Professional Documents
Culture Documents
net/publication/327853197
CITATIONS READS
3 310
1 author:
SEE PROFILE
All content following this page was uploaded by Madhav Prasad Koirala on 25 September 2018.
- .
!
"- (
%
. %
% % % $
$ $ -
-
- -
2
3.12 Qualities in Projects: Challenges ..................................................................................... 43
3.13 Problems Related to Technical Aspects .......................................................................... 45
3.14 Human Resource in the Infrastructure Projects ............................................................... 46
3.15 Components of Nepalese Society and Infrastructure....................................................... 47
3.16 Culture of Consumers in Infrastructure Projects ............................................................. 48
3.17 Organization/Institution and Infrastructure Projects ....................................................... 50
3.18 Concluding Remarks ....................................................................................................... 51
CHAPTER-4 ................................................................................................. 53
RISK RESPONSE IN INFRASTRUCTURE CONSTRUCTION FIELD53
4.1 Integrated Policy for Enhance infrastructure....................................................................... 54
4.2 Existing Legal Polices should guided by Developers Friendly........................................... 57
4.4 Frequent Development and Research work is needed......................................................... 60
4.5 HRM Team must be experienced for Risk Mitigation ........................................................ 61
4.6 Responses Based on their work Experience ......................................................... 61
4.7 Implementation Phase is to be careful Compare to other Phase ......................................... 61
4.8 Cosmetic treatment for Mitigation is not Permanent Solution ............................................ 62
4.9 Products of Infrastructure must be Branded and Qualitative .............................................. 63
4.10 Risk Response Plan.......................................................................................................... 64
4.15 Concluding Remarks ....................................................................................................... 66
References ...................................................................................................................................... 67
3
Chapter-1
1.1 Introduction
It is a challenge and an opportunity to manage risk factors in the construction
infrastructure projects within a limit. Professionals are not due concentrating their
expertise and skill in this direction, so as every minute, every second passes by, there
is a chance of cost and time over-running and degradation of quality in each
infrastructure projects because of many more causes. Particularly, developing
countries were severely suffering by those risk factors. In Asia, many countries are
developing countries, Among them Nepal has suffered for more than one decade by
the civil insurgency, now it is on queue to the peace process which is not yet
concluded. It is landlocked country and situated between China and India. In the
infrastructures development either in rural area or urban, professional¶V
consciousness is a must. Previously performed infrastructures were not properly
planed so that could not become result oriented. Although first five year development
plan was started from 1956, its economic plan was started and now already passed
tenth five years and could not get success as per the expected objective.
It is difficult for a new professional to identify new risks, in a new environment
and politically instable countries. It is more difficult to assess these risks and impact
of relationships among them. Legal policy framework has not been made by the
government because of frequent change in government and hence legal and political
risks are more catastrophically influencing equitable infrastructures development,
simultaneously financial, economic and other risk factors. It is more difficult to
assess these risks and impact of relationships among them. The trend in construction
projects is just ignoring and making the decisions which are unrealistic and
irresponsible by authorized professionals as well as other fact is identifying,
4
analyzing new risks becoming complicated, expensive and time consuming due to
omission of the risks management plan during planning phase (Koirala, 2012).
The economic and social circumstances of infrastructures have stimulated calls
for redevelopment and renewal since the Industrial Revolution transformed the
economic base and spatial makeup of American cities during the second half of the
nineteenth century. Industrialization not only brought about a fundamental
transformation in the nature of work, but also brought change in the systems of
transportation, the structure and operations of city government, the experience of
poverty, and the demographic movement of racial and ethnic groups on an
unprecedented scale. Henry Mayhew, Charles Booth, and Lewis Mumford
documented in graphic detail the pathological nature of uneven development
characterizing urban growth under industrial capitalism in the United States (Gotham,
2001).
Redevelopment and renewal need to be worked out as per requirement of
people and country. Existing infrastructures and amenities need expansion and hence
redevelopment renewal, maintenance is a regular process. Americans came to know
urbanization, infrastructure, housing and economic growths as interrelated subjects,
which was not natural gift but an art to manage the excess population.
Urbanization with infrastructure development is one of the fundamental
characteristics of the European civilization. It gradually spread from Southeast
Europe around 700 BC., across the whole continent. Cities and the urban networks
they formed were always an important factor in the development and shaping of their
surrounding regions. Polarization of territory between urban and rural and
accessibility are still important aspects in landscape dynamics. Urbanization and its
associated transportation infrastructure define the relationship between city and
countryside. Urbanization, expressed as the proportion of people living in urban
places shows a recent but explosive growth reaching values around 80% in most
European countries. Simultaneously, the countryside became abandoned (Antrop,
2003? 2004).
Similarly the urban and infrastructure development had started quite earlier in
European countries. In the southeast Europe, the urbanization and infrastructure
development started before 700 BC and rest of the Europeans learnt it and followed
the same pattern.
In Madrid, as in other cities, urban planning projects accompanying the
globalization process have provoked new episodes of social mobilization. In Spain,
there have been few studies of this type of urban infrastructure struggle to date,
5
despite an increase in number and intensity. Understanding the characteristics of the
phenomenon and interpreting them, taking the theoretical and empirical contributions
of others into account should form part of the Spanish urban investigation agenda
(Orueta, 2007).
Social mobilization, social awareness and social cohesiveness were developed
early in Spain and other parts of Europe. As a result, these countries progressed in
urban development as well as in infrastructure and housing sectors.
8
predominantly rural society, and that urbanization could drain resources from rural
areas to urban centers. In many instances, the populist emphasis on rural and
agricultural development as the only strategy has caused development agents to
depict urbanization as the wrong path to development, highlighting the negative
aspects of urbanity (Tibari, 2008).
The migrant pattern is growing in rural areas. From the beginning, state has not
concentrated on infrastructure and urbanization planning. It was found that large
fertile land was used to build the housings.
Migrant from urban in Nepal is less compared to rural. Similarly, migrant from
outside to Nepal is least one compare to other two. According to the projected data
81.2% of rural people migrate, 7% people migrate from urban. Similarly, 11.8%
people migrated to outside of Nepal in 2010/2011 (NLFS III, 2008).
The above statistics show that urban population pressure is rising every year in
Nepal. In 2001, population in urban area was 3,227,879 i.e., 86.1% of total
population, whereas in 2011, it was 4525787 and 83.00% of total population.
The Infrastructure and urban development accelerates when migration took
place either from internal or external. In the past decade the main causes of migration
was civil insurgency, war, not maintaining law and order, security problem,
impunity, government plan of land accusation and attraction of better opportunity.
Institutionalisms consider rules of law, policy and organizations, the way mentioned
above factors govern in every country's social relations and their attitudes.
As institutions are exercised the rules of law, which affect human behavior in
the infrastructure and housing and land development process, institutionalisms dealt
with institutional changes of various organizations, individual behavior within
broader social, political and economic forces. These standard norms are stabilized in
developed countries whereas not in developing countries because of the government,
not able to maintain law and order resulting impunity. That was still more in
developing countries during their transition phase due to civil insurgency, war,
conflict in the past decades.
In the same causes urbanization increased when people started migrating from
rural to urban to seek peace and security, dreaming good opportunity for business and
employment. It is argued that the pace and scale of urbanization should match the
pace and scale of economic development.
