WORK CONDITION REPORT FORM ID : 001-REV02

ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.


SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

SCOPE OF WORK

1. INCOMING INSPECTION

2. CLEANING

3. INSPECTIION AND DISPOSITION


- VISUAL INSPECTION
- DISPOSITION

4. NON-DESTRUCTIVE TEST
a. Penetrant Test
b. Ultrasonic Test

5. DESTRUCTIVE TEST
a. Hardness Test
b. Coating Thickness Test

6. FINAL INSPECTION

7. INSPECTION REPORT

8. PACKAGING AND SHIPMENT

Note : Prepared by:

PAGE : 01 ARI HERDIANA


WORK CONDITION REPORT FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

APPLYING SERMETEL "W" FOR COMPRESSOR SECTION CENTAUR


( COMP. DISK, STATOR, SPACER AND IGV )
A. GENERAL

1. PURPOSE
This process routine provides paint instruction for the prevention of heat scaling, oxidation,
abration, erosion and corrosion by using Sermetel "W" Coating.
Applicability : # 1 st thru # 11 th stage Compressor Disk
# 3 rd thru # 11 th Compressor Stator
# 4 th thru # 11 th Compressor Spacer
IGV, 1st and 2nd Variable Vanes Stator
2. SCOPE
2.1.1 Masking area not to be coated on compressor disk
2.1.2 Applying sermetel W and sermeseal to the disks as shown
2.2.1 Masking area not to be coated on compressor stator
2.2.2 Applying sermetel W and sermeseal to the stators
2.3.1 Masking area not to be coated on compressor spacer
2.3.2 Applying sermetel W and sermeseal to the spacers
2.4.1 Masking area not to be coated on stator vanes.
2.4.2 Applying sermetel W and sermeseal to the stator vanes

3. REFERENCES
3.1 Overhaul inspection standard No. CCR-I-101
3.2 Overhaul repair standard No. CPT-R-101-1-4-1

4. MATERIAL REQUIREMENTS
4.1 Sermetel 'W'
4.2 120-240 Aluminum Oxide
4.3 Masking Tape
4.4 Plastic plugs, cups, etc.
4.5 Clean, dry shop air

5. EQUIPTMENT, TOOLING :
5.1 Spray Gun
5.2 Oven with temperature recorder.
5.3 Rubber Gloves
5.4 Isolated spray booth arrestor type.
5.5 Compressed air ( dry )
5.6 Grit blast machine
5.7 Mechanical agitator or paint shaker
5.8 Humidity and temperature indicator
Note : Prepared by:

PAGE : 02 ARI HERDIANA


WORK CONDITION REPORT FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

B. ACCOMPLISHMENT INSTRUCTION

1 Chemical Cleaning
2 Stripping old coating
3 Non-Destructive Test
4 Masking area not to be coated ( Disk, Stator, Space and Vanes)
5 Apply SERMETEL W (0.0010 - 0.0030 inch)
6 Baking the part per PMP no. PS-001 step 6.2.4
7 Thickness Measurment on Coating

NO Complete Description of Work/Services


To Cover cost for repair/recondition services of 1 (one) set Turbine
Compressor Rotor (11 Disks)
A. Stripping and cleaning existing coating
B. Magnetic Particle test for material fatigue analysis and temperature
1
C. Ultrasonic examination
D. Inspection of material hardness for measuring material resistance to axial
movement other caused by rotation
E. Heating, apply high temperature sermetal coating and blasting
To Cover cost for repair/recondition, cleaning, sand blasting and sermetal
coating of 1 (one) set Centaur Compressor Rotor, stage 1 thru stage 11 (11
Stages)
A. Stripping coating with blasting method
2 B. Non Destruction Test (NDT), Flourescent particle inspection to track
information on surface crack on nozzle
C. Rework on crack using welding method
D. Coating for high temp resistant
E. Preservation
To Cover cost for repair/recondition, cleaning, sand blasting and sermetal
coating of :
- Centaur Compressor Stator 9 Stages (stage 1 - 9)
- IGV Blade/ Vanes (108 ea)
A. Stripping coating with blasting method
3
B. Non Destruction Test (NDT), Flourescent particle inspection to track
information on surface crack on nozzle
C. Rework on crack using welding method
D. Coating for high temp resistant
E. Preservation

Note : Prepared by:

PAGE : 03 ARI HERDIANA


WORK CONDITION REPORT FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23
APPLYING COATING METCO 962 AMDRY FRAXAIR N1Z11 FOR NOZZLE SECTION CENTAUR

