Professional Documents
Culture Documents
Flare systems are typically designed to meet recognized load (e.g., gas compressors from two or more trains failing to
and generally accepted good engineering practice for foresee- stop on demand once blowdown has started, coupled with
able vent and relief scenarios. API 521 [American Petroleum feed gas valves failing to close). Finally, the probability of
Institute, ANSI/API Standard 521 Guide for Pressure- exceeding the flare capacity and the associated consequences
Relieving and Depressuring Systems: Petroleum Petrochemi- were compared against the project’s qualitative risk assess-
cal and Natural Gas Industries, Fifth Edition, American ment matrix to determine if the probability of flare exceed-
Petroleum Institute, 2007] allows for multitrain units to be ance was tolerable. V C 2014 American Institute of Chemical
protected by the same flare system. Therefore, these systems Engineers Process Saf Prog 34: 250–258, 2015
must be reliable, available, auditable, and maintainable. Keywords: fault tree analysis; liquefied natural gas; flare;
However, any designer’s concern should be the possibility of common cause failure; as low as reasonably practicable
a common-cause failure (CCF) that impairs several safe-
guards or causes a plant-wide failure. A shutdown incident INTRODUCTION
can result in flare relief demands that are higher than the There are several approaches that can be used to trans-
designed capacity. CCF is defined as a failure of more than port natural gas from its source to market. One of these
one device, function, or system due to the same cause. Exam- methods involves liquefaction of the natural gas at just above
ples of common causes are errors in design, installation, atmospheric pressure and the resultant cryogenic tempera-
maintenance, or operation of redundant components. To ture. The industry refers to these units as Liquefied Natural
ensure that the designed flare capacity for a Liquefied Natu- Gas (LNG) plants. LNG plants consist of either single or
ral Gas (LNG) facility is appropriate, it is necessary to assess multigas independent liquefaction units called “LNG trains.”
the frequency of relieving combinations that have the poten- Multitrain LNG plants are more common simply because
tial of exceeding flare capacity during a shutdown which is they increase the production availability. Shutting down a
the result from a CCF. A common practice for this purpose is single train in a multitrain unit will not result in an interrup-
to perform probabilistic risk assessment using fault tree anal- tion in production because the plant will continue to pro-
ysis (FTA) techniques during the front-end engineering duce with other (redundant) trains.
design stage. However, CCFs are rarely or not commonly Single or multiple train emergency shutdown (ESD) inci-
considered in the analysis. CCFs might have a significant dents can occur due to fault(s) in the system [1]. When a sin-
impact on the final calculations, resulting in probabilities of gle failure or condition affects the operation of multiple
overloading the flare system by one or more orders of magni- devices that would otherwise be considered independent, a
tude greater, with the potential of not meeting the project’s common-cause failure (CCF) occurs. CCFs are dangerous
tolerability threshold. The analysis starts with the identifica- because they have the potential to impair multiple safe-
tion of CCF scenarios resulting in relief loads from one and guards, leading to plant-wide failures and forcing a possible
multiple trains. Following the identification of these scenar- plant shutdown. This can result in flare relief demands
ios, the frequency of such events is quantified and compared higher than the designed capacity.
with each facility’s tolerability threshold. Historical data from Flare systems are typically designed to meet recognized
published sources were used to calculate the likelihood for and generally accepted good engineering practice for fore-
both CCFs and their impacts. A FTA was used to illustrate the seeable vent and relief scenarios. They are able to handle a
various outcomes that may arise from a CCF producing predefined number of failures and credible combinations of
simultaneous reliefs. The scope of each analysis included a relief events. This is referred as normal flaring. When
facility in multitrain operation with common infrastructure multitrain units are protected by the same flare system, flare
and supporting utility systems. A one train (initial startup overloading is most likely to occur, because of the possibility
case) analysis was done for a baseline comparison, and dif- of a CCF impairing multiple safeguards, or causing a plant-
ferent scenarios were then analyzed for potential flare over- wide shutdown. As such, CCFs must be identified during the
design process and the potential impact on the flare relief
functionality must be understood. Some examples of CCFs
This article was originally presented at the 10th Global Congress include [2]:
on Process Safety, New Orleans, LA, March 31–April 2, 2014.
Errors in design: This commonly refers to hardware
C 2014 American Institute of Chemical Engineers
V design issues, and/or software failures and bugs
METHOD
Figure 1. Probabilistic assessment method.
