You are on page 1of 4

PROJECT: EMBASSY CENTRAL

OWNER: URBAN LAND CENTRAL BKK CO., LTD.


CONTRACTOR: CANASINO CONSTRUCTION CORPORATION

METHOD STATEMENT FOR CONSTRUCTION


ITEM: SOIL TERMITES TREATMENT METHOD

CONSTRUCTION DEPARTMENT:
SURVEY DEPARTMENT:
QA/QC DEPARTMENT:

PHNOM PENH 10-2016 DOC. CODE:


NOTES :

00 CONSTRUCTION 06-OCT-16

REV. AMENDMENTS DATE

TENDER
PRELIMINARY
FOR APPROVAL
FOR CONSTRUCTION
REVISED
AS-BUILT

CLIENT :

AUTHORITY`S/CLIENT APPROVAL :

ARCHITECTS :

SOIL TERMITES TREATMENT METHOD STATEMENT SOIL TERMITES TREATMENT METHOD STATEMENT
1 STEP-1: APPLICATION OF TERMITE CHEMICAL SOLUTION UNDER THE STAGE
2 STEP-2: APPLICATION OF TERMITE CHEMICAL SOLUTION UNDER THE BEAM
BEFORE PILE CAP LEAN CONCRETE. BEFORE LEAN CONCRETE.

CONTRACTOR :

Canadia Tower :
22nd, No.315, Ang Duong St. Phnom Penh, Cambodia
TEL : (855) 23-990-815 E-mail : info@canasino.net

PROJECT MANAGER : (MR.) HUANG ZHONG GUO

CHEF ENGINEER (MR.) PHAN HUU DUC

TECHNICAL MANAGER (MR.) VOEK PITOU

CHECKED BY : (MR.) VOEK PITOU

DRAWN BY : (MR.) SAMNANG PISAL

PROJECT MANAGEMENT :

LEGEND
OPERATING WORK OF SOIL TERMITES
TREATMENT.

ADDRESS:
READY WORK OF SOIL TERMITES
UrbanLand Tower
TREATMENT. #20E0 ,St.51. SK.Boeung Keng Kong 1
Phnom Penh, Cambodia

SITE LOCATION :

PHNOM PENH, CAMBODIA

ITEM :

SOIL TERMITES TREATMENT METHOD STATEMENT SOIL TERMITES TREATMENT METHOD STATEMENT SOIL TERMITES TREATMENT METHOD
3 STEP-3: APPLICATION OF TERMITE CHEMICAL SOLUTION UNDER PIT BEFORE
4 DRAWING TITLE :
STEP-4: APPLICATION OF TERMITE CHEMICAL SOLUTION ON NATURAL LAND
SLAB CASTING. BASEMENT OUTSIDE.
SOIL TERMITES TREATMENT METHOD

SCALE : DATE : 06-OCT-2016 REVISION : 00

DWG NO : EMB-ST-001
Soil Termites Treatment Method Statement
1. Inspection and consulting with clients at project site.
2. Use PVC pipe size 21mm and 13.50 of thickness.
3. Application of termite chemical solutions under the pile stage before lean concert.
4. Application of termite chemical solutions under the besetment building structure with the rate of premise at the rate
of 5 (five) liters per square meter.
5. Plastic cover after chemical spray before lean concert or slab.
6. Install PVC pipe before laying the concrete slap on natural land around besetment outside (PVC had wrapped by
G.O Tech Style on every small holes).
7. Chemical spray into the soil at outdoor wall of basement.
8. Chemical spray on the soil 0.50m or 1.00m around from outdoor wall after land preparation.
9. Re-check after the work has been completed.

Application of termite chemical solutions under the Application of termite chemical solutions under the
pile stage before lean concert. beam before lean concert.

Application of termite chemical solutions Application of termite chemical solutions under the
under Pit before slab. beam before lean concert.
Plastic cover after chemical spray before lean concert Install PVC pipe before laying the concrete slap on
or slab. natural land around besetment outside

You might also like