Professional Documents
Culture Documents
Prepared for:
Prepared by:
36006727160
Sign-off Sheet
This document entitled Gunnedah Solar Project - Underground Cable Ampacity Report was prepared by
Stantec Consulting Ltd. (“Stantec”) for the account of PCL Constructors Canada Inc. (the “Client”). Any
reliance on this document by any third party is strictly prohibited. The material in it reflects Stantec’s
professional judgment in light of the scope, schedule and other limitations stated in the document and in
the contract between Stantec and the Client. The opinions in the document are based on conditions and
information existing at the time the document was published and do not take into account any subsequent
changes. In preparing the document, Stantec did not verify information supplied to it by others. Any use
which a third party makes of this document is the responsibility of such third party. Such third party agrees
that Stantec shall not be responsible for costs or damages of any kind, if any, suffered by it or any other
third party as a result of decisions made or actions taken based on this document.
Prepared by
(signature)
Andrew St Jean
Reviewed by
(signature)
John Sullivan, Senior Electrical Engineer
Independent
Revision Description Author Review Issue Date
Reviewer
A For Review Andrew St Jean John Sullivan Sean Freihaut 09/25/20
erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
Executive Summary
September 25, 2020
Table of Contents
1.0 EXECUTIVE SUMMARY ........................................................................................... 1
1.1 OBJECTIVES ............................................................................................................ 1
1.2 MODEL INPUTS ....................................................................................................... 1
1.3 RESULTS AND RECOMMENDATIONS.................................................................... 3
1.4 REFERENCE DOCUMENTATION ............................................................................ 3
LIST OF TABLES
Table 1: Module Ampacity Data for Canadian Solar HIKU .................................................... 4
Table 2: DC PV Source Circuit Ampacity Summary Table .................................................... 4
Table 3: Typical 5W1H Direct Buried Road Crossing ............................................................ 5
Table 4: 8W1H Typical Direct Buried .................................................................................... 5
Table 5: Section AC Feeder 4W1H Typical Direct Buried for Road Crossings and
Culverts .................................................................................................................. 7
Table 6: Section AC Feeder 3W1H Typical Direct Buried ...................................................... 8
Table 7: Section AC Feeder Substation Typical Direct Buried ............................................... 8
Table 8: Section AC Incomer Substation Typical Direct Buried ............................................. 9
LIST OF APPENDICES
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 3
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
Executive Summary
September 25, 2020
1.1 OBJECTIVES
This report is provided by Stantec Consulting Ltd. (Stantec) to demonstrate that all Gunnedah Solar
Project underground cable trenches are designed to meet or exceed applicable ampacity
requirements based on site specific conditions in the highest loading and heating scenarios.
This report is divided into two main sections. The first section covers DC collector cable sizing and
ampacity calculations from the PV modules to the MV Station Inverters. The DC collector system is
comprised of the following installations:
1. PV Sub-Array Cable bundled on racking and in direct buried conduit from PV modules to
combiner boxes;
2. PV String Cable in underground direct buried trenches from Combiner boxes to Inverters.
The second section covers underground medium voltage AC feeder cable sizing from the MV Station
transformers to the substation switchgear. It also includes the underground medium voltage AC
incomer cable sizing from the substation switchgear to transformer. The AC collector system is
comprised of the following installations:
1. AC Feeder circuits direct buried underground cable between MV stations and from MV
stations to the switchgear. This report analyzes the highest heating scenario of direct buried
installation.
Based on geotechnical reports and field test pits, it was found the majority of the site had silty clay soil
classifications. The geotechnical report also noted that there was approximately 170mm of rain in the
previous three weeks, otherwise the region had generally experienced ongoing drought conditions.
Taken from the Government of Australia’s website, it was also found that the Gunnedah site lies in an
above average relative soil moisture percentile.
A native soil resistivity value of 1.60°C•m/W at 2% moisture content is used in modelling based on site
specific dry-out curves (see Appendix B). Due to inconsistency in the soil and adding additional
conservatism, the native backfills in the trench surrounding the conductors have been assumed to dry
out under a worst-case scenario. The native soil backfill selected has a resistivity value of
1.90°C•m/W at 0% moisture content.
