Professional Documents
Culture Documents
Employer :
Engineer :
Contractor :
DEDUCTION FOR FILLING IMPORTED SOIL ( GRADE SLAB INCLUDING HARD CORE)
GRAD SLAB
SI NO DRW NO REV LOCATION DESCRIPTION NO LENGTH WIDTH DEPTH PERIMETER HOR. AREA QUERY ANSWER
CONC.
A DEDUCTION FOR FILLING IMPORTED SOIL ( GRADE SLAB INCLUDING HARD CORE) - - 68.00
GRID A1-D1-D4-B'4-
1 S-BN-11.1-1111 A 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 0.02 73.35 269.84 5.40
B'4'-A4'
2 -do- GRID C4-B'5 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 1.80 7.70 0.02 19.00 13.86 0.28
GRID D4-D6-A6-A4'-
3 -do- 200mm THK GRADE SLAB FROM -0.770 TO -0.450 (AT -0.370 LVL) 1.00 0.32 77.25 193.75 62.00
B'4'-B'5-C5-C4
4 -do- ENTRANCE FRONT 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 2.56 1.51 0.02 5.57 3.85 0.08
5 -do- ENTRANCE REAR 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 2.31 1.21 0.02 4.72 2.78 0.06
6 -do- DCT COLUMN - C4 (4.00) 0.75 0.20 0.02 7.60 (0.60) (0.01)
50mm thk
SI NO DRW NO REV LOCATION DESCRIPTION NO LENGTH WIDTH DEPTH HOR. AREA CONC. ADD/DEDUCTION FOR FORMWORK QUERY ANSWER
BLINDING
(m) (m) (m) (m²) (m³) DESCRIPTION NO L W H QTY QTY
3 -do- EXTERNAL GB2 1.00 5.45 0.54 0.05 2.94 0.15 ADD GRID-A4 1.00 0.75 0.29 0.05 0.01 0.16
4 -do- EXTERNAL GB2 1.00 2.30 0.54 0.05 1.24 0.06 ADD GRID-A4' 1.00 0.20 0.19 0.05 0.00 0.06
5 -do- EXTERNAL GB2 1.00 5.20 0.54 0.05 2.81 0.14 ADD GRID-A5 1.00 0.20 0.29 0.05 0.00 0.14
6 -do- EXTERNAL GB2 1.00 7.00 0.54 0.05 3.78 0.19 ADD GRID-A6 1.00 0.49 0.29 0.05 0.01 0.20
7 -do- EXTERNAL GB2 1.00 5.28 0.54 0.05 2.85 0.14 ADD GRID-A6 1.00 0.75 0.29 0.05 0.01 0.15
8 -do- EXTERNAL GB2 1.00 2.53 0.54 0.05 1.36 0.07 ADD GRID-B6 & C6 2.00 0.75 0.29 0.05 0.02 0.09
9 -do- EXTERNAL GB1 1.00 5.00 0.54 0.05 2.70 0.14 ADD GRID-D6 1.00 0.75 0.29 0.05 0.01 0.15
10 -do- EXTERNAL GB2 1.00 5.28 0.54 0.05 2.85 0.14 ADD GRID-A1 1.00 0.75 0.29 0.05 0.01 0.15
11 -do- EXTERNAL GB2 1.00 2.53 0.54 0.05 1.36 0.07 ADD GRID-B1 & C1 2.00 0.75 0.29 0.05 0.02 0.09
12 -do- EXTERNAL GB1 1.00 5.00 0.54 0.05 2.70 0.14 ADD GRID-D1 1.00 0.75 0.29 0.05 0.01 0.15
13 -do- EXTERNAL GB1 1.00 5.73 0.54 0.05 3.09 0.15 ADD GRID-D1 1.00 0.49 0.29 0.05 0.01 0.16
14 -do- EXTERNAL GB2 1.00 3.45 0.54 0.05 1.86 0.09 ADD GRID-D2 & D3 2.00 0.75 0.29 0.05 0.02 0.11
15 -do- EXTERNAL GB2 1.00 2.98 0.54 0.05 1.61 0.08 ADD GRID-D3' 1.00 0.20 0.29 0.05 0.00 0.08
16 -do- EXTERNAL GB2 1.00 2.55 0.54 0.05 1.38 0.07 ADD GRID-D4 1.00 0.20 0.29 0.05 0.00 0.07
17 -do- EXTERNAL GB2 1.00 7.70 0.54 0.05 4.16 0.21 ADD GRID-D5 1.00 0.20 0.29 0.05 0.00 0.21
18 -do- EXTERNAL GB2 1.00 7.00 0.54 0.05 3.78 0.19 ADD GRID-D6 1.00 0.49 0.29 0.05 0.01 0.20
19 -do- INTERNAL GB4 1.00 2.53 0.30 0.05 0.76 0.04 0.04
20 -do- INTERNAL GB3 1.00 5.00 0.30 0.05 1.50 0.08 0.08
21 -do- INTERNAL GB3 1.00 7.10 0.30 0.05 2.13 0.11 0.11
22 -do- INTERNAL GB3 1.00 2.53 0.30 0.05 0.76 0.04 0.04
23 -do- INTERNAL GB3 1.00 7.70 0.30 0.05 2.31 0.12 0.12
24 -do- INTERNAL GB3 1.00 7.70 0.30 0.05 2.31 0.12 0.12
25 -do- EXTERNAL DDT RECESS (23.00) 0.80 0.10 0.05 (0.09) (0.09)
26 -do- EXTERNAL DDT RECESS (5.00) 0.50 0.10 0.05 (0.01) (0.01)
27 S-BN-11.1-1111 A SECTION 3-3 STEPS-FRONT 1.00 2.56 1.00 0.05 2.56 0.13 0.13
28 -do- SECTION 3-3 STEPS-REAR 1.00 2.31 1.00 0.05 2.31 0.12 0.12
29 S-BN-11.1-1111 A SECTION 4-4 RAMP 1.00 6.90 1.61 0.05 11.07 0.55 0.55
30 S-BN-11.1-1111 A SECTION 4-4 BW AT ENTRANCE FRONT 2.00 2.61 0.54 0.05 2.81 0.14 DDT C3 (2.00) 0.45 0.25 0.05 (0.01) 0.13
31 -do- SECTION 4-4 BW AT ENTRANCE REAR 1.00 2.41 0.54 0.05 1.30 0.06 DDT C3 (1.00) 0.45 0.25 0.05 (0.01) 0.06
32 -do- SECTION 4-4 BW AT ENTRANCE REAR 1.00 2.41 0.54 0.05 1.30 0.06 DDT C3 (1.00) 0.45 0.25 0.05 (0.01) 0.06
33 -do- SECTION 4-4 DDT RAMP (1.00) 1.61 0.05 0.05 (0.00) (0.00)
TOTAL
SI NO DRW NO REV LOCATION DESCRIPTION NO LENGTH WIDTH DEPTH HOR. AREA ADD/DEDUCTION QUERY ANSWER
AREA
(m) (m) (m) (m²) DESCRIPTION NO L W H QTY (m²)
9 -do- EXTERNAL GB2 1.00 2.30 0.54 1.24 ADD GRID-A4' 1.00 0.20 0.19 0.04 1.28
10 -do- EXTERNAL GB2 1.00 5.20 0.54 2.81 ADD GRID-A5 1.00 0.20 0.29 0.06 2.87
11 -do- EXTERNAL GB2 1.00 7.00 0.54 3.78 ADD GRID-A6 1.00 0.49 0.29 0.14 3.92
12 -do- EXTERNAL GB2 1.00 5.28 0.54 2.85 ADD GRID-A6 1.00 0.75 0.29 0.22 3.07
ADD GRID-B6 &
13 -do- EXTERNAL GB2 1.00 2.53 0.54 1.36 2.00 0.75 0.29 0.43 1.80
C6
14 -do- EXTERNAL GB1 1.00 5.00 0.54 2.70 ADD GRID-D6 1.00 0.75 0.29 0.22 2.92
15 -do- EXTERNAL GB2 1.00 5.28 0.54 2.85 ADD GRID-A1 1.00 0.75 0.29 0.22 3.07
ADD GRID-B1 &
16 -do- EXTERNAL GB2 1.00 2.53 0.54 1.36 2.00 0.75 0.29 0.43 1.80
C1
17 -do- EXTERNAL GB1 1.00 5.00 0.54 2.70 ADD GRID-D1 1.00 0.75 0.29 0.22 2.92
18 -do- EXTERNAL GB1 1.00 5.73 0.54 3.09 ADD GRID-D1 1.00 0.49 0.29 0.14 3.23
ADD GRID-D2 &
19 -do- EXTERNAL GB2 1.00 3.45 0.54 1.86 2.00 0.75 0.29 0.43 2.30
D3
20 -do- EXTERNAL GB2 1.00 2.98 0.54 1.61 ADD GRID-D3' 1.00 0.20 0.29 0.06 1.66
21 -do- EXTERNAL GB2 1.00 2.55 0.54 1.38 ADD GRID-D4 1.00 0.20 0.29 0.06 1.44
22 -do- EXTERNAL GB2 1.00 7.70 0.54 4.16 ADD GRID-D5 1.00 0.20 0.29 0.06 4.22
23 -do- EXTERNAL GB2 1.00 7.00 0.54 3.78 ADD GRID-D6 1.00 0.49 0.29 0.14 3.92
36 S-BN-11.1-1111 A SECTION 4-4 BLOCK WORK AT ENTRANCE FRONT 2.00 2.61 0.54 2.81 DDT C3 (2.00) 0.45 0.25 (0.23) 2.59
37 -do- SECTION 4-4 BLOCK WORK AT ENTRANCE REAR 1.00 2.41 0.54 1.30 DDT C3 (1.00) 0.45 0.25 (0.11) 1.19
38 -do- SECTION 4-4 BLOCK WORK AT ENTRANCE REAR 1.00 2.41 0.54 1.30 DDT C3 (1.00) 0.45 0.25 (0.11) 1.19
39 -do- SECTION 4-4 DDT RAMP (1.00) 1.61 0.05 (0.08) (0.08)
AFTER
SITE FORMATIO EXCAVATIO
SI NO DRW NO REV LOCATION DESCRIPTION SSL OGL NO LENGTH WIDTH DEPTH AREA QUERY ANSWER
CLEARANC N LVL N
E
(m) (m) (m) (m²) (m³)
=-0.870
SI NO DRW NO REV LOCATION DESCRIPTION SSL OGL FORMATION LVL NO LENGTH WIDTH DEPTH AREA VOLUME QUERY ANSWER
A Carefully demolished the existing shanties and cart away the debris away items 350,000.00
from site
B Carefully demolished existing retaining wall 300mm thick x 162 meter items 3,000,000.00
long x 6meter high.(292cu.m Approx.) and cart away the debris
C Ditto retaining wall base assume 500mm thick x 4000mm wide x items 3,500,000.00
162meter long (324cu.m Approx.) and cart away the debris
Pit excavation
Excavate pit for basement from ground level maximum depth not
B exceeding 10metres deep . 14,137 m3 1,083.00 15,310,371.00
G Extra over for filling ramp base in basement level 01 467 m3 5,000.00 2,335,000.00
Termite treatmment
J dieldrex 20" or other equal and approved anti-termite solution to sides 6,772 m2 142.00 961,624.00
and bottom of excavtions
K Keeping excavation free from general and ground water item 450,000.00
L Extra for cut and chase on pile cap (600mm & 700mm diamter) to
accomodate pile cap 800mm deep 821 nr. 7,500.00 6,157,500.00
To collection : 81,683,612.00
E IN - SITU CONCRETE
Pile cap
D generally; 800 - 1600mm thick 1,672 m3 48,100.00 80,423,200.00
Columns stud
E generally (rectangular/square) 42 m3 48,100.00 2,020,200.00
Beds
G Level 01 basement slabs thickness 150-450mm thick 728 m3 48,100.00 35,016,800.00
150mm Topping
P Basememt floor slab (level 01) 633 m3 48,100.00 30,447,300.00
To collection : 195,291,820.00
150mm Topping
C Basememt floor slab (level 02) 633 m3 48,100.00 30,447,300.00
Beam
D Level 01 (basement ) 271 m3 48,100.00 13,035,100.00
Ramp
Ramp (4nr)
Slopping ramp
H Level 01-Level 02 47 cu.m 48,100.00 2,260,700.00
Ramp Beam
K Level 01-Level 02 15 cu.m 48,100.00 721,500.00
Driveway ramp/bridge
Slopping ramp
M Level 01-Level 02 62 cu.m 48,100.00 2,982,200.00
Ramp/bridge Beam
P Level 01-Level 02 20 cu.m 48,100.00 962,000.00
S Retaining wall 300mm thick (6000mm x 300mm thick) 621 cu.m 48,100.00 29,870,100.00
To collection : 129,292,800.00
Staircase in basement
Landing
A generally in landing (level 01-level 02) 1 cu.m 48,100.00 48,100.00
Steps
E generally (Level 01- Level 02) 1 cu.m 48,100.00 48,100.00
Landing beams
G generally (Level 01- Level 02) 1 cu.m 48,100.00 48,100.00
Columns stud
K Vertical sides of column stud(rectangular/Square) 350 m2 4,000.00 1,400,000.00
To collection : 43,290,200.00
Beam
C Sides and soffit of beam (level 01) 1,974 m2 4,000.00 7,896,000.00
G Vertical sides of lift wall (level 01 -Level 02) 350 m2 4,000.00 1,400,000.00
H Vertical sides of lift wall (level 02 -Level 03) 350 m2 4,000.00 1,400,000.00
Ramp
J Sides and soffit of ramp (level 01-level 02) 253 m2 4,000.00 1,012,000.00
K Sides and soffit of ramp (level 02-level 03) 253 m2 4,000.00 1,012,000.00
Ramp beam
L Sides and soffit of ramp (level 01-level 02) 161 m2 4,000.00 644,000.00
M Sides and soffit of ramp (level 02-level 03) 161 m2 4,000.00 644,000.00
Driveway ramp/bridge
Slopping ramp
N Sides and Soffit of slopping ramp (Level 01 - Level 02) 372 m2 4,000.00 1,488,000.00
P Sides and Soffit of slopping ramp (Level 01 - Level 02) 217 m2 4,000.00 868,000.00
Ramp beam
R Sides and soffit of ramp (level 02-level 03) 139 m2 4,000.00 556,000.00
To collection : 67,146,000.00
Staircase
A 4,000.00 36,000.00
slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m 9 m2
Pile Cap
G H12 0.87 t 710,000.00 617,700.00
Columns
To collection : 155,307,200.00
Column stud
A H10 4.15 t 710,000.00 2,946,500.00
To collection : 226,376,400.00
Lift base(Provisional)
N H12 6.30 t 710,000.00 4,473,000.00
To collection : 110,937,500.00
Driveway ramp/bridge
Level 01-Level 02
L H12 2.13 t 710,000.00 1,512,300.00
To collection : 31,978,400.00
Ramp/bridge Beam (level 02)
A H10 0.52 t 710,000.00 369,200.00
Expansion Joint
U Expansion joint 20mm thick ploystrene naked panel 614 m2 761.00 467,254.00
To collection : 265,689,679.00
To collection : 13,820,600.00
Collection
SUBSTRUCTURE.
