80W mercury vapour
luminaire with copper wound ballast and capacitor including 80W
M.V.Lamp etc., complete.
a) Material
80W MV Lamp fitting single piece die cast Aluminium body with copper each 1.00
wound ballast and capacitor
80W MV lamp each 1.00
Sundries and rounding off
Rate per each
7.2.2 Supply of single piece die cast Aluminium body with 125W M.V. luminaire
with copper wound ballast and capacitor including 125W HPMV lamp etc.,
complete.
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
125W MV Lamp fitting single piece die cast Aluminium body with copper each 1.00
wound ballast and capacitor
125W MV lamp each 1.00
Sundries and rounding off
Rate per each
BLD-ELEC-7-3 7.3 High Pressure Sodium Vapour (S.V.) LUMINAIRE
7.3.1 Supply of Integral street light luminaire of 70W HPSV lamp fitting
comprises of single piece die cast Aluminium body with copper wound
ballast and capacitor, Ignitor, with pot optics including 70W HPSV lamp
etc., complete.
a) Material
70W HPSV Lamp fitting single piece die cast Aluminium body with copper each 1.00
wound ballast and capacitor, Ignitor, with pot optics
70W HPSV lamp each 1.00
Sundries and rounding off
Rate per each
7.3.2 Supply of Integral street light luminaire of 150W HPSV lamp fitting
comprises of single piece die cast Aluminium body with copper wound
ballast and capacitor, Ignitor, with pot optics including 150W HPSV lamp
etc., complete.
a) Material
150W HPSV Lamp fitting single piece die cast Aluminium body with each 1.00
copper wound ballast and capacitor, Ignitor, with pot optics
156W HPSV lamp each 1.00
Sundries and rounding off
Rate per each
7.3.3 Supply of Integral street light luminaire of 250W HPSV lamp fitting
comprises of single piece die cast Aluminium body with copper wound
ballast and capacitor, Ignitor, with pot optics including 250W HPSV lamp
etc., complete.
a) Material
250W HPSV Lamp fitting single piece die cast Aluminium body with each 1.00
copper wound ballast and capacitor, Ignitor, with pot optics
250W HPSV lamp each 1.00
Sundries and rounding off
Rate per each
BLD-ELEC-7-4 7.4 METAL HALIDE LUMINAIRE
7.4.1 Supply of Integral street light luminaire of 70W MH lamp fitting comprises
of single piece die cast Aluminium body with copper wound ballast and
capacitor, Ignitor, with pot optics including 70W MH lamp etc., complete
a) Material
70W MH Lamp fitting single piece die cast Aluminium body with copper each 1.00
wound ballast and capacitor, Ignitor, with pot optics
70W MH lamp each 1.00
Sundries and rounding off
Rate per each
7.4.2 Supply of Integral street light luminaire of 150W MH lamp fitting comprises
of single piece die cast Aluminium body with copper wound ballast and
capacitor, Ignitor, with pot optics including 150W MH lamp etc.,
complete.
a) Material
150W MH Lamp fitting single piece die cast Aluminium body with copper each 1.00
wound ballast and capacitor, Ignitor, with pot optics
150W MH lamp each 1.00
Sundries and rounding off
Rate per each
7.4.3 Supply of Integral street light luminaire of 250W MH lamp fitting comprises
of single piece die cast Aluminium body with copper wound ballast and
capacitor, Ignitor, with pot optics including 250W MH lamp etc.,
complete.
a) Material
250W MH Lamp fitting single piece die cast Aluminium body with copper each 1.00
wound ballast and capacitor, Ignitor, with pot optics
250W MH lamp each 1.00
Sundries and rounding off
Rate per each
7.4.4 Supply of integral street light luminaire of 250W MH with IP-65 protection,
POT optics comprises of single piece die cast Aluminium body with
copper wound ballast and capacitor with 250W MH lamp etc., complete.
a) Material
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
250W IP-65 MH Lamp fitting single piece die cast Aluminium body with each 1.00
copper wound ballast and capacitor
Lamp cost of 250W MH lamp each 1.00
Sundries and rounding off
Rate per each
BLD-ELEC-7-5 7.5 POST TOP LUMINAIRE
7.5.1 Supply of post top luminaire of mushroom type with clear acrylic cover
and comprises of control gear capsule die cast Aluminium alloy with
VPIT / copper ballast suitable for 9/11/13W CFL with lamp etc., complete.
a) Material
1X9/11/13W CFL Lamp fitting each 1.00
1X9/11/13W CFL Lamp each 1.00
Sundries and rounding off
Rate per each
7.5.2 Supply of 125W HPMV integral post top luminaire with Aluminium canopy
and acrylic diffuser with all standard accessories and 125W HPMV lamp
etc., complete.
a) Material
125W HPMV post top Lamp fitting each 1.00
Cost of 125W HPMV post top LAMP each 1.00
Sundries and rounding off
Rate per each
7.5.3 Supply of 70W HPSV integral post top luminaire with Aluminium canopy
and acrylic diffuser with all standard accessories and 70W HPSV lamp
etc., complete.
a) Material
70W HPSV post top Lamp fitting each 1.00
Cost of 70W HPSV post top lamp each 1.00
Sundries and rounding off
Rate per each
7.5.4 Supply of diamond / sphere type 80W HPMV post top lantern luminaire
with all standard accessories including 80W M.V. lamp etc., complete
a) Material
80W HPMV post top diamond / sphere type Lamp fitting each 1.00
80W HPMV post top diamond / sphere type Lamp each 1.00
Sundries and rounding off
Rate per each
7.5.6 Supply of diamond / sphere type 125W HPMV post top lantern luminaire
with all standard accessories including 125W M.V. lamp etc., complete.
a) Material
125W HPMV post top Lamp fitting each 1.00
125W HPMV post top Lamp each 1.00
Sundries and rounding off
Rate per each
7.5.7 Supply of diamond / sphere type 70W HPSV post top lantern luminaire
with all standard accessories including 70W S.V. lamp etc., complete.
a) Material
70W HPSV diamond / sphere post top Lamp fitting each 1.00
70W HPSV diamond / sphere post top Lamp each 1.00
Sundries and rounding off
Rate per each
BLD-ELEC-7-6 7.6 Well Glass Luminaires
7.6.1 Supply of 80W M.V integral wellglass luminaries with all standard
accessories and 80W MV lamp etc., complete.
a) Material
80W MV wellglass luminaries each 1.00
80W MV wellglass luminaries lamp each 1.00
Sundries and rounding off
Rate per each
7.6.2 Supply of 70W S.V. integral wellglass luminaries with all standard
accessories and 70W S.V. lamp etc., complete.
a) Material
70W SV wellglass luminaires each 1.00
70W SV wellglass luminaries. each 1.00
Sundries and rounding off
Rate per each
BLD-ELEC-7-7 7.7 Flood Light Luminaires
7.7.1 Supply of 500W Halogen fitting with all accessories including 500W
Halogen lamp etc., complete.
a) Material
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
500W halogen lamp fitting. each 1.00
500W halogen lamp each 1.00
Sundries and rounding off
Rate per each
7.7.2 Supply of 1000W Halogen fitting with all accessories including 1000W
Halogen lamp etc., complete.
a) Material
1000W halogen lamp fitting. each 1.00
1000W halogen lamp each 1.00
Sundries and rounding off
Rate per each
7.7.3 Supply of integral type flood light metal halide luminaire of 250W
comprising of die cast Aluminium housing and a heat resistant toughned
glass firmly fixed by means of gasket and toggles with IP-65 protection
incluidng control gear housing and all accessories with 250W MH-T lamp
etc., complete.
a) Material
250W MH flood light fitting each 1.00
250W MH lamp. each 1.00
Sundries and rounding off
Rate per each
7.7.4 Supply of integral type flood light metal halide luminaire of 400W
comprising of die cast Aluminium housing and a heat resistant toughned
glass firmly fixed by means of gasket and toggles with IP-65 protection
incluidng control gear housing and all accessories with 400W MH-T lamp
etc., complete.
a) Material
400W MH flood light fitting each 1.00
400W MH flood light lamps each 1.00
Sundries and rounding off
Rate per each
BLD-ELEC-7-8 7.8 Labour Charges
7.8.1 Fixing of CFL luminaire (Down lights / Mirror optic / Ornamental type fitting
with all necessary accessories in false ceiling / on wall including giving
connections and all labour charges etc., complete.
a) Material
23/0060 twin core flexible copper cable M 1.00
screws with rawal plugs each 2.00
Aluminium flat / cement and sand etc., labour charges. LS
b) Labour charges.
Skilled Electrician/carpenter day 0.07
Semi skilled Electrician / Helper day 0.07
Rate per each
Note : Labour Charges considered for15 fixtures / day .
7.9.2 Fixing of 70W MH down light and control gear box with necessary
accessories in false ceiling including giving connections and all labour
charges etc., complete.
a) Material
23/0060 twin core flexible copper cable M 1.00
screws with rawal plugs each 2.00
Aluminium flat / cement and sand etc., labour charges. LS
b) Labour charges
Skilled Electrician/carpenter day 0.13
Semi skilled Electrician / Helper day 0.13
Rate per each
Note : Labour Charges considered for 8 fixtures / day .
7.9.3 Fixing of 40W tube light luminaire on wall / Ceiling with / TW round
blocks with all accessories including giving connections and all labour
charges etc., complete.
a) Material
23/0060 twin core flexible copper cable M 1.00
screws with rawal plugs each 2.00
T.W round blocks each 2.00
Cement and sand etc., LS
b) Labour charges
Skilled Electrician/carpenter day 0.10
Semi skilled Electrician / Helper day 0.10
Rate per each
Note : Labour Charges considered for 10 fixtures / day .
7.9.4 Fixing of 40W tube lights with 1/2 Mtr conduit suspension arrangements
from ceiling with hooks etc., including giving connections and all labour
charges etc., complete.
a) Material
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
20mm dia No.16 gauge conduit pipe . M 1.00
23/0060 twin core flexible copper cable each 1.00
Anchor screws / Hooks / Sockets & Check each 2.00
b) Labour charges
Skilled Electrician/carpenter day 0.17
Semi skilled Electrician / Helper day 0.17
Rate per each
Note : Labour Charges considered for 6 fixtures / day .
7.9.5 Fixing of 40W street light luminaire to the wall with 1.0 Mtr., 25mm dia GI
pipe bracket and anti tilting MS flat etc., including giving connections and
labour charges etc., complete.
a) Material
25mm dia G.I pipe M 1.00
23/0060 twin core flexible copper cable M 2.00
Pipe bending charges LS
M.S flat and welding charges LS
b) Labour charges
Skilled Electrician/carpenter day 0.20
Mason day 0.20
Semi skilled Electrician / Helper day 0.20
Rate per each
Note : Labour Charges considered for 5 fixtures / day .
7.9.6 Fixing of CFL street light luminary with 1.0 Mtr., 25mm dia GI pipe
bracket and anti tilting MS flat etc., including giving connections and
labour charges etc., complete.
a) Material
25mm dia G.I pipe M 1.00
23/0060 twin core flexible copper cable M 2.00
Pipe bending charges LS
M.S flat and welding charges LS
b) Labour charges
Skilled Electrician/carpenter day 0.13
Mason day 0.13
Helper day 0.13
Rate per each
Note : Labour Charges considered for 8 fixtures / day .
