Professional Documents
Culture Documents
Company : Unique engineering and construction public company limited Date : 27 SEP 2023
Ref Locatio Proces Work Remarks
n s Activity
1 PP26 Deep Excavation General site clearance
Top down excavation (From existing ground level to 1st
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
1 - Excavator to be operated
by competent and appointed
operator (4)
- Ensure no workers /
property are in the radius of
the excavator (4)
supervisor
- Deploy Banksman to guide
Hit by moving / Serious injury or the moving (4) - Conduct additional task briefing (3)
- Banksman to stand at safe lV I B t highlight on the high risk area V I C Immediate
slewing excavator fatality to workers (4)
distance away from the (4)
moving excavator (4)
- Excavator warning
lights to be on during
operation (3)
- Ensure un-obstructed cabin
window, so that operator
can have clear view
around (4)
2
- To construct suitable mean
Improper access for of access for machinery and supervisor
machinery workers to work area (3)
Bruises, minor injury
workers may cause - To ensure access is free IV III C - Closely monitor by Supervisor (4) V Ill D Immediate
slip and fall for
for workers from obstruction (4) (4)
workers - Access to be maintain
3
- To embark/ disembark
at safe designated location
(4)
- To maintain 3 point contact
Slip / trip during during embark/disembark - Conduct additional briefing to
Minor injury or (3) supervisor
embark f disembark from excavator at all times IV III C highlight on high risk areas to the V III D Immediate
bruises for workers (4)
from excavator (8) workforce (4)
- Ensure excavator step are in
good condition
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
4
- Prior to start work ensure
emergency access should he
provided (Main — Con) (4)
Workers trapped at supervisor
- No obstruction of
worksite due to - To debrief workforce on
emergency access (4)
insufficient escape Major injury or fatality evacuation procedure (4)
access for to workers
- Assembly point to be IV I B - To update escape route whenever (#) v i c Immediate
clearly stated on site (4)
personnel during there is any site changes (4)
- To abide to Main-Con
emergency
evacuation procedure (4)
- To abide on reporting
flowchart (4)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Obtain approved PTW /
PTD (4)
- Ensure proper safe access
for excavator to travel (3)
- Excavator to be operated
by competent and appointed
operator (4)
- Excavator warning lights
to be on during operation to
warn other operators and
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Ensure no workers / other
machinery or Banksmen are
i n t h e radius of the
excavator (4)
- Ensure sufficient space for
excavators to manoeuvre (4)
- Excavator warning lights
to be on during operation to supervisor
- Conduct additional task briefing
Worker or Property Major injury' or fatality rem other operators and (3)
to highlight on the high risk area
hit by turning / to worker, property workers (3) IV I Immediate
(4) (4)
slewing excavator damage - Ensure un-obstructed cabin
- Close supervision by Supervisor
endow. so that operator can
have clear view around (4)
- Coordinate with adjacent
works and sub-contractors
(4)
- To cordon off work area
and prov ide warning
signage to prevent
unauthorized entry (3)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Ensure proper access
for excavator (3)
- Do not position
excavator on slope or
edge of slope to do
excavation (4)
Poor access way
- Excavator to position at supervisor
due to uneven or
least lm away from the
soft ground - Provide steel plates (3)
Serious injury or edge of slope (4)
condition resuming when necessary (3) V I C Immediate
fatality to workers - Proper machine " (4)
in toppling of - Conduct additional task
parking orientation (4)
excavator and briefing to workers on high
- Excavator must be
filling workers risk areas (4)
on stable ground (4)
- Do not over-excavate
under the Excavator (4)
- Regular visual
inspection to ground
condition especially
after heavy rain
- To apply PTW
for excavation
works (4)
- To engage LCDW to
carry out cable detection
works (3)
- Location of services to - Standing Supervision by
be marked out on site Site Supervisor when supervisor
Damage to by LCDW (3) working near "LIVE"
Property damage,
underground - To carry out trial holes {p {{ services (4) (3)
work delay due to loss V II C
services using manually when working - Trial holes before
of power supply
excavator near utilities prior to actual excavation (4)
Immediate
excavating (4) - If diversion of services not
feasible. liaise with relevant
- Only excavator authority on protection method
operator with valid REO (4)
license to work when
excavating near live
utilities (4)
- Provide Banksmen
for excavator at all
times (4)
- Manual digging when
excavation reaches or
near utilities (4)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Operators to take precautionary
- Stop existing work supervisor
