You are on page 1of 8

OTC 7328

Arun Indonesia: Big Bore Completion Tool Design


Darrell McKenna, Mobil Drilling; Richard Sukup, Mobil E&P Technical Center;
Tom Stambaugh, Otis Engineering Corp.; and R.A. Biggs, TEC-Lindsey Completion Systems

Copyright 1992, Offshore Technology Conference

This paper was presanted at the 25th Annual OTC in Houston, Texas, U. S.A., 3-6 Mey 1993

This paper wae selected for presentation by the OTC Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper,
as presented, have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(a). The material, aa presented, does not neoassarliy reflact
any position of the Offshore Technology Conference or hs officers. Permlsslon to copy Is restricted to an abstract of not more than 300 words. Illustrations may not be copied. Tha abstract
should contain conaplcuous acknowledgment of whera and by whom tha paper is presented.

ABSTRACT INTRODUCTION

All hcmgh the current gross production average of the giant The Arun gas field, located in the Aceh province (Fig. 2), is
Arun gas field in northern Sumatra exceeds 3.3 BCFD, a Indonesia’s largest gas field currently on production. Several
number of projects were initiated in 1991 to increase field options were evaluated to improve field productivity to meet
productivity, One of those projects, a monobore approach to future LNG commitments, including large bore completions.
completions, is being utilized to improve well performance on The use of large tubing strings would satisfy the projected
a series of ten 9-5/8-inch “Big Bore” completions. production needs at a lower cost per MMSCFD than the exis-
ting 7-inch tubing completions.
This is the first time a monobore completion has been uti-
lized in the Arun field and, as far as we know, these are the Productivity projection for each Big Bore well was originally
largest bore producing gas completions in the world. 120 MMSCFD. This projected production exceeded that of
the existing 7-inch tubing completion (averaging 70
Extensive tool development work, including detailed -design MMSCFD) by 71%. With the application of the monobore
reviews, FEA modeling, and prototype testing, was required concept, full field development will be achieved with fewer
to ensure that the project’s objectives of achieving opera- wells.
tional tool reliability, improved equipment performance, and
increased operational flexibility would be achieved. Although a significant opportunity, the application of the
monobore completion technology in the severe Arun field
Six “Big Bore” wells have been successfully drilled and conditions (Table 1) presented a major technical challenge.
completed without any serious operational or equipment pro- By applying several lessons learned during the initial Arun
blems. All 9-5/8-inch completions will be drilled and field development to the monobore program, significant ex-
completed by mid-year, 1993. The productivity improvements penses were saved during both equipment development and
have far exceeded the rates originally expected (Fig. 1). operations.

The concept was originally considered in early 1990 and


actual engineering design and manufacturing was initiated in
1991 after full project approval. All engineering design work,
prototype testing and manufacturing was completed in ap-
proximately 11 months. The drilling and completion of the
References and figures appear at end of paper ten planned “Big Bore” wells was begun in early January, 1992

653


2 ARUN INDONESIA - BIG BORE COMPLETION TOOL DESIGN OTC 7328

with the first 9-5/8-inch monobore well put on production in Unlike the API monogram found on various well compo-
March of that year. Drilling and completion is expected to nents, completion tool equipment is not routinely manu-
be completed by mid-year, 1993. factured to a recognized indust~ standard. In light of this
deficiency, steps were taken to ensure that confidence in all
The original projected well performance of 120 MMSCFD completion tools would remain high. For example, the op-
was far exceeded. Rates as high as 220 MMSCFD during erator either supplied all the raw material used in prototype
high rate clean-up testing have been realized. Efforts to and production tool manufacture or approved vendor raw
minimize well operational problems and provide maximum material specifications. Full quality plans were developed to
completion tool reliability have proven successful. ensure process integrity and provide complete traceability of
all components. In addition, all operations were virtually
100% third party monitored.
COMPLETION OVERVIEW