A cable load factor was also considered. The longest day of the year was found to be approximately
14 hours and 10 minutes. The provided “Typical Meteorological Year (P50)- Hourly Values of Solar
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 1
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
Executive Summary
September 25, 2020
Radiation and Meteorological Parameters” was able to display irradiation vs time over the course of a
day shown below.
Gunnedah
1200
1000
800
600
Irradiation (Wh/m²)
400
200
Time
It is assumed that the cables will be under full load when 1000 Wh/m² of irradiation is present. It is
shown that from only 10:30am until 2:30pm, the cables will be under full load. At approximately
8:30pm until 4:30am, there is 0 Wh/m² of irradiation present. Given these variables, and a
conservative approach, the load factor was calculated by applying 100% loading for all daylight hours
and 0% for night. These calculations provided a load factor of 0.67. A load factor of 0.7 was
simulated in the models
PV Output Circuit and AC Collector are analyzed using the IEC 60287 and 60853 calculation method
based on Neher-McGrath equations and completed using CYMCAP 7.2 Rev.1 modeling software.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 2
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
Executive Summary
September 25, 2020
• AS/NZS 3008.1.1-2017
• Ausgrid NS130
• E-RPT-001 to E-RPT-008
• Gunnedah Solar Farm – Thermal Resistivity Sampling by Douglas Partners, April 2020
• https://www.agriculture.gov.au/abares/research-topics/agricultural-outlook/australian-crop-
report/climatic-agronomic-conditions
• http://www.australiaab.com/sun/29181450
• https://weatherspark.com/y/144517/Average-Weather-in-Gunnedah-Australia-Year-Round
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 3
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
DC Cable Ampacities
September 25, 2020
Table 2 summarizes the various DC PV Source Circuit cable ampacities based on location, applicable
codes, and installation type.
Trenches are designed to ensure cables have a minimum ampacity of 125% of the short circuit
current (Isc) and coordinate with the overcurrent protection within 90°C cable temperature limits.
Scenarios are analyzed at steady-state loading, with all cables carrying the maximum continuous
current to ensure steady state cable temperature does not exceed 75°C.
Table 3 to Table 4 summarizes the various DC PV Source Circuit cable ampacities based on location,
applicable codes, and installation type.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 4
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
DC Cable Ampacities
September 25, 2020
2.2.1 Steady State Analysis Scenario 1: 5W1H Typical Direct Buried Road
Crossing
Table 3 Notes:
1. See Appendix C for detailed ampacity calculations completed using IEC 60287 and 60853
methods.
3. The cable with the highest temperature from the steady state analysis is shown at the 90°C
cable temperature rating as confirmation for coordination with the overcurrent protection
device. The remaining cables will have an ampacity greater than (>) the highest temperature
cable and are confirmed acceptable with the overcurrent devices shown.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 5
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
DC Cable Ampacities
September 25, 2020
Summary
Steady-State Steady-State Fuse Ampacity at 90°C
Cable Size
Current Temp. Size Cable Rating (Note 3)
Cable No. Circuit Number mm² Amp °C Amp Amp
12 6 400 300.0 62.4 450 >450
13 7 240 175.0 56.0 350 >350
14 7 240 175.0 56.4 350 >350
15 8 240 200.0 53.8 350 >350
16 8 240 200.0 54.3 350 >350
Table 4 Notes:
1. See Appendix C for detailed ampacity calculations completed using IEC 60287 and 60853
methods.
4. Worst case scenarios were modelled for six and seven circuit trenches. See Appendix C for
detailed ampacity calculations.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 6
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
AC Cable Ampacities
September 25, 2020
Error! Reference source not found. to Error! Reference source not found. summarizes the AC co
llector circuit cable ampacities based on location and installation type.
Table 5: Section AC Feeder 4W1H Typical Direct Buried for Road Crossings and
Culverts
Table 5 Notes:
1. Cable Types are modeled as 33kV, XLPE, Al. 100% Ins, 120mm²=3kA CS, 400mm²=3kA CS
and 630mm²=3kA CS with multi-point concentric screen bonded ends. See Stantec
Drawing E101, Single Line Diagram for details.
