100% found this document useful (1 vote)
4K views24 pages

Module 2 Manpower Leveling

The document discusses the process of manpower leveling for construction project management. It describes manpower leveling as redistributing labor across project activities to comply with workforce availability and create a balanced usage curve over time. The document then provides a sample problem demonstrating how to analyze a network diagram to determine workforce requirements per day and level manpower as needed. It walks through calculating workforce needs on a daily basis over the duration of the project activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
4K views24 pages

Module 2 Manpower Leveling

The document discusses the process of manpower leveling for construction project management. It describes manpower leveling as redistributing labor across project activities to comply with workforce availability and create a balanced usage curve over time. The document then provides a sample problem demonstrating how to analyze a network diagram to determine workforce requirements per day and level manpower as needed. It walks through calculating workforce needs on a daily basis over the duration of the project activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

CE168P-2 .

CONSTRUCTION METHODS AND PROJECT


MANAGEMENT
MODULE 2

Prepared By:

Engr. Jeffrey E. Germono, CPM, PSM CM

SCHOOL OF CIVIL, ENVIRONMENTAL, AND GEOLOGICAL ENGINEERING


SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

2: CASH PLANNING AND CONTROL


2a: RESOURCE ALLOCATION
MODULE 1

2
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

2-A1: MANPOWER LEVELING


MANPOWER (WORKFORCE) LEVELING

Basically, is the manpower redistribution on the project activities to comply


with manpower availability and a balanced smooth manpower usage curve

Two (2) Main Reasons for Using MANPOWER LEVELING:

•The availability of certain resources does not fulfill the project requirement
rate, so we have to level the rate of resource daily usage to comply with the
resource availability as the driving resource for the project duration.

•The manpower resource curve is going up and down according to the big
variances of the resource daily usage that are not practical as we don’t hire
labor for short periods of time. In this way, we should level it to have a
constant daily rate as possible for manpower usage.

3
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

“The consequence of employment fluctuation and


equipment utilization adds to the cost of the project.”
THEREFORE…

MANPOWER LEVELING is a SOLUTION in which you, as the Project


Manager, keep the employment at an ACCEPTABLE LEVEL

4
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

SAMPLE PROBLEM
FIRST STEP: DRAW THE NETWORK DIAGRAM

ACTIVITY/EVENTS

TIME MANPOWER SAMPLE TIME-SCALED


ESTIMATE LOADING NETWORK DIAGRAM

5
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

SECOND STEP: ANALYZE THE DIAGRAM IN TSN

SAMPLE TIME-SCALED SAMPLE TIME-SCALED


NETWORK DIAGRAM NETWORK DIAGRAM

6
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: ANALYZE THE WORKFORCE PER DAY OF ACTIVITES

IN THIS WAY,

YOU MAY SEE THE ACTIVITIES


WORKFORCE LOADING PER DAY OF
ITS ASSIGNMENT.

MORE DETAILED EXPLANATION (SEE


NEXT SLIDE/PAGE)

SAMPLE TIME-SCALED
NETWORK DIAGRAM

7
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: ANALYZE THE WORKFORCE PER DAY OF ACTIVITES


NODE 1-4 (ACTIVITY E) WAS SCHEDULED TO HAVE
15 MEN IN 5 DAYS

BUT NODE 1-2 (ACTIVITY B) WAS SCHEDULED TO


HAVE 10 MEN IN 7 DAYS

TIP:

ANALYZE THE FIRST NODE WITH MINIMUM DAYS


OF DURATION AND ANALYZE THE PARALLEL
ACTIVITIES
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 4-DAY MARK OF


NODE 2 ARE AS FOLLOWS:

ACTIVITY A: 10 MEN
ACTIVITY B: 10 MEN
ACTIVITY C: 5 MEN 4

ACTIVITY E: 15 MEN
SAMPLE TIME-SCALED
GET THE SUMMATION OF THE WORKFORCE AT THE NETWORK DIAGRAM
4TH DAY FROM THE MENTIONED ACTIVITIES
ABOVE:

TOTAL = 40 MEN x 4 DAY = 160 MAN DAYS

8
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 5-DAY MARK OF


THE PROJECT ARE AS FOLLOWS:

ACTIVITY A : 10 MEN
ACTIVITY C : 5 MEN
ACTIVITY D : 15 MEN
ACTIVITY E : 15 MEN*

GET THE SUMMATION OF THE WORKFORCE AT THE


5TH DAY FROM THE MENTIONED ACTIVITIES
ABOVE:

TOTAL = 45 MEN x 1 DAY = 45 MAN DAYS

ACTIVITY B IS NO LONGER INCLUDED AS IT WAS 4


ALREADY FINISHED ON THE 4TH DAY OF THE
PROJECT.
SAMPLE TIME-SCALED
ACTIVITY E IS INCLUDED SINCE IT WAS NETWORK DIAGRAM
SCHEDULED TO HAVE 5 DAYS OF TOTAL
DURATION. MEANING, THE REMAINING 1 DAY IS
INCLUDED*

