Volume of planned

No. Bridge Position Operation


works total
1 M1 BRIDGE km 45+208 Piles 88
2 M1 BRIDGE km 45+208 Foundations 12
3 M1 BRIDGE km 45+208 Middle piers 12
4 M1 BRIDGE km 45+208 Abutments 8
5 M1 BRIDGE km 45+208 Bearing beams 12
6 M6 OVERPASS km 54+014 Middle Piers 2
7 M6 OVERPASS km 54+014 Bearing beams 4
8 M7 OVERPASS km 56+354 Pedestrian walkways 2
9 M7 OVERPASS km 56+354 Transition slabs 2
10 M7 OVERPASS km 56+354 Hidroisolation 1
11 M7 OVERPASS km 56+354 Steel guardrail
pedestrian protective
12 M7 OVERPASS km 56+354
fence
13 M8 BRIDGE km 56+773 Pedestrian walkways 4
14 M9 OVERPASS km 58+170 Pedestrian walkways 2
15 M10 BRIDGE km 58+641 Hidroisolation 2
16 M12 BRIDGE km 61+300 Hidroisolation 2
17 M12 BRIDGE km 61+300 Steel guardrail
18 M13 BRIDGE km 62+350 Hidroisolation 2
19 M15 BRIDGE km 63+700 Hidroisolation 2
Volume of planned works in Volume of executed production from
May 1st of May to 28th of May
20 13
2 2
3 3
3
2
1 1
4 1
1 1
2 2
1 1
100%
100%
2 4
2
1
1
50%
1 1
1 1
Volume of executed production from 15th of Description of executed production from 15th of May to
May to 21st of May 21st of May
3 concreted 3 piles.

2 Concreted 1 middle pier.

1 concreted 1 bearing beam.

100% Steel guardrail finishead 100%.


100% Pedestrian protective fence finishead 100%.
2 concreted 1 pedestrian walkways.

50% Steel guardrail finishead 50%.