150mm Topping
Waffle Ribs
Q 1st floor slab (level 03) 473 cu.m 48,100.00 22,751,300.00
To collection : 250,312,400.00
Beams
E 1st floor beam (level 03) 305 cu.m 48,100.00 14,670,500.00
K 1st floor (level 03) -2nd floor (level 04) 57 cu.m 48,100.00 2,741,700.00
L 2nd floor (level 04) - 3rd floor (level 05) 57 cu.m 48,100.00 2,741,700.00
M 3rd floor (level 05) -4th floor(level 06) 57 cu.m 48,100.00 2,741,700.00
N 4th floor (level 06) -5th floor( level 07) 57 cu.m 48,100.00 2,741,700.00
P 5th floor(level 08) -6th floor (level 09) 57 cu.m 48,100.00 2,741,700.00
Column
Square column type
A Ground floor (level 03) -1st floor (level 04) 68 cu.m 48,100.00 3,270,800.00
B 1st floor (level 04) -2nd floor (level 05) 68 cu.m 48,100.00 3,270,800.00
C 2nd floor (level 05) - 3rd floor (level 06) 67 cu.m 48,100.00 3,222,700.00
D 3rd floor (level 06) -4th floor(level 07) 65 cu.m 48,100.00 3,126,500.00
To collection : 202,404,800.00
A 4th floor (level 06) -5th floor( level 07) 65 cu.m 48,100.00 3,126,500.00
B 5th floor(level 07) -6th floor (level 08) 65 cu.m 48,100.00 3,126,500.00
C 6th floor(level 08) -Lower roof level (level 09) 65 cu.m 48,100.00 3,126,500.00
D Lower roof level (level 09)- Upper roof level 33 cu.m 48,100.00 1,587,300.00
Circular Column
E Ground floor (level 03) -1st floor (level 04) 45 cu.m 48,100.00 2,164,500.00
F 1st floor (level 04) -2nd floor (level 05) 30 cu.m 48,100.00 1,443,000.00
G 2nd floor (level 05) - 3rd floor (level 06) 29 cu.m 48,100.00 1,394,900.00
H 3rd floor (level 06) -4th floor(level 07) 29 cu.m 48,100.00 1,394,900.00
J 4th floor (level 06) -5th floor( level 07) 29 cu.m 48,100.00 1,394,900.00
L 6th floor(level 08) -Lower roof level (level 09) 20 cu.m 48,100.00 962,000.00
M Lower roof level (level 09)- Upper roof level 14 cu.m 48,100.00 673,400.00
Swimming pool
N Base 200mm thick 23 cu.m 48,100.00 1,106,300.00
Gallery
S Slab 200mm thick 90 cu.m 48,100.00 4,329,000.00
To collection : 32,419,400.00
To collection : 190,056,000.00
H 1st floor (level 03) -2nd floor (level 04) 351 m2 4,000.00 1,404,000.00
J 2nd floor (level 04) - 3rd floor (level 05) 351 m2 4,000.00 1,404,000.00
K 3rd floor (level 05) -4th floor(level 06) 351 m2 4,000.00 1,404,000.00
L 4th floor (level 06) -5th floor( level 07) 351 m2 4,000.00 1,404,000.00
M 5th floor(level 08) -6th floor (level 09) 351 m2 4,000.00 1,404,000.00
Column square
Vertical sides of column
P Ground floor (level 03) -1st floor (level 04) 659 m2 4,000.00 2,636,000.00
Q 1st floor (level 04) -2nd floor (level 05) 659 m2 4,000.00 2,636,000.00
R 2nd floor (level 05) - 3rd floor (level 06) 652 m2 4,000.00 2,608,000.00
S 3rd floor (level 06) -4th floor(level 07) 645 m2 4,000.00 2,580,000.00
T 4th floor (level 06) -5th floor( level 07) 644 m2 4,000.00 2,576,000.00
U 5th floor(level 07) -6th floor (level 08) 644 m2 4,000.00 2,576,000.00
V 6th floor(level 08) -Lower roof level (level 09) 644 m2 4,000.00 2,576,000.00
W Lower roof level (level 09)- Upper roof level 374 m2 4,000.00 1,496,000.00
To collection : 99,924,000.00
Circular column
A Ground floor (level 03) -1st floor (level 04) 295 m2 4,000.00 1,180,000.00
B 1st floor (level 04) -2nd floor (level 05) 239 m2 4,000.00 956,000.00
C 2nd floor (level 05) - 3rd floor (level 06) 234 m2 4,000.00 936,000.00
D 3rd floor (level 06) -4th floor(level 07) 234 m2 4,000.00 936,000.00
E 4th floor (level 06) -5th floor( level 07) 234 m2 4,000.00 936,000.00
F 5th floor(level 07) -6th floor (level 08) 234 m2 4,000.00 936,000.00
G 6th floor(level 08) -Lower roof level (level 09) 191 m2 4,000.00 764,000.00
H Lower roof level (level 09)- Upper roof level 147 m2 4,000.00 588,000.00
T m 1,000.00 51,000.00
Ditto edges of swimming pool base not exceeding 250mm wide 51
Gallery formwork
V Soffit of the gallery slab 450 m2 4,000.00 1,800,000.00
Beam
1st floor beam (Level 03)
J H10 13.06 t 710,000.00 9,272,600.00
To collection : 121,069,200.00
To collection : 158,784,400.00
Column
Ground floor (level 03) -1st floor (level 04)
F H10 8.54 t 710,000.00 6,063,400.00
To collection : 131,534,600.00
Lift shaft
Ground floor (level 03) -1st floor (level 04)
N H12 2.13 t 710,000.00 1,512,300.00
Swimming pool
In Swimming pool wall
E H12 0.73 t 710,000.00 518,300.00
Gallery
In gallery slab
L H12 8.23 t 710,000.00 5,843,300.00
In gallery beam
M H10 1.36 t 710,000.00 965,600.00
To collection : 43,789,300.00
Brc cont'd
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE
To collection : 4,858,100.00
Steps
A Level 03 - Level 04 5 m3 48,100.00 240,500.00
To collection : 3,811,500.00
Edges of landing
not exceeding 250mm wide
A Level 03 - Level 04 33 m 1,000.00 33,000.00
To collection : 1,482,600.00
E30: REINFORCEMENT FOR IN-SITU CONCRETE
Reinforcement bars; B.S.4449, hot rolled deformed high yield steel
(TMT-TIGER)
Straight and bent
Stairs
Level 03 - Level 04
A H12 1.80 t 710,000.00 1,278,000.00
Level 04 - Level 05
C H12 1.80 t 710,000.00 1,278,000.00
Level 06 - Level 07
E H12 1.80 t 710,000.00 1,278,000.00
Level 07 - Level 08
G H12 1.10 t 710,000.00 781,000.00
Level 08 - Level 09
J H12 1.10 t 710,000.00 781,000.00
Level 09 - Level 10
L H12 1.10 t 710,000.00 781,000.00
To collection : 790,308.00
Landing
A Level 03 - Level 04 14 m2 15,036.00 210,504.00
Skirting on wall
height 100mm
G Level 03 - Level 04 198 m 1,503.60 297,712.80
M20: PLASTERED/RENDERED
To collection : 7,866,532.80
Slopping soffit of stairs
slope exceeding 15 degrees
A Level 03 - Level 04 71 m2 1,500.00 106,500.00
To collection : 1,213,625.00
Raking string of staircase
width not exceeding 375mm
A Level 03 - Level 04 40 m 234.38 9,375.00
To collection : 113,750.00
To collection : 809,812.50
Collection
STAIRCASE.
Page 2/26 4,858,100.00
E IN - SITU CONCRETE
A lower roof beam not exceeding 600mm deep 203 m3 48,100.00 9,764,300.00
B Upper roof beam not exceeding 600mm deep 102 m3 48,100.00 4,906,200.00
To collection : 76,733,000.00
Parapet wall
D m2 5,731.00 8,298,488.00
225mm blockwall filled with concrete (1: 4:8-20mm aggregate) 1,448
M Precast concrete copping 300mm wide x 50mm thick 180 m 1,500.00 270,000.00
70,174,188.00
Rafters
A 65 x 65 x 6mm thick (Top and bottom members) 585 m 10,500.00 6,142,500.00
Zed Purlins
B 150 x 50 x 2mm thick Zed purlins @ 909 ctrs 1441 m 7,850.00 11,311,850.00
Internal Members
C 65 x 65 x 6mm thick (Internal members) 506 m 6,800.00 3,440,800.00
Bracing
D 70 x 70 x 6mm L bracing 462 m 2,550.00 1,178,100.00
Antisag Rods
E 12mmØ Antisag rods 252 m 500.00 126,000.00
Connecting Plates
G 450 x 300 x 20mm thick mild steel plate on end trusses 30 nr 6,800.00 204,000.00
45,424,225.00
STRUCTURAL STEEL WORK (UPPER ROOF TRUSSES)
Zed Purlins
A 150 x 50 x 2mm thick Zed purlins @ 909 ctrs 2160 m 7,850.00 16,956,000.00
Antisag Rods
B 12mmØ Antisag rods 384 m 500.00 192,000.00
Angle cleat
C 125 x 75 x 8mm thick angle cleat on purlins 504 nr 6,800.00 3,427,200.00
H to falls and crossfalls and to slopes not exceeding 15 degrees from 2,302 m2 3,500.00 8,057,000.00
horizontal
49,816,450.00
Collection
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE
Lintel
Lintel
generally in basement floor (level 01)
A H16 0.70 t 710,000.00 497,000.00
To collection : 29,751,600.00
MASONRY
F10: BLOCK WALLING
Stone dust hollow blockwork, bedded and jointed in cement and sand
mortar
230mm Walls
230mm thick; stretcher bond; regular
G generally in basement floor (level 01) 577 m2 5,000.00 2,885,000.00
Gable ends
R 230mm thick; stretcher bond; regular in gable 263 m2 5,000.00 1,315,000.00
150mm wall
150mm thick; stretcher bond; regular
S generally in basement floor (level 01) 601 m2 4,250.00 2,554,250.00
To collection : 114,157,950.00
Expansion Joint
H Expansion joint 20mm thick ploystrene naked panel 2,046 m2 761.00 1,557,006.00
To collection : 69,293,506.00
Collection
(i) Timber flush door and steel frames, anodised aluminium doors and
windows.
(ii) The contractor is however referred to the Architectural doors and
windows schedule for details and scope of work.
L10: WINDOWS
SUPPLY AND FIX the following aluminium or approved equal best quality
purpose made. EBM system on sliding window . EBM curtain wall with
6mm/10mm clear glass glazed . including cutting and pinning lugs to
blockwork or concrete and pointing in mastic.
