You are on page 1of 1

ASWAR ALANDULS

Histogram For Manpower Required

May-24
Mar-24
Dec-23

Apr-24
Feb-24

Jun-24
Jan-24
Total Unit Rate Amount
SR Equipment Aramco Registration
Months SAR SAR

1 Permit Holder 12 1 1 2 2 2 2 2 Required

3 Saftey Officer 13 1 2 2 2 2 2 2 Required

4 Rigger III 12 - 2 2 2 2 2 2 Required

6 QC Inspector 11 - 1 2 2 2 2 2 Required

7 Civil Supervisor 7 1 1 1 1 1 1 1 Required

8 Carpenter 12 2 10 - - - - - Required

9 Steel Fixer 20 10 10 - - - - - Required

10 Labor ( Excavation ) 80 30 30 20 - - - - Required

11 Labor ( Flagman,Firewatcher) 24 4 20 - - - - - Required