2. See Appendix D for detailed ampacity calculations completed using IEC 60287 and 60853
methods.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 7
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
AC Cable Ampacities
September 25, 2020
Table 6 Notes:
1. Cable Types are modeled as 33kV, XLPE, Al. 100% Ins, 120mm²=3kA CS, 400mm²=3kA CS
and 630mm²=3kA CS with multi-point concentric screen bonded ends. See Stantec
Drawing E101, Single Line Diagram for details.
2. See Appendix D for detailed ampacity calculations completed using IEC 60287 and 60853
methods.
Table 7 Notes:
1. Cable Types are modeled as 33kV, XLPE, Al. 100% Ins, 120mm²=3kA CS, 400mm²=3kA CS
and 630mm²=3kA CS with multi-point concentric screen bonded ends. See Stantec
Drawing E101, Single Line Diagram for details.
2. See Appendix D for detailed ampacity calculations completed using IEC 60287 and 60853
methods.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 8
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
AC Cable Ampacities
September 25, 2020
Table 8 Notes:
1. Cable Types are modeled as 33kV, XLPE, CU. 100% Ins, 800mm²=3kA CS with multi-point
concentric screen bonded ends. See Stantec Drawing E101, Single Line Diagram for details.
2. See Appendix D for detailed ampacity calculations completed using IEC 60287 and 60853
methods.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 9
GUNNEDAH SOLAR PROJECT - UNDERGROUND CABLE AMPACITY REPORT
Conclusion
September 25, 2020
4.0 CONCLUSION
This cable ampacity analysis has been completed to show that the selected cables and trench
configurations of the DC and AC collection systems have sufficient ampacity to carry the required
system current without exceeding the maximum operating temperature rating of cables and
terminations.
jod erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx 10
APPENDIX A
PV Module Specifications
erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx
BiHiKu
SUPER HIGH POWER BIFACIAL MONO PERC MODULE
420 W ~ 445 W
UP TO 30% MORE POWER FROM THE BACK SIDE
CS3W-420|425|430|435|440|445MB-AG (IEC1000 V)
CS3W-420|425|430|435|440|445MB-AG (IEC1500 V)
PRODUCT CERTIFICATES*
Lower internal current, IEC 61215 / IEC 61730: VDE / CE / MCS / INMETRO
lower hot spot temperature UL 1703: CSA / IEC 61701 ED2: VDE / IEC 62716: VDE / IEC 60068-2-68: SGS
Take-e-way
Canadian Solar recycles panels at the end of life cycle
30 1048
1019
A-A 11 11
10 10
23 9 9
6-Φ5
Grounding 8 8
Hole
7 7
30
6 6
8-14x9
Mounting 5
5
Hole
A A
4-10x7 4 4
Mounting
Hole(tracker) 3 3
2132
1155
1300
2
400
2
Mounting Hole 1 1
R 0 V0 V
R 5 10 15 20 25 30 35 40 45 50 5 10 15 20 25 30 35 40 45 50
14
10
800 W/m2 25°C
600 W/m2 45°C
50
ELECTRICAL DATA
Operating Temperature -40°C ~ +85°C TEMPERATURE CHARACTERISTICS
Max. System Voltage 1500 V (IEC/UL) or 1000 V (IEC/UL) Specification Data
TYPE 3 (UL 1703)
Module Fire Performance Temperature Coefficient (Pmax) -0.35 % / °C
or CLASS C (IEC61730)
Max. Series Fuse Rating 25 A Temperature Coefficient (Voc) -0.27 % / °C
Application Classification Class A Temperature Coefficient (Isc) 0.05 % / °C
Power Tolerance 0~+5W Nominal Module Operating Temperature 41 ± 3°C
Power Bifaciality* 70 %
* Power Bifaciality = Pmaxrear / Pmaxfront, both Pmaxrear and Pmaxfront are tested under STC, Bifacia-
lity Tolerance: ± 5 %
PARTNER SECTION
* The specifications and key features contained in this datasheet may deviate slightly from our
actual products due to the on-going innovation and product enhancement. Canadian Solar Inc.
reserves the right to make necessary adjustment to the information described herein at any time
without further notice.
