You are on page 1of 27

Operating and maintenance manual - Part 3

CONTROGEN HX
Static Excitation System for Hydrogenerator
100MW

Tri An HPP
Vietnam

OPERATING INSTRUCTION

ACCESSIBILITY Free

DATE 2014-05-16

NAME SIGNATURE
WRITTEN BY W.M. CHEONG
CHECKED BY H.L. CHENG

APPROVED D. TOMERLIN

DOCUMENT TYPE
ALSTOM DOCUMENT CODE

REFERENCE LG REV ORIGIN FORMAT STAT. SH/SH NUM SH


END
E C 2 - 4 0 0 0 4 4 - A 4 -
C G O M M - 0 3 - E N EN A PAC A4 REL 1/2727 27

© ALSTOM 2014 - All rights reserved. We reserve all rights in this document and in the information contained therein.
Reproduction, use or disclosure to third parties without express authority is strictly forbidden.Template No.: EM-T-010
Rev.G (20090116)
REVISION HISTORY

REV WRITTEN BY CHECKED BY APPROVED DATE DESCRIPTION STAT.

A W.M. CHEONG H.L. CHENG D. TOMERLIN 2014-05-16 For approval, After FAT REL

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
2/27
TABLE OF CONTENTS
Remarks
Chapters
Yes No
Section 3 OPERATING INSTRUCTIONS 6
3.1 Important Information 6 X
3.2 Risks & Protection 7 X
3.3 Standards & codes 7 X
3.4 General 8
3.5 Safety recommendations 8
3.6 Preparing the system for operation 9
3.6.1 Electrical checking 9
3.6.2 Downloading the system software 10
3.6.3 Downloading the parameters 10
3.7 Operation 11
3.7.1 Controls and indicators 11
Local/Remote control 11
Channel 1/Channel 2 changeover 12
Auto/Manual switching 13
Regulator switching philosophy (double redundant channels auto +manu) 14
Voltage control 15
Reactive power control 15
Fault acknowledgement 16
Setpoint raise \ Setpoint lower commands 17
Field breaker closing / opening 18
Excit ON/OFF 19
“Show standby” and “Show active” for measured values 19
“GENERATOR” and “GRID” for Active and Reactive power measurement 20
“RAMP” sequence or line charging 20
“Sync ON” and “Sync OFF” for voltage matching during synchronisation 21
PSS ON/OFF commands. 21
Bridge1/bridge 2 operation selection. 22
3.7.2 Start-up sequence 22
3.7.2.1 Starting sequence in generator mode 23
Exactly Synchronizing Sequence 23
Self Synchronizing Sequence 24
3.7.3 Shut-down sequence 25
Normal stop sequence 25
Emergency shut-down 27

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
3/27
Remarks
Chapters
Yes No

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
4/27
Notice to readers

The WARNING notice uses this symbol to emphasize that hazardous


voltages, currents, temperatures, or other conditions that could cause
personal injury exist or may be associated with a particular use of
equipment.
In situations where inattention could cause either personal injury or
Hardware damage to equipment, a WARNING notice is used.
The CAUTION notice uses this symbol to emphasize that certain conditions
could cause damage to the equipment operation.
The INFORMATION notice with this symbol merely calls attention to
information that is especially significant to understand and operate the
equipment.
The DOCUMENT notice with this symbol signals a reference to other
documents belonging to the Operation & Maintenance Documentation set.

This document is based on information available at the time of its publication. While efforts have been
made to be accurate, the information contained herein does not purport to cover all details or variations
in hardware or software, nor to provide for every possible contingency in connection with installation,
operation, or maintenance.
Features may be described herein which are not present in all systems. Alstom assumes no obligation of
notice to holders of this document with respect to changes subsequently made.
Alstom makes no representation or warranty, expressed, implied, or statutory with respect to, and
assumes no responsibility for the accuracy, completeness, sufficiency, or usefulness of the information
contained herein. Alstom gives no warranties of merchantability or fitness for purpose shall apply.
In this publication, no mention is made of rights with respect to trademarks or trade names that may
attach to certain words or signs. The absence of such mention, however, in no way implies there is no
protection.
Partial reproduction of this document is authorized, but limited to internal use, for information only and for
no commercial purpose. However, such authorization is granted only on the express condition that any
partial copy of the document bears a mention of its property, including the copyright statement.
© Copyright ALSTOM 2014 - All rights reserved. We reserve all rights in this document and in the
information contained therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
5/27
Section 3 OPERATING INSTRUCTIONS

3.1 Important Information

Alstom Power Systems is committed to high quality products. In


compliance with our high standards of quality.
Users and Installation staff that operate on the equipment are qualified
and are trained.
Before performing any action on the equipment, the user should read
and understand the Operating and Maintenance Manual.
To reduce risks for yourself and your equipment, only an accredited
technician shall service your equipment or work inside it.

