You are on page 1of 2

led away to a water-recharging

system specifically constructed


by the owner/ management of
the fuel station/ facility in case
lined drains of sufficient length
upto a natural course/ outfall
sewer are not available.
21 i. Provision of drinking Drawing showing these Yes/No
water and toilet facilities arrangements as per
ii. Provision of proper satisfaction of highway
drainage arrangement for authorities to be submitted
fuel station premises

22 Provision of adequate signs, Minimum requirement as Yes/No


display board and markings as per shown in the Drawing
the drawings
23 Whether the oil company has Yes/No
certified that the fuel station is ____
neither in operation nor energized
and that construction of the fuel
station has not been commenced.

C. Retail Outlet on Urban/ Hilly/ Mountainous Stretches


Sr. Item Measurement MORTH Whether
No. at site Norms complying
with MORTH Norms**
1 Distance form intersection:
Intersection with any category of 100 m Yes/No
road/ Median Gap
2 Distance from Check barrier/ Minimum 1000m Yes/No
Toll Plaza/ Railway level
crossing
3 Distance from start of approach Minimum 200m Yes/No
road of Road Over Bridge
4 Distance from start of Grade Minimum 300m Yes/No
Separator/ Flyover
5 Distance from nearest Fuel 300 m. Yes/No
Station
However, this restriction shall
Undivided carriageway (for both
not apply in case access/
side of carriageway) and
egress for all such fuel
Divided carriageway (with no
stations are provided through
gap in median at this location)
common service road of 7.0m
width and not directly to NH.
Further, access for fuel
stations at closer proximity
than 300m may be allowed
provided entry/ exit for both
the Fuel Stations are provided

26
through service road of 7.0m
width having sufficient length;
further, additional length of
such service road shall be
constructed at the cost of the
latter fuel station owner/
company seeking grant of
permission for access for the
facility.
6 Provision of service /connecting Necessary at clustering of Yes/No
road retail outlet/ intersection with
any category of road less than
300 mtr
i. Length of the service [Mention the lengths in m]
road including
deceleration and
acceleration lanes

ii. Whether additional Yes/No


Land acquisition is
required (for service
road/ turning radius)

iii. If Yes, mention the [Mention Area (sq. m.)]


extent of additional L.A.
required

iv. Whether additional Yes/No/


Land Acquisition as Not Applicable
above has been done
by oil company

v. If Yes, whether the Yes/No/


documentary evidence Not Applicable
of the L.A. details are
attached

7 Gradient of Highway section Maximum 5% Yes/No


8 Slope of Fuel Station Minimum 2% Yes/No
Premises/Service Area for
drainage purpose
9 Width of Frontage of Plot Minimum 30 m for Urban area, Yes/No
20m for Hilly/ Mountainous
area
10 Depth of Plot Minimum 30m for Urban area, Yes/No
20m for Hilly/ Mountainous
area
11 Length of Buffer Strip Minimum 5m Yes/No
12 Width of Buffer Strip extending Minimum 3m Yes/No