9
1.4 Role of Infrastructure Housing, Apartment and Real Estate
Shelter is one of the basic needs for human beings not only for protection against
unwanted environmental event with including hostile weather, but also for
maintaining standard infrastructures of living acceptable to family or even to elevate
one's position in the society through enhanced living status. First housing and real
estate play the role about to accelerate the economy of the country by getting
employment opportunity to unskilled people. Housing and apartments provide shelter
to the people.
Housing is a major aspect of human development. As noted by the World Bank
(1992), housing investment typically accounts for 2% to 8% of GNP, and the flow of
housing services for an additional 5% to 10% of GNP. Residential real estate
represents around 30% of the world wealth, greater than both bonds (27%) and
equities (19%). Residential construction is a major employer often accounting for
more than 5% of total employment. Housing is an important economic sector with
linkages to the real and financial parts of the economy (Lea & Chiquier, n.d.).
Similarly, housing prevents from unwanted environment degradation and
provides the feeling of satisfaction. Secondly, it fulfills the three objective
developments: to increase the availability, to raise level of living and to expand the
range of economic (Todaro & Smith, 2007).
Housing plays important role in fulfilling the above mentioned characteristics.
The other role of housing in Nepal is to provide equal status: individual and grouped
housing on social investigation. It can remove the disparities between the so-called
high caste and low caste.
11
by doing 12-point agreement between government and Maoist, so people wanted to
have own house in cities so as to do some business where security and physical
facilities are available.
Professionals are giving due concentration with customer's desire by making
houses and supply them to those who have been demanding. Meanwhile, Rastra Bank
of Nepal (the government financial monitoring and regulatory body), is watching
over commercial banks against their limitation to lending on housing and developers.
The Rastra bank is taking action to the commercial banks, and then the financial
problem has becoming concerned to developer, buyer, banker, and other stakeholders.
Thereafter housing and real estate sector facing financial risks along with political
parties and their sister organization were asking donation, if they did not get said
donation they were to lock the project. In the name of indigenous group and ethnicity,
they asked the employment for locals even they were not fit for the project.
Particularly in housing and real estate projects or any construction process can
be divided into four main phases: Formulation or Pre-planning, Planning,
Implementation, and Operation/Handover. In the formulation phase, the client has an
idea about the project and analyses conditions for its execution. During the planning
phase, the architects and engineers produce design and construction drawings
accoUGLQJWRWKHFOLHQW¶VUHTXLUHPHQWV
Depending on the Implementation option, the design phase follows either the
programme phase or the procurement phase. In the procurement phase, the client
chooses the contractor and the parties sign the contract. Finally, the contractor
executes the job in the implementation phase. Management involve planning,
organizing, staffing, leading or directing, and controlling an organization (a group of
one or more people or entities) or effort for the purpose of accomplishing a goal.
Resourcing begins from the deployment and manipulation of human resources,
financial resources, technological resources, and natural resources. During
management, organization is another important pre-requisite entity, which can be
viewed as system, and to manage the human action as it includes design, to facilitate
the production of a useful output from the system. It is also known as the opportunity
to 'manage' one self and attempting to manage others.
Housing and real estate construction projects mobilized with the huge
investment for large sectors of human beings and the society. Most of the projects are
characterized by the incidence of cost and time overruns with unsatisfactory quality
performance, poor project management practices drive to the inability of the
constructions to meet the expectation of customers and investors. This has been
12
important that the need to carry out on this research to explore the reasons for these
failures so as to evaluate practices that can guarantee improvement to construction
projects. As improving, the performance measures of construction projects would
have major effect on competitiveness.
Professionals and developers have found it difficult to agree on methodology
and metrics to apply that can bring improvement to the construction industry. To
improve these issues, how to qualify and quantify practices is capable of ensuring
improvement has not been easy to discuss but it needs skills and practices in the field
arising from the divergent views of professionals in developer's institutions.
6WDNHKROGHUV¶FRQIOLFWLQJYLHZVDQGLQWHUHVWFDQQRWEHUXOHGRXWDVRQHRIWKH
reasons why these measures have been difficult to ascertain. However, it is worthy of
note that the question of how project performance is measured is critical to bringing
improvement to construction organization.
Although construction projects have been part of the human race, old
profession you must agree, projects continue to fail and even now the rate is on the
increase in recent time. Observations in our environment show that investors of
construction projects have not been able to justify their investment because of
frequent project failures.
These increasing failures is of major concern to investors, project team leaders,
stakeholders and larger members of the public whose economic, social and political
lives have been devastated and negatively impacted. In the western world, the
situation is better only to the extent that researchers in that environment were
vigorously and consistently attempting for finding solution to halt such trend.
13
survive and slowly try to make progress whenever the opportunity presents itself
(Karki, 2004).
If this trend continues, our city would be registered as one of the ugliest built
cities in the world. It is fact that the construction takes place without taking any basic
amenities. At present, there is haphazard growth of housing and real estate companies
(developers' organization), land accusation and development design Land escaping is
being questionable, and consequently the miss understanding arises with the authority
and developers. Looking to some investors' profit, more people jump to invest on
housing and real estate, consequently leading to bankruptcy.
Another important factor is legality issues, as per building byelaw made by
municipality , floor area ratio (FAR), coverage, height of building, open spaces,
greenery offset are basic issues that developers have to maintain it. Political issues
like donation in the name of meeting conference and conventions are also other
problems. Political system is unstable and there is no clear policy of government to
monitor and control the unmanaged land polling (plotting) and housings, and
apartment system.
A very large number of housing developments both apartment houses and
individual family dwellings involve individual property to the housing unit itself
combined with communal property to the grounds, recreational facilities, and other
joint facilities. While individuals can buy and sell their individual housing units, at
the time of purchase, they assume a set of duties in respect to the closely related
communal properties (Ostrom, 2000).
In the old cities, beauty of the city has become worse as compared to Nepali's
original Malla's period and what is called medieval period. Regulating this has not
been effective. Dispute has been arising about the ownership within the neighbor
because of the lack of open space. Safety and security to the citizens has become big
problem during construction and maintenance period. Each decision to invest in the
housing and real estate project implies that risks are taken. In other words, how the
stakeholders manage to recognized take risk. To put it in simple terms, there is also
the problem in GLD (Guided Land Development) policy adopted by Town
Development Committee (TDC) that imagine 4, 6, and 8 m or wide river corridor
road is perfect to the papers stored at TDC office and is interesting to listen. Actually,
the danger lies right there that it is virtually unknown to public. Only after a customer
has bought a land, paid registration taxes, thought on building a house there, drawn a
house map, and gone to the Municipal Offices for ill-fated approval of the drawing,
14
he now knows that GLD overlaps his land and now he has to sacrifice his land in the
name of GLD.
It does not end there. Of course the person or company who is about to lose
his land will never be able to approve the drawing but since a permission is needed to
build a house, one now starts thinking of extreme alternatives such as bribing the
officials.
Government of Nepal conducted several land pooling projects in such areas
where more development can be ensured through the pooling projects. Government
needs to be able to devise a plan for the particular area right from the beginning and
thus ensure linked roads to new roads being developed. Also there is a need to
manage sewerage to a green area. These can allow the acquiring a large piece of land
and developing it as a perfect residential colony or a business zone.