Overview
The method used to conduct the probabilistic assessment
simultaneously affecting both the process control system can be summarized in three basic steps: problem modeling
and the safety instrumented system (SIS) (including the graphical representation of the relief scenarios
Errors during installation: Redundant components and preparation of input data), probability calculations, and
installed in close proximity, sharing the same physical comparison with tolerability criteria. The detailed method is
illustrated in Figure 1 and described in subsections below:
space, and subject to fire, explosion, or flooding events
Incorrect maintenance or no maintenance: This is likely to
Understand Process Design and Identify Flare Overloading Scenarios
happen when the same operator, for some reason, makes
Project documentation, including process flow diagrams
the same mistake when calibrating a set of redundant
(PFDs) and piping and instrumentation diagrams, is reviewed
sensors.
in order to understand the process, its safeguards, the shut-
Finally, to ensure that the designed capacity is appropriate, down philosophy, and to identify the major flare overloading
it is necessary to estimate the likelihood of exceeding the flare scenarios. Under the assumptions for this work, a flare relief
capacity, and compare this probability with a tolerability event might occur when a total power loss incident or a
threshold. The tolerability in this context refers to the willing- plant-wide failure happen, forcing a plant shutdown. An
ness by society as a whole to live with a risk in order to excess flare relief event is then likely to occur if some critical
secure certain benefits in the confidence that the risk is one components fail causing the impairment of safeguards and
that is worth taking and that it is being properly controlled. protective functions.
Process Safety Progress (Vol.34, No.3) Published on behalf of the AIChE DOI 10.1002/prs September 2015 251
Electronics Engineers (IEEE) [4], Stiftelsen for Industriell og Compare Probability against Project Tolerability Criteria
Teknisk Forskning (SINTEF) [5], Centre for Marine and Petro- Once the probability of exceeding flare capacity is deter-
leum Engineering (CMPT) [6], and International Association mined by analyzing foreseeable combinations of multitrain
of Oil and Gas Producers (OGP) [7]. scenarios, the risk can be qualitatively or semiquantitatively
assessed using a risk assessment matrix. Applicable company
Model the Causes of Each Simultaneous Relief Scenario or regulatory standards in risk assessment can and should be
The identified flare overloading scenarios, including their applied to compare the risk to the appropriate tolerability
initiating events and CCFs (called basic events) can be mod- criteria. Risk tolerance (project’s tolerability threshold) is typi-
eled by using a fault tree analysis (FTA) approach. FTA is a cally defined based on common practice or client’s input,
tool for systematically identifying root causes of an undesired and it is not part of the scope of this article. For this study,
event (top event), by graphically representing their basic the results were compared to an assumed tolerability thresh-
events and interdependencies, and by calculating the proba- old of 1.00 E 207 in 1 year.
bility of the top event occurring, in this case the flare over- It should be noted, though, that for typical onshore facili-
loading event. ties, this threshold could range between 1.00 E 204 and 1.00
E 207 in 1 year, depending on land use around industrial
Determine the Probability of Exceeding Flare Capacity for Each facilities and other factors. For example, the Major Industrial
Simultaneous Relief Scenario Accidents Council of Canada [9] sets acceptability levels of
Fault trees are typically quantified by first calculating the 1.00 E 205 to 1.00 E 206 in 1 year for “. . .uses involving con-
probability of basic events (initiating events, failure of pro- tinuous access but easy evacuation, e.g., commercial uses, low
duction train safeguards, CCFs, etc.) as seen in Table 1, and density residential areas, offices” and beyond 1.00 E 206 in 1
then combining the different outcomes of these basic events year for “. . .all other land uses without restriction including
through logic gates (AND, OR) into one single top event, in institutional uses, high density residential areas, etc.”
this case the probability of exceeding flare capacity.
Failure of basic events can further be classified as either CASE STUDY
“detected” or “undetected.” Undetected failures are usually The case study presented in this section illustrates the
evaluated as “probability of failure on demand” (PFD). The effect of considering CCFs in the risk analysis of the flare
probability of failure on demand quantifies the likelihood overloading scenarios, compared with the same case without
that a system will fail to perform as designed due to danger- the consideration of CCFs. In this case study, it is assumed
ous undetected failures (with rate k failures per year) during that an excess flare relief event might occur in a typical
the period when it is not known that the function is unavail- multitrain LNG plant when an initiating event and a defined
able [8]. The average duration of this period is T/2, where T set of equipment components simultaneously fail due to a
5 test period. For small values of kT (less than 0.02), CCF. Figure 2 shows a block flow diagram depicting a simpli-
PFD 5 kT/2. fied version of the liquefaction subsystem of one LNG train. It
The probability calculation for multiple redundant compo- uses a typical cascade liquefaction process with the usual heat
nents assumes a repairable system with unrevealed failures exchangers, refrigeration loops, and emergency shutdown
where function tests are carried out simultaneously [5]. A SIS valves (SDVs) for the inlet feed gas (the high integrity pres-
with M out of N (MooN) voting scheme will achieve its func- sure protection system [HIPPS] valves shown in the figure).
