PERHITUGAN VOLUME GROUND 20 M3

SKETSA 1 - PEMBERSIHAN LAHAN


P = 7.400 M1
L = 4.900 M1

L
Volume = ((P+2) x (L+2))
= 64.86 M2

P Vtotal = 64.860 M2

SKETSA 2 - PEMASANGAN BOWPLANK


Ln = 12.800 M1 H
Ln = 11.700 M1 V

Volume = (L1+L2+Ln)
= 28.50 M1

Vtotal = 28.500 M1

SKETSA 3 PEKERJAAN TANAH DAN URUGAN


- GALIAN TANAH
Ground
Latas = 6.150 M1
Lbawah = 5.800 M1
Tinggi = 0.800 M1
P = 3.600 M1

Volume = (Latas + Lbawah)


x Tinggi x P
2
= (6.15 + 5.8)
x 0.8 x 3.600
2
= 17.208 M3

Rabat
P = 6.800 M1
L = 4.300 M1
T = 0.200 M1
Jumlah = 1.000 Bh

Volume = (P x L x T) X Jumlah
= (6.8 x 4.3 x 0.2) X 1
= 5.848 M3

Drainase
P = 27.800 M1
L = 0.400 M1
T = 0.300 M1
Jumlah = 1.000 Bh

Volume = (P x L x T) X Jumlah
= (27.8 x 0.4 x 0.3) X 1
= 3.336 M3

Box Valve
P = 1.000 M1
L = 0.900 M1
T = 0.850 M1
Jumlah = 1.000 Bh

Volume = (P x L x T) X Jumlah
= (1 x 0.9 x 0.85) X 1
= 0.765 M3

Vtotal = 27.157 M3

SKETSA 3 PEKERJAAN TANAH DAN URUGAN


- URUGAN TANAH

Latas = 0.360 M1
Lbawah = 0.270 M1
Tinggi = 0.450 M1
P = 19.800 M1

Volume = (Latas + Lbawah)


x Tinggi x P
2
= (0.36 + 0.27)
x 0.45 x 19.800
2
= 2.807 M3

Latas = 0.700 M1
Lbawah = 0.100 M1
Tinggi = 0.350 M1
P = 19.800 M1

Volume = (Latas + Lbawah)


x Tinggi x P
2
= (0.7 + 0.1)
x 0.35 x 19.800
2
= 2.772 M3

Vtotal = 5.579 M3

SKETSA 4 - URUGAN PASIR


- LANTAI KERJA
P = 5.800 M1
L = 3.300 M1
T = 0.100 M1
T

L
Volume = (P x L x T)
= (5.8 x 3.3 x 0.1)
= 1.914 M2

- RABAT
P = 19.800 M1
L = 0.700 M1
T = 0.050 M1

Volume = (P x L x T)
= (19.8 x 0.7 x 0.05)
= 0.693 M2
- DRAINASE
P = 27.800 M1
L = 0.400 M1
T = 0.050 M1

