1 Project: New Manufacturing plant Client: Fastform Fabricators Ltd
PRELIMINARY & GENERAL
% of total contract 9.71% $7,750,000.00 contract value $110.30 6826 m2 of floor area
Description Duration ??? Working Total $
Days Access Roading Metal to site entrance, carparking and sheds 5,690.00 Road Cleaning Road cleaning during earthworks by sub 2 months 2,845.00 Silt & Sediment Control Full project 1,815.00 CW Insurance 0.2% of Contract Value 15,500.00 PL Insurance 0.04% of Contract Value 3,100.00 Temporary Fencing Erection 2,230.00 Dismantling 1,125.00 Hire $130.00 per week 11,150.00 Plant Hire Builders Plant 8,305.00 Work platforms EWPs 6,305.00 Scaffolding Erection 12,551.00 Dismatling 6,706.00 Hireage 20,295.00 Fall Protection Handrails 24,600.00 Temporary Office 2 No. 4.8 x 2.5m offices 9,255.00 Temporary Storage 6m container 2,800.00 Temporary Toilets 4.8 x 3m toilet 5,605.00 Temporary Mess 6 x 3m lunchroom 5,828.00 Project Manager $105 x 50% 115,080.00 Site Manager $80x 100% 175,360.00 Site Foreman $70 x 50% 76,720.00 Quantity Surveyor $90 x 50% 98,640.00 Health & Safety Manager $85 x 5% 12,316.00 Fire Protection Fire extinguishers 925.00 First Aid Kit ($250) + Top Ups 3 @ $125 770.00 Personal Protective Equipment 6 No. sets x $80 790.00 Safety Signage Directional & general safety signage site setup 1,735.00 Computers Laptop with aircard 2,768.00 Photocopier Multifunction Printer 4,133.00 Consumables Office & sanitary consumables 4,330.00 Security Connect alarms to site sheds 615.00 Temporary Water Temporary connection 675.00 Temporary Services Connect toilet & lunch room to water & waste 625.00 Temporary Power Lifeguards, leads, power etc. 9,870.00 Surveyor Building Setout & As-built 6,642.00 Clean Up - Labour General cleaning 15,520.00 Skips, Dump Fees, etc 5 No. 9m3 skips + 2 No. sacks x 8 empties @ $1,250.00 12,300.00 Hoardings Erection 3,153.00 Dismantling 1,633.00 Hireage 14,225.00 Car Parking Car parks 26,155.00 Cartage Miscellaneous freight 13,690.00 Final Cleaning Commercial Cleaning (exterior & interior) 8,500.00 Total Preliminary & General 752,875.00