This daily safety checklist is for the Bocaue-Balagtas Bulacan subtransmission line project for the month of September 2023. It lists the names and positions of 30 personnel working on the project. Each day, the checklist is used to record inspections of personnel, work practices, and work areas to ensure safety. Signatures are required from all personnel to confirm their attendance and acknowledgement of safety protocols.
This daily safety checklist is for the Bocaue-Balagtas Bulacan subtransmission line project for the month of September 2023. It lists the names and positions of 30 personnel working on the project. Each day, the checklist is used to record inspections of personnel, work practices, and work areas to ensure safety. Signatures are required from all personnel to confirm their attendance and acknowledgement of safety protocols.
This daily safety checklist is for the Bocaue-Balagtas Bulacan subtransmission line project for the month of September 2023. It lists the names and positions of 30 personnel working on the project. Each day, the checklist is used to record inspections of personnel, work practices, and work areas to ensure safety. Signatures are required from all personnel to confirm their attendance and acknowledgement of safety protocols.
PROJECT NAME AND LOCATION: BOCAUE-BALAGTAS BULACAN SUBTRANSMISSION LINE PROJECT
NAME POSITION MONTH OF SEPTEMBER 2023 TYPE OF WORK 25 26 27 28 29 30 ROMEL AGUISANDA SITE SUPERVISOR A. EXCAVATION WORKS (MANUAL OR WITH POWER TOOLS) RIZALINO ALCAUSIN SAFETY OFFICER B. POLE RETIREMENT/POLE ERECTION CRESPOLO ALFEREZ LINEMAN C. POLE DRESSING AND GUYING CHARLIECADIZ LINEMAN D. CONDUCTOR STRINGING WORKS AND/OR RETIREMENT EGLINO EBORDE LINEMAN E. CONDUCTOR SWINGING WORKS RAYMUNDO FROYALDE FOREMAN F. INSTALLATION OF ARMORS AND SPACERS EDRITO MAGALLANES LINEMAN/LEADMAN PERSONNEL ARMANDO MALUYA DRIVER/OPERATOR KENNETH JAMES MALUYA GROUNDMAN A. CHECK FITNESS OF WORKERS JESUS MANGILIC DRIVER/LINEMAN B. PERSONNEL PROTECTIVE EQUIPMENT GLEND PALINO OPERATOR/LINEMAN C. USE OF GLOVES RODERICK PALINO DRIVER/LINEMAN D. USE OF RUBBER GLOVES FOR HOTLINERS RON-RON PALINO LINEMAN WORK PRACTICES RUBEN PALINO LINEMAN/HOTLINER SONNY PALINO LINEMAN A. DISCUSS WORK THOROUGHLY (TAIL GATE CONFERENCE) ROGELIO PEBRIS DRIVER/GROUNDMAN B. SECURE/HOLD CAUTION CLEARANCE CLARENCIO SOBREMONTE OPERATOR/DRIVER C. TEST LINE EQUIPMENT JOJO SUMAWANG DRIVER/LINEMAN D. INSTALLATION OF GROUNDING CLUSTER REGIE SUPAN GROUNDMAN E. ENSURE PROPER GROUNDING OF EQUIPMENT/CHASIS CHRISTOPHER TABAMO LINEMAN F. USE OF PROPER TOOLS/EQUIPMENT/INSTRUMENT MARC TURBOLENCIA LINEMAN G. INSTALL ADEQUATE CONDUCTOR PROTECTIVE COVER CARMELO VILLAMARZO LINEMAN H. OBSERVE LOADING LIMITS OF EQUIPMENT TANNY SALVE DRIVER/LINEMAN WORK AREA RAPHAEL ABAYA GROUNDMAN FRANCIS PASCA LINEMAN/HOTLINER A. BARRICADE WORK AREA RICKY SOBREMONTE HOTLINER/GROUNDMAN B. INSTALL APPROPRIATE WARNING DEVICES & CAUTION SIGNS JAY-AR DOMAQUET GROUNDMAN C. PROVIDE ADEQUATE LIGHTING ( NIGHT TIME SCHEDULES) ROBERT CABARLES GROUNDMAN/LINEMAN D. CHECK/CLEAN WORK AREA AFTER WORK ALJAY DELA CRUZ LINEMAN NOTE: ALL PERSONNEL MUST SIGN WITH THEIR CORRESPONDING NAMES IN LINE WITH LEMMUEL AGAPOR LINEMAN THE DATE PROVIDED ABOVE. NO SIGNATURE, NO ATTENDANCE MARK LAURITO LINEMAN