Level 02
B Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00
Level 03
C Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00
Level 04
E Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00
Level 05
G Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00
Level 06
J Aluminium sliding window 900mm x 1500mm high 27 nr 164,062.00 4,429,674.00
Level 07
L Aluminium sliding window 900mm x 1500mm high 27 nr 164,062.00 4,429,674.00
To collection : 58,900,408.40
Level 08
D Aluminium sliding window 900mm x 1500mm high 27 nr 164,062.00 4,429,674.00
Level 09
K Aluminium sliding window 900mm x 1500mm high 19 nr 164,062.00 3,117,178.00
Level 04
S 2700mm x 1500mm high 50 nr 961,875.00 48,093,750.00
Level 05
T 2700mm x 1500mm high 50 nr 961,875.00 48,093,750.00
Level 06
U 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00
Level 07
V 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00
To collection : 264,236,556.60
Level 08
A 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00
Level 09
C 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00
Level 04
F Front shop glass façade size 2700mm x 1500mm high 54 nr 639,900.00 34,554,600.00
Level 05
G Front shop glass façade size 2700mm x 1500mm high 54 nr 639,900.00 34,554,600.00
Back Elevation
N Size 6400mm x 16000mm high 3 nr 8,704,000.00 26,112,000.00
Subframe(window only)
Q 40mm x 20mm aluminium subframe 6,478 m 1,600.00 10,364,800.00
To collection : 355,552,100.00
Burglar Proofing
Level 01
A Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00
Level 02
B Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00
Level 03
C Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00
Level 04
E Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00
Level 05
G Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00
Level 06
J Size 900mm x 1500mm high 27 nr 11,475.00 309,825.00
Level 07
L Size 900mm x 1500mm high 27 nr 11,475.00 309,825.00
Level 08
A Size 900mm x 1500mm high 27 nr 11,475.00 309,825.00
Level 09
G Size 900mm x 1500mm high 19 nr 11,475.00 218,025.00
Level 04
P 2700mm x 1500mm high 50 nr 34,425.00 1,721,250.00
Level 05
Q 2700mm x 1500mm high 50 nr 34,425.00 1,721,250.00
Level 06
R 2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00
Level 07
T 2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00
Level 08
2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00
To collection : 11,945,730.00
Level 09
A 2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00
Shop front
Level 03
C Size 2700mm x 1500mm high 38 nr 34,425.00 1,308,150.00
Level 04
D Size 2700mm x 1500mm high 54 nr 34,425.00 1,858,950.00
Level 05
E Size 2700mm x 1500mm high 54 nr 34,425.00 1,858,950.00
Back Elevation
L Size 6400mm x 16000mm high 3 nr 870,400.00 2,611,200.00
Ready made door complete with lock ,frame & architrave and stopper
Solid core, single leaf; single swing; solid door, factory finish with
hardwood lipping all edges and polished door frames and all sprayed with
approved quality varnish paint
Level 01
P 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
To collection : 29,109,700.00
Level 02
A Size 750mm x 2100mm high 20 nr 175,000.00 3,500,000.00
B 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
Level 03
C Size 750mm x 2100mm high 66 nr 175,000.00 11,550,000.00
D 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
Level 04
E Size 750mm x 2100mm high 74 nr 175,000.00 12,950,000.00
F 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
Level 05
G Size 750mm x 2100mm high 74 nr 175,000.00 12,950,000.00
H 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
Level 06
J Size 750mm x 2100mm high 48 nr 175,000.00 8,400,000.00
K 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
Level 07
M Size 750mm x 2100mm high 48 nr 175,000.00 8,400,000.00
N 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
Level 08
Q Size 750mm x 2100mm high 48 nr 175,000.00 8,400,000.00
R 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
Level 09
U 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00
To collection : 142,800,000.00
Aluminium Swing Door (EBM profile system with 10mm clear glass)
Level 03
A Size 900mm x 2100mm high 34 nr 156,000.00 5,304,000.00
Level 04
B Size 900mm x 2100mm high 50 nr 156,000.00 7,800,000.00
Level 05
C Size 900mm x 2100mm high 50 nr 156,000.00 7,800,000.00
Aluminium sliding door (EBM syytem with 10mm glazed clear glass)
Level 03
D Size 2700mm x 2100mm high 20 nr 239,318.16 4,786,363.20
Level 04
E Size 2700mm x 2100mm high 20 nr 239,318.16 4,786,363.20
Level 05
F Size 2700mm x 2100mm high 20 nr 239,318.16 4,786,363.20
Level 06
G Size 1350mm x 2100mm high 33 nr 119,659.08 3,948,749.64
Level 07
H Size 1350mm x 2100mm high 33 nr 120,000.00 3,960,000.00
Level 08
J Size 1350mm x 2100mm high 29 nr 120,000.00 3,480,000.00
Level 09
K Size 1350mm x 2100mm high 14 nr 120,000.00 1,680,000.00
Name plates
' TOILET' sign engraved on stainless steel plate size 350 x 100; Ref IRXX;
L finish: SS 523 nr 9,000.00 4,707,000.00
N Shop Numbers and other spaces sign engraved on stainless plate 134 nr 9,000.00 1,206,000.00
To collection : 57,133,839.24
Collection
Wardrobe
Fitted wardrobe cabinet comprising 18mm thick laminated door 2mm
thick edging complete with matching screws,glues and necessary
accessories
Level 06
A 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00
Level 07
E 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00
Level 08
J 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00
level 09
N 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00
To collection : 349,370,000.00
Store shelves
Level 06
A 1600mm Long x 600mm wide x 2500mm high (3 steps) 5 nr 200,000.00 1,000,000.00
Level 07
B 1600mm Long x 600mm wide x 2500mm high (3 steps) 5 nr 200,000.00 1,000,000.00
Level 08
C 1600mm Long x 600mm wide x 2500mm high (3 steps) 1 nr 200,000.00 200,000.00
Level 09
D 1600mm Long x 600mm wide x 2500mm high (3 steps) 1 nr 200,000.00 200,000.00
Kitchen cabinet
Level 06
E L-Shaped 5600mm Long x 600mm wide x 900mm high 5 nr 1,411,200.00 7,056,000.00
Level 07
F L-Shaped 5600mm Long x 600mm wide x 900mm high 5 nr 1,411,200.00 7,056,000.00
Level 08
G L-Shaped 5600mm Long x 600mm wide x 900mm high 1 nr 1,411,200.00 1,411,200.00
Level 09
H L-Shaped 5600mm Long x 600mm wide x 900mm high 1 nr 1,411,200.00 1,411,200.00
Level 07
Level 08
N 2100mm Long x 600mm wide x 1500mm high 22 nr 630,000.00 13,860,000.00
Level 09
Q 2100mm Long x 600mm wide x 1500mm high 22 nr 630,000.00 13,860,000.00
To collection : 100,814,400.00
Aluminium duct cover grille
Level 01
A Size 450mm x 3200mm high 4 nr 50,400.00 201,600.00
Level 02
B Size 450mm x 3200mm high 4 nr 50,400.00 201,600.00
Level 03
C Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00
Level 04
E Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00
Level 05
G Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00
Level 06
J Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00
Level 07
L Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00
Level 09
Q Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00
To collection : 29,833,650.00
Balcony handrailings
Frameless glass railing with 10mm tampered glass fixed with leg spider,
glass connector and all necessary accessories
Alucobond cladding
Aluminium Composite Material consisting of two aluminium
H cover sheets with fireretardant or non combustible mineral filled 9,244 m2 35,000.00 323,540,000.00
core
To collection : 475,565,000.00
COLLECTION
Page/55 349,370,000.00
Page/56 100,814,400.00
Page/57 29,833,650.00
Page/58 475,565,000.00
SURFACE FINISHES
INFORMATION
level 01
A level and to falls only not exceeding 15 degrees from horizontal with anti 4,472 m2 5,000.00 22,360,000.00
dust additives
level 02
B level and to falls only not exceeding 15 degrees from horizontal with anti 4,472 m2 5,000.00 22,360,000.00
dust additives
C level and to falls only not exceeding 15 degrees from horizontal to 201 m2 3,000.00 603,000.00
received tiles
level 02
D level and to falls only not exceeding 15 degrees from horizontal to 201 m2 3,000.00 603,000.00
received tiles
level 03
E level and to falls only not exceeding 15 degrees from horizontal to 2,294 m2 3,000.00 6,882,000.00
received tiles
level 04
F level and to falls only not exceeding 15 degrees from horizontal to 3,056 m2 3,000.00 9,168,000.00
received tiles
level 05
G level and to falls only not exceeding 15 degrees from horizontal to 3,079 m2 3,000.00 9,237,000.00
received tiles
level 06
H level and to falls only not exceeding 15 degrees from horizontal to 3,050 m2 3,000.00 9,150,000.00
received tiles
To collection : 80,363,000.00
level 07
A level and to falls only not exceeding 15 degrees from horizontal to 3,001 m2 3,000.00 9,003,000.00
received tiles
level 08
B level and to falls only not exceeding 15 degrees from horizontal to 2,997 m2 3,000.00 8,991,000.00
received tiles
level 09
C level and to falls only not exceeding 15 degrees from horizontal to 3,125 m2 3,000.00 9,375,000.00
received tiles
level 01
D height 100mm 402 m 150.00 60,300.00
level 02
E height 100mm 402 m 150.00 60,300.00
To collection : 188,215,600.00
M40: TILING
Unglazed vitrified floor tiles; 3 joints systematic layout, bedding in
10mm cement mortar (1:3); including pointing.
450mm x 450mm x 8mm thick to floors on cement and sand base; level
to falls only not exceeding 15 degrees from horizontal
To collection : 1,269,038.40
Collection
Floor Finishing
(i) Walls finishings with and including other associated works but
excluding painting which is measured in a separate element.
(ii) The Contractor is hereby referred to
the various Architect's location drawings in relation to this section for the
nature and content of the work to be executed.
M20: PLASTERED/RENDERED
D width not exceeding 300mm; isolated columns square 83.00 m2 1,500.00 124,500.00
J width not exceeding 300mm; isolated columns square 166.00 m2 1,500.00 249,000.00
3rd floor
To collection : 15,938,400.00
Pent floor
A Pent floor wall width exceeding 300mm 679.00 m2 1,500.00 1,018,500.00
1st floor
F patterned, width exceeding 300mm 176.00 m2 7,750.00 1,364,000.00
2nd floor
G patterned, width exceeding 300mm 176.00 m2 7,750.00 1,364,000.00
3rd floor
H Patterned, width exceeding 300mm 1,200.00 m2 7,750.00 9,300,000.00
EXTERNAL WORK
12mm work to walls on concrete base or blockwork
Ground Floor
M width exceeding 300mm 741.00 m2 1,500.00 1,111,500.00
Pent floor
T width exceeding 300mm 589.00 m2 1,500.00 883,500.00
To collection : 20,773,450.00
Lift wall entrance façade
A 15mm thick granite wall fixed to entrance of lift wall façade 230.00 m2 15,036.00 3,458,280.00
D 50mm x 2mm thick hollow steel pipe decoration on façade painted with m 1,700.00 132,600.00
gloss paint 78.00
To collection : 19,391,564.00
Collection
WALL FINISHING
INFORMATION
(i) Ceiling finishings with and including other associated works but
excluding painting which is measured in a separate Element
(ii) The Contractor is hereby referred to the various Architect's location
drawings in relation to this section for the nature and content of the work
to be executed.
SURFACE FINISHES
B over 300mm wide; internal; as architectural details Pent floor 877.00 m2 5,250.00 4,604,250.00
D over 300mm wide; internal; as architectural details 1st floor 2,275.00 m2 8,562.00 19,478,550.00
E over 300mm wide; internal; as architectural details 2nd floor 2,275.00 m2 8,562.00 19,478,550.00
C width not exceeding 300mm; isolated columns square 83.00 m2 625.00 51,875.00
3rd floor
K Third floor wall width exceeding 300mm 3,579.00 m2 625.00 2,236,875.00
Pent floor
Ceiling screeding
Wall screeding (I-nox)
T over 300mm wide; internal; as architectural details 3rd floor 1,579.00 m2 625.00 986,875.00
U over 300mm wide; internal; as architectural details Pent floor 877.00 m2 625.00 548,125.00
To collection : 7,383,375.00
Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
C width not exceeding 300mm; isolated columns square 83.00 m2 1,312.50 108,937.50
3rd floor
K 1st floor-5th floor wall width exceeding 300mm 3,579.00 m2 1,312.50 4,697,437.50
Pent floor
P Pent floor wall width exceeding 300mm 679.00 m2 1,312.50 891,187.50
S width not exceeding 300mm; isolated columns round 33.00 m2 1,312.50 43,312.50
Ceilings painting
U over 300mm wide; internal; as architectural details Pent floor 877.00 m2 1,312.50 1,151,062.50
To collection : 15,505,087.50
Externally
Wall screeding ( x-nox exterior)
Ground Floor
A width exceeding 300mm 741.00 m2 1,000.00 741,000.00
3rd floor
E width exceeding 300mm 654.00 m2 1,000.00 654,000.00
Pent floor
G width exceeding 300mm 589.00 m2 1,000.00 589,000.00
Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
Ground Floor
3rd floor
L width exceeding 300mm 654.00 m2 1,312.50 858,375.00
Pent floor
N width exceeding 300mm 589.00 m2 1,312.50 773,062.50
Collection
DEMOLITION #REF!
SUBSTRUCTURE 1,320,814,211.00
STAIRCASES 58,372,404.30
136879.422
QTY L W H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
1st Basement floor Beams 6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222
BM 60 X 50 H04-17 1.00 40 40 0.60 0.50 12.00 64.00
BM 60 X 50 H17-21 1.00 11 11 0.60 0.50 3.30 17.60
BM 60X50 H1-22 1.00 62 62 0.60 0.50 18.60 99.20
BM60 X 50 H17-20 1.00 7 7 0.60 0.50 2.10 11.20
BM 60 X 50 H01-5 1.00 15 15 0.60 0.50 4.50 24.00
BM 60 X50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H07-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50H7-H15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H17-23 1.00 13 13 0.60 0.50 3.90 20.80
BM 60 X 50 H19-23 1.00 10 10 0.60 0.50 3.00 16.00
BM 60 X 50 H19-25 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60X50 V04-17 1.00 61 61 0.60 0.50 18.30 97.60
BM60X50V01-18 1.00 86 86 0.60 0.50 25.80 137.60
BM 60X50V01-4 1.00 16 16 0.60 0.50 4.80 25.60
BM 60X50V01-17 1.00 82 82 0.60 0.50 24.60 131.20
BM60X50 V01-17 1.00 82 82 0.60 0.50 24.60 131.20
BM 60X50 V01-17 1.00 82 82 0.60 0.50 24.60 131.20
BM 60 X50 V01-4 1.00 16 16 0.60 0.50 4.80 25.60
BM 60X50 V01-4 1.00 16 16 0.60 0.50 4.80 25.60
BM60X50 V04-17 1.00 61 61 0.60 0.50 18.30 97.60
BM60X50 V4-5 1.00 6 6 0.60 0.50 1.80 9.60
BM60 X50 V07-14 1.00 36 36 0.60 0.50 10.80 57.60
BM 2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM 2 20X50 1.00 4 4 0.20 0.50 0.40 4.80
BM 2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM2 20X50 1.00 4 4 0.20 0.50 0.40 4.80
BM 2 20 X50 1.00 4 4 0.20 0.50 0.40 4.80
BM 2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM2 20 X50 1.00 4 4 0.20 0.50 0.40 4.80
Cu.m Sq.m
#REF!
B1 60 X50 1.00 62 62 0.60 0.50 18.60 99.20
BM 1 60 X 50 1.00 11 11 0.60 0.50 3.30 17.60
BM 1 60 X 50 1.00 40 40 0.60 0.50 12.00 64.00
BM 150 X60 1.00 11 11 0.60 0.50 3.30 17.60
BM 1 50 X 60 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 50 X60 1.00 16 16 0.60 0.50 4.80 25.60
BM 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 50 X 60 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 60 X 50 1.00 20 20 0.60 0.50 6.00 32.00
BM 60 X 50 1.00 20 20 0.60 0.50 6.00 32.00
BM 50 X 60 1.00 20 20 0.60 0.50 6.00 32.00
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 60 X50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 50 X 60 1.00 16 16 0.60 0.50 4.80 25.60
B2 20 X 50 1 5.58 5.58 0.2 0.5 0.56 6.70
B2 20 X 50 1 4 4 0.2 0.5 0.40 4.80
B2 20 X 50 1 4 4 0.2 0.5 0.40 4.80
B2 20 X 50 1 5.58 5.58 0.2 0.5 0.56 6.70
363.16 105.12 573.39
ITEM DESCRIPTION UNIT QTY RATE DEL RATE
TO SITE FIXED
A AIR-CONDITIONING SYSTEM INSTALLATION
Split Units
1 Wall mounted split air-conditioing unit complete with installation
bracket, electrical cable and other installation accessories
Capacity: 9000 BTU Nr 165 FIX ONLY 12,000.00
Pipes
Light gauge annealed copper tubes in coils and rigid pipes to BS 2871.
Table Y for connection by means of autogenous welding.
