Professional Documents
Culture Documents
1 Shuttering 1. Collapse of Injury, death of 4 4 12 H Permit to work to be obtained 1. First Aider 1 4 4 L Site
props. kept
obstruction
Ensure proper stacking of
free and
materials.
clearly
Implement proper
marked and
Housekeeping.
signage
Close supervision by
provided.
competent supervisor.
appropriate punch.
provided.
3 Working at Falling of men/ Injury, fatality 3 4 12 M Provide TBT prior to start the 1. First Aider and 1 4 4 L Project
4 While Fall of personnel Injury, cut, 3 4 12 M Provided TBT prior to start 1. First Aider and 1 4 4 L Site
materials failure in lifting /Severe injury 2. Cranes operator shall be third Supervisor
( Manual & equipment’s party certified. / Foremen
/Fatality
Mechanical) Over loading 3. Trained and certified rigger/
must be provided.
6. Stop lifting activity if the wind
working load.
compacted/Ground leveled.
the area.
suspended load.
6 De-Shuttering 1.Fall of materials 1. Fatalities. 4 4 16 H 1. Permit to work to be obtained 1. Implement Permit 1 4 4 L Project
2. Fall of personnel. Injuries. prior to start De-shuttering work. to work system for Engineer /
The Following Persons Have Received the Information Contained in this Assessment
When completing this Performa, you must take due consideration of local conditions, including adjacent operations and premises.
REV: 01
RISK MATRIX
Risk Rating (RR) = Severity x Likelihood
every 3 years or more) (typically once in a year) (on average quarterly) once a month or more) (once a week or more)
SEVERITY
1 2 3 4 5
(IMPACT)
1-4 Quick, easy controls should be implemented immediately and further action planned for when resources permit. Monitoring required
ensuring controls are maintained. Manage through routine procedures. Go for economic improvements where possible. Incident
Low
report must be completed.
Aim to reduce risks but costs of prevention may be limited. Undertake a risk assessment of the situation / task and implement the
appropriate actions. Actions should have a timescale and should be monitored. Where the risk involves work in progress undertake
5-12 a risk assessment as soon as possible to ensure the safety of the situation or task. Work should not start until the risk is
Medium reduced to an acceptable level. Considerable resources may have to be allocated. Contact your Manager and Risk Manager by
telephone about the actions that should be taken to reduce the risk/s. incident report must be completed. Incident must be added
Do not commence the activity until a risk assessment has been completed to ensure the safety of the situation or task. If it is
15-25 not possible to reduce or eliminate the risk even with unlimited resources, work must remain prohibited. Inform your relevant
High Director, your Manager and the Risk Manager immediately by telephone. Incident report must be completed. Incident must be