A. GENERAL

1 PURPOSE
This process routine provides paint instruction for the prevention of heat scaling, oxidation,
abration, erosion and corrosion by using AMDRY Coating.
Applicability : # 1 st Nozzle
# 2 nd Nozzle
# 3 th Nozzle

2 SCOPE
2.1.1 Masking area not to be coated on nozzle
2.1.2 Applying Amdry to nozzle stg #1
2.2.1 Masking area not to be coated on nozzle
2.2.2 Applying Amdry to nozzle stg #2
2.3.1 Masking area not to be coated on nozzle
2.3.2 Applying Amdry to nozzle stg #3

3 REFERENCES By User

4 MATERIAL REQUIREMENTS
4.1 METCO 962 AMDRY FRAXAIR N1Z11
4.2 120-240 Aluminum Oxide
4.3 Masking Tape
4.4 Plastic plugs, cups, etc.
4.5 Clean, dry shop air

5 EQUIPTMENT, TOOL
5.1 Plasma spray machine
5.2 Rubber Gloves
5.3 Grit blast machine
5.4 Compressed air ( dry )

Note : Prepared by:

PAGE : 04 ARI HERDIANA


WORK CONDITION REPORT FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

B. ACCOMPLISHMENT INSTRUCTION

1 Chemical Cleaning
2 Stripping old coating
3 Non-Destructive Test
4 Masking area not to be coated
5 Apply METCO 962 AMDRY

NO Complete Description of Work/Services


To Cover cost for inspection, repair/recondition and high temperature coating
for turbine nozzle:
- 1st Stage
- 2nd Stage
- 3rd Stage
1 A. Stripping coating with blasting method
B. Non Destruction Test (NDT), Flourescent particle inspection to track
information on surface crack on nozzle
C. Rework on crack using welding method
D. Coating high temp resistant
E. Preservation

SETTING PLASMA SPRAY:

1 Argon 80 psi
2 Hidrogen 60 psi
3 Flow argon 120 psi for bond coat
4 Flow argon 90 psi for top coat
5 Volt 75 ±5
6 Ampere 500
7 Carrier gas flow 10±/-1 @40 psi
8 Powder fort number 6 p/n ( 3mb 288 )
9 Vibrator pressure 25 ± 5
10 Primary gas argon flow 120±/-2 SCFH@80psi
11 Hydrogen flow 2-20 SCFH @60psi

Note : Prepared by:

PAGE : 05 ARI HERDIANA


WORK CONDITION REPORT FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23
REPAIR COMPRESSOR HUB CENTAUR

A. SCOPE OF WORK

1 Chemical Cleaning
2 Dimensional Inspection
3 Creating production drawing
4 Prepare for coating process
5 Masking areas not to be coated
6 Applied coating on the taper hub
7 Finish grinding
8 Inspection :
a Dimensional Inspection
b Mechanical Run out
c NDT ( FPI/MPI and UT)
d Check taper contact
9 Engineering Report
10 Packaging and delivery

Note : Prepared by:

PAGE : 06 ARI HERDIANA


WORK CONDITION REPORT FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

INSPECTION SUMMARY

WORK
NO DESCRIPTION QTY GOOD REPAIR
INSTRUCTION

1 Inlet Guide Vane 36 36 0 Coating

2 IGV stage #1 36 36 0 Coating

3 IGV stage #2 36 36 0 Coating

4 Comp. spacer stage #4 - #11 8 8 0 Coating

5 Comp. Stator stage #3 - #11 9 9 0 Coating

6 Comp. Disk #1 - #11 11 11 0 Coating

Welding (21ea),
7 Nozzle stg #1 22 1 21 Coating. Replace
Cooling Cup (8)
Welding (20ea),
8 Nozzle stg #2 22 2 20
Coating
Welding (6ea),
9 Nozzle stg #3 13 7 6
Coating

Note : Prepared by:

PAGE : 07 ARI HERDIANA


INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 31/NDT/PT/V/23
PT LEVEL : II DATE : 27-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED
REPAIR
36 EA - INLET GUIDE VANE (IGV) FINAL
PROCEDURE
ASTM E1417 - API 687/616
010/NDT-PT/PRD-GT/II//22
GENERAL PENETRANT DESCRIPTION
TEST AREA : ALL VISIBLE SURFACES ARDROX 970P25E ( FLUORESCENT )
PENETRANT TYPE DWEEL TIME Part Disposition According ARDROX-907 PB ( RED DYE )
FLOURESCENT 15 MINUTE to Specification ZYGLO ZL-27A ( FLUORESCENT )
RED DYE 30 MINUTE Accepted Rejected DEVELOPER APPLICATION :
OTHER : 60 MINUTE MAGNAFLUX ZP-9F
PT - OK
REMOVALL METHOD OTHER :

