Professional Documents
Culture Documents
Installation Guide
Issue 05
Date 2022-03-04
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees
or representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Website: https://e.huawei.com
Purpose
This document describes how to install the STS-3000K-H1 and STS-6000K-H1
smart transformer stations (STSs). Before installing the STSs, read through this
document to understand the safety precautions and get familiar with the
functions and features of the STSs.
Intended Audience
This document is intended for photovoltaic (PV) plant operators and qualified
electricians.
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol Remarks
Symbol Remarks
Change History
Changes between document issues are cumulative. The latest document issue
contains all the changes made in earlier issues.
Issue 05 (2022-03-04)
Updated 1 Safety Information
Updated 2.1 Appearance.
Updated 2.2.2 LV Room.
Updated 3.1 Site Requirements.
Updated 3.3 Hoisting Equipment.
Updated 3.5 Securing a Container.
Updated 5.1 Opening or Closing a Cabinet Door.
Updated 5.2 Interlocking Between STSs.
Updated 7.1 Preparing Cables.
Updated 7.2 Connecting a PE Cable for the STS.
Updated 7.5 Installing the AC Output Power Cable.
Updated 7.7 (Optional) Connecting Cables to the UPS.
Deleted Requirements for the Foundation Dimensions.
Issue 04 (2021-09-13)
Deleted Installing a Lightning Arrester for the Ring Main Unit.
Issue 03 (2021-08-10)
Updated 2.2 Components.
Updated 7.6 Connecting Cables to an SACU.
Issue 02 (2020-10-30)
Updated 2.1 Appearance.
Issue 01 (2019-11-15)
This issue is used for first office application (FOA).
Contents
2 Product Overview.................................................................................................................. 13
2.1 Appearance............................................................................................................................................................................. 14
2.2 Components............................................................................................................................................................................ 16
2.2.1 Transformer Station.......................................................................................................................................................... 16
2.2.1.1 STS-3000K-H1................................................................................................................................................................. 16
2.2.1.2 STS-6000K-H1................................................................................................................................................................. 17
2.2.2 LV Room................................................................................................................................................................................17
2.2.2.1 STS-3000K-H1 Single-sided Cabinet........................................................................................................................ 17
2.2.2.2 STS-3000K-H1 Double-sided Cabinet......................................................................................................................19
2.2.2.3 STS-6000K-H1 Single-sided Cabinet........................................................................................................................ 19
2.2.2.4 STS-6000K-H1 Double-sided Cabinet......................................................................................................................21
2.2.3 Transformer Room............................................................................................................................................................ 21
2.2.3.1 STS-3000K-H1................................................................................................................................................................. 21
2.2.3.2 STS-6000K-H1................................................................................................................................................................. 23
2.2.4 MV Room............................................................................................................................................................................. 25
2.2.4.1 DQS-24 (CVC)................................................................................................................................................................. 25
2.2.4.2 CGM.3 (DVC)................................................................................................................................................................... 26
2.2.4.3 DQS-40.5 (DVC)............................................................................................................................................................. 27
2.2.4.4 8DJH24 (CCV)..................................................................................................................................................................28
3 Equipment Installation........................................................................................................ 30
3.1 Site Requirements................................................................................................................................................................. 30
3.2 Preparing Tools...................................................................................................................................................................... 32
1 Safety Information
General Requirements
DANGER
WARNING
CAUTION
● Do not install other devices on the top of the equipment without the
permission of the Company.
● Do not perform operations such as arc welding, drilling, or cutting on the
equipment. Such operations may damage the container airtightness, equipment
electromagnetic containment, internal components, and cables. Metal scraps
generated during such operations may enter the equipment, which will cause
short circuits on circuit boards, affect equipment functions, or damage the
equipment.
● Do not touch any area where a burn warning sign is attached to prevent burn
hazard.