Alstom is committed to top customer assistance services.


If you require further information or face serious problem, please
contact:Alstom Power
Alstom Power Systems Customer Assistance
• Hardware repair
• Annual preventive maintenance
• Telephone, e-mail, fax, remote maintenance,
facilities support
• On site intervention on demand
• Software maintenance
• Site support and remote maintenance
• Commissioner and Customer training sessions
• On Site intervention
Contact: helpdesk.control-systems@power.alstom.com

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
6/27
3.2 Risks & Protection

ELECTRICAL PROTECTION
Your equipment may imply various risks for you or your equipment.
These risks essentially concern Electricity
• electric shock
• transient increases and decreases in electrical power
• electrostatic discharge
As a result, you may be injured and/or your operator station may suffer
damage. Please remember that operating or working inside your
equipment may impact your physical integrity.

POWER OFF
Power off your equipment before hardware installation.

RADIO FREQUENCY INTERFERENCE


Most electronic equipment is influenced by radio frequency
interference (RFI). Caution should be exercised with regard to the use
of portable communications equipment around such equipment. Signs
should be posted near the equipment cautioning against the use of
portable communication equipment.

STATIC SENSITIVE DEVICES


Modules in the ALSPA system may contain static sensitive devices
which can be damaged by incorrect handling of the module. The
procedure for module removal is detailed in relevant product
descriptions and must be followed. All ALSPA equipment must have
labels fitted to the personnel to observe antistatic precautions when
touching modules.

3.3 Standards & codes

ALSPA Control System’s operation station has been developed, manufactured and
tested in compliance with the relevant standards.
All these standards are indicated in the following document
ALSPA System - Standards and Codes ptp20a49970
Always bear in mind that optimal operation of the equipment begins with the
compliance with its standards.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
7/27
The abovementioned document specifies the certification, the operating
environment and the electro-magnetic environment in which your equipment should
be operated.

3.4 General

This section gives an operational description of the excitation system along with
relevant safety instructions.
It describes the automatic and manual operating sequences of the regulator.

3.5 Safety recommendations

The personnel must follow all applicable safety regulations in order to avoid any risk.
Before any action detailed in this manual is carried out, the Site Health and Safety
Instructions must be read and fully understood. The instructions in this document
shall also be read and fully understood.
Whenever the equipment is operated, maintained or used in any way, the
procedures in the Site Health and Safety instructions and any procedures detailed in
this document shall be followed.
Before the excitation equipment is powered, all doors of the cubicle must be
correctly closed.
Safety procedures have to be followed to lock the excitation system during
operations inside the excitation cubicle by using a key switch or other equivalent
devices.
High voltages and heavy currents are present inside the cubicle, hence the cubicle
doors must not be opened during operation.
Only authorised personnel may perform manipulations inside the excitation cubicle.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
8/27
3.6 Preparing the system for operation

3.6.1 Electrical checking

After a long period of shut down, the system must be prepared for testing the
insulation of circuits and checking that all power supply voltages are available.

See the wiring diagram for details.


Preparing the test
Check the connection of all power supply cables to the excitation-regulation cubicle.
Disconnect the supply cable from each electronic device, relay, transducer or
converter.
Remove all the fuses from the system.
Check that all protective covers, screens and other safety devices are in place.
Check that the air filters in the excitation cubicle doors are clean.
Insulation test
If the insulation resistance is less than indicated below, an investigation must be
carried out to find the defective circuit.
Measurements are performed using a megger, applying 500 V or 1000 V between
the circuit to be tested and earth for 1 minute.
Power circuits (500 V)
The insulation resistance should be greater than 3 MΩ.
Field flashing circuits and Self-Sync Circuit (500 V)
The insulation resistance should be greater than 3 MΩ.
Control, signalling and measuring circuits (1000 V)
The insulation resistance should be greater than 5 MΩ.
Power supply circuits (500 V)
The insulation resistance should be greater than 5 MΩ.
Check the power supply voltages of:
Field flashing circuit,
Control and signalling circuits,
Regulator 1,
Regulator 2,
Measurement and protection circuits,
Auxiliaries.
When these checks have been completed, continue to:
Reconnect the power supply to all electronic devices and relays, transducers and
converters.
Re-insert the supply fuses.
Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
9/27
Electrical checks
Check the electronic boards, relays, transducers and converters.
Check the control and signalling systems.
Check the relay systems.
Check and correct the settings of the measuring system.
Test the automatic control system.

