Basildon Rooftop Project RSM550 Edit - vc0 Results
Basildon Rooftop Project RSM550 Edit - vc0 Results
Normalized productions (per installed kWp): Nominal power 3762 kWp Performance Ratio PR
6 1.0
Lc : Collection Loss (PV-array losses) 0.17 kWh/kWp/day PR : Performance Ratio (Yf / Yr) : 0.914
0.9
Ls : System Loss (inverter, ...) 0.06 kWh/kWp/day
5 Yf : Produced useful energy (inverter output) 2.45 kWh/kWp/day
0.8
[kWh/kWp/day]
0.7
4
Performance Ratio PR
0.6
Energy
3 0.5
0.4
Normalized
2
0.3
0.2
1
0.1
0 0.0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Legends: GlobHor Horizontal global irradiation GlobEff Effective Global, corr. for IAM and shadings
DiffHor Horizontal diffuse irradiation EArray Effective energy at the output of the array
T_Amb Ambient Temperature E_Grid Energy injected into grid
GlobInc Global incident in coll. plane PR Performance Ratio
PVSYST V6.81 01/06/23 Page 4/5
The probability distribution variance is also depending on some system parameters uncertainties
Specified Deviation PV module modelling/parameters 1.0 %
Inverter efficiency uncertainty 0.5 %
Soiling and mismatch uncertainties 1.0 %
Degradation uncertainty 1.0 %
Global variability (meteo + system) Variance 1.9 % (quadratic sum)
Probability distribution
0.50
0.45
P50 = 3302726 kWh
0.40
0.35
0.30
Probability
0.25
E_Grid simul =
0.20 3370128 kWh
P90 = 3223026 kWh
0.15
0.05
0.00
3100000 3150000 3200000 3250000 3300000 3350000 3400000 3450000 3500000
E_Grid system production kWh