● Repaint any scratched surfaces caused during equipment transportation or
installation in a timely manner. Scratched equipment surface should not be
exposed to an outdoor environment for extended periods.
● The keys to the door locks of the medium-voltage room, low-voltage room, and
transformer room must be properly kept. Unauthorized personnel are not
allowed to work on the equipment.
● After installing the equipment, clear away packing materials such as cartons,
foam, plastics, and cable ties from the equipment area.
● When performing operations (such as hoisting) over the top of the equipment,
take measures to protect the equipment against damage. After the operations
are complete, check whether the protective paint is damaged. If yes, repair the
paint in a timely manner.
● If there is a likelihood of personal injury or equipment damage during
operations, immediately stop the operation, report the case to the supervisor,
and take feasible protective measures.
● The equipment has an arc discharge channel for the medium-voltage room.
Install the equipment according to the equipment foundation diagram and
ensure that the gap between the medium-voltage room and the foundation is
filled with materials such as mortar.
● During the operation and maintenance of the equipment, if you need to leave
temporarily, close and lock the cabinet doors.
NOTICE
NOTE
● Class C environment: Outdoor areas more than 500 m away from the sea. If a site
is near a pollution source, it must be 1500–3000 m away from heavy pollution
sources, such as smelteries, coal mines, and thermal power plants; 1000–2000 m
away from medium pollution sources such as chemicals, rubber, and galvanization;
or 500–1000 m away from light pollution sources, such as packing houses,
tanneries, boiler rooms, slaughterhouses, landfill sites, and sewage treatment
plants.
● Class D environment: Sea environments or outdoor areas within 500 m away from
the sea. If a site is near a pollution source, it is within 1500 m away from heavy
pollution sources such as smelteries, coal mines, and thermal power plants, within
1000 m away from medium pollution sources such as chemical, rubber, and
galvanization industries, or within 500 m away from light pollution sources such as
packing houses, tanneries, boiler rooms, slaughterhouses, landfill sites, and sewage
treatment plants.
● Class E environment: Special environments, such as underground or underwater
environments.
Grounding
● Do not damage the ground conductor.
● Do not work on the equipment in the absence of a properly installed ground
conductor.
● For the equipment that needs to be grounded, install the ground cable first
when installing the equipment and remove the ground cable last when
removing the equipment.
● The main grounding body of the equipment must be permanently connected
to the grounding grid. Before working on the equipment, check its electrical
connections to ensure that it is reliably grounded.
NOTICE
Using Ladders
● Before using a ladder, ensure that it is intact and its load bearing capacity is
adequate. Do not load a ladder with a weight in excess of its duty rating.
● Use wooden or fiberglass ladders when you need to perform live-line working
at heights.
● Platform ladders with protective rails are preferred. The ladder must be
secured at the four feet and held by a person.
● When a step ladder is used, ensure that the pull ropes are secured and the
ladder is held firm by a person.
● If a straight ladder is used, the ladder must be placed in a secure place. The
recommended angle for a ladder against the floor is 75 degrees, as shown in
the following figure. An angle ruler can be used to measure the angle. Ensure
that the wider end of the ladder is at the bottom, or protective measures have
been taken at the bottom to prevent the ladder from sliding. The ladder must
be held by another person during the operation.
● When climbing a ladder, take the following precautions to reduce risks and
ensure safety:
– Keep your body steady.
– Do not climb higher than the fourth rung of the ladder from the top.
– Keep your center of gravity between the side rails, and do not overreach
to the sides.
● Wear protective gloves and anti-smashing shoes when manually moving the
equipment.
● Do not scratch the equipment surface or damage components or cables when
moving the equipment.
● When transporting the equipment using a forklift truck, ensure that the forks
are properly positioned so that the equipment does not topple. Before moving
the equipment, secure it to the forklift truck using ropes. When moving the
equipment, assign dedicated personnel to take care of it.
● Move the equipment with caution to prevent collision or fall.
