Geotekindo - Clarification of Secant Pile For Terboyo Pump House R03
Geotekindo - Clarification of Secant Pile For Terboyo Pump House R03
6 November 2023 1
Shanghai GEOHARBOUR Construction Group
• Professional entity specializing in Soil Improvement and Geotechnical Design to Construction.
• Chief Editor of Chinese National Standard for Reclamation Soil Treatment.
• Director member of Technical Committee of China Soft Soil Treatment.
• Soft Soil Treatment more than 50.000 Ha.
• Founded Date : Jan. 28th, 2000.
• Group IPO : Sep. 17th, 2021.
• Subsidiary in Indonesia :
Our Clients
PT. GEOTEKINDO Ground Improvement Project Experience List in Indonesia (up to June 2023)
No. Project Name Client Quantity Project Duration No. Project Name Client Quantity Project Duration
VACUUM CONSOLIDATION SYSTEM (VCM) & SOIL PRELOADING DYNAMIC COMPACTION, VIBROFLOTATION & STONE COLUMN
1 PLT 3 3x315 MW Power Plant, Banten PLN 42 Ha 2008.01-2009.12 1 Tarahan Port Expansion (Stone Column) Bukit Asam Tbk 80000 m' 2012.09-2013.03
2 PLTU 1 2x60 MW, Kalimantan Tengah PLN 15 Ha 2011-2012 2 Sumsel-5 Coal Fired Power Plant (DC) Sinarmas Group 12 Ha 2013.5-2015.8
3 TCT Coal Yard, Kalimantan Selatan TCT 12 Ha 2011 -2012 3 Regatta Apartment Phase 2 (Vibroflotation) Intiland 200000 m3 2014.03-2014.07
4 Cikarang Listrindo Fired Coal Power Plant PT. Cikarang Listrindo 21 Ha 2012.12-2014.12 4 Golf 2A Island (DC, Vibroflotation) Agung Sedayu 313 Ha 2014.01-2022.06
5 Sumsel-5 Coal Fired Power Plant Sinarmas Group 12 Ha 2013.05-2013.12 5 Island 2B (DC, Vibroflotation) Agung Sedayu 70 Ha 2015.06-2017.07
6 Trisakti Port's Container Yard, Banjarmasin Pelindo III 2.2 Ha 2013.05-2015.08 6 Takalar Power Plant, Sulawesi Selatan (SC & Vibroflotation) MIC 2 Ha 2016.03-2017.07
7 Chip Pile, ETP, and salt storage area of Paper Factory Sinarmas Pulp & Paper 10 Ha 2014.10-2015.08 7 Pekanbaru - Dumai Toll Road (DC) Hutama Karya 6 Ha 2017.8 ~ 2017.11
8 Palm Oil Factory, Gresik Project Mitra Pemuda 1 Ha 2015.09-2016.01 8 New Yogyakarta International Airport, Kulon Progo (DC) PT. PP 57 Ha 2017.11-2018.12
9 Palembang - Indralaya Toll Road Hutama Karya 105 Ha 2015.08-2018.12 9 Runway 3 Bandara Soekarno Hatta Section 1 & 2 (SC & PVD) PT. PP 24 Ha 2018.02-2019.06
10 Nunukan KPS Shuangma Indonesia Shuangma Chemical 70 Ha 2014.07-2019.05 10 PLTU Cirebon II (Sand Compaction Pile) Hyundai (HDEC) 141000 m' 2018.02-2019.05
11 Kosambi - PIK 2 Agung Sedayu 2 Ha 2016.02-2016.08 11 Reklamasi Apron Barat Bandara I Gusti Ngurah Rai (Vibroflotation) PT. PP 10 Ha 2018.05-2020.12
12 PLTU Muara Jawa SEPCO 3 8 Ha 2016.03-2016.09 12 ERiC Sidoarjo (SC) PT. PP 42000 m' 2019.01-2019.05
13 PLTU Jawa 7 Energy China 27 Ha 2016.05-2017.09 13 Indonesia Meulaboh Power Plant (2 x 225MW) Coal Fired (SC) PT. Energy China Tianjin Indonesia 160000 m' 2019.07-2021.05
14 Kayu Agung - Palembang Toll Road Section 1 PT. Waskita Karya 45 Ha 2016.08-2020.07 14 Dhoho International Airport, Kediri (SC) Sinohydro & Victory 220000m' 2020.09-2022.08
15 Pantai Indah Kapuk 2 Agung Sedayu > 600 Ha 2016.11-now 15 Lawe-Lawe Facilities RMDP RU-V, Kaltim (SC) Krakatau Engineering 15400 m2 2021.03-2022.02
16 Kayu Agung - Palembang Toll Road Section 2 PT. Waskita Karya 33 Ha 2016.12-2019.10 DEEP CEMENT MIXING, GROUTING, CFG PILE & BORED PILING WORKS
