Hussein Farhat
Run #4
Experiment #6:
Analysis of Air Conditioning Unit
Instructor: Asieh Jalali-Farahani
Section #5
Date of Experiment: November 9, 2020
Date Report Submitted: December 3, 2020
Group #2
Raw Data:
RH SH (X) h V
Tdry Twet TDew
(%) gram moisture/kg (kJ/kg) 3
o o o (m /kg)
( C) ( C) air ( C)
Psychrometric Chart for all points in process connecting (to show process):
Note:
Black = Point 1
Blue = Point 2
Green = Point 3
Purple = Point 4
Calculations:
Discussion:
Process 1-2: Heating and humidification process
Process 2-3: Cooling and dehumidification process
Process 3-4: Heating and humidification process
The process 1-2 was expected to be only heating and no adding of moisture and
humidification. As for process 2-3, it was expected to have cooling and dehumidification
since some of the moisture was removed. Finally, in process 3-4, the expected result was
humidification and heating because the air is pushed out towards point 4 so moisture will be
added in.
For the changes of relative humidity in process 1-2, it was expected to see relative
humidity drop because the temperature increased due to the preheating process. For process
2-3 the expected result was to see relative humidity rise, because the temperature decreased
due to the cooling process. Finally, for process 3-4, the expected result was to see relative
humidity drop since the temperature here increased because of the reheating process.
At process 2-3. Dehumidification was not expected because the temperature at point 3
increases when compared to the dewpoint temperature at point 2.