1.7 Commissioning
After the equipment is powered on for the first time, ensure that the parameters
are set correctly by professional personnel. Incorrect parameter settings may result
in noncompliance with local grid connection requirements and affect the normal
operations of the equipment.
CAUTION
Before removing a component from the cabinet, ensure that other components on
the cabinet are secure.
NOTICE
● After the equipment stops running, wait for at least 10 minutes to ensure that
the voltage is in the safe range. Before maintenance or repair, ensure that the
transfer switch is turned to the ground position, the potential indicator is off,
the grounding switch of cabinet V in the ring main unit is turned on, and the
low-voltage cabinet is grounded.
● During maintenance, turn off the air circuit breaker on the low-voltage side
and the switch on the high-voltage side of the equipment, and place warning
signs indicating that the switches must not be turned on. If the equipment
supports the automatic mode, disable the automatic mode to ensure that the
equipment will not be powered on unexpectedly.
● Before maintaining the equipment, ensure that the switches on the low-
voltage and high-voltage sides of the equipment are turned off, and the
grounding switch of the circuit breaker cabinet on the medium-voltage side is
turned on.
● If a switch needs to be turned off for maintenance, place a warning sign
indicating that the switch must not be turned on.
2 Product Overview
2.1 Appearance
Figure 2-1 Appearance
(1) Low-voltage room (LV) (2) Transformer room (TR) (3) Medium-voltage room
(MV)
(4) Position for the distributed (5) Position for the smart array (6) Double-swing door of the
power system (uninterruptible controller (SACU) MV room
power supply, UPS)
(7) Ring main unit (8) Auxiliary transformer (9) Double-swing screen door
for the transformer room
(10) AC input cable hole (LV (11) Manhole entrance (12) AC input cable hole (LV
PANEL B) PANEL A)
(13) Single-swing door for the (14) Double-swing door for the
LV room LV room
NOTE
2.2 Components
2.2.1.1 STS-3000K-H1
(4) Transformer (5) Ring main unit (6) Power distribution box
2.2.1.2 STS-6000K-H1
2.2.2 LV Room
This section shows only the components. The actual product appearance may vary.
(1) Multimeter (2) Measurement and control (3) Temperature and humidity
(MULTIFUNCTION METER) device (STS MONITORING controller (TEMPERATURE
DEVICE) AND HUMIDITY CONTROLLER)
(4) Off button (PUSH TO (5) On button (PUSH TO (6) Changeover switch
OPEN ACB) CLOSE ACB) (REMOTE/LOCAL SWITCH)
(1) Multimeter (2) Measurement and control (3) Temperature and humidity
(MULTIFUNCTION METER) device (STS MONITORING controller (TEMPERATURE
DEVICE) AND HUMIDITY CONTROLLER)
(4) Off button (PUSH TO (5) On button (PUSH TO (6) Changeover switch
OPEN ACB) CLOSE ACB) (REMOTE/LOCAL SWITCH)
(1) Multimeter (2) Measurement and control (3) Temperature and humidity
(MULTIFUNCTION METER) device (STS MONITORING controller (TEMPERATURE
DEVICE) AND HUMIDITY CONTROLLER)
(4) Off button (PUSH TO (5) On button (PUSH TO (6) Changeover switch
OPEN ACB) CLOSE ACB) (REMOTE/LOCAL SWITCH)
(1) Multimeter (2) Measurement and control (3) Temperature and humidity
(MULTIFUNCTION METER) device (STS MONITORING controller (TEMPERATURE
DEVICE) AND HUMIDITY CONTROLLER)
(4) Off button (PUSH TO (5) On button (PUSH TO (6) Changeover switch
OPEN ACB) CLOSE ACB) (REMOTE/LOCAL SWITCH)
2.2.3.1 STS-3000K-H1
The transformer room converts the LV AC power into the MV AC power. The main
equipment is a transformer configured with gas, oil temperature, pressure, and oil
level protection. At the same time, a comprehensive protection device is
configured in the MV room for the transformer.
