Project: New Manufacturing plant
Client: Fastform Fabricators Ltd

PRELIMINARY & GENERAL


% of total contract 9.71% $7,750,000.00 contract value
$110.30 6826 m2 of floor area

Description Duration ??? Working Total $


Days
Access Roading Metal to site entrance, carparking and sheds 5,690.00
Road Cleaning Road cleaning during earthworks by sub 2 months 2,845.00
Silt & Sediment Control Full project 1,815.00
CW Insurance 0.2% of Contract Value 15,500.00
PL Insurance 0.04% of Contract Value 3,100.00
Temporary Fencing Erection 2,230.00
Dismantling 1,125.00
Hire $130.00 per week 11,150.00
Plant Hire Builders Plant 8,305.00
Work platforms EWPs 6,305.00
Scaffolding Erection 12,551.00
Dismatling 6,706.00
Hireage 20,295.00
Fall Protection Handrails 24,600.00
Temporary Office 2 No. 4.8 x 2.5m offices 9,255.00
Temporary Storage 6m container 2,800.00
Temporary Toilets 4.8 x 3m toilet 5,605.00
Temporary Mess 6 x 3m lunchroom 5,828.00
Project Manager $105 x 50% 115,080.00
Site Manager $80x 100% 175,360.00
Site Foreman $70 x 50% 76,720.00
Quantity Surveyor $90 x 50% 98,640.00
Health & Safety Manager $85 x 5% 12,316.00
Fire Protection Fire extinguishers 925.00
First Aid Kit ($250) + Top Ups 3 @ $125 770.00
Personal Protective Equipment 6 No. sets x $80 790.00
Safety Signage Directional & general safety signage site setup 1,735.00
Computers Laptop with aircard 2,768.00
Photocopier Multifunction Printer 4,133.00
Consumables Office & sanitary consumables 4,330.00
Security Connect alarms to site sheds 615.00
Temporary Water Temporary connection 675.00
Temporary Services Connect toilet & lunch room to water & waste 625.00
Temporary Power Lifeguards, leads, power etc. 9,870.00
Surveyor Building Setout & As-built 6,642.00
Clean Up - Labour General cleaning 15,520.00
Skips, Dump Fees, etc 5 No. 9m3 skips + 2 No. sacks x 8 empties @ $1,250.00 12,300.00
Hoardings Erection 3,153.00
Dismantling 1,633.00
Hireage 14,225.00
Car Parking Car parks 26,155.00
Cartage Miscellaneous freight 13,690.00
Final Cleaning Commercial Cleaning (exterior & interior) 8,500.00
Total Preliminary & General 752,875.00