HYDRONIC SYSTEM CHECKLIST

System / Package No. Testpack No.

P&ID/Dwg No. Room No.

Equipment Name / Tag No.

NOTE: If a section is NOT relevant enter N/A


Item Yes No N/A
1. Are the correct bolts and gaskets installed at all joints?
2. Have all the hydrotest vents and drains been sealed?
3. Have all testing spades been removed?
4. Have all system T Handle spades been left in place?
5. Have control valves been installed in correct “Flow” position?
6. Have specified block valves locking devices been correctly installed?
7. Are all valves functioning properly and have spindles been lubricated?
8. Have all extended spindles required for specified valves been installed?
9. Have relief valves been correctly installed?
10. Have restriction and orifice plates been correctly installed?
11. Have thermowells been correctly installed?
12. Have all pump suction strainers been correctly installed?
13. Is flow direction through filters and strainers, traps, check valves and globe
valves correct?
14. Have all gags been removed from spring loaded pipe supports and expansion
bellows?
15. Are all supports, valves handles, gaskets and handles complete?
16. Is in-line equipment tagged?
17. Has this Testpack been reinstated after testing?
18. Are the piping pressure records complete?
FOR ITEMS MARKED ‘NO’, RAISE PUNCHLIST
Comments: (If there are NO ADDITIONAL remarks enter NONE, initial and date)
Reason to be written in comments section and, where applicable, raised as an exception or outstanding issue as part
of the system handover. If resolved prior to handover comments to be marked appropriately and signed of
accordingly.

Completed by Witnessed by Approved by Accepted by


Company
Signature
Print Name
Date

XXXXX 3 CON 8749 REC 13 –Hydronic System Checklist


Prepared By: Amalina Kamal Revision Date: 16-Mar-2020 Page 1 of 1
Create Date: 22-Dec-2011 Revision: 2