Professional Documents
Culture Documents
Table of Contents
GLOSSARY ............................................................................................................... 6
1 INTRODUCTION................................................................................................. 8
1.1 PROJECT DESCRIPTION ........................................................................................... 8
1.2 DEFINITIONS ........................................................................................................... 8
1.3 TERMINOLOGY ........................................................................................................ 9
2 CODES AND STANDARDS ............................................................................. 10
2.1 GENERAL .............................................................................................................. 10
2.2 ORDER OF PRECEDENCE ....................................................................................... 10
2.3 EGYPTIAN GOVERNMENT REQUIREMENTS............................................................... 10
2.4 PROJECT DOCUMENTS .......................................................................................... 10
2.5 INTERNATIONAL CODES AND STANDARDS ............................................................... 10
2.5.1 European Union Directives .......................................................................................................... 12
3 SCOPE OF SUPPLY ........................................................................................ 13
Table of Figures
Figure 1-1 Qasr Development Location...................................................................... 8
HOLDS LIST
REVISION HISTORY
GLOS S ARY
N North
NW North-West
PE Protective Earth
RA Risk component (injury to living beings – flashes to a structure)
RB Risk component (physical damage to a structure – flashes to a
structure)
RC Risk component (failure of internal systems -flashes to a structure)
RD Risk for a structure due to flashes to the structure
RM Risk component (failure of internal systems – flashes near a structure)
RU Risk component (injury to living being – flashes to a connected service)
RV Risk component (physical damage to structure flashes to a connected
service)
RW Risk component (failure of internal systems – flashes to the connected
service)
RZ Risk component (failure of internal systems – flashes near a service)
r.m.s Root Mean Square
S Cross-sectional Area of Earthing Conductor
s Second
SLD Single Line Diagram
SOL Start of Line
TN-S Three Phase and Neutral and Separate Earth System
Uo Phase Voltage
V Voltage
Z Impedance
1 INTRODUCTION
Field production is initially handled at the Start of Line (SOL) Qasr Plant. After initial
treatment (cooling and water removal) the gas/condensate is exported to a
combination of the Salam, Tarek and Obaiyed gas plants for further treatment.
The Qasr gas and condensate currently free flows from the wellheads through the
Qasr Phase I and Phase II facilities and export pipelines to the SHAMS manifold and
Salam gas plant under reservoir pressure. As the reservoir pressure declines the
peak gas rate of 800 mmscfd will no longer be achieveable. The Qasr Compression
Project is designed to improve recovery as the reservoir production rate and
pressure decline.
The Qasr Compression Project scope comprises:
• Gas turbine driven single stage compressor sets
• Condensate export pumps
• Power generation
• Utility systems
1.2 Definitions
For the purpose of this specification, the following definitions apply:
CONTRACTING
Khalda Petroleum Company
AUTHORITY OR “CA”
EPC Contractor or
INDEPENDENT
Inspection Body or Authority appointed by the CA
VERIFICATION BODY
1.3 Terminology
The word “shall” is to be understood as a mandatory requirement
The word “should” is to be understood as strongly recommended.
The word “may” is to be understood as an action to be undertaken at the
SUPPLIER’s discretion.
2.1 General
The design, construction and supply of the equipment shall be in accordance with
the latest revisions of the following specifications, Data Sheets, codes and
standards.
2. This Specification
3 SCOPE OF SUPPLY
The scope of work shall consist of the following items, as a minimum:-
4 SITE CONDITION
All earthing and lightning protection devices shall be manufactured and tested to
meet the environmental conditions as defined in the Process and Utilities Basis of
Design, J08509A-P-SD-12001 and HVAC Philosophy, J08509A-M-ST-13201.
Design and selection of the Earthing and Lightning Protection system components
shall therefore be continuously rated for operation in the following ambient
conditions:
Temperature
Maximum ambient air temperature (Outdoor): 50°C (summer)
25°C (winter)
Minimum ambient air temperature (Outdoor): 0°C
Maximum ambient air temperature (LER): 35°C
Minimum ambient air temperature (LER): 15°C
Maximum ambient air temperature (Battery Room): 35°C
Minimum ambient air temperature (Battery Room): 15°C
Altitude
The height above sea level shall be 200m
Humidity
Relative humidity (Outdoor): 100% (Maximum)
Relative humidity (LER): 50% + 10%
Relative humidity (Battery Room): 50% + 10%
Rainfall
Maximum monthly average 28mm (January)
Winds
Maximum wind speed 115 km/h
Design wind speed (mechanical and civil design requirements) 160 km/h
Solar Radiation
A design figure for solar radiation of 1.05 kW/m² shall be applied to predicted flare
radiation levels to assess potential impacts on personnel in the area.
Special Conditions
The area is subject to sandstorms.
