YEMEN DRILLING JOB SAFETY ANALYSIS

PROJECT DESCRIPTION: SPOOLING WINCH CABLE

CONSIDERATIONS: LINE SHOULD BE CHECKED FOR FLAT SPOTS,BURRS AND CORRISION.OPERATION OF WINCH SHOULD BE DONE SLOWLY.

TASK POTENTIAL ACCIDENT HOW WILL YOU CONTROL


DESCRIPTION OR HAZARD THE HAZARD
TENSION SHOULD BE MAINTAINED ON LINE UNSPOOLING OFF DRUM CAUSING BIRDNESTING FLOORMEN TO MAINTAIN TENSION AS LINE UNSPOOLED
THE WIRELINE AS IT LEAVES THE REEL AND CATSARSES

CARE MUST BE TAKEN TO PREVENT CAUGHT BETWEEN TENSION TO BE KEPT IN LINE


KINKS IN THE LINE AS IT IS UNSPOOLED LINE BURRS

THERE SHOULD BE ENOUGH WIRELINE LINE PULLING OUT OF ANCHOR SREWS ON DRUM. ENSURE LINE HAS ENOUGH LENGTH WHEN ORIGINALLY RIGGED UP
ON THE DRUM TO REACH THE END OF
THE CATWALK AND STILL HAVE 1
LAYER ON THE DRUM

WIRELINE ANCHOR GRUB SCREWS LINE PULLING OUT OF ANCHOR SREWS ON DRUM. DRILLER AND FLOORHANDS TO REGULARLY CHECK SCREWS
SHOULD BE CHECKED FOR TENSION
WHEN ONE LAYER REMAINS ON THE
DRUM AND GRUB SCREWS ACCESSABLE.

REMOVE LINE UNTIL THREE WRAPS LINE PULLING OUT OF ANCHOR SREWS ON DRUM. GRUB SCREWS TO BE CHECKED WHILST 1 LAYER OF LINE STILL ON DRUM.
REMAIN AND LINE SPOOLED AND
TENSIONED ON DRUM

HOLD TENSION IN LINE AND USING BURRS. LINE HANGING UP LINE GUIDE TO BE MAINTAINED IN GOOD CONDITION
AIR TUGGER LINE GUIDE START LINE BURRS , PINCH POINTS. LINE TO BE SPOOLED ONTO DRUM NEATLY
SPOOLING LINE ONTO DRUM.

OPERATION STOPS WHEN WIRELINE LOOSE LINE GETTING ENTANGLED IN FLOOR EQUIPMENT COMMUNICATION AND VISUAL TO BE MAINTAINED BETWEEN WINCH OPERATOR
HOOK REACHES THE FLOOR AND CREW DURING OPERATION
LINE TO BE SECURED AT COMPLETION OF RESPOOLING

Originated by : GRAHAM BLUE DATE December 3 / 03


Date:
Rig # :
JSA # : 11
JOB SAFETY ANALYSIS
PROJECT DESCRIPTION: CHANGING OUT AIR TUGGER LINE

IS A PERMIT TO WORK REQUIRED YES NO


PRE JOB SAFETY MEETING HELD YES NO

TASK POTENTIAL ACCIDENT HOW WILL YOU CONTROL


DESCRIPTION OR HAZARD THE HAZARD

PULL & REVIEW JSA SAFETY


MEETING TRAPPED PRESSURE. BLEED UNIT ASSURE AIR PRESSURE
SHUT DOWN ALL OTHER FLOOR
IS BLEAD OFF.
OPERATION
REMOVE OLD LINE FROM
DRUM POLLUTION, IRRITATION TO PERSONELL USE POLL.PADS.AND SPILL CONTAINMENT

ATTACH SNAKE SKIN FOR 5/8


OD SMALLER AND BAN CLAMPS DUE TO CONTACT. WEAR PROPER P.P.E.
MINIMIZE PERSONEL ON THE
FLOOR
FALLING, BEING STRUK BY FALLING OBJECTS WEAR PROPER P.P.E. KEEP PERSONELL FROM UNDER

CABLE BURRS . WORK AREA.

BLOWING HOSES, AIR PRESSURE EXPOSURE. ASSURE SAFETY PINS ARE IN PLACE. ASSURE THAT LINES
AND VALVES ARE LINED UP PROPERLY.

CABLE BURRS. WEAR PROPER P.P.E.

SAME AS ABOVE SAME AS ABOVE.

WEAR NORMAL PPE AT ALL TIMES

Originated by Checked by