This document uses the appearance of a transformer as an example. The
appearance of transformers of different models may be different. The actual
product may vary.
2 Oil surface Measures and Displays the top layer of transformer oil in
thermometer controls the real time and issues alarms and trip signals
temperature of the through the built-in temperature control
top layer of switch.
transformer oil.
3 Off-load tap Regulates the There are five levels. Level 1 indicates the
changer voltage. maximum tapping value, level 3 indicates the
rated tapping value, and level 5 indicates the
minimum tapping value.
4 Oil refilling/ Transformer oil ● Oil refilling: Refills the transformer oil
draining valve refilling/draining using an uncontaminated metal or non-
valve rubber hose and oil injection equipment.
(Note: Prevent air from entering.)
● Oil draining: The cabinet oil is led to the
oil container through an uncontaminated
metal or non-rubber hose.
5 Oil level gauge Indicates the oil Indicates the oil level of the transformer oil
level. cabinet and reports the alarms of high and
low oil levels.
2.2.3.2 STS-6000K-H1
The transformer room converts the LV AC power into the MV AC power. The main
equipment is a transformer configured with gas, oil temperature, pressure, and oil
level protection. At the same time, a comprehensive protection device is
configured in the MV room for the transformer.
This document uses the appearance of a transformer as an example. The
appearance of transformers of different models may be different. The actual
product may vary.
2 Oil refilling/ Transformer oil ● Oil refilling: Refills the transformer oil
draining valve refilling/draining using an uncontaminated metal or non-
valve rubber hose and oil injection equipment.
(Note: Prevent air from entering.)
● Oil draining: The cabinet oil is led to the
oil container through an
uncontaminated metal or non-rubber
hose.
4 Off-load tap Regulates the There are five levels. Level 1 indicates the
changer voltage. maximum tapping value, level 3 indicates
the rated tapping value, and level 5
indicates the minimum tapping value.
5 Oil surface Measures and Displays the top layer of transformer oil in
thermometer controls the real time and issues alarms and trip signals
temperature of the through the built-in temperature control
top layer of switch.
transformer oil.
6 Oil level gauge Indicates the oil level. Indicates the oil level of the transformer oil
cabinet and reports the alarms of high and
low oil levels.
2.2.4 MV Room
For details about the ring main unit, see the ring main unit manual provided by
the manufacturer. See the ring main unit model on the nameplate.
No cable connector is installed in cabinet G1 or G3. The cable connectors in the figure are
for reference only. The actual position and dimensions may vary.
(1) Operation holes of (2) Load switch operation (3) Isolation switch operation
grounding switches holes hole
No cable connector is installed in cabinet G1 or G3. The cable connectors in the figure are
for reference only. The actual position and dimensions may vary.
(1) Load switch operation (2) Grounding switch operation (3) Cable connectors
holes holes
No cable connector is installed in cabinet G1 or G3. The cable connectors in the figure are
for reference only. The actual position and dimensions may vary.
(1) Operation holes of (2) Load switch operation (3) Isolation switch operation
grounding switches holes hole
● The CCV ring main unit includes a circuit breaker cabinet and two load switch cabinets.
● The secondary room of the ring main unit cannot be opened when the power is on.
(4) Manually switching off the (5) Manually switching on the (6) Relay
circuit breaker circuit breaker
3 Equipment Installation
NOTE
Check Items
No. Check Item Acceptance Criteria
Tool
Measuring tape Bubble or digital level Hydraulic pliers Heat shrink tubing
Step ladder
Safety Tools
Tool
N/A
Reflective vest
NOTE
NOTICE
● Before hoisting, ensure that the crane and hoisting ropes meet the load-bearing
requirements.
● When installing or removing the hoisting equipment, do not drag it on the
container to prevent scratches.