9
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
Days 6-7
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 6-7-DAY MARK


OF THE PROJECT ARE AS FOLLOWS:

ACTIVITY A : 10 MEN
ACTIVITY C : 5 MEN
ACTIVITY D : 15 MEN

GET THE SUMMATION OF THE WORKFORCE AT THE


6TH – 7TH DAY FROM THE MENTIONED ACTIVITIES
ABOVE:

TOTAL = 30 MEN x 2 DAY = 60 MAN DAYS

ACTIVITY E IS NO LONGER INCLUDED AS IT WAS 4


ALREADY FINISHED ON THE 5TH DAY OF THE
PROJECT.
SAMPLE TIME-SCALED
NETWORK DIAGRAM

10
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
Days 8-11
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 8-11 DAY MARK


OF THE PROJECT ARE AS FOLLOWS:

ACTIVITY A : 10 MEN
ACTIVITY D : 5 MEN
ACTIVITY F : 15 MEN
ACTIVITY K : 10 MEN

GET THE SUMMATION OF THE WORKFORCE AT THE


8TH – 11TH DAY FROM THE MENTIONED ACTIVITIES
ABOVE:

TOTAL = 40 MEN x 4 DAY = 160 MAN DAYS

ACTIVITY A AT THIS STAGE IS FINISHED (11 DAYS 4


PROJECTION)

ACTIVITY D AND F WILL HAVE A REMAINING 1 SAMPLE TIME-SCALED


DAY TO FINISH NETWORK DIAGRAM

11
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
Day 12
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 8-11 DAY MARK


OF THE PROJECT ARE AS FOLLOWS:

ACTIVITY D : 5 MEN
ACTIVITY F : 15 MEN
ACTIVITY K : 10 MEN

GET THE SUMMATION OF THE WORKFORCE AT THE


12TH DAY FROM THE MENTIONED ACTIVITIES
ABOVE:

TOTAL = 30 MEN x 1 DAY = 30 MAN DAYS

ACTIVITY (D & F) WILL BE FINISHED ON THIS 4


MARKED DATE, IN REFERENCE TO THEIR
SCHEDULED WORK DURATION
SAMPLE TIME-SCALED
ACTIVITY K WILL HAVE A REMAINING 1 DAY TO NETWORK DIAGRAM
FINISH

12
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
Day 13
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 13 DAY MARK


OF THE PROJECT ARE AS FOLLOWS:

ACTIVITY G : 10 MEN
ACTIVITY H : 5 MEN
ACTIVITY I : 15 MEN
ACTIVITY K : 10 MEN

GET THE SUMMATION OF THE WORKFORCE AT THE


13TH DAY FROM THE MENTIONED ACTIVITIES
ABOVE:

TOTAL = 40 MEN x 1 DAY = 40 MAN DAYS

ACTIVITY K WILL BE FINISHED ON THIS MARKED 4


DATE, IN REFERENCE TO THEIR SCHEDULED WORK
DURATION
SAMPLE TIME-SCALED
ACTIVITY (G,H,I) WILL PROCEED STARTING DAY 14 NETWORK DIAGRAM

13
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
Day 14-18
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 14-18 DAY MARK


OF THE PROJECT ARE AS FOLLOWS:

ACTIVITY G : 10 MEN
ACTIVITY H : 5 MEN
ACTIVITY I : 15 MEN

GET THE SUMMATION OF THE WORKFORCE ON


THE 14TH TO 18TH DAY FROM THE MENTIONED
ACTIVITIES ABOVE:

TOTAL = 30 MEN x 5 DAY = 150 MAN DAYS

AT THIS STAGE, THE ACTIVITY G & H ARE SET TO BE 4


FINISHED.

SAMPLE TIME-SCALED
NETWORK DIAGRAM

14
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
Day 19-26
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 19-23 DAY MARK


OF THE PROJECT ARE AS FOLLOWS:

ACTIVITY I : 15 MEN
ACTIVITY J-L : 5 MEN

GET THE SUMMATION OF THE WORKFORCE ON


THE 19TH TO 26th DAY FROM THE MENTIONED
ACTIVITIES ABOVE:

TOTAL = 20 MEN x 8 DAY = 160 MAN DAYS

AT THIS STAGE, THE ACTIVITY J IS SET TO BE 4


FINISHED.