The Housings, apartment units, and real estate developers are constructing or
producing same range and categories of product targeting upper middle and higher
economic group of income level. No developers or government's authorities are
constructing the housing units targeting middle, lower and even marginalized
economic group of income level. There is no research about the rural-urban
migration. How many of them want the housing units? What was their affordability?
16
Chapter-2
Risk Identification is an iterative process because new risks may become known as
the project progresses through its life cycle. The frequency of iteration and who
participates in each cycle will vary from case to case. The project team should be
involved in the process so that they can develop and maintain a sense of ownership
17
of, and responsibility for, the risks and associated risk response actions. Stakeholders
outside the project team may provide additional objective information. The Risk
Identification process usually leads to the Qualitative Risk Analysis process.
Alternatively, it can lead directly to the Quantitative Risk Analysis process when
conducted by an experienced risk manager. On some occasions, simply the
identification of a risk may suggest its response, and these should be recorded for
further analysis and implementation in the Risk Response Planning process.
List of identified risks: The identified risks, including their root causes and
uncertain project assumptions, are described. Risks can cover nearly any topic, but a
few examples include the following: A few large items with long lead times are on
critical path. There could be a risk that industrial relations disputes at the ports will
delay the delivery and, subsequently, delay completion of the construction phase.
Another example is a project management plan that assumes a staff size of ten, but
there are only six resources available. The lack of resources could impact the time
required to complete the work and the activities would be late. List of potential
responses-Potential responses to a risk may be identified during the Risk
Identification process. These responses, if identified, may be useful as inputs to the
Risk Response Planning process. Root causes of risk- These are the fundamental
conditions or events that may give rise to the identified risk. Updated risk
categories- The process of identifying risks can lead to new risk categories being
added to the list of risk categories. The RBS developed in the Risk Management
Planning process may have to be enhanced or amended, based on the outcomes of the
Risk Identification process (Koirala, M. P., 2017).
20
Nepal is fertile land to obstruct in the name of politics. Political risks are beginning
when project get conceptualize. Planning Commission who makes the plan itself is
influenced by the political party. Similarly, strike, closed, donation to political party,
interference by the political parties, disturbance due to different issues as mentioned
above, confidentiality of political parties and permits and licenses delay due to
political instability etc are main issues of political risks.
Political risks are a bundle of distinct risks that can include not only political factors
but also administrative, social and economic factors. Political risks associated with a
project are closely evaluated as they are generally outside the control of the parties to
the project, other than the government to a certain extent. But even the government
fixing the policies of the telecom industry does not have control over all the
categories of political risks. It should be kept in mind that many of the political risks
arise from the possibility of arbitrary action by the government and altering the
framework on which the very foundation of the project rests. The main categories of
political risks include (a) Risk of political instability such as riots, revolutions, coup,
terrorism, guerrilla warfare (b)War, whether declared or undeclared.(c)International
sanctions (d)Expropriation (e) Nationalization (f) Creeping expropriation
(discretionary regimes, excessive taxation, import restrictions, refusal to allow or
provide for collection or review of tariffs, etc) (g) Failure to grant or renew approvals
and (h) Excessive interference in the implementation of the project, thereby causing
severe prejudice to the concessionaire (Pelling, et al, 2004).
We read in news paper, during contract biding period that lots of illegal works like
capturing the bidding document, not allowed to bid the good contractors using force,
buying and selling before assigning the contract etc were being faced by the
professional good contractor. To remove such incidents, professional contractors
were demanded an electronic bidding. Government tried to introduce it in certain
21
limited department of government authority but it could not be possible to implement
in all sectors because of lack of resources. Feedback is coming that some contractors
are facing within the department the problems of giving and taking still taking place
even in electronic bidding, so professional contractors are not satisfied and they want
improvement in electronic bidding system.
Technical risks are mainly oriented due to pure technical issues. For example
engineering designed quality of the project can be one risk, new technology in the
hands of untrained operator can be other risk, Spoil type, and strata of the layer will
be other type of risk. For example, during the site inspection time we estimated soft
soil but there was hard rock in the foundation. This type of risk is technical risk.
24
I Financial Risks & Exposures
Project Financing (Debt, Equity), Labor and Material Costs (FTE's, Contract,
Outsourced), Earnings Volatility (Revenue Recognition, EPS Growth), Currency
Fluctuation (Foreign Exchange, Arbitrage), Interest Rate Changes (Credit Risks,
Bonding), Commodity Price Fluctuations (Options, Derivatives), Regulatory
Exposures (IRS, FASB), Funding Risks (Government Contract Funding,
Allocations) and Employee Stock Options (Pension Funds, Dividends)
There are many things commonly called barriers to the successful completion of a
project. Some of the barriers are listed as follow:
i. Poor communication:-Many projects will fail because the project team does
not know exactly what to get done out of the project or what already been
done on the project
ii. Disagreement between customer and project manager
iii. Failure to comply with standards and regulations
iv. Inclement weather
v. Labor strikes
vi. Personality conflicts
vii. Poor management
viii. Poorly defined project goals
As mentioned above, a good successful completion depends very much on the ability
of the owner representative or project manager to direct and supervise the project
from beginning to the end. Some important roles of a project manager are listed
below:
i. The project manager must define the project, reduce the project to a set of
manageable task
ii. The project manager must set the final goal of a project and must motivate
the project team members to complete the project on time
iii. A project manager must be equipped with technical skills. These should
include financial planning, contract management, creative thinking and
problem solving techniques
iv. Project manager must learn to adapt to changes.
26
In other words, there are three main points that are most important to a successful
project:
i. A project must meet customer requirement
ii. A project must be under budget
iii. A project must be on time
Contractors are independent business organizations and are awarded the projects to
produce the required end product as stipulated in the contract documents. In the case
of the owner and the contractor may disagree on certain things, the achievement of
the end product must always be the top priority of both parties. A good relationship
EHWZHHQRZQHUDQGWKHSURMHFWFRQWUDFWRUPXVWEHPDLQWDLQHGVRWKDWWKHFRQWUDFWRU¶V
expertise, labor and equipment can be best utilised to achieve the objectives of the
project. The contractor is also required to produce a quality control plan to maintain a
job surveillance of its own, to perform tests and keep records to ensure the works
conform to the contract requirements. The owner should monitor and supervise the
FRQWUDFWRU¶VTXDOLW\SODQDQG make a sport checks inspection from time to time during
the construction process
(Oberlender, 1993)
$FFRUGLQJ WR ³$UXQ-,,, 3URMHFW 1HSDO¶V (OHFWULFLW\ &ULVLV DQG LWV 5ROH LQ &XUUHQW
/RDG 6KHGGLQJ DQG 3RWHQWLDO 5ROH <HDUV +HQFH´ LQ WKH DUWLFOH RI 5DWQD Sansar
Shrestha time overrun has described as follows.
Table 1
Kulekhani I 21 months
Marsyangdi 7 months
Chilime 60 months
28
Chapter-3
Risk Analysis in Infrastructure Construction Field
In this chapter, it is discuss the risk analysis in infrastructure construction field.