17 Light Rail Train Depo, Palembang PT. Waskita Karya 3 Ha 2017.02-2017.09 1 RB Area of Paper Factory (DCM) Sinarmas Pulp Paper / APP 250000 m' 2014.10-2015.08
18 Pematang Panggang - Kayu Agung Toll Road Section 2 PT. Waskita Karya 40 Ha 2017.04-2018.09 2 Sarulla Geothermal Power Plant, Sumatera Utara (DCM) Hyundai (HDEC) 2.9 Ha 2015.02-2015.09
19 Pemalang - Batang Toll Road section 3 Sumber Mitra Jaya 113 Ha 2017.06-2020.02 3 Meikarta Estate, Cikarang (Borepile) CSCEC-SAJR JO 36 towers 2017.07-2018.12
20 Kayu Agung - Palembang Toll Road section 1A & 1B PT. Waskita Karya 20 Ha 2017.07-2019.07 4 Nanshan Bintan Plant (Borepile) CSCEC-SAJR JO 3000 point 2018.01-2019.05
21 PLTU Tanjung Jati A, Cirebon Harbin Electric 5.6 Ha 2018.05-2019.01 5 YILI Factory Plant, Karawang (DCM) PT. Yili Indonesia 213000 m' 2019.04-2019.07
22 Kijing Container Terminal, Kalimantan Barat PT. Wijaya Karya 14 Ha 2018.12-2020.07 6 Jakarta - Bandung High Speed Railway (Borepile) PT. Wijaya Karya 52000 m' 2019.05-now
23 Lianfa Textile Factory, Kendal Lianfa Textile, Co. 17 Ha 2019.9-2020.12 7 Jakarta - Bandung High Speed Railway (CFG) PT. Wijaya Karya 409000 m' 2019.05-now
24 Nanshan Bintan Park, Bintan CSCEC 1 Ha 2020.02-2020.08 8 PLTU Meulaboh Aceh (CFG & Borepile) China Energy Group 50000m' 2019.07-2021.05
25 Semarang - Demak Toll Road Section 2 PT. PP 40 Ha 2020.02-now 9 Pantai Indah Kapuk 2 (Borepile) Agung Sedayu 3000 m' 2019.08
26 Prabumulih - Muara Enim Toll Road Zone 2 & 3 PT. Waskita Karya 50 Ha 2021.05-2021.07 10 Amazon CGK060, Karawang (Boredpile) PT. Indokomas Buana Perkasa 6300 m' 2020.01-2020.06
27 Smelter Grade Alumina Refinery, Mempawah Kalbar PT. PP 50 Ha 2021.05-now 11 Nanshan Bintan Park, Bintan (DCM) CSCEC 2018.01-2019.05
28 Kayu Agung - Palembang Toll Road Package IV Section 2A PT. Waskita Karya 5 Ha 2021.06-now 12 GISTET 500KV, Muara Karang (Boredpile) PT. Indokomas Buana Perkasa 2600 m' 2021.01-2021.09
29 Golf 2B Island Extension Agung Sedayu 15 Ha 2020.12-now 13 Amazon CGK063, Karawang (Boredpile) Amazon Web Services 12000 m' 2020.12-2021.10
30 MMP Smelter Project, Kalimantan Timur PT. Wijaya Karya 4 Ha 2021.11- 2023.02 14 Kura-Kura Bali Project (Bored Pile) PT. China State Construction 5300 m; 2020.04-2021.06
31 Semarang - Demak Toll Road Section 1B (Trial Embankment) PT. PP 5.6 Ha 2021.10-now 15 Golf 2A Island (Compaction Grouting) PT. KNI 87000 m3 2020.06-2022.02
32 PIK2 Toll Phase 3 Agung Sedayu 16.5 Ha 2022.05-now 16 Serbaraja Toll Road (Soil Nailing) PT. Wijaya Karya 14000 m' 2021.08-2022.03
33 Nava Park LR06 Sinarmas Group 5.6 Ha 2022.09-2023.3 17 Ignite Data Center, Cikarang (Boredpile) PT. Digital Hyperspace Id 2023.02-now
34 Trial Vacuum Preloading for PIPIT Group PT. Pipit Mutiara Jaya 16 Ha 2023.03-now 18 Tanjung Benoa Port (CFG Pile) PT. Wijaya Karya 2023.02-now
35 Kalibaru Port 1B PT. PP 120 Ha 2023.04-now
Piling Project Experience
Project Duration
No. Project Name Location Owner Main Contractor Bidder Scope Of Work
From To
1 Meikarta Project Cikarang, West Java PT Lippo Cikarang Tbk. CSCEC - SAJR JO Bored Pile Jul-17 Dec-18
Perawatan Pondasi Proyek Taman Industri PT. Port Engineering CSCEC
2 Bintan, Riau PT. Bintan Alumina Indonesia Bored Pile Nov-18 Jul-19
Nanshan Indonesia
PT. Wijaya Karya (Persero) Tbk.
