Professional Documents
Culture Documents
Single line drawing starts with the incoming power source from the
utility service and/or on-site generation and their associated
distribution equipment. It then follows the power �ow down through
the various conductors as well as any voltage transformations to feed
distribution equipment buses for the key loads served.
Initially, the Single Line Diagram (SLD) provides a framework for the
incorporation of di�erent types of required information such as:
Ok, let’s dive into details of a single line diagram now, by describing
the most important elements:
Table of Content:
Moving toward the end of the Design Development Phase, the Single
Line Diagram and associated drawings such as equipment room
elevations and �oorplans are provided to the client for their review
and approval. At this point, both the client’s comments and the
construction manager’s additional inputs are integrated into the
design.
During the various stages of a project design, changes are made often
to re�ect the client’s preferences and budget.
The proper use of notes on the Single Line Diagram can further
de�ne the requirements.
As an example, a note can be added clarifying that all NEMA 4X rated
enclosures are to be of 316 stainless steel versus the less expensive
304 Grade. The di�erence between these two grades is critical as 316
Stainless is far more resistant to saltwater, sulfuric acid and
chlorides, and is preferred in several applications including
pharmaceutical manufacturing and wastewater treatment plants.
The System Single Line Diagram is the common map that all the
other project documents must reference and be checked against. To
ensure consistency and avoid con�icts after a project is awarded to a
contractor, distribution panelboard schedules and speci�cations also
need to include the correct information about details such as the
enclosure type required.
For these reasons, it is critical that the engineer be vigilant and take
a proactive role in identifying changes and updating the Single
Line Diagram and associated design documents appropriately and
consistently.
3.1 General
Transformer information:
Transformer “T1”
Primary unit substation style
13.8 kV delta primary – 95kV BIL
4.16/2.4 kV grounded wye – 60kV BIL
Eaton “peak” 55c/65c/75c
7500/8400/9156 kVA KNAN
9375/10500/11445 kVA KNAF
Fr-3 �uid �lled, 6.5% minimum z
With surge + lightning arresters
P/FA = current rating. Primary, forced air.
S/FA = current rating. Secondary, forced air.
The “T
T1” transformer is described as “Delta” Primary, “Wye”
Secondary con�guration in the text as well as further depicted by
the relationship of the “H
H1, H2 and H3” connections to the X1, X2, X3
and X0 symbols adjacent to it.
Similarly, the verbiage in the text calls for surge and lightning
protection. Symbols for the arrester and the capacitor are shown
connected to the incoming terminations. Their actual ratings should
be de�ned on the drawing or in the speci�cations.
When sizing the MV cables, the NEC derating factors must also be
applied depending on the type of raceway or duct bank that will be
required.
The dots, X’s or boxes are used to denote the instantaneous polarity
orientation of the CT. The polarity marks on the conductor generally
face toward the source of the current �ow. The polarity mark on the
CT winding represents the relationship of the CT’s X1 secondary
terminal to the H1 medium-voltage terminal on bar type CTs or its
input orientation for donut style CTs.
Figure 6 – Current Transformer Symbols
Note the “Y” symbol, as well as the quantity “(3)” next to the CTs.
This represents three CTs con�gured in a three-phase grounded
wye arrangement.
While most of the CTs on the system single line diagram in Figure 2a
and 2b are shown this way, the CTs on the output side of the 2000 A
breaker S1A are not grounded. This is done to indicate to the
equipment manufacturer or installing contractor that the CT inputs
to the relay should not be grounded in more than one location.
This may result in a higher accuracy class with more physical mass or
a higher CT ratio being speci�ed.
Most of the CTs shown on Figure 7 are Standard Accuracy Class for
the ratios selected. The exception is the single 600:5 CT in
transformer T1’s Neutral to Ground Connection. This is shown as a
high accuracy CT.
Where loads are light, during construction or during early build out
stages, the actual current that must be measured by the meter may be
only 100 A. Multi-ratio CTs are frequently used to set the maximum
ratio lower. If set at 100:5A, this would improve accuracy down to 10
A for a 100 A load.
Conversely, as the end loads grow, the maximum ratio setting can be
easily increased by changing the CT tap settings.
In both cases, the associated (86) lockout relay then trips the
incoming main breaker “M1” and the transformer secondary
breaker “S1” (see their positions).
This re�ects the engineer’s desire to have only one output contact
for both the 27 and 59 functions. Because two breakers need to be
tripped, this will only require two separate relay contacts instead of
four individual output contacts otherwise necessary.
The direct trip shown on the System SLD purposely does not use an
86 lockout relay, as this under or over voltage disturbance is
anticipated to be caused by the utility and not a fault on the end
user’s power system. In these instances, a separate contact from the
relay may be allocated to start a backup generator or to initiate a
Main-Tie-Main Transfer Scheme.
One such requirement is the breaker’s close and latch rating. Where
higher fault current values exist, some utilities specify this value at
130 kA peak, which is more in line with the older 1000 MVA rated
design. Because the 40 kA K=1 design’s close and latch rating is only
104 kA, the 130 kA close and latch rating for the 50 kA breaker would
dictate it being used instead.
As shown on the Single Line Diagram, there are ground studs on the
incoming and outgoing sides of both the “USG-1A”, (13.8 kV) and
“PSG-1A” (4.16 kV) switchgear. Applying these portable ground
cables requires a safe disconnection of power in the zone to be
grounded to ensure personnel safety.