Accessories
5 19mm Internal Diameter Insulation Tube (15mmThick) m 5541 477.00 95.40 572.40
6 16mm Internal Diameter Insulation Tube (19mmThick) m 5541 405.00 81.00 486.00
8 65mm Diammeter non-kink PVC Pipe Sleeve m 5076 1,035.00 207.00 1,242.00
Condensate Pipework
9 50mm m 1,460 981 196.2 1,177.20
TOTAL TO SUMMARY
SUBTOTAL
7.5% VAT
TOTAL
912,000.00
2,568,000.00
175,000.00
245,952.00
9,521,928.00
4,231,200.00
8,245,008.00
3,171,668.40
2,692,926.00
12,400,758.00
6,304,392.00
1,718,712
453,024
175,140
1,684,800.00
538,380.00
120,960.00
3,000,000.00
62,136,848.40
62,136,848.40
4,660,263.63
66,797,112.03
176
Prepared by Nazedees Borner Nig Ltd
PIPES
1 25mm m 2 1,196 239 2,870
Fittings
Elbow
3 25mm Dia Nr 4 420 84 2,016
Wallplate
5 20mm x 1/2" Nr 3 1,200 240 4,320
Equal Tee
6 25 x 25 x 25mm Nr 1 450 90 540
Reducing Tee
8 25 x 20 x 25mm Nr 1 450 90 540
Nipple
9 25mm X 1/2" male Nr 1 1,800 360 2,160
Sockets
10 25mm Nr 1 420 84 504
Valves
12 25mm Gate Valve Nr 1 9,000 1800 10,800
13 15mm Angle Valve with chrome cover plate Nr 3 3,500 700 12,600
MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot
177
Prepared by Nazedees Borner Nig Ltd
FITTINGS
Bends (90 Degree)
3 100mm Nr 1 1,385 277 1,662
TEES
7 100 x 100 x 100mm Nr 1 1,680 336 2,016
TRAPS
10 100mm Pan Connector Nr 1 2,000 400 2,400
Socket
12 100mm Nr 1 1,385 277 1,662
178
Prepared by Nazedees Borner Nig Ltd
COST COLLECTION
179
Prepared by Nazedees Borner Nig Ltd
180
Prepared by Nazedees Borner Nig Ltd
PIPES
1 25mm m 948 1,196 239 1,360,570
Fittings
Elbow
3 25mm Dia Nr 1,896 420 84 955,584
Wallplate
5 20mm x 1/2" Nr 1,422 1,200 240 2,047,680
Equal Tee
6 25 x 25 x 25mm Nr 474 450 90 255,960
Reducing Tee
8 25 x 20 x 25mm Nr 474 450 90 255,960
Nipple
9 25mm X 1/2" male Nr 474 1,800 360 1,023,840
Sockets
10 25mm Nr 474 420 84 238,896
Valves
12 25mm Gate Valve Nr 474 9,000 1800 5,119,200
13 15mm Angle Valve with chrome cover plate Nr 1,422 3,500 700 5,972,400
MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot
181
Prepared by Nazedees Borner Nig Ltd
FITTINGS
Bends (90 Degree)
3 100mm Nr 474 1,385 277 787,788
TEES
7 100 x 100 x 100mm Nr 474 1,680 336 955,584
TRAPS
10 100mm Pan Connector Nr 474 2,000 400 1,137,600
Socket
12 100mm Nr 474 1,385 277 787,788
182
Prepared by Nazedees Borner Nig Ltd
COST COLLECTION
183
BILL NR 6
- EXTERNAL PLUMBING
BILL #6
Nr 1 15,000,000.00 15,000,000.00
- SANITARY FIXTURE
BILL #2
SANITARY FIXTURE: All sanitary fixtures
shall be: AMITAGE SHANK or approved equal.
B.5 Hand Driers. Slieber Eltron or approved equal. Nr 252 27,000.00 2,700.00
BILL NR 3
Elbows
C.6 50mm diameter Nr 20 2,175.00 217.50
Gate valves
Tees
Sockets
Union
C.28 50mm diameter Nr 4 8,700.00 870.00
Nipple
Reducers
Non-return valves
C.41 50mm diameter Nr 2 8,700.00 870.00
Bib taps
Angle valves
Bib taps
Angle valves
Piping
Sockets
UPVC Y - Tees
Elbow
End plug
Bottle trap
BILL NR 5
Pipes
Tees
Elbow
Socket
Nipples
E.20 100mm diameter Nr 10 5,800.00 580.00
Gate valve
Union
Reducers
Landing valve
Hydrant
AMOUNT
157,125.00 76,991,250.00
133,650.00 65,488,500.00
170,775.00 12,295,800.00
89,100.00 4,633,200.00
29,700.00 7,484,400.00
15,444.00 3,891,888.00
5,940.00 2,910,600.00
222,750.00 30,071,250.00
96,525.00 13,030,875.00
37,125.00 18,191,250.00
220,000.00 220,000.00
S PIPES
1,871,100.00
3,814,965.00
2,095,632.00
1,015,740.00
1,675,080.00
47,850.00
115,797.00
391,604.40
324,901.50
383,597.50
36,366.00
51,040.00
41,470.00
12,760.00
31,900.00
159,500.00
574,200.00
390,775.00
95,700.00
133,980.00
AMOUNT
95,700.00
102,080.00
15,950.00
31,900.00
44,660.00
39,875.00
59,812.50
38,280.00
279,125.00
357,280.00
598,125.00
398,750.00
33,176.00
17,545.00
344,520.00
1,339,800.00
19,140.00
287,100.00
344,520.00
19,140.00
47,850.00
AMOUNT
7,975.00
44,660.00
4,083,750.00
1,993,750.00
7,975.00
33,495.00
4,455,000.00
1,722,600.00
622,050.00
7,018,000.00
2,392,500.00
86,130.00
797,500.00
358,875.00
1,516,845.00
421,080.00
861,300.00
119,625.00
601,425.00
222,750.00
135,575.00
95,700.00
442,612.50
by builder
165,000.00
AMOUNT
by builder
by builder
by builder
500,000.00
29,700.00 2,673,000.00
22,275.00 2,004,750.00
22,052,250.00
594,000.00
705,375.00
1,351,350.00
341,550.00
267,300.00
95,700.00
43,862.50
87,725.00
44,660.00
38,280.00
119,625.00
AMOUNT
95,700.00
71,775.00
56,144.00
27,753.00
63,800.00
510,400.00
717,750.00
430,650.00
356,400.00
57,420.00
25,520.00
76,560.00
79,750.00
51,040.00
297,000.00
519,750.00
534,600.00
AMOUNT
430,650.00
1,722,600.00
40,987,839.50
31
Prepared by Nazedees Borner Nig Ltd
PIPES
1 25mm m 2 1,196 239 2,870
Fittings
Elbow
3 25mm Dia Nr 4 420 84 2,016
Wallplate
5 20mm x 1/2" Nr 3 1,200 240 4,320
Equal Tee
6 25 x 25 x 25mm Nr 1 450 90 540
Reducing Tee
8 25 x 20 x 25mm Nr 1 450 90 540
Nipple
9 25mm X 1/2" male Nr 1 1,800 360 2,160
Sockets
10 25mm Nr 1 420 84 504
Valves
12 25mm Gate Valve Nr 1 9,000 1800 10,800
13 15mm Angle Valve with chrome cover plate Nr 3 3,500 700 12,600
MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot
32
Prepared by Nazedees Borner Nig Ltd
FITTINGS
Bends (90 Degree)
3 100mm Nr 1 1,385 277 1,662
TEES
7 100 x 100 x 100mm Nr 1 1,680 336 2,016
TRAPS
10 100mm Pan Connector Nr 1 2,000 400 2,400
Socket
12 100mm Nr 1 1,385 277 1,662
33
Prepared by Nazedees Borner Nig Ltd
COST COLLECTION
34
Prepared by Nazedees Borner Nig Ltd
35
Prepared by Nazedees Borner Nig Ltd
PIPES
1 25mm m 2 1,196 239 2,870
Fittings
Elbow
3 25mm Dia Nr 4 420 84 2,016
Wallplate
5 20mm x 1/2" Nr 3 1,200 240 4,320
Equal Tee
6 25 x 25 x 25mm Nr 1 450 90 540
Reducing Tee
8 25 x 20 x 25mm Nr 1 450 90 540
Nipple
9 25mm X 1/2" male Nr 1 1,800 360 2,160
Sockets
10 25mm Nr 1 420 84 504
Valves
12 25mm Gate Valve Nr 1 9,000 1800 10,800
13 15mm Angle Valve with chrome cover plate Nr 3 3,500 700 12,600
MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot
36
Prepared by Nazedees Borner Nig Ltd
FITTINGS
Bends (90 Degree)
3 100mm Nr 1 1,385 277 1,662
TEES
7 100 x 100 x 100mm Nr 1 1,680 336 2,016
TRAPS
10 100mm Pan Connector Nr 1 2,000 400 2,400
Socket
12 100mm Nr 1 1,385 277 1,662
37
Prepared by Nazedees Borner Nig Ltd
COST COLLECTION
38
ITEM DESCRIPTION UNIT QTY RATE DEL RATE
TO SITE FIXED
A AIR-CONDITIONING SYSTEM INSTALLATION
Split Units
1 Wall mounted split air-conditioing unit complete with installation
bracket, electrical cable and other installation accessories
Capacity: 9000 BTU Nr 2 FIX ONLY 12,000.00
CCP748M.BOQ Page 39
ITEM DESCRIPTION UNIT QTY RATE DEL RATE
TO SITE FIXED
SUB TOTAL C/B
Pipes
Light gauge annealed copper tubes in coils and rigid pipes to BS 2871.
Table Y for connection by means of autogenous welding.
Accessories
4 19mm Internal Diameter Insulation Tube (15mmThick) m 3400 477.00 95.40
ARMAFLEX
Condensate Pipework
8 32mm m 810 600.00 120
14 25mm Internal Diameter Insulation Tube for condensate with 19 m 1900 1,200.00 240.00
Armaflex insulation tube
TOTAL TO SUMMARY
CCP748M.BOQ Page 40
SUMMARY OF COST FOR MAIN BUILDING
SUBTOTAL
7.5% VAT
TOTAL
CCP748M.BOQ Page 41
24,000.00
72,000.00
3,264,000.00
3,360,000.00
CCP748M.BOQ Page 42
3,360,000.00
10,886,616.00
78,720.00
5,803,200.00
1,946,160.00
19,440.00
7,609,200.00
3,974,400.00
583,200
76,800
80,640
591,624.00
486,000.00
60,480.00
2,736,000.00
3,000,000.00
41,292,480.00
CCP748M.BOQ Page 43
41,292,480.00
41,292,480.0
41,292,480.00
3,096,936.00
44,389,416.00
CCP748M.BOQ Page 44
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT (N)
CONDITIONS OF CONTRACT
The Contractor will be deemed to have read each of the clauses in the
Conditions Of Contract And Contract Forms of which only the marginal
heading is stated below and he is to allow opposite to the number and title of
each clause carring a monetary value for carrying out the clause in its
entirety.
For convenience, only those provisions considered to have an obvious
financial effect are set out below and against each provision, the price shall
be inserted for
The Contractor shall include/ allow for complying in all respects with the Conditions
of Contract Clauses 1 to 20 as per FIDIC 99 Condition of Contract for Construction
G item
for building and engineering works designed by the Employer. JCT 80;1994 revision
standard conditions
Access to site
Construct access to the site and obtain by prior arrangement with the Engineer.
K Alter, shift and adopt from time to time as necessary in order to access the site or item
building
L The site shall not be used for any purpose other than the execution of the Contract item
The Contractor will allocate the site as indicated on the Engineer's site plans and he
must allow for setting out of temporary office accommodation and for storage of
M materials etc. Either within the site areas or at such other location that the item
Contractor may provide himself and at his own cost as per the Municipality
Regulations.
The Contractor shall take all reasonable precautions to prevent work people
N including those employed by the Sub-contractors from trespassing on adjoining
owner's property.
item
Limitations of working hours
Working hours shall be as per the labour law of Nigeria (Nigeria or Governing Law).
P Contractor shall allow for any additional working hours in order to achieve item
construction programme in coordination with Engineer
Existing services
The Contractor shall ascertain for himself the location of existing services on, under
or over the site. He shall take precautions to protect all such services within the
Q item
confines of the site and immediately make good any damage at his own expenses
in coordination with service authorities
BILL NO-01/ 45
CARRIED TO COLLECTION PAGE N
BILL NO-01/ 46
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
Site Administration.
The Contractor shall allow for providing all that is required for the proper
A administration of the contract at site level and in particular for complying in all item
respects with the relevant clauses in the Standard Conditions of Contract.
Supervision
Contractor shall allow for supervision and the site agent shall be replaced with
B item
appropriate person within reasonable time as approved by the Engineer
Security
The Contractor shall be responsible for and shall allow for providing 24 hours
C item
security through-out construction period
Provide for all costs and charges incurred by complying with all safety, health and
D welfare regulations, pertaining to staff and work people employed on the site item
including those employed by all sub-contractors
The Contractor shall be responsible for and shall allow for providing medical
E facilities including emergency medical facilities for his staff and shall made these item
available to Engineer's staff
Transport of Workpeople
Allow for the cost of all transport to and from site on the work people engaged on
F item
the site
BILL NO-01/ 47
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
CONSTRUCTION PLANTS
Provide for all necessary small plants and tools for the proper execution and
A item
completion of the Works
Scaffolding
Provide all necessary temporary scaffolding for the proper execution and
completion of the Works. Alter, relocate and adapt from time to time as necessary.
B The Contractor is to ascertain whether any scaffolding is required by any sub- item
contractor before striking. If the Contractor should strike any of his scaffolding and
is so required it shall be re-erected at his own expense.
Provide all necessary mobile/ tower cranes and lifting plant for the proper execution
C and completion of the contract. (Note: The tower crane should not be installed in
permanent structure)
Site Transport
Provide all necessary plants required for specific trades for the proper execution
E item
and completion of the contract.
BILL NO-01/ 48
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
Sign Boards
The Contractor shall allow for the provision, erection and maintenance of necessary
site notice board as required by the Engineer to display image of the project, project
A nr
name, the Employer's name and names of all Consultants associated with the
Project
The sign boards shall be complete weather durable with all necessary foundations,
supports, framing, painting and sign writing in English denoting the title of the
project and name of the Employer, Consultants and contractors with their
B item
respective addresses and building permit details. The Contractor shall provide all
details of the sign board to the Engineer for his approval before any work is put in
hand and to enable erection to commence in the early stages of the contract.
The Contractor shall provide sufficient lighting to sign boards which includes power
C item
supply and lighting fixture.
The Contractor shall clean, maintain and at the completion of the Contract remove
D item
the sign board, supports and foundations.
BILL NO-01/ 49
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
ENGINEER'S FACILITIES
Office construction shall be light airy manner with air-conditioned for Employer,
Engineer and Clerk of works/ General office (but not limited to three office) shall be
constructed comprising of Meeting room, toilets, pantry facilities & sample room,
etc. all as per specification
The Contractor shall supply and place Port-a- cabins, comprising of carpet floors
B item
and all other finishes as stated in the specification
The Contractor shall Supply and install all electromechanical works including fire
C alarm and fire fighting system in accordance with ROP standard and approval of item
works as per engineer's
The Contractor shall obtain power, water, drainage and telephone to meet office
D item
requirement (separate for Employer's and Engineer's office)
The Contractor shall supply minimum of following new furniture and other items for
each office (Contractor shall provide warranty card or slip for all Electronic items)
F Tables nr
Drawing hangers complete with drawing suspension clamps or one chest of drawer
J nr
specifically designed for drawing storage
M Conference table nr
N Conference chairs nr
P Visit Chairs nr
Q Fixed shelving required for storage/ display of samples and other materials nr
R Electric kettle nr
T Microwave oven nr
BILL NO-01/ 50
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
ENGINEER'S FACILITIES
The Contractor shall supply, install and maintain following equipment with
necessary cabling, wiring and power connection.