Check and correct the settings of the protection relays (refer to the setting
specifications of the equipment).
Check the closing and opening command sequences of the switches (field breaker
locked in open position).
Inform the control room that the excitation-regulation system is ready for start-up.

3.6.2 Downloading the system software

Check whether the system software has been downloaded into the regulator, if not,
download it using CONTROCAD. In case of a problem or after replacement of the
CPU board, the system software should be downloaded again.
See the document "Commissioning Guide" for instructions on how to download the
system software.

3.6.3 Downloading the parameters

Check whether the parameters of the project have been downloaded into the
regulator, if not, upload them using CONTROCAD . In the event of a problem after
the CPU board has been replaced, the parameters should be uploaded again.
In the event of a problem after the TTM211 or TPC215 board has been replaced,
the parameters should be checked before operation.
See the document "Commissioning Guide" for instructions on how to download the
parameters.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
10/27
3.7 Operation

3.7.1 Controls and indicators

The following table lists the main controls and indicators of the excitation system.
These controls and indicators are accessed locally, either by using push buttons or
a dedicated ControLCP, and also a remote control system. The controls and
indicators listed below are available on the ControLCP but depend on the project
configuration. Local controls are only active if appropriate user level and local mode
control have been selected.

Please refer to part 2 of “Operating and maintenance manual” document for


supplementary information on the indicators and controls of the ControLCP.

Local/Remote control

The command signals may originate from, and status signals may be displayed at
different locations: the local control system (in front of the excitation cubicle), a
separate control cubicle, or a remote control system (e.g. a DCS system) in a
separate control room.
Remote control means that only the command signals received from the remote
control system are taken into account, therefore the local control system is
disabled.
Local control means that only the commands given on the ControLCP on the
front of the cubicle are effective, whereas the commands from other locations are
ineffective.

To toggle between Local and Remote control refer to part 2 of “Operating


and maintenance manual” document.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
11/27
Channel 1/Channel 2 changeover

In a redundant configuration with two regulators, it is possible to change over


from Channel 1 to Channel 2 and from Channel 2 to Channel 1.
Regulator changeover may be automatic after a fault in the active channel, or it
may be selected by the operator in both control modes, Remote and Local.
Automatic regulator changeover takes place after the following faults:
Excitation overcurrent – 1st stage fault.
Regulator watchdog.
Measuring system fault.
Thyristor firing pulse generator fault.
.
Modbus connection to DCS lost.
Faults indicated above are not exhaustive and further indication on the reason for
changeover can be obtained through the LCP alarm display.
The inactive channel operates in tracking mode, i.e. it behaves as a shadow
regulator; this is to ensure a smooth changeover from one channel to the other.
Channel 1 or Channel 2 is selected either from the ControLCP with the
appropriate user level, or by a command from the remote control system.

To toggle between Channel 1 and Channel 2 through LCP refer to part 2 of


“Operating and maintenance manual” document.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
12/27
Auto/Manual switching

Each channel has an integrated manual mode, and the generator can be
controlled by this manual mode as well.
When the generator is controlled by the automatic mode, its voltage is maintained
constant whatever the network conditions.
When the generator is controlled by the manual mode, only the excitation current
is maintained constant. In case of a network disturbance, it is the responsibility of
the operator to ensure a constant generator voltage by adjusting the excitation
current. The manual mode is mainly used at the commissioning stage, or for
special start-up and maintenance operations.
During operation with the manual mode, when the field breaker is closed, the
excitation current setpoint is set to the no load rotor current value of the
generator. When the generator breaker is opened, the excitation current setpoint
is also automatically set to the no load rotor current value.
At any time it is possible to switch between the automatic and the manual mode
without any problems, since the non active mode operates in follow up mode.
The automatic channel is selected either from the ControLCP, or by a command
from a remote control system. The status is indicated on the ControLCP.

To toggle between the different regulation modes through LCP refer to part
2 of “Operating and maintenance manual” document.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
13/27
Regulator switching philosophy (double redundant channels auto +manu)

If a fault is detected in the active channel, a channel changeover is command


occurs according to the following sequence:

Automatic mode of ACTIVE


CHANNEL

Fault in automatic mode

Standby No
channel OK ?