7.9.7 Fixing of mirror optic tube light luminaire in false ceiling / pop with
necessary arrangment including giving connections and all labour charges
etc., complete.
a) Material
28/0060 twin core flexible copper cable M 1.00
Aluminium flat (as per requirment) LS
b) Labour charges for cutting P.O.P / false ceiling and Fixing MOT
1 2 3 4 5 6 7
Sundires LS
Rate per each
Note : Labour Charges considered for 25Jobs per Day
8.1.2 Supply and fixing of double fancy bracket with glass shade and bulb of
approved colour and quality etc., by field officers.
a) Material
Double Fancy bracket each 1.00
60W Bulb each 2.00
b) Labour charges
Skilled Electrician day 0.05
Helper day 0.05
Sundires
Rate per each
Note : Labour Charges considered for 20Jobs /Day
8.1.3 Supply and fixing 10" ceiling fittings with glass doom and bulb apporved
by dept., officers including giving connection etc., complete.
a) Material
10" Ceiling fitting with glass doom each 1.00
60W Bulb each 1.00
b) Labour charges
Skilled Electrician day 0.05
Helper day 0.05
Sundires
Rate per each
Note : Labour Charges considered for 20 Jobs / Day
8.1.4 Supply and fixing of Bulk head fitting with cast Aluminium enamel painted
body with water tight, clear glass with wire guard hinged with lock and key
arrangements etc., complete with lamp.
a) Material
Bulkhead fitting each 1.00
60W Bulb each 1.00
b) Labour charges
Skilled Electrician day 0.08
Helper day 0.08
Sundires such as TW block / screws, cement etc.,
Rate per each
Note : Labour Charges considered for 12 Jobs / Day
Bldngs_Elec-8-2 8.2 Flourescent Luminaire
8.2.1 Supply and transportation of 1x11 W mirror light with all standard
accessories diffuser and 1No 11W CFL lamp etc., complete
a) Material
1x11W M.O. fitting each 1.00
Cost of C.F.L. each 1.00
Sundries and rounding off
Rate per each
8.2.2 Supply and Transportation of 1x36/40W box type tube light luminaire with
copper / VPIT Choke, condensor, starters etc., and 1No 36/40W tube
etc., complete.
a) Material
1x40/36 box type T.L fitting each 1.00
36/40 Tube each 1.00
Sundries and rounding off
Rate per each
8.2.3 Supply and transportation of 2x36/40W box type tube light luminaire with
2Nos copper / VPIT chokes, starters, with condensor and 2Nos 36/40W
tube etc., complete.
a) Material
2x40/36 box type T.L fitting each 1.00
36/40 FTL each 2.00
Sundries and rounding off
Rate per each
8.2.4 Supply and Transportation of 1x40W patty type tube light luminaire with
copper choke, starter etc., including 1No 40W tube etc., complete.
a) Material
1x40 patty type T.L. fitting each 1.00
40W FTL each 1.00
Sundires and rounding off
Rate per each
Bldngs_Elec-8-3 8.3 INDUSTRIAL luminaire
8.3.1 Supply and Transportation of white vitreous 1x36 / 40W industrial box
type luminaire with Copper / VPIT Choke, Condensor, Starters etc., with
reflector including 1No 40W tube etc., complete.
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
1x36/40W Industrial box type T.L. fitting each 1.00
36/40W FTL each 1.00
Sundries and rounding off
Rate per each
8.3.2 Supply and Transportation of white vitreous 2x36 / 40W industrial box
type luminaire with 2Nos Copper / VPIT Choke, Condensor, Starters
etc.,complete with reflector including 2Nos 40W tube etc., complete.
a) Material
2x36/40W Industrial box type T.L. fitting each 1.00
36/40W FTL each 2.00
Sundries and rounding off
Rate per each
Bldngs_Elec-8-4 8.4 MIRROR OPTIC luminaire
8.4.1 Supply and Transportation of 2x36 / 40W surface mounting mirror optic
luminaire with powder coated CRCA sheet steel housing with Aluminium
mirror reflectors with VPIT chokes, Starters, Condensor etc., complete
with 2Nos 36/40W tubes etc.,complete.
a) Material
2x36/40 Surface M.O.L fitting each 1.00
40/36 FTL each 2.00
Sundries and rounding off
Rate per each
8.4.2 Supply and transportation of 2x36/40W recessed mounting mirror optic
(darklite) luminaire with powder coated CRCA sheet steel housing with
Aluminium mirror reflector with VPIT Chokes, Starter, Condensor etc.,
complete with 2Nos 36/40W tubes etc., complete.
a) Material
2x36/40 Recessed M.O. L fitting each 1.00
36/40 FTL each 2.00
Sundries and rounding off
Rate per each
8.4.3 Supply and transportation of 2x11W surface mounting mirror optic
luminaire with powder coated CRCA sheet steel housing with Aluminium
mirror refector with VPIT Chokes and 2Nos 11W CFL lamps etc.,
complete.
a) Material
2x11W CFL surface M.O.L fitting each 1.00
11W CFL each 2.00
Sundries and rounding off
Rate per each
8.4.4 Supply and transportation of 2x11W Recessed type luminaire with powder
coated CRCA sheet steel housing with Aluminium mirror refector with
VPIT Chokes and 2Nos 11W CFL lamps etc., complete.
a) Material
2x11W CFL recessed M.O.L fitting each 1.00
11W cfl each 2.00
Sundries and rounding off
Rate per each
8.4.5 Supply and transportation of 2x36w CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising bright anodised Aluminium
reflector with VPIT Chokes and 36w CFL lamps.
a) Material
2x36 CFL PS paralite Louvars fitting each 1.00
36w CFL each 2.00
Sundries and rounding off
Rate per each
8.4.6 Supply and transportation of 3x36w CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising bright anodised Aluminium
reflector with VPIT Chokes and 3x36w CFL lamps.
a) Material
3x36 CFL PS paralite Louvars fitting each 1.00
36w CFL each 3.00
Sundries and rounding off
Rate per each
Bldngs_Elec-8-5 8.5 T- 5 Luminaires.
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
8.5.1 Supply and transportation of 1X28W surface pendant mounting T- 5
extruded Aluminium with Aluminium reflector luminaire with all standard
accessories and connections etc., complete with 1 No. 28 W tube
a) Material
1x28w pendant T5 lugs fitting each 1.00
28w T5 FTL each 1.00
Sundries and rounding off
Rate per each
8.5.2 Supply and transportation of 2X28W recessed With 2 Nos. pendant
mounting low glare T- 5 mirror optic luminaire with electronic Ballasts etc.,
complete 28w tubes.
a) Material
2x28w T5 M.O. fitting each 1.00
28w T5 FTL each 2.00
Sundries and rounding off
Rate per each
Bldngs_Elec-8-6 8.6 C.F.L. Down Lights
8.6.1 Supply and transportation of recessed mounting 1x13W CFL down light
with all standard accessories with 1No. 13W CFL lamp (D type) etc.,
complete.
a) Material
1x13W CFL Down light fitting each 1.00
13W CFL each 1.00
Sundries and rounding off
Rate per each
8.6.2 Supply and transportation of recessed mounting 2x13W CFL down light
with all standard accessories with 2No. 13W CFL lamp etc., complete.
a) Material
2x13W CFL Down light fitting each 1.00
13W CFL each 2.00
Sundries and rounding off
Rate per each
8.6.3 Supply and transportation of recessed mounting 1x18W CFL down light
with all standard accessories with 1No. 18W CFL lamp etc., complete.
a) Material
1x18W CFL Down light fitting each 1.00
18W CFL each 1.00
Sundries and rounding off
Rate per each
8.6.4 Supply and transportation of recessed mounting 2x18W CFL down light
with all standard accessories with 2No. 18W CFL lamp etc., complete.
a) Material
2x18W CFL Down light fitting each 1.00
18W CFL each 2.00
Sundries and rounding off
Rate per each
8.6.5 Supply and Transportation recess mounting 70W metal hallide down
lighter with control gear and 1No 70W M.H lamp etc., complete.
a) Material
70W M.H down light fitting each 1.00
70W M.H lamp each 1.00
Sundries and rounding off
Rate per each
8.6.6 Supply and Transportation of Ceiling / Wall mounted Circular 1x13W
luminaire with decorative acrylic diffuser and 1 No. 13W CFL lamp
(circular type) etc., complete.
a) Material
1x13W Circular CFL fitting each 1.00
13W CFL each 1.00
Sundries and rounding off
Rate per each
8.6.7 Supply and Transportation of Ceiling / Wall mounted Circular 2x13W
luminaire with decorative acrylic diffuser and 2 No. 13W CFL lamp
(circular type) etc., complete.
a) Material
2x13W Circular CFL fitting each 1.00
13W CFL each 2.00
Sundries and rounding off
Rate per each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Bldngs_Elec-8-7 8.7 HALOGEN DOWN LIGHTERS
8.7.1 Supply and Transportation of recess mounting 12v, 50w adjustable
halogen down light with white / colour Shade including transformer and
1No 50w halogen lamp etc., complete.
a) Material
50w Halogen recessed mounting each 1.00
50w Halogen bulb each 1.00
Sundries and rounding off
Rate per each
8.7.2 Supply and Transportation of recess mounting 12v, 50w Zoom type
halogen down light with white / colour Shade including transformer and
1No 50w halogen lamp etc., complete.
a) Material
50w Halogen zoom type down light. each 1.00
50w Halogen bulb each 1.00
Sundries and rounding off
Rate per each
Bldngs_Elec-9 9 AIR CONDITIONING & REFRIGERATION
Bldngs_Elec-9-1 9.1 Air-Conditioners
9.1.1(a Supply and Transportation of Window mounted type, Room Air-
) Conditioner 1.5 Ton confirming to IS : 1391, Suitable for operation on
230V + 10% 50 Hz.., Single phase, A.C. Supply capable for performing
Cooling, Dehumidifying, Air Circulating, Filtering and Ventilation etc.,
complete.
a) Material
1.5 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material 0.02
Rate per each
9.1.1( Supply and Transportation of Window mounted type, Room Air-
b) Conditioner 2.0 Ton confirming to IS : 1391, Suitable for operation on
230V + 10% 50 Hz.., Single phase, A.C. Supply capable for performing
Cooling, Dehumidifying, Air Circulating, Filtering and Ventilation etc.,
complete.
a) Material
2.0 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material 0.02
Rate per each
9.1.2 Supply and Transportation of 1.5 Ton Split type Air-Conditiner, fitted with
(a) Hermetically sealed compressor, Operating on refrigerant R-22 / Non -
CFC High wall mounting confirming to IS : 1391, suitable for operation on
230V, 50 Hz.., Single phase, A.C Supply capable of performing Cooling,
Dehumidifying, Air Circulating, Filtering with cooling and condensing units,
with 5 Mtr of required size of copper piping duly insulated and 3 core
copper flexible chord of required length etc., complete.
a) Material
1.5 Ton Split A.C Unit ABS (Plastic Cabin)
ADD : Duties & Taxes as applicable
Transportation on Material 0.02
Rate per Each
9.1.2 Supply and Transportation of 2.0 Ton Split type Air-Conditiner, fitted with
(b) Hermetically sealed compressor, Operating on refrigerant R-22 / Non -
CFC High wall mounting confirming to IS : 1391, suitable for operation on
230V, 50 Hz.., Single phase, A.C Supply capable of performing Cooling,
Dehumidifying, Air Circulating, Filtering with cooling and condensing units,
with 5 Mtr of required size of copper piping duly insulated and 3 core
copper flexible chord of required length etc., complete.
a) Material
2.0 Ton Split ABS Plastic Cabin A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material 0.02
Rate per Each
9.1.3 Installation Charges for 1/0 / 1.5 / 2.0 Ton Window type room Air-
Conditioner with insulating foam, testing and commissioning etc.,
complete.
a) Material
Installation Charges of Window type A.C.Unit. (as per observed Data)
1 2 3 4 5 6 7
9.1.4 Installation Charges for 1.5 / 2.0 Ton Split Air-Conditioner with foam,
insulation for copper pipings connected for the Indoor and outdoor unit
including testing and commissioning etc., complete.
a) Material
Installation Charges of 1/5 / 2.0 Ton Split A.C.Unit. (As per observed
Data )
Rate per Each
9.1.5 Supply, Fabrication and installation of well seasoned T.W. frame of size
685 x 483 mm (27" x 19") ( with section size of 75 x 100 mm (3" x 4"
T.W.)) for 1.0 / 1.5 / 2.0 Ton Window A.C.Unit duly making necessary
provision in the wall / Window with cost and conveyance of all materials
etc., complete
a) Material
Well seasoned wooden frame for Window A.C Units cum 0.02
b) Labour charges for fabrication & Fixing
Carpenter day 0.50
Mason day 0.50
Helper day 0.50
Making necessary provision in wall / window with Hardware LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
9.1.6 Supply, Fabrication and installation of 38 x 38 x 6 mm (1.5" x 1 1/2" x 1/4")
M.S. angle Iron frame suitable for condensing Unit for Split A.C including
2 Coats of Red oxide the followed by 2 coats enamel paint etc., complete.
a) Material
38 x 38 x 6 mm (1.5" x 1 /12" x 1/4") angle iron frame, 13 M length (1 Mtr kg 10.50
= 3.5 Kgs)
Fabrication charges including Painting kg 10.50
b) Labour charges for Fixing
Carpenter day 0.25
Mason day 0.25
Helper day 0.25
Sundires such as cement etc. LS
Rate per Each
Note : Labour is Considered for 4 jobs / day
9.1.7 Supply and Installation of copper tubing between indoor and outdoor unit
for split Air-Conditioner including foaming etc., complete.
a) Material
Copper tubing between indoor and outdoor units inlcuding foaming
1 2 3 4 5 6 7
b) Labour charges
Skilled Electrician day 0.50
Helper day 0.50
Rate per Each
Note : Labour is Considered for 2 jobs / day
9.2.5 Replacement of Unserviceable fan motor capacitor 6 mfd by new
capacitor for A.C machine of 1.0 1.5 / Ton Capacity.
a) Material
6 MFD motor capacitor each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
9.2.6 Replacement of Unserviceable Thermostat switch by supply and
installation of new thermostat switch suitable for 1.0 / 1.5 / 2.0 Ton
A.C.Unit.
a) Material
Thermostat switch for 1.0 / 1.5 / 2.0 Ton A.C.Unit. each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
9.2.7 Replacement of Unserviceable starting capacitor of 80 to 120 mfd. By
new approved make capacitor suitable for compressor motor of 1.0 / 1.5
Ton A.C. Unit.
