TRAINING OBJECTIVES:

This course aims to develop the skillful work force in the field of concrete

construction as construction industry is facing a lot of difficulties for doing the

shuttering works in the construction field without the trained man power. The

work of shuttering carpenter is of paramount important in the field of concrete

constructions in the specific areas/works. It is one of the major areas of skills,

which is still ignored for formal training. Presently they learn the skill, from senior

artisan by working with them for many years as helper. This course covers all the

related topics of studies & practicals enabling the job market to have skillful

persons resulting into better results for timely & safely completion of the civil

works specially for concrete construction.

CURRICULUM SALIENT:

Entry level : Primary (Preference will be given


to matriculation)
Duration : 3 – Month
Total Training Hrs : 360 Hrs
: 30 Hrs per week
6 days a week
5 Hrs per day
Training methodology : Theory 10 %
: Practical 90 %
Medium of Instruction : Urdu

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 2

SKILL PROFICIENCY DETAILS:

On successful completion of this course, a trainee should be able to:

1. Apply all safety precautions, personal and equipment.


2. Use, sharpen and set common hand tools e.g. measuring, marking,
sawing and planning tools.
3. Measure, cut and plane timber to given size
4. Construct and use the wood work joints, butt joints, lap joint, cross joint,
dove tail joint, mortise and tennon joint.
5. Operate joints, use and maintaining wood working power machines
6. Use spirit level and plumb line for maintaining structural alignment
7. Erect wooden scaffolding to any height for construction and repair works
8. Cut, shape and assemble wooden parts of column base and beam etc.
9. Construct wooden formwork for roof slab with beam and projection and
staircase.
10. Erect timbering of trenches.
11. Make centering for arches e.g. segmental, semicircular and inverted.
12. Erect tabular scaffolding to any height for construction work.
13. Erect steel form work for roof slab, beam estimate and walls
14. Read & interpret structural drawing and calculate number and sizes of
formwork / shuttering components.

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 3

KNOWLEDGE PROFICIENCY DETAILS:

On successful completion of this course, a trainee should be able to:

1. Define the reading and interpreting drawings & sketches


2. Define the building components and their sequence of construction
3. Describe the covered area calculations of buildings
4. Describe the thumb rules for material and cost estimation
5. Identify the types of timbers and be able to distinguish good and defective
timber
6. Express the types of screws, nails and bolts commonly used in the trade.
7. Express the types of saws, planes, making tools and method of
sharpening and setting
8. Explain the method and the seasons for seasoning timber
9. Explain the different types of joints and their uses
10. Explain the method of erecting timbering for trenches
11. Describe the method of constructing centering for various types of arches
12. Identify the types and importance of joints in concrete construction.

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 4

SCHEME OF STUDIES
Shuttering Carpenter
(3-Month Course)

Sr. Theory Practical Total


Main Topics
No Hrs. Hrs. Hrs.
1. Trade Related Math 7 33 40

2. Reading Drawing 9 10 19

3. Wood Working 9 100 109

4. Scaffolding 03 41 44

5. Form Work 8 128 136

6. Work Ethics - 12 12

Total 36 324 360

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 5

Detail of Course Contents


Shuttering Carpenter
(3 - Month Course)

Theory Practical
Sr. No Detail of Topic
Hrs. Hrs.
1. Trade Related Mathematics
1.1 Basic Mathematic 1 6
1.1.1. Additions & subtraction of whole
number
1.1.2 Multiplication and division of whole
numbers
1.1.3 Multiplication & division of fraction
1.1.4 Addition & subtraction of fraction
1.1.5 Addition & subtraction of decimal
fraction
1.1.6 Multiplication & division of decimal
fraction
1.1.7 Percentage: change number to
percent, change percent to decimal
and fraction
1.1.8 Solve problems related to addition,
subtraction, multiplication, division
and percentage
1.2 Measurement System 1
1.2.1 Foot pound system of measurement
1.2.2 Parts / fraction of inches and foot
1.2.3 Metric system of measurement
1.2.4 Multiples and parts of units
1.2.5 Conversion of foot pound to metric
system vise versa