measures when doing excavation
Encounter war relic immediately and
- Execute as according to Main-
(bombs) during Major injury or fatal Qty inform Main-Con (4) I
IV I B Coo Emergency Evacuation Pian Immediate
excavation to workers - Cordon off affected area (4)
(4)
to prevent unauthorised
- Conduct additional TBM to
entry upon discovery of
brief on high risk area (4}
bombs (3)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
-Banksmen to ensure that
no workers and other
machineries working within
- Site Supervisor to supervise supervisor
the loading radius of the
work activity at all times (4)
Hit by falling excavator (4)
Bruises and cuts From - Banksman to stand safe - Site Supervisor to Iiaise and
excavated materials
being hit by sharp distance away from the IV I B coordinate with adjacent I Immediate
during loading onto
objects excavated work area (4) contractors working in The
tipper trucks
- Installed warning signs area during the daily
and cordoned off coordination meeting (4)
excavation area to ensure
no workers are in the
excavation area (3)
- Ensure proper access
and egress provided for
workers io work area (3)
Top down
- Work access to be supervisor
Excavation (from Worker slip/trip clear from any - Conduct additional task
1st Layer to 2nd when accessing onto Minor injury/ bruises obstruction (4) briefing n o h i g h r i s k
layer and continue basement work area a r e a s (4) V III D Immediate
from falling - Workers to adopt proper
to final formation Technique such as 3 point - Conduct internal training to the
level) contact when accessing workforce (4)
any mean of access such
as scaffold access / steps
with rail to the basement
work area (4)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Obtain approved PTW (4)
- Ensure proper safe access
for excavator to travel (3)
- Excavator to be operated
by competent arid appointed
operator (4)
- Excavator warning lights
to be on during operation to
cam other operators mad
workers (3)
- Deploy Banksman to guide
the moving excavator (4)
- Banksman to stay safe - Site supervisor to closely monitor supervisor
distance away for the traffic movement on-site (4)
Worker or Property Property damage,
hit by moving major injury or fatality moving excavator (4) iv I B
- Conduct additional task briefing
to workers on high risk areas (4) (4)
v i c Immediate
excavator to workers - Banksman to keep
personnel or machinery out - Ensure Banksman been brief on
of the path of moving his roles and responsibility (4)
excavator t4)
- Banksman to ensure that
nobody (including himself)
must not be in the blind
spots of the machinery (4)
- Banksman to be equip with
whistle to alert or warn
workers (4)
- Ensure un-obstructed cabin
window. so that operator can
have clear view around (4)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Supervisor to check
periodically For required supervisor
level during excavation (4)
- Instability of - To carry out joint inspection with
- Close coordination with
ERSS design Over-excavation from Main-Con (4)
Main-con surveyor (4) V III D Immediate
- Excavation not as required level. - Site supervisor to closely monitor
- Application of PTW (4) on site (4)
per design
- Excavation as per method
statement submitted (4)
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Responsible Operation
person
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- To obtain approved PTW
(4)
- To ensure forced
ventilation is applied (Main-
con) (3) - Site supervisor to closely monitor
Lack of oxygen/ - To ensure ventilation supervisor
Excavation on site (4)
Presence of toxic system is in working
Works in - Conduct additional briefing on (3)
4 gasses in confined fatality to workers condition (4) IV I B V I C Immediate
high risk areas (4} (4)
areas - Monitor and checking for
Zone - Briefing workforce on the RA and
toxic gasses every 4 hours
SWP (4)
(3)
- Use of tally system for
controlling entry/exit (3)
- Provision of escape points
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Banksmen to ensure that no -Site Supervisor to supervise
workers and other
machineries working within work activity at all times (4)
the loading radius of an -Site Supervisor to liaise and
excavator (4) coordinate with adjacent
Hit by falling - To cordoned off work area contractors working in the area supervisor
excavated with adequate warning signs
material during during the daily coordination (3)
Bruises and cuts (3) IV II C V II C Immediate
loading on to from being hit by - Banksman to ensure no meeting (4) (4)
tipper trucks sharp objects entry to unauthorized
excavated personnel into the work area
(4)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Traffic controller
/Banksmen to ensure that no
machinery / workers
working behind of the tipper
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Personnel must attend
relevant course and
obtain certificates such as
Rigger / Signal Course or
LSSC (4)
- Only competent person
such as the lifting crew
is allowed to carry out