a) Material
Starting capacitor of 80 to 120 mfd. each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
9.2.8 Replacement of unserviceable running capacitor of 36 mfd by new
approved make capacitor suitable for compressor motor of 1.0 / 1.5 Ton
A.C.Unit.
a) Material
Running capacitor 36 mfd each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
9.2.9 Replacement of Unserviceable relay by new approved make having
pickup voltage 220 Volts and dropout voltage 120 Volts suitable for 1.0 /
1.50 Ton A.C. Unit.
a) Material
Relay having pickup 220V and dropout voltage 120V each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
9.2.10 Replacement of Unserviceable filter and capillary tube by supply and
installation of new filter and capillary tube including welding et., complete
for 1.0 / 1.5 / 2.0 Ton A.C.Unit.
a) Material
Filter and capillary tube for 1.0 / 1.5/2.0 Ton A.C.Unit each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
9.2.11 Replacement of Unserviceable air filter by new air filter suitable for 1.50
Ton A.C.Unit P.V.C. / NYLON for Window A.C.
a) Material
PVC / Nylon Air Filter for Window type A.C.Unit. each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
9.2.11( Replacement of Unserviceable air filter by new air filter suitable for 1.50
a) Ton A.C.Unit P.V.C. / NYLON for Split A.C.
a) Material
PVC / Nylon Air Filter for Split type A.C.Unit. each 1.00
b) Labour charges for removing old one & fixing
Semi skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Bldngs_Elec-9-3 9.3 Refrigerators
9.3.1 Supply Refrigerator domestic type approved make 165 to 310 Ltrs.
Storage capacity, suitable for operation on 230 /250 Volts 50 Hz..
complete with automatic temparture control confirming to IS specifications
No. 1476 / 79 with one year guarantee for seale unit in refrigeration
system including cost and conveyance of all materials and labour charges
etc., complete.
a) Material
----- capacity refrigerator cost each 1.00
Transportation @ 2% of Unit Cost 0.02
Loading, Unloading & Instalation @ 2% of Unit Cost 0.02
Rate per Each
Bldngs_Elec-9-4 9.6 Stabilizers
9.6.1 Supply and erecting fully automatic line voltage stabilizer for operation on
input voltage 200 to 250V. rated for 0.5 KVA maximum load and time
delay model with Volt meter, selector switch, 6A / 16A flush type, 5 pin
socket for out put and with 3 core flexible chord and 3 pin 6/16A plug top
suitable for refrigerator for continuous operation including cost and
conveyance of all mateials and all labour charges etc., complete.
a) Material
0.5 KVA Stabilizer each 1.00
b) Labour Charges
Semi skilled Electrician day 0.04
Helper day 0.04
Transportation Charges on Unit Cost 0.02
Rate per Each
Note : Labour is Considered for 23 jobs / day
9.6.2 Supply and erecting fully automatic line voltage stabilizer for operation on
input voltage 200 to 250V. rated for 1 KVA maximum load and time delay
model with Volt meter, selector switch, 6A / 16A flush type, 5 pin socket
for out put and with 3 core flexible chord and 3 pin 6/16A plug top suitable
for refrigerator for continuous operation including cost and conveyance of
all mateials and all labour charges etc., complete.
a) Material
1 KVA Stabilizer each 1.00
b) Labour Charges
Semi skilled Electrician day 0.04
Helper day 0.04
Transportation Charges on Unit Cost 0.02
Rate per Each
Note : Labour is Considered for 23 jobs / day
9.6.3 Supply and erecting fully automatic line voltage stabilizer for operation on
input voltage 200 to 250V. rated for 3 KVA / 4 KVA / 5 KVA maximum
load and time delay model with Volt meter, selector switch, 6A / 16A flush
type, 5 pin socket for out put and with 3 core flexible chord and 3 pin
6/16A plug top suitable for refrigerator for continuous operation including
cost and conveyance of all mateials and all labour charges etc., complete.
a) Material
3 KVA / 4 KVA / 5 KVA Stabilizer each 1.00
b) Labour Charges
Skilled Electrician day 0.10
Helper day 0.10
Transportation Charges on Unit Cost 0.02
Rate per Each
Note : Labour is Considered for 10 jobs / day
Bldngs_Elec-9-5 9.7 Fans
9.7.2 Supply of 900 mm (36") / 1200 mm (48") / 1400 mm (56") sweep 230V,
A.C 50 Hz.Ceiling fan with 3 Blades and double ball bearings with all
standard accessories.
a) Material
900 mm (36") / 1200 mm (48") / 1400 mm (56") Ceiling Fan each 1.00
Transportation Charges on Unit Cost 0.01
Rate per Each
9.7.7 Supply and erecting wall mounting fan 400mm (16") / 450 mm (18")
sweep A.C. 50Hz.. 1350 r.p.m oscillating type with regulator.
a) Material
400mm (16") / 450 mm (18") wall mounting Fan each 1.00
b) Labour Charges
Semi Skilled Electrician day 0.10
Helper day 0.10
Rate per Each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Note : Labour is Considered for 10 jobs / day
9.7.10 Supply of pedastal fan (16") 400mm, 250 Volts, 50Hz. oscillating type
complete with all standard accessories.
a) Material
400mm (16") Pedastal Fan each 1.00
Transportation Charges on Unit Cost 0.02
Rate per Each
9.7.16 EXHAUST FANS
Supply of fresh air exhaust fan of light duty 250V A.C.50Hz.. 225 mm
(9") / 300mm size (12") 1350 R.P.M Metallic body plastic blades, wire
mesh, etc., complete.
a) Material
225 mm (9") / 300mm (12") L.D. Exhaust Fan each 1.00
Transportation Charges on Unit Cost 0.01
Rate per Each
9.7.18 Supply of fresh air exhaust fan of Heavy duty 250V A.C.50Hz.. 300mm
size (12") / 375 mm (15") 900 R.P.M etc., complete.
a) Material
300mm (12") / 375 mm (15") H.D. Exhaust Fan each 1.00
Transportation Charges on Unit Cost 0.01
Rate per Each
9.7.24 Supply and erecting fan hook of 12/15mm dia M.S. rod / bar grouted in
RCC slab with making the slab as original.
a) Material
12/15mm plain M.S rod for Fan hook each 1.00
Cement, Sand and Rounding off LS
b) Labour charges for grouting in RCC slab, Fixing of Fan hook with
masonary work.
Mason day 0.17
Helper day 0.17
Rate per Each
Note : Labour is Considered for 6 jobs / day
9.7.25 Supply and erecting 19/20mm steel tube down rod of one meter length
with bolts & nuts duly painted with matching colour of fan complete
a) Material
19/20mm steel tube down rod with bolts & nuts for fan with maching M 1.00
colour.
b) Labour charges for Fixing
Helper day 0.10
Rate per Each
Note : Labour is Considered for 10 jobs / day
9.7.26 Supply and erecting resistance type regulator for ceiling fans
900/1200/1400mm sweep complete erected on existing board.
a) Material
Resistance type Regulator M 1.00
b) Labour charges.
Semi skilled Electrician day 0.10
Rate per Each
Note : Labour is Considered for 10 jobs / day
9.7.33 Cleaning of Ceiling fan in existing position .
Labour charges for cleaning greasing / oilingoverhauling
Helper day 0.20
Rate per Each
Note : Labour is Considered for 10 jobs / day by 2 helpers
9.7.34 Removing the ceiling fan and refixing after overhauling and greasing the
bearings and replacement of wire leads etc complete
a) Material
23/0060 twin core wire M 1.00
b) Labour charges.
Removing and refixing of ceiling fan after overhauling
Semi skilled Electrician day 0.17
Helper day 0.17
sundries LS
Rate per Each
Note : Labour is Considered for 6 jobs / day
9.7.35 Labour Charges
Labour charges for Fixing of Ceiling fan and regulator including
transportation and giving connections with twin core wire etc., complete.
a) Material
23/0060 Twin Core wire M 1.00
Unforseen item works, such as painting to down rod, screws etc., LS
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
b) Labour charges.
Skilled Electrician day 0.13
Helper day 0.13
Rate per Each
Note : Labour is Considered for 8 fans / day
9.7.36 Labour charges for fixing of Exhaust fan in wall with necessary
connections and masonary work of making hole, finishing etc., complete
a) Material
23/0060 Twin flat wire M 1.00
Cement kg 25.00
b) Labour charges.
Skilled Electrician day 0.25
Helper day 0.25
Mason day 0.25
Sundries such as Sand, Bolt, Nuts etc., LS
Rate per Each
Note :1. Labour is Considered for 6 jobs / day
2. Cost of louver shutter may be added if required.
3. If hole is already made available, labour charges of Mason shall be
deleted.
Bldngs_Elec-10 10 WATER HEATERS
10.1.2 Supply and Transportation of stove enamelled storage / pressure type
vertical / Horizontal water heater with copper tank 25 / 35 / 50 Ltrs.
Capacity with non return valve on inlet side and dead weight pressure
reducing valve on outlet side 230/ 250V, single phase 2000 watts heating
Bldngs_Elec-10-1 element, thermostat control, fusible plug, pilot lamp etc., erected and
tested complete with ISI specifications etc., including all materials,
transportation, and labour charges complete.
a) Material
25 / 35 / 50 Ltrs. Water Heater each 1.00
Transportation Charges on Unit Cost 0.02
Rate per Each
10.1.5 Labour charges for erection of storage water heater with 2Nos Nylon /
PVC / Metalic hose pipe etc., on wall duly making necessary fixing
arrangments including connections etc., complete.
a) Material
Flexible Nylon / PVC / Metallic hose pipe each 2.00
50 / 100 mm (2" / 4") long bolt and nut with washers each 4.00
Towards wooden plugs, cement etc., LS
b) Labour charges.
Skilled Electrician day 0.25
Helper day 0.50
Semi skilled Mason day 0.25
Rate per Each
Note : Labour is Considered for 4 jobs / day
Bldngs_Elec-10-2 10.2 INSTANT WATER HEATERS
10.2.1 Supply and erecting ISI Mark 3KW Instant Water heater with multiple
safety system, rust free ABS plastic body, 230V, 50Hz.., A.C. supply with
inlet and outlet connections with pvc/ nylon / metallic hose pipe,
thermostat control and thermal cutoff with 3 core P.V.C. flexible wire leads
duly tested including cost of all materials and all labour charges etc.,
complete.
a) Material
3KW Instant Water Heater each 1.00
Transportation Charges on Unit Cost 0.02
Hose pipe PVC/ Nylon each 2.00
T.W getting Bolt / Nuts, Cement, Sand etc. LS
b) Labour charges.
Skilled Electrician day 0.25
Helper day 0.25
Rate per Each
Note : Labour is Considered for 4 jobs / day
Bldngs_Elec-10-3 10.4 REPAIRS TO WATER HEATERS.
10.4.1 Replacement of unserviceable heating element by new one for 1.5 / 2.0 /
3.0 Kw water heater
a) Material
2/3 KW heating Element each 1.00
b) Labour charges.
Skilled Electrician day 0.20
Sundries and rounding off LS
Rate per Each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Note : Labour is Considered for 5 jobs / day
10.4.2 Replacement of Unserviceable thermostat by new thermostat with range
30 to 90 C. adjustable and suitable for 25 to 50 Ltrs. Capacity.
a) Material
Thermostat range 30-90 Degree suitable for 25 to 50 Ltrs. each 1.00
b) Labour charges.
Skilled Electrician day 0.20
Sundries and rounding off LS
Rate per Each
10.4.5 Replacing unserviceable pressure release valve by new water heater of
15 to 50 Ltrs.capacity.
a) Material
Pressure release valve for 25 to 50 Ltrs water heater each 1.00
b) Labour charges.
Skilled Electrician day 0.20
Sundries and rounding off LS
Rate per Each
Bldngs_Elec-11 11 WATER PUMPS
Bldngs_Elec-11-1 11.1 Mono-Block Pumps
11.1.1 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 230V, Single
phase, 50Hz.. 1440 RPM A.C.Supply of 0.5HP exculding suction / delivery
pipe with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
0.5HP, 230V, single phase A.C 50Hz. 1440 RPM with all accessories. each 1.00
Including all taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 0.50
Helper day 1.00
Plumber day 0.50
Sundries and rounding off LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.1.2 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 230V, Single
phase, 50Hz.. 1440 RPM A.C.Supply of 1HP exculding suction / delivery
pipe with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
1 HP, 230V, single phase A.C 50Hz. 1440 RPM with all accessories. each 1.00
Including all taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 0.50
Helper day 1.00
Plumber day 0.50
Sundries and rounding off LS
Rate per Each
11.1.3 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 230V, Single
phase, 50Hz.. 1440 RPM A.C.Supply of 1.5 HP exculding suction /
delivery pipe with nuts duly grouted on existing C.C foundation and bolts,
spring washers of requisite size for monoblock motor and pump (IS :
9079).
a) Material
1.5 HP, 230V, single phase A.C 50Hz. 1440 RPM with all accessories. each 1.00
Including all taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges.