WATER WASHABLE ( TYPE A )


SOLVENT WIPE ( TYPE C )
EMULSIFIER (TYPE D )

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT :

Inspected by : :
PENETRANT TESTING LEVEL

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 08 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT IGV PHOTOGRAPHS

Fig 1. Penetrant Application on Part, Fig 2. Developer Application, Developing


Dwell Time : 15 Minute Time for Inspectioin : 10 Minute.

Fig 3. Penetrant Inspection on part, Fig 4. Penetrant Inspection on part, Using


Using Black Light (UV 365nm) Black Light (UV 365nm)

Page : 09 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 32/NDT/PT/V/23
PT LEVEL : II DATE : 27-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED
REPAIR
36 EA - INLET GUIDE VANE (IGV) FINAL
1st STAGE PROCEDURE
ASTM E1417 - API 687/616
010/NDT-PT/PRD-GT/II//22
GENERAL PENETRANT DESCRIPTION
TEST AREA : ALL VISIBLE SURFACES ARDROX 970P25E ( FLUORESCENT )
PENETRANT TYPE DWEEL TIME Part Disposition According ARDROX-907 PB ( RED DYE )
FLOURESCENT 15 MINUTE to Specification ZYGLO ZL-27A ( FLUORESCENT )
RED DYE 30 MINUTE Accepted Rejected DEVELOPER APPLICATION :
OTHER : 60 MINUTE MAGNAFLUX ZP-9F
PT - OK
REMOVALL METHOD OTHER :

WATER WASHABLE ( TYPE A )


SOLVENT WIPE ( TYPE C )
EMULSIFIER (TYPE D )

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT :

Inspected by : :
PENETRANT TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 10 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT IGV 1st STAGE PHOTOGRAPHS

Fig 1. Penetrant Application on Part, Fig 2. Developer Application, Developing


Dwell Time : 15 Minute Time for Inspectioin : 10 Minute.

Fig 3. Penetrant Inspection on part, Fig 4. Penetrant Inspection on part, Using


Using Black Light (UV 365nm) Black Light (UV 365nm)

Page : 11 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 33/NDT/PT/V/23
PT LEVEL : II DATE : 27-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED
REPAIR
36 EA - INLET GUIDE VANE (IGV) FINAL
2nd STAGE PROCEDURE
ASTM E1417 - API 687/616
010/NDT-PT/PRD-GT/II//22
GENERAL PENETRANT DESCRIPTION
TEST AREA : ALL VISIBLE SURFACES ARDROX 970P25E ( FLUORESCENT )
PENETRANT TYPE DWEEL TIME Part Disposition According ARDROX-907 PB ( RED DYE )
FLOURESCENT 15 MINUTE to Specification ZYGLO ZL-27A ( FLUORESCENT )
RED DYE 30 MINUTE Accepted Rejected DEVELOPER APPLICATION :
OTHER : 60 MINUTE MAGNAFLUX ZP-9F
PT - OK
REMOVALL METHOD OTHER :

WATER WASHABLE ( TYPE A )


SOLVENT WIPE ( TYPE C )
EMULSIFIER (TYPE D )

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT :

Inspected by : :
PENETRANT TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 12 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT IGV 2nd STAGE PHOTOGRAPHS

Fig 1. Penetrant Application on Part, Fig 2. Developer Application, Developing


Dwell Time : 15 Minute Time for Inspectioin : 10 Minute.

Fig 3. Penetrant Inspection on part, Fig 4. Penetrant Inspection on part, Using


Using Black Light (UV 365nm) Black Light (UV 365nm)

Page : 13 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 34/NDT/PT/V/23
PT LEVEL : II DATE : 27-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED
REPAIR
8 EA - COMPRESSOR ROTOR FINAL
SPACER STG #4 - #11 PROCEDURE
ASTM E1417 - API 687/616
010/NDT-PT/PRD-GT/II//22
GENERAL PENETRANT DESCRIPTION
TEST AREA : ALL VISIBLE SURFACES ARDROX 970P25E ( FLUORESCENT )
PENETRANT TYPE DWEEL TIME Part Disposition According ARDROX-907 PB ( RED DYE )
FLOURESCENT 15 MINUTE to Specification ZYGLO ZL-27A ( FLUORESCENT )
RED DYE 30 MINUTE Accepted Rejected DEVELOPER APPLICATION :
OTHER : 60 MINUTE MAGNAFLUX ZP-9F
PT - OK
REMOVALL METHOD OTHER :