Yes
Changeover to manual mode of
ACTIVE CHANNEL
Changeover to automatic mode of
STANDBY CHANNEL

No
Fault still
No present?
Fault still
present? Yes
Yes
Tripping
Changeover to manual mode of
STANDBY CHANNEL

No
Fault still
present?
Yes

Yes
Previous regulator
OK ?
No

Tripping

When the manual mode is used, it is essential that the generator is


operated by experienced staff.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
14/27
Voltage control

During operation with the automatic mode, the generator voltage is controlled by
the voltage regulation loop.
It is possible to switch from other regulation modes (reactive power control or
power factor control) to the voltage control mode. To switch to voltage control a
command may be sent either with the ControLCP on the front of the excitation
cubicle, or through the remote control system. When voltage control is in use, this
is displayed on LCP.
As soon as the field breaker is closed, the voltage setpoint is set to the rated
value of the generator.

To toggle between the different regulation modes through LCP refer to part
2 of “Operating and maintenance manual” document.
On ControLCP, the voltage set point can be adjusted by means of lower and
raise commands. In remote control mode, if the external setpoint is validated
(Modbus, HMI or hardwired), the voltage setpoint will be followed with a ramp.

Reactive power control

During operation with the automatic mode, provided the generator is connected
to a network, it is possible to control the reactive power of the generator. For this,
the regulator is switched to the reactive power control mode through the LCP, or
through the remote control system.
When reactive power control is in use, this is displayed on LCP.

To toggle between the different regulation modes through LCP refer to part
2 of “Operating and maintenance manual” document.
When reactive power control is not active, the reactive power set point follows the
actual reactive power. Hence, switching to reactive power control is always
smooth since the generator will keep on working at the same operating point.
On ControLCP, the reactive power set point can be adjusted by means of lower
and raise commands. In remote control mode, if the external setpoint is validated
(Modbus, HMI or hardwired), the reactive power setpoint will be followed with a
ramp.

When the generator breaker is opened, the regulator is automatically


switched to the voltage control mode.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
15/27
Fault acknowledgement

Alarms can be acknowledged through the ControLCP, or through the remote


control system, if any.

To acknowledge faults through LCP refer to part 2 of “Operating and


maintenance manual” document.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
16/27
Setpoint raise \ Setpoint lower commands

These commands are used to adjust the set points for different control modes,
i.e. manual control, voltage control, reactive power control or power factor control.
Only the operational set point is adjusted, the other set points simply follow their
respective actual values.
Setpoint raise \ setpoint lower are given either on the ControLCP on the front of
the excitation cubicle or through the remote control system.

To raise or lower setpoint through LCP refer to part 2 of “Operating and


maintenance manual” document.

Set point changes can also be commanded by means of analogue 4-20 mA


current signals.

Which set point is changed depends on the control mode selected. E.g: If
the voltage control has been selected, the voltage setpoint will be adjusted, but in
manual mode it is always the current setpoint which is adjusted.

This function is available in all operating modes. The setpoint values can
also be set directly by a digital signal from the remote control system (HMI or
Modbus).

Automatic voltage control


If the automatic mode with voltage control has been selected, the operating
point of the generator can be changed by means of Setpoint raise \ Setpoint
lower commands.
As long as the generator is not connected to a power network, the Setpoint
raise \ Setpoint lower commands cause the output voltage of the generator to
change.
When the generator is connected to a power network, the Setpoint raise \
Setpoint lower commands cause the reactive power of the generator to
change.
When the operating limits of the generator are reached, the Setpoint raise \
Setpoint lower commands are no longer effective. This is indicated on the
ControLCP.
Manual current control
If the manual mode has been selected, it is the excitation current of the
generator which is changed by the Setpoint raise \ Setpoint lower commands.
As long as the generator is not connected to a network, the Setpoint raise \
Setpoint lower commands cause the output voltage of the generator to
change.
When the generator is connected to a network, the Setpoint raise \ Setpoint
lower commands cause the reactive power of the generator to change.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
17/27
When the operating limits of the generator are reached, the Setpoint raise \
Setpoint lower commands are no longer effective. This is indicated on the
ControLCP.

During operation with the manual mode, the only limitation is usually that
of the field current, which is not allowed to exceed 110 % of its rated value.
This limit may permit operation with a stator current above rated when the
generator voltage is less than rated.
Optionally, the manual mode may include an upper and/or a lower stator
voltage limitation.
The operator must ensure that the generator's operating point remains within
the range of safe operation (referring to the P/Q diagram of the generator).

