You are on page 1of 5

Installation Method Lafarge can produce

concrete pipe in a variety


The usual construction sequence for tunneling and jacking concrete pipe is:
Installation Method Lafarge can produce
of sizes for trenchless
Installation
The•Installation
Excavate
usual
Method
Method
jacking
construction pits or shafts,
sequence construct
for tunneling andjacking
jackingabutments or thrust
concrete pipe is: blocks, and
Lafarge
Lafarge cancan
concrete pipeproduce
installation in awith
produce variety
the jacking
install jacks, jacking frame and guide rails. concrete
of sizes
concrete pipe
for in
orpipe in a variety
trenchless
tunnelinga variety
methods. The
The The
usual
usualconstruction
construction sequence
sequence forfortunneling
tunnelingand andjacking
jacking concrete
concrete pipepipe is: is:
• Begin jacking
• Excavate tunnel excavation
pits or shafts, by machine,
construct or hand,abutments
jacking dependingoron conditions.
thrust blocks, and of sizes
of installation
sizes for for trenchless
trenchless
with the
pipe sections are jacking
designed
• Lower firstjacking
section of pipe,andposition jacks and abutments
jacking frame, and jack pipe
• •install
Excavate jacks,
Excavate jackingjacking frame
pitspits
or or shafts,
shafts, guide rails.
construct
construct jackingabutments
jacking or thrust
thrustblocks,
blocks,and and installation
installation
or tunnelingwith the
with jacking
the
methods. jacking
for the additional axialThe
forward.
• install
Begin tunnel
install jacks,excavation
jacking by and
frame machine,
and guide or hand, depending on conditions.
rails.
jacks, jacking frame guide rails. or pipe
tunneling
or tunneling
sectionsmethods. TheThe
methods.
are designed
• ••Lower
Continue
Beginfirsttunnel excavation,
section of pipe,
excavation remove
position
by soiljacks
machine, through
and pipe,
jacking insert
frame, succeeding
and jack pipe sections of pipe force encountered in these
Begin tunnel excavation by machine, ororhand,
hand, depending
depending on
on conditions.
conditions. pipe
pipesections
sections are are
designed
designed
between the lead pipe and jacks and jack forward. for the additional axial
operations and can be
• •forward.
Lower
Lower firstfirst section
section of pipe,
of pipe, positionjacks
position jacksandandjacking
jacking frame,
frame, andand jack
jackpipepipe forfor
thethe
additional axial
• •forward.
Repeat
forward.
Continue sequence,remove
excavation, excavation, soil removal,
soil through pipe insertion
pipe, insert succeeding andsections
jacking,ofuntilpipethe force additional
encountered
produced axial
withinports
thesefor
• operation
Continue is complete.
excavation, remove soil through pipe, insert succeeding sections of pipe force encountered in these
• between
Continuethe lead piperemove
excavation, and jacks soil and
throughjack pipe,
forward. insert succeeding sections of pipe force encountered
operations
grout and can inbethese
between
• •between
Consistency
Repeat the lead
the leadofpipe
sequence, pipe andfacilitates
material
excavation,
and jacks
jacks
soilandand easier
jack forward.
removal, grading
pipe
jack forward. and even
insertion compaction.
and jacking, until the operations andorcan
lubrication.
be
•operation
Repeatissequence, excavation, soil removal, pipe insertion and jacking, until the operationswith
produced and ports
can be for
complete.
• Repeat sequence, excavation, soil removal, pipe insertion and jacking, until the produced with ports for
operation is complete. produced
grout with ports for
or lubrication.
• operation
Consistency of material facilitates easier grading and even compaction.
is complete. grout or lubrication.
• Consistency of materialsuch facilitates easier grading and even compaction. grout or lubrication.
• Consistency oflubricant,
Occasionally a material facilitates as bentonite
easier grading slurry,and is pumped into the space between
even compaction.
the tunnel bore and the outside of the pipe to reduce frictional resistance. After the
jacked
Occasionally pipe
Occasionally have
a lubricant, reached
a lubricant, suchsuchtheir
asas final
bentonite position,
bentonite slurry,grout
slurry, isispumpedis frequently
pumped into thepumped
into the spacebetween
space into this
between
thesame
tunnel space
Occasionally bore
the tunnelabore to
and insure
the
lubricant,
and thesuchcontinuous
outside of thebearing
as bentonite
outside pipe to
of the pipeslurry,with
reduce
to reducethe surrounding
frictional
is pumped
frictionalinto soil.
resistance.
the space
resistance. After the
between
After the
jacked pipe
the tunnel
jacked pipe have
bore have reached
and the their
outside
reached final
theiroffinal position,
the position, grout
pipe to reduce is frequently
grout isfrictional pumped
frequentlyresistance.
pumped into into
Afterthis
thisthe
When
same
jacked space
samepipeincreased
to insure
have
space resistance
to reached
insure their develops
continuous
continuous bearing
final due
position,
bearing with to
with soilsurrounding
the
grout
the isconditions
frequentlysoil.
surrounding orpumped
length of
soil. intorun,this
intermediate
same space to insure jacking stations may
continuous bearing be inserted at periodic intervals.
with the surrounding soil. The intermediate
When increased
jacking
When station
increased resistance
pushes
resistance develops
only due
the several
develops duetoto soil
soilconditions
lengths ahead while
conditions or
or length of run,
bearing
length of run,
on the pipe
intermediate
intermediate
behind.
When The use
increased jacking
jacking stations
stations
of intermediate
resistance may may be be
develops jacking inserted
inserted
due to soil atat periodic
periodic
stations
conditions intervals.
intervals.
reduces The
The
axial loads
or length intermediate
intermediate
of run, on the pipe and
jacking
jacking
required
intermediate station
station pushes
jacking
jacking pushes only
capacity.only
stations the the
may several
several lengths
lengths
be inserted ahead
atahead
periodic while
while bearing The
bearing
intervals. on
on thethe pipe
pipe
intermediate
behind.
behind. The The
use use
of of intermediate
intermediate jacking
jacking stations
stations
jacking station pushes only the several lengths ahead while bearing on the pipe reduces
reduces axial
axial loads
loads on
on the
the pipe
pipeandand
required
required jacking
jacking capacity.
capacity.
The number
behind. The useand capacity of the
of intermediate jacksstations
jacking primarily reducesdepends axialuponloadsthe onsize and length
the pipe and of
required
the pipejacking
to becapacity.
jacked and the type of soil encountered. Abutments for the jacks must
The
Thebe number
number andand capacity
capacity of ofthethe jacksprimarily
jacks primarilydepends
depends upon upon thethe size
size and
andlength
length of
thestrong
pipe toenough
be jacked andand largetheenough
type of soil to distribute
encountered. theAbutments
maximum capacity
for the jacks theofjacks to
of must
the pipe
Thethe to behind
number be andjacked
capacityand thethe
of typejacksof soil encountered. Abutments for the jacks must
be soil
strong enough the andbackstops.
large enough toprimarily
distribute depends
the maximum upon the size
capacity and
of thelength
jacksofto
be
thestrong
pipe to enough
be jackedand and largethe enough
type tosoil
of distribute the maximum
encountered. Abutments capacity
for of jacks
the the jacks
mustto
the soil behind the backstops.
the soil behind
be strong enough theand backstops.
large enough to distribute the maximum capacity of the jacks to
the soil behind the backstops.

