No.

Bridge Position Operation

1 M1 BRIDGE km 45+208 Bridge deck


2 M1 BRIDGE km 45+208 Sidewalks
Installation of the precast
3 M1 BRIDGE km 45+208
girders
4 M1 BRIDGE km 45+208 End slopes
5 M1 BRIDGE km 45+208 Transition slabs
6 M3 BRIDGE km 48+951 Waterproofing of deck slab
7 M3 BRIDGE km 48+951 End slopes
8 M4 BRIDGE km 50+816 Waterproofing of deck slab
9 M5 BRIDGE km 51+438 Pedestrian walkway
10 M6 BRIDGE km 54+014 Bridge deck
11 M6 BRIDGE km 54+014 Pedestrian walkway
12 M8 BRIDGE km 56+773 Waterproofing of deck slab
13 M9 OVERPASS km 58+170 Waterproofing of deck slab
14 M11 OVERPASS km 59+967 Transition slabs
15 M11 OVERPASS km 59+967 End slopes
16 M11 OVERPASS km 59+967 Waterproofing of deck slab
17 M12 BRIDGE km 61+300 Asphalt expansion joint
18 M13 BRIDGE km 62+350 Asphalt expansion joint
19 M14 OVERPASS km 62+938 Waterproofing of deck slab
20 M15 BRIDGE km 63+700 Asphalt expansion joint
21
22
23
24
25
26
27
28
29
30
31
Volume of planned Volume of planned works in Volume of executed production from
works total August 30th of July to 5th of August
4 1.75 0.25
8 3.75 0.75

144 58 0

2 1 0
8 3 0
2 1 1
2 2 0
2 1 1
2 2 0
1 0.5 0.5
2 2 0
2 2 1
1 1 1
2 2 1
2 2 0
1 1 0
4 4 0
4 4 0
1 1 0
4 4 0
Volume of executed production from 06th Volume of executed production from
of August to 12th of August 13th of August to 19th of August2
0
0.5

58

0
0
0
0.5
0
0
0
0
0
0
0
0
0
0
2
1
2