भारत सरकार GOVERNMENT OF INDIA

रे ल मंत्रालय MINISTRY OF RAILWAYS


(रे लवे बोर्ड RAILWAY BOARD)

No New Delhi, dated 15.07.2023

DRM Jhansi
North Central Railway

Sub: Review of Amrit Stations Work of Jhansi Division of North Central


Railway

Please find the attached Inspection Note of Review of Amrit Stations Work of Jhansi,
division carried out by JD/GS/SD-V on 26.06.2023 for necessary action.

(Ashish Verma)
JD/GS/SD-V
Railway Board

DA-As above

Copy :

1.GM/NCR for kind information please

2.PCE/NCR, CE/SD/NCR for information and necessary action please

3.PED/GS, ED/SD&T for kind information please


Inspection Note of Shri Ashish Verma, Joint Director/Station Development/RB

Review of Amrit Stations Work of Jhansi Division of North Central Railway on


26/06/2023

Officials accompanied:
1.D P Garg, CPM/GSU/JHS
2.Mr Gyanendra Pratap Singh,Dy CPM/GSU/JHS
3.Mr. Ashutosh Chaurasia, Sr DEN/Co/JHS
4.Mr Kapil Goel, Sr DEN/JHS
5.Mr Sudhir Kumar, Sr DEN/JHS

SNo Items Discussed/Observations


1 In Jhansi Division, total 19 nos. of stations are identified as Amrit
Stations.

Out of 19 no’s stations, 1 station (Gwalior) is being executed by


Construction Organization. Jhansi Division is executing the works for 18
nos of Amrit Stations.

Dy. CE/GSU advised that the consultant for all the stations has been fixed
and the preparation of master plan and 3D façade views is under progress.

Works has been distributed among Sr DEN’s and GSU of Jhansi Division.
2 2 Stations (Khajuraho & VGLJ) are under Master Planning. Needs to be
expedited.
It was informed that Work at Sheopur Kalan Railway Station will be
developed as part of Gauge Conversion Work.
3 A presentation on the master planning of Amrit Stations was given by the
Architectural Consultant/s. General Observations are:

• Second Entry has not been planned.Integration with both sides of


city should be focused.
• It was also observed that the commercial area has not been marked
in the master plan at most of the stations. All the commercial area
for phase-1 and future land parcel provision should be properly
marked in the master plan. Holistic Master Planning shall be done.
• No master plan has been got approved from DRM/Jhansi and
GM/NCR. Approval of Master Plans to be expedited.

4 Tenders for 15 stations have been invited.


Signage Layout Plan for all stations are yet to be prepared as per Railway
Board Instructions. Further, tender for Signages shall be planned.
5 Inspected Orcha Station. Observations are:
• The works in Circulating & Platform area is under progress.
• All safety precautions shall be followed.
• Advised that all works shall be executed as per approved Master
Plans.
6 Requirement of PSSA and GC needs to be assessed. Accordingly, tenders
may be planned.
7 Documentation of Existing station photographs and work in progress
photos to be properly done. The photographs shall be taken from the same
spot for better comparison