ACTIVITY I AND L WILL PROCEED TO DAY 26TH TO SAMPLE TIME-SCALED


27TH DAY RESPECTIVELY NETWORK DIAGRAM

15
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

STEP 3: continuation
Day 27
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 24-26 DAY MARK


OF THE PROJECT ARE AS FOLLOWS:

ACTIVITY L : 5 MEN

GET THE SUMMATION OF THE WORKFORCE ON


THE 27TH DAY FROM THE MENTIONED ACTIVITIES
ABOVE:

TOTAL = 5 MEN x 1 DAY = 5 MAN DAYS

AT THIS STAGE, ALL ACTIVITIES ARE SET TO BE 4


FINISHED

SAMPLE TIME-SCALED
NETWORK DIAGRAM

16
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

SUMMARY OF SCHEDULE OF MEN PER DAY


NUMBER OF DAYS NUMBER OF MEN TOTAL MAN DAYS
DAY 1-4 40 160
DAY 5 45 45
DAY 6-7 30 60 Therefore:

DAY 8-11 40 160 The lowest possible constant


DAY 12 30 30 manpower level per day is:

DAY 13 40 40 810 man-days / 27 days


= 30 men
DAY 14-18 35 150
DAY 19-26 20 160
DAY 27 5 5
27 DAYS TOTAL 810

REFER TO PREVIOUS SLIDES FOR VERIFICATION OF THE


BREAKDOWN OF MEN PER DAY OF SCHEDULE
17
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

LAST STEP: PLOT THE COMPUTED WORKFORCE LOADING


The previous slide shows that the constant
TIME-SCALED NETWORK AND MANPOWER LOADING
manpower per day is 30 men. 50

Pertaining to the graph, try to flatten all 45


humps over 30 and raise all dips under 30 of
the 40

35

30

MANPOWER
TIP 25
Try first the activities with Free Float and 20
scheduled them at the peak periods. These
activities may be re-scheduled by moving 15
them to a low resource requirement period.
10

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
PROJECT DURATION

No. of Men Target

18
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

LAST STEP: PLOT THE COMPUTED WORKFORCE LOADING


The previous slide shows that the TIME SCALED NETWORK AND MANPOWER LOADING
constant manpower per day is 30 35
men.

Pertaining to the graph, try to 30


flatten all humps over 30 and raise
all dips under 30 of the Time
Scaled Network and Manpower 25
Loading Graph

TIP 20
MANPOWER

Try first the activities with Free


15
Float and scheduled them at the
peak periods. These activities may
be re-scheduled by moving them
10
to a low resource requirement
period.
5

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
PROJECT DURATION

No. of Men Target

19
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

continuation
TIP

For the first four (4) days of activity, there are 40


men and to bring this down to a level of 30 men,
one of the starting activities will be delayed.

The FLOAT STATUS of the four (4) activities involved


are as follows:

Activity A : 6 FF (EF of A and ES)


Activity B : 0 FF
Activity E : 7 FF (EF of E and ES)
Activity C : Critical

Activity has no FF, hence, will not be moved


unless there is no more alternative.

If Activity E will be delayed by 4 days, the


utilization of manpower for the first 4 days will be
25 men only (Still lower than 30 men constant 4

manpower needed)

SAMPLE TIME-SCALED
NETWORK DIAGRAM

20
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

continuation
At 4 days:
OPTION 1: Delay Activity E for 4 days
SHOWN IN THE FIGURE:

ACTIVITIES THAT WILL CROSS THE 4-DAY MARK OF


NODE 2 ARE AS FOLLOWS:

ACTIVITY A: 10 MEN
ACTIVITY B: 10 MEN
ACTIVITY C: 5 MEN
ACTIVITY E: 15 MEN

TOTAL = 25 MEN

OPTION 2: Delay Activity A for 4 days

ACTIVITIES THAT WILL CROSS THE 4-DAY MARK OF


NODE 2 ARE AS FOLLOWS:

ACTIVITY A: 10 MEN
ACTIVITY B: 10 MEN
ACTIVITY C: 5 MEN
ACTIVITY E: 15 MEN 4

TOTAL = 30 MEN
SAMPLE TIME-SCALED
NETWORK DIAGRAM
“OPTION 2 IS THE MOST IDEAL”

21
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

continuation
At 5 days:
The 5th day has a manpower requirement of 45.
By further analysis, we have the following
alternatives:

A. Delay Activity A by one more day


B. Delay Activity D by one day
C. Stop Activity D

 Option B: Not logical because men in this


activity are not yet working
 Option C: Not advisable because men in this
activity are already working

If we choose Option A:
35 Men will be required for the 5th day.
BUT if we choose Option B, it will satisfy the level of
manpower of 30 MEN (this is somehow
recommended to satisfy the equation)

SAMPLE TIME-SCALED
NETWORK DIAGRAM

22
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

continuation

The graph shows the partially leveled TIME SCALED NETWORK AND MANPOWER LOADING
schedule. 70

From the 8th day to the 15th day, the


60
manpower requirements exceed 30 men.
50

BUT!!!

MANPOWER
40

“It is not possible to bet a completely


leveled schedule for a real project” 30

20
The problem would be complicated if there
is more than one resource that has to be 10
leveled. It is practical to have a gradual
build-up in work force followed by an 0
equally tapering drop at the end of the 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
project. PROJECT DURATION

23
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING

continuation

OTHER OPTION:

You may plot this using MS EXCEL to get an instant summary of total manpower during the project duration

24

You might also like