You are on page 1of 1

ABSTRACT OF SEPTIC TANK

QUANTITY UNIT OF AMOUNT IN


SR.NO DESCRIPTION RATE (Rs) PER REMARK
(m3) QUANTITY ( G* I )

EXCAVATION IN SEPTIC TANK FOR GIVEN


1 TYPE OF SOIL UPTO REQUIRED DEPTH 9.282 M3 500 M3 4641
2 PCC ( 1:3:6 ) AT BOTTOM OF SEPTIC TANK 1.235 M3 10000 M3 12350
RCC SLAB AT TOP OF SEPTIC TANK OF 75MM
3 THK 0.234 M3 10000 M3 2340
4 BURNT BRICK MASONARY IN C.M ( 1:4 ) 2.751 M3 3000 M3 8253
5 RCC BAFFLE WALL IN CC ( 1:2:4 ) 0.63 M3 10000 M3 6300
INTERNAL PLASTER FOR SEPTIC TANK
6 INCLUDING BAFFLE WALL 13.3 M2 350 M2 4655
7 MANHOLE COVER 2 NOS 1000 NOS 2000
8 VENT PIPE 5 M 100 M 500
9 COWL 1 NOS 150 NOS 150
10 PVC PIPE OF 80MM DIA ( INLET PIPE ) 2 M 350 M 700
11 PCV PIPE OF 100MM DIA ( OUTLET PIPE ) 5 M 450 M 2250
12 COST 44139
13 ADD 1.5 % OF WORK CHARGE ESTABLISHMENT 662.085
14 ADD 3 % OF CONTIGENCIES 1324.17

TOTAL COST 46125.255 SUM(J16:J19)