Volume = (P x L x T)
= (27.8 x 0.4 x 0.05)
= 0.556 M2

- BOX VALVE
P = 1.000 M1
L = 0.900 M1
T = 0.050 M1

Volume = (P x L x T)
= (1 x 0.9 x 0.05)
= 0.045 M2

Vtotal = V.Lantai Kerja + V. Rabat + V. Drainase + V. Box Valve


= 3.208 M3

SKETSA 5 - BETON TUMBUK 1 : 3 + DRAINASE


- LANTAI KERJA
P = 5.820 M1
L = 3.340 M1
T = 0.050 M1
T

Volume = (P x L x T)
L
= (5.82 x 3.34 x 0.05)
= 0.972 M2

- RABAT
P = 19.800 M1
L = 0.700 M1
T = 0.150 M1

Volume = (P x L x T)
= (19.8 x 0.7 x 0.15)
= 2.079 M2

- DRAINASE
P = 27.800 M1
L = 0.200 M1
T = 0.100 M1

Volume = (P x L x T)
= (27.8 x 0.2 x 0.1)
= 0.556 M3

Vtotal = V.Lantai Kerja + V. Rabat + V. Drainase


= 3.607 M3

SKETSA 6 - PAS. DRAINASE BATU BATA


- DINDING DRAINASE BATU BATA
P = 27.800 M1
L = 0.250 M1
J = 2.000 Bh
T

Volume = (P x L x J)
L = (27.8 x 0.25 x 2)
= 13.900 M2

Vtotal = 13.900 M2
SKETSA 7 - COR BETON BERTULANG 1 : 2 : 3
Lantai Dinding H Dinding V
P = 5.820 M1 P = 5.400 M1 P = 2.500 M1
L = 3.340 M1 L = 1.850 M1 L = 1.850 M1
T = 0.200 M 1
T = 0.200 M 1
T = 0.200 M1
J = 2.000 Bh J = 2.000 Bh

Volume = (P x L x T) Volume = (P x L x T) x J Volume = (P x L x T) x J


= (5.82 x 3.34 x 0.2) = (5.4 x 1.85 x 0.2 x 2 = (2.5 x 1.85 x 0.2 x 2
= 3.888 M3 = 3.996 M3 = 1.850 M3

Dag Penguras Balok


P = 5.400 M1 P = 4.800 M1 P = 2.500 M1
L = 2.900 M1 L = 0.050 M1 L = 0.200 M1
T = 0.150 M1 T = 0.200 M1 T = 0.050 M1
J = 1.000 Bh

Volume = (P x L x T) Volume = (P x L x T) x J Volume = (P x L x T)


= (5.4 x 2.9 x 0.15) = (4.8 x 0.05 x 0.2 x 1 = (2.5 x 0.2 x 0.05)
= 2.349 M3 = 0.048 M3 = 0.025 M3
T

L
Vbeton B = 12.156 M3 Lantai = 3.936 M3
Dinding = 5.846 M3
Vlobang = 0.108 M3 Dak = 2.266 M3

Vtotal = VBAK - Vlobang


= 12.048 M3

SKETSA 8 - PEKERJAAN BOX VALVE


- PEKERJAAN BOX VALVE ( TYPE 1 )
P = 1.00 M1
L = 0.90 M1
T = 1.00 M1
Tebal = 0.10 M1
J = 1.00 M1

Volume = (P x L x Tebal) + ((2P + 2L) x T x Tebal) x J


= (1 x 0.9 x 0.1) + ((2(1) + 2(0.9)) x 1 x 0.1)x4
= 0.47 M3

- PEKERJAAN BOX VALVE ( TYPE 2 )


P = 0.00 M1
L = 0.00 M1
T = 0.00 M1
Tebal = 0.00 M1

Volume = (P x L x Tebal) + ((2P + 2L) x T x Tebal)


= (0 x 0 x 0) + ((2(0) + 2(0)) x 0 x 0)
= 0.00 M3

Vtotal = V.type 1 + V.type 2 + V.type 3


= 0.470 M3

SKETSA 9 - PEKERJAAN PLESTERAN


- PLESTERAN LUAR BAK
P = 5.400 M1 P = 2.900 M1 P = 5.400 M1
L = 1.350 M1 L = 1.350 M1 L = 2.900 M1
J = 2.000 Bh J = 2.000 Bh J = 1.000 Bh

Volume = (P x L x J) Volume = (P x L x J) Volume = (P x L x J)


= (5.4 x 1.35 x 2) = (2.9 x 1.35 x 2) = (5.4 x 2.9 x 1)
= 14.580 M3 = 7.830 M3 = 15.660 M3

- PLESTERAN RABAT - PLESTERAN DRAINASE


P = 19.800 M1 P = 27.800 M1
TAMPAK D EPAN
Skala 1 : 50

L = 0.800 M 1
L = 0.700 M1

Volume = (P x L x2) Volume = (P x L x2)


TAMPAK BELAKAN G
Skala 1 : 50 = (19.8 x 0.8x 2) = (27.8 x 0.7x 2)
= 31.680 M2 = 38.920 M2