Under the topics, following subtopics are being discussed: Big Issue about
ownership, Permit from authority, Bylaws, 2007 for town and rural, Global Issue
the Environment Protection, Local Government :Pre-Matured Authority, Hurdle in
approval Procedure, Problems in the policies level framework-related rules and
acts, Problems: unstable politics and unstable Government, Financial factors and
role of projects, Economic Aspect in infrastructure Projects, Qualities in the
projects: Challenges, Problem related to technical Aspects, human resource in the
infrastructure projects, Components of Nepalese Society and Infrastructure, culture
of Nepalese Society and Infrastructure, Organization/ Institution and Infrastructure,
Concluding remarks and Finally summaries of this chapter are outlined.
30
constructing new towns and maintaining health, convenience and economic interest
of general public.
The land acquiring process is very complicated and so need to be made easy in
the act and policy to give good service to the people.
There are two types of opposing landowners. The first includes those who are
only concerned with what they will lose and do not believe that there is anything to
gain. There are good reasons for this attachment to the land; there are few diversified
HPSOR\PHQWRSSRUWXQLWLHVLQ1HSDODQGSHRSOH¶VODQGLVWKHLUODVWKRSHLQFDVHRID
financial crisis. The second type of opposing landowners have their own plans for
their land and, for this reason, they motivate others to go against the project. Large or
small, all opposing landowners belong to one of these two categories, and the
majorities are in the first category (Karki, 2004)
Therefore, to take land from the owner is very challenging job. If they are
convinced they will agree, if not they will go to court and court says no to proceeding
RQSULYDWHSURSHUW\ZLWKRXWRZQHU¶VDSSURYDO6RWKLVDFWQHHGVWREHXSGDWHGJLYLQJ
more option for land development work. The model may be different like PPP (public
private partnership) model, cooperative model, and proportional contribution model,
etc.
Migration from rural to urban is big intensity in cities and town including all
main cities of Nepal due to security and opportunity in cities. Therefore, it was
started to build unplanned and unmanaged infrastructure, housing and land plotting
which created huge environment risk in the cities.
Urban areas of Nepal are facing an unprecedented rural-urban migration and
subsequent increase in population. The 2001 census recorded an annual population
growth of 2.25 per cent while the urban population grew three times of that rate i.e.,
6.4 per cent (UN-HABITAT, 2010).
Present situation in the cities are dominated by migrated people to purchase
minimum land, make one drawing, and go to municipality or city-oriented village
development authority for approval. The authority gives approval with additional
letter instructing that they need to build as per approved drawing in mentioned
property. According to the provision space for road building in future need to be left
while constructing buildings. When the house is complete there is need of water
supply pipeline, wide road, electricity supply line, etc. So everywhere, it was looking
unplanned and unmanaged.
31
$UFKLWHFWXUHV¶feeling that the time taking was much more by authority. Based on
their education, construction management, and architect felt that time taken to take
planning permit from authority was in fist and second rank.
33
Procedure is becomes lengthy as lot of other activities has to be incorporated.
Publishing notice from daily newspaper is not enough to give the excess of
information. It is also essential to use electronic media for advertisement.
The environment issue is becoming a global issue and the by-product from
environment risk is a disaster, which need to be examined carefully. To mitigate the
environment risk cost varies from one housing project to another, one place to
another. Public consultation, impact identification, zone of influence, baseline survey
and its reliabilities need to be updated in the act as well as it needs to be incorporated
in policies as well.
All living things are dependent on each others. Particularly, cities need to be
sensitive in this manner, because the water which is needed for drinking, air which
need for respiration and vegetables for eating, all are becoming polluted. Due to the
environment pollution citizens suffer from health risk. It was observed, the
improvement was always there. Preliminary it could be reduced to some extent.
During that approval period, developers would have been experienced procedural
risks because long procedural work and more time taking, legally the notice need to
be published in national daily newspaper, put it on different public places, and
verified by legal authority.
36
Political risk is the risk that the laws of a country will unexpectedly change to
WKHLQYHVWRU¶VGHWULPHQWDIWHUWKHLQYHVWRUKDVLQYHVWHGFDSLWDOLQWKHFRXQWU\WKHUHE\
UHGXFLQJWKHYDOXHRIWKHLQGLYLGXDO¶VLQYHVWPHQW3XWVLPSO\SROLWLFDOULVNis the risk
of government intervention. Examples of political risk are the risks that a government
will raise import or export duties, increase taxes, impose further regulations, or
nationalize or expropriate the assets of the investor (Comeaux & Kinsella, 1994).
Civil insurgency, civil war was in favor of the business group. In the period,
people who were working out of the country were not able to pass their money to
rural areas because of terrorism and possibility of loss of property along with his life.
So, at that time, the urban cities became safe place to invest, and they thought tot
purchase one unit of house or one flat or one plot of land. In the period during 2003
to 2007, developers came to housing and real estate sectors as an investment for good
profit. From the beginning due to Maoist insurgency middle class people migrated in
Kathmandu valley seeking security and they started buying and selling land
excessively.
In the mid-1990s, the government began to encourage private-sector
investment in land and housing development and promulgated the Apartment
Ownership Act 1997, which was only finalized in 2003 due to legal and
administrative obstacles. Within a span of 2 years (2003±2005), as many as 15
housing companies were sanctioned by the KVTDC for the development of housing
units (independent, duplex and apartment types) in the valley. Over a 3-year period,
14 private housing programs produced about 965 dwelling units on 254.3 ropani of
ODQG,QUHVSRQVHWRWKHSXEOLF¶VRYHUZKHOPLQJDSSURYDORIWhe programme, as many
as 150 real estate companies have since registered with the Nepal Land and Housing
Development Association. Among them, about 40 to 50 of those companies are
registered as Housing Developers and are engaged in various types of developments,
each with variation in design, facilities and prices (Shrestha, 2010).
Therefore, everyone invested on land and houses-apartments and sold as soon
as possible with good profit, so the value of land and housing raised in an optimum
level. Secondly, in the past, banks and financial institutions were attracted to the real
estate sector because the Nepali economy was not competitive in terms of
manufacturing and with political problems and unfavorable business environment,
the responsibility of the economy shifted towards non-manufacturing areas like real
estate. The property bubble was because of over investment of banks, finance
companies, adding that frequent strikes (bandhs), lack in policy implementation, and
absence of state support to manufacturing led by financial institutions to turn away
37
from manufacturing and investing in real estate. To prevent this collapse, over-
investment had diluted at the earliest by creating direct interaction between sellers
and genuine buyers. In addition to this, equal proportion of demand and supply must
be ensured. Investors started their investment for resell purposes in housing,
apartment, and real estate projects. It is due to these reasons that the value of land,
housings, and apartment was being increased. Therefore, the accessibility of middle
and lower class was impossible to be the owner of the land and housing hence
professional developers felt the risks.
After 2007, buyers focused on the product and started qualitative product
because market was starting to govern the price, escalation of construction materials
is raised excessively. It was the crunch of financial investment, which was not able to
maintain. No one was able to stop it. Country was in transition period and people
hoped well that the constitution will allocate more power to state government. People
were confused weather to stay in urban area or move to native place? Similarly, there
was labor shortage in the market i.e., labor risk was increasing.
Nepal Rasta Bank fixed the ceiling and instructed to commercial banks not to
invest more than 20 percent of lend or loan in real estate sector, increased the bank
interest, government's policies were not addressing to all issues and not consistent.