1. Steel Bell 4. Confined Groove Joint


1. Steel Bell 4. Confined Groove Joint
2.2.Reinforcing
Reinforcing 5.Lube
5. LubeororGrout
Grout Port
Port
1. Steel Bell Cushion 4. Confined Groove Joint
3.3.Jacking
Jacking Cushion
2. Reinforcing 5. Lube or Grout Port
1. Steel Bell 4. Confined Groove Joint
3. Jacking Cushion
2. Reinforcing 5. Lube or Grout Port
3. Jacking Cushion EDMONTON PIPE PLANT
PHONE: (780) 479-5232 | FAX: (780) 410-3699
17
MICRO TUNNELING PIPE
MICRO TUNNELLING PIPE
MICRO TUNNELLING PIPE
> STRAIGHT-WALL PIPE
> STRAIGHT-WALL PIPE
> STRAIGHT-WALL PIPE
Price Per MetrePrice Per Metre Actual Dimensions (mm) Actual Dimensions (mm)
Price Per Metre Actual Dimensions (mm)
Diameter
Diameter (mm) Diameter Diameter
(mm) (in.) (in.) (m) Weight
Length Length (m)
(kgs/m) A Weight (kgs/m)
B A B
Diameter (mm) Diameter (in.) Length (m) Weight (kgs/m) A B
300
300 12” 12” 1.22 1.22
200 445 20070 445 70
300
375
375 12”
15” 15” 1.22
1.22 200
254
1.22 445
500 25470
98 500 98
375
450
450 15”
18” 18” 1.22
1.22 254
337
1.22 500
623 33798
83 623 83
450
525 18”
21” 1.22 337 623 83
525 21” 1.22 509
1.22 713 50990 713 90
525
600 21”
24” 1.22 509 713 90
600 24” 1.22 616
1.22 799 61695 799 95
600
750 24”
30” 1.22 616 799 95
750 30” 2.45 715
2.45 979 109
715 979 109
750
900 30”
36” 2.45 715 979 109
900 36” 2.45 943
2.45 1160 123
943 1160 123
900 36” 2.45 943 1160 123

