Professional Documents
Culture Documents
IPE 4111
Afia Ahsan
Lecturer
MPE, AUST
Facility Layout
Cellular Production
Layout in which machines are grouped into a cell that can
process items that have similar processing requirements
Group Technology
The grouping into part families of items with similar design or
manufacturing characteristics
Design Product Layouts: Line Balancing
❖ Line Balancing is the process of assigning tasks to workstations in
such a way that the workstations have approximately equal time
requirements.
❖ The goal is to obtain workstations with well balanced workload.
❖ Need to match the output rate with desired plan.
Line Balancing in Product Layouts
1. Central problem in product layout is to balance the output at
each workstation along the production line
2. Line Balancing is the process of assigning tasks to workstations in
such a way that the workstations have approximately equal time
requirements
Cycle time
❑ Cycle time is the maximum time allowed at each workstation to
complete its set of tasks on a unit.
❑ Time between successive units coming off end of the line
General Procedure for Line Balancing
➢ Determine precedence relationships – the order in which tasks must be performed in the assembly process.
Total work time available
➢ Calculate Cycle time , C= Units required
Total of all task time
➢ Determine minimum number of workstations, N =
Cycle time
➢ Determine the candidate list which includes the following tasks
➢ Decision rule: Primary rule: Assign task with the longest processing time
➢ After task assignment, determine idle time = Cycle time-sum of time already assigned tasks
Station Candidate List Task Assigned Task Time Total Time Idle Time
Number
1 A A 0.1 0.1 0.3
B B 0.2 0.3 0.1
2 C C 0.4 0.4 0
3 D D 0.3 0.3 0.1
Line Balancing (Example 1)
0.1+0.2+0.4+0.3
=
3 𝑆𝑡𝑎𝑡𝑖𝑜𝑛𝑠 ×0.4
= 83.33%
Line Balancing (Exercise 1)
There are 500 productive minutes available per day. The production schedule
requires to complete 65 units each day. Arrange the work activities into workstations
to balance the assembly line.
Immediate
Task Time (Min)
Predecessor
A - 5
B A 3
C B 4
D B 3
E C 4
F C 1
G D, E, F 4
H G 7
THANK
YOU