Colour printer photocopier and scanner on high speed (A3/A4 format, reduction/
C nr
enlargement facility, 2 sides coping, cassette feeds and sorting facility), scanner
Laptop with network facility and internet, minimum configuration; Intel Core i7,
2GHz processor, 1 TB SSD hard disk, 16 GB RAM, DVD super multi DL Rewriter,
15.4" LED monitor, in built card reader, in built web cam & mic, Wi-Fi, Bluetooth,
D nr
complete with wireless mouse, flash memory stick (8GB), printer, Anti virus, Micro
soft Office - all programs with single user license agreement, with latest softwares
(return to Employer after completion of the project)
E The Contractor shall replace any defected item during the course of Construction. item
BILL NO-01/ 51
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
CONTRACTOR'S FACILITIES
Maintenance of project office and office equipment includes cleaning on daily basis
A and to provide consumable items for the use of Employer and consultant such as month
toilet soaps, towels, pantry items like clean drinking water, milk, coffee, sugar, etc.,
The Contractor shall supply of stationaries and other sundry items (copy papers, fax
papers, pens, pencils, leads, erasers, pins, staplers, pin boards, binder, paper
B month
cutter, heavy duty punching machine, mirror, waste bins, desk paper trays, clocks,
etc.).
C The Contractor shall supply of toners, special colour printing paper, CDs, DVDs, etc. month
The Contractor shall maintain site office and floor and window cleaning and removal
D month
of rubbish
The Contractor shall pay the cost of utilities. (Water, Electricity, Telephone, Internet,
E month
etc.)
The Contractor shall provide high speed ADSL internet connection with Wi-Fi for
F month
exclusive use of Employer & Engineer
The Contractor shall supply PPE for sole use of the Employer, Engineer and their
G staff visiting the site, safety helmets, safety shoes, protective eye glass, ear muffs, item
reflective jackets, etc., as requested by the Engineer
The Contractor shall maintain and provide necessary security to the Engineer's
H item
facilities after issuing of completion certificate until the Employer take over security.
BILL NO-01/ 52
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
CONTRACTOR'S FACILITIES
The Contractor shall provide, erect, maintain and remove on completion all
necessary site offices, stores, mess rooms, sanitary accommodation and other
A facilities as may be required by the contractor for his own and his sub-contractors item
use, together with all associated water, drainage, electrical lighting and power, air
conditioning, telephone/ equipment and attendance.
The position of all site office stores etc. shall be to the approval of the Engineer,
and the contractor must allow for any 'off site' facilities he may require additional to
B item
the area allocated to him. Contractor shall submit the Facilities Plan for Engineer’s
approval.
Temporary Roads
Provide, maintain and alter as necessary temporary roads, paths, hard standings,
C pavement crossings and the like to and within the site. Remove and reinstate all item
ground and work disturbed when required.
Temporary Works
Supply, install, remove and handover all temporary fencing to Employer at the
D item
completion of the Works
Provide all water required for the works and provide and remove on completion all
requisite temporary pipe work, pumps, storage tanks etc. The Contractor must
E item
include for obtaining water from an independent source up to the issuance of
Taking Over Certificate.
Provide all electric light and power required for the Works and remove all temporary
F item
installations on completion up to the issuance of Completion Certificate.
BILL NO-01/ 53
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
CONTRACTOR'S FACILITIES
Foul Discharge
Testing of Materials
The Contractor shall carry out tests by an independent third party laboratory
B approved by the Engineer as per specification and shall report all test results item
promptly to the Engineer
Copies of Orders
The Contractor shall provide the Engineer with a copy of all orders for the supply of
D such materials or goods required in connection with the Works as the Engineer may item
specify.
Allow for all tests required by the specification to be carried out including all
E necessary equipment, materials and reports as per scope of Works and item
specification.
Provide water, fuel and electricity necessary for the plumbing and engineering
F item
installations.
As-built Drawings
As-built' drawings shall be six sets hard copies and one set of electronic copy in CD
in latest AutoCAD format as specified in the specification. Each set of hard copy of
G item
drawings shall be properly bound and presented in a suitable manner acceptable to
the Engineer
BILL NO-01/ 54
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
CONTRACTOR'S FACILITIES
A Allow for O&M manuals for MEP and other works as per specifications item
The Contractor shall not be entitled for any extra payment or extension of time for
B the correction, preparation and supplying of the above mentioned drawings and item
information.
Training on Completion
Allow for trainings of Employer's staff related to all system on completion of the
C item
project
Provide for carefully covering up and protecting all of the Works by whatever means
D item
necessary as required during construction and on completion until handover
Disposal of debris
Keep the site free from debris arresting from the works during the construction
E period and leave the site free from debris on completion to the satisfaction of the item
Engineer.
Allow for maintenance of public and private roads used by the Contractor around
F item
the site
BILL NO-01/ 55
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
The Contractor shall take all necessary precautions in reducing noise caused by
A plant by means of mufflers, silencers, screens and the like in line with HSE item
requirements.
Watering of roads, fill granular materials as required at exit points, clean dirt carried
B item
beyond exit point on daily basis.
Provide for removing all rubbish from the site both as it accumulates from time to
C item
time and at completion.
Provide for cleaning the buildings inside and out, removing stains and touching up
D paint work and polish work and leaving the whole of the works clean, ready for item
occupation and to the satisfaction of the Engineer on completion.
The Contractor shall provide dedicated workmen to observe and clear designated
E item
areas of Foreign Object Debris as it occurs.
The Contractor shall be responsible for cleaning the site and work area completely
of all his temporary installation on completion of the Works shall be required to
grade or rake the area he has occupied to remove all traces of his occupation and
F item
leave the site as close to its original condition as possible. The Contractor shall
provide constantly available labour transport and materials to maintain the
cleanliness and tidiness of the Site.
The Contractor shall make every effort to comply with local authorities rulles and
G item
requirements
BILL NO-01/ 56
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
The Contractor shall provide guarantee/warrantee for the items as required in the
specification. Guarantee/warrantee are to be taken in the name of the Employer
A item
and forward the originals to the Engineer prior to the issue of the certified of
completion. All Guarantee/Warrantee should be started from the date of completion.
Submittals
Prepare and submit to the Engineer all submittals, materials, working drawings,
B item
record drawings, procurement schedule etc. as required by the Specification.
Samples
The Contractor shall allow for submitting samples of all materials and goods as
required to the Engineer/specification for obtaining his approval, and for paying all
C item
fees and charges etc., in connection therewith. (after approval sample may be used
in construction of the project)
Technical Literature
The Contractor shall obtain copies of the latest editions of standard manuals
D specified in the specification to be kept on site for the use of the Engineer. Upon item
completion of the project they are to be handed over to the Employer.
Statutory Obligations
Allow for all costs for permission, licenses, inspection compliance to regulation and
E item
no objection certificates.
Shop Drawings
F Prepare and submit to the Engineer all shop drawings required by the specification. item
BILL NO-01/ 57
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
The Contractor shall note that the Employer may appoint other contractors to
carryout certain items of specialist, ancillary or other works. The contractor shall
afford any such other contractors, Employers own workmen or any other duly
A item
constituted authorities all reasonable opportunity to resource and execute their
works. The Contractor shall include for liaising with all such other contractors, direct
workmen or other authorities and for co-coordinating his works with
A preliminary outline programme for carrying out the works shall be prepared by the
Contractor and submitted with the tender. Within 14 days upon receipt of Engineer's
B order to commence the work, the Contractor shall prepare a detailed programme in item
the manner as detailed in the specification for carrying out the works and shall
submit copies of the programme to the Engineer for his approval
This shall be accompanied by labour force monthly loading for each trade, including
C item
sub-contractors, supervisory staff, cash flow and details of materials procurement.
The programme shall be updated and expanded at such times as stated in the
specification and shall be submitted to the Engineer in monthly intervals. Two week
D look ahead programmes shall be Look ahead program shall contains with details of item
Plan and method he propose to employ. No works based on such proposals shall
proceed without the approval of Engineer
In addition to the above, the Contractor shall submit in a Monthly Progress Report
E item
showing all the details in accordance as specified in the
BILL NO-01/ 58
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
Photographs
Each month during the progress of the works, the Contractor shall arrange at his
own expense the taking of progress photographs from viewpoints selected by the
Engineer sufficient to record progress at the appropriate stage of the work. Six
copies comprising 36 No. 100x75 mm and 6 No. 300 x 250 mm colour photographs
presented in a proper manner approved by the Engineer, together with negatives
D and electronic copy shall be handed to the Engineer for his retention. The item
photographs shall be properly documented with dates, details of the viewpoint and
location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written
permission. The Contractor shall provide suitable albums for the correct storage of
the above photographs as specified in the Specification.
BILL NO-01/ 59
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
Site Meetings
The Contractor will attend with adequate responsible representation to Site Meeting
A item
and all other meetings to which the Engineer has given instructions to attend.
The Contractor will further undertake to inform and present to attend meeting(s) any
B representative(s) for those sub-contractors, suppliers, etc., under his direct control, item
if so requested by the Engineer.
The Contractor will ensure that all meetings with sub-contractors are held just prior
C item
to the site meetings to ensure accurate reporting on progress, information, etc.
Climatic Condition
Daily maximum and minimum air temperature (including overnight) shall be included
D item
in the Daily Report
Number of hours per day in which works are prevented by inclement weather (flood,
E item
etc.).
Other Costs
Allow for all costs, expenses etc. details of which must be set out below & extended
separately by the contractor incurred in carrying out the requirements of the
G Contract and not otherwise included in this bill. All costs & expenses not entered item
hereinafter will be deemed to be included in the prices inserted elsewhere in this
Bill.
BILL NO-01/ 60
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
COLLECTION
BILL NO-01/ 61
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
BILL No. 1
PRELIMINARIES
External works consists of Hard & soft landscaping. The entire paved hardstanding. 1 item
STRUCTURAL ENGINEER
PTL Project Ttowers Limited
26 christmas Street phase 4 Kubwa, Abuja
QUANTITY SURVEYORS
BILLSTEC ASSOCIATES .
SUITE 6, Develyn Place
60 Nouarchott Street, wuse zone 1, Abuja
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
Prelims Page 1 / 62
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
C "PLANNING SUPERVISOR:
The Architect" 1 item
E Form of contract
Mobilization of all supervisions, labours, plants, materials and equipments necessary for the
proper execution of the Works. 1 item
De-mobilization of all supervisions, labours, plants, materials and equipments necessary for the
proper execution of the Works 1 item
No part of the tender document shall be copied or use for any other purposes than for this
project without the written consent of the consultant (s) concerned
the contractor shall be required to carry out test for all concrete work including an not
limited to cube tests (for 7, 14 and 28 days) after casting and re-bar test to determine
strength of each supplies to site.
L Testing of Materials
M Statutory charges
Include the Provisional Sum of N15,000,000.00 15,000,000.00
for Statutory/Stacking/Community Charges (Council) to be
expended directly by the client
Prelims Page 1 / 63
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
Photographs
A
The contractor shall submit progress photograph in 5 sets on monthly basis with site
progress report on the basis approved by the Project Manager. The Contractor shall
arrange at his own expense the taking of progress photographs from viewpoints selected
by the Project Manager sufficient to record progress at the appropriate stage of the
work.The photographs shall be properly documented with dates, details of the viewpoint
and location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written permission.
The Contractor shall provide suitable albums for the correct storage of the above
photographs as specified in the Specification.
An English speaking qualified full time supervisor shall be required for the duration of the
contract period.Contractor shall allow for supervision and the site agent shall be replaced
with appropriate person within reasonable time as approved by the Project Manager
J
Design constraints; Contractors are advised to view the designs (Architectural, Structural
and Services) and allow here for complying with any constrain imposed on the work due
to the nature of the design, component materials and specifications.
K Method and sequence of work: Tenderers are advised to read through the "instruction to
persons tendering" and allow herein for any special obligation imposed on the
contractors on method and work sequence
L Access: This shall include maintaining of the existing road adjoining the site for the
duration of the work.
Prelims Page 1 / 64
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A
Use of the site; It is expected that the site will be used only for the purpose of the work.
The site shall not be for any other unrelated activities except with the express and written
permission of the Architect.
Working hours: This shall be between the hours of 7am to 5pm (Monday to Saturday).
Any additional working hour may be employed by the contractor for the purpose of
meeting work schedule and targets as laid down in the work program.
Any additional cost of fulfilling the contractors obligation in term of meeting program
targets should be allowed here.
D
EMPLOYER'S REQUIREMENTS: FACILITIES /TEMPORARY WORKS /SERVICES
F Offices - site offices for use by the contractor for the project duration
G Sanitary accommodation
Prelims Page 1 / 65
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A Name boards (1 nr.)
The Contractor shall allow for the provision, erection and maintenance of necessary site
notice board as required by the Engineer to display image of the project, project name,
the Employer's name and names of all Consultants associated with the Project.The sign
boards shall be complete weather durable with all necessary foundations, supports,
framing, painting and sign writing in English denoting the title of the project and name of
the Employer, Consultants and contractors with their respective addresses and building
permit details. The Contractor shall provide all details of the sign board to the Engineer
for his approval before any work is put in hand and to enable erection to commence in the
early stages of the contract.The Contractor shall provide sufficient lighting to sign boards
which includes power supply and lighting fixture.The Contractor shall clean, maintain and
at the completion of the Contract remove the sign board, supports and foundations.Any
authority payments
Fixed charge 1 item 500,000.00 500,000.00
The contractor shall be expected to maintain and keep the building free of defect for six
months duration of defect liability period.
General management staff including site supervisors, site clerk and other site
management staff.
Site accommodation
shall include site office and sanitary rooms for consultants (2nr offices) The Contractor
shall supply and place Port-a- cabins, comprising of carpet floors and all other finishes as
stated in the specification.The Contractor shall obtain power, water, drainage.The
Contractor shall supply minimum of following new furniture and other items for each office
(Contractor shall provide warranty card or slip for all Electronic items)complete with air-
conditioning, office desk and drawers and drawing tables, Photocopy machine
one air-conditioned large meeting room to contain a minimum of 15 persons within the
existing structure complete with comfortable meeting table and chairs and the contractor
shall provide for one wireless fixed digital telephone for use by consultants and provide
for refreshments (finger meals and drinks) for every site meetings (ONCE monthly)
Prelims Page 1 / 66
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
CONTRACTOR'S GENERAL COST ITEMS: SERVICES AND FACILITIES
A Temporary Power including standby generator for general use by main contractor and
subcontractors for the duration of the contract.
B Temporary Water for the works including for general use by main contractor and sub -
contractors for the duration of the contract.
G Rubbish disposal
H Cleaning
Prelims Page 1 / 67
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A Site Security including day and night security staff.
Mechanical plant
All plant required for effective executive and completion of the project .This shall include
but not limited to mobile and fixed cranes , excavators, earthmoving equipment, concrete
mixers (mobile and fixed ), standing and mobile scaffolds and other equipment and plant
that the contractor shall allow necessary for keeping ground excavation free of general
water for the entire period of substructure works as described in the description of works .
(Note: The tower crane should not be installed in permanent structure)
Dimensions in descriptions
All dimensions in the descriptions are in millimeters unless otherwise indicated (i.e. 100
girth means 100mm girth)
The client may be supplying some of the materials for which P. C. rates are indicated in
the bills of quantities and some materials listed in the basic price list and are to be
incorporated into the works.