Please be kindly advised that PV modules should be handled and installed by qualified people
who have professional skills and please carefully read the safety and installation instructions
before using our PV modules.
erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx
Douglas Partners Pty Ltd
ABN 75 053 980 117
www.douglaspartners.com.au
96 Hermitage Road
West Ryde NSW 2114
PO Box 472
West Ryde NSW 1685
Phone (02) 9809 0666
Email: roconnell@pcl.com
Dear Sirs
1. Introduction
This letter report presents the results of undisturbed push-tube sampling carried out at the above site.
The work was undertaken at the request of PCL Constructors Canada Inc., to provide subsurface soil
thermal resistivity data at cable burial depth to assist in the design of buried power transmission
cables and trench backfill between the solar arrays and the substation.
The samples were taken at ten locations on 3 March 2020 by an engineering geologist from Douglas
Partners Pty Ltd (DP) in accordance with our Proposal SYD200032. Test pits were excavated to
maximum expected cable burial depth and push-tube samples were taken at the expected cable burial
depth. The tubes were sealed to maintain insitu moisture content and a geotechnical test-pit log was
recorded. Samples were sent for laboratory analysis to produce Thermal Resistivity dry-out curves in
accordance with ASTM D5334 Standard Test Method for Determination of Thermal Conductivity of
Soil and Soft Rock by Thermal Needle Probe Procedure.
The surface soils consisted of dry sandy and silty soils, covering flat plains within wheat and cotton
fields (The Manilla 1:250k Geological Sheet SH56-09, first edition 1973 indicated the area comprised
Quaternary stream alluvial deposits, including riverine plain deposits, comprising sandy to silty soils
and minor gravelly soils).
Subsurface soil moisture was recorded in the upper silty clay layer in all 10 Test Pits. All of the U75
push-tube samples were taken from the sidewall of this layer, refer Table 1. Below. Rainfall during the
previous months, December to March, is attached (cf. the Bureau Of Meteorology). Gunnedah airport,
~9 km from site, recorded 170 mm during the previous 3 weeks, otherwise the region has generally
Brisbane • Cairns • Canberra • Central Coast • Coffs Harbour • Darwin • Geelong • Gold Coast • Macarthur • Melbourne
FS 604853 Newcastle • North West Sydney • Perth • Port Macquarie • Sunshine Coast • Sydney • Townsville • Wollongong
Page 2 of 4
experienced ongoing drought conditions in recent years. The site is on the Gunnedah Plains with
negligible topographic variation (i.e. essentially flat), and is largely an irrigated cotton farm, with some
adjoining wheat fields, so the subsurface will be receiving some moisture due to seepage from the
irrigation channels and the flooded plantation fields.
Test Pits were excavated using a 30 t excavator with 1.2 m wide toothed bucket. Pits were excavated
to ~1.5 m depth, essentially in the upper silty clay layer; the 75 mm diameter, 450 mm long steel
sample tubes were hammered into the sidewall at 0.8 - 1.0 m depth, enough to be held in place before
being pushed in with the bucket. Bulk samples of ~5 kg were also taken where gravel inclusions may
have restricted the filling of the tube. Tubes were sealed with a tight-fitting plastic cap and securely
taped for moisture retention.
3. Results
Dry-out curve results from testing by the NATA Accredited laboratory - Geotherm Australasia, are
provided for your assessment. The oven-drying process took up to 4 weeks for all samples to fully
dry. Samples were tested at approximately weekly intervals to acquire five thermal resistivity readings
for each sample.
4. Limitations
Douglas Partners (DP) has prepared this report for this project at Gunnedah NSW in accordance with
DP’s proposal SYD200032 dated 26 January 2020 and acceptance received from
PCL Constructors Canada Inc.. This report is provided for the exclusive use of PCL Constructors
Canada Inc for the specific project and purpose as described in the report. It should not be used by or
be relied upon for other projects or purposes on the same or another site or by a third party. DP has
necessarily relied upon information provided by the client and / or their agents.