● Before installing the equipment, check the container for damage, such as holes
and cracks, and check the equipment model. If the appearance is abnormal or
the equipment model is incorrect, contact your dealer.
● Remove the crane after leveling the container as described in Step 6.
Hoisting Precautions
Stage Precautions
Before hoisting Ensure that the crane can hoist a load heavier than 50 t,
and the working radius is not less than 10 m. If the onsite
environment does not meet the required working
conditions, ask a professional to assess the conditions.
Ensure that the crane and steel hoisting ropes provide the
required bearing capacity.
Stage Precautions
Ensure that the angle between every two ropes is less than
or equal to 90 degrees.
Procedure
Step 1 Determine the installation position of the container based on the foundation
design drawings.
Step 2 Measure the support points for the container on the foundation. Ensure that the
support points are on the same plane and the deviation is no more than 5 mm.
Step 3 Hoist the container to the installation position using a crane.
NOTICE
● If it is difficult to open or close the container door, take out metal washers from
the fittings and place them under the container support feet. You can adjust
the container door for multiple times until it can be opened and closed
smoothly.
● For details about how to open and close a container door, see 5.1 Opening or
Closing a Cabinet Door.
----End
NOTE
● There are four mounting holes where angle steel brackets contact the base. Mark all
mounting holes. Each angle steel bracket must be secured by two mounting holes.
Preferentially drill the outer two mounting holes. If steel bars in a concrete base block
the drill bit, drill the inner mounting holes.
● Ensure that the expansion bolts are tightened when securing the angle steel to the base.
----End
4 Switch mechanical 1. Turn on and off the ACB in the LV cabinet for
operation test two times. The operation is successful.
2. Turn on and off all MCCBs in the LV cabinet for
two times. The operation is successful.
3. Turn on and off the load switch, circuit breaker,
and grounding switch in the ring main unit in
sequence for two times. The operation is
successful.
4. Operate the interlocking system of the STS for
two times. The operation is successful.
6 Oil level gauge The oil level displayed on the gauge in the
transformer oil cabinet is normal.
5 Operating Components
NOTICE
----End
Screen Door
Step 1 Open the screen door.
----End
Step 1 Mechanical lock K1 is configured at the operation hole of the cable room door of
cabinet G1. After the K1 key is inserted, you can open the door. You can remove
the K1 key only after the door is closed.
Step 2 Mechanical lock (not a padlock) K2 is configured at the operation hole of the
grounding switch in cabinet G3. After the K2 key is inserted, you can turn on or off
the grounding switch. You can remove the K2 key only after the grounding switch
is turned on.
Step 3 Based on the hand-in-hand connection diagram of the STSs obtained from the
customer, put the K2 key of cabinet G3 in STS 1 and the K1 key of cabinet G1 in
STS 2 on the same key ring. Mark the STS and switch numbers on the labels. The
operations for STS 2 and STS 3 are similar. Turn on the grounding switch of
cabinet G3 in the last STS. Remove the K2 key and hand it over to the O&M
personnel.
Step 4 For the first STS closest to the booster station, the key to the cable room door of
cabinet G1 needs to be interlocked with the outgoing cable knife switch of the
booster station. The interlocking logic is the same as that of STSs.
Step 5 If the grounding switch does not have the interlocking function, close the cable
room door of cabinet G1 and remove the key. Then hand the key over to the O&M
personnel for proper storage. According to the requirements, interlock the
grounding switch of the booster station with the cable room door of cabinet G1 of
the first STS to ensure operation safety.
Figure 5-5 Interlocking between STSs with a DVC ring main unit
----End
Step 1 Mechanical lock K1 is configured for the grounding switch of cabinet G1. After the
K1 key is inserted, you can turn on the grounding switch and open the door of the
cable room. You can remove the K1 key only after the door of the cable room is
closed and the grounding switch is turned off.
