Installation checklist and request for authorized start-up engineer


To:
Job name:
Location:
Customer order number:
JCI telephone number:
JCI order number:
JCI contract number:

Chiller model number:


Serial number:
The work (as checked below) is in process and
___________________ /___________________ /___________________
will be completed by (MM/DD/YYYY):

The following work must be completed in accordance with installation instructions:


A. Chiller g. Hot gas valve, if the option was ordered
1. Initial inspection:
h. Refrigerant in vessels
a. Check unit shipment to ensure that all
major components, boxes, and crates 3. Condenser components:
arrived without any damages.
a. Condenser relief valves
Note: Any damage MUST be reported to
the transportation company immediately
b. Condenser piping
for their inspection.
b. Ensure that all boxes and crates are c. Condenser coils
opened and inventoried with the
packing list. d. Condenser fans
Note: Any damage MUST be reported to
Johnson Controls immediately for inspec- 4. Control Panel components:
tion.
a. User interface and display
2. Evaporator shell components:
a. Evaporator relief valves b. Internal wiring and components

b. Evaporator transducers c. Any evidence of water infiltration

c. Evaporator wiring harnesses d. Panel mounts and enclosure

d. Evaporator insulation e. Internal components and wiring

e. Evaporator paint 5. Compressor components:


a. Compressor relief valves
f. Evaporator waterbox shipping blanks in
place
b. Compressor transducers
F. Electrical wiring
c. Compressor wiring harnesses
1. Variable Speed Drive:
d. Compressor insulation a. Main power supply is available.
e. VGD actuator, harnesses, and linkages b. Wiring is completed from main power
supply to single point power connection
f. Compressor paint in accordance with 160.88-PW1.

6. VSD panel components: Note: Do NOT cut to length or connect to


drive without Johnson Controls supervi-
a. Any evidence of water infiltration sion.
c. Wiring is completed to the evaporator
b. Panel mounts and enclosure freeze protection power connection.

c. Check cooling system for leaks Note: Do NOT cut to length or connect
without Johnson Controls supervision.
Note: Any component notes can be 2. Control Center:
recorded in the components notes space
a. Jumper wire is NOT installed between
provided on the following page(s).
terminal 24 and 25 located on the
control center terminal strip (TB-6).
B. Vibration isolators b. External control wiring is completed
from the control center to chilled
1. Isolators meet the requirements as outlined water flow switches or interlocks
in the isolator table in 160.88-N1, Isolator in accordance with the YORK Wiring
selection and mounting. Diagram Form 160-88-PW2.
2. Isolators are adjusted so that the unit c. Power is available and wiring is
is level and that all isolators are equally completed to the chilled water pump,
deflected. and rotation has been checked.
Note: Do NOT check the compressor
C. Water piping motor rotation.
1. Chilled water piping is installed between
cooler, pumps, and cooling coils. G. Testing, evacuation, and charging
2. Make-up and fill lines are installed to the
1. Dry nitrogen is available for testing.
chilled water system.
3. All water piping is checked for strain. Piping 2. A high vacuum pump is available for
must not spring when connections are evacuation and dehydration of system.
broken at unit.
3. Refrigerant, as supplied by Johnson
4. Water piping is leak tested and flushed, and Controls, is available for charging.
water strainers are cleaned after flushing.
4. Unit has been or is ready to be been
5. Piping systems are filled with water and pressure tested, evacuated, dehydrated,
trapped and all air is vented. and charged as outlined in 160.88-OM1.
6. Chilled water flow is available to meet the
unit design requirements.
H. Conditions
1. Cooling load is available for testing and
D. Refrigerant relief piping (when required) operating the unit.
1. Refrigerant relief piping with flexible 2. Personnel are available for final wiring
connection is installed from unit to connections.
atmosphere in accordance with local codes.
3. Personnel are available for start-up and
testing.
E. Unit clearances
1. Ensure that the clearances around the
unit meet the requirements of 160.88-N1,
Installation section.

2 Model YVAM Installation Checklist and Start-up Request


Owner's operating personnel:

Name: _______________________________________

Phone Number: _______________________________________

Name: _______________________________________

Phone Number: _______________________________________

Name: _______________________________________

Phone Number: _______________________________________

Model YVAM Installation Checklist and Start-up Request 3


Contractor's responsibilities and instructions to use form
This installation checklist provides a quick way to check if all necessary installation work was completed in accordance
with all applicable installation instructions in Forms 160.88-N1, and when completed, acts as a request for Johnson
Controls to furnish start-up supervision.
Complete this form as follows:
1. Fill out the top of page 1.
2. Check off each item as required. Cross out (x) items that do not apply.
3. Enter names, initials, and date of the operating personnel who completed the checklist.
4. Bottom of form: Enter the date that the Johnson Controls start-up technician should be at the job site and the
name(s) of the supervisor(s) to be contacted.
5. Retain one copy in files and send one copy to customer.

With reference to the terms of the above contract, we are requesting the presence of your JCI Authorized Representative
at the job site on _______/_______/_______ (Month / Day / Year) to start the system and instruct operating personnel.

Have the JCI representative contact:____________________________________________ (Name/Phone).

TERMS: We understand that the services of the Johnson Controls Authorized Representative will be furnished in
accordance with the contract for a period of time of not more than ________ consecutive normal working hours, and we
agree that a charge of __________ per diem plus travel expenses will be made to Johnson Controls if services are required
for longer than _________ consecutive normal hours or if repeated calls are required, through no fault of Johnson Controls.

Customer/Contractor Signature: ___________________________________________________________

Customer/Contractor Name (Print): ___________________________________________________________

Title: ___________________________________________________________

Form Completed by: ___________________________________________________________

© 2021 Johnson Controls. 5000 Renaissance Drive, New Freedom, York, PA 17349, USA. Subject to change without notice. All rights
reserved.

You might also like