TUNNEL
> MICRO TUNNELING PIPE WITH STEEL BANDS

TUNNEL
> > MICRO TUNNELING PIPE
MICROTUNNELING WITHWITH STEEL
STEEL BANDS
BANDS

PIPEPIPE
Contact
Contact your Lafarge
your Lafarge Representative
Representative for more
Contact
for more on
information your Lafarge
information Representative
on pipes and
Microtunneling
for more
available information
sizes.
Microtunneling pipes on
and available
Microtunneling pipes and available
Wesizes.
can also offer technical assistance on
sizes.
We can
selecting also offer
trenchless technical
method and designing
We can also offer technical
assistance on selecting trenchless
pipes.
assistance
method and ondesigning
selecting trenchless
pipes.
method and designing pipes.

EDMONTON PIPE PLANT EDMONTON PIPE PLANT


18 PHONE: (780) 479-5232EDMONTON PIPE
| FAX: (780) PLANT
410-3699
17
PHONE: (780) 479-5232 | FAX: (780) 410-3699
PHONE: (780) 479-5232 | FAX: (780) 410-3699
17
CATCH BASIN MATERIAL - 600MM

95 610 95

800
PARTIAL
PARTIAL OPENING FOR
1950

400

150mm -

CATCH BASIN
OPENING

600MM
300mm PIPE
500
250

800

Weight Price
Product
(kgs/pc) ($ each)

600mm x 1.95m catch basin c/w monolithic floor 1005 $679

0.150m x 635mm Grade Ring 120 $113

0.100m x 635mm Grade Ring 80 $100

0.075m x 635mm Grade Ring 60 $95

0.050m x 635mm Grade Ring 40 $90

Notes:
1. 600mm catch basins do not come with steps.
2. For 600mm diameter catch basins, 1.95m is the only available height. Barrels are not available for this size.
3. Catch basins come with 2 lift pins. 4-ton lifting clutches are required. Please inquire.
4. Please see page 23 for additional catch basin material.
5. Gaskets do not come with catch basins. Please inquire if required.
6. If pipe to manhole connector is needed (for smooth wall flexible pipe only) please call for additional price.

EDMONTON PIPE PLANT


PHONE: (780) 479-5232 | FAX: (780) 410-3699
19
CATCH BASIN MATERIAL - 750MM
750mm Catch Basin C/W Monolithic Floor
CATCH BASIN
750MM
LES

Weight Price
Product
(kgs/pc) ($ each)

750mm x 1.83m CB c/w Monolithic Base 1460 $863

750mm x 1.22m CB c/w Monolithic Base 1030 $658

750mm x 1.22m CB Barrel (No Steps) 820 $390

750mm x 0.61m CB Barrel (No Steps) 400 $233

750mm Slab Top with 635mm Opening 220 $265

Notes:
1. Catch basins and riser barrels do not come with steps for this diameter.
2. Catch basins come with 2 lift-pins, 4-ton lifting clutches are required. Please inquire.
3. Please see page 23 for additional Catch Basin material.
4. Gaskets do not come with monolithic catch basins. Please inquire if required.
5. If pipe to manhole connector is needed (for smooth wall flexible pipe only) please call for additional price.

EDMONTON PIPE PLANT


20 PHONE: (780) 479-5232 | FAX: (780) 410-3699
CATCH BASIN MATERIAL - 900MM

900mm Catch Basin C/W Monolithic Floor

CATCH BASIN
900MM
Weight Price
Product
(kgs/pc) ($ each)

900mm x 1.83m catch basin c/w monolithic base 1975 $1284

900mm x 1.22m catch basin c/w monolithic base 1440 $1002

900mm base 420 $413

900mm slab top c/w 910mm opening 195 $385

900mm slab top c/w 635mm opening 315 $387

0.150m x 900mm grade ring w/910mm opening 220 $198

0.100m x 900mm grade ring w/910mm opening 180 $149

Notes:
1. Monolithic catch basins in 900mm size do not come with steps.
2. For 900mm CB’s with steps, use separate base and barrels as shown above. (This method is required for Strathcona County)
3. Please see page 23 for manhole barrel riser pricing.
4. Catch basins come with 2 lift pins cast in. 4-ton lifting clutches are required. Please inquire if required.
5. Gaskets do not come supplied with monolithic catch basin material. They do come included with separate base and barrel configuration.
6. If pipe to manhole connector is needed (for smooth wall flexible pipe only) please call for additional price.

EDMONTON PIPE PLANT


PHONE: (780) 479-5232 | FAX: (780) 410-3699
21

You might also like