Kabupaten :

PERHITUNGAN VOLUME PEKERJAAN Kecamatan :


Desa :
Lokasi :
SKETSA PERHITUNGAN VOLUME

01. Pek. Bouplank - Panjang Bouplank


P = P + P + L + L
= 21,00 + 21,00 + 3,00 + 3,00
= 48,00 m1

Pek. Pembersihan Lahan - Pembersihan lahan


Luas = P x L
= 22,00 x 4,00
= 88,00 m2

02. Pek. Galian Tanah - Volume Galian Tanah tinggi 1,6m


V = unit x L x T x P
= 2,00 x 0,70 x 1,6 x 20,00
= 44,8 m3

- Volume Galian Tanah tinggi 0,25m


V = unit x L x T x P
= 1,00 x 1,60 x 0,25 x 20,000
= 8 m3

- Volume timbunan kembali =


V = P x L x T x rumus x unit
= 20,000 x 0,40 x 1 x 0,5 x 2
= 8 m3

02. Pek. Batu kali - Volume batu kali =


V = P x L x T x unit
= 20,00 x 0,70 x 0,6 x 2
= 16,8 m3

V = P x L x T x unit
= 20,00 x 1,60 x 0,15 x 1
= 4,8 m3
-
V = P x ((a1 + a2) / 2) x T x Unit
= 20,00 x 0,36 + 0,7 / 2 x 0,85 x 2
= 18,02 m3

V = P x ((a1 + a2) / 2) x T x Unit


= 20,00 x 0,21 + 0,15 / 2 x 0,15 x 2
= 1,08 m3

V Total = 40,7 m3

02. Pek. Beton - Volume Beton k-300 =


V = P x L x T x unit
= 20,00 x 1,90 x 0,15 x 1
= 5,7 m3
02. Pek. Bekisting - Volume Bekisting Untuk Beton
V = P x T x SISI x Unit
= 1,90 x 0,15 x 2,00 x 1,00
= 0,57 M2

- Volume Bekisting Untuk Bodex


V = P x L
= 20,00 x 1,6
= 32 M2

0,5 Pek. Pembesian - Volume Pembesian wermes M12 - Volume Bodex


Luas = p x L x dabel V = P x L
= 20,00 x 1,900 x 2 = 20,00 x 1,9
= 76 M2 = 38 M2
= Luas x Koef
= 76,00 x 12,26
= 931,76 kg

Jumlah = Luas / Koef


= 76 / 11,3
= 7 Lembar