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Skilled Fitter day 0.50
Helper day 1.00
Plumber day 0.50
Sundries and rounding off LS
Rate per Each
11.1.4 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 230V, Single
phase, 50Hz.. 1440 RPM A.C.Supply of 2.0 HP exculding suction /
delivery pipe with nuts duly grouted on existing C.C foundation and bolts,
spring washers of requisite size for monoblock motor and pump (IS :
9079).
a) Material
2 HP, 230V, single phase A.C 50Hz. 1440 RPM with all accessories. each 1.00
Including all taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 0.50
Helper day 1.00
Plumber day 0.50
Sundries and rounding off LS
Rate per Each
11.1.5 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 415V, 3 phase,
50Hz.. 2880 RPM A.C.Supply of 3.0HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
3 phase, 3 HP, 415V, 50Hz., 2880 RPM centrifugal Water pump with all each 1.00
taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 1.00
Plumber day 1.00
Sundries and rounding off LS
Rate per Each
11.1.6 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 415V, 3 phase,
50Hz.. 2880 RPM A.C.Supply of 5HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
3 phase, 5 HP, 415V, 50Hz., 2880 RPM centrifugal Water pump with all each 1.00
taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 1.00
Plumber day 1.00
Sundries and rounding off LS
Rate per Each
11.1.7 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 415V, 3 phase,
50Hz.. 2880 RPM A.C.Supply of 7.5HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
3 phase, 7.5 HP, 415V, 50Hz., 2880 RPM centrifugal mono block pump each 1.00
with all taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 1.00
Plumber day 1.00
Sundries and rounding off LS
Rate per Each
11.1.8 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 415V, 3 phase,
50Hz.. 2880 RPM A.C.Supply of 10HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
3 phase, 10 HP, 415V, 50Hz., 2880 RPM centrifugal mono block pump each 1.00
with all taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 1.00
Plumber day 1.00
Sundries and rounding off LS
Rate per Each
11.1.9 Supply and erecting approved make centrifugal water pump with impeller,
priming funnel cork, companion metallic flanges, with bolts and nuts and
mounted on a common shaft of high efficient squirrel cage Induction motor
totally enclosed and fan cooled type suitable to operate on 415V, 3 phase,
50Hz.. 2880 RPM A.C.Supply of 15HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C foundation and bolts, spring
washers of requisite size for monoblock motor and pump (IS : 9079).
a) Material
3 phase, 15 HP, 415V, 50Hz., 2880 RPM centrifugal Water pump with all each 1.00
taxes
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 3.00
Plumber day 1.00
Sundries and rounding off LS
Rate per Each
Bldngs_Elec-11-2 11.2 EJECTO PUMPS
11.2.1 Supply and erecting Ejecto type water pump single phase, 0.5HP single
stage with brass venturi and having suction pipe 40mm dia, pressure pipe
32mm dia and delivery pipe 32mm dia, with maximum discharge head of
80 feet including transportation of all materials and labour charges etc.,
complete.
a) Material
0.5 HP, single phase, 230V, 50Hz. Ejecto type pump set. Including all each 1.00
taxes
M.S clamps suitable for 40mmx32mm pipes with nuts and bolts. each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Electrician day 0.50
Helper day 1.00
Fitter day 0.50
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.2.2 Supply and erecting Ejecto type water pump single phase, 1.0HP single
stage with brass venturi and having suction pipe 40mm dia, pressure pipe
32mm dia and delivery pipe 32mm dia, with maximum discharge head of
80feet including transportation of all materials and labour charges etc.,
complete.
a) Material
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
1.0 HP, single phase, 230V, 50Hz. Ejecto type pump set. Including all each 1.00
taxes
M.S clamps suitable for 40mmx32mm pipes with nuts and bolts. each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Electrician day 0.50
Helper day 1.00
Fitter day 0.50
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.2.3 Supply and erecting Ejecto type water pump single phase, 1.5HP single
stage with brass venturi and having suction pipe 40mm dia, pressure pipe
32mm dia and delivery pipe 32mm dia, with maximum discharge head of
80 feet including transportation of all materials and labour charges etc.,
complete.
a) Material
1.5 HP, single phase, 230V, 50Hz. Ejecto type pump set. Including all each 1.00
taxes
M.S clamps suitable for 40mmx32mm pipes with nuts and bolts. each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Electrician day 0.50
Helper day 1.00
Fitter day 0.50
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.2.4 Supply and erecting Ejecto type water pump single phase, 2.0HP single
stage with brass venturi and having suction pipe 40mm dia, pressure pipe
32mm dia and delivery pipe 32mm dia, with maximum discharge head of
80 feet including transportation of all materials and labour charges etc.,
complete.
a) Material
2.0 HP, single phase, 230V, 50Hz. Ejecto type pump set. Including all each 1.00
taxes
M.S clamps suitable for 40mmx32mm pipes with nuts and bolts. each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Electrician day 0.50
Helper day 1.00
Fitter day 0.50
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.2.6 Supply and erecting Ejecto type water pump 3 phase, 3 HP single stage
with brass venturi and having suction pipe, pressure pipe and delivery
pipe, with maximum discharge head of 80 feet , including transportation,
and all materials all labour charges etc., complete.
a) Material
3.0 HP, single phase, 230V, 50Hz. Ejecto type pump set. Including all each 1.00
taxes
M.S clamps suitable for 40mmx32mm pipes with nuts and bolts. each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Electrician day 0.50
Helper day 1.00
Fitter day 0.50
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.2.7 Supply and erecting Ejecto type water pump 3 phase, 5 HP single stage
with brass venturi and having suction pipe, pressure pipe and delivery
pipe, with maximum discharge head of 80', including transportation, and
all materials all labour charges etc., complete.
a) Material
3Ph, 5 HP 415V, 50Hz. Ejecto pump set with all taxes each 1.00
M.S clamps suitable for Air and delivery pipes with nuts and bolts. each 2.00
Transportation Charges on Unit Cost 0.02
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 0.50
Helper day 1.50
Plumber day 0.50
Sundries and rouding off LS
Rate per Each
Note : Labour is Considered for 2 jobs / day
Bldngs_Elec-11-3 11.3 SUBMERSIBLE PUMPS (Bore well type)
11.3.1 Supply and erecting, ISI mark submersible 1.0 HP,Single Phase
(a) 18stages pumpset suitable for 106 / 156mm dia borewell with high quality
water resistant and dynamically balanced bronze impeller with stainless
steel shaft sleeves, pump coupling and pivot of Single phase 250V, 50Hz..
A.C. power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
1HP, Single Phase 18 stage submerisible pump set including all taxes each 1.00
a) Material
1.5HP, Single Phase 20 stage submerisible pump set including all taxes each 1.00
a) Material
2HP, Single Phase 30 stage submerisible pump set including all taxes each 1.00
1 2 3 4 5 6 7
Note : Labour is Considered for 2 jobs / day
11.3.2 Supply and erecting, ISI mark submersible 2.0 HP, 3 Phase, 3 stages
pumpset suitable for 156mm dia borewell with high quality water resistant
and dynamically balanced bronze impeller with stainless steel shaft
sleeves, pump coupling and pivot of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water proof insulation and high precision
strength not to be effected by chemical in water and suitable bronze
bearings with nut and bolts etc., with necessary H-type clamp of suitable
size and strength.
a) Material
2HP, 3 Ph 3 stage submerisible pump set including all taxes each 1.00
Special M.S. clamps with bolts and nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.3 Supply and erecting, ISI mark submersible 3.0 HP,3 Phase, 4 stages
pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V , 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
3HP, 3 Ph 4 stage submerisible pump set. Including all taxes each 1.00
Special M.S. clamps with bolts and nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.4 Supply and erecting, ISI mark submersible 3 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V , 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump set. Including all taxes each 1.00
Special M.S. clamps with bolts and nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.5 Supply and erecting, ISI mark submersible 3 HP, 3 Phase, 8 stages
pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V , 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump set. Including all taxes each 1.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Special M.S. clamps with bolts and nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.6 Supply and erecting, ISI mark submersible 3 HP, 3 Phase, 9 stages
pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V , 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump set Including all taxes each 1.00
Special M.S. clamps with bolts and nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.7 Supply and erecting, ISI mark submersible 4 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V, 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
4HP, 3 Ph 6 stage submerisible pump set including all taxes each 1.00
Special M.S. clamps with bolts and nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.8 Supply and erecting, ISI mark submersible 4 HP, 3 Phase, 12 stages
pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V, 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
4HP, 3 Ph 12 stages submerisible pump set Including all taxes each 1.00
Special M.S. clamps with bolts and nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
11.3.1 Supply and erecting, ISI mark submersible 5 HP, 3 Phase, 8 stages
0 pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V, 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
Cost of 3 Ph, 5 HP, 8 St. S.M pumpset each 1.00
Special Clamps with Bolts & Nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 2.00
Helper day 3.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.1 Supply and erecting, ISI mark submersible 5 HP, 3 Phase, 13 stages
1 pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V , 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
Cost of 3 Ph, 5 HP, 8 St. S.M pumpset each 1.00
Special Clamps with Bolts & Nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 2.00
Helper day 3.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.1 Supply and erecting, ISI mark submersible 7.5 HP,3 Phase, 6 stages
2 pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V, 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
3 Ph, 7.5 HP, 6 St. S.M pumpset each 1.00
Special Clamps with Bolts & Nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 2.00
Helper day 3.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.1 Supply and erecting, ISI mark submersible 7.5 HP, 3 Phase, 12 stages
3 pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V , 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
3 Ph, 7.5 HP, 12 St. S.M pumpset each 1.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Special Clamps with Bolts & Nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 2.00
Helper day 3.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.1 Supply and erecting, ISI mark submersible 10 HP,3 Phase, 12 stages
5 pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V, 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
Cost of 3 Ph,10 H.P 12St. S.M pumpset each 1.00
Special Clamps with Bolts & Nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 2.00
Helper day 3.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.1 Supply and erecting, ISI mark submersible 10 HP,3 Phase,16 stages
6 pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V, 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
Cost of 3 Ph,10 H.P 16 St. S.M pumpset each 1.00
Special Clamps with Bolts & Nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 2.00
Helper day 3.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.1 Supply and erecting, ISI mark submersible 15 HP, 3 Phase, 15 stages
7 pumpset suitable for 156mm dia borewell with high quality wear
resistance and dynamically balanced bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot of 3 phase 415V, 50Hz.. A.C.
power supply copper winding with water proof insulation and high
precision strength not to be effected by chemical in water and suitable
bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
Cost of 3 Ph,15 H.P 15 St. S.M pumpset each 1.00
Special Clamps with Bolts & Nuts each 2.00
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 2.00
Helper day 4.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
Bldngs_Elec-11-4 11.4 SUB MERSIBLE PUMPS (OPEN WELL)
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
11.4.1 Supply and erecting ISI make submersible pumpset suitable for erection
in open well with water resistant dynamically balanced impeller with
stainless steel shaft sleeves, pump coupling and pivot with squirrel cage
Induction Motor of 3 phase, 415V, 50Hz.., A.C.Supply, heavy copper
windings with water proof insulation and high precision strength not to be
effected by chemicals in water with suitable bronze bearings, 3 HP pump
erected with necessary H-type clamps of suitable size and strength
including cost of all materials, Transportation and labour charges etc.,
complete.
a) Material
3 Ph, 3HP Submersible motor each 1.00
Special clamps with nut and bolis each 2.00
MS Girders across the open well to support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.4.2 Supply and erecting ISI make submersible pumpset suitable for erection
in open well with water resistant dynamically balanced impeller with
stainless steel shaft sleeves, pump coupling and pivot with squirrel cage
Induction Motor of 3 phase, 415V, 50Hz.., A.C.Supply, heavy copper
windings with water proof insulation and high precision strength not to be
effected by chemicals in water with suitable bronze bearings, 5 HP pump
erected with necessary H-type clamps of suitable size and strength
including cost of all materials, Transportation and labour charges etc.,
complete.
a) Material
3 Ph, 5HP Submersible motor each 1.00
Special clamps with nut and bolis each 2.00
MS Girders across the open well to support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
11.4.3 Supply and erecting ISI make submersible pumpset suitable for erection
in open well with water resistant dynamically balanced impeller with
stainless steel shaft sleeves, pump coupling and pivot with squirrel cage
Induction Motor of 3 phase, 415V, 50Hz.., A.C.Supply, heavy copper
windings with water proof insulation and high precision strength not to be
effected by chemicals in water with suitable bronze bearings, 7.5 HP
pump erected with necessary H-type clamps of suitable size and strength
including cost of all materials, Transportation and labour charges etc.,
complete.
a) Material
3 Ph, 7.5HP Submersible motor each 1.00
Special clamps with nut and bolis each 2.00
MS Girders across the open well to support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 2.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
11.4.4 Supply and erecting ISI make submersible pumpset suitable for erection
in open well with water resistant dynamically balanced impeller with
stainless steel shaft sleeves, pump coupling and pivot with squirrel cage
Induction Motor of 3 phase, 415V, 50Hz.., A.C.Supply, heavy copper
windings with water proof insulation and high precision strength not to be
effected by chemicals in water with suitable bronze bearings, 10 HP pump
erected with necessary H-type clamps of suitable size and strength
including cost of all materials, Transportation and labour charges etc.,
complete.
a) Material
3 Ph, 10 HP Submersible motor each 1.00
Special clamps with nut and bolis each 2.00
MS Girders across the open well to support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost 0.02
b) Labour charges for erection of pump set including pipe
connection for suction & delivery
Skilled Fitter day 1.00
Helper day 3.00
Plumber day 1.00
Hire charges of tripod with winch 50% of Labour charges
Sundries and rouding off LS
Rate per Each
Note:- Above rates of pumpsets are exculding suction & delivery
pipes
Bldngs_Elec-11-5 11.5 ACCESSORIES
11.5.1 Providing cement concrete with 1:2:4 foundation for pump and motor with
required size and length of foundation bolts and nuts including cost and
conveyance of all materials and labour charges etc., complete.
a) Material
Rate as per Civil SSR, since it is a Civil item.