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 6

1.2.6 Exercise to solve problems related to 4


conversion, addition, subtraction and
multiplication & division of
measurements
1.3 Angles 1 4
1.3.1 Angle and its units
1.3.2 Types of angles
1.3.3 Calculation (addition and subtraction
etc.)
1.4 Surface Area 1 4
1.4.1 Surface area of rectilinear plane
figures (square, rectangle, triangle,
trapezium, rhombus & parallelogram
etc.
1.4.2 Surface area of angular plane
figures (circle, segment, sector etc.)
1.4.3 Practice in calculating area of
different geometrical figures
1.4.4 Pythagoras theorem and its
application
1.4.5 Area and perimeter of composed
figures
1.4.6 Practice in calculating areas and
perimeter of composed figures 4
1.4.7 Practice in calculating covered area
of building from working drawing
1.5 Volume 1
1.5.1 Volume and unit of volume
1.5.2 Volume of geometrical solids

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 7

1.5.3 Surface area of geometrical solids


1.5.4 Quantity of liquid in container
1.5.5 Practice in calculating volume and 3
surface areas of different
geometrical solid
1.6 Weight 1 4
1.6.1 Weight and its units
1.6.2 Specific weight / density
1.6.3 Specific weight of different
construction material & components
1.6.4 Practice to calculate the weight of
different materials on the basis of
volume and density
1.7 Estimation & Wastage 1 4
1.7.1 Estimating cost of formwork on the
basis of surface area
1.7.2 Calculating wastage on the basis of
area and length
1.7.3 Practice of solving problem
regarding estimating cost of
formwork
2. Reading Drawing
2.1 Introduction Of Drawing 1
2.1.1 Necessity & importance of drawing
2.1.2 Types of engineering drawing
2.2 Free hand sketching 1
2.2.1 Types and material for free hand
sketching
2.2.2 Sketching of lines and geometrical
figures
2.2.3 Exercise to draw different lines, 3
circle, ellipse, triangle, rectangle &
polygons

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 8

2.2.4 Free hand pictorial sketching


2.2.5 Exercise to draw pictorial sketches 3
of different wooden blocks
2.3 Scales 1
2.3.1 Types and uses of scales
2.3.2 Reading exercise of different scales 1
2.4 Building Drawing Symbols 1
2.4.1 Alphabet of lines
2.4.2 Symbol for material, door, windows,
plumbing, electrical fitting and fixture
2.5 Technical Term Used In Building 1
2.5.1 Structural terms
2.5.2 House planning term (corridor,
balconies, powder, pantry etc.)
1
2.6 Building Drawing
2.6.1 Presentation & Working drawings
2.6.2 Brief introduction to plans, elevation
& section
2.6.3 Reading exercise of working and 3
structural drawings of different
buildings
2.7 Introduction Of Building Materials 2
2.7.1 Cement; types and properties
2.7.2 Sand; types and properties
2.7.3 Aggregate; types and properties
2.7.4 Bricks; types and properties
2.7.5 Reinforcement; types and properties
2.8 Components Of Building 2
2.8.1 Foundation
2.8.1.1 Spread footing
2.8.1.2 Column footing

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 9

2.8.1.3 Deep foundation


2.8.2 Walls
2.8.3 Columns
2.8.4 Beams
2.8.5 Lintels & sunshade
2.8.6 Roof slab
2.8.7 Stair case
2.8.8 Arches
2.8.9 Floors
3. Wood Working
3.1 Measuring tools and their uses 1
3.1.1 Steel rule, folding rule, steel tape etc.
3.1.2 Tri-square and sliding bevel
3.1.3 Vernier calipers
3.1.4 Practice to use steel rule, tri-square 3
& sliding tee bevel & calipers etc.
3.2 Marking Tools And Their Uses 1
3.2.1 Marking gauge
3.2.2 Mortise gauge
3.2.3 Scriber, divider, tri-square
3.2.4 Practice to use marking tools 3
3.3 Sawing Tools 1
3.3.1 Handsaw; types & parts
3.3.1 Cross cut saw, rip saw, back saw,
coping saw, dove tail saw etc.
3.3.2 Method of sharpening saw
3.3.3 Practice of sawing wood along the 6
grain and cross the grain
3.3.4 Practice to sharpening and saw 3
setting
3.4 Planning Tools 1

