You are on page 1of 5

JSA FOR crane operation

Name of the Site - NISSAN (2ASDU PROJECT)


Date of Preparation – 07/01/2014
JSA Preparation – R.RAMESH BABU
S.NO SCOPE OF ACTIVITY HAZARD CONTROL MEASURES REQUEST BY
1) Mobile Crane to 1) Faults with Crane 1) Pre-start Checks EHS SAFETY
onsite destination 2) Plant becoming bogged in sand & 2) Plant to stick to designated roadways and turning areas OFFICER/SECURITY
mud 3) Personnel on hand to warn others of crane movement in the vicinity or via
3) Pedestrians radio where available. OFFICER
4) Onsite Traffic/plant 4) Alternate pathway defined by bollards and reflective tape.
2) Pre-job meeting 1) Inexperienced workers 1) Sufficiently skilled employees to complete task (competencies and EHS SAFETY
and Toolbox 2) Inadequate consultation Licences) OFFICER/SECURITY
3) Inadequate understanding of 2) Adequate consultation with all relevant employees
equipment 3) Adequate competent supervision throughout the project OFFICER
4) Site hazards and emergency 4) Proper planning for equipment required for the task
Procedures not known 5) Site & work area inductions compulsory for all personnel
3) Locate crane into 1) Pedestrians 1) Desired setup area should also be level, EHS SAFETY
lifting positions on 2) Traffic 2) unless prior consultation has been made with the supplier of the crane OFFICER/SECURITY
3) Other Plant 3) The workplace is adequately prepared for the incoming mobile crane,
site 4) Other Equipment including where possible a clear predefined area/crane pad for the crane OFFICER
5) Buildings Power lines & underground to position upon
Utilities 4) Check and confirm exclusion areas - Barricades, witches Hats, Danger
6) Lift radius Access Tape, Warning Signs
7) Ground Conditions 5) Access road are available and soundly constructed with suitable entry
points to site
6) Crew should always inspect site prior to positioning crane in final position
7) Elements to observe include
8) Load location and scope of lift
9) Location of any overhead obstructions including wires, trees, buildings,
restricted airspace (i.e. near airport)
10) Location of any underground services and/or trenches including utilities
and drainage arrangements that may affect integrity of ground
11) Adequate room for rigging and erection of mobile crane
12) Adequate tail (counterweight/winch) swing clearance
13) Ability to cordon off area with suitable barricading
resources
JSA FOR crane operation
Name of the Site - NISSAN (2ASDU PROJECT)
Date of Preparation – 07/01/2014
JSA Preparation – R.RAMESH BABU
4) Inspect chains and 1) Tears in Slings 1) Check slings for rips and tears and remove from service is faults are found
or slings, shackles, 2) Cracks in chains, shackles, rings and 2) Check chains, shackles, hooks and rings for cracks, corrosion, wears,
hooks mechanism faults etc and remove from service if faults are found
hooks and 3) Dropping of load due to faulty 3) Lifting gear/equipment inspected and tagged with appropriate monthly
attachment points in 4) lifting gear or faulty colour tag
preparation for use attachment points 4) Make certain personnel are sufficiently trained with appropriate certificates/
licences