WATER WASHABLE ( TYPE A )


SOLVENT WIPE ( TYPE C )
EMULSIFIER (TYPE D )

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT :

Inspected by : :
PENETRANT TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 14 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. SPACER PHOTOGRAPHS

Fig 1. Penetrant Application on Comp Fig 2. Penetrant Inspection on Comp Stg


Stg #4, Dwell Time : 15 Minute #4, Using Black Light (UV 365nm)

Fig 3. Penetrant Application on Comp Fig 4. Penetrant Inspection on Comp Stg


Stg #5, Dwell Time : 15 Minute #5, Using Black Light (UV 365nm)

Fig 5. Penetrant Application on Comp Fig 6. Penetrant Inspection on Comp Stg


Stg #6, Dwell Time : 15 Minute #6, Using Black Light (UV 365nm)

Fig 7. Penetrant Application on Comp Fig 8. Penetrant Inspection on Comp Stg


Stg #7, Dwell Time : 15 Minute #7, Using Black Light (UV 365nm)

Page : 15 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. SPACER PHOTOGRAPHS

Fig 9. Penetrant Application on Comp Fig 10. Penetrant Inspection on Comp Stg
Stg #8, Dwell Time : 15 Minute #8, Using Black Light (UV 365nm)

Fig 11. Penetrant Application on Comp Fig 12. Penetrant Inspection on Comp Stg
Stg #9, Dwell Time : 15 Minute #9, Using Black Light (UV 365nm)

Fig 13. Penetrant Application on Comp Fig 14. Penetrant Inspection on Comp Stg
Stg #10, Dwell Time : 15 Minute #10, Using Black Light (UV 365nm)

Fig 15. Penetrant Application on Comp Fig 16. Penetrant Inspection on Comp Stg
Stg #11, Dwell Time : 15 Minute #11, Using Black Light (UV 365nm)

Page : 16 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 35/NDT/PT/V/23
PT LEVEL : II DATE : 27-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED
REPAIR
9 EA - COMPRESSOR ROTOR FINAL
STATOR STG #3 - #11 PROCEDURE
ASTM E1417 - API 687/616
010/NDT-PT/PRD-GT/II//22
GENERAL PENETRANT DESCRIPTION
TEST AREA : ALL VISIBLE SURFACES ARDROX 970P25E ( FLUORESCENT )
PENETRANT TYPE DWEEL TIME Part Disposition According ARDROX-907 PB ( RED DYE )
FLOURESCENT 15 MINUTE to Specification ZYGLO ZL-27A ( FLUORESCENT )
RED DYE 30 MINUTE Accepted Rejected DEVELOPER APPLICATION :
OTHER : 60 MINUTE MAGNAFLUX ZP-9F
PT - OK
REMOVALL METHOD OTHER :

WATER WASHABLE ( TYPE A )


SOLVENT WIPE ( TYPE C )
EMULSIFIER (TYPE D )

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT :

Inspected by : :
PENETRANT TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 17 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. STATOR PHOTOGRAPHS

Fig 1. Penetrant Application on Comp Fig 2. Penetrant Inspection on Comp Stg


Stg #3, Dwell Time : 15 Minute #3, Using Black Light (UV 365nm)

Fig 3. Penetrant Application on Comp Fig 4. Penetrant Inspection on Comp Stg


Stg #4, Dwell Time : 15 Minute #4, Using Black Light (UV 365nm)

Fig 5. Penetrant Application on Comp Fig 6. Penetrant Inspection on Comp Stg


Stg #5, Dwell Time : 15 Minute #5, Using Black Light (UV 365nm)

Page : 18 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. SPACER PHOTOGRAPHS

Fig 7. Penetrant Application on Comp Fig 8. Penetrant Inspection on Comp Stg


Stg #6, Dwell Time : 15 Minute #6, Using Black Light (UV 365nm)

Fig 9. Penetrant Application on Comp Fig 10. Penetrant Inspection on Comp Stg
Stg #7, Dwell Time : 15 Minute #7, Using Black Light (UV 365nm)

Fig 11. Penetrant Application on Comp Fig 12. Penetrant Inspection on Comp Stg
Stg #8, Dwell Time : 15 Minute #8, Using Black Light (UV 365nm)