The contractor is implored to allow herein for receiving and storing such materials before
incorporation into the works.
The amount allow herein or somewhere else in this bill shall be deemed to cover all
incidental expenses in connection with receiving and keeping in secured store up to
incorporation into the works including insurance of such materials and goods
The amount allowed within the description in the bills of quantities as 'PC supply' are the
basic rates of such materials delivered to site. The client reserves the right to supply such
materials and where-ever such is the case these rates shall be the basis of adjustment of
the measured work executed by the contractor.
No claim for loss of profit or incidental expenses whatsoever shall be entertained on such
adjustment.
Prelims Page 1 / 68
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A A55: DAYWORKS
Include the following provisional sums
For work ordered to be paid for on a daywork basis in accordance with JCT'80 Clause
13.5.4.1 and 13.5.4.2
(the Provisional hours, sums and percentage additions are to be considered as part of the
overall contingency sum)
PLANT: (as defined in Section 5) - (percentages are to be extended in the cash column)
(plant shall be charged at the market rates current at the time the work is executed)
SECTION B: (daywork ordered to be carried out after the date of commencement of the
defects liability period) - the following schedule of Dayworks shall be as defined in section
1 except that sub-clause 1:2 referring to the defects liability period shall be deemed to be
deleted (percentages are to be extended in the cash column)
LABOUR: (as defined in Section 3) - include the provisional sum for skilled labour (insert
all-in rate against provisional hours shown and extend to cash column)
LABOUR: (as defined in Section 3) - include the provisional sum for un-skilled labour
(insert all-in rate against provisional hours shown and extend to cash column)
Prelims Page 1 / 69
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
Preliminaries 1/1 -
Preliminaries 1/8
Preliminaries
Carried to summary 144,253,859.95
Prelims Page 1 / 70
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA
GROUNDWORK
B maximum depth not exceeding 1500mm; commencing surface 150mm 656 m3 2,048.00 1,343,029.25
below existing ground level
C maximum depth not exceeding 2000mm; commencing surface 150mm 2475 m3 2,048.00 5,068,247.04
below existing ground level
To collection : 12,412,749.68
Filling to excavation
Termite treatmment
D dieldrex 20" or other equal and approved anti-termite solution to sides 6552 m2 173.00 1,133,482.16
and bottom of excavtions
E Keeping excavation free from general and ground water item 250,000.00
E IN - SITU CONCRETE
K Sand blinding not exceeding 150mm thick; poured on consolidated 538 m3 4,577.00 2,460,595.20
hardcore surfaces
To collection : 30,756,794.72
Columns
C generally 45 m3 85,625.00 3,812,667.19
Beds
D ground slabs thickness 150-450mm thick 538 m3 85,625.00 46,032,000.00
Columns; isolated
K regular shaped; rectangular 374 m2 5,000.00 1,870,650.00
To collection : 207,609,283.34
Column bases
A H16 44.89 t 800,000.00 35,913,703.10
Columns
Lift base
G H16 4.59 t 800,000.00 3,675,334.66
Lift shaft
Ground floor -1st floor
H H16 1.48 t 800,000.00 1,182,169.50
MASONRY
F10: BLOCK WALLING
Stone dust hollow blockwork, bedded and jointed in cement and sand
mortar (1:6)
Expansion Joint
M Expansion joint 20mm thick ploystrene naked panel 180 m2 676.00 121,680.00
To collection : 132,504,177.26
Plain areas
Collection
SUBSTRUCTURE.
Beams
G 1st floor beam 229 cu.m 85,625.00 19,635,043.36
To collection : 348,815,658.39
To collection : 118,368,929.98
10224
Columns
regular shaped; rectangular
To collection : 70,280,150.50
To collection : 285,794,388.23
To collection : 212,511,873.65
Lift shaft
Ground floor -1st floor
A H16 1.31 t 800,000.00 1,047,786.13
Lift slab
R H12 0.24 t 800,000.00 192,000.00
11.36
To collection : 9,084,178.55
Collection
FRAME & UPPER FLOOR
Page 2/6 348,815,658.39
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE
Beams
N Ground floor - 1st floor 3.7 m3 85,625.00 320,734.13
To collection : 2,882,754.00
To collection : 1,858,732.50
To collection : 612,000.00
No Item Description Qty Unit Rate Amount
To collection : 11,224,358.37
To collection : 8,777,234.40
To collection : 221,414.40
To collection : 588,024.00
No Item Description Qty Unit Rate Amount
To collection : 4,108,320.00
To collection : 484,524.00
To collection : 416,077.20
To collection : 252,168.00
One mist coat and two full coats of "dulux" emulsion paint
Cement rendered general surfaces
Horizontal soffit of landing
regular shaped; rectangular; height to soffit 1.50 - 3.00m
G Ground floor - 1st floor 9 m2 1,654.00 14,290.56
To collection : 289,983.91
To collection : 218,824.20
Collection
STAIRCASE.
Page 2/13 2,882,754.00
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE
Ramp Beams
G Ground floor - 1st floor 5 m3 85,625.00 437,406.75
To collection : 6,584,940.00
To collection : 29,073,606.13
To collection : 13,846,894.35
Ramp Beams
slope exceeding 15 degrees
A Ground floor - 1st floor 31 m2 1,484.00 46,327.51
To collection : 518,373.07
Ramp beams
regular shaped; rectangular
To collection : 1,370,988.00
One mist coat and two full coats of "dulux" emulsion paint
Cement rendered general surfaces
Slopping soffit of Ramp
slope exceeding 15 degrees
A Ground floor - 1st floor 170 m2 1,654.00 281,643.12
Ramp beams
regular shaped; rectangular
To collection : 2,714,194.15
RAMPS.
Page 2/27 25,175,188.50
(i.) Bituminious felt, structural steel works, roof covering and associated
works.
(ii.) The Contractor is however referred to Architect's and Structural
Engineer's drawing for the scope of work.
(iii.) Reinforced concrete roof slab and beam and associated works.
(iv.) The Contractor is however referred to Structural Engineer's
drawings for details and scope of the Works.
D Ditto edges of the roof slab not exceeding 250mm wide 212 m 1,250.00 265,000.00
Roof beam
J H25 17.77 t 800,000.00 14,213,701.60
Parapet wall
N 225mm blockwall filled solid with lean concrete 504 m2 8,500.00 4,287,400.00
To collection : 123,397,493.90
Prepare and apply 3mm thick one layer of bituminious felt or equal and
approved to concrete below ground level
B Horizontal surfaces 2268 m2 8,500.00 19,278,000.00
Backing
D 42mm cement and sand backing horizontally 2268 m2 3,175.00 7,200,900.00
To collection : 33,821,235.00
STRUCTURAL/CARCASSING METAL/TIMBER
G20: CARPENTRY/ TIMBER FRAMING/ FIRST FIXING
50 x 150mm
75mm x 100mm
50 x 100mm
50 x 75mm
25 x 225mm
50 x 50mm
E noggins; internally 9226 m 445.00 4,105,570.00
To collection : 8,897,016.00
To collection : 7,545,520.00
Collection
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE
Lintel
A generally in ground floor 7 m3 85,625.00 570,724.88
To collection : 5,051,063.06
Lintel
Ground floor
A H12 0.45 t 800,000.00 358,060.95
1st floor
C H12 0.56 t 800,000.00 448,997.07
2nd floor
E H12 0.56 t 800,000.00 448,997.07
3rd floor
G 12mm diameter 0.56 t 800,000.00 448,997.07
4th floor
J H12 0.04 t 800,000.00 31,259.29
5th floor
L H12 0.04 t 800,000.00 31,259.29
6th floor
N 12mm diameter 0.04 t 800,000.00 31,259.29
To collection : 3,238,572.92
B 230mm thick; stretcher bond; regular in 1st floor 1360 m2 5,432.00 7,385,999.04
C 230mm thick; stretcher bond; regular in 2nd floor 1360 m2 5,432.00 7,385,999.04
D 230mm thick; stretcher bond; regular in 3rd floor 1164 m2 5,432.00 6,324,803.52
E 230mm thick; stretcher bond; regular in 4th floor 344 m2 5,432.00 1,867,847.52
F 230mm thick; stretcher bond; regular in 5th floor 344 m2 5,432.00 1,867,847.52
G 230mm thick; stretcher bond; regular in 6th floor 344 m2 5,432.00 1,867,847.52
6113
150mm wall
H 150mm thick; stretcher bond; regular in Ground floor 39 m2 3,728.00 145,671.60
Expansion Joint
M Expansion joint 20mm thick ploystrene naked panel 455 m2 761.00 345,933.86
To collection : 34,133,023.94
Collection
(i) Timber flush door and steel frames, anodised aluminium doors and
windows.
(ii) The contractor is however referred to the Architectural doors and
windows schedule for details and scope of work.
L10: WINDOWS
L11 ALUMINIUM WINDOWS AND DOORS/CURTAIN WALL
Ground floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall
A Size 3600mm x 2850mm high with aluminium swing door 1800mm x 155 m2 120,000.00 18,576,000.00
2100mm high (measured seperately)
Projected Window 6mm laminated clear glass single glazing EBM with
nett
B Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00
1st floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall
C Size 3600mm x 2850mm high with aluminium swing door 1800mm x 206 m2 120,000.00 24,768,000.00
2100mm high (measured seperately)
Projected Window 6mm laminated clear glass single glazing EBM with
nett
D Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00
2nd floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall
E Size 3600mm x 2850mm high with aluminium swing door 1800mm x 206 m2 120,000.00 24,768,000.00
2100mm high (measured seperately)
Projected Window 6mm laminated clear glass single glazing EBM with
nett
F Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00
3rd floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall
G Size 3600mm x 2850mm high with aluminium swing door 1800mm x 155 m2 657,600.00 101,796,480.00
2100mm high (measured seperately)
Projected Window 6mm laminated clear glass single glazing EBM with
nett
H Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00
To collection : 170,657,280.00
4th floor
Projected Window 6mm laminated clear glass single glazing EBM with
nett
A Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00
5th floor
Projected Window 6mm laminated clear glass single glazing EBM with
nett
B Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00
6th floor
Projected Window 6mm laminated clear glass single glazing EBM with
nett
C Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00
Subframe
D 40mm x 20mm aluminium subframe on window 35 m 1,903.00 66,605.00
Ready made door complete with lock ,frame & architrave and stopper
Solid core, single leaf; single swing; solid door, factory finish with
hardwood lipping all edges and polished door frames and all sprayed with
approved quality varnish paint
Ground floor
E Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00
1st floor
G Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00
2nd floor
J Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00
3rd floor
L Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00
4th floor
N 900 X 2100mm high overall 2 nr 100,000.00 200,000.00
5th floor
P 900 X 2100mm high overall 2 nr 100,000.00 200,000.00
5th floor
Q 900 X 2100mm high overall 2 nr 100,000.00 200,000.00
To collection : 5,628,205.00
1st Floor
B Aluminium Swing Door size 1800mm x 2100mm high 32 nr 321,300.00 10,281,600.00
2nd floor
C Aluminium Swing Door size 1800mm x 2100mm high 32 nr 321,300.00 10,281,600.00
3rd Floor
D Aluminium Swing Door size 1800mm x 2100mm high 24 nr 321,300.00 7,711,200.00
1st Floor
F Door size 3600mm x 2850mm high 32 nr 415,800.00 13,305,600.00
2nd floor
G Door size 3600mm x 2850mm high 32 nr 415,800.00 13,305,600.00
3rd Floor
H Door size 3600mm x 2850mm high 24 nr 415,800.00 9,979,200.00
Name plates
' TOILET' sign engraved on stainless steel plate size 350 x 100; Ref IRXX;
J finish: SS 28 nr 7,000.00 196,000.00
K Room Numbers and other spaces sign engraved on stainless plate 20 nr 7,000.00 140,000.00
L Shop Numbers and other spaces sign engraved on stainless plate 112 nr 7,000.00 784,000.00
To collection : 83,675,200.00
Collection
Balcony handrailings
Laser-cut steel handrailing bolted, with connector and all necessary
accessories
A 1st floor 120 m2 95,500.00 11,460,000.00
D Allow a provisional sum of N150,000,000.00 for the fabrication of steel sum 150,000,000.00
work and Alucobond covering on external facade as may be instructed by
the Architect (2385m2)
SURFACE FINISHES
INFORMATION
Ground floor
A level and to falls only not exceeding 15 degrees from horizontal (To 503 m2 3,174.00 1,596,522.00
receive Light grey ceramic tiles)
C level and to falls only not exceeding 15 degrees from horizontal (To 389 m2 2,365.00 919,985.00
receive Granite)
First Floor
42mm work to floors on concrete base; one coat; screeded
D level and to falls only not exceeding 15 degrees from horizontal (To 663 m2 3,174.00 2,104,362.00
receive Light grey ceramic tiles)
F level and to falls only not exceeding 15 degrees from horizontal (To 460 m2 2,365.00 1,087,900.00
receive Granite)
Second Floor
42mm work to floors on concrete base; one coat; screeded
G level and to falls only not exceeding 15 degrees from horizontal (To 663 m2 3,174.00 2,104,362.00
receive Light grey ceramic tiles)
J level and to falls only not exceeding 15 degrees from horizontal (To 460 m2 2,365.00 1,087,900.00
receive Granite)
To collection 9,148,603.00
No Item Description Qty Unit Rate Amount
A level and to falls only not exceeding 15 degrees from horizontal (To 663 m2 3,174.00 2,104,362.00
receive Light grey ceramic tiles)
C level and to falls only not exceeding 15 degrees from horizontal (To 430 m2 2,365.00 1,016,950.00
receive Granite)
Fourth floor
30mm work to floors on concrete base; one coat; screeded
D level and to falls only not exceeding 15 degrees from horizontal (To 33 m2 2,365.00 78,045.00
receive Granite)
Fifth floor
30mm work to floors on concrete base; one coat; screeded
E level and to falls only not exceeding 15 degrees from horizontal (To 33 m2 2,365.00 78,045.00
receive Granite)
Sixth floor
30mm work to floors on concrete base; one coat; screeded
F level and to falls only not exceeding 15 degrees from horizontal (To 45 m2 2,365.00 106,425.00
receive Granite)
First floor
H height 100mm 604 m 165.00 99,613.80
2nd floor
J height 100mm 604 m 165.00 99,613.80
3rd floor
K height 100mm 424 m 165.00 69,913.80
4th floor
L height 100mm 28 m 165.00 4,573.80
5th floor
M height 100mm 28 m 165.00 4,573.80
6th floor
N height 100mm 28 m 165.00 4,573.80
To collection : 3,825,067.60
Ground floor
A Ground floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00
First Floor
B First floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00
Second floor
C Second floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00
Third floor
D Third floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00
104
Water proofing to wet Area
E Bituminious felt double layer 104 m2 8,500.00 884,000.00
1st floor
B First floor patterned; over 300mm wide 663 m2 15,000.00 9,945,000.00
2nd floor
C Second floor patterned; over 300mm wide 663 m2 15,000.00 9,945,000.00
3rd floor
D Third floor patterned; over 300mm wide 663 m2 15,000.00 9,945,000.00
4th floor
E Fourth floor patterned; over 300mm wide 33 m2 15,000.00 495,000.00
5th floor
F Fifth floor patterned; over 300mm wide 33 m2 15,000.00 495,000.00
6th floor
G Sixth floor patterned; over 300mm wide 45 m2 15,000.00 675,000.00
2603
100mm skirting
Ground floor
H height 100mm 460 m 1,500.00 689,580.00
1st floor
J height 100mm 604 m 1,500.00 905,580.00
2nd floor
K height 100mm 604 m 1,500.00 905,580.00
3rd floor
L height 100mm 424 m 1,500.00 635,580.00
4th floor
M height 100mm 28 m 1,500.00 41,580.00
5th floor
N height 100mm 28 m 1,500.00 41,580.00
6th floor
P height 100mm 28 m 1,500.00 41,580.00
2174
To collection : 42,306,060.00
1st floor
B First floor patterned; over 300mm wide 460 m2 16,500.00 7,590,000.00
2nd floor
C Second floor patterned; over 300mm wide 460 m2 16,500.00 7,590,000.00
3rd floor
D Third floor patterned; over 300mm wide 430 m2 16,500.00 7,095,000.00
4th floor
E Fourth floor patterned; over 300mm wide 33 m2 16,500.00 544,500.00
5th floor
F Fifth floor patterned; over 300mm wide 33 m2 16,500.00 544,500.00
6th floor
G Sixth floor patterned; over 300mm wide 45 m2 16,500.00 742,500.00
1850
100mm skirting
Ground floor
H Ground floor patterned; over 300mm wide 245 m 2,500.00 612,500.00
1st floor
J First floor patterned; over 300mm wide 310 m 2,500.00 775,000.00
2nd floor
K Second floor patterned; over 300mm wide 310 m 2,500.00 775,000.00
3rd floor
L Third floor patterned; over 300mm wide 310 m 2,500.00 775,000.00
4th floor
M Fourth floor patterned; over 300mm wide 10 m 2,500.00 24,000.00
5th floor
N Fifth floor patterned; over 300mm wide 10 m 2,500.00 24,000.00
6th floor
P Sixth floor patterned; over 300mm wide 10 m 2,500.00 24,000.00
1204
To collection : 33,534,500.00
(i) Walls finishings with and including other associated works but
excluding painting which is measured in a separate element.