tion if at least MooN components execute the system com- This simplified plant can operate under two configura-
mand upon signal (in this case to stop on demand). In other tions: one train or two parallel trains. The one-train scenario
words, the system can tolerate N 2 M failures, but not more. is powered by four active electrical generators, one spare
For example, for a system where 17 out of 18 units are generator, six refrigeration compressors, and three SDVs for
the feed gas. The number of components for the two-train
required to operate (17oo18 voting) then “18 2 17 1 1 5 2”
scenario is almost doubled, except that the power generation
must fail for the system to fail. unit only adds two extra active generators. By design, the
The modeling of CCFs can be performed by using the power generation system is common to both trains.
multiple beta factor model described in the SINTEF method
[5]. The multiple beta factor model also considers common
One-Train Scenario
cause factors (b) as the standard beta model but introduces
a correction factor C(MooN) that modifies the contribution
Initiating Event (OR gate)
of CCFs for different voting configurations (See Table 2).
This common cause factor varies with the number of com- Local power loss, assumed to occur when 2oo4 gas
ponents involved. turbine generators (GTG have a critical failure AND
252 September 2015 Published on behalf of the AIChE DOI 10.1002/prs Process Safety Progress (Vol.34, No.3)
Table 1. Failure frequencies and probabilities.
the running spare GTG fails to ramp-up electrical load Two-Train Scenario
on demand.
ESD, prompted by operator action in case of a signifi- Initiating Event (OR gate)
cant (>50-mm hole) hydrocarbon release in 1oo6
compressors. Local power loss, assumed to occur when 3oo6 GTG
Inadvertent manual shutdown. have a critical failure AND the running spare GTG fails
to ramp-up electrical load on demand.
Equipment Failure ESD, prompted by operator action in case of a signifi-
cant (>50-mm hole) hydrocarbon release in 1oo12
2oo6 compressors fail to stop on demand AND feed compressors.
valves fail to close on demand in a single train. Inadvertent manual shutdown (1oo2 trains).
Process Safety Progress (Vol.34, No.3) Published on behalf of the AIChE DOI 10.1002/prs September 2015 253
Table 2. Common cause factors.
*b Factor ranges between 0.01 for highly diverse components to 0.1 for similar components or systems [8].
**C(MooN) means modification factor for MooN success (voting) configuration.
†
Common cause factor 5 b 3 C(MooN).
Figure 3. Fault tree for one-train scenario—includes CCF events. [Color figure can be viewed in the online issue, which is
available at wileyonlinelibrary.com.]
254 September 2015 Published on behalf of the AIChE DOI 10.1002/prs Process Safety Progress (Vol.34, No.3)
Figure 4. Fault tree for two-train scenario—includes CCF events. [Color figure can be viewed in the online issue, which is
available at wileyonlinelibrary.com.]
following the plant shutdown, an excess flare relief event is Figure 4: Fault tree diagram for the two-train scenario
not likely to occur. including CCF events. For the no CCF case, it is assumed
Now, an excess flare relief event is possible if some criti- that CCF in the model is zero.
cal components fail causing the impairment of safeguards
and protective functions. In general, these flare relief sys-
tems are designed to safely handle a wide range of relief FTA Results
loads, but specific combination of component failures, The results of the analyses (probability of overloading
either in one train or mixing components from different the flare system in 1 year) are presented separately in
trains have the potential to trigger an excess flare relief Table 3 (one-train scenario) and Table 4 (two-train sce-
nario). Values in bold represent the calculated probabilities
event.
for the the main gates of each fault tree (Top event, initiat-
ing events, and relief events).
RESULTS
Process Safety Progress (Vol.34, No.3) Published on behalf of the AIChE DOI 10.1002/prs September 2015 255
Figure 4. (Continued)
adjustments to bring flare exceedance to tolerable levels, and possibly redesign the ESD control panel, and
and iteration of the fault trees until the tolerability increase the quality of operators training and aware-
threshold was met. Had the impact of CCFs been ness to minimize the possibility of human error result-
neglected, the resulting probability would have been ing in inadvertent shutdown.
deemed satisfactory which would have potentially yielded Risk driver 2: Increase the testing frequency of
misleading conclusions. components used on demand to increase their reliability
Since the risk did not meet the tolerability criterion, the (e.g., fuel gas valves used to stop the gas turbines
project team made the following recommendations: driving the refrigeration compressors, feed gas HIPPS
valves).
Risk driver 1: Perform a detailed human factors reliabil- Perform additional evaluations to evaluate further risk
ity study to improve operational procedures, examine reduction.
256 September 2015 Published on behalf of the AIChE DOI 10.1002/prs Process Safety Progress (Vol.34, No.3)
Table 3. Fault tree analysis results (one-train scenario).