In early 1991, during the original 9-5/8-inch completion LINER TOP PACKER/PBR/SEAL ASSEMBLY
feasibility review, four separate options were considered.
These included various combinations of conventional cased- To accomplish the stated objectives of the completion, it was
hole tubing/packer and open hole tubing/packer completions. necessa~ to develop a unique permanent packer system using
The monobore option, a fifth configuration, was identified existing design technology and develop a comprehensive test-
and adopted. This includes a 9-5/8-inch tubing string in ing program to verify temperature/pressure ratings and overall
conjunction with a liner hanger, liner top packer and polish structural integrity. To optimize the design, components sub-
bore receptacle (PBR), as shown in Fig. 3. ject to extreme loads were examined using finite element an-
alysis (FEA) prior to the initiation of the testing program.
These 9-5/8-inch monobore completions are essentially FEA was used to focus attention on selected areas most criti-
tubingless completions made up of a cemented heavy wall cal to equipment performance. This technique provides an
liner coupled with a free 9-5/8-inch tieback liner. The accurate assessment of the state of stress upon and location
cemented liner and liner hanger are the foundation of the of that part or parts of the structure most likely to fail.
completion and support the thermal tubing loads during pro-
duction. In addition, the monobore option: The design of the permanent liner top packer had to be
unique as the packer would be required to withstand extreme
- provides a means to monitor the integrity of thermal compressive loads while minimizing the loads into
both the tubing/production casing annulus and the 13-3/8-inch production casing. In order to achieve this
the liner lap; requirement, a packer system was designed such that the slips
eliminates the gas turbulence areas common and molded Aflas packing element are energized during the
to conventional completions; application of a predetermined compressive force during the
- eliminates any potential liner lap problems setting sequence. The slip/element assembly is then sheared
directly into the produced fluid stream; at the intersection of the slip support and the packer mandrel
allows tubing retrieval to the liner top in the when this force is exceeded, which completely frees the ele-
event of future tubular corrosion; ment assembly from the mandrel. Doing so allows the man-
minimizes the amount of ancillary equipment. drel to travel downward and bottom out against a packer load
sub so that any subsequent loading is transmitted directly
While accomplishing a number of very key objectives, sig- from the PBR load shoulder through the packer mandrel to
nificant effort was required to design and manufacture the load sub and into the linger hanger. This design allows
completion tools to satis@ the field conditions and the the operator to compress the elements with a much higher
expected high production rates of the monobore completion, setting force than conventional packer design.
Detailed completion tool design was needed to consider not
only the severe reservoir conditions but also future projected One of the challenges presented by this design is the need to
loads, which include 17.0 ppg equivalent collapse loads from energize the slips and elements with sufficient setting force to
high pressure shale above the Arun formation, particularly provide an effective seal under temperature extremes where
after the installation of field compression, and 1,000 kip subsequent element relaxation is possible. Initial tests were
thermal expansion loads. Additionally, deformation or performed on the element package in order to determine the
damage to the 13-3/8-inch production casing could not be optimum setting force needed to maintain an effective seal
tolerated. under a temperature range of 90 to 350”F with a working

654
OTC 7328 McKENN& D.. SUKUP, R., STAMBAUGH, T., AND BIGGS. B. 3

pressure differential of 7500 psi. Once defined, these LINER HANGER TECHNOLOGY
parameters were integrated into the design of the packer.
A specially designed liner hanger system was engineered,
The original packer design utilized only one set of upper slips performance tested, and installed as part of the monobore
to resist differential pressure applied from below. However, completion tool package. Since the heavy wall 10-inch liner
to trap the required setting force in the packing element so is required to withstand the Arun pore pressure (Fig 4),
that an effective seal will be maintained throughout the entire comparable performance of the hanger system was necessary
anticipated operating range, a lower set of slips was added. to control safely the projected productivity of the Arun
This effectively prevents element relaxation. monobore completions at elevated temperature.