11.5.2 Supplying and erecting D.O.L Starter 250V, Single phase, 50Hz. With SS
enclouser comprising of contactor with bi-metalic relay with necessary
push buttons, transportation and all labour charges etc., complete .
a) Material
D.O.L. Starter 1Ph, 250V each 1.00
b) Labour charges for fixing and giving connections.
Skilled Electrician day 0.33
Helper day 0.33
Sunries such, as bolts, nuts and rounding off
Rate per Each
Note : Labour is Considered for 3 jobs / day
11.5.2( Supplying and erecting D.O.L Starter 400V, 3 phase, 50Hz. enclosed with
a) no volt coil and overload protection with necessary materials,
transportation and all labour charges etc., complete suitable upto 3/4/5
HP.
a) Material
D.O.L. Starter 3Ph, 415V upto 3/4/5HP each 1.00
b) Labour charges for fixing and giving connections.
Skilled Electrician day 0.33
Helper day 0.33
Sunries such, as bolts, nuts and rounding off
Rate per Each
Note : Labour is Considered for 3 jobs / day
11.5.3 Supply and fixing of approved make semi automatic hand operated 3ph,
415V star - delta started suitable from 7.5 HP upto 15 HP motor totally
enclosed with over load protection and No-volt relay etc., to complete
including Transportation and all labour charges.
a) Material
Semi automatic 3Ph, Induction motor with enclosure (Including of all taxes each 1.00
with Transportation)
b) Labour charges for fixing and giving connections.
Skilled Electrician day 0.50
Helper day 0.50
Sunries such, as bolts, nuts and rounding off
Rate per Each
Note : Labour is Considered for 2 jobs / day
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
11.5.4 Supply and fixing of approved make semi automatic hand operated 3ph,
415V star - delta started suitable upto 15 to 25 HP motor totally enclosed
with over load protection and No-volt relay etc., to complete including
Transportation and all labour charges.
a) Material
Deduct
Cost of semi Automatic star - Delta starter each 1.00
Semi automatic 3Ph, Induction motor with enclosure (Including of all taxes each 1.00
with Transportation)
b) Labour charges.
Skilled Electrician day 0.50
Helper day 0.50
Sunries such, as bolts, nuts and rounding off
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.5.5 Supply and fixing of approved make automatic operated 3ph, 415V star -
delta started suitable 10 to 12.5 HP automatic star delta starter motor
totally enclosed with over load protection and No-volt relay to complete
including Transportation and all labour charges .
a) Material
Cost of semi Automatic star - Delta starter each 1.00
Semi automatic 3Ph, Induction motor with enclosure (Including of all taxes each 1.00
with Transportation)
b) Labour charges.
Skilled Electrician day 0.50
Helper day 0.50
Sunries such, as bolts, nuts and rounding off
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.5.6 Supply and fixing of approved make semi automatic hand operated 3ph,
415V star - delta started suitable for 15 HP fully automatic star delta
motor totally enclosed with over load protection and No-volt relay to
complete including Transportation and all labour charges.
a) Material
Cost of semi Automatic star - Delta starter each 1.00
Semi automatic 3Ph, Induction motor with enclosure (Including of all taxes each 1.00
with Transportation)
b) Labour charges.
Skilled Electrician day 0.50
Helper day 0.50
Sunries such, as bolts, nuts and rounding off
Rate per Each
Note : Labour is Considered for 2 jobs / day
11.5.7 Supply and erecting directly operated single phasing preventer connected
to A.C. supply upto 45A range with guarantee to operate on single phase
for one Year.
a) Material
Single phase parameter upto 45A (Including all taxes and Transportation) each 1.00
b) Labour charges.
Skilled Electrician day 0.20
Helper day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
Bldngs_Elec-12 12 Bus Bars
For details, Please see after Chapter 20.
Bldngs_Elec-13 13 SWAGED POLES (Confirming to IS 2713 / 1980).
13.1 Fabrication, supply and transportation of swaged poles up to site
confirming to IS 2713 / 1980 specifications. The pole should be painted
Bldngs_Elec-13-1 with primary coat of red oxide and black bituminous paint up to ground
level with base plate, including cost of all materials etc., complete.
a) Material
Cost of swaged pole
Add: Labour for handling
Transportation charges, loading unloading as per Common SSR taking
250Km as average load considering fabrication point at hyd and
Visakhapatnam.
Transportation charges upto 250Km Breakup.
P.No. 156 of Common SSR (Civil)
Upto 20 Km 163.80 / Tonne
Upto 50 Km 3.40 x 10
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Upto 80 Km 2.80 x 50
Beyond 106 Km 2.20 x 156
Loading 15.50 / Tonne
Unloading 12.00 / Tonne
Stacking 7.00 / Tonne
Rate per Kg
Data
No. Length
Specification of pole Overall length of pole. Planting of
as per IS 2713 / 1980 depth in Section Middle Top
mtrs. s
In Mtrs.
Bottom 5b 5c
1 2 3 4 5a 1.50 1.50
13.1.1 410 SP.2 7 Mtrs. 1.25 4.00 1.50 1.50
13.1.2 410 SP.3 7 Mtrs. 1.25 4.00 1.50 1.50
13.1.3 410 SP.5 7.5 Mtrs. 1.25 4.50 1.50 1.50
13.1.4 410 SP.6 7.5 Mtrs. 1.25 4.50 1.75 1.75
13.1.5 410 SP.11 8 Mtrs. 1.50 4.50 1.75 1.75
13.1.6 410 SP.12 8 Mtrs. 1.50 4.50 2.00 2.00
13.1.7 410 SP.26 9 Mtrs. 1.50 5.00 2.00 2.00
13.1.8 410 SP.27 9 Mtrs. 1.50 5.00 2.40 2.40
13.1.9 410 SP.41 10 Mtrs. 1.80 5.20 2.40 2.40
13.1.10 410 SP.42 10 Mtrs. 1.80 5.20 2.70 2.70
13.1.11 410 SP.50 11 Mtrs. 1.80 5.60 2.70 2.70
13.1.12 410 SP.51 11 Mtrs. 1.80 5.60 3.10 3.10
13.1.13 410 SP.59 12 Mtrs. 2.00 5.80 3.10 3.10
13.1.14 410 SP.60 12 Mtrs. 2.00 5.80 4.00 4.00
13.1.15 410 SP.73 14.5 Mtrs. 2.00 6.50 4.00 4.00
13.1.16 410 SP.74 14.5 Mtrs. 2.00 6.50 4.50 4.50
13.1.17 410 SP.77 16 Mtrs. 2.30 7.00 4.50 4.50
13.1.18 410 SP.78 16 Mtrs. Rate/ Kg
including
Transporta Total cost
tion and of pole
Fabricatio
n
2.30 7.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
O.D Weight of Total
and Base weight
thickn plate in Kgs.
ess in Kgs.
Weigh
t of
Pole
in Kgs
1 2 3 4 5 6 7
13.3.1 Supply and fixing of 50mm dia 0.5 mtrs single arm M.S. pipe bracket with
sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire.
a) Material
0.5Mtr length 50mm 'B' class pipe. Kg 2.55
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and enamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.20
Fitter day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
13.3.2 Supply and fixing of 50mm dia 0.5 mtrs double arm M.S. pipe bracket
with sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire
a) Material
2 x 0.5Mtr length 50mm 'B' class pipe. Kg 5.10
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and enamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.33
Fitter day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs / day
13.3.3 Supply and fixing of 50mm dia 0.5 mtrs triple arm M.S. pipe bracket with
sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire.
a) Material
3 x 0.5Mtr length 50mm 'B' class pipe. Kg 7.65
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and enamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.50
Fitter day 0.50
Rate per Each
Note : Labour is Considered for 2 jobs / day
13.3.4 Supply and fixing of 50mm dia 1 mtrs single arm M.S. pipe bracket with
sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire
a) Material
1Mtr length 50mm 'B' class M.S pipe. Kg 5.10
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.20
Fitter day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
13.3.5 Supply and fixing of 50mm dia 1 mtrs double arm M.S. pipe bracket with
sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire.
a) Material
2 x 1Mtr length 50mm 'B' class M.S pipe. Kg 10.20
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.33
Helper day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs / day
13.3.6 Supply and fixing of 50mm dia 1 mtrs triple arm M.S. pipe bracket with
sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire.
a) Material
3 x 1Mtr length 50mm 'B' class M.S pipe. Kg 15.30
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Skilled Electrician day 0.50
Helper day 0.50
Rate per Each
Note : Labour is Considered for 2 jobs / day
13.3.7 Supply and fixing of 50mm dia 1.5 mtrs single arm M.S. pipe bracket with
sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire.
a) Material
1.5 Mtr length 50mm 'B' class M.S pipe. Kg 7.65
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.20
Helper day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
13.3.8 Supply and fixing of 50mm dia 1.5 mtrs double arm M.S. pipe bracket
with sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire.
a) Material
2 x 1.5Mtr length 50mm 'B' class M.S pipe. Kg 15.30
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.33
Helper day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs / day
13.3.9 Supply and fixing of 50mm dia 1.5 mtrs triple arm M.S. pipe bracket with
sleeve and fasteners with necessary angle including painting etc.,
complete on existing pole including fixing of luminaire.
a) Material
3 x 1.5Mtr length 50mm 'B' class M.S pipe. Kg 22.95
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.50
Helper day 0.50
Rate per Each
Note : Labour is Considered for 2 jobs / day
13.3.1 Supply and fixing of 50mm dia 1.5 mtrs curved single arm M.S. pipe
0 bracket with sleeve and fasteners with necessary angle including painting
etc., complete on existing pole including fixing of luminaire.
a) Material
1.5 Mtr length 50mm 'B' class M.S pipe. Kg 7.65
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.20
Helper day 0.20
For Moulding & making Suitable curve on length job 1.00
Rate per Each
Note : Labour is Considered for 5 jobs / day
13.3.1 Supply and fixing of 50mm dia 1.5 mtrs curved double arm M.S. pipe
1 bracket with sleeve and fasteners with necessary angle including painting
etc., complete on existing pole including fixing of luminaire.
a) Material
2 x 1.5 Mtr length 50mm 'B' class M.S pipe. Kg 15.30
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.33
Helper day 0.33
For Moulding & making Suitable curve on length job 1.00
Rate per Each
Note : Labour is Considered for 3 jobs / day
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
13.3.1 Supply and fixing of 50mm dia 1.5 mtrs curved triple arm M.S. pipe
2 bracket with sleeve and fasteners with necessary angle including painting
etc., complete on existing pole including fixing of luminaire.
a) Material
3 x 1.5 Mtr length 50mm 'B' class M.S pipe. Kg 22.95
45cm length , 10cm dia and cap. Kg 5.40
Painting with red oxid and anamel paint. job 1.00
b) Labour charges for fixing with Spl. T & P
Skilled Electrician day 0.50
Helper day 0.50
For Moulding & making Suitable curve on length job 1.00
Rate per Each
Note : Labour is Considered for 2 jobs / day
Bldngs_Elec-13-4 13.4 Erection Charges for Swaged Poles
13.4.1 Erection charges for 7 mtrs. to 8 mts long swaged pole including
excavation of pit, coil earthing, hire charges of special T&P painting of
Pole CC 1:3:6 upto ground and 1:2:4 for Couping work, including labour
and transportation charges etc., complete
a) Material
Pit excavation 156 Cmx 60Cmx60cm.(Civil SSR) cum 0.54
C.C.work for pit 1:3:6 (Civil SSR) cum 0.54
Couping 1:2:4 (Civil SSR) cum 0.05
Painting with red oxid and enamel paint. M 6.20
Coil earthing each 1.00
b) Labour charges
Skilled Electrician day 0.33
Helper day 2.67
Mason day 0.33
Hire charges for Spl.T&P 40% on labour cost
Rate per Each
Note : Labour is Considered for 3 jobs / day
13.4.2( Erection charges for 9 mtrs to 11 mtrs long swaged pole including
a) excavation of pit, coil earthing, hire charges of special T&P painting of
Pole CC 1:3:6 upto ground and 1:2:4 for Couping work, including labour
and transportation charges etc., complete.