Page : 19 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. SPACER PHOTOGRAPHS

Fig 13. Penetrant Application on Comp Fig 14. Penetrant Inspection on Comp Stg
Stg #9, Dwell Time : 15 Minute #9, Using Black Light (UV 365nm)

Fig 15. Penetrant Application on Comp Fig 16. Penetrant Inspection on Comp Stg
Stg #10, Dwell Time : 15 Minute #10, Using Black Light (UV 365nm)

Fig 17. Penetrant Application on Comp Fig 18. Penetrant Inspection on Comp Stg
Stg #11, Dwell Time : 15 Minute #11, Using Black Light (UV 365nm)

Page : 20 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 36/NDT/PT/V/23
PT LEVEL : II DATE : 27-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED
REPAIR
11 EA - COMPRESSOR ROTOR FINAL
DISK STG #1 - #11 PROCEDURE
ASTM E1417 - API 687/616
010/NDT-PT/PRD-GT/II//22
GENERAL PENETRANT DESCRIPTION
TEST AREA : ALL VISIBLE SURFACES ARDROX 970P25E ( FLUORESCENT )
PENETRANT TYPE DWEEL TIME Part Disposition According ARDROX-907 PB ( RED DYE )
FLOURESCENT 15 MINUTE to Specification ZYGLO ZL-27A ( FLUORESCENT )
RED DYE 30 MINUTE Accepted Rejected DEVELOPER APPLICATION :
OTHER : 60 MINUTE MAGNAFLUX ZP-9F
PT - OK
REMOVALL METHOD OTHER :

WATER WASHABLE ( TYPE A )


SOLVENT WIPE ( TYPE C )
EMULSIFIER (TYPE D )

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT :

Inspected by : :
PENETRANT TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 21 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. STATOR PHOTOGRAPHS

Fig 1. Penetrant Application on Comp Fig 2. Penetrant Inspection on Comp Stg


Stg #1, Dwell Time : 15 Minute #1, Using Black Light (UV 365nm)

Fig 3. Penetrant Application on Comp Fig 4. Penetrant Inspection on Comp Stg


Stg #2, Dwell Time : 15 Minute #2, Using Black Light (UV 365nm)

Fig 5. Penetrant Application on Comp Fig 6. Penetrant Inspection on Comp Stg


Stg #3, Dwell Time : 15 Minute #3, Using Black Light (UV 365nm)

Page : 22 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. SPACER PHOTOGRAPHS

Fig 7. Penetrant Application on Comp Fig 8. Penetrant Inspection on Comp Stg


Stg #4, Dwell Time : 15 Minute #4, Using Black Light (UV 365nm)

Fig 9. Penetrant Application on Comp Fig 10. Penetrant Inspection on Comp Stg
Stg #5, Dwell Time : 15 Minute #5, Using Black Light (UV 365nm)

Fig 11. Penetrant Application on Comp Fig 12. Penetrant Inspection on Comp Stg
Stg #6, Dwell Time : 15 Minute #6, Using Black Light (UV 365nm)

Fig 13. Penetrant Application on Comp Fig 14. Penetrant Inspection on Comp Stg
Stg #7, Dwell Time : 15 Minute #7, Using Black Light (UV 365nm)

Page : 23 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT COMP. SPACER PHOTOGRAPHS

Fig 15. Penetrant Application on Comp Fig 16. Penetrant Inspection on Comp Stg
Stg #8, Dwell Time : 15 Minute #8, Using Black Light (UV 365nm)

Fig 17. Penetrant Application on Comp Fig 18. Penetrant Inspection on Comp Stg
Stg #9, Dwell Time : 15 Minute #9, Using Black Light (UV 365nm)

Fig 19. Penetrant Application on Comp Fig 20. Penetrant Inspection on Comp Stg
Stg #10, Dwell Time : 15 Minute #10, Using Black Light (UV 365nm)

Fig 21. Penetrant Application on Comp Fig 22. Penetrant Inspection on Comp Stg
Stg #11, Dwell Time : 15 Minute #11, Using Black Light (UV 365nm)

Page : 24 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

ULTRASONIC TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 37/NDT/UT/V/23
PT LEVEL : II DATE : 28-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED

