SR.NO DESCRIPTION RATE (Rs) PER REMARK (m3) QUANTITY ( G* I )
EXCAVATION IN SEPTIC TANK FOR GIVEN
1 TYPE OF SOIL UPTO REQUIRED DEPTH 9.282 M3 500 M3 4641 2 PCC ( 1:3:6 ) AT BOTTOM OF SEPTIC TANK 1.235 M3 10000 M3 12350 RCC SLAB AT TOP OF SEPTIC TANK OF 75MM 3 THK 0.234 M3 10000 M3 2340 4 BURNT BRICK MASONARY IN C.M ( 1:4 ) 2.751 M3 3000 M3 8253 5 RCC BAFFLE WALL IN CC ( 1:2:4 ) 0.63 M3 10000 M3 6300 INTERNAL PLASTER FOR SEPTIC TANK 6 INCLUDING BAFFLE WALL 13.3 M2 350 M2 4655 7 MANHOLE COVER 2 NOS 1000 NOS 2000 8 VENT PIPE 5 M 100 M 500 9 COWL 1 NOS 150 NOS 150 10 PVC PIPE OF 80MM DIA ( INLET PIPE ) 2 M 350 M 700 11 PCV PIPE OF 100MM DIA ( OUTLET PIPE ) 5 M 450 M 2250 12 COST 44139 13 ADD 1.5 % OF WORK CHARGE ESTABLISHMENT 662.085 14 ADD 3 % OF CONTIGENCIES 1324.17