5) Locate crane in 1) Crane overturning due to unstable 1) Outriggers must be positioned on a flat surface,
lifting position on ground condition 2) Using timbers or suitable material for pads to evenly distribute the load to
2) Personnel being crushed by the ground
site outriggers 3) Crane to be located within the radius for the loads being
– place timbers Lifted.
(pads) and set 4) Outriggers should only be extended on the side where the
outriggers Operator is positioned or with a suitable spotter.
5) Where space permits, outriggers shall always be fully extended
6) Where space is limited, crane should be configured to maximum capacity
– this may require the use of reduced outriggers or on rubber; when
permitted by the manufacturer
7) Outriggers shall always be extended to manufacturers procedures and
specifications, including the requirement to fit manual pins
8) All outriggers-jacks should be utilized at all time
9) Generally Standard Safe Working Load capacity charts are based on all
outriggers fully extended and set with wheels clear of ground.
10) Outrigger Packing –
11) Additional packing should always be utilized under outrigger floats
12) Commonly used Outrigger Mats should carry design information and be
subject to periodic inspection
13) When timber packing is utilized, it should be in a ‘pigsty ‘packing
14) Arrangement ‘Rule of Thumb’ formulae and calculations should be
observed;
JSA FOR crane operation
Name of the Site - NISSAN (2ASDU PROJECT)
Date of Preparation – 07/01/2014
JSA Preparation – R.RAMESH BABU
15) Area (m2) = 0.65 x (Cm + L)
-------------
V
Cm = Total mass of crane (KN)
L = Total mass of load (KN)
V = maximum permissible bearing pressure of soil (kpa
6) Attaching Fly or Pin Working at heights/falling 1) Follow W/H permit use appropriate attachment point & safety harness
Jib to Crane when walking along crane boom
2) Use an EWP or ladder for this task & follow safe work practices

7) Position Position 1) Plant to be positioned in area clear of obstruction. Roads


counterweight truck counterweight truck 2) Traffic control in place if required
3) Once crane is elevated and level, a trial operation should be completed by
in an easily in an easily the operator; this may include
accessible spot for accessible spot for 4) Bluffing boom to high angle, and slewing 360 degrees with spotter in
the crane to load its the crane to load its position – purpose to review tail swing and outrigger packing suitability
counterweights counterweights 5) Executing ‘dry-run’ where load is required to be picked up and placed –
Purpose to ensure crane is capable of task and set required limits
JSA FOR crane operation
Name of the Site - NISSAN (2ASDU PROJECT)
Date of Preparation – 07/01/2014
JSA Preparation – R.RAMESH BABU
8) Re-assessing Changes in weather 1) Continual safe operation can be aided by periodic inspection throughout
Situation throughout conditions the project of the following;
job Changes in operators 2) Outrigger Jacks – Leaking oil/retraction of shaft
Changes in ground suitability 3) Outrigger Mats – excessive settlement and/or sinking into ground; i.e.,
loadings increasing beyond estimated capacity of ground – such as
unknown back-filling
4) Outrigger Floats – Cracking or critical damage
5) Evidence of water content in ground
6) Should requirements change during operation, then crew shall re-assess
and review crane capacity and wider environment to ensure revised work
practice is within limits and safe to continue operation

9) 10.Packing up and/or Unauthorised person access 1) Upon completion of project, or specific stage the crane
leaving crane onsite crane site 2) equipment and site shall be left in a secure and safe manner
Damage to crane 3) If the crane is to be left onsite;
Injury to public 4) Retract Boom, remove keys from the ignition and secure/lock
5) Outriggers should be inspected prior to next use
6) Barricading should remain in place around the crane and any work area
deemed necessary
JSA FOR crane operation
Name of the Site - NISSAN (2ASDU PROJECT)
Date of Preparation – 07/01/2014
JSA Preparation – R.RAMESH BABU
10) Packing up and Trip hazards 1) Use correct manual handling techniques
cleaning up work site Manual handling injuries 2) Wear appropriate PPE
Crush & Pinch injuries 3) Rubbish to be placed in bins
Equipment damage 4) Tools & Equipment to be packed
Counterweights coming off 5) Lifting gear packed
the back of the truck 6) Timbers packed
Crush & pinch injuries 7) Pads loaded
8) Make certain counterweights are stacked on rubber mats and correctly tied
Falls
down for trip
9) Guide counterweights onto the truck tray with taglines
10) Where possible use EWP or Platform Ladder Access otherwise be
cautious of footing

11) Exit site and return Overhead Powerlines 1) Crane boom to be down when travelling under power lines
to Depot Collision with 2) Maintain site speed limit when exiting work site
people/personnel and other 3) Communicate with other vehicles onsite is necessary
vehicles/plant when exiting 4) Observe road rules and take into consideration drivers and riders who
site don’t understand the nature of cranes and trucks.
Counterweights sliding off
during travel
Traffic Accident

You might also like