The results provided in the report are considered to be indicative of the sub-surface conditions on the
site only to the depths investigated at the specific sampling and / or testing locations, and only at the
time the work was carried out. Sub-surface conditions can change abruptly due to variable geological
processes and also as a result of human influences. Such changes may occur after DP’s field testing
has been completed.
DP’s results are based upon the conditions encountered during this investigation. The accuracy of the
results provided by DP in this report may be affected by undetected variations in ground conditions
across the site between and beyond the sampling and / or testing locations.
This report must be read in conjunction with all the attachments and should be kept in its entirety
without separation of individual pages or sections. DP cannot be held responsible for interpretations
or conclusions made by others unless they are supported by an expressed statement, interpretation,
outcome or conclusion stated in this report.
Yours faithfully
Douglas Partners Pty Ltd Reviewed by
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
150° 19' 48" E 150° 21' 0" E
6,575,500 mN
TP1 (1.0 m)
TP3 (0.9 m)
TP2 (0.9 m)
6,574,500 mN
TP5 (0.9 m)
TP4 (0.8 m)
TP6 (0.8 m)
TP7 (1.0 m)
Route
6 0m
TP8 (1.0 m)
6,573,500 mN 30° 56' 42" S
TP9 (1.0 m)
6,572,500 mN
6,571,500 mN
Sample Details
Sample ID / Name / Number TP1 - 1m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
1/04/2020 Probe inserted into sample. Fully dry A 0.00% 600 19.4 0.78 1.28
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 179 73 1389.53 1.86
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by PV. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
TP1 - 1m Average
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 2nd April 2020 Report Number : 171502
Sample Details
Sample ID / Name / Number TP2 - 0.9m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
31/03/2020 Probe inserted into sample. Fully dry A 0.00% 600 21.1 0.80 1.25
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 246 73 1908.03 1.85
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by BL. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 7th April 2020 Report Number : 171509
Sample Details
Sample ID / Name / Number TP3 - 0.9m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
16/03/2020 Probe pushed into tube. Partially dry. A 6.82% 600 19.3 0.88 1.14
20/03/2020 Probe pushed into tube. Partially dry. A 4.15% 600 20.6 0.75 1.33
30/03/2020 Probe pushed into tube. Partially dry. A 1.78% 600 20.5 0.65 1.54
7/04/2020 Probe pushed into tube. Fully dry A 0.00% 600 21.7 0.61 1.65
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 174 73 1274.68 1.75
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by BL. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 2nd April 2020 Report Number : 171510
Sample Details
Sample ID / Name / Number TP4 0.8m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
16/03/2020 Probe pushed into tube. Partially dry. A 16.52% 600 19.2 1.25 0.80
19/03/2020 Probe pushed into tube. Partially dry. A 10.90% 600 20.1 0.93 1.07
23/03/2020 Probe pushed into tube. Partially dry. A 7.60% 600 21.8 0.82 1.22
27/03/2020 Probe pushed into tube. Partially dry. A 4.10% 600 20.6 0.71 1.41
1/04/2020 Probe pushed into tube. Fully dry A 0.00% 600 21.4 0.56 1.78
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 178 73 1201.87 1.61
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by PV. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20% 22% 24% 26%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 7th April 2020 Report Number : 171503
Sample Details
Sample ID / Name / Number TP5 - 0.9m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
7/04/2020 Probe inserted into sample. Fully dry A 0.00% 600 19.8 0.54 1.85
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 177 73 1279.32 1.73
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by PV. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 7th April 2020 Report Number : 171504
Sample Details
Sample ID / Name / Number TP6 - 0.8m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
7/04/2020 Probe inserted into sample. Fully dry A 0.00% 600 20.7 0.63 1.60
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 180 72 1365.13 1.86
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by BL. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 2nd April 2020 Report Number : 171505
Sample Details
Sample ID / Name / Number TP7 - 1m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
30/03/2020 Probe inserted into sample. Fully dry A 0.00% 600 22.2 0.68 1.46
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 248 73 1804.83 1.74
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by PV. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