REPAIR
8 EA - SPACER STAGE 4 -11 FINAL

PROCEDURE
ASTM E 144 - API 687/616
012/NDT-UT/PRD-GT/II//22
TEST AREA : ACCESIBLE AREA
INSTRUMENT Part Disposition According to AMPLITUDE
MFG : RIGOR NDT Specification GAIN (DBS) 42 db
TYPE : RFD1000 Accepted Rejected Review AMPL. (%FSH ) 80%
S.N : A00214110806 TRANSDUCER
UT - OK
CALIBRATION BLOCK SINGLE DUAL
ASTM CERT. F.B. H.: 5/64 ULTRASONIC METHOD STRAIGHT WAVE SHEAR WAVE
V2 BLOCK CONTACT FREQ.(MHZ) 4 -
IIW BLOCK IMMERSSION DIA. (mm) 10 -
STEP WEDGE ANGLE 0 -

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT

Inspected by : :
ULTRASONIC TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 25 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

ULTRASONIC TESTING REPORT


NDT COMP. SPACER PHOTOGRAPHS

Fig 1. UT Inspection and Evaluation on Fig 2. UT Inspection and Evaluation on


Internal Area of Spacer STG #4 Internal Area of Spacer STG #5

Fig 3. UT Inspection and Evaluation on Fig 4. UT Inspection and Evaluation on


Internal Area of Spacer STG #6 Internal Area of Spacer STG #7

Fig 5. UT Inspection and Evaluation on Fig 6. UT Inspection and Evaluation on


Internal Area of Spacer STG #8 Internal Area of Spacer STG #9

Fig 7. UT Inspection and Evaluation on Fig 8. UT Inspection and Evaluation on


Internal Area of Spacer STG #10 Internal Area of Spacer STG #11

Page : 26 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

ULTRASONIC TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 38/NDT/UT/V/23
PT LEVEL : II DATE : 28-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED

REPAIR
11 EA - COMP. DISK STAGE 1 -11 FINAL

PROCEDURE
ASTM E 144 - API 687/616
012/NDT-UT/PRD-GT/II//22
TEST AREA : ACCESIBLE AREA
INSTRUMENT Part Disposition According to AMPLITUDE
MFG : RIGOR NDT Specification GAIN (DBS) 40 db
TYPE : RFD1000 Accepted Rejected Review AMPL. (%FSH ) 80%
S.N : A00214110806 TRANSDUCER
UT - OK
CALIBRATION BLOCK SINGLE DUAL
ASTM CERT. F.B. H.: 5/64 ULTRASONIC METHOD STRAIGHT WAVE SHEAR WAVE
V2 BLOCK CONTACT FREQ.(MHZ) 4 -
IIW BLOCK IMMERSSION DIA. (mm) 10 -
STEP WEDGE ANGLE 0 -

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT

Inspected by : :
ULTRASONIC TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 27 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

ULTRASONIC TESTING REPORT


NDT COMP. ROTOR PHOTOGRAPHS

Fig 1. UT Inspection and Evaluation on Fig 2. UT Inspection and Evaluation on Internal


Internal Area of Comp. DIsk STG #1 Area of Comp. DIsk STG #2

Fig 3. UT Inspection and Evaluation on Fig 4. UT Inspection and Evaluation on Internal


Internal Area of Comp. DIsk STG #3 Area of Comp. DIsk STG #4

Fig 5. UT Inspection and Evaluation on Fig 6. UT Inspection and Evaluation on Internal


Internal Area of Comp. DIsk STG #5 Area of Comp. DIsk STG #6

Page : 28 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

ULTRASONIC TESTING REPORT


NDT COMP. ROTOR PHOTOGRAPHS

Fig 7. UT Inspection and Evaluation on Fig 8. UT Inspection and Evaluation on Internal


Internal Area of Comp. DIsk STG #7 Area of Comp. DIsk STG #8

Fig 9. UT Inspection and Evaluation on Fig 10. UT Inspection and Evaluation on Internal
Internal Area of Comp. DIsk STG #9 Area of Comp. DIsk STG #10

Fig 11. UT Inspection and Evaluation on Fig 12. UT Inspection and Evaluation on Internal
Internal Area of Comp. DIsk STG #11 Area of Comp. DIsk STG #11

Page : 29 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

MAGNETIC PARTICLE TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 39/NDT/MT/V/23
PT LEVEL : II DATE : 28-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED

AS RECEIVED
REPAIR
FINAL
11 EA - COMP. DISK STG 1 - 11 RESIDUAL FIELD CHECK

MAGNETIZATION OTHER
PROCEDURE
ASTM E-1444
TEST AREA : ALL VISIBLE SURFACE 011/NDT-MT/PRD-GT/II/22
MAGNETIZER METHOD Part Disposition RESIDUAL MAGNETISM