Step 2 Mechanical lock (not a padlock) K2 is configured at the operation hole of the
grounding switch in cabinet G3. After the K2 key is inserted, you can turn on or off
the grounding switch. You can remove the K2 key only after the grounding switch
is turned on.
Step 3 Based on the hand-in-hand connection diagram of the STSs obtained from the
customer, put the K2 key of cabinet G3 in STS 1 and the K1 key of cabinet G1 in
STS 2 on the same key ring. Mark the STS and switch numbers on the labels. The
operations for STS 2 and STS 3 are similar. Turn on the grounding switch of
cabinet G3 in the last STS. Remove the K2 key and hand it over to the O&M
personnel.
Step 4 For the first STS closest to the booster station, the interlock key K1 to the
grounding switch of cabinet G1 needs to be interlocked with the outgoing cable
knife switch of the booster station. The interlocking logic is the same as that of
STSs.
Step 5 If the grounding switch does not have the interlocking function, turn off the
grounding switch of cabinet G1 and remove the interlock key K1. Then hand the
key over to the O&M personnel for proper storage. According to the requirements,
interlock the grounding switch of the booster station with that of cabinet G1 of
the first STS to ensure operation safety.
Figure 5-6 Interlocking between STSs with a CVC ring main unit (1)
Figure 5-7 Interlocking between STSs with a CCV ring main unit (2)
----End
----End
Step 2 Install the rainproof canopy delivered with the STS on the pressure release valve.
Figure 5-9 Installing the rainproof canopy for the pressure release valve
----End
(1) Position of the dehydrating breather for (2) Position of the dehydrating breather for
STS-3000K-H1 STS-6000K-H1
Procedure
Step 1 Remove the flange cover from the position to install the dehydrating breather.
NOTICE
There is a sealing washer between the flange cover and dehydrating breather.
When tightening the bolt, ensure that the sealing washer is 1/4 compressed in
height.
----End
Step 3 Rotate the cover clockwise to reinstall the glass cover. Ensure that the white
pointer is on the left and the red pointer is on the right.
Step 4 Rotate the knob to put the red and white pointers together.
----End
The STS insulation tests cover the transformer MV side, ring main unit,
transformer LV side, bus on the LV side, and auxiliary loop. For details, see the
STS-(3000K, 6000K)-H1 Smart Transformer Station User Manual.
NOTE
Perform the insulation tests before connecting incoming cables and sealing cable holes.
7 Connecting Cables
Precautions
DANGER
Before connecting cables, ensure that the upstream and downstream switches of
the STS are turned off, and that the STS is not energized. Otherwise, the high
voltage of the STS may result in electric shocks.
WARNING
NOTE
The cable colors shown in the electrical connection diagrams provided in this chapter are
for reference only. Select cables in accordance with local cable specifications (green-and-
yellow cables are only used for protective earthing).
Wiring Requirements
● Cables should be arranged neatly and the cable insulation layer should be
intact.
● The cable connectors prepared onsite must be secure, reliable, neat, and
comply with relevant regulations.
● Power cables, ground cables, and signal cables should be securely and reliably
connected in conformity with wiring regulations.
NOTICE
Figure 7-1 Cable connections (configure the components in the dotted box as
required)
(A) Side view of the STS LV (B) Front view of the STS (C) Side view of the STS MV
cabinet room
(G) Smart array controller (H) Support tracking system (I) Power-consuming device
(SACU)
Note a: The AC input power cable can connect to a 300 mm2 or 400 mm2 single-core cable. The
restrictions are as follows:
● Outer diameter of a single-core cable ≤ 35 mm
● Dimensions of the wiring terminal: width ≤ 43 mm; length ≤ 136.5 mm; outer diameter of the
crimping tube ≤ 37 mm
Procedure
Step 1 Connect a PE cable.
Figure 7-3 Connecting a PE cable to the main ground bar in the LV room
----End
Follow-up Procedure
To enhance the corrosion resistance of a ground terminal, apply silica gel or paint
on it after connecting the PE cable.