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 10

3.4.1 Types of planes & parts


3.4.2 Jack plan, jointer plane, smoothing
plane, rabbet plane, router plane,
grooving plane, spoke shape plane,
circular plane
3.4.3 Practice to use planes 9
3.4.4 Practice to assemble and 1
dismantling iron jack plane
3.4.5 Practice to sharpen the iron blade 1
3.5 Wood Chisels 1
3.5.1 Types of chisel; firmer chisel,
mortise chisel
3.5.2 Practice to sharpen chisel 1
3.5.3 Practice to make square hole in 4
wood
3.6 Nailing / Screwing Tools & Their Uses 1
3.6.1 Nails; types and sizes
3.6.2 Screws (flat head screw, Phillip
screw and oval head screw)
3.6.3 Screw drivers; Ratchet brace
3.6.4 Hammers; types and weight
3.6.5 Hand drill and electric drill machine
3.6.6 Practice of nailing and screwing in 4
wood
3.6.7 Practice to use hand drill and 2
electrical drill machine
3.7 Wooden Joints 1
3.7.1 Types
3.7.1.1 Dovetail joints
3.7.1.2 Tee joints
3.7.1.3 Mortise and tennon joints

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 11

3.7.2 Practice of making Butt and Lap 6


joints
3.7.3 Practice of making dovetail and tee 6
joint
3.7.4 Practice of making cross & miter joint 6
3.8 Wood & Artificial Wood 1
3.8.1 Types of wood
3.8.2 Wood seasoning
3.8.3 Wood defects
3.8.4 Artificial wood; Vernier, ply, wood,
hard board, farmica and chip board
etc.
3.9 Wood Working Machines 1
3.9.1 Jointer machine, thickness planer,
circular saw, band saw, drill machine
etc.
3.9.2 Practice to use the wood working 8
machines
3.9.3 Practice to measure, cut and plane 8
timber to given size
3.9.4 Practice to cut, shape and assemble 15
parts of column formwork
3.9.5 Practice to make wooden moulds for 15
precast beam, post, block etc.
4. Scaffolding 3
4.1 Wooden scaffolding components
4.2 Types of knots
4.3 Practice to make different types of knots 4
4.4 Practice to erect wooden scaffolding for wall 6
construction
4.5 Practice to erect wooden ramp for roof slab 8

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 12

4.6 Practice to erect timbering of trenches 5


4.7 Practice to erect tubular scaffolding for wall 6
construction
4.8 Practice to erect tubular scaffolding for co- 5
lumn
4.9 Tubular scaffolding; components 5
5. Form Work
2
5.1 Shuttering for lintels & arches
5.1.1 Lintel, bearing, thickness of
lintel and components of shuttering
5.1.2 Shuttering for sunshade
5.1.3 Arches, components & centering
procedure
5.1.4 Practice to erect shuttering for lintel
and sunshade 4
5.1.5 Practice to erect shuttering /
centering for arches 10
5.2 Reinforcement Placing
2
5.2.1 Types of reinforcement bars
5.2.2 Location of reinforcement bars in
structure (main & distributor bar)
5.2.3 Concrete cover, spacer etc
5.2.4 Practice of placing reinforcement in
lintel & sunshade etc. 3
5.3 Form Work For Frame Structure 2
5.3.1 Introduction to frame structures
5.3.2 Types of beams; tee beam, isolated
beam, inverted beam etc
5.3.3 Types of roof slab; R.C.C slab,
Ribbed roof slab, R.B slab etc.
5.3.4 Column and column base

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 13

5.3.5 Concrete walls


5.3.6 Components of form work for beam,
slab, column & wall
5.3.7 Practice to construct form work for 4
isolated beam
5.3.8 Practice to construct / erect wooden 8
form work for R.C.C roof slab
5.3.9 Practice to erect formwork for roof 8
slab with beams
5.3.10 Practice to erect formwork for roof 8
slab with beam and projection
5.3.11 Practice to dismantle above 3
formwork
5.3.12 Practice to erect steel formwork for 4
column
5.3.13 Practice to erect formwork for roof 12
slab having beams by using tubular
scaffolding and steel plates
5.3.14 Practice to dismental steel formwork 3
5.3.15 Practice to construct formwork for 13
ribbed roof slab
5.3.16 Practice to construct formwork for 12
concrete wall
1
5.4 Form Work For Stair
5.4.1 Types of stairs
5.4.2 Components of stairs
5.4.3 Components of formwork for
concrete stair
5.4.4 Calculating slope and layout of stair
5.4.5 Practice to make shuttering for 8
single flight concrete stair

