Professional Documents
Culture Documents
OPERATIONAL EXPERIENCE
WAMS / PMUs Pilot Projects
NR - 13 Nos
WR - 10 Nos
ER - 12 Nos
SR - 10 Nos
NER – 08 Nos
PMU IN SR (AFTER PILOT PROJECTS IN SR & NR PHASE-II)
RSTPS
GAZUWAKA
HYDERABAD
HYDERABAD VIJAYWADA
NARENDRA
GOOTY
KOLAR
CHENNAI Commissioned (kalkitech)
SOMANHALLI
Commissioned (SEL)
SRIPERUMBDUR
3
Utilization of Synchrophasor data
410
405 kV
400
k 390
V
380
370
370 kV
Voltage Plot
Current Plot
3 phase fault
Voltage plot
Current plot
Duration of fault and detection of
possible protections operated
Faults cleared by Distance
protection Zone-2
Phase-Earth Fault
in B-Phase cleared
500ms
Fault cleared in
920ms
Fault cleared in
1020ms
• High resistance fault :
Detection of High resistance Faults
voltage dip is less and less
fault current
• Duration of dip in voltage
As for a long time.
Location of fault
Inference from Voltage drop and df/dt at 400kV buses
Kolar Gooty
Auto-reclose
after dead time
of 1 sec
Sequence of Events from SCADA
02-01-2012 03:59:44.085 InvRTU BASSI CB F_12 H PURA-1 MAIN BUS-1 STTS INVALID Bad
02-01-2012 03:59:44.124 InvRTU BASSI CB F_8 BHIWA-2 &HEERAPURA-1 STTS OPEN GOOD
02-01-2012 03:59:45.222 InvRTU BASSI CB F_12 H PURA-1 MAIN BUS-1 STTS CLOSED GOOD
Dadri end
400kV Dadri-Mandola line-1 (Mandola) end) 400kV Dadri-Panipat line-1 (Panipat end)
13:55:01.789 13:55:03.770
SCADA Sequence of Events
Fault cleared by ICT back up
protection
00:56:57.699
00:56:37.349
Validation of D.R/ E.L
Detection of Non-
synchronization of D.R with
G.P.S
Station Event
Logger print
15:17:07.620 hrs
Station
Disturbance
recorder print
(Digital Signals)
15:15:57.221 hrs
Load throw off / Generation loss
due to cascade tripping & Spl.
cases
Cascade tripping in 220kV
Punjab system 20th July 2011
due opening of overloaded
220kV line
Load loss
Inference from angle difference
plots
P= V1 .V2 Sin
X
• Consequence
– If a critical point is exceeded, the network may not be able to
withstand the next contingency and result in cascading or islanding.
– A large standing angle can prevent reclosing of circuit breakers should
a line trip.
– Possible damage to nearby generation if a circuit breaker is reclosed
with a large angle across it.
Complete outage of
400/220kV Allahabad
Substation handling around
1900MW power
= Sin-1 P.X
V1.V2
Tripping of HVDC Rihand-Dadri
Bipole carrying 1400 MW, SPS
operation
= Sin-1 P.X
V1.V2
Failure of L.A at Dadri (Dadri-
G.Noida line)
Tripping of ICT’s at G.Noida
substation (load before tripping
: 430MW)
Tripping of 2No. 400kV lines
= Sin-1 P.X
V1.V2
2000MW Generation loss
at Rihand STPS
= Sin-1 P.X
V1.V2
Commutation Failure at Kolar
HVDC
19th Feb 2013
7:59:32 hrs
Brief about commutation Failure in HVDC
• Local Mode or Plant mode: Swinging of units at a generating station with respect to the rest of the
power system
– Small part of the power system
– Frequency : 0.8 to 2 Hz
• Intra-Plant Oscillations
– Confined within a plant & not common
– Frequency range is 2 to 3 Hz
Power flow of this line was gradually increased upto 1050 MW.
49.751 Hz
Sl. Generation Change in FRC=
Date & Time Event
No. loss freq MW/Hz
• From these events the power number of S.R grid can be approximated as
2000MW/Hz
Validation of measurement cycle
of df/dt relay
Thank You