Process Safety Progress (Vol.34, No.3) Published on behalf of the AIChE DOI 10.1002/prs September 2015 257
initiated simultaneous shutdown events. Furthermore, the LITERATURE CITED
rupture frequency data is dominated by compressor 1. NASA, Fault Tree Handbook with Aerospace Applica-
releases. Source: Process Release Frequencies, OGP, tions, NASA Office of Safety and Mission Assurance,
Report No. 434-1. March 2010, Section 2.0 – Equipment Washington, DC, 2002.
Type: (9) Compressors Centrifugal – Hole
diameter > 50 mm – Limited Releases. 2. OREDA, Offshore Reliability Data Handbook, 4th ed.,
5. Large gas release event probability (1oo6 Prepared by SINTEF Technology and Society, Trondheim,
compressors) 5 1 2 (1 2 3.50 E 204)6 5 2.10 E 203 in 1 Norway, 2002.
year. The calculation is based on the “addition rule” [8] 3. American Petroleum Institute, ANSI/API Standard 521,
where the probability of one or more of n events occur- Pressure-relieving and Depressuring Systems, Fifth Edi-
ring is: 1 2 (1 2 Pa)(1 2 Pb),. . ..,(1 2 Pn). If all items tion, American Petroleum Institute, Washington, DC,
are the same, the formula reduces to 1 2 (1 2 Pa)n. 2007.
6. Probability of failure to stop one Gas Turbine Compressor 4. IEEE 493 - Recommended Practice for the “Design of
(GTC) on demand 5 PFD(1 GTC) 5 (8.50 E 203)1/ Reliable Industrial and Commercial Power Systems,” Insti-
2 5 4.25 E 203 in 1 year. The probability of failure on tute of Electrical and Electronics Engineers, 2007, Avail-
demand for safety systems not used continuously or only able at http://standards.ieee.org/downloads/493/
in emergencies, assuming a constant failure rate k and a 493-2007/493-2007.AnnexQ.pdf [Accessed 14 October
test interval T, can be approximated by the following 2014].
expression if kt is small: PFD5 kT/2.
7. Probability of failure to stop 2oo6 Gas Turbine Compres- 5. SINTEF A17956, Reliability Prediction Method for Safety
sors (GTC) on demand 5 PFD(2oo6 GTC) 5 1 2 (1 2 Instrumented Systems – PDS Example Collection, SINTEF
[PFD(GTC1) 3 PFD(GTC2)]) 3 (1 2 [PFD(GTC1) 3 Technology and Society, 2010 Edition, Available at http://
PFD(GTC3)]) 3 . . . 3 (1 2 [PFD(GTCn 2 1) 3 www.sintef.no/project/PDS/Reports/PDS%20example
PFD(GTCn)]) 5 1 2 (1 2 [PFD(1 GTC) 3 PFD(1 %20collection%2024-01-11_open.pdf [Accessed 14 Octo-
GTC)])Comb(2oo6) 5 1 2 (1 2 [4.25 E 203 3 4.25 E ber 2014].
203])15 5 2.71 E 204 in 1 year. The calculation is based 6. Centre for Marine and Petroleum Technology (CMPT), A
on the “addition rule” [8] where the probability of one or Guide to Quantitative Risk Assessment for Offshore
more of n events occurring is: 1 2 (1 2 Pa)(1 2 Installations, CMPT, Aberdeen, UK, 1999.
Pb),. . ..,(1 2 Pn). If all items are the same, the formula 7. International Association of Oil & Gas Producers (OGP),
reduces to 1 2 (1 2 Pa)n. In this case, “Pa” is the proba- Process Release Frequencies, Report No. 434-1, March
bility of two of the GTCs failing to stop, for example, 2010, Available at http://www.ogp.org.uk/pubs/434-
GTC1 and GTC2, joined by an AND gate. 01.pdf [Accessed 14 October 2014].
Comb(2oo6) 5 15 means that we can arrange 15 combi-
nations of two elements out of six. 8. D.J. Smith, Reliability, Maintainability and Risk, 7th Edi-
8. Probability of failure to close one feed valve (HIPPS) on tion, Elsevier, Oxford, UK, 2005.
demand 5 PFD(1 feed valve) 5 (6.79 E 202)1/2 5 3.49 E 9. Major Industrial Accidents Council of Canada (MIACC),
202 in 1 year. The probability of failure on demand for Risk-Based Land Use Planning Guidelines, First Edition,
safety systems not used continuously or only in emergen- 1995, Available at http://www.cheminst.ca/sites/
cies, assuming a constant failure rate k and a test interval default/files/pdfs/Connect/PMS/Risk-Based%20Land
T, can be approximated by the following expression if kt %20Use%20Planning%20Guidelines.pdf [Accessed 14
is small: PFD 5 kT/2. October 2014].
258 September 2015 Published on behalf of the AIChE DOI 10.1002/prs Process Safety Progress (Vol.34, No.3)