Professional Documents
Culture Documents
All downloaded and printed copies of this document are considered as Uncontrolled
Page 1 of 8
AVANTIS
POLICY
This Avantis procedure covers the testing of power cable installations with voltage rating not exceeding 33Kv .
The tests may take place immediately after the cables are installed or after the cables have been in service for
some time.
ARRANGEMENTS
RISK ASSESSMENT
A risk assessment of the hazards arising from any work activity that might expose any persons to danger from
High voltage will be undertaken by a competent person and a corresponding safe working procedure developed.
GENERAL
The mechanical completion inspection sheet shall be accepted by the client before tests are done
All temporary wiring and test equipment shall be removed after testing is completed
The company will ensure that any personal protective equipment will be suitable for its intended use, well
maintained and properly used.
All connections and covers removed during the tests shall be replaced and the cables left ready for service
The test results shall be recorded on the standard forms contained in the procedure
Before commencing any high voltage tests, the area shall be roped off and warning notices posted. all cables
ends shall be suitably supported and insulated against the test voltage to prevent danger to personnel and
equipment. the area at each end of the cable shall be kept clear of all personnel excepting those involved in the
test.
Care shall be taken to ensure that high voltage and insulation resistance tests are not applied to circuit items,
such as potential transformers, electronic components etc.
All downloaded and printed copies of this document are considered as Uncontrolled
Page 2 of 8
AVANTIS
High voltage tests shall not be applied to cables with an unacceptable insulation resistance. the cables with a
value below minimum specifie3d shall be examined for mechanical damage or presence of moisture and, if
present, rectified: if neither moisture nor damage is present the decision on whether to apply the voltage tests
shall be made in consultation with the technical authority.
After each high voltage or insulation resistance test has been performed the cable cores shall be connected to
proven earth and the connection shall be removed only when the cable is completely discharged.
INSTALLATION TESTING
The tests shall be carried out between each core in turn, with the remaining cores bunched and connected to the
cable metallic sheath, armour and earth.
For single cores cables, the test shall be made between the conductor and the metallic sheath and armour which
are connected to the earth.
Table 1 : The test voltages and minimum values of insulation resistance shall be as below.
All downloaded and printed copies of this document are considered as Uncontrolled
Page 3 of 8
AVANTIS
If the minimum resistance above are not achieved the client shall advise what further action is required, such as
either proceed with high voltage test, put cable into service, or replace cable.
High voltage tests are not required on cables with a voltage rating up to and including 600/1,000 volts.
The voltage test on a new installation shall be made with direct current at the appropriate voltage, specified in
table 2 below, and the leakage current recorded.
The voltage shall be increased gradually to the specified value and maintained for 15 minutes, between each
conductor and earth, and between conductors. The tests between each conductor and earth shall be done
before the tests between the conductors.
It should take approximately 10 seconds to reach 75% of the final test voltage and the same time to raise the
voltage from 75% to 100% of the final value.
All downloaded and printed copies of this document are considered as Uncontrolled
Page 4 of 8
AVANTIS
Note (1) : for cables having metal sheathing and/or armouring , the voltage shall be applied between each
conductor and the earthed sheath/armour.
Note (2) : test no required for cores which are individually screened.
For an existing installation it may not be desirable to subject cables to a full voltage test unless requested
otherwise by the client. The recommended test is the application of the cable rated voltage to the live
conductors for 24 hours before putting the installation back into service.
Factors which affect the decision on whether or not to conduct a high voltage test on existing cables are :-
a) If the main object is to discover as accurately as possible if the cable has weak spots which may lead to
subsequent failure then the high voltage test should be carried out. This is the case where the cable is a single
feeder to critical load or if its replacement after being placed in service would be either inconvenient or
expensive.
b) If the main object is to extract as much life as possible from an existing cable , it is recommended that the high
voltage test should be carried out. This is the case where the consequences of a cable failure are not severe and
do not justify the risk of precipitating the failure of a cable which might otherwise remain in operation for an
indefinite time.
a) This test is conducted to ensure the integrity (that is freedom from damage) of cable’s outer sheath. This
sheath provides a barrier against the ingress of corrosive substances which would lead to eventual damage and
deterioration of the metal armour. Integrity of armour is of prime importance particularly where it forms and
earth continuity conductor.
All downloaded and printed copies of this document are considered as Uncontrolled
Page 5 of 8
AVANTIS
b) If required, this test is to be carried out before terminating cable armouring and sheath. The cable sheath shall
be tested by applying a test voltage of 4,000 volts DC for each millimetre of sheath thickness, between the
unearthed cable armour or metal sheath and earth, the test voltage shall be maintained for one minute.
c) Repairs to damage sheathing may be carried out using cable manufacturers recommended procedures
approved by the client.
STANDARD FORMS
The following standard forms included as appendices in this procedure shall be sued for recording the results
REFERENCES: As below or the latest issues thereof (or equivalent IEC standard)
BS 5467 1977 (1984) - Specification for armoured cables with thermo – setting insulation for electricity supply
BS 6346 1897 - Specification for PVC insulated cables for electricity supply
BS 6622 1985 - Specification for cables with extruded cross linked polyethylene or ethylene propylene rubber
insulation for rated voltages from 3,800/6,00V to 19,000,33,000V
Note : BS 6622 - Permits higher test voltages values to be used for a completely new installation , than those
listed in the test procedure
BS 6883 - Is the British industry standard for the offshore oil and gas ship building and marine industries.
All downloaded and printed copies of this document are considered as Uncontrolled
Page 6 of 8
AVANTIS
PURPOSE
To ensure suitable compliance, safety consideration and control of Electrical Testing in-line with the Electricity
Regulations.
All downloaded and printed copies of this document are considered as Uncontrolled
Page 7 of 8
AVANTIS
On completion of all testing, re-connect cabling as required and remove LO/TO as necessary
On completion of all tests, re-connect cabling as required and remove LO/TO as necessary
RECORDS
Records will be kept of:
All downloaded and printed copies of this document are considered as Uncontrolled
Page 8 of 8