TAMPAK KIRI TAMPAK KAN AN


Skala 1 : 50 Skala 1 : 50

- PLESTERAN BOX VALVE


P = 0.800 M1 P = 0.850 M1 P = 0.850 M1
L = 0.700 M1 L = 0.800 M1 L = 0.800 M1

Volume = (P x L) Volume = (P x L) Volume = (P x L)


= (0.8 x 0.7) = (0.85 x 0.8) = (0.85 x 0.8)
P

= 0.560 M2 = 0.680 M2 = 0.680 M2

L P = 0.850 M1 P = 0.850 M1 P = 1.000 M1


L = 0.700 M1 L = 0.700 M1 L = 0.150 M1

Volume = (P x L) Volume = (P x L) Volume = (P x L)


= (0.85 x 0.7) = (0.85 x 0.7) = (1 x 0.15)
= 0.595 M2 = 0.595 M2 = 0.150 M2

P = 1.000 M1 P = 0.900 M1 P = 0.900 M1


L = 0.150 M1 L = 0.150 M1 L = 0.150 M1

Volume = (P x L) Volume = (P x L) Volume = (P x L)


= (1 x 0.15) = (0.9 x 0.15) = (0.9 x 0.15)
= 0.150 M2 = 0.135 M2 = 0.135 M2

Vbeton Plesteran = VPlesteran BAK + Vplesteran Box Valve


= 112.350 M2

Vlobang = 0.720 M2

Vtotal = VPlesteran - Vlobang


= 111.630 M2
SKETSA 10 PEKERJAAN PLESTERAN WATER PROOFING
- PLESTERAN DALAM BAK WATER PROOFING
Lantai + DAG dinding H dinding V
P = 5.000 M1 P = 5.000 M1 P = 2.500 M1
L = 2.500 M 1
L = 1.850 M 1
L = 1.850 M1
J = 2.000 Bh J = 2.000 Bh J = 2.000 Bh

Volume = (P x L x J) Volume = (P x L x J) Volume = (P x L x J)


= (5 x 2.5 x 2) = (5 x 1.85 x 2) = (2.5 x 1.85 x 2)
= 25.000 M3 = 18.500 M3 = 9.250 M3

Balok
P = 2.500 M1
L = 0.100 M1

Volume = (P x L)
= (2.5 x 0.1)
= 0.250 M2

Vbeton Plesteran = 53.000 M2


P

Vlobang = 0.720 M2

L
Vtotal = VPlesteran - Vlobang
= 52.280 M2

1 PANCANG KAYU DIA. 10 CM


Jumlah = 0.00 M1

11 - PENGECETAN BIASA
Jumlah = 38.07 M2

12 - PENGECETAN WATER PROFING


Jumlah = 52.28 M2

13 - PENGECETAN PIPA GIP


Jumlah = 6.28 M2

13 - PEKERJAAN ACIAN BIASA


Jumlah = 111.63 M2

14 - PEKERJAAN ACIAN WATER PROFING


Jumlah = 52.28 M2

15 - PEKERJAAN PLESTERAN 1.5 CM


Jumlah = 163.91 M2

SKETSA 16 - PEMASANGAN ACCESSORIES


- PEMASANGAN WATER STOP
Jumlah = 15.80 m'

