works total 1 M1 BRIDGE km 45+208 Piles 88 2 M1 BRIDGE km 45+208 Foundations 12 3 M1 BRIDGE km 45+208 Middle piers 12 4 M1 BRIDGE km 45+208 Abutments 8 5 M1 BRIDGE km 45+208 Bearing beams 12 6 M6 OVERPASS km 54+014 Middle Piers 2 7 M6 OVERPASS km 54+014 Bearing beams 4 8 M7 OVERPASS km 56+354 Pedestrian walkways 2 9 M7 OVERPASS km 56+354 Transition slabs 2 10 M7 OVERPASS km 56+354 Hidroisolation 1 11 M7 OVERPASS km 56+354 Steel guardrail pedestrian protective 12 M7 OVERPASS km 56+354 fence 13 M8 BRIDGE km 56+773 Pedestrian walkways 4 14 M9 OVERPASS km 58+170 Pedestrian walkways 2 15 M10 BRIDGE km 58+641 Hidroisolation 2 16 M12 BRIDGE km 61+300 Hidroisolation 2 17 M12 BRIDGE km 61+300 Steel guardrail 18 M13 BRIDGE km 62+350 Hidroisolation 2 19 M15 BRIDGE km 63+700 Hidroisolation 2 Volume of planned works in Volume of executed production from May 1st of May to 28th of May 20 13 2 2 3 3 3 2 1 1 4 1 1 1 2 2 1 1 100% 100% 2 4 2 1 1 50% 1 1 1 1 Volume of executed production from 15th of Description of executed production from 15th of May to May to 21st of May 21st of May 3 concreted 3 piles.