5 SERVICE CONDITIONS
The earthing and lightning protection installations shall in all respects be suitable for
operation in the ambient temperatures detailed above. They shall have a design life
of at least twenty years and require minimal periodic maintenance.
The earthing network shall consist of a main grid of bare copper conductors directly
buried in the ground and connected to bored earthing wells with surface link boxes to
permit measurement of earth resistance.
The secondary connections are made with green / yellow insulated copper flexible
conductors of suitable cross-sectional area.
The earthing of the emergency generators star point for the low voltage systems
shall be carried out by connecting the star point to the earth grid creating a TN-S
earthing system as defined in IEC 60364.
Each section of the earthing system shall be sized in accordance with the maximum
earth fault currents possible on the associated section of that circuit. Protective
conductors shall also be sized to minimize the earth loop impedance.
Earthing systems shall consist of earthing wells, earthing grids and equipment,
earthing conductors and above grade equipment e.g. connection buses (BTH). The
BTH shall be utilized as the measurement point for earth system readings.
Earthing grids shall consist of buried-conductor loops installed around all major
process units, building structures, and the electrical substation.
Earthing grids in adjacent process areas and other individual earthing systems shall
be interconnected, in order to ensure that all earthing systems operate at a common
potential.
Earthing grids and conductors shall normally be of bare copper, according to the
earthing system installation.
Insulated copper conductors shall be required under more onerous conditions, such
as exposure to highly corrosive soil conditions, proximity to extensive underground
piping systems or buried metallic structures connected to cathodic protection
systems.
7 BASIC DATA
Local emergency generators at 400V will provide power in the event of failure of the
Main Power Supply and the earth fault current will flow through the generator (star-
point for L.V.) via the protective earth conductor (PE) and to the main earthing grid.
Therefore the earthing system must eliminate the phase-to-earth faults which give
rise to touch or step voltages higher than 50V A.C.
8 CALCULATIONS
I2 ∗ t
S=
K
Where:
In addition, in the case of fault on an external user, the fault current path to earth can
have multiple paths usually through a minimum of two paths; one through the PE
(steel wire armour inside the feeder cable) and the other through the earthing
conductor connected to the main grid, providing a cross-sectional area of PE bigger
than the minimum required.
25mm2 if the earth cables are PVC insulated (to prevent corrosion) copper
or steel
50mm2 if the earth cables are bare copper
The following formula must be satisfied for protection against indirect contact:
Zs * Ia ≤ Uo
Where:
Zs = impedance of the fault loop comprising the source, the live conductor up
to the point of the fault and the protective conductor between the point of the
fault and the source.
TABLE 41A (of IEC 60364) – maximum disconnecting time(s) for TN earthing
systems.
Uo (V) Disconnecting time (s)
120 0.8
230 0.4
277 0.4
400 0.2
>400 0.1
To verify the touch voltage we apply the previous formula at the worst case, (under
emergency generator operation), where we have the lowest earth fault current
(higher distance and lowest cable cross section, hence maximum impedance).
For the proposed design case the maximum disconnection time for any circuit is
0.4s, in order to satisfy the touch voltage requirements. The Contractor shall ensure
during detailed design that electrical protection and protective earth conductors are
suitably rated satisfying the requirements of both voltage and disconnection time.
9 LIGHTNING PROTECTION
The general earthing of the plant shall ensure that the plant is suitably earthed from
the effects of lightning strikes.
The site is situated in an area where there are a high number of lightning strikes per
year and the Contractor shall ensure during detail design that the requirements of
this specification have been met.
(1) Only for structures with risk of explosion and for hospitals with life-saving
electrical equipment or other structures when failure of internal systems
immediately endangers human life
R2 = RB + RC + RM + RV + RW + RZ
R3 =RB + RV
R4 = RA(2) + RB + RC + RM + RU(2) + RV + RW + RZ
Only risk components R1 & R4 are required to be considered for this project.
Because of the need to reconcile the above requirements, with their possible
conflicting demands into one integrated system the normal strategy is to consider
each earthing requirement as a sub-system. All these sub-systems form an
equipotential point that will be the centre of a star earthing arrangement.
As it is most important that every earth within a building remains at the same relative
potential at all times, to avoid flashover, this equipotential point must also be
connected to the Lightning Protection earth of the building or mast. Sub-systems for
consideration are:-
a) Earth system diverting high energy lightning safely to earth via a low impedance
earth net
c) Radio frequency earth system carries only low levels of radio frequency current
but is a likely source of earth loop currents
Where operational problems prevent equipment earth being bonded directly to the
building safety earth the use of a suitable suppresser between the equipment earths
should be considered.
The coupling mechanisms causing transient voltage surges in cables, services etc.
entering or leaving a building are as follows:-
d) High voltage surges transferred from potential rise elsewhere e.g. through the
metal piping of plant and sheaths of connected cables
An air terminal rod shall be provided on top of each tower to protect telecom
antennae.
