Professional Documents
Culture Documents
Assumption:
Cement = RM385.00/tonne (1m3 = 1.40 tonne)
Sand = RM51.33/tonne (1m3 = 1.52 tonne)
Aggregate = RM50.33 (1m3 = 1.62 tonne)
Wastage & shrinkage = 50%
Concrete mixer capacity & output= 10/7 @ 3.25m3/hour
Concrete mixer (rental) = RM425.00/day (including delivery to site)
Concrete mixer (operator) = RM74.50/day
General worker (concrete mixer) = 4 pax @ RM53.50/day
General worker (placing concrete) = 8 hours @ RM53.50/day
Diesel = 1.80 liters/hour @ RM1.90/liter
Lubricant = 0.07 liter/hour @RM42.50/liter
Profit & overhead = 15%
Question:
Based on the information given, calculate price per m3 for the concrete work.
Assumption:
Cement = RM19.25/bag (1 bag = 50kg, 1m3 = 1.40tonne)
Sand = RM49.33/tonne (1m3 = 1.52tonne)
Aggregate = RM81.50/m3
Wastage & shrinkage = 50%
Concrete mixer capacity & output= 7/5 @ 2.25m3/hour
Concrete mixer (operator) = RM74.50/day
General worker (concrete mixer) = 3 pax @ RM57.50/day
General worker (placing concrete) = 8 hours @ RM57.50/day
Diesel = 1.60 liters/hour @ RM1.90/liter
Lubricant = 0.06 liter/hour @RM42.50/liter
Profit & overhead = 15%
Question:
Based on the information given, calculate price per m3 for the concrete work.
TUTORIAL WEEK 3 – CONCRETE WORK 2
COST ESTIMATING DDWQ3373
Assumption:
Cost of material = refer answer in Question 1
Wastage & shrinkage = 33%
Cost of mixing concrete = refer answer in Question 2
Mobile crane 20 tonne (rental) = RM500.00/day
General worker (placing concrete) = 5 pax @ RM57.50/day
Diesel = 1.80 liters/hour @ RM1.90/liter
Lubricant = 0.07 liter/hour @RM25.00/liter
Profit & overhead = 15%
Question:
Based on the information given, calculate price per m3 for the concrete work.
Assumption:
Question:
Based on the information given, calculate price per m3 for the concrete work.
Assumption:
Mild Steel Round Bar R12 MS146= RM2,466.67/tonne
Wastage = 5%
Binders = 10kg @ RM2.35/kg
General worker (unload bars) = 1.50 hours @ RM53.00/day
Barbender = 50 hours (cutting & bending) & 70 hours (fixing) @ RM84.50/day
Profit & overhead = 15%
Question:
Based on the information given, calculate price per kg for the concrete work.
TUTORIAL WEEK 3 – CONCRETE WORK 3
COST ESTIMATING DDWQ3373
25mm diameter high tensile steel reinforcement in straight and bent bars in pad foundation -
kg
Assumption:
Question:
Based on the information given, calculate price per kg for the concrete work.
Fabric reinforcement to M.S. 145 Ref A10 with 200mm side and end laps in ground floor slab – m2
Assumption:
Question:
Based on the information given, calculate price per m2 for the concrete work.
Assumption:
Question:
Based on the information given, calculate price per m2 for the concrete work.
Assumption:
Plywood 1.22m (4’) x 2.44m (8’) x 12mm = RM52.33/piece
Timber support = 0.04m3 @ RM1,480.00/tonne (1.40m3)
Wastage = 10%
Number of use = 4 times
Nails = 0.35kg @ RM4.50/kg
General worker (prepare & fix to place) = 0.75hours @ RM57.50/day
General worker (removal & storage) = 0.75hours @ RM57.50/day
Carpenter (prepare & fix to place) = 1.50hour @ RM84.00/day
Profit & overhead = 15%
Question:
Based on the information given, calculate price per m2 for the concrete work.