a) Material
Pit excavation 156 Cmx 60Cmx60cm.(Civil SSR) cum 0.72
C.C.work for pit 1:3:6 (Civil SSR) cum 0.72
Couping 1:2:4 (Civil SSR) cum 0.05
Painting with red oxid and enamel paint. M 8.35
Coil earthing each 1.00
b) Labour charges
Skilled Electrician day 0.33
Helper day 2.67
Mason day 0.33
Hire charges for Spl.T&P 40% on labour cost
Rate per Each
Note : Labour is Considered for 3 jobs / day
13.4.2( Erection charges for 12 Mts to 14Mts long swaged pole including
b) excavation of pit, coil earthing, hire charges of special T&P
(Crane)painting of Pole CC 1:3:6 upto ground and 1:2:4 for Couping
work, including labour and transportation charges etc., complete.
a) Material
Pit excavation 2.0x1.0x1.0Mtr cum 2.00
1:3:6 CC Work cum 2.00
couping 1:2:4 cum 0.05
Painting with red oxid and alluminum paint. M 12.00
Coil earthing each 1.00
b) Labour charges
Skilled Electrician day 0.50
Helper day 4.00
Mason day 0.50
Hire charges for Spl.T&P 20% on labour cost
Rate per Each
Note : Labour is Considered for 2 jobs / day
13.4.3 Erection charges for 16Mts long swaged pole including excavation of pit,
coil earthing, hire charges of special T&P (Crane)painting of Pole CC
1:3:6 upto ground and 1:2:4 for Couping work, including labour and
transportation charges etc., complete.
a) Material
Pit excavation 2.30x1.0x1.0Mtr cum 2.30
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
1:3:6 CC Work cum 2.30
couping 1:2:4 cum 0.05
Painting with red oxid and alluminum paint. M 14.00
Coil earthing each 1.00
b) Labour charges
Skilled Electrician day 0.50
Helper day 4.00
Mason day 0.50
Hire charges for Spl.T&P 20% on labour cost
Rate per Each
Note : Labour is Considered for 2 jobs / day
13.4.4 Erection charges for 7to 9Mts long swaged pole on bridge kerb portion
( R.C.C. work with V.C.C. M.15 concrete with 3 Nos 25x6 mm MS Special
clamps bolts with nuts and locking nuts etc.including cost and con
veyance of all material and all labour charges etc. complete with painting.
a) Material
Painting with red oxid and enamel paint. M 6.20
Coil earthing each 1.00
3 Nos, 25 x 6 mm MS Special Clamps of 1 M Length each @ 1.18 Kg Kg 3.54
a) Material
50mm 'B' class MS pipe of 5.7mts (1Mt=5.106Kgs) Kg 29.07
40mm 'B' glass pipe MS pipe of 3.6Mtr (1Mt=3.61Kgs) Kg 13.00
200mm MS pipe for pole cap.C-Class (heavy) 0.3Mts (1Mt=31Kgs) Kg 13.00
1 2 3 4 5 6 7
Note : Labour is Considered for 2 jobs / day
Bldngs_Elec-13-5 13.5 Accessories
13.5.1 Supply and fixing of 300mm x 260mm x 140mm No.16 gauge CRCA
sheet box with hinged door and locking arrangements and din channel for
fixing 2Nos MCBs duly powder coated with matching colour of poles
including fixing with necessary arrangments etc., complete.
a) Material
300x260x140mm 16 guage CRCA box finished of item(as per 14.1.2) sqm 0.35
a) Material
300x180x140mm 16 guage CRCA sheet box as per 14.1.2 sqm 0.29
Sundries as rounding off
Rate per Each
13.5.3 Supply and fixing of 1 No.10A SP MCB in existing M.S. box with Din
channel, 4way 63A connector including cost & conveyance of all materials
and labour charges etc., complete.
a) Material
10A SP MCB each 1.00
4Way connector. each 1.00
b) Labour charges
Skilled Electrician day 0.07
Rate per Each
Note : Labour is Considered for 15 jobs / day
13.5.4 Supply and fixing of 2 Nos 10A SP MCBs in existing M.S box with Din
channel, 4way 63A connector including cost & conveyance of all materials
and labour charges etc., complete.
a) Material
10A SP MCB each 2.00
4Way connector. each 1.00
b) Labour charges
Skilled Electrician day 0.07
Sundries such as screws, tape
Rate per Each
Bldngs_Elec-14 14 CONTROL PANEL AND METERING EQUIPMENT
Bldngs_Elec-14-1 14.1 CONTROL PANEL
14.1.1 Supply, Transportation, fabrication and erection of following guage CRCA
sheet steel enclosure for power control cubicle panel / boxes etc.,
including cutting, bending drilling, welding and reveting etc., complete
with cleaning with 7 tank process and painting with powder coating
including cost and conveyance of all materials and labour charges.
1 2 3 4 5 6 7
a) Material
18 SWG (2mm) CRCA sheet - 1 sft (Wt of 8 x 4 feet sheet, 30Kg) kg 0.94
Transportation charges 0.02
Fabrication including cutting, bending, drilling and Dust proof arrnagments 0.30
etc.,
Cleaning of cubicals in seven tank process 0.40
Painting with powder coating. 0.40
Erection charges 0.30
Sundires such as hardware etc.,
Rate per sft
Rate per sqm
Bldngs_Elec-14-2 14.2 METERING EQUIPMENT
14.2.1 Supply and erection of 0-500V volt meter of size 96x96mm on exisiting
box / panel board including connections etc., complete.
a) Material
0-500 Voltmeter Analog / Degital inclusive of all Taxes. each 1.00
b) Labour charges for fixing & Connections
Skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
14.2.2 Supply and erection of 0-100 / 200 / 400 / 600 /1000 - 5A CT Ammeter of
size 96x96mm on existing box / panel board including connections etc.,
complete.
a) Material
96 x 96mm size Ammeter Analog / Degital inclusive of all Taxes each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.20
Rate per Each
14.2.3 Supply and erection of frequency meter of size 96x96mm on existing
box / panel board including connections etc., complete.
a) Material
Frequency meter Analog / Degital inclusive of all Taxes. each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.20
Rate per Each
14.2.4 Supply and erection of power factor meter, 3 phase, 4 wire balanced or
unbalanced load 5A, 415V of size 96x96mm on existing box / panel board
including connections etc., complete.
a) Material
Power Factor meter Analog / Degital inclusive of all Taxes. each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.20
Rate per Each
14.2.5 Supply and erection of L.T. 3phase multifunction energy meter with 3 lines
LCD display of size 96x96mm for measuring all the parameters (voltage /
Current / Power / frequency / power factor / KW / KWH / KVAR/ KVARH)
on existing box panel board including connections etc., complete.
a) Material
L.T. 3 Ph. Multifunction energy meter Analog / Degital inclusive of all each 1.00
Taxes.
b) Labour charges for fixing and connections.
Skilled Electrician day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs / day
14.2.6 Supply and erection of selector switch for voltmeter / Ammeter on the
existing box / panel including connections etc., complete.
a) Material
Selector switch for Ammeter / Voltmeter. each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.20
Rate per Each
Note : Labour is Considered for 5 jobs / day
14.2.7 Supply and erection of LED indicator lamps on the existing box / panel
board.
a) Material
LED indicator lamp Analog each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.10
Rate per Each
Note : Labour is Considered for 10 jobs / day
14.2.8 Supply and erection of LT current transformer with bar primary 100/5A to
1000 / 5A ratio in the existing box / panel including connections etc.,
complete.
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
L.T. C.T with bar primary 100 / 5A to 1000 / 5A each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.10
Rate per Each
Note : Labour is Considered for 10 jobs / day
14.2.9 Supply and fixing of single phase energy Meter,240V AC,50 HZ as per
IS13010 with 2.5-5 /5-10/10-20 Amps range with 200% over load capacity
complete with connections etc., complete on the existing board.
a) Material
cost of single phase energy meter each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.33
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs / day
14.2.1 Supply and fixing of three phase energy Meter,415V AC,50 HZ as per
0 IS13010 with 2.5-5 /5-10/10-20 Amps range with 200% over load capacity
complete with connections etc., complete on the existing board.
a) Material
Cost of three phase energy meter each 1.00
b) Labour charges for fixing and connections.
Skilled Electrician day 0.33
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs / day
Bldngs_Elec-15 15 CABLES / CABLE GLANDS / LUGS
Bldngs_Elec-15-1 15.3 CABLE GLANDS
15.3.1 Supply and Fixing of heavy duty flange type brass cable glands for 2 to 4
core, 2.5 Sq.mm to 6 Sq.mm PVC armoured cable with brass washers
complete.
a) Material
Brass cable gland for 2-4 core, 2.5 Sqmm to 6 Sq.mm armoured cable each 1.00
a) Material
Brass cable gland for 2-4 core, 10 Sqmm armoured cable each 1.00
b) Labour charges for fixing glands.
Semi skilled Electrician day 0.07
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15 jobs / day
15.3.3 Supply and Fixing of heavy duty flange type brass cable glands for 4 core,
16 Sq.mm / 3.5 core 25Sq.mm PVC armoured cable with brass washers
complete.
a) Material
Brass cable gland suitabtle for 4core 16 Sq.mm / 3.5 core 25 Sq.mm each 1.00
armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.07
Sundireis and Rounding off
Rate per Each
15.3.4 Supply and Fixing of heavy duty flange type brass cable glands for 3.5
core, 35 Sq.mm / 3.0 core 50Sq.mm PVC armoured cable with brass
washers complete.
a) Material
Brass cable gland suitabtle for 3.5core 35 Sq.mm / 3 core 50 Sq.mm each 1.00
armoured cable
b) Labour charges for fixing glands.
Skilled Electrician day 0.07
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15 jobs / day
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
15.3.5 Supply and Fixing of heavy duty flange type brass cable glands for 3.5
core, 50 Sq.mm PVC armoured cable with brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core 50 Sq.mm armoured cable each 1.00
a) Material
Brass cable gland suitabtle for 3.5core 70Sq.mm armoured cable each 1.00
a) Material
Brass cable gland suitabtle for 3.5core 95 Sq.mm armoured cable each 1.00
a) Material
Brass cable gland suitabtle for 3.5core 120 Sq.mm armoured cable each 1.00
a) Material
Brass cable gland suitabtle for 3.5core 150 Sq.mm armoured cable each 1.00
a) Material
Brass cable gland suitabtle for 3.5core 185 Sq.mm armoured cable each 1.00
1 2 3 4 5 6 7
a) Material
Brass cable gland suitabtle for 3.5core 240 Sq.mm armoured cable each 1.00
a) Material
Brass cable gland suitabtle for 3.5core 300 Sq.mm armoured cable each 1.00
a) Material
Brass cable gland suitabtle for 3.5core 400 Sq.mm armoured cable each 1.00
1 2 3 4 5 6 7
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75 jobs / day
15.4.5 Supply and fixing of crimping type copper lugs confirming to I.S
specifications for cable of 70Sq.mm including nuts and bolts with
connections.
a) Material
Copper Lugs upto 70 Sq.mm. each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75 jobs / day
15.4.6 Supply and fixing of crimping type copper lugs confirming to I.S
specifications for cable of 95 Sq.mm including nuts and bolts with
connections.
a) Material
Copper Lugs up to 95 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.02
Helper day 0.02
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 60 jobs / day
15.4.7 Supply and fixing of crimping type copper lugs confirming to I.S
specifications for cable of 120 Sq.mm including nuts and bolts with
connections.
a) Material
Copper Lugs up to 120 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.02
Helper day 0.02
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 50 jobs / day
15.4.8 Supply and fixing of crimping type copper lugs confirming to I.S
specifications for cable of 150 Sq.mm including nuts and bolts with
connections.
a) Material
Copper Lugs up to 150 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.03
Helper day 0.03
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 30 jobs / day
15.4.9 Supply and fixing of crimping type copper lugs confirming to I.S
specifications for cable of 185 Sq.mm including nuts and bolts with
connections.
a) Material
Copper Lugs up to 185 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.03
Helper day 0.03
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 30 jobs / day
15.4.1 Supply and fixing of crimping type copper lugs confirming to I.S
1 specifications for cable of 240 Sq.mm including nuts and bolts with
connections.