the activity (4)
- To cordoned off lifting
zone and provide warning
signage to prevent
unauthorized entry (3)
- To follow lifting plan
sequence (4)
- Applied lifting PTW prior
to lifting activity (4)
- Lifting Supervisor to
Poor access way - Site supervisor to closely monitor
ensure that the crane supervisor
due to uneven or on site (4)
operator have checked the
soft ground Major injury or fatality - To conduct additional task (3)
7 condition resulting to worker
crane according to the crane IV I B briefing by Lifting Supervisor to V I C Immediate
checklist (4) (4)
in toppling of crane the workforce prior to lifting
- Rigger to check and inspect activity (4)
and hitting workers
the LE before work
commence (4)
- Ensure that the crane is
park at firm ground and steel
plates been provided if
necessary (3)
- Ensure that the crane must
have a sufficient capacity to
hoist the respective materials
or excavator's self-weight
- Rigging/unrigging of the
excavator or materials to be
done by trained Rigger /
Signalman f4)
- Provide proper
communication tools such as
walkie-talkie tor lifting
Team and crane operator (3)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Ensure engine must be
switched off and at towed to
cool to room temperature
before any servicing works
- Leakage of oil
while changing of
- Ensure at I workers to wear
hydraulic / engine - Cover with sand or soil to the
Land pollution proper and approved PPE (5) III III C IV III C supervisor Immediate
oil to the ground affected area it necessary (3)
- Provide drip tray (3)
- Environmental
Hazard
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
- Qualified mechanic with
proper hand tools and an
assistant shall be assigned
- Traffic controller
/Banksmen to ensure that no
machinery / workers - Ensure that the diesel truck
working behind of the diesel drivers to horn before reversing to supervisor
H it by reversing Serious injury or truck (4) IV I B warn others (4) (3) V I C Immediate
Diesel Trucks Fatality to workers
- Reverse alarms and - C lose supervision by Site (4)
warning lights for diesel Supervisor (4)
trucks must be in good
condition (3)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level person Operation
- Provide drip tray (3)
Spillage to the supervisor
- Provide spillage kitto clean - Close supervision by Site
ground during Affects wildlife III III C IV III C Immediate
up any spillage immediately Supervisor (3)
refueling
(3)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Process Responsible
No Hazard Effect Control measure Risk Rating Summary of risks Level Operation
person
Working in raining
environment may - Rąincoat to be provided
- Supervisor to closely monitor
Inclement cause poorer and use (5) (4)
Minor injury. cuts and weather condition (4) supervisor
10 Weather (Non- visibility to - Work to be stopped (5) Immediate
bruises IV IV D - Conduct additional briefing on V IV D
routine) workers, resuIting once visibiIity of
operator is affected (4) workforce on the high risk (4}
V'ea i n s l i p arid
fher raw or hit by
tools
- Drinking water
Working in hot management (4) - Supervisor to closely monitor
Fatality without (3)
weather / under - Sufficient work rest area weather condition (4)
immediate medical (3) IV I B V I C Immediate
sunlight resulting " attention
- Conduct additional briefing on (4) supervisor
heat stress - To remind personnel for workforce on the high risk (4)
good water intake (4)
- Provision of suitable
respiratory mask such as
N95 (5) - Supervisor to closely monitor
- Reduce outdoor strenuous weather condition (4)
Prolonged exposure to supervisor
Working in haze work to all workers. (4) - Get updated info on PSI reading
dust particles: lung V II C Immediate
environment - Conduct haze thru NEA website (4
problems, irritated eyes
communication system IV I C - Conduct additional briefing on
through daily TBM (4) workforce on the high risk (4)
- Ensure workers consume
sufficient water (4)
- Workers to immediately
Thunder/Lightning take cover in lightning - Supervisor to assess situation
may result in Major injury or fatality during inclement weather (4)
protected shelter when there IV I B (4) V I C Immediate
workers being to struck worker - Conduct additional briefing on supervisor
is thunder / lightning
struck by lightning workforce on the high risk (4)
occurrence (4)
MRT Purple Line Project: Tao Pun – Rat Burana (Kanchanapisek Road) Section
Contract 4: Underground Civil Works (Memorial Bridge – Dao Khanong Section)
Responsible
No Process Hazard Effect Control measure Risk Rating Summary of risks Level person Operation
- Proper maintenance of
damage to ear equipment to ensure smooth - Operator to conduct daily check
Excessive noise (4)
drums from running of equipment / on excavator before work start (4)
being transmitted to IV III C (5) V III D Immediate
prolonged machines (4) - Site Supervisor to closely supervisor
workmen.
exposure -To put on earplugs when monitor on site (4)
carrying out the works (5)