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 14

5.4.6 Practice to make shuttering for dog 16


legged stair
5.5 Shell Roof Formwork 1
5.5.1 Introduction to shell roof
5.5.2 Components of formwork for shell
roof
5.5.3 Hoisting devices
5.5.4 Visit of under construction shells 12
6. Work ethics 12

Total 36 324

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 15

LIST OF MACHINERY / EQUIPMENT

For the Class of 25 Students


(3-Month Course)

The following machinery / equipment etc. would be required for effective and

comprehensive training of the trainees at the institute level/ their timely

modifications, improvements and innovations are also recommended miniature

sectional working models of plants machinery / equipment are preferred.

Sr. No Item Quantity

1. Circular saw 01 No.

2. Plainer (Jointers Plainer) 01 No.

3. Thickness plainer (platform type) 01 No.

4. Band saw 01 No.

5. Zig saw 01 No.

6. Drill machine (pedestal type) 01 No.

7. Jack planers 25 Nos.

8. Jointer plainer 10 Nos.

9. Smoothing plane 10 Nos.

10. Rabbet plane 10 Nos.

11. Spoke shape plans 05 Nos.

12. Circular plane 05 Nos.

13. Steel rule 10 Nos.

14. Folding rule 05 Nos.

15. Steel tape 25 Nos.

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 16

16. Tri square 05 Nos.

17. Sliding bevel 05 Nos.

18. Vernier caliper 15 Nos.

19. Marking gauge 25 Nos.

20. Mortise gauge 05 Nos.

21. Scriber 10 sets.

22. Divider 05 Nos.

23. Cross cut saw 25 Nos.

24. Rip saw 05 Nos.

25. Back saw 05 Nos.

26. Coping saw 05 Nos.

27. Dovetail saw 05 Nos.

28. Wood working bench with vise 13 Nos.

29. Wooden chisel set (set of 20) 25 Nos.

30. Screw driven set (set of three) 15 sets.

31. Hand drill with bits 15 Nos.

32. Ball pin hammer 25 Nos.

33. Zambox 25 Nos.

34. Tubular scaffolding; steel pipe 1 ½” 20 feet length 100 ft.

35. Fixed joints 100 meter

36. Universal joints 50 Nos.

37. Steel plates (different sizes) 200 sqft.

38. Wooden planks (different sizes) 200 Nos.

39. Wooden props 50 Nos.

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 17

40. Crowbar 05 Nos.

41. Spanner set 10 sets.

42. Screw wrench set 05 sets

43. Dangry 30 Nos.

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 18

MINIMUM QUALIFICATION OF TEACHERS

D.A.E in civil with five years experience in relevant field.

D.A.E (Mechanical) with five years experience in construction industries.


OR

Certificate in carpenter trade (2 Years) with seven years experience as


Shuttering Foreman

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 19

REFERENCE BOOKS

1. Rasul Manual on field work

2. Building construction By

a. Arura & Gupta

b. Sharma

c. Michel’s

3. Building construction By Sharma

4. Building construction By Churly Vol 1–4

5. Wood working By Development Cell, Lahore.

D e ve l o p e d b y C u r r i c u l u m S e c t i o n , A c a d e m i c s D e p a r t m e n t TE V TA .
Shuttering Carpenter (3-Month Course) 20

EMPLOYABILITY OF PASS OUTS

The pass-outs of this course can find job/ employment opportunities in the
following sectors / areas:-

1. Communication & works department


2. Govt. development authorities
3. Civil contractors
4. Pak P.W.D
5. Military engineering services MES
6. NES PAK and other consulting firms
7. National logistic cell, NLC
8. Frontier works organization FWO.