3 Jakarta - Bandung High Speed Railway Jakarta - Bandung PT. Kereta Cepat Indonesia China Bored Pile & CFG Pile May-19 TBA
China Railway Group Ltd.
4 Proyek Jembatan PIK 2 PIK, Jakarta Agung Sedayu PT. Wijaya Karya (Persero) Tbk. Bored Pile Jul-19 TBA
Indonesia Meulaboh Power Plant (2 x 225MW) Spun Pile
5 North Sumatra 大唐米拉务发电有限公司 PT. Energy China Tianjin Indonesia Sep-19 Mar-21
Coal Fired & Stone Column
PT. Amazon Data Services
6 Amazon Data Center CGK060 Karawang, West Java PT. Indokomas Buana Perkasa Bored Pile Feb-20 Sep-20
Indonesia
7 GISTET 500 KV Muara Karang Baru Jakarta PT. PLN (Persero) PT. Indokomas Buana Perkasa Bored Pile Jan-21 Sep-21
PT. Amazon Data Services
8 Amazon Data Center CGK063 Karawang, West Java N/A Bored Pile Dec-20 Oct-21
Indonesia
PT. China State Construction
9 Bali Creative Campus Bali PT. Kura-Kura Bali Development Bored Pile Mar-21 Jun-21
Overseas Development
Bored Pile, Spun Pile,
10 Ignite Data Center Cikarang, West Java PT. Digital Hyperspace Indonesia N/A Feb-23 Jul-23
& Pile Cap
Kariangau, East
11 IKN Toll 3A PUPR PT. Hutama Karya (Persero) Bored Pile May-23 Sep-23
Kalimantan
Penajam Paser, East
12 IKN Kemenko 2 PUPR PT. Hutama Karya (Persero) Bored Pile Jul-23 Oct-23
Kalimantan
“Advanced and Innovative Geotechnical
Contractor”
Secant Pile provides economical structural support for lateral force that made by height difference between working platform and surroundings.
Secant Pile is cast-in-place piles. The piles are built by making a hole in the ground and then filling it with concrete. Secant piles is divided into
two types of pile: (a) primary piles and (b) secondary piles.
Advanced and
Innovative
TYPE OF MACHINE
(1) (2)
1. Rotary Drilling Rig (Suitable for any lithological condition – Soft to hard layer)
2. Reverse Circulation Mud Rotary Drilling (Suitable for height limited working area – Soft layer)
Advanced and
Innovative
Advanced and
Innovative
Model
CRRC 150 YTR 230 SR285R YTR 300 GF-400
Item
Max. output Torque (KNm) 150 230 285 320 42
Advanced and
Innovative
Project Location
Advanced and
Innovative 13
PROJECT LOCATION
Advanced and
Innovative 14
PROJECT LOCATION
Advanced and
Innovative
CURRENT SITUATION
Advanced and
Innovative
Soil Condition (DB – 069)
Advanced and
Innovative
Soil Condition (DB – 070)
Advanced and
Innovative
SOIL CONDITION
1. From elevation 0 ~ -19, the soil is very soft clay, plastic-flow, SPT 0 ~ 2;
2. From elevation -19 ~ -47m, the soil is soft to medium stiff clay, SPT 3 ~ 17.
Therefore,
A. Flat and dry working platform is necessary and should be able for boring rig weight 80 tons.
B. Full casing drilling method is applied for primary piles (25 m) meanwhile secondary piles will use 9 m
casing.
C. For drilling method will be use wet method with bentonite slurry as stabilizer.
Advanced and
Innovative
Secant Pile Design in Pump Station
Innovative
Advanced and
Innovative
CONSTRUCTION FLOW
Advanced and
Innovative
WORKING METHOD
Start
A
Working Platform
Preparation
Drilling Secondary Piles
A
Finish
23
WORKING METHOD
24
WORKING METHOD
Working Platform
On several site’s condition, having a
Preparation
working platform is a mandatory thing.
Working platform is used to ease the
heavy equipment access. Usually used
steel plate for working platforms if
necessary.
25
WORKING METHOD
Guide Wall Construction
27
WORKING METHOD
Finish
28
WORKING METHOD
Finish
29
WORKING METHOD
30
WORKING METHOD
Finish
31
Disposal Work
32
PILE TESTING
Advanced and
Innovative
Project Schedule
Project Schedule
Terboyo Pump House Semarang-Demak 1C
Daily Machine Total Month-1 Month-2 Month-3
No. Description Day Volume Unit
Volume Capacity Unit 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A Preparation Works
1 Equipment mobilization 14 2.00 set
2 Manpower mobilization 10 1.00 ls
3 Site facility & equipment set-up 14 1.00 ls
Notes:
- Assumed total production capacity for 2 shifts/day (16 hours of effective working time)
- Productivity and schedule will depend on site actual condition (concrete supply, working platform)
Advanced and