MOBILE UNIT RESIDUAL MAGNETISM According to Specification GAUS METER AT SURFFACE :

HEAD SHOT CONTIOUS MAGNETISM ACCEPTED REJECTED - BLADE AREA

COIL PARTICLE MEDIA - CENTER OF DISK


MT-OK
CONDUCTOR WET BATH (FLUORESCENT) DEMAGNETIZED < 2.0 GAUSS
PROD DRY POWDER (VISIBLE) PARTICLE MFG
PARTS WITH DISCOUNTINUITIES
YOKE AC/DC SPRAY CAN (FLUORESCENT) CHEMETALL LUMOR J MARKED

INSPECTION RESULT :

FOUND NO INDICATION (SATISFACTORY),


SEE DETAIL AND PHOTOGRAPHS IN THE ATTACMENT

Inspected by : :
MAGNETIC PARTICLE TESTING LEVEL II

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 30 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

MAGNETIC PARTICLE TESTING REPORT


NDT COMP. ROTOR PHOTOGRAPHS

Fig 1. MT Inspection and Evaluation on Fig 2. MT Inspection and Evaluation on


Com. Disk STG #1 Com. Disk STG #2

Fig 3. MT Inspection and Evaluation on Fig 4. MT Inspection and Evaluation on


Com. Disk STG #3 Com. Disk STG #4

Fig 5. MT Inspection and Evaluation on Fig 6. MT Inspection and Evaluation on


Com. Disk STG #5 Com. Disk STG #6

Page : 31 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

MAGNETIC PARTICLE TESTING REPORT


NDT COMP. ROTOR PHOTOGRAPHS

Fig 7. MT Inspection and Evaluation on Fig 8. MT Inspection and Evaluation on


Com. Disk STG #7 Com. Disk STG #8

Fig 9. MT Inspection and Evaluation on Fig 10. MT Inspection and Evaluation on


Com. Disk STG #9 Com. Disk STG #10

Fig 11. MT Inspection and Evaluation Fig 12. MT Inspection and Evaluation on
on Com. Disk STG #11 Com. Disk STG #11

Page : 32 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


INSPECTED BY : DADANG HERMAWAN REPORT NO. : 40/NDT/PT/V/23
PT LEVEL : II DATE : 28-May-23
QTY PART & SERIAL NO. ITEM DESCRIPTION TEST PERFORMED
AS RECEIVED
REPAIR
22 Ea - NOZZLE STG #1 FINAL

22 Ea - NOZZLE STG #2 PROCEDURE

13 Ea - NOZZLE STG #3 ASTM E1417 - API 687/616


010/NDT-PT/PRD-GT/II//22
GENERAL PENETRANT DESCRIPTION
TEST AREA : ALL VISIBLE SURFACES ARDROX 970P25E ( FLUORESCENT )
PENETRANT TYPE DWEEL TIME Part Disposition According MAGNAFLUX SKL-SP2 (RED DYE )
FLOURESCENT 15 MINUTE to Specification ZYGLO ZL-27A ( FLUORESCENT )
RED DYE 30 MINUTE Accepted Rejected DEVELOPER APPLICATION :
OTHER : 60 MINUTE MAGNAFLUX ZP-9F
10 Ea 47 Ea
REMOVALL METHOD MAGNAFLUX SKD-S2

WATER WASHABLE ( TYPE A ) Note :

SOLVENT WIPE ( TYPE C )


EMULSIFIER (TYPE D )

INSPECTION RESULT :

Good Crack Scrap Other


Nozzle Stg #1 1 21 - Replace Cooling Hole Cup 8 Segment Nozzle

Nozzle Stg #2 2 20 -
Nozzle Stg #3 7 6 -

Inspected by : :
PENETRANT TESTING LEVEL

( Dadang Hermawan )
Note : Prepared by:

ARI HERDIANA
Page : 33 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT NOZZLE STG #1 PHOTOGRAPHS

Fig 1. Penetrant Application on Part, Fig 2. Developer Application, Developing


Dwell Time : 15 Minute Time for Inspectioin : 10 Minute.