(ii) The Contractor is hereby referred to
the various Architect's location drawings in relation to this section for the
nature and content of the work to be executed.
M20: PLASTERED/RENDERED
First floor
E First floor wall width exceeding 300mm 1657 m2 1,650.00 2,734,363.50
2nd floor
J second floor wall width exceeding 300mm 1621 m2 1,650.00 2,674,963.50
3rd floor
N Third floor wall width exceeding 300mm 1209 m2 1,650.00 1,994,239.50
To collection : 14,491,883.84
4th floor
A Fourth floor wall width exceeding 300mm 73 m2 1,650.00 120,037.50
5th floor
E Fifth floor wall width exceeding 300mm 73 m2 1,650.00 120,037.50
6th floor
J Sixth floor wall width exceeding 300mm 73 m2 1,650.00 120,037.50
To collection : 1,958,974.88
EXTERNAL WORK
12mm work to walls on concrete base or blockwork
Ground floor
A width exceeding 300mm 1059 m2 1,650.00 1,747,746.00
1st floor
C width exceeding 300mm 1140 m2 1,650.00 1,881,660.00
2nd floor
E width exceeding 300mm 1176 m2 1,650.00 1,941,060.00
3rd floor
G width exceeding 300mm 1198 m2 1,650.00 1,977,096.00
To collection : 8,642,007.00
5th floor
C width exceeding 300mm 615 m2 1,650.00 1,014,700.50
6th floor
E width exceeding 300mm 615 m2 1,650.00 1,014,700.50
Roof floor
G width exceeding 300mm 504 m2 1,650.00 832,260.00
To collection : 6,598,231.50
Collection
WALL FINISHING
INFORMATION
(i) Ceiling finishings with and including other associated works but
excluding painting which is measured in a separate Element
(ii) The Contractor is hereby referred to the various Architect's location
drawings in relation to this section for the nature and content of the work
to be executed.
SURFACE FINISHES
First floor
C over 300mm wide; internal; 689 m2 1,650.00 1,136,850.00
Second floor
E over 300mm wide; internal; 689 m2 1,650.00 1,136,850.00
Third floor
K13 RIGID SHEET LINNING/COVERING
High quality plaster of paris; 12.5mm thick secrete fixing with screws or
other approved method; filling fixing holes and joints with plaster;
including all necessary screeding
Fourth floor
J over 300mm wide; internal; 211 m2 1,650.00 348,150.00
Fifth floor
L over 300mm wide; internal; 33 m2 1,650.00 54,450.00
Sixth floor
N over 300mm wide; internal; 45 m2 1,650.00 74,250.00
First floor
E First floor wall width exceeding 300mm 1657 m2 1,000.00 1,657,190.00
To collection : 4,535,552.00
3rd floor
F Third floor wall width exceeding 300mm 1209 m2 1,000.00 1,208,630.00
4th floor
L Fourth floor wall width exceeding 300mm 73 m2 1,000.00 72,750.00
5th floor
R Fifth floor wall width exceeding 300mm 73 m2 1,000.00 72,750.00
6th floor
A Six floor wall width exceeding 300mm 73 m2 1,000.00 72,750.00
To collection : 5,330,084.50
1st floor
C over 300mm wide; internal; 689 m2 1,000.00 689,000.00
2nd floor
E over 300mm wide; internal; 689 m2 1,000.00 689,000.00
3rd floor
G over 300mm wide; internal; 1140 m2 1,000.00 1,140,000.00
4th floor
J over 300mm wide; internal; 211 m2 1,000.00 211,000.00
5th floor
L over 300mm wide; internal; 33 m2 1,000.00 33,000.00
6th floor
N over 300mm wide; internal; 45 m2 1,000.00 45,000.00
7463
To collection : 7,462,688.00
Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
On wall
Ground floor
A Ground floor wall width exceeding 300mm 1414 m2 1,654.00 2,338,144.02
First floor
E First floor wall width exceeding 300mm 1657 m2 1,654.00 2,740,992.26
2nd floor
J second floor wall width exceeding 300mm 1621 m2 1,654.00 2,681,448.26
3rd floor
N Third floor wall width exceeding 300mm 1209 m2 1,654.00 1,999,074.02
4th floor
S Fourth floor wall width exceeding 300mm 73 m2 1,654.00 120,328.50
5th floor
W Fifth floor wall width exceeding 300mm 73 m2 1,654.00 120,328.50
To collection : 15,663,188.14
Ceilings painting
Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
Ground floor
E over 300mm wide; internal; 529 m2 1,654.00 874,966.00
1st floor
G over 300mm wide; internal; 689 m2 1,654.00 1,139,606.00
2nd floor
J over 300mm wide; internal; 689 m2 1,654.00 1,139,606.00
3rd floor
L over 300mm wide; internal; 1140 m2 1,654.00 1,885,560.00
4th floor
N over 300mm wide; internal; 211 m2 1,654.00 348,994.00
5th floor
Q over 300mm wide; internal; 33 m2 1,654.00 54,582.00
6th floor
S over 300mm wide; internal; 45 m2 1,654.00 74,430.00
To collection : 12,997,860.59
1st floor
C over 300mm wide; external. 1140 m2 950.00 1,083,380.00
2nd floor
E over 300mm wide; external. 1176 m2 950.00 1,117,580.00
3rd floor
G over 300mm wide; external. 1176 m2 950.00 1,117,580.00
4th floor
J over 300mm wide; external. 615 m2 950.00 584,221.50
5th floor
L over 300mm wide; external. 615 m2 950.00 584,221.50
6th floor
N over 300mm wide; external. 615 m2 950.00 584,221.50
6th floor
Q over 300mm wide; external. 504 m2 950.00 479,180.00
To collection : 7,466,952.50
Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
Ground floor
A over 300mm wide; external. 1059 m2 1,654.00 1,751,982.96
2nd floor
E over 300mm wide; external. 859 m2 1,654.00 1,420,786.00
3rd floor
G over 300mm wide; external. 859 m2 1,654.00 1,420,786.00
4th floor
J over 300mm wide; external. 615 m2 1,654.00 1,017,160.38
5th floor
L over 300mm wide; external. 615 m2 1,654.00 1,017,160.38
6th floor
N over 300mm wide; external. 615 m2 1,654.00 1,017,160.38
Parapet wall
Q over 300mm wide; external. 504 m2 1,654.00 834,277.60
To collection : 11,956,352.50
Collection
PAINTING AND DECORATION
SUBSTRUCTURE 388,928,125.00
STAIRCASES 31,934,414.98
RAMPS 79,284,184.20
Floor Drain
Mirror
600 x 700mm Top Basin wall fitted mirror c/w all
J 24 Nos 20,000.00
installation accessories.
SANITARY FITTING
Fittings
Elbow
E 50mm Dia 22 Nr 500.00
Reducing Elbow
J 32 x 20mm 7 Nr 450.00
Wallplate
K 20mm 83 Nr 4,200.00
Equal Tee
L 50 x 50 x 50mm 3 Nr 1,380.00
M 32 x 32 x 32mm 18 Nr 650.00
N 25 x 25 x 25mm 94 Nr 576.00
P 20 x 20 x 20mm 32 Nr 450.00
Reducing Tee
Q 50 x 32 x 50mm 2 Nr 1,380.00
R 32 x 25 x 25mm 8 Nr 650.00
S 32 x 20 x 32mm 7 Nr 650.00
T 32 x 32 x 20mm 7 Nr 650.00
U 20 x 25 x 20mm 7 Nr 576.00
V 25 x 20 x 20mm 7 Nr 576.00
Carried to collection;
C 20mm 91 Nr 2,485.00
Sockets
D 50mm 12 Nr 1,140.00
E 32mm 8 Nr 780.00
F 25mm 72 Nr 504.00
Valves
G 50mm 8 Nr 18,321.60
Union Connector
N 50mm 28 Nr 2,500.00
Tank Connector
P 50mm 4 Nr 3,000.00
MISCELLANEOUS ACCESSORIES
Q Pressure Testing of Supply Pipes Lot
Commissioning:
Preparation of shop and as built drawings to be
A 1 lot 250,000.00
approved by the Engineer.
Carried to collection;
COLLECTION
Page/ 3
Page/4
Page/5
B 110mm 62 m 5,110.80
C 75mm 13 m 3,550.00
D 50mm 88 m 2,050.80
FITTINGS
Bends (90 Degree)
E 110mm 12 Nr 1,782.00
F 75mm 2 Nr 1,215.00
G 50mm 48 Nr 840.00
Y TEES
H 110 x 110 x 110mm 36 Nr 3,062.40
J 75 x 50 x 75mm 4 Nr 2,300.00
K 50 x 50 x 50mm 44 Nr 936.00
TRAPS
L 110mm Vent Cowl 28 Nr 4,800.00
Carried to collection;
Carried to collection;
COLLECTION
Page/ 6
Page/7
FITTINGS
Bends (90 Degree)
C 110mm 72 Nr 1,782.00
Equal Tee
D 200 x 200 x 200mm 3 Nr 2,673.00
Reducing Elbow
E 200 x 110mm 2 Nr 1,782.00
Reducing Tee
F 200 x 110 x 200mm 9 Nr 2,673.00
other fittings
Tee
H 100 x 100 x 100mm 4 Nos 19,538.00
Carried to collection;
Cross Tee
Bend
U 100x100mm 5 Nos 16,640.00
Carried to collection;
Socket
A 80mm 50 Nos 10,255.20
Reducing Socket
Nipple
J 80mm 7 Nos 97,200.00
Gate Valve
N 100mm 8 Nos 154,351.20
Carried to collection;
F Lot
All installation Acessories e.g bushingand cap plugs etc.
Tee
L 100 x 100 x 100mm 2 Nos 19,538.00
Carried to collection;
Bend
A 100mm 7 Nos 16,640.00
Socket
D 100mm 10 Nos 19,840.00
Nipple
G 100mm 15 Nos 97,200.00
Gate Valve
P 100mm 4 Nos 123,480.00
Landing Valve
S 100mm 15 Nos 312,480.00
Carried to collection;
Breaching Inlet
A Twin breaching inlet with enclosure 1 Nos 269,514.00
Carried to collection;
COLLECTION
Page/9
Page/10
Page/11
Page/12
Page/13
Page/14
COLLECTION
Page/ 14
Page/15
MOBILIZATION
Mobilization of drilling equipment, materials and
A 1 sum 46,950.00
personnel to site.
DRILLING
C Construction of mud-pit for drilling process. 1 sum 18,780.00
PLUMBING WORK
Allow a provisional sum of N250,000.00 for plumbing
L pipe work from the bore hole to the Raw water tank 1 Lot 250,000.00
( Provisional depth 1000m)
PIPE AUXILIARIES
CONDENSATE DRAINAGE
Supply and install pvc condensate drain pipe work as
G shown on the contract drawing. Pipes shall be insulated 995 m 4,850.00
with Armaflex insulation.