As far as protection from lightning is concerned, feeders and waveguides are safest
when run down the centre of a tower, since they are shielded from the effects of high
lightning currents by the many members of the tower structure i.e. they act as a
Faraday cage (This can only be achieved if the tower is constructed in a suitable
manner).
When feeder cables are run down the legs of a structure such as a mast it is
impossible to isolate them totally from the effects of lightning. Therefore it is
important to solidly bond to earth coaxial sheaths and waveguide casing at both top
and bottom ends of the vertical run. Feeder cables should be brought off the mast
with the sharpest bend permitted by the manufacturer's specification with the lowest
earth bond made just prior to the bend. On longer feeder runs additional bonding at
approximately 30 metre intervals minimises the risk of side flashing.
To limit any residual induced feeder sheath currents from entering the buildings and
hence equipment it is essential to earth all feeders and waveguides at the building
entry equipotential point and then to the Lightning Protection earth.
Feeder cables should be supported on the horizontal run between tower and
equipment building by being attached to the underside of cable trays or gantries
thereby providing an electrical shield from the effects of horizontally induced lightning
currents. These cables trays or gantries must be adequately bonded to the tower
and the building equipotential earth.
Therefore the structure is suitable for utilising to act as the air termination and down
conductor path. It should be ensured that no aerial or dish mounted to the structure
projects above the top of the tower. If this is the case an air finial(s) shall be installed
to project above the aerial / dish concerned and bonded back into the structure.
Note: In certain satellite dish arrangements involving rotating axle mountings flexible
bonding links may need to be employed within the additional protection method.
One bonding conductor shall be connected to each leg of the tower or to the base of
the mast and taken to an earth termination network (to achieve an overall resistance
to earth of 1 ohm - together with any equipotential bonding that may be required).
Where guy wires are used to support the tower or mast it shall be ensured that the
upper ends of the wires are continuous with the structure, and the lower anchorage
points earthed by electrodes and interconnected into the ring earth conductor of the
system.
Where associated buildings located beneath or local to the tower / mast fall outside
of the zone of protection provided by it, the lighting protection system installed to the
building should be interconnected with that of the tower / mast usually by way of the
earth ring conductor arrangements.
For single tanks the spacing of the bonds and electrodes shall be every 20m of
perimeter for structures up to 20m in height, and every 10m of perimeter for
structures either over 20m in height or where classed as hazardous.
For a group each tank shall have at least two independent connections to the
earthing system. Tanks in groups should be assessed in each case to establish the
exact requirements needed, taking into consideration their arrangement, spacing,
heights etc.
9.11 Buildings
The buildings will be equipped with a Lightning Protection System as detailed in IEC
62305. To establish equipotential bonding the earthing conductors of all systems in a
building will be connected to a single point.
Marshalling cabinets will be provided in the under floor area, to terminate the
incoming cables and house the necessary surge protection devices. From these
cabinets the cables routed into the control room will be designated 'clean' and run in
metal cable trays, bonded and earthed to the equipotential bonding bar.
9.13 Fences
Where the fence is constructed of electrically continuous metal, bonds shall be made
to it at 75m intervals (max) and / or at its corners, and connected via earth
conductors to either the earth termination network of the associated structure / plant
it surrounds, or to individual electrode positions.
Link gate posts via ground conductors and bond gates by flexible connections to
adjacent fence sections.
Should the mast be of non-metallic nature an air finial shall be installed, mounted to
its top, connected to a down conductor and applicable earth termination
arrangement.
For flat roofs a surface air termination network mesh not exceeding a 20m x 10m
grid shall be inserted.
For pitched roofs surface air termination conductors shall be installed to ridges, hips,
and eaves.
On large multiple ridge roofs further consideration may be required to establish the
conductor layout needed dependent on the ridge separation and pitch fall distances.
Where structures consist of portions of various heights and have more than one roof
air termination network the lower roof network should not only be joined to its own
down conductors, but also joined to the down conductors of the taller portions of the
structure. This will ensure that a lightning strike to a lower portion of the structure will
not lead to side flashing to other 'remote' down conductors and will provide a multi-
down conductor path for the lightning current to disperse.
For pitched roof layouts they shall be mounted to salient ridge level(s) at evenly
spaced intervals not exceeding 10 metres.
For flat roof grid layouts they shall be fixed at each intersection and at intermediate
positions along the horizontal conductors spaced no more than 10m apart.
All metallic cladding, projections etc. on or above the main roof surface shall be
bonded to the lightning protection system.
They should be externally installed and located symmetrically around the outside
walls of the structure starting from the external corners. Routing and locations to
avoid side flashing shall be considered.
The number shall be one for each 20m or part thereof of the perimeter at roof or
ground level, whichever is the greater, for structures up to 20m in height. For
structures over 20m in height the spacing should be reduced to 10m or part thereof.
