works total 1 M3 BRIDGE km 48+951 Montage of girders 60 2 M3 BRIDGE km 48+951 Deck slab 2 3 M4 BRIDGE km 50+816 Abutment piers 4 4 M4 BRIDGE km 50+816 Deck slab 2 5 M5 OVERPASS km 51+438 Precast girders 21 6 M6 OVERPASS km 54+014 piles 14 7 M7 OVERPASS km 56+354 Bearing beams 4 8 M7 OVERPASS km 56+354 Precast girders 18 9 M8 BRIDGE km 56+773 Deck slab 2 10 M11 OVERPASS km 59+967 Deck slab 1 11 M14 OVERPASS km 62+938 Deck slab 1 Volume of planned works in Volume of executed production from January 9th of January to 22th of January 20 20 1 0 1(2x0.5) 0 1 0 5 0 9 5 4 4 9 8 1 0 0.5 0.5 1 0 Volume of executed production from 16th of Description of executed production from 16th of January January to 22th of January to 22h of January 0 0 0 0 0 4 concreted 4 piles 0 5 concreted 5 girders 0 0.5 concreted 1/2 deck slab (finishead whole deck slab) 0