It was determined that a large slack-off weight was needed in The liner hanger system was first analyzed using engineering
order to provide for the initial compressive setting force to mechanics principles. Each component of the system was
the slips and the elements. Subsequently, setting procedures evaluated under anticipated load conditions to simulate Arun
were developed that allowed the packer to be set mechani- field production conditions. Comprehensive studies of com-
cally, hydraulically, or in combination to allow flexibility for ponents in worst case scenarios of maximum load at mini-
specific well conditions and rig limitations. The final design mum material condition were undertaken. Further, the effect
was submitted for full-scale testing for verification of opera- of manufacturing tolerances on system fit, form, and function
tional limitations under actual downhole conditions in a deep (particularly during thermal expansion and loading) were ex-
well simulator. amined. Each component was compared to the performance
level and design safety factors of the 10-inch heavy wall
The design of the bottom locating production seal assembly parent liner. Marginal conditions existed dictating that FEA
and PBR provides a system that will withstand both the anti- modeling was again required.
cipated well conditions and the potentially high thermal com-
pressive loads. In addition, all internal upsets were removed A number of critical components of the liner hanger system
to eliminate the potential for erosional corrosion. The sys- under consideration for the Arun Project were analyzed using
tem also satisfies the need to maintain a smooth continuous the FEA method. These components were assumed to be
bore throughout which is characteristic of monobore comple- perfectly elastic (linear) over the range of applied loads or
tions, thus eliminating flow turbulence in the production deflections simulative of Arun field conditions. No plastic
tubing. deformation, creep, large deflection, or transient conditions
were accounted for in the analysis.
Another important consideration in this design is that con-
tingency completion plans were developed which utilize the The main areas of concern included the liner hanger top load
monobore completion-tools. If necessaty, the production seal shoulder, which supports the uncemented 9-5/8-inch tubing,
assembly may be used to seal directly the liner tieback seal and the hanger body slips. Detailed FEA modeling was per-
area, instead of the packer and PBR. In addition, the anti- formed on these components, which resulted in two major
cipated service of the PBR and production seal assembly is design modifications.
static. However, design considerations focused on worst-case,
dynamic sealing conditions to ensure reliability during cold The 45” top load shoulder was shown to be overstressed when
stimulation or well-kill operations. The test performed to subjected to the full anticipated induced load. Flattening the
veri~ seal integrity involved stabbing the seal stack into the shoulder to 0° and removing both the inside and outside
PBR and stroking it under pressure to approximately 1200 bevels increased its load bearing capacity. Thus, the over-
linear feet of travel. The same seal components were sub- stressed condition was eliminated.
jected to an additional stroke test of 1200 feet in the seal
bore without pressure to determine the wear characteristics The results of the FEA modeling on the liner hanger body in-
of the components. All tests were performed with full-scale dicated that the hanger’s slip system stress levels exceeded
prototype equipment under anticipated well conditions. The material strength. Therefore, slip geometry was changed,
sealing system, made up of Chetnraz, Teflon, and PEEK chev- Slips were increased in number from four (with 90° radial
ron vee packing in various combinations, ensured pressure spacing) to six (60° radial spacing) and in length from 13-1/2-
integrity across the broad temperature range. inch to 18-inch. With these slip design changes, the incre-
mental induced loads are transmitted axially into the
production casing at areas of slip engagement at levels suf-
ficiently below the yield point of the production casing.

655


4 ARUN INDONESIA - BIG BORE COMPLETION TOOL DESIGN OTC 7328

The revised design was full-scale prototype tested in a hy- running procedures and bottomhole assembly as the pro-
draulic load frame with detailed strain gauge data gathered. duction PBR/packer assembly. Once the drift tool lands on
Strain gauge data was reviewed with three main objectives: the liner, subsequent slack-off weight shears the load sub
1) determine the distribution of load among the slips; 2) mechanism, giving a clear indication if the tool had preset.
determine the stress levels in the liner hanger body and sur- In addition, the lower seal assembly of the drift tool allows
rounding casing and 3) determine the sequence of failure in testing of the liner tieback seal bore for any damage as a
the system. Under an induced load of 1,145 kips the casing result of milling operations prior to running the permanent
performed as designed without failure, even after plastic de- liner top packer.
formation of the slip splines. Visual inspection after the
test’s completion showed uniform radial casing expansion. A hydrostatic test tool was designed to test the retrievable
Both casing deformation and slip wicker yielding were within cement bushing to 5,000 psi in the field. In this way, the
acceptable levels. operator confirmed that cement would not by-pass back into
the liner hanger ID, thus jeopardizing the integrity of the
Additional full-scale performance verification testing included liner and liner top cement job that is critical to load support
tests of the tieback receptacle, landing collar, liner wiper and lap pressure integrity.
plug, float collar and shoe, and running tool. A number of
component redesigns were necessary to meet project require-
ments. SECURING ZONE - RETRIEVABLE BRIDGE PLUGS