TP7 - 1m Average
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 2nd April 2020 Report Number : 171506
Sample Details
Sample ID / Name / Number TP8 - 1m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
31/03/2020 Probe inserted into sample. Fully dry A 0.00% 500 18.7 0.72 1.39
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 179 73 1352.02 1.81
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by BL. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
TP8 - 1m Average
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 7th April 2020 Report Number : 171507
Sample Details
Sample ID / Name / Number TP9 - 1m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
7/04/2020 Probe inserted into sample. Fully dry A 0.00% 600 20.9 0.53 1.87
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 178 72 1257.67 1.74
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by BL. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
TP9 - 1m Average
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Test Report
Client : Douglas Partners Project Number : 1715
Project Details : Gunnadah - Project 99577.01
Order/Request Number :
Report Date : 7th April 2020 Report Number : 171508
Sample Details
Sample ID / Name / Number TP10 - 1m
Sample Description
Sampled by Client
Sample Type Push Tube
Date Sampled
7/04/2020 Probe inserted into sample. Fully dry A 0.00% 600 21.2 0.65 1.54
Specimen Length (mm) Diameter (mm) Mass (g) Dry Density (t/m3)
A 170 73 1230.94 1.73
Notes
- *Thermal resistivity calculation = 1 / Thermal Conductivity.
- All testing undertaken at Geotherm’s Hornsby Laboratory, unless noted.
- Specimens prepared by BH. Wet specimens tested by BL. Dry and partially dry specimens tested by PV, BL,
- The above samples will be discarded after 2 weeks.
Brett Hobson
Approved Signatory
TP10 - 1m Average
2.00
1.80
1.60
1.40
1.20
Thermal Resistivity (Km/W)
1.00
0.80
0.60
0.40
0.20
0.00
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%
Moisture Content (% Dry weight)
Gunnedah Airport to ctr of site approx 9 km
Nate Grove landholder & irrigator knows site rainfall in detail
29-Dec19 to 1-Feb20
APPENDIX C
DC PV Output Circuit Analysis Results
erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx
Study Summary
CYMCAP Version 7.2 Revision 01
Execution: Gunnedah-DC-5W1H-RC
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.7 1.0 0.4 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Execution: Gunnedah-DC-5W1H-RC
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.7 1.0 0.4 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Execution: DC-6W1H-90
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.55 1.5 0.5 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Execution: DC-6W1H-SS
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.55 1.5 0.5 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Execution: DC-7W1H-90
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.55 1.5 0.5 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Execution: DC-7W1H-SS
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.55 1.5 0.5 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Execution: Gunnedah-DC-8W1H-90
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.525 2.0 0.45 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Execution: Gunnedah-DC-8W1H-SS
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.525 2.0 0.45 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx
Study Summary
CYMCAP Version 7.2 Revision 01
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.5 1.0 0.6 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.7 4.0 0.4 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.45 5.5 0.5 1.9
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
Induced currents in metallic layers as a fraction of conductor current (applied to all single phase circuits) : 0.0
Thermal
Layer Name Resistivity
X [m] Y [m] Width [m] Height [m] [K.m/W]
Backfill 0.0 0.6 4.0 0.6 1.4
Results Summary
Conductor
Cable Daily Load X coordinate Y coordinate temperature
Cable No. Cable ID Circuit No. Feeder ID Cable Phase Frequency Factor [m] [m] [°C] Ampacity [A]
erpt009_36006727160_pcl_gunnedah-cable_ampacity_200925.docx
1 2 3 4 5
Copyright Reserved
The Contractor shall verify and be responsible for all dimensions. DO NOT scale the
D drawing - any errors or omissions shall be reported to Stantec without delay.
The Copyrights to all designs and drawings are the property of Stantec. Reproduction or
use for any purpose other than that authorized by Stantec is forbidden.
Notes
Legend
Permit/Seal
B
PRELIMINARY
NOT FOR
CONSTRUCTION
Client/Project Logo
Client/Project
PCL CONSTRUCTORS PACIFIC RIM Pty Ltd.
Title
AC AND DC
TRENCHING DETAILS
2020.09.24 5:42:00 PM, St. Jean, Andrew