Similarly, instable political condition, one government endorsed one policy and
another cancelled it, no healthy professional's practice, etc. are main causes for
stagnation of housing-apartments and real estate after 2007.
The government is unstable and Nepal being a budding democracy, comprise
of officials lacking a vision or commitment towards the improvement of housing and
infrastructure to meet present day needs or to cope with future growth (Mathema,
1999)
The people who have money were waiting and seeing because the transition
period becoming longer since the major political party that people made largest
(United Nepal Communist Party Maoist) in constitution assembly. The prime-
minister belonged to the same party. Later, the prime-minister dissolved the
constitution assembly without concerning public decision. Therefore, at present
people are not ready to buy the housing and land due to the long transition period.
Particularly high-level of income group family are thinking weather they can stay in
the country or should go out of the country Particularly the people of high-level or
who have money are trying to deposit their money out of the country where their
children are studying due to insecurity physiology.
38
The undue pressure from sister organizations, cadres of the political parties
including donation was being severe, which was in first rank, followed by Industries'
environment is political stability, which was the agenda of Nepal land and Housing
Developers' Association (NLHDA) and hence political instability being second rank .
Similarly, politLFDOLQIOXHQFHRIWUDGHXQLRQV¶VWULNHORFNRXWLQDQGRXWRI KRXVLQJ
apartment and real estate was the third severe problem and strikes called by different
political parties during the construction phase was fourth severe problem.
From the facts and survey undue pressure from various political parties, their
sister organization, cadre who want the money from the project in the name of
various meeting, agitations, convention and seminar is first. Next problem was not
being ready the industry-friendly environment due to unstable politics and
government, since one government make one policy and next government eliminate
that policy, third problem was in the name of trade union supported by different
political parties raise unnecessary problem and lockout and strike. The fourth
problem was Strike called by the different political parties, from which working
environment becomes deteriorate and couldnot create friendly environment for
investment. Therefore conclusion could be drawn from the above facts that due to
political problem industry- friendly environment is not yet established in Nepal.
40
created big risks. Developers were dependent on bank and if bank did not give money
then the project would be stopped.
It was also observed that respondent identified the lack of budgeting and cash
flow management being the first rank problem followed by lacking of promoter's
cash flow management, high operation cost and high cost of project equipment as
second, third and fourth rank of problems respectively.
Housing projects are facing the problems of lack of budgeting and cash flow
management. Similarly, lack of promoter's cash flow management is another
problem. It seems that developer's equity and loan from financial institution were
being used for housing and apartment projects. Government change in its financial
SROLF\DQGFRPPHUFLDOEDQNV¶FKDQJHLQWKHLULQWHUHVWUDWHVDUHVome of the important
problems that could not be managed and it affected the promoters' cash flow
management. As interest being higher, machine cost increases and hence operation
cost becomes high. Commercial banks accept the proposals in one condition and
increase the rate of interest and other conditions to housing and apartment projects
before completing the project.
42
between demand by the client to production time is taken as the opportunity time.
This time is risky for producers.
From the above facts it can be concluded that response of client to the project
more the demand, more the supply principle might be risky which is in first rank
IROORZHGE\ORFDOSHRSOH¶VGHPDQGOLNHHPSOR\HHWRORFDOGHYHORSPHQWWRORFDODQG
so on create economic risk is in second rank. Similarly, ODFNRISURPRWHUV¶FDVKIORZ
because in the right time promoters could not mange the case flow they cannot supply
the goods as per demand and face the risk is in the third rank, and instability of
political system and government create number of problems for creating economic
risk being the fourth risk . Here all the developers need to start the research and
development work. Housing sectors are important, in which they are contributing in
GDP as well as employment opportunity to the people and hence need to be
facilitated by the state.
44
concentrate how to construct the wall so that plaster quantity would be reduced.
Similarly, we decorate clearing (decorated sheet) after plaster, without plaster also we
can put clearing. If we did clearing without applying the plaster price could be
reduced. Next example is, the size of doors-windows all had maintained the standard
size but not required size or demanded size by that particular room.
In the quality issue, the tabulated data given above due to unavailability of
skilled and trained human resources is observed as serious.
It can be conclude from the research that quality of housing, apartment projects
is due to unavailability of skilled and trained human resources, which is in first rank
because without skilled and experienced architect effective design cannot be imagine
and without good construction manager quality cannot be maintained. In the same
way, single person handled in ventured project cannot maintain the quality because
s/he cannot supervise and review due to his/her busyness is in second rank. Suitable
or effective planning and suitable or effective design is ranked third and fourth
respectively because they would not make poor quality but improve it. Similarly,
research and development work need to achieve the quality. Quality is important
factor in every industry and in housing projects it is still important and Nepalese
housing industries are still facing problems in maintaining quality.
7HFKQLFDO ULVN LV UHVSRQVLEOH IRU WKH LQGLUHFW FDXVH¶V WRR)RU H[DPSOH LI WKH
political influence is there, there will be high technical risk. If clients are ready to pay
IRU WKH ULVNV FRQWUDFWRUV DQG GHYHORSHUV ZLOO QRW JLYH HIIRUWV WR VDYH FOLHQWV¶
H[SHQGLWXUH DV WKH H[SHQGLWXUH LV LQ FOLHQW¶V SDUW DQG KHQFH OHW LW EH ZKLFK LV
irresponsible and unethical. For example, a client was required the commercial
building, which have double basement. The contractor searched for low cost
insurance company so that the risk could be transferred. In this particular case, if
client would have committed to bear the rLVNFRQWUDFWRUZRXOGVD\µ2NJRDKHDG¶LW
was client's money and the contractor did not care of it.
Among many questions asked with respondents, I segregated the above-mentioned in
table that is oriented to technical and generates the technical problems, based on the
same ranked according to its severity. It has been plotted in column chart as given
below. Developers want cheaper technical team and they are not able to complete the
work as required is the problem.
49
Developers did not concentrate for research and development regarding the
perfect requirement of buyers. As incorporating cultural requirements with amenities
based on the research, product could be sold easily in the market. Therefore, the joint
apartment would not be appropriate as per their culture and religion compared to
individual housing. Next, the culturally matured citizen wants the modern amenities
as they are using.
In latest days the frequently changing government policy changes the cultural
dimensions too. Previously it was a Hindu state and now no discrimination in the
name of religion and all religions are treated equally. Local peoples' demand for
money influence in the name of renovation of temple and new temple construction
and un-due pressure from different political parties to celebration the cultural day and
programmes. Risk Response Plan is prepared and implemented by housing projects,
which is very limited because hard working culture is being disappearing in our
culture.
It could be concluded that frequent change in government policy is creating
problem whether in Hindu state or religion equality state, holiday on which festival
was in first rank.
50
Due to organizational or Instructional weakness, it there were various risk
being faced. Team must have contained experienced, skilled, motivated, innovative,
and commanding leader. Decision power need to be quick and bold. Construction
manager need to be competitive, technically and experienced. Formally, housing and
real estate work started from around 2003 in Nepal. Therefore, every developer got
the experience of about one decade. They could identify particular problem in the
policy risk, approval risk, financial risk, political risk, labor risk, safety risk, and
other risks factors.