NOTICE
● The cable material must comply with local regulations and standards.
● Do not connect aluminum wiring terminals to the AC terminal block. Otherwise
electrochemical corrosion may occur, affecting the reliability of cable
connections.
● Comply with the IEC 61238-1 requirements when using copper-to-aluminum
wiring terminals, or aluminum wiring terminals along with copper-to-
aluminum washers.
● Do not mix up the aluminum and copper sides of the copper-to-aluminum
washers. Ensure that the aluminum side of the washer contacts the aluminum
wiring terminal, and the copper side contacts the AC terminal block.
Procedure
Step 1 Connect an AC input power cable.
NOTICE
● The screw assembly whose model is subject to the delivery should be tightened
according to the corresponding standard torque.
● Partially tighten the nut for the AC input power cable using a torque of 5 N·m
when securing the cable.
● The wiring terminal must be installed with heat shrink tubing at the crimping
area of the cable conductor to ensure that the electrical clearance between the
conductors is greater than 20 mm.
● Lay out the AC input power cable according to the design, route the cable to
the correct wiring position on the corresponding switch, and label the cable.
Step 2 Use firestop putty to seal the cable hole at the bottom.
----End
NOTICE
● The cable material must comply with local regulations and standards.
● Do not connect aluminum wiring terminals to the AC terminal block. Otherwise
electrochemical corrosion may occur, affecting the reliability of cable
connections.
● Comply with the IEC 61238-1 requirements when using copper-to-aluminum
wiring terminals, or aluminum wiring terminals along with copper-to-
aluminum washers.
● Do not mix up the aluminum and copper sides of the copper-to-aluminum
washers. Ensure that the aluminum side of the washer contacts the aluminum
wiring terminal, and the copper side contacts the AC terminal block.
Procedure
Step 1 Connect an AC input power cable.
NOTICE
● The screw assembly whose model is subject to the delivery should be tightened
according to the corresponding standard torque.
● Partially tighten the nut of the AC input power cable using a torque of 5 N·m
when securing the cable.
● The wiring terminal must be installed with heat shrink tubing at the crimping
area of the cable conductor to ensure that the electrical clearance between the
conductors is greater than 20 mm.
● Lay out the AC input power cable according to the design, route the cable to
the corresponding wiring position on the corresponding switch, and label the
cable.
Step 2 Use firestop putty to seal the cable hole at the bottom.
----End
NOTICE
● The door of the power cable room of the ring main unit is interlocked with the
grounding switch. The door can be opened only when the grounding switch is
turned on.
● When connecting the incoming cables, ensure that the grounding switch of the
upstream outgoing cable cabinet is turned on. After connecting cables, ensure
that the grounding switch of cabinet G1 in the ring main unit of the STS is
turned off.
● Before turning on the grounding switch of cabinet G1, turn off the switch in the
upstream cabinet G3.
● If multiple STSs are cascaded, cabinet G3 of the last STS should be installed
with insulation plugs by the Engineering, Procurement, Construction (EPC).
● Route cables to corresponding positions according to the design and label the
cables.
● If the foundation is too high to connect cables, the customer needs to add a
construction platform to facilitate cable connections.
● If the outer diameter of a cable is small, fill the removed insulation layer
between the cable clip and the cable to ensure that the cable is securely
connected. If the cables are not securely connected, the ring main unit may be
damaged, causing gas leakage.
Procedure
Step 1 Cut a cable inlet according to the cross-sectional area of the cable.
Step 2 Prepare terminals and secure them by referring to the installation guide to the
split-type shielded cable connector.
Figure 7-11 Connecting AC output power cables (multiple ring main units of 8DJH
series are cascaded)
Figure 7-12 Connecting AC output power cables (multiple ring main units of other
models are cascaded)
NOTE
The cable room of the load switch cabinet supports the access of two rows of cables. The
actual situation may vary.