For structures classed as hazardous the down conductors should be spaced at 10m
or part thereof.
A number of earth wells shall be drilled for each of the segregated systems to
achieve the desired resistance to earth of 1 ohm. The number shall be determined
on site based on the soil resistivity survey and the measured values of resistance to
earth of the earthing system. Only when the desired resistance to earth value is
reached will the number of earth wells be deemed to be satisfactory.
The depth of each earth well shall be determined at site depending on the soil
resistivity found during the construction process and this will have to be assessed by
the Contractor.
Connections from the earth wells to the earth mat shall be made to complete the
earthing network.
Earth wells shall be bored into the ground as close as practicable to structures and /
or down conductors.
9.19 Bonds
Where surface tapes are installed to steel frame and / or block work structures
having either metallic or non-metallic cladding, consideration shall be made to
forming bonds between the lightning protection system and the following where
applicable:
To avoid corrosion contact surfaces shall be of adequate area, clean and dry.
Suitable inhibitor paste should be applied to exclude moisture ingress with the finial
bonded connection area wrapped in an approved petroleum - wax - based thixotropic
tape dressing to facilitate future periodic inspection.
External bonding conductors should have a cross sectional area not less than that
employed for the main lightning protection system conductors.
9.20 Joints
The Lightning Protection system shall have as few joints as possible.
Joints shall be mechanically and electrically effective and carried out by the use of
proprietary clamp type connections.
Where overlapping joints occur the overlap shall not be less than 25mm for all
conductors. The contact area should be clean and dry and anti-corrosion inhibitor
paste applied.
The test points should, if possible be mounted approximately 1 metre above ground
level.
The whole of the earth termination network shall have a combined resistance to
earth not exceeding 1 ohm maximum (resistance of grid and termination), without
taking into account any bonding to other services.
Buried ring earth conductors when installed as described above can be considered
as part of the earth termination network and should be taken into account when
assessing the overall resistance to earth value of the installation.
The conductor between the earth termination network and down conductor shall be
of 25 x 3mm bare copper conductor.
9.24.1 General
The instrumentation systems covered in this section may include one or more of
each of the following cubicles:
a) Auxiliary fields interface cubicles (to receive incoming cables from field plant
and provide Zener of galvanic isolation where appropriate
c) ESD cubicles
d) ICSS cubicles
For instrumentation purposes the resistance of the power system network to true
earth should not exceed 1 ohm.
Where applicable, the use of earthing instrumentation systems with and without
Zener barrier diodes is illustrated in the Earthing and Lightning Protection Layout,
drawing number J08509A-E-LY-15450 to 15455.
A protective earth bar shall be provided in each control room / building containing
ICSS systems / instrumentation cubicles.
The exterior metalwork of all instrumentation cubicles and all other cubicles within
the room / building shall be connected to the protective earth bar.
The protective earth bar shall be connected to the main power system plant earthing
conductor ring.
A separate insulated instrument (‘clean’) earth bar shall also be provided in each
control room / building. The instrument earth bar shall be connected radially by
insulated conductor to the instrument earth bars in all instrument cubicles and to the
protective (‘dirty’) earth bar.
Where there is only an instrumentation cubicle, the need for an external marshalling
bar is eliminated and the cubicle instrument earth shall be directly connected to the
protective earth conductor.
Where Zener barriers are being used in hazardous areas an additional Intrinsically
Safe (IS) insulated earth bar shall be provided. This shall be connected radially by
insulated earth conductor to the IS earth bus bars in all auxiliary field interface
cubicles and to the instrument earth bar.
In all cases the cable screen shall be isolated from earth at the field instrument.
(earthed only at the instrument earth bar in the control room).
Where the field instrument housing is Glass Reinforced Plastic (GRP), or continuity
from the housing to the protective earth cannot be guaranteed, separate earthing
conductors shall be provided from each gland to the nearest point on the protective
earth network.
Method B
a) The method of testing against another earth is known as a dead earth test
b) The tester is operated in the normal way and the reading obtained is the
resistance of the earth electrode, combined with that of the "dead earth"
If the resistance of the dead earth can be taken as being negligible, then the reading
obtained is that of the earth electrode.
The test, and subsequent calculations, can offer a guide as to the extent and method
that will be required for the earth termination network.
Reference should be made to IEC 60079-14 for procedures and guidance as to the
type test instructions that can or cannot be used in certain conditions and situations.
10.4 Records
The following records in the form of a logbook or maintenance Manual should be
kept on site or by the person responsible for the upkeep of the Lightning Protection
system upon completion of an installation:
c) The type and position of the earth electrodes include reference electrodes
if applicable
d) The test conditions and results obtained from initial and periodic testing as
outlined in section four
f) The name of the person responsible for the installation or its upkeep
11 QUALITY ASSURANCE