a) Material
Copper Lugs up to 240 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25 jobs / day
15.4.1 Supply and fixing of crimping type copper lugs confirming to I.S
2 specifications for cable of 300 Sq.mm including nuts and bolts with
connections.
a) Material
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Copper Lugs up to 300 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.05
Helper day 0.05
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 20 jobs / day
15.4.1 Supply and fixing of crimping type copper lugs confirming to I.S
3 specifications for cable of 400 Sq.mm including nuts and bolts with
connections.
a) Material
Copper Lugs up to 400 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.06
Helper day 0.06
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 16 jobs / day
15.4.1 Supply and fixing of crimping type Aluminium lugs confirming to I.S
4 specifications for cables upto 16 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 16 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100 jobs / day
15.4.1 Supply and fixing of crimping type Aluminium lugs confirming to I.S
5 specifications for cable of 25 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 25 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100 jobs / day
15.4.1 Supply and fixing of crimping type Aluminium lugs confirming to I.S
6 specifications for cable of 35 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 35 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75 jobs / day
15.4.1 Supply and fixing of crimping type Aluminium lugs confirming to I.S
7 specifications for cable of 50 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 50 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75 jobs / day
15.4.1 Supply and fixing of crimping type aluminium lugs confirming to I.S
8 specifications for cable of 70 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 70 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.01
Helper day 0.01
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75 jobs / day
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
15.4.1 Supply and fixing of crimping type aluminium lugs confirming to I.S
9 specifications for cable of 95 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 95 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.02
Helper day 0.02
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 60 jobs / day
15.4.2 Supply and fixing of crimping type aluminium lugs confirming to I.S
0 specifications for cable of 120 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 120 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.02
Helper day 0.02
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 50 jobs / day
15.4.2 Supply and fixing of crimping type aluminium lugs confirming to I.S
1 specifications for cable of 150 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 150 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25 jobs / day
15.4.2 Supply and fixing of crimping type aluminium lugs confirming to I.S
2 specifications for cable of 185 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 185 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25 jobs / day
15.4.2 Supply and fixing of crimping type aluminium lugs confirming to I.S
4 specifications for cable of 240 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 240 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.04
Helper day 0.04
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25 jobs / day
15.4.2 Supply and fixing of crimping type aluminium lugs confirming to I.S
5 specifications for cable of 300 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 300 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.05
Helper day 0.05
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 20 jobs / day
15.4.2 Supply and fixing of crimping type aluminium lugs confirming to I.S
6 specifications for cable of 400 Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 400 sqmm each 1.00
b) Labour charges for crimping
Semi Skilled Electrician day 0.06
Helper day 0.06
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 16 jobs / day
Bldngs_Elec-15-3 15.5 CABLE JOINTS
15.5.1 Providing and erecting epoxy staight through joint out door / indoor for
L.T, PVC Armoured cable 1100V grade complete with ferrule, bushings,
accessories and suitable clamps duly erected and connected to the
supply for the following multi core cables including cost and conveyance
of materials and all labour charges etc., complete.
1 2 3 4 5 6 7
15.6.1 Earth work excavation of Trench in hard ground soil, laying of U.G cables upto 50 Sq,mm on sand cushion covering the cable with bricks and ba
a) Material
Excavation of earth 100 x 0.3 X 0.9 m cum 27.00
Cost of bricks (Civil SSR) 1000 Nos 0.92
a) Material
Excavation of earth 100 x 0.3 X 0.9 m cum 27.00
Cost of bricks (Civil SSR) 1000 Nos 0.92
1 2 3 4 5 6 7
15.6.4 Supply and laying of one number double walled corrugated (DWC) HDPE
pipe of following sizes having corrugation on the outer wall and plain
surface inner wall confirming to IS : 14930 Part - I and II complete with
necessary HDPE fittings for protection of 1.1 KV grade U.G cable directly
in ground at a depth of 60Cms including excavation and refilling the trench
as required.
1 2 3 4 5 6 7
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation, erection of 3 Ph Air-Cooled 20KVA, D.G.Set with
(b) alternator, Diesel Engine, Control panel etc., with acoustic enclosure as
per specifications mentioned above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz., D.G.Set each 1.00
cost of acoustic enclosure each 1.00
Erection and commissioning charges :
the cost of the DG set. 0.10
cost of acoustic enclosure 0.05
Transportation at 2% on unit cost 0.02
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation, erection of 3 Ph Air-Cooled 25KVA, D.G.Set with
(c) alternator, Diesel Engine, Control panel etc., as per specifications
mentioned above.
a) Material
3Ph, 415V, 50Hz., 25 KVA Air Cooled D.G.Set each 1.00
Erection and commissioning charges @ 10% of the cost of the set. 0.10
a) Material
40KVA, 3Ph,415V,D.G.Set each 1.00
Erection and commissioning charges @ 10% of the cost of the set. 0.10
Transportation at 2% 0.02
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation , erection of 3 Phase Water Cooled / Air-Cooled
(h) 63KVA, D.G.Set with alternator, Diesel Engine, Control panel etc., with
acoustic enclosure as per specifications mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set each 1.00
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Cost of Acoustic enclosure each 1.00
Erection and commissioning charges :
the cost of the DG set. 0.10
cost of acoustic enclosure 0.05
Transportation at 2% 0.02
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation , erection of 3 Phase Water cooled 125 KVA,
(i) D.G.Set with alternator, Diesel Engine, Control panel etc., as per
specifications mentioned above.
a) Material
125KVA, Water Cooled, 3Ph, 415V D.G.Set. each 1.00
Erection and commissioning charges @ 10% of the cost of the set. 0.10
Transportation at 2% 0.02
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation, erection of 3 Phase Water-Cooled 125KVA,
(j) D.G.Set with alternator, Diesel Engine, Control panel etc., with acoustic
enclosure as per specifications mentioned above.
a) Material
125KVA, Water Cooled, 3Ph, 415V D.G.Set. each 1.00
Cost of Acoustic enclosure each 1.00
Erection and commissioning charges :
the cost of the DG set. 0.10
cost of acoustic enclosure 0.05
Transportation at 2% 0.02
Sundires and Rounding off
Rate per Each
Bldngs_Elec-17-2 17.2 Transformers
17.2.1 Supply, transportation, erection and commissioning of following
specifications of 3 Phase, 50 Hz., Oil immersed and naturally cooled, out
door / Indoor type copper wound transformer connected delta on H.V. side
and star on L.V side with additional neutral brought out on load side,
rating 11000 / 433 volts with HV tapping + 2.5% cotinuously rated for full
load and temparature rise not exceeding 450 C by thermometer in oil and
500 C by the resistance of the winding after continuous run on full load
rating complete with the following standard mounting.
(a) 63 KVA, 3Ph, aluminium wound Tansformer, CSP type (Core Self
Protection)
a) Material
63KVA Aluminium wound CSP type Transformer each 1.00
1 2 3 4 5 6 7
(b) Labour charges for erection and commissioning. 0.10
Rate per Each
(f) 250 KVA, 3Ph, copper wound Tansformer
a) Material
250 KVA Copper wound Transformer each 1.00
a) Material
630A, 415V Fixed type 3 pole ACB each 1.00
Shunt release each 1.00
U/V release each 1.00
Earth fault release each 1.00
Transportation @ 2% on Unit Cost 0.02
b) Labour charges for installation @ 5% 0.05
Rate per Each
17.3.8 Supply and errecting Air circuit Breaker (ACB) manually operated non
drawout type with 6 way secondary isolating contacts necessary micro
switches for over load and short circuit indicator, door interlocking, shunt
release, under voltage release as well as 10%-20% earth fault release
suitable for operational voltage 415V, 800A, erected in position on
provided panel boards in an approved manner with necessary material
complete.
a) Material
800A, 415V Fixed type 3 pole ACB each 1.00
Shunt release Coil. each 1.00
U/V release Coil. each 1.00
Earth fault release each 1.00
Transportation @ 2% on Unit Cost 0.02
b) Labour charges for installation @ 5% 0.05
Rate per Each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
17.3.9 Supply and errecting Air circuit Breaker (ACB) manually operated non
drawout type with 6 way secondary isolating contacts necessary micro
switches for over load and short circuit indicator, door interlocking, shunt
release, under voltage release as well as 10%-20% earth fault release
suitable for operational voltage 415V, 1000A, erected in position on
provided panel boards in an approved manner with necessary material
complete.
a) Material
1000A, 415V, Fixed type 3 pole ACB. each 1.00
Shunt release each 1.00
U/V release each 1.00
Earth fault release each 1.00
Transportation @ 2% on Unit Cost 0.02
b) Labour charges for installation @ 5% 0.05
Rate per Each
Bldngs_Elec-17-4 17.4 SUB - STATION EQUIPMENT
17.4.1 Supply and fixing printed instructions chart both in English and Telugu and
duly framed with front glass for treatment of person suffering from Electric
shock.
a) Material
Printed insturction chart both of size 0.9 x 0.6 M in English and Telugu. each 1.00
Towards making wooden frame with front glass including cost of material 1.50
and labour on unti cost of Item 1.
Rate per Each
17.4.2 Supply of pair of rubber hand gloves suitable for working 11/22 KV supply.
a) Material
Rubber hand gloves suitable for working on 11/22 KV supply each 1.00
Rate per Each Pair
17.4.3 Supply of 11KV, ISI, approved rubber mat of thickness, required length
and breadth.
a) Material
6mm thick, ISI make Rubber mat suitable for working on 11/22 KV each 1.00
Sundries and rounding off
Rate per sqmt
17.4.4 Supply of standard 18"x12"x8" first aid box with all standard contents.
a) Material
18" x 12" x 8" size First Aid box. each 1.00
Set of Cotton, band aid cloth Antiseptic cream etc., set 1.00
Rate per Each
17.4.5 Supply of G.I sheet bucket of round bottom of 13 Ltrs. Capacity with
printed letters and filled with sand and arranged to existing stand or hook.
a) Material
13 Ltrs. Capacity G.I. bucket. each 1.00
Painting with 2 coats of red color enamell paint on out side. sqm 0.50
Cost of sand cum 0.13
Sundires for printing letter etc.,
Rate per Each
17.4.6 Supply of Tranformer oil tested and having good resistance to high
electric stress di-electric strength 50KV, low viscocity, low pour point, high
flash point and excellent thermal properties for efficient heat transfer and
cooling as per IS 335-1972.
a) Material
Transformer Oil having Dielectric strength of 50 KV L 1.00
Sundries and rounding off
Rate per Lt
17.4.7 Providing floor mounting stand for keeping 4Nos of bucket 1500mm
length, 900mm height made out of 40x40x6mm angle iron welded with 4
hooks and duly painted with one coat of red lead and two coats of enamel
paint.
a) Material
1500mm length, 900mm height Floor mounting stand fabricated with kg 17.50
40x40x6mm angle iron welded with 4 Nos Hooks. (1Mtr = 3.5Kg)
(5x3.5Kgs = 17.5Kgs)
Fabrication cost of hooks including painting (on cost of material) 0.50
Sundries and rounding off
Rate per Each
17.4.8 Supply and erecting ABC Powder (stored pressure type) fire extinguisher
5kg conforming to IS 2171-85 with necessary clamps made from
50x6mm MS flat with nuts & bolts grouted in wall complete.
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
ABC Powder Stored pressure type fire extengensher of 5 Kg capacity . each 1.00
50 x6mm M.S Apl. Clamps with bolt & nut. each 1.00
(b) Labour charges for erection.
Helper day 0.20
Sundires and Rounding off
Rate per Each
Note : Labour is considered for 5 jobs / day
17.4.9 Supply and erecting ABC Powder (stored pressure type) fire extinguisher
10kg conforming to IS 2171-85 with necessary clamps made from
50x6mm MS flat with nuts & bolts grouted in wall complete.
a) Material
ABC Powder Stored pressure type fire extengensher of 10 Kg capacity . each 1.00
50 x6mm M.S Apl. Clamps with bolt & nut. each 1.00
(b) Labour charges for erection.
