Phase
Installed power
Status as of 31.01.2023 Region - for EE producers according to amendments to the Energy Act

- for EE consumers and producers under the Energy Act


Change to permanent connection
1 TE-TO Skopje Skopje 230 MW phase change to permanent connection
Total Change to permanent connection 230 MW

Consumer 1
workshop Cranfield Foundry 2 TS Ovÿe Probist 40 MW 5 Phase - Completed connection
Pole 3 factory IGM TREJD 4 Mine Plavica Saint Nicholas 25 MW 5 Phase - Completed connection
Dubrovo 27 MW 4 Phase - Performance
Probistip 15 MW 2 Phase - Analysis, Study and Decision for Consent
Total Consumer 107 MW

SEE - Electric energy storage


1 Phase - Requirements for joining, Feasibility studies,
1 SEE Kumanovo Kumanovo 80 MW
additional data
Total SEE 80 MW

RENEWABLE ENERGY SOURCES (OIE) VEC - Wind


Power Stations
1 VEC Bogdanci 2 Bogdanci 37 MW 5 Phase - Completed connection
VEC Bogoslovec 3 VEC Saint Nicholas 36 MW 5 Phase - Completed connection
Demir Kapija - Dren 2 4 VEC Miravci Demir Gate 44 MW 3 Phase - Project documentation
1A 5 VEC Koprišnica 6 VEC Petrovo 7 Valandovo 14 MW 2 Phase - Analysis, Study and Decision for Consent
VEC Ramno 8 VEC Kiÿevo Demir Gate 40 MW 2 Phase - Connection Variants and Connection Analysis
Demir Gate 40 MW 2 Phase - Connection Variants and Connection Analysis

Kumanovo 50 MW 2 Phase - Connection Variants and Connection Analysis


Kitsch 35 MW 2 Phase - Connection Variants and Connection Analysis
1 Phase - Requirements for joining, Feasibility studies,
9 VEC Dojran 1 Dojran 50 MW
additional data
1 Phase - Requirements for joining, Feasibility studies,
10 VEC Dojran 2 Dojran 50 MW
additional data
1 Phase - Requirements for joining, Feasibility studies,
11th century Prilep* Sticky 47 MW
additional data
1 Phase - Requirements for joining, Feasibility studies,
12th century Kazandol Valandovo 50 MW
additional data
1 Phase - Requirements for joining, Feasibility studies,
13 CENTURY Springs* Kumanovo 414 MW
additional data
Total VEC - 5, 4, 3, 2, and 1 phase 907 MW
14 VEC Bogdanci 1B 15 Valandovo 13 MW 0 Phase - Idea

VEC Bogdanci 2 16 VEC Valandovo 50 MW 0 Phase - Idea

Miravci 1B 17 VEC Miravci Valandovo 36 MW 0 Phase - Idea

2 Valandovo 50 MW 0 Phase - Idea


Total VEC - 0 Phase - Idea 86 MW
Total VEC 993 MW

FEC - Photovoltaic Electric Power Stations 1 FEC


Okta 2 FEC Novaci 3 FEC Oslomej 3a (JPP with ESM) 4 Skopje 12 MW change to permanent connection
FEC Oslomej 3b (JPP with ESM) 5 FEC Erzhelija* 6 FEC Bitola 50 MW 3 Phase - Project documentation
Dubrovo IGM Calm down 50 MW 3 Phase - Project documentation
Calm down 50 MW 3 Phase - Project documentation
Saint Nicholas 80 MW 2 Phase - Analysis, Study and Decision for Consent
3 phases - Project programs for the Basic project for connection and
Dubrovo 80 MW
Preliminary opt-in consent
3 phases - Project programs for the Basic project for connection and
7 FEC Dolneni Sticky 400 MW
Preliminary opt-in consent
Total FEC - Performed plug-in analysis 722 MW

FEC Bitola 2 FEC 60 MW 3 phases - Project programs for the Basic project for connection and
8 Bitola
Bitola 3 100 MW Preliminary opt-in consent

Bitola
3 phases - Project programs for the Basic project for connection and
9 FEC Ship Gneotino 100 MW
Preliminary opt-in consent

Bitola
3 phases - Project programs for the Basic project for connection and
10 FEC Gneotino 29 MW
Preliminary opt-in consent

Bitola
3 phases - Project programs for the Basic project for connection and
11 FEC Armature 29 MW
Preliminary opt-in consent

Bitola
3 phases - Project programs for the Basic project for connection and
12 FEC Dobromiri 30 MW
Preliminary opt-in consent
13 FEC Pelagonia Bitola 63 MW 2 Phase - Connection Variants and Connection Analysis
Total FEC - Prepared analyzes for connection in the Pelagon region 411 MW
Machine Translated by Google