- PEMASANGAN VENTILASI
Jumlah = 2.00 Unit

- PEMASANGAN BEND 90 LAS GIP Ø 150 MM


Jumlah = 6.00 Unit
TAMPAK D EPAN
Skala 1 : 50

- PEMASANGAN FLANGE LAS GIP Ø 150 MM


Jumlah = 15.00 Bh
TAMPAK BELAKAN G

- STRAINER ALL FLANGE GIP Ø 150 MM


Skala 1 : 50

Jumlah = 1.00 Bh

- PEMASANGAN GATE VALVE FLANGE GIP Ø 150 MM


TAMPAK KIRI TAMPAK KAN AN
Skala 1 : 50 Skala 1 : 50

Jumlah = 2.00 Unit

- WATER STOP
Jumlah = 15.80 Meter

- PUDDLE FLANGE Ø 150 MM


Jumlah = 4.00 Bh

- POMPA
Jumlah = 0.00 Unit

- PEMASANGAN PIPA GIP Ø 150 MM


Jumlah = 20.00 Meter

- PEMASANGAN PENUTUP MAN HOLE + GEMBOK


Jumlah = 2.00 Unit

- PEMASANGAN PENUTUP BOX VALVE + GEMBOK


= 1.00 Unit

- PEMASANGAN TANGGA MONYET


Jumlah = 4.00 Unit
RECAP GROUND 20 M3
No Nama Pekerjaan Volume
1 - PEMBERSIHAN LAHAN 64.86 M2
2 - PEMASANGAN BOWPLANK 28.50 M1
3 - GALIAN TANAH 27.16 M3
4 - URUGAN TANAH 5.58 M3
5 - URUGAN PASIR 3.21 M3
6 - BETON TUMBUK 1 : 3 + DRAINASE 3.61 M3
7 - PAS. DRAINASE BATU BATA 13.90 M2
8 - COR BETON BERTULANG 1 : 2 : 3 12.05 M3
Lantai 3.94 M3
Dinding 5.85 M3
Dak 2.27 M3
9 - PEKERJAAN BOX VALVE 0.47 M3
10 - PENGECETAN BIASA 38.07 M2
11 - PENGECETAN WATER PROFING 52.28 M2
12 - PEKERJAAN ACIAN BIASA 111.63 M2
13 - PEKERJAAN ACIAN WATER PROFING 52.28 M2
14 - PEKERJAAN PLESTERAN 1.5 CM 163.91 M2
15 - PEMASANGAN ACCESSORIES
- PEMASANGAN VENTILASI 2.00 Bh
- PEMASANGAN BEND 90 LAS GIP Ø 150 MM 6.00 Bh
- PEMASANGAN FLANGE LAS GIP Ø 150 MM 15.00 Bh
- STRAINER ALL FLANGE GIP Ø 150 MM 1.00 Bh
- PEMASANGAN GATE VALVE FLANGE GIP Ø 150 MM 2.00 Bh
- WATER STOP 15.80 M1
- PUDDLE FLANGE Ø 150 MM 4.00 Bh
- POMPA - Bh
- PEMASANGAN PIPA GIP Ø 150 MM 20.00 M1
- PEMASANGAN PENUTUP MAN HOLE + GEMBOK 2.00 M1
- PEMASANGAN PENUTUP BOX VALVE + GEMBOK 1.00 M1
- PEMASANGAN TANGGA MONYET 4.00 Unit

16 PEKERJAAN BETON
- BEGESTING 50.55 M2
Lantai 3.64 M2
Dinding 29.23 M2
Dak 17.68 M2
- BESI Ø 12
PANJANG 1,157.40 M1
LEBAR 1,030.09 Kg
- BESI Ø 10
PANJANG 1,860.60 M1
LEBAR 1,153.57 Kg
PERHITUGAN VOLUME PAGAR BRC

SKETSA 1 - PEKERJAAN PAFIN BLOCK


P = 19.700 M1
L = 19.400 M1

L
Volume = ((P+2) x (L+2))
= 464.38 M2

P -GROUND
P = 12.400 M1
L = 7.210 M1

T Volume = ((P+2) x (L+2))


= 132.62 M2
L

-Box Valve
P = 1.750 M1
L = 1.400 M1

Volume = ((P+2) x (L+2))


= 12.75 M2

Vtotal = Pembersihan Lahan - Ground


Vtotal = 300.706 M2

RECAP BRONCAP
No Nama Pekerjaan
1 - PEKERJAAN PAFIN BLOCK
PAGAR BRC

-Box Valve
P = 1.000 M1
L = 1.000 M1

Volume = ((P+2) x (L+2))


= 9.00 M2

-Box Valve
P = 1.100 M1
L = 1.000 M1

Volume = ((P+2) x (L+2))


= 9.30 M2

Lahan - Ground

BRONCAP
Volume
300.71 M2