When the manual mode is used, it is essential that the generator is


operated by experienced staff.

Reactive Power control (option)


When the generator operates with reactive power control control, the regulator
controls and imposes a reactive power supply consistent with the turbine
power to maintain a constant power factor. The operating point of the
generator can be changed by using the Setpoint raise \ Setpoint lower
commands.
This facility is only available with generators connected to a powerful network.
When the generator is disconnected from the network to operate as an
isolated power source, the regulator is forced to voltage control.
This function is interlocked with the position of the generator breaker or of any
other circuit breaker designed to disconnect the generator from the power
network.
When the operating limits of the generator are reached, the Setpoint raise \
Setpoint lower commands are no longer effective. This is indicated on the
ControLCP.

Field breaker closing / opening

Field breaker closing is selected either on the ControLCP or through the remote
control system. When the field breaker is closed, the status is displayed on the
ControLCP.

To close or open field breaker through LCP refer to part 2 of “Operating and
maintenance manual” document.
On field breaker closing, the setpoint value, depending on the operating mode
(automatic or manual) is automatically pre-set to a previously defined value.
Field breaker opening is selected either on the ControLCP, or through the remote
control system and forces the pulse generator in inverter mode during 200ms
(standard value) and open the field breaker after. When the field breaker is
opened, the ControLCP displays the status of the breaker.
Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
18/27
During operation with the manual mode, the excitation current setpoint is
automatically pre-set to the no load rotor current, as soon as the generator
breaker is opened.

Excit ON/OFF

Excit on is selected either on the ControLCP, or through the remote control


system. The ControLCP displays the status.

To perform Excit ON and Excit OFF through LCP refer to part 2 of


“Operating and maintenance manual” document.
On Excit on, the setpoint value, depending on the operating mode (automatic or
manual) is automatically pre-set to a previously defined value.
Excit off is selected either on the ControLCP, or through the remote control
system and forces the pulse generator in permanent inverter mode without
opening the field breaker. The ControLCP displays the status.
During operation with the manual mode, the excitation current reference is
automatically pre-set to the no load current If0, as soon as the generator breaker
is opened.

“Show standby” and “Show active” for measured values

Measured values of Channel 1 or Channel 2, can be displayed on the


ControLCP.

To show active or standby measured values through LCP refer to part 2 of


“Operating and maintenance manual” document.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
19/27
“GENERATOR” and “GRID” for Active and Reactive power measurement

The active and reactive power values on the generator side on the network side
through ControLCP, or through the remote control system. The ControLCP
displays the status of the selected regulation mode.
This facility is only available when Reactive Power or Power factor control has
been selected.

To select generator or grid regulation through LCP refer to part 2 of


“Operating and maintenance manual” document.

“RAMP” sequence or line charging

The generator voltage can be increased slowly to avoid stressing the generator
windings and to increase the life time of the unit.
The “RAMP” facility must be selected before starting the unit.
It can be selected on the ControLCP, or through the remote control system. The
ControLCP displays the status of the ramp mode.

To select generator or grid regulation through LCP refer to part 2 of


“Operating and maintenance manual” document.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
20/27
“Sync ON” and “Sync OFF” for voltage matching during synchronisation

An external 4-20 mA voltage setpoint may be used for synchronisation purpose


on the regulator.
Sync ON is selected either on the ControLCP or through the remote control
system.
Sync OFF is selected either on the ControLCP, or through the remote control
system.
The ControLCP displays the status of the synchronization.

To select generator or grid regulation through LCP refer to part 2 of


“Operating and maintenance manual” document.

PSS ON/OFF commands.

In special operation, it can be useful to inhibit the PSS operation.

PSS On is selected either on the ControLCP, or through the remote control


system.
PSS Off is selected either on the ControLCP, or through the remote control
system.
The ControLCP displays the status of the PSS.

To inhibit or allow PSS through LCP refer to part 2 of “Operating and


maintenance manual” document.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
21/27
Bridge1/bridge 2 operation selection.

In redundant twin operation, it is possible to select which bridge is in operation.


Selection of bridge is performed through ControLCP.
The ControLCP displays the status of the active bridge.

To select bridge operation through LCP refer to part 2 of “Operating and


maintenance manual” document.