When considering a monobore completion, one of the most


FIELD INSTALLATION - SPECIALIZED TOOLS difficult challenges is determining how to secure the zone
upon completion of the drilling phase. This problem was
A unique liner hanger running tool is used to set the system overcome in Arun by designing, prototype testing, and manu-
hydraulically. This ensures proper placement and full slip facturing a large bore retrievable bridge plug.
casing engagement, which optimizes load transfer into the
production casing. The 9-5/8-inch retrievable plugs are wireline run and re-
trieved by coiled tubing or drill pipe. This provides a cost
Once cementing was completed, specially developed milling effective plug recovery alternative to moving a rig back on
tools were employed for the clean-up operation. A brass- location for retrieval.
faced impression locator shoulder was incorporated into the
tools to verify the location and condition of the hanger load All wetted surfaces of the newly designed plug were machined
shoulder in preparation for locating the isolation packer seal from high nickel alloy steel, again to satisfy the harsh Arun
assembly for the 9-5/8-inch tubing tieback. Because of the service conditions. The plug provides an effective means of
need to support high expected thermal loads, it was critical securing the Arun formation during both the drilling phase
that the liner hanger load shoulder condition be verified prior and future production operations.
to running the packer.
A mixed elastomeric system (HSN and Atlas) was utilized on
A standard 13-3/8-inch casing scraper was modified to incor- the packing element to satisfy the temperature range of 90 to
porate a locator to position the scraper on the liner top 350”F. The packing elements were FEA modeled utilizing a
within the distance required by the isolation packer’s elas- non-linear technique to predict elastomeric performance.
tomer packing elements. This ensured proper casing condi- Upon completion of the modeling process, full-scale pro-
tioning and packer differential sealing integrity. totype testing was completed at minimum material conditions.
A 9-5/8-inch casing test fiiture was machined to minimum
A packer drift tool was designed to the same dimensions as API tolerance (maximum ID), while the plug was machined
the PBR and liner top packer assembly and contained a to minimum OD dimensions for the qualification testing. As
shear-pinned load sub mechanism and lower seal stack in the with the isolation packer, a lower set of slips was added to
same spacing arrangement as that of the assembled packer prevent element relaxation, thus enabling the plug to be
and PBR. This piece of equipment gauges the casing prior to qualified for service in all Arun pressure and temperature
the running of the packer and, by means of the load sub environments. Repeated pressure cycles through the tem-
shear mechanism, give a clear indication of any casing debris, perature range confirmed the structural and pressure integrity
constriction, or other adverse condition(s) which might ini- of the plugs. In addition, full-scale plugs were set in shallow
tiate presetting of the packer. The drift tool was designed to test wells to veri$ running and retrievability of the plugs.
drift the casing down to the liner tieback, using the same

656
OTC 7328 McKENN~ D., SUKUP, R., STAMBAUGH. T., AND BIGGS, B. 5

In these monobore completions, two plug barriers are rou- We gratefully acknowledge permission of the management of
tinely utilized to secure the well. To mitigate against any Mobil Drilling, Mobil Exploration and Producing Technical
velocity-induced erosion and production corrosion problems Center, OTIS Engineering Corporation, Technology Export
caused by slip marks in the tubing string, three ten-inch OD Company - Lindsey Completion Systems to publish this
heavy wall landing joints a~e strategically located throughout paper.
the completion; one below the liner hanger to allow workover
operations, one above the seal assembly, and one at 3,000 The attention to detail and integrity of all the members of
feet. the “Big Bore”project team, including vendor staff and con-
tract consulting personnel, resulted in a total team success.

CONCLUSIONS
REFERENCES
1. Testing programs utilized during the design and pro-
totype testing successfully demonstrated the structural 1. Aladyrus, M. U. and Bordelon, T. P.: “Boosting De-
integrity and service rating of all completion com- liverability in the Giant Arun Gas Field”, paper SPE
ponents. Suitability for service of all components 22997, presented at the 1991 SPE Asia-Pacific Con-
utilized in this completion design with respect to tem- ference, Perth, Australia, Nov.
perature, pressure, flow rates and gas composition
have been clearly demonstrated. 2. Cannan, W. L., Calvert, D. G., Ellison, P. C.,
McKenna, D. L,, Quitzau, R., Sandjano, S., and
2. Full-scale testing and detailed design work provided Sukup, R. A.: “Big Bore Well Completions - A New
an effective means of defining operational procedures Completion Technique for the Arun Field,” paper
for installation of the large monobore completion SPE 25384, presented at the 1992 SPE Asia-Pacific
equipment. Conference, Singapore, Feb. 8-10.

3. Emergency fallback positions were developed for all 3. Simonds, F. R., Cannan, W. L., and McKenna, D. L.:
tools during the development phase. Compatibility of Management Summary Technical Report, Mobil Ex-
all components was accomplished by maintaining con- ploration and Production Technical Center, “9-5/8-
sistent machining dimensions and tolerances. inch Arun Completions: The Big Bore Project”,
January 1993. -
4. Strategic vendor alliances developed during the de-
sign, prototype testing, performance verifi~tion and
manufacturing were key to meeting the projected time FIGURES
restraints. Only nine months elapsed between the
project approval and shipment of ‘the first series of Fig. 1- High rate clean-up test flow rates
completion tools.

ACKNOWLEDGEMENTS

Aflas is a registered trademark of the Asahi Glass Co. Ltd.


for Propylene Tetrafluoroethylene Copolymer.

Chemraz is a registered trademark of Greene, ‘llveed, & Co., 7“ Tubing

Inc. for Perfluoro Elastomer.