Helper day 0.20
Sundires and Rounding off
Rate per Each
Note : Labour is considered for 5 jobs / day
17.4.1 Supply and erecting fencing of section having size 2450 mm in height
0 from ground level and 1200mm width by using angle iron size
50x50x6mm erected in CC foundation 15x15x40cms deep. The section of
the frame shall be fitted with flat iron supports of size 25x6mm on top,
bottom and middle and chain link jali of 8 SWG G.I to the angle iron at
every distance of 30 cms by iron studs complete duly painted with one
coat of red oxide and two coats of aluminium paint.
a) Material
50x50x6mm Angle Iron (1 Mt. = 4.37 Kg) 4.8 m Length kg 20.97
25x6mm M.S Flat (1 Mt. 1.18 Kg) 3.6 M length kg 4.25
Chain link Mesh (Civil SSR) sqm 2.40
Fabrication of Frame with angles, Flat and chain link mesh kg 25.22
C.C.Work M 15 using 20 mm metal (15 x 15 x 40) x 2 As per Civil SSR cum 0.02
Painting with one coat of red oxide and two coat of alluminium paint. sqm 5.88
a) Material
50x50x6mm Angle. (1 mt. 4.37 Kg) 2m Length kg 8.74
C.C.Work M 15 using 20 mm metal (15 x 15 x 40) x 2 As per Civil SSR cum 0.02
Painting with one coat of red oxide and two coats of Aluminium paint (on 0.10
cost of Item 1)
Sundires and Rounding off
Rate per Each
17.4.1 Supply and erecting double leaf hinged door each 150cms width x
2 185cms height using 38.1 mm dia B grade ISI marked G.I pipe from all
four sides with necessary bends with cross supports of angle iron 40 x 40
x 6mm with the door leaf covered with chain link mesh of No. 8 SWG G.I
wire with necessary flat iron covering all around frame. The door shall
have heavy latches, and side channels of 100x50x5mm locking
arrangement with lock of medium size with duplicate keys, the fencing
completely erected with anti corrosive red oxide paint and two coats of
prescribed enamel paint / silver paint. The channel iron of size
100x50mm x 2.5Mtr. length shall be provided and erected at both sides of
gate with C.C work
a) Material
38.1mm dia B Class G.I pipe. RM 14.00
(1.85 x 4 Nos + 1.5x 4Nos = 13.4 Mt or say 14 Mtrs.) ( civil SSR)
1 2 3 4 5 6 7
Steel Aldrop with bolts and Nuts. each 1.00
Chain link mesh of 8 SWg G.I (Civil SSR) sqm 5.55
Medium size lock and Key each 1.00
Fabrication charges including welding etc., complete. kg 118.00
Painting Charges sqm
b) Labour charges for erection including cost of hinges on items 1-6. 0.05
On site.
a) Material
Labour charges for filterations at site
Rate per Each
17.5.1 Filteration of transformer oil as per ISS for removal of moisture, carbon Data shall be
(b) slurry etc. by means of circulating oil through vaccum pump from heating arrived based
elements and filters to withstand the dielectric strength of the oil above on observed
40KV beyond one minute tested in oil testing Kit. Data
At Factory.
a) Material
Labour charges for filterations at site
Rate per Each
17.5.3 Carryout routine maintenance, servicing and testing of 630A to 1000A
L.T.ACB by cleaning fixed contacts, moving contacts and arcchutes
including servicing and putting the ACB in perfect working condition after
detting all relay and ON, OFF mechanism etc.
a) Material
Removing the existing ACB and servicing and testing of 630A to 1000A
L.T.ACB.
Clearing of fixed contacts, moving contacts and arcchutes
Refix the ACB inposition and testing and commissioning charges.
b) Labour charges for entire job
Skilled Electrician day 3.00
Semi Skilled Electrician day 3.00
Helper day 6.00
Sundries and Rounding
Rate per Each
Note :Job requires 3 days. Keeping this labour arrived.
17.5.4 Carryout routine maintenance and servicing of LT.Cubical panel board
having approximately 15 to 22 Nos of switches by cleaning with power
blower and servicing the contacts, tightning the connection of incoming
and outgoing cables, and clicking the operating mechanism for smooth
functioning of switches and putting them in smooth working condition.
a) Material
Removing all the doors of switches, busbar chamber and back doors.
1 2 3 4 5 6 7
Rate per Each
Note : Labour is considered for 3 jobs / day
17.6.3 Supply and erecting porcelain disc type insulator suitable for 11KV line
with suitable hardware on existing cross arms.
a) Material
Cost of porcelain disc type insulator suitable for 11 KV each 1.00
b) Labour charges for erection.
Skilled Electrician day 0.13
Helper day 0.25
Sundries
Rate per Each
Note : Labour is considered for 8 jobs / day
17.6.5 Supply and erecting porcelain pin type insulator suitable for 11KV line
with suitable hardware on existing cross arms.
a) Material
Cost of porcelain pin type insulator suitable for 11 KV each 1.00
b) Labour charges for erection.
Skilled Electrician day 0.13
Helper day 0.25
Sundries
Rate per Each
Note : Labour is considered for 8 jobs / day
17.6.6 Supply and erecting porcelain post type insulator suitable for 11KV line
with suitable hardware on existing cross arms.
a) Material
Cost of porcelain post type insulator suitable for 11 KV each 1.00
b) Labour charges for erection.
Skilled Electrician day 0.13
Helper day 0.25
Sundries
Rate per Each
Note : Labour is considered for 8 jobs / day
17.6.8 Supply and fixing of lightning protective system conforming to IS : 2309
with all standard accessories such as metal globe finials on the top of the
builiding with 25.4 mm dia 3.0 mtrs. Length of 'B' class G.I pipe etc.,
complete without down conductors and earthing
a) Material
Lightning protective system with all standard accessories such as metallic each 1.00
globe, finials etc.,
25.4 mm B Class GI Pipe, ISI Mark M 3.00
b) Labour charges
i) for fixing the System on G.I pipe.
ii) for fixing on top of the building with C.C work / Clamping arrangement.
1 2 3 4 5 6 7
a) Material
Cost of 11kV, 200A (Tilting) A.B switch wth all standard accessories. each 1.00
a) Material
Cost of MPP capacitor operation on 3 Ph. 415V. Kvar 1.00
b) Labour charges for erection.
Skilled Electrician day 0.04
Helper day 0.08
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs / day
17.6.1 Supply and erecting of bank of mixdielectric condensors with the standard
5 capacities of 2,3,5,7,10,12.5 and 15 KVAR units for PF correction for
operation on 3 phase 50 cycles 400/440V (+10%) with externally
discharging resistances, earthing terminals etc., complete.
a) Material
Cost of of mixed Dielectric capacitor operation on 3 Ph. 415V. Kvar 1.00
b) Labour charges for erection.
Skilled Electrician day 0.04
Helper day 0.08
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs / day
Bldngs_Elec-18 18 Repairs to Motors and Rewinding
Datas of 11.6.1 to 11.6.4 are hold good and be adopted.
18.1.1 Rewinding the motor of the table / pedestal / cabin fan of all types, and
makes and overhauling including minor repairs, testing for the original
Bldngs_Elec-18-1 speed and consumption with guarantee for one year including
tansporation from site and back.
a) Material
Copper enamelled winding wire of fine quality. kg 0.30
Labour charges towards removing unserviceable winding wire and 0.50
cleaning. (on cost of winding wire)
Labour charges towards rewinding the coils complete with connections 1.00
etc., complete.(on cost of winding wire)
Sundries such as sleeves cotton tape, minolex paper, solution etc., with 0.40
transportion charges.
Less cost towards old winding wire kg 0.30
Rate per Each
18.1.2 Rewinding the motor of the ceiling fan of 1200mm / 1400mm of all types
and makes and over hauling including minor repairs and testing for
original speed and consumption
a) Material
35 / 36 Copper enamelled winding wire of fine quality. kg 0.20
Labour charges towards removing unserviceable winding wire and 0.50
cleaning. (on cost of winding wire)
Labour charges towards rewinding the coils complete with connections 1.00
etc., complete.(on cost of winding wire)
Sundries such as sleeves cotton tape, minolex paper, solution etc., with 0.40
transportion charges.
Less cost towards old winding wire kg 0.20
Rate per Each
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
18.1.3 Rewinding the motor of the exhaust fan of light duty 225/300mm of
900/1400 RPM of all types and makes and over hauling including minor
repairs and testing for original speed and consumption
a) Material
23 / 24 / 28 Copper enamelled winding wire of fine quality. kg 0.05
Labour charges towards removing unserviceable winding wire and 0.50
cleaning. (on cost of winding wire)
Labour charges towards rewinding the coils complete with connections 1.00
etc., complete.(on cost of winding wire)
Sundries such as sleeves cotton tape, minolex paper, solution etc., with 0.40
transportion charges.
Less cost towards old winding wire kg 0.05
Rate per Each
18.1.4 Rewinding the motor of the exhaust fan of heavy duty 375mm of
900/1400 RPM of all types and makes and over hauling including minor
repairs and testing for original speed and consumption
a) Material
23 / 24 / 28 Copper enamelled winding wire of fine quality. kg 0.45
Labour charges towards removing unserviceable winding wire and 0.50
cleaning. (on cost of winding wire)
Labour charges towards rewinding the coils complete with connections 1.00
etc., complete.(on cost of winding wire)
Sundries such as sleeves cotton tape, minolex paper, solution etc., with 0.40
transportion charges.
Less cost towards old winding wire kg 0.45
Rate per Each
18.1.5 Rewinding of electric motor upto 1 HP single phase upto 1400 RPM of all
types and makes with copper wire, overhauling with minor repairs, testing
for the original speed and no load consumption .
a) Material
Suitable guage copper winding wire fine quality kg 2.70
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 2.70
Rate per Each
18.1.6 Rewinding of electric motor 2 HP single phase 1400 RPM of all types and
makes with copper wire, overhauling with minor repairs, testing for the
original speed and no load consumption.
a) Material
Suitable guage copper winding wire fine quality kg 3.20
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 3.20
Rate per Each
18.1.7 Rewinding of electric motor 3 HP three phase 1400 RPM of all types
and makes with copper wire, overhauling with minor repairs, testing for
the original speed and no load consumption .
a) Material
Suitable guage copper winding wire fine quality kg 4.50
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 4.50
Rate per Each
18.1.8 Rewinding of electric motor 5 HP three phase 1400 RPM of all types and
makes with copper wire, overhauling with minor repairs, testing for the
original speed and no load consumption .
a) Material
Suitable guage copper winding wire fine quality kg 5.70
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 5.70
Rate per Each
18.1.9 Rewinding of electric motor 7.5 HP three phase 1400 RPM of all types
and makes with copper wire, overhauling with minor repairs, testing for
the original speed and no load consumption .
a) Material
Suitable guage copper winding wire fine quality kg 6.50
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 6.50
Rate per Each
18.1.1 Rewinding of electric motor 10 HP three phase 1400 RPM of all types
0 and makes with copper wire, overhauling with minor repairs, testing for
the original speed and no load consumption .
a) Material
Suitable guage copper winding wire fine quality kg 10.00
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 10.00
Rate per Each
18.1.1 Rewinding of electric motor 12.50 HP three phase 1400 RPM of all types
1 and makes with copper wire, overhauling with minor repairs, testing for
the original speed and no load consumption .
a) Material
Suitable guage copper winding wire fine quality kg 12.00
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 12.00
Rate per Each
18.1.1 Rewinding of electric motor 15 HP three phase 1400 RPM of all types
2 and makes with copper wire, overhauling with minor repairs, testing for
the original speed and no load consumption .
a) Material
Suitable guage copper winding wire fine quality kg 15.00
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 15.00
Rate per Each
18.1.1 Rewinding of electric motor 20 HP three phase 1400 RPM of all types
3 and makes with copper wire, overhauling with minor repairs, testing for
the original speed and no load consumption.
a) Material
Suitable guage copper winding wire fine quality kg 18.00
Labour charges towards removing of old unserviceable winding wire.(on 0.05
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.12
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.02
transportation.
Less cost towards old winding wire kg 18.00
Rate per Each
18.1.1 Rewinding of submersible motor upto 15 HP three phase of all types
4 and makes with copper wire, overhauling with minor repairs, testing for
the original speed and no load consumption .
Specif
icatio Quantit Amount
Index-code n No. Description Unit Rate Rs. Remarks
y Rs.
1 2 3 4 5 6 7
a) Material
PVC insulated copper winding wire of suitable guage. kg 18.00
Labour charges towards removing of old unserviceable winding wire.(on 0.10
cost of winding wire)
Labour charges towards rewinding copper coils complete with 0.15
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape, minolex paper solution etc., with 0.05
transportation.
Less cost for winding wire kg 18.00
Rate per Each
Bldngs_Elec-18-2 18.2 Bearings
18.2.1 Replacing the existing bearing of approved make for electric motor single
phase / 3 phase AC upto 1 HP of all types with due alignment of the shaft
and tested.
a) Material
Ball Bearings suitable for 1 HP Motor inclusive of taxes each 1.00
Labour charges for removing the existing unserviceable bearing and fixing 0.50
the new ball bearing with special T&P. (on cost of Ball Bearing)
1 2 3 4 5 6 7
Cost of GM / Bush / Rubber / Ring washer etc., each 1.00
Labour charges for removing the existing unserviceable bush/ ring washer 0.50
and fixing the new with special T&P.(on cost of material)
Rounding Off
Rate per Each
18.2.8 Replacing the existing capacitor of table / cabin / pedestal / ceiling /
exhaust fan complete with wiring.
a) Material
Cost of 2.5 / 3.5 mfd condensor suitable for ceiling / pedastal Exhaust Fan each 1.00