Fig 3. Found Crack Indication on Fig 4. Found Crack Indication on Nozzle


Nozzle STG #1 Segment 1 STG #1 Segment 2

Fig 5. Found Crack Indication on Fig 6. Found Crack Indication on Nozzle


Nozzle STG #1 Segment 3 STG #1 Segment 4

Fig 7. Found Crack Indication on Fig 8. Found Crack Indication on Nozzle


Nozzle STG #1 Segment 5 STG #1 Segment 6

Page : 34 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT NOZZLE STG #1 PHOTOGRAPHS

Fig 9. Found Crack Indication on Fig 10. Found Crack Indication on Nozzle
Nozzle STG #1 Segment 7 STG #1 Segment 8

Fig 11. Found Crack Indication on Fig 12. Found Crack Indication on Nozzle
Nozzle STG #1 Segment 9 STG #1 Segment 10

Fig 13. Found Crack Indication on Fig 14. Found Crack Indication on Nozzle
Nozzle STG #1 Segment 11 STG #1 Segment 12

Fig 15. Found Crack Indication on Fig 16. Found Crack Indication on Nozzle
Nozzle STG #1 Segment 13 STG #1 Segment 14

Page : 35 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT NOZZLE STG #1 PHOTOGRAPHS

Fig 17. Found Crack Indication on Fig 18. Found Crack Indication on Nozzle
Nozzle STG #1 Segment 15 STG #1 Segment 16

Fig 19. Found Crack Indication on Fig 20. Found Crack Indication on Nozzle
Nozzle STG #1 Segment 17 STG #1 Segment 18

Fig 21. Found Crack Indication on Fig 22. Found Crack Indication on Nozzle
Nozzle STG #1 Segment 19 STG #1 Segment 20

Fig 23. Found Crack Indication on Fig 24. Found Damage on Cup Cooling
Nozzle STG #1 Segment 21 Hole 8 Segment Nozzle.

Page : 36 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT NOZZLE STG #2 PHOTOGRAPHS

Fig 1. Penetrant Application on Part, Fig 2. Developer Application, Developing


Dwell Time : 15 Minute Time for Inspectioin : 10 Minute.

Fig 3. Found Crack Indication on Fig 4. Found Crack Indication on Nozzle


Nozzle STG #2 Segment 1 STG #2 Segment 2

Fig 5. Found Crack Indication on Fig 6. Found Crack Indication on Nozzle


Nozzle STG #2 Segment 3 STG #2 Segment 4

Fig 7. Found Crack Indication on Fig 8. Found Crack Indication on Nozzle


Nozzle STG #2 Segment 5 STG #2 Segment 6

Page : 37 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT NOZZLE STG #2 PHOTOGRAPHS

Fig 9. Found Crack Indication on Fig 10. Found Crack Indication on Nozzle
Nozzle STG #2 Segment 7 STG #2 Segment 8

Fig 11. Found Crack Indication on Fig 12. Found Crack Indication on Nozzle
Nozzle STG #2 Segment 9 STG #2 Segment 10

Fig 13. Found Crack Indication on Fig 14. Found Crack Indication on Nozzle
Nozzle STG #2 Segment 11 STG #2 Segment 12

Fig 15. Found Crack Indication on Fig 16. Found Crack Indication on Nozzle
Nozzle STG #2 Segment 13 STG #2 Segment 14

Page : 38 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT NOZZLE STG #2 PHOTOGRAPHS

Fig 17. Found Crack Indication on Fig 18. Found Crack Indication on Nozzle
Nozzle STG #2 Segment 15 STG #2 Segment 16

Fig 19. Found Crack Indication on Fig 20. Found Crack Indication on Nozzle
Nozzle STG #2 Segment 17 STG #2 Segment 18

Fig 21. Found Crack Indication on Fig 22. Found Crack Indication on Nozzle
Nozzle STG #2 Segment 19 STG #2 Segment 20

Page : 39 Form-005
INSPECTION DATA RECORDS FORM ID : 001-REV02
ENGINE TYPE - MODULE PART NO. - SERIAL NO. ISSUED BY : ARI H.
SOLAR TURBINE TURBINE ROTOR APPROVED BY :
CENTAUR 45 N/A DATE : 29-May-23

PENETRANT TESTING REPORT


NDT NOZZLE STG #3 PHOTOGRAPHS

Fig 1. Penetrant Application on Part, Fig 2. Developer Application, Developing


Dwell Time : 15 Minute Time for Inspectioin : 10 Minute.

Fig 3. Found Crack Indication on Fig 4. Found Crack Indication on Nozzle


Nozzle STG #3 Segment 1 STG #3 Segment 2

Fig 5. Found Crack Indication on Fig 6. Found Crack Indication on Nozzle


Nozzle STG #3 Segment 3 STG #3 Segment 4

Fig 7. Found Crack Indication on Fig 8. Found Crack Indication on Nozzle


Nozzle STG #3 Segment 5 STG #3 Segment 6

Page : 40 Form-005