According to Paul C. Stern, (2000), at first step towards understanding the
complexities is to elaborate on the truism that behavior is a function of the organism
and its environment. In one formulation (Guagnano et al., 1995), behavior (B) is an
interactive product of personal-sphere attitudinal variables (A) and contextual factors
(C). The attitude-behavior association is strongest when contextual factors are neutral
and approaches zero when contextual forces are strongly positive or negative,
effectively compelling or prohibiting the behavior in question (an inverted U-shaped
function)
They do not keep in mind whatever risk they felt in previous projects. In the
current project when they feel, oh how to cross the particular risk just make
contingent plan and go away. This was the risk management system in Nepalese
housing and apartment, so no one adopted the systematically risk management
procedure.
Answers of the respondents were segregated related to organizational or
institutional, and tabulated in above table. Based arithmetic means and standard
deviation the ranks were determined as shown in the above table. As mentioned
above, based on the rank the cylindrical column chart was plotted. According to the
column chart, problem due to lack of job description was in first rank followed by
lack of regular meeting of board of director (BoD), periodic review of BoD decision
and undefined or ad-hoc organizational structure of human resource managements
were 2,3,and 4 rank of problems respectively. Problem facing internal and external
must be identified solved by good human resource management. However, without
self-satisfying he cannot give his output in the organization.
52
Chapter-4
In WKH WDEOH EHORZ UHVSRQGHQWV µYLHZ RQ WKH 5LVN 5HVSRQVH 3ODQ LV SUHSDUHG DQG
implemented by Housing and real estate projects in Nepal are given.
Most of the infrastructure, housing apartment and real estate projects are not
prepared and implemented according to the Risk Response Plan. If it occurred then
they used to mitigate from contingency plan which may lead problem.
The main purpose of this chapter is to mitigate the risk factors in infrastructure,
housing and real estate considering the various problems, which occurs due to not
working out the risk management during planning phase, and arising in
implementation phases, considering intensity of uncertainty of money, time, and
quality management, and loss occurs due to various adversities.
Risk mitigation is common of all risk handling strategies. Project manager may
have to be responsible and emphasize to reduce or minimize the expected probability
that the risk may suppose to occur from what the construction manager try to reduce
the negative impacts. The project manager must develop risk mitigation plan from
53
which trace the activities based on the proposed plan. In the policy framework
authority need to break down different economic levels of income group.
55
claim to the authority with legal documents within 7, 15 and 35 days. It is seriously
objectionable. Neighbors would have been out of country during informing or
information access would have not enough. In the property right s/he must be able to
claim his/her property in life time if the proposed project would have been used.
The bylaws and regulations in the city are limited within plot coverage, height
of the building, minimum setback, and right of way. Besides, there are no effective
regulations, laws and policies regarding the housing development that ultimately
resulted in improper and unplanned housing settlements. Very little effort has been
made on the urban form and its overall impact on the city .The approval of building
plan is vested with the local authority where the local authority shall ensure that the
applicant-developer has complied with all necessary rules and regulations, in
particular the Uniform Building By-Laws (UBBL) (Sufian & Rahman, 2008).
The Agreement will stipulate as the primary duty of the engineer that s/he
carefully observes the requirements of the employer in the realization of the project.
It is important to note, however, that the conditions of contract between the employer
DQGWKHRQWUDFWRUVWLSXODWHWKDWZKHUHXQGHUWKHFRQWUDFWDQ\RIWKHHQJLQHHU¶VGXWLHV
are discretionary, the engineer shall act fairly between the employer and the
contractor and apply the contract in an impartial manner. The conditions are based
upon this fundamental principle and this requirement applies even if the engineer is a
PHPEHURIWKHHPSOR\HU¶VVWDII *XLGHWRWKHXVHRI),',& 8VWD
In fact, in our projects there will be different companies, professionals are
employed like A/E consultant, M/S contractor, M/S suppliers and so on. Every
SURMHFW H[SHFWV WKHLU H[SHUWLVH DQG WKH SURIHVVLRQDO¶V VNLOO $FFRUGLQJ WR WKHLU
condition of contract, they must be responsible. Therefore, based on document if the
proposed projects have maintained the Nepal standard building code from the safety
point of view he can supervise or instruct, otherwise need not supervise by DUDBC,
but others professional must be responsible. A/E consultant can determine the height
of the building. Moreover, why to give other authority to make complication from
others nock and corners were existed and facing so many hurdles?
Anyone company registered with the ministry of industry and tax office is a
developer and other side anyone who do not register with authority is developer. Both
are doing housing and real estate business. If it is continuing why to register with
government authority and pay the tax when individuals are doing business without
paying money as a developer.
Validity for the democratic component of DLG (and much for its local
governance as well) deepen in the final analysis on participation and accountability
56
bringing as many citizens as possible into the political arena assuring that local
governs are responsible to the governed for their action. Fortunately, there is
considerable scope for enhancing both participation and accountability at the local
level (Blair, 2000).
58
Land use plan must be endorsed in the cities, land need to supply to the market.
Therefore, in the land pooling need to be further expanded and public amenities need
to develop. In cites owner built houses are unplanned and unmanaged, which are
scattered but state responsibility is to provide drinking water, drainage, good road for
the public. The mentioned work is continuously doing through local development
authorities. If it coordinates with local authorities and urban development authorities
and start housing and public infrastructure more efficiency could be achieved.
In such an imperfect market, the government should intervene, although this
may have positive or negative effects. This intervention has largely been in terms of
planning. In order to protect the natural environment and to avoid uncontrolled
development, new housing can only occur subject to planning approval. Also as
industrial restructuring has left vacant and derelict land in many cities, urban
regeneration has become important in government policy and attracting new housing
GHYHORSPHQWWRµEURZQILHOG¶ODQGKDVEHHQJLYHQDFHQWUDOSODFHZLWKWDUJHWVEHLQJ
set for the proportion of new development allocated between brown field and green
field sites(White & Allmendinger,2003).
Previous policy was not interpreted and applying this is also a problem,
because if we execute the policy then only we can decide whether the policy is
successful or not? So integrated policies by combining all social, economical,
financial and other related problems need to be identified and addressed properly and
endorsed policies need to be implemented perfectly.
59
Risk management is a vital work in developing countries. Even global
competition is not experienced because political instability, impunity financial crises
are frequently occurred and hence decision-making procedure takes more time.
Therefore, projects became more uncertain. Risk management is important in
housing, apartment, and real estate project for cash-flow management, by anticipating
loss or profit. Similarly, project can experience the mitigation if it occurred and for
future which is treating as an asset.
60
4.5 HRM Team must be experienced for Risk Mitigation
Developers are conscious about their profit, which is a positive aspect, whereas they
were always concentrated to employee cheap construction manager, engineer,
supervisors including all human resource team to save the profit, which is negative
aspect because experienced and skilled technical person expect good salary. It is
always true that experienced and skilled risk manager do better risk management than
inexperienced and unskilled risk manager.
Most of the developers were employing inexperienced and unskilled
construction manager including all human resources team. They were proud of
themselves for saving the overhead cost but they never thought the consequences due
to risks factors which may have adverse effect and big lost for company.
63
severe. Acceptance is also known as retention and it is broken down in two types of
acceptance: one is passive and the other one is active. Passive acceptance is the
acceptance of risk without taking any action to manage it whereas active acceptance
acknowledge the risks as well but calls for development of contingency plans and
other special plan to mitigate.
