Professional Documents
Culture Documents
Abid Hussain
Head of Asset Reliability and Integrity Management (ARIM)
Fauji Fertilizer Company Limited, Pakistan
Figure 6.
Reformer Shell
Figure 4. Circumferential crack in the air inlet
pipe (a) and crack in seal weld (b). Catalyst and alumina lumps were found in
healthy condition. No observations were found
regarding detrimental depressurization of vessel.
Refractory was generally in satisfactory condi-
tion except for damage in the neck portion in the
vicinity of the dish to neck flange.
Burner Assembly
The hole of 70mm x 35mm observed in the air
inlet pipe had burnt-like appearance (Figure 7).
The area around the hole was also degraded. This
degradation was also observed around the pe-
riphery of the seal ring; however, the damage was
more pronounced at the hole location. This phe-
nomenon was absent just above the sealing ring
interface.
All the welding job was done while adhering to Air Inlet Pipe
the Pre Heat and Post Heat requirements of the SS-321 H
material followed by a Post Weld Heat Treat- Figure 11. Crack initiated at the toe of the lower
ment. weld and propagated circumferentially along
the toe as well as radially inside.
Considering the crack size and morphology, it the annular space
appears that the pipe base metal was cracked in
the through thickness followed by consequential
growth of the crack in the seal weld. Over a long
period of time the base metal cracks got through
and allowed process air to flow into the annular
space filled with ceramic wool (the annular space
or chamber is the space between air inlet pipe and
top nozzle of the dome, which is marked by white
arrow in Figure 12).
Due to this flow of ~460°C hot air the tempera- Figure 13. Leaking air mixes with process gas
ture of annular space between Air Inlet Pipe and to form a flame impinging the pipe resulting in
top nozzle of Secondary Reformer increased, material deterioration
thus changing the color of the temperature indic-
ative paint on the nozzle from green to white.
However, this change in color didn’t raise any
alarm since the color changing phenomenon had
been witnessed several times in the past at all
three plants of FFC. But in these instances, the
change in color was due to the pressurization of
the process gas in to the chamber between air in-
let pipe and top dome, which was caused by the
poor packing of ceramic wool inside the chamber
and the inherent gaps in the sealing ring. The pro- Figure 14. Air gushed out of this newly formed
cess gas surrounding the burner pipe is already at hole and turned into a jet of high temperature
auto ignition temperatures, and leaking air flame hitting, damaging the refractory, over-
through the annular space, therefore, made a heating the metal which then explode to fish
flame at this location. The phenomenon is mouth.
sketched in Figure 13 and Figure 14. From the
thermographs of February 2022, it is clear that Although this flame would have been all around
the process air was not entering the annulus space the circumference of the pipe OD (also evident
behind the air inlet pipe since the skin tempera- from the material degradation signs observed on
ture of the nozzle were below 200°C and the tem- the pipe circumference), the fire intensity re-
perature indicating paint was also green in color. mained particularly high at one location causing
deterioration of the air pipe due to direct flame
impingement through a small hole in seal ring.
Conclusion
Failures of secondary reformers are very rare in
industry and the risks associated with such fail-
ures are normally very high. The explosion in
FFC was a result of a weld crack in the air inlet
Figure 17. Existing design pipe of the burner. This crack formed a passage
which let air into the reformer, ahead of the
burner where flammable process gas ignited and
this resulted in failure of the refractory, thus ex-
posing the metal surface to very high tempera-
tures above the design values and eventually re-
sulting in loss of containment.