Excel Spread Sheet to distribute quantities between dates

As a planning engineer, you deal with dates and quantities. Therefore, during your daily tasks, you
may need to create a cash flow, manpower histogram, or even a quantity-based small schedule.

This Excel spreadsheet will help you to distribute any quantities, man-hours, or even costs between
dates. For example, if you have an activity that starts on 1-Oct-2015 and finishes on 15-Nov-2015,
taking the weeks as periods what would be the planned % in Months 1, 2, 3, etc.? I have kept this
spreadsheet unformatted so it will be easy to copy, edit, or use the formula only in your works.

Spreadsheet applications:
1- Create Cash Flow for a project.

2- Create a Manpower Histogram.

3- Create a Quantity Distribution of an activity/activities.

All three of the mentioned items share a common underlying concept. I will now elaborate on the
concept of cash flow as an example, and you can apply the same idea to the other aspects. If you
possess information such as the activity ID, activity start date, activity finish date, and activity cost
from the Primavera P6, you can utilize this spreadsheet to manage cash flow.

Simply, copy the activity ID, activity start date, and activity finish date into the spreadsheet and
determine the weight for each month, week, or day, depending on your chosen time frame. The
weight value is set at 1000, meaning that if an activity is projected to span two months, weeks, or
days, each unit will be assigned a weight of 500.

Once you have established the weight distribution based on the selected time frame, you can
employ the Vlookup function in Microsoft Excel. This function will enable you to locate the relevant
Activity ID and allocate the appropriate weight to each month, week, or day. You can then proceed
to multiply these weights by the respective quantities, man-hours, or costs, and subsequently divide
the cumulative result by 1000.
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 1 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

Feeling overwhelmed by the complexity of the process? That's perfectly okay. It's important to note
that this tool isn't designed to function in isolation. Instead, think of it as an intermediary tool that
assists you in conducting various calculations. The outcome is not obtaining the final results, which
you can then integrate into your own customized format or dashboard.

By engaging in this procedure to manage a schedule, you will acquire the ability to generate all three
applications—Cash Flow analysis, Manpower Histograms, and Quantity Distribution—using a single
file. The only variable lies in how you choose to leverage the weight factor to ascertain costs, hours,
or quantities for each component.

This is the sheet at first sight, you won’t understand it but it is quite easy

1. The “Activity ID” is exported from Primavera P6.


2. Stands for the “Early Start Date” for the activities exported from Primavera P6.
3. Stands for the “Early Finish Date” for the activities.
4. All these columns represent the months of project life and they can be changed to weeks or
years as you want.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 2 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

This is the overview of the first sight of the sheet.

How the Spreadsheet Works

This sheet sees any cost, resources, and quantities as 1000 units regardless of the real unit of the
parameter (cost, resources, and quantities).

A-001 Activity

This activity starts on 10 May 2015 and finishes on 10 June 2015, so the Excel sheet distributes the
1000 units in May and June as follows:

It takes 21 days in May and 10 days in June so it distributes the 1000 units at them, so, May got the
majority of the units whatever it is (cost, resources, and quantities).

A-002 Activity

This activity starts on 10 May 2015 and finishes on 19 May 2015, so the Excel sheet distributes the
1000 units in May because the activity starts and finishes in May.

It takes 9 days in May, so it distributes the 1000 units in May only.

The privilege of this sheet is that you don’t need to add values, it gives you percentages and you can
multiply them with the real values for the 3 parameters (cost, resources, and quantities).

So you can use them in your reports your forms or Power BI formats.

The Bar Chart


Find the total monthly weight and the cumulative monthly weight to draw the chart.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 3 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

The total monthly weight is calculated by the number of added activities.

Total Monthly weight = {number of activities * weight of the activity(1000)}

So the first month's weight will be calculated by this formula:

= sum of the all weight in this month divided by the all weight of the project.

This will give you the monthly weight.

Apply this equation to all the columns till the end of the project date.

Then, calculate the cumm. monthly weight percentage.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 4 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

The cumm. monthly weight for the first month will be equal to the first month's total weight but the
cumm. monthly weight for the second month will be equal to the first and second month's total
weight.

Then drag this formula to all the columns.


You will find that the bar chat will be drawn.

You can also use the manhours to make this chart


If the total manhours for the projects are 1000 hours then the above percentage will be
multiplied by the monthly percentage.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 5 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

Monthly hours = Total monthly percentage * Total hours.


Copy the above steps and apply them to create a bar chart with the monthly man-hours in
the project.
It can be done to the cash flow as well and have a chart too.

If you are interested in Excel tools here are many of them:

• Paste cells from a Single Cell to a Merged Cell


• Copy Primavera and Paste it into Excel with WBS
• How to make 3 weeks ahead by Excel
• Mini Schedule Plan using Excel

Article Link & Attachements: https://planningengineer.net/excel-spread-sheet-to-distribute-


quantities-between-dates/

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 6 of 7
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

---------------

Useful links:

Join our email Newsletter, we send useful free content regularly:


https://planningengineer.net/newsletter/

Our Services https://planningengineer.net/our-services/

Our Courses: https://planningengineer.net/lp-courses/

Free Arabic Basic Course Playlist:


https://youtube.com/playlist?list=PL7qHhNmknL6F5IOHAsNnPVMt1X-fvYe3J

---------------

Keep in Touch:

WhatsApp: +201277767728

Email: Info@PlanningEngineer.Net

English YouTube Channel: https://www.youtube.com/c/PlanningengineerNet/videos

Arabic YouTube Channel: https://www.youtube.com/@planningengineer3906

Linked in: https://www.linkedin.com/company/planning-engineer-est/

Facebook Page: https://www.facebook.com/PlanningEngineerDotNet

Facebook Group: https://www.facebook.com/groups/1138400132963230

Twitter: https://twitter.com/PlanningEEst

Instagram: https://www.instagram.com/planningengineerest/

TikTok: https://www.tiktok.com/@planningengineerest

---------------

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 7 of 7

You might also like