65
assessment of work; 4) by performing extensive test and evolution and 5) by
minimize system complexity and use design margins.
References
67
Science, Engineering and Technology, Vol:39 2010-03-25,
http://waset.org/publications/5772
Bonapace,C. & Sestini V. (2003). Traditional materials and construction technologies
used in the Kathmandu valley. United Nations Educational, Scientific and
Cultural Organization (UNESCO). Retrieved from http://www.barbara-
brink.com/nepaltradbuildmat.pdf
Blair, H. (2000). Participation and accountability at the periphery: democratic local
governance in six countries. World development, 28(1), 21-39, Retrieved from
http://isites.harvard.edu/fs/docs/icb.topic845003.files/
Chapman,C. & Ward, S.(2003). Project risk management, processes, techniques and
insights [Second edition].
http://www.ajtvdw.info/uni/Project%20Management%20Book%20Flood%20(9
8%20Books)/
Chau, K.W., Wong, S.K. & Yiu, C.Y. (2005, July). Housing quality in the forward
contracts market. (A paper submitted to NUS-HKU Symposium on Real
Estate Research ). Retrieved from
http://www.rst.nus.edu.sg/research/symposium_files/
Chen, M. A. , Jhabvala , R. & Lund, F. (2001). Supporting workers in the informal
economy: A policy framework. Paper Prepared for ILO Task Force on the
Informal Economy. Retrieved from http://wiego.org/sites/wiego.org/
Chileshe,N. & Yirenkyi-Fianko, A. B. (2011). Perceptions of threat risk frequency
and impact on construction projects in Ghana:Opnion survey and findings.
Journal of Construction in Developing Countries,16(2), 115±149. Retrieved from
http://web.usm.my/jcdc/input/
Comeaux , P. E. and Kinsella, N. S.(1994). Reducing Political Risk in Developing
Countries: Bilateral Investment Treaties, Stabilization A uses and Mega and
Optics Investment Insurance , New York Law School Journal of International and
Comparative Law, Volume 5, Number 1, 1994, http://www.kinsellalaw.com/wp-
content/uploads/publications/comeaux_kinsella_pol_risk_ny.pdf
Denney, D. (2005). Risk and society. New Delhi: SAGE Publications. Retrieved from
http://220.227.128.112/downloads/CriticalPerspectives/booksforreview%20CP
T%20S7/
Dougls M.(9085).Risk Acceptability According to Social Science, Russell Sage
Foundation Publications,New Yourk
Farias, L. de L., Travassos, G. H. & Rocha, A. R. (2003). Managing organizational
risk knowledge. Journal of Universal Computer Science, 9(7), 670-681. Retrieved
68
from
http://www.jucs.org/jucs_9_7/managing_organizational_risk_knowledge/de_Land
a_Farias_L.pdf
Fewings, P.(2005). Construction Project Management, Taylor & Francis is an imprint
of the Taylor & Francis Group, 270 Madison Ave, New York, NY 10016, USA, ©
2005 Peter Fewings,ISBN 0-203-00698-4
Gotham, K. F. (2001). Urban redevelopment, past and present. Critical Perspectives
on Urban Redevelopment, 6, 1±31.
Guagnano, G, P Stern, and T Dietz (1995) Influences on attitude behavior
relationships ± a natural experiment with curbside recycling, Environment and
Behavior, 27(5), pp. 699-718.
HKSAR, (1959). CAP 123 Building (Planning) Regulations ± Lighting and
Ventilation, Hong Kong Special Administrative Region The Government of
Hong Kong SAR, China, 1959.
Hatch, M. J. & Schultz, M. (2003), Bringing the corporation into corporate branding.
European Journal of Marketing Vol. 37 No. 7/8, pp. 1041-1064.
Doi:10.1108/03090560310477654. Retrieved from
http://www.livingthebrand.com/upload/Corporate%20Branding.pdf
Junior, J. da R. L., Alencar C. T. de & Monetti, E. (2003, June). Investment Analysis
provided for developers in the housing sector using the Internet. XXXI IAHS.
Retrieved from
http://www.realestate.br/images/File/arquivosPDF/finalpaperIAHS_I_259.pdf
Kamau, P.K.(2002). Enhancing housing development and ownership: Prospects for
individual housing development in Nairobi, Kenya (Master's thesis, University
of Tsukuba). Retrieved from http://www.sk.tsukuba.ac.jp/sse/degree/2001/
Karki, T.K. ( 2004).Challenges of managing a government town planning office in
1HSDO D SODQQHU¶V H[SHULHQFH. Environment & Urbanization,16 (2).
doi:10.1177/095624780401600213. Retrieved from
http://eau.sagepub.com/content/16/2/
Kamsi, R. (2005). Spatial database for residential property: Customers' and
developers' requirement (Bachelor's thesis).Retrieved from
http://eprints.ptar.uitm.edu.my/946/1/RAMIZAH_KAMSI_05_24.pdf
Keizer, J. A., Halman, J. I.M. & Song, M. (2002). From experience: applying the risk
diagnosing methodology. The Journal of Product Innovation Management 19,
213±232.
69
http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.196.348&rep=rep1&
type=pdf
Kerzner, H.(2006). Project management: a systems approach to planning, scheduling,
and controlling (9th ed.). Canada: John Wiley & Sons, Inc.
Khadka, R. B., Dalal-Clayton, B., Mathema, A. & Shrestha, P. (2012). Safeguarding
the future, securing Shangri-La Integrating environment and development in
Nepal: achievements, challenges and next steps. United Kingdom: the
International Institute for Environment and Development (UK) in 2012.
Retrieved from http://www.environmental-
mainstreaming.org/documents/Shangri-La%20report%20(web%20file).pdf
Koirala, M.P., (2012). Risk in Housing and Real Estate Construction Project Study
in Nepal. A thesis submitted to the Singhania University, Rajasthan, India, in
partial fulfillment of the requirement for the degree of Doctor of Philosophy in
Engineering.
Koirala, M.P.(2014) , Risk in housing and real estate Construction Project, Journal of
the Institute of Engineering vol-10,No.1,pp34-44. TUTA/IOE/PCU,
http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.1004.6894&rep=rep
1&type=pdf
Koirala, M.P. (2016). Health and Safety Concern of Workers of Building Materials
Producing Industries in Nepal, International Journal of Engineering Research
& Technology (IJERT), Vol. 5 Issue 12, December-201, ISSN: 2278-0181,
http://www.ijert.org
Koirala, M.P.(2017) Contribution of Risk Factors for Infrastructure Development of
Nepal. American Journal of Civil Engineering. Vol. 5, No. 3, 2017, pp. 124-
131. doi: 10.11648/j.ajce.20170503.11,
http://www.sciencepublishinggroup.com/journal/paperinfo?journalid=229&doi
=10.11648/j.ajce.20170503.11
Lea,M. & Chiquier,L.(n.d.).Providing long-term financing for housing: the role of
secondary market (Research Report). Retrieved from Office of Development
Studies, Bureau for Development Policy, United Nations Development
Programme website http://www.microfinancegateway.org/gm/document-
1.9.26067/318.pdf
Levi, (1905). Chapter II: The Newars , At the Indo-Tibetan Interface, vol.I 1905:366
Li B. and Piachaud D., (2006), Urbanization and Social Policy in China, Asia-Pacific
Development Journal Vol. 13, No. 1, June 2006, http://www.unescap.org/sites/
70
Lohani, S. N. (2006, September). Factors contributing to the desertification of
productive agriculture land and its implication on environment. Agri-
Environment and Biodiversity Section. Retrieved from
http://aicc.gov.np/publications/environment_journal/agriculture_environment_
publication_2006.pdf#page=28
Mathema, A.S. (1999). Housing and land market in Kathmandu, Nepal.