Phase
Installed
Status as of 31.01.2023 Region - for EE producers according to amendments to the Law on Energy
power
- for consumers and producers of EE according to the Law on Energy
3 phases - Project programs for the Basic project for connection and
14 FEC Scandals A pinch 450 MW
Preliminary opt-in consent
3 phases - Project programs for the Basic project for connection and
15 FEC Scholarship* A pinch 400 MW
Preliminary opt-in consent
3 phases - Project programs for the Basic project for connection and
16 FEC Dolni Balvan* A pinch 85 MW
Preliminary opt-in consent
3 phases - Project programs for the Basic project for connection and
17 FEC Probistip A pinch 35 MW
Preliminary opt-in consent
3 phases - Project programs for the Basic project for connection and
18 FEC Cup A pinch 30 MW
Preliminary opt-in consent
3 phases - Project programs for the Basic project for connection and
19 FEC Suševo 1 20
A pinch 100 MW
Preliminary opt-in consent
A pinch 130 MW 2 Phase - Connection Variants and Connection Analysis
FEC Sveti Nikole Total FEC -
Prepared analyzes for connection to Štip region 1,230 MW

21 FEC Sušica 22 Strumica 40 MW 2 Phase - Connection Variants and Connection Analysis


Pehcevo 70 MW 2 Phase - Connection Variants and Connection Analysis
FEC Pehÿevo* 23
FEC Buÿište 24 FEC Probist 35 MW 2 Phase - Connection Variants and Connection Analysis

Goten 25 FEC Berovo 80 MW 2 Phase - Connection Variants and Connection Analysis


A pinch 75 MW 2 Phase - Connection Variants and Connection Analysis
Slatina 26 FEC
Probistip 2 27 FEC Probist 300 MW 2 Phase - Connection Variants and Connection Analysis

Kopanica 28 FEC Ubogo Skopje 120 MW 2 Phase - Connection Variants and Connection Analysis
1 Phase - Requirements for joining, Feasibility studies,
Urban 600 MW additional data Phase 1 -
Requirements for joining, Feasibility studies,
29 FEC Suševo 2 A pinch 30 MW additional data
1 Phase - Requirements for joining, Feasibility studies,
30 FEC Suševo GIM A pinch 50 MW additional data Phase 1 -
Requirements for joining, Feasibility studies,
31 FEC Nova Breznica Skopje 391 MW additional data
1 Phase - Requirements for joining, Feasibility studies,
32 FEC Dimonce Kratovo 40 MW additional data
1 Phase - Requirements for joining, Feasibility studies,
Kochani 25 MW
33 FEC Banja additional data Phase 1 -
Requirements for joining, Feasibility studies,
Welles 400 MW
34 FEC Source additional data
1 Phase - Requirements for joining, Feasibility studies,
Bitola 138 MW
35 FEC Baldovenci* additional data Phase 1 -
Requirements for joining, Feasibility studies,
36 FEC Kumanovo 1 Kumanovo 100 MW additional data
1 Phase - Requirements for joining, Feasibility studies,
37 FEC Kumanovo 2 Kumanovo 100 MW additional data
1 Phase - Requirements for joining, Feasibility studies,
Bitola 30 MW
38 FEC Novaci 2 additional data Phase 1 -
Requirements for joining, Feasibility studies,
Bitola 261 MW
39 FEC Fog lights additional data
1 Phase - Requirements for joining, Feasibility studies,
40 FEC Bistrenci Kavadarci 21 MW
additional data Phase 1 -
Requirements for joining, Feasibility studies,
41 FEC Dabilje - Strumica Strumica 126 MW additional data
1 Phase - Requirements for joining, Feasibility studies,
Bitola 30 MW
42 FEC Armature 2 additional data
1 Phase - Requirements for joining, Feasibility studies,
43 FEC Strugovo Companion 24 MW
additional data Phase 1 -
Requirements for joining, Feasibility studies,
44 FEC Buchim I'm making noise 29 MW additional data
1 Phase - Requirements for joining, Feasibility studies,
Bitola 40 MW
45 FEC Pelagonija 2 additional data
Total FEC - 1 Phase - Connection Requirements and Connection Variants 46 FEC 3,155 MW
Nexan Stip 700 MW 0 Phase - Idea
Total FEC - 0 Phase - 700 MW

Idea Total FEC 6,218 MW


TOTAL RES 7,211 MW
Investor* - strategic investor with the decision of the Government of RSM
Phases for EE consumers and EE producers under the Energy Act Phases for producers of EE with changes to the Law on Energy
phase of change to permanent 7 Phase - Finished connection
connection 5 Phase - Completed connection 6 Phase - Performance

4 Phase - Performance 5 Phase - Project documentation

4 Phase - Authorization for construction, Study for connection and


3 Phase - Project documentation
Opt-in Consent Decision
3 phases - Project programs for the Basic project for connection and
2 Phase - Analysis, Study and Decision for Consent
Preliminary approval for connection 2 Phase - Variants for
1 Phase - Request for joining and variants for joining connection and Analysis for connection 1 Phase - Requirements for
connection, Feasibility studies,
0 Phase - Idea
additional data
0 Phase - Idea