3.7.2 Start-up sequence

When the generator is about to be synchronised with the network for the first
time, check carefully that the phase sequence of the network is consistent with that
of the generator and also that the synchronisation equipment is properly connected
and working correctly. Such checks must be made after any works carried out on
the power circuits, whether on the generator side or on the network side.
Automatic mode
During operation with voltage (V) control using the automatic mode, when the
load is increased, the reactive power does not change as long as the network
voltage is constant.
Any change in the network voltage produces a change in reactive power, which
must remain within the limits of the reactive power capability curve (P/Q
diagram).
With power factor (tan phi) control, the reactive power changes only with the load,
keeping the power factor at its reference value.
With reactive power (Q) control, the reactive power is maintained at its reference
value.
Manual mode
During operation with excitation current control using the manual mode, the
reactive power changes when either the load or the network voltage is changed,
and the operator must adjust the field current set point to keep the generator
within its safe operating range.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
22/27
3.7.2.1 Starting sequence in generator mode

Exactly Synchronizing Sequence

Step AVR received commands AVR status or actions


1
 Unit Exactly Synchronizing Sequence
(digital input command)

Excitation field breaker shall be opened


before the command is applied.

2
 Speed>95% Nn (digital input command) -Exactly Synchronizing
Sequence Selected

3
 Excitation system field breaker closing -DC breaker closing.
-DC or AC Field Flashing
Breaker Close

3
 Generator Voltage Synchronizing with -AVR regulates generator
Line Voltage output voltage to be
balanced with gird voltage
(from TV14).

4
 Synchronization of Generator and Line - Excitation system send
Voltage complete output signal to Control
Panel cubicle, Control Panel
check Voltage + frequence
and Close GCB.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
23/27
Self Synchronizing Sequence

Step AVR received commands AVR status or actions


1
 Unit Self Synchronizing Sequence
(digital input command)

Excitation field breaker shall be opened


before the command is applied.

2
 Speed Threshold Correct ( Digital Input -Exactly Synchronizing
Command) Sequence Selected
-Control Panel will send
signal to Close Generator
Circuit Breaker , (This time
Excitation is still OFF)
3
 Self Sync Contactor closing. -Self Sync Contactor close
-Field Breaker close
• Excitation system field breaker closes
after Self Sync Contactor is closed
4
 Excitation On -AVR raises the field current
to approximately 10%

5
 Self Sync Contactor opens -Self Sync Contactor opens

Remarks:
Self Sync Sequence Condition - Self synchronizing mode is
chosen when exactly
synchronizing is
unsuccessful.

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
24/27
3.7.3 Shut-down sequence

Normal stop sequence

The normal stop sequence is the following:

Step Description AVR status or actions


1
 Reduce the power of the driving - Give +Stp/-Stp commands to
engine (active power will decrease). decrease the reactive power

2
- Reduce the reactive power to
zero before opening the generator
 Reduce reactive power through circuit breaker.
AVR (Normal Unit Stop digital input
command)

3
- Generator breaker opening
- The generator breaker is
 Generator breaker opening opened. This causes the excitation
current reference to be pre-set to the
no-load field current, or the voltage
reference to the value corresponding to
the rated voltage.
4
- Field breaker will be opened
when reactive power is reduced to Zero
 Field breaker opening and GCB is opened,

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
25/27
NORMAL STOP SEQUENCE FLOW CHART

Start

<- Load reduction

Step 1 Load reduced

<- Excitation breaker opening order & main CB open

Step 2 -> Full inverter to cancel field current

<- Time

-> Remain in Full inverter


Step 3
-> Field breaker opening

<- Field breaker opened

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
26/27
Emergency shut-down

Emergency shut-down
An emergency shut down can be selected by the generator protection device.

Step Description AVR status or actions


1
Depending on the type of fault, the driving Tripping fault
engine is tripped or its power is reduced.
The generator breaker is opened
2
The thyristor bridge is forced to operate in Field breaker opening
inverter mode. In all cases, when the turbo-
generator slows down or is stopped, the
field breaker must be opened

Thyristor bridge fault


Depending on the redundancy structure, in case of a thyristor bridge faults (over
temperature, fuse fault, non-conduction) the generator is able to operate without the
faulty bridge. The supply of firing pulses to the faulty bridge is interrupted and
maintenance actions can take place according to the configuration of the excitation
system (excitation system isolated and shut down or during operation of the
generator).

The field breaker cannot be opened unless the generator breaker has been
opened

Copyright © ALSTOM 2014. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Operating and maintenance manual – Part 3 EC2-400044-A4-CGOMM-03-EN


OPERATING INSTRUCTION
27/27