Massachusetts Institute of Technology, Cambridge, MA. Retrieved from
http://www.ucl.ac.uk/dpuǦrojects/drivers_urb_change/urb_economy/
Mathur,O.(2011).Urban challenges in south & south-west Asia. In Fifth Asia Pesific
Urban Forum, United Nations, ESCAP. Retrieved from
http://www.unescap.org/apuf-5/documents/updates/
Ng,E.(2003,August).Applying computational simulation result to the development of
design method for daylighting design and regulation in high densities cities.
Paper presented Eighth International IBPSA Conference, Eindhoven,
Netherland. Retrieved from http://www.inive.org/members_area/medias/pdf/
NLHDA. (2008). Building by-laws for the construction apartment. Nepal Land and
Housing Developers's Association website. Retrieved from
http://www.housingnepal.com/articles/display/the-building-by-laws-for-the-
construction-of-apartment
Nepal Labour Force Survey. ( 2008). Central Bureau of Statistics, National Planning
Commission Secretariat, Government of Nepal, July 2009,
http://cbs.gov.np/wp-content/uploads/2012/02/NLFS-2008%20Report.pdf
NLSS. (2011). Nepal Living Standard Survey (NLSS). Nepal: Central Bureau of
Statistics, National Planning Commission Secretariat Government of Nepal.
Retrieved from http://cbs.gov.np/wp-content/uploads/2012/
Oberlender,G.D.(1993).'Project Management For Engineering And Management'
McGraw-Hill Inc, New York.
Ofori,G. (1994) "Construction technology development: role of an appropriate
policy", Engineering, Construction and Architectural Management, Vol. 1
Issue: 2, pp.147-168, doi: 10.1108/eb020998,
http://www.emeraldinsight.com
Orueta,F. D. (2007). Madrid: Urban regeneration projects and social mobilization.
Cities, 24(3), 183±193. Retrieved from
http://cuimpb.cat/politiquesurbanes/docs/Num_32_JCIT769.pdf
Ostrom, E. (2000, n.m.). Private and common property rights. Paper Presented on
Workshop in Political Theory and Policy Analysis, and Center for the Study of
71
Institutions, Population, and Environmental Change, Indiana University.
Retrieved from http://www.sfu.ca/~allen/common%20property.pdf
Pelling , M., et al.(2004). Reducing Disaster Risk: a challenge for development. New
York : United Nations, http://archive-ouverte.unige.ch/unige:77685
Shaha, R. (n.d.). Ancient and medieval Nepal. Kathmandu Nepal. Retrieved from
http://himalaya.socanth.cam.ac.uk/collections/journals/kailash/pdf/
Shen, J. (2000). Chinese urbanization and urban policy. China Review, 455-480.
Retrieved http://ihome.cuhk.edu.hk/~b890706/download/P13Y2000.pdf
Shrestha,B.K. (2010). Housing provision in the Kathmandu valley: Public agency and
private sector initiation. Urbani izziv, 21(2). doi: 10.5379/urbani-izziv-en-
2010-21-02-002. Retrieved from http://urbani-
izziv.uirs.si/Portals/uizziv/papers/
Shrestha, R.S.(2011). The Kantipur Daily, 2 march, Kantipur Publication.
Siegel, C.(2008). The Politics of Simple Living, A New Direction for Liberalism.
Berkeley,California: Preservation Institute. Retrieved from
http://fog.its.uiowa.edu/~lsahunni/200/siegel%20PoliticsOfSimpleLiving.pdf
Stern, P.C.(2000). Toward a Coherent Theory of Environmentally Significant
Behaviour, Journal of Social Issues, Vol 56, No.3, 2000, PP, 407-424,
http://www.ce.cmu.edu/~gdrg/readings/2006/02/28/Stern_Coherent_Theory_of
_Env_Significant_Behavior.pdf
Sufian, A. & Rahman, R. A. (2008). Quality housing: Regulatory and administrative
framework in Malaysia. Int. Journal of Economics and Management 2(1): 141
± 156. Retrieved from http://econ.upm.edu.my/ijem/vol2no1/bab07.pdf
Tansey, J. & O'Riordan , T. (1999). Cultural theory and risk: a review. Health, Risk &
Society, 1(1). Retrieved from http://paul-
hadrien.info/backup/LSE/IS%20490/utile/
Tibari, I.P.(2008). Urban Migration and Urbanization in Nepal. Asia-Pacific
Population Journal. Retrieved from
http://s3.amazonaws.com/zanran_storage/www.unescap.org/ContentPages/108
193381.
Todaro, M. P. & Smith, S. C. (2003), "Economic development eight edition".India:
Dorling Kindersley Pvt.Ltd.
Turskis, Z. , Zavadskas, E. K. & Peldschus F.(2009). Multi-criteria optimization
system for decision making in construction design and management.
Engineering Economics No 1 (61) Economics of Engineering Decisions.
Retrieved from http://www.ktu.edu/lt/mokslas/zurnalai/inzeko/
72
Tuuli, M.M. & Rowlinson, S.(n.d). Empowerment in project teams: A multilevel
examination
of the job performance implications ,WHPZDVVXEPLWWHGWR/RXJKERURXJK¶V
Institutional Repository). Retrieved from https://dspace.lboro.ac.uk/dspace-
jspui/bitstream/2134/
Tummala,V.M.R. & Burchett J.F. (1999). Applying a Risk Management Process
(RMP) to manage cost risk for an EHV transmission line project, International
Journal of Project Management Vol. 17, No. 4, pp. 223-235, 1999
UN-HABITAT,United Nations Human Settlements Programme. (2010). Nepal urban
housing sector profile (electronic version). Nairobi 0010, Kenya: UN-
HABITAT Retrieved from
www.unhabitat.org/pmss/getElectronicVersion.aspx?nr=3156&
Usta, E.(2005). Comparison of international federation of consulting engineers and
general specification for public works contracts from risk management
perspective (Master's thesis Middle East Technical University). Retrieved from
http://etd.lib.metu.edu.tr/upload/12606443/index.pdf
White, M. & Allmendinger, P. (2003). Land-use Planning and the Housing Market: A
Comparative Review of the UK and the USA. Urban Studies, 40( 5±6), 953±
972. doi: 10.1080/0042098032000074263. Retrieved from http://www.china
up.com:8080/international/case/case/1390.pdf
Wollmann, H. (2004). Local Government Reforms in Great Britain,
Sweden, Germany and France: Between Multi-Function and Single-Purpose
Organizations. Local Government Studies, Vol.30, No.4, pp.639 ± 665. doi:
10.1080/0300393042000318030. Retrieved from
http://unpan1.un.org/intradoc/groups/public/documents/
73
74
View publication stats