Step 3 Fill the rubber insulation layer removed when preparing the cables between the
cables and the cable clips to ensure that the cables are securely connected.
NOTE
If the cables are not securely connected, the ring main unit may be damaged, causing gas
leakage.
Step 4 Seal the bottom cable hole using firestop putty, clear the cable room sundries, and
close the door.
----End
WARNING
● For the SACU that houses one potential induced degradation (PID) module,
connect the three-phase AC power cable to the FU01 switch, and the functional
earthing (FE) cable to FE01 on the FE bar.
● For the SACU that houses two PID modules, connect the three-phase AC power
cable of the first route to the FU01 switch, and the corresponding FE cable to
FE01 on the FE bar. Connect the three-phase AC power cable of the second
route to the FU02 switch, and the corresponding FE cable to FE02 on the FE
bar.
● Do not reversely connect the cables connected to FE01 and FE02.
● This document describes how to connect three-phase AC power cables for the
SACU that houses two PID modules. For details about how to connect a three-
phase AC power cable for the SAC that houses one PID module, refer to the
way of connecting the first route of the three-phase AC power cable for the
SAC that houses two PID modules.
Step 5 Connect the single-phase AC power cable. Insulate the unused cable terminals and
bind them in the cable holder.
This document describes how to connect IMD cables for the SACU that houses two PID
modules.
Step 7 Use firestop putty to seal the cable hole in the container.
----End
Procedure
Step 1 Install the UPS.
1. Install a mounting kit.
NOTE
2. Install the lithium battery module on the external wall of the STS.
3. Install the connecting kit and combine the PSU with the lithium battery
module.
Step 3 Connect the cables between the PSU and the lithium battery module.
NOTE
Please remove the quick connector from the BAT1 port on the lithium battery module
before connecting the cables.
Step 5 Connect signal cables for the SACU. Insulate the unused cable terminals and bind
them in the cable holder.
NOTE
----End
A FAQ
Paint Repair
The container should be intact. If paint has flaked off in a specific area, repaint
that area.
NOTE
Check the paint damage on the container and prepare appropriate tools and materials. The
number of materials depends on site requirements.
Procedure
Step 1 Gently polish the damaged areas using fine sandpaper to remove smudges or rust.
Step 2 Dip a piece of cotton cloth into anhydrous alcohol and wipe the polished or
damaged area to remove the dirt and dust. Then wipe off the alcohol with a clean
and dry cotton cloth.
Step 3 Paint zinc-rich primer on the damaged coat using a brush or painting gun.
NOTICE
● If the base material is exposed in the area to be repaired, apply epoxy zinc-rich
primer, wait until the paint has dried, and then apply acrylic acid top coating.
● Select epoxy zinc-rich primer or acrylic acid top coating with a color the same
as the surface coating color of the equipment.
Step 4 Apply paint evenly to the damaged area based on the damage degree of the paint
using a spray bottle, brush, or painting gun until all damage traces are invisible.
NOTICE
Step 5 Wait for 30 minutes and check whether the painting meets the requirements.
NOTE
● The color of the repainted area must be consistent with that of the surrounding area.
Use a colorimeter to measure the color difference (ΔE), which should be less than or
equal to 3. If a colorimeter is unavailable, ensure that there is no visible edge between
the repainted area and the surrounding area. The paint should also be free of bulges,
scratches, flaking, or cracks.
● If you choose to spray paint, it is recommended that you spray paint three times before
checking the result. If the color does not meet the requirements, paint more times until
the painting meets the requirements.
----End
NOTE
The following is a paint model list provided by Huawei. The list may be updated irregularly
and is for reference only. The price of paint and technical services shall be subject to local
price standards.
A
ACB air circuit breaker
C
COM communication
I
IMD Insulation Monitor Device
L
LV low voltage
M
MV medium voltage
S
STS smart transformer station
T
TR transformer