Expected work schedule of WBM A&B rubber lining replacement plan 2023

2023
PM Unit EQUIPMENT WO Activity January February March April May June July August
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3
Document for PTW & Safety Induction
WBM A
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
Open WBM inlet & outlet manhole
Drain all steel ball
Dismantle WBM drum bolt
Cleaning and painting inside drum
Install new rubber lining
Fabricating inlet & outlet manhole rubber lining
Close manhole
Leakage test
Commisioning
COM
Document for PTW & Safety Induction
WBM B
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
Open WBM inlet & outlet manhole
Drain all steel ball
Dismantle WBM drum bolt
Cleaning and painting inside drum
Install new rubber lining
Fabricating inlet & outlet manhole rubber lining
Close manhole
Leakage test
Commisioning
Document for PTW & Safety Induction
WBM A
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
152075 Open WBM inlet manhole
Dismantle WBM drum bolt
Install new rubber lining (half side)
Fabricating inlet manhole rubber lining
Close manhole
Leakage test
Commisioning
COM
Document for PTW & Safety Induction
WBM B
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
153419 Open WBM inlet manhole
Dismantle WBM drum bolt
Install new rubber lining (half side)
Fabricating inlet manhole rubber lining
Close manhole
Leakage test
Commisioning

Prepared by

Senior Staff
August September October November December
W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

Prepared by Reviewed by Approved by

Senior Staff Mechanical Leader Mechanical Manager


Expected work schedule of WBM A&B rubber lining replacement plan 2024

2023
PM Unit EQUIPMENT WO Activity January February March April May June July August
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3
Document for PTW & Safety Induction
WBM A
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
Open WBM inlet & outlet manhole
Drain all steel ball
146071 Dismantle WBM drum bolt
Cleaning and painting inside drum
Install new rubber lining
Fabricating inlet & outlet manhole rubber lining
Close manhole
Leakage test
Commisioning
COM
Document for PTW & Safety Induction
WBM B
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
Open WBM inlet & outlet manhole
146073 Drain all steel ball
Dismantle WBM drum bolt
Cleaning and painting inside drum
Install new rubber lining
Fabricating inlet & outlet manhole rubber lining
Close manhole
Leakage test
Commisioning
Document for PTW & Safety Induction
WBM A
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
Open WBM inlet manhole
Dismantle WBM drum bolt
Install new rubber lining (half side)
Fabricating inlet manhole rubber lining
Close manhole
Leakage test
Commisioning
COM
Document for PTW & Safety Induction
WBM B
Preparation tools and mobilization
Isolation equipment (Rack Out)
Install scafold for acces
Open WBM inlet manhole
Dismantle WBM drum bolt
Install new rubber lining (half side)
Fabricating inlet manhole rubber lining
Close manhole
Leakage test
Commisioning

Prepared by

Senior Staff
August September October November December
W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

Prepared by Reviewed by Approved by

Senior Staff Mechanical Leader Mechanical Manager