Teflon is a registered trademark of Dupont Co. for Poly- 1000 1


I I 1 I I I I I I I T I I I I I 1 I I I I t
tetrafluoroethylene. o 20 40 60 80 100 120 140 160 180 200 220
Flow Rate (MMSCFD)

PEEK is a registered trademark of ICI Americas, Inc. for


Poly-Ether-Ether-Ketone,

657
6 ARUN INDONESIA - BIG BORE COMPLETION TOOL DESIGN OTS 7328

Fig. 2- Arun field map

N
o MALACCA STRAIT

.\w *MWA

“:%.*Q.
‘ ‘-”
DON

JAVA
BCRNEO

SIA

P~

1& RESIOW GAS


35’
42- GAS

Z&

1~
CONDENSATE

NGL
xi “ POINT “A”
13 LHOK SUKON LANDING

‘* *
*$ I NOTES :
~ . GAS INJECTION WlL5.
\

u
ARUN GAS RESERVOIR
o mn
o

Table 1: Arun field conditions as of January, 1993

Average reservoir pressure 3,000 psig

Static reservoir temperature 350”F

C02 content 12- 16%

H2S content 40-60 ppm

Water production 10 bbl/MMSCFD

Average ‘7”completion moduction 65 MMSCFD at 1.750 FT’HP

II Average depth
1’
I
1
10,400’ TvD II
1]

I 658

——

OTC 7328 McKENNAy D., SUKUP, R., STAMBAUGH, T., AND BIGGS, E. 7

~g. 3- Monobore well schematic with detail of completion took

-98”
TubingHanger

20’ 133PPF,
K-55ButtCasii

9-98’,53,5PPF,L-M),
5Fii
.
.F--
:::
:::
...
.J.
: M
:
;

PremiumTubing :
PBRandTubirq
13-3/8’,72 PPF, :
L-W,Premium :.. w Assy.
*
Casing .
IN [.
.
LinerTop
IsolationPac&
TBRand Tieback

-3!
. LinerHangef
seal Assy. . !
.
Crossover :.$ & .. +75CrCr
Ft
9-Y8’x 10’
T$$f;
10’,72PPF,L-8(I
PremiumTubing ...... -*9750[
8-112”
@en Hole
*
All DepthsAreFromTheKellyBushing.

. >

PBR with seal


running tool lwacutbry
instatlcd

---4 Liner top


Liner hanger packer
and TBR llcback
seals
659

——— —

— ——— —
~_— —— ._—_ ___ .—.

.__——:.
_. .—. . _....—..
_.——.
_. -.
_.___ . ..-==* -..+:~<=-.. J: .—., ~=. ._—
~- _ ~_=A.:T_=—~ .=.. -.=. ,_=—. . ._— , .= . ._ . - -.
——
.— —

.==. ..—: .=. -

.
,__—..=. L ,= .— = .— ,—_ ,—
-—

— -————— =__—=__— = -—.-—- — —— ——. —=-—.


——

~_= ..:—.. _— .——=—. .—
= — ————-———. —— -—.=— _. —

— - =.=.-——, ———. . -- —- ——-. -=— ——=—=-—

—=. -__—_=_
s ARUN INDONESIA - BIG BORE COMPLETION TOOL DESIGN OTS 7328

Fig. 4- Arun CI-19 pore pressure plot

Casirrg
True Vertical Depth, Ft. - KB

r
Depth,Ft-KB
o
Icncr

20’CSG
201XI @ 1600’KB
LOT= 13.5PPG

400

6000

7(XHI
- @ 7282’ TVD
8000 LOT = 17.5 PPG
Pore Pressure ~ 13-3/8” CSG

<-l 9-5/8” CSG


1000O I @ 9553’ TVD
i 8.5” Hole
11OOO ‘1 I I I 1
1’ I 1
I I I 1
I I I I 1 1 1 1 I I 1 1
TD 10,057’ TVD
7.0 9.0 11.0 13.0 15.0 17.0 19.0
Pressure,Equivppg

660

——— —

— ————
~_— —— ._—_ ___ .—.

.-_——:.
_. .—. . _....—..
_.——.
_. -.
_.___ . ..-==* -..+:~<=~.. J: .—., ~=. ._—
~- _ ~_=A.:T_=—~ .=.. -.=. ,_=—.. ._—
,.= . ._ . - -. ——
.——

.==. ..—:
.=.-
,__—..=.
L,=.— = .—,—_,— .
-— — -—————
— =__—=__—= -—.-—-
———
——.
—=-—.

— ——
~_=
..:—.._—.——=—.
.— = —————-———.
—— -—.=—
_. —
— - =.=.-——,
———.
. -- —-
——-.
-=———=—=-— —
—=.

You might also like