ELECTRICAL WIRING
H 4C X 4.0mm2 Flexible (Nocaco) 995 m 4,850.00
N 1 items
Record drawings, Operation and Maintenance Manuals
P 1 items
Mobilization and Demobilization of Tools and Equipment
TO COLLECTION
Installation Drawings
4 Sets each; A1 paper prints, binding into sets;
E 1 Item 250,000.00
electronic copies in CD roms
Routine Maintenance
D Warranty Period 1 Item 300,000.00
COLLECTION
Page 20
Page 21
Page 22
1 SANITARY FITTINGS
4 RAINWATER
7 BOREHOLES
9 LIFT INSTALLATION
AMOUNT
3,936,000.00
4,076,800.00
3,220,000.00
840,000.00
487,200.00
4,056,000.00
406,000.00
420,000.00
480,000.00
17,922,000.00
AMOUNT
712,206.00
750,182.40
639,347.50
1,528,538.00
11,000.00
8,250.00
19,200.00
14,800.00
3,150.00
348,600.00
4,140.00
11,700.00
54,144.00
14,400.00
2,760.00
5,200.00
4,550.00
4,550.00
4,032.00
4,032.00
4,144,781.90
AMOUNT
26,832.00
223,516.80
226,135.00
13,680.00
6,240.00
36,288.00
146,572.80
606,528.00
360,000.00
252,000.00
53,280.00
456,500.00
70,000.00
12,000.00
2,000,000.00
2,000,000.00
5,000,000.00
11,489,572.60
AMOUNT
250,000.00
250,000.00
4,144,781.90
11,489,572.60
250,000.00
15,884,354.50
AMOUNT
1,662,000.00
316,869.60
46,150.00
180,470.40
21,384.00
2,430.00
40,320.00
110,246.40
9,200.00
41,184.00
134,400.00
67,200.00
301,000.00
3,000,000.00
5,932,854.40
AMOUNT
660,000.00
15,000,000.00
15,660,000.00
5,932,854.40
15,660,000.00
21,592,854.40
AMOUNT
2,659,200.00
2,243,641.20
128,304.00
8,019.00
3,564.00
24,057.00
709,500.00
448,800.00
500,000.00
2,000,000.00
8,725,085.20
AMOUNT
2,635,000.00
5,751,900.00
1,626,800.00
7,975,040.00
1,917,600.00
1,075,680.00
2,730,000.00
78,152.00
129,150.00
55,350.00
17,584.00
420,024.00
80,160.00
160,320.00
240,715.00
18,960.00
75,490.80
24,987,925.80
AMOUNT
20,588.40
27,451.20
31,348.80
31,348.80
1,600.00
4,416.00
1,725.00
11,880.00
68,628.00
36,573.60
36,573.60
10,449.60
13,930.00
41,790.00
20,895.00
95,558.40
238,896.00
30,456.00
83,200.00
39,936.00
19,104.00
32,640.00
8,064.00
907,052.40
AMOUNT
512,760.00
20,984.40
479,424.00
83,520.00
223,872.00
219,648.00
139,860.00
77,155.20
680,400.00
3,643,358.40
880,320.00
112,080.00
1,234,809.60
864,360.00
9,172,551.60
AMOUNT
5,937,624.00
3,612,000.00
165,480.00
2,000,000.00
1,000,000.00
1,000,000.00
25,000,000.00
2,976,000.00
807,040.00
170,640.00
39,076.00
19,538.00
5,000.00
42,732,398.00
AMOUNT
116,480.00
19,040.00
12,288.00
198,400.00
41,968.80
4,060.80
1,458,000.00
541,800.00
87,696.00
377,280.00
473,400.00
221,400.00
112,080.00
493,920.00
581,760.00
255,360.00
4,687,200.00
9,682,133.60
AMOUNT
269,514.00
5,760,000.00
2,100,483.00
2,522,520.00
1,000,000.00
2,000,000.00
300,000.00
13,952,517.00
AMOUNT
24,987,925.80
907,052.40
9,172,551.60
42,732,398.00
9,682,133.60
13,952,517.00
101,434,578.40
AMOUNT
57,600,000.00
27,500,000.00
24,357,942.00
24,947,247.00
6,875,226.00
43,785,546.26
9,600,000.00
2,400,000.00
4,800,000.00
201,865,961.26
AMOUNT
500,000.00
145,000.00
245,000.00
890,000.00
201,865,961.26
890,000.00
202,755,961.26
AMOUNT
46,950.00
93,900.00
18,780.00
7,045.00
5,335.00
70,425.00
46,950.00
14,085.00
46,950.00
2,300,460.00
250,000.00
46,950.00
2,947,830.00
AMOUNT
4,179,000.00
5,572,000.00
1,028,163.35
1,470,391.10
5,600,000.00
2,835,750.00
4,825,750.00
4,825,750.00
1,312,500.00
1,500,000.00
1,500,000.00
1,500,000.00
1,500,000.00
4,000,000.00
41,649,304.45
AMOUNT
0.00
AMOUNT
100,000,000.00
8,000,000.00
1,500,000.00
350,000.00
250,000.00
200,000.00
110,300,000.00
AMOUNT
3,500,000.00
150,000.00
150,000.00
300,000.00
350,000.00
4,450,000.00
0.00
110,300,000.00
4,450,000.00
114,750,000.00
AMOUNT
17,922,000.00
15,884,354.50
21,592,854.40
8,725,085.20
101,434,578.40
202,755,961.26
2,947,830.00
41,649,304.45
114,750,000.00
527,661,968.21
B 15W led wall mounted stairways & passage fitting 15 nr. 11,520.00 172,800.00
C 22W led ceiling recessed fitting (shop area) 692 nr. 11,520.00 7,971,840.00
D 18W led surface light (car park area) 818 nr. 5,760.00 4,711,680.00
SWITCHES
A 10A, 1 Gang, 1 Way Switch 'LEGRAND' 175 No. 1,800.00 315,000.00
CABLE 117,590,921.50
TO COLLECTION 8,250,000.00
TO COLLECTION 2,150,000.00
TO COLLECTION 900,000.00
COLLECTION
Page/5 8,250,000.00
Page/6 2,150,000.00
Page/7 900,000.00
PANEL 11,300,000.00
L Allow for the earthing of all equipment metal works 1 lot 1,000,000.00 1,000,000.00
within the building to the reinforcement and steel
works at all floors and sub-structure levels
SUMMARY
PANELS & CABLING/LIGHTING
PROTECTION/EARTHING/CABLE TRAY
CABLE 117,590,921.50
PANEL 11,300,000.00
Wiring works
Fittings
Addressable Ceiling mounted smoke detectors with
C 174 Nos 35,000.00 6,090,000.00
intergral sounder and LED indicator (Gent/Zeta))
B 0.5Ω Cable for telephone outlet points 113 Nos 18,400.00 2,079,200.00
TELECOMMUNICATIONS 2,644,200.00
E U-Rack for PAS Control equipment (42 ELV RACK) 1 Nr 437,500.00 437,500.00
Generator
TO COLLECTION 134,420,000.00
Isolator/Synchronizing panel
TO COLLECTION 26,025,000.00
S/N DESCRIPTION QTY UNIT RATE AMOUNT
COLLECTION FOR POWER
A Page/18 134,420,000.00
B Page/19 26,025,000.00
SUMMARY
GENERAL SUMMARY
S/N DESCRIPTION QTY UNIT RATE AMOUNT
SUB-TOTAL 1 3,750,600,358.80
GENERAL CONTINGENCIES
SUB-TOTAL 11 3,830,600,358.80
ADD
6 VAT @ 7.5% 7.50% 287,295,026.91
____________________
Designation
GENERAL SUMMARY
S/N DESCRIPTION QTY UNIT RATE AMOUNT
SUB-TOTAL 1 292,504,651.16
GENERAL CONTINGENCIES
SUB-TOTAL 11 293,004,651.16
ADD
6 VAT @ 7.5% 7.50% 21,975,348.84
____________________
Designation
CONDITIONS OF CONTRACT
The Contractor shall include/ allow for complying in all respects with the Conditions
G of Contract Clauses 1 to 20 as per FIDIC 99 Condition of Contract for Construction item
for building and engineering works designed by the Employer.
Access to site
Construct access to the site and obtain by prior arrangement with the Engineer.
K Alter, shift and adopt from time to time as necessary in order to access the site or item
building
L The site shall not be used for any purpose other than the execution of the Contract item
The Contractor will allocate the site as indicated on the Engineer's site plans and he
must allow for setting out of temporary office accommodation and for storage of
M materials etc. Either within the site areas or at such other location that the item
Contractor may provide himself and at his own cost as per the Municipality
Regulations.
The Contractor shall take all reasonable precautions to prevent work people
N including those employed by the Sub-contractors from trespassing on adjoining
owner's property.
item
Limitations of working hours
Working hours shall be as per the labour law of Nigeria (Nigeria or Governing Law).
P Contractor shall allow for any additional working hours in order to achieve item
construction programme in coordination with Engineer
Existing services
The Contractor shall ascertain for himself the location of existing services on, under
or over the site. He shall take precautions to protect all such services within the
Q item
confines of the site and immediately make good any damage at his own expenses
in coordination with service authorities
Site Administration.
The Contractor shall allow for providing all that is required for the proper
A administration of the contract at site level and in particular for complying in all item
respects with the relevant clauses in the Standard Conditions of Contract.
Supervision
Contractor shall allow for supervision and the site agent shall be replaced with
B item
appropriate person within reasonable time as approved by the Engineer
Security
The Contractor shall be responsible for and shall allow for providing 24 hours
C item
security through-out construction period
Provide for all costs and charges incurred by complying with all safety, health and
D welfare regulations, pertaining to staff and work people employed on the site item
including those employed by all sub-contractors
The Contractor shall be responsible for and shall allow for providing medical
E facilities including emergency medical facilities for his staff and shall made these item
available to Engineer's staff
Transport of Workpeople
Allow for the cost of all transport to and from site on the work people engaged on
F item
the site
CONSTRUCTION PLANTS
Provide for all necessary small plants and tools for the proper execution and
A item
completion of the Works
Scaffolding
Provide all necessary temporary scaffolding for the proper execution and
completion of the Works. Alter, relocate and adapt from time to time as necessary.
B The Contractor is to ascertain whether any scaffolding is required by any sub- item
contractor before striking. If the Contractor should strike any of his scaffolding and
is so required it shall be re-erected at his own expense.
Provide all necessary mobile/ tower cranes and lifting plant for the proper execution
C and completion of the contract. (Note: The tower crane should not be installed in
permanent structure)
Site Transport
Provide all necessary plants required for specific trades for the proper execution
E item
and completion of the contract.
Sign Boards
The Contractor shall allow for the provision, erection and maintenance of necessary
site notice board as required by the Engineer to display image of the project, project
A nr
name, the Employer's name and names of all Consultants associated with the
Project
The sign boards shall be complete weather durable with all necessary foundations,
supports, framing, painting and sign writing in English denoting the title of the
project and name of the Employer, Consultants and contractors with their
B item
respective addresses and building permit details. The Contractor shall provide all
details of the sign board to the Engineer for his approval before any work is put in
hand and to enable erection to commence in the early stages of the contract.
The Contractor shall provide sufficient lighting to sign boards which includes power
C item
supply and lighting fixture.
The Contractor shall clean, maintain and at the completion of the Contract remove
D item
the sign board, supports and foundations.
ENGINEER'S FACILITIES
Office construction shall be light airy manner with air-conditioned for Employer,
Engineer and Clerk of works/ General office (but not limited to three office) shall be
constructed comprising of Meeting room, toilets, pantry facilities & sample room,
etc. all as per specification
The Contractor shall supply and place Port-a- cabins, comprising of carpet floors
B item
and all other finishes as stated in the specification
The Contractor shall Supply and install all electromechanical works including fire
C alarm and fire fighting system in accordance with ROP standard and approval of item
works as per engineer's
The Contractor shall obtain power, water, drainage and telephone to meet office
D item
requirement (separate for Employer's and Engineer's office)
The Contractor shall supply minimum of following new furniture and other items for
each office (Contractor shall provide warranty card or slip for all Electronic items)
F Tables nr
Drawing hangers complete with drawing suspension clamps or one chest of drawer
J nr
specifically designed for drawing storage
M Conference table nr
N Conference chairs nr
P Visit Chairs nr
Q Fixed shelving required for storage/ display of samples and other materials nr
R Electric kettle nr
T Microwave oven nr
ENGINEER'S FACILITIES
The Contractor shall supply, install and maintain following equipment with
necessary cabling, wiring and power connection.
Colour printer photocopier and scanner on high speed (A3/A4 format, reduction/
C nr
enlargement facility, 2 sides coping, cassette feeds and sorting facility), scanner
Laptop with network facility and internet, minimum configuration; Intel Core i7,
2GHz processor, 1 TB SSD hard disk, 16 GB RAM, DVD super multi DL Rewriter,
15.4" LED monitor, in built card reader, in built web cam & mic, Wi-Fi, Bluetooth,
D nr
complete with wireless mouse, flash memory stick (8GB), printer, Anti virus, Micro
soft Office - all programs with single user license agreement, with latest softwares
(return to Employer after completion of the project)
E The Contractor shall replace any defected item during the course of Construction. item
CONTRACTOR'S FACILITIES
Maintenance of project office and office equipment includes cleaning on daily basis
A and to provide consumable items for the use of Employer and consultant such as month
toilet soaps, towels, pantry items like clean drinking water, milk, coffee, sugar, etc.,
The Contractor shall supply of stationaries and other sundry items (copy papers, fax
papers, pens, pencils, leads, erasers, pins, staplers, pin boards, binder, paper
B month
cutter, heavy duty punching machine, mirror, waste bins, desk paper trays, clocks,
etc.).
C The Contractor shall supply of toners, special colour printing paper, CDs, DVDs, etc. month
The Contractor shall maintain site office and floor and window cleaning and removal
D month
of rubbish
The Contractor shall pay the cost of utilities. (Water, Electricity, Telephone, Internet,
E month
etc.)
The Contractor shall provide high speed ADSL internet connection with Wi-Fi for
F month
exclusive use of Employer & Engineer
The Contractor shall supply PPE for sole use of the Employer, Engineer and their
G staff visiting the site, safety helmets, safety shoes, protective eye glass, ear muffs, item
reflective jackets, etc., as requested by the Engineer
The Contractor shall maintain and provide necessary security to the Engineer's
H item
facilities after issuing of completion certificate until the Employer take over security.
CONTRACTOR'S FACILITIES
The Contractor shall provide, erect, maintain and remove on completion all
necessary site offices, stores, mess rooms, sanitary accommodation and other
A facilities as may be required by the contractor for his own and his sub-contractors item
use, together with all associated water, drainage, electrical lighting and power, air
conditioning, telephone/ equipment and attendance.
The position of all site office stores etc. shall be to the approval of the Engineer,
and the contractor must allow for any 'off site' facilities he may require additional to
B item
the area allocated to him. Contractor shall submit the Facilities Plan for Engineer’s
approval.
Temporary Roads
Provide, maintain and alter as necessary temporary roads, paths, hard standings,
C pavement crossings and the like to and within the site. Remove and reinstate all item
ground and work disturbed when required.
Temporary Works
Supply, install, remove and handover all temporary fencing to Employer at the
D item
completion of the Works
Provide all water required for the works and provide and remove on completion all
requisite temporary pipe work, pumps, storage tanks etc. The Contractor must
E item
include for obtaining water from an independent source up to the issuance of
Taking Over Certificate.
Provide all electric light and power required for the Works and remove all temporary
F item
installations on completion up to the issuance of Completion Certificate.
CONTRACTOR'S FACILITIES
Foul Discharge
Testing of Materials
The Contractor shall carry out tests by an independent third party laboratory
B approved by the Engineer as per specification and shall report all test results item
promptly to the Engineer
Copies of Orders
The Contractor shall provide the Engineer with a copy of all orders for the supply of
D such materials or goods required in connection with the Works as the Engineer may item
specify.
Allow for all tests required by the specification to be carried out including all
E necessary equipment, materials and reports as per scope of Works and item
specification.
Provide water, fuel and electricity necessary for the plumbing and engineering
F item
installations.
As-built Drawings
As-built' drawings shall be six sets hard copies and one set of electronic copy in CD
in latest AutoCAD format as specified in the specification. Each set of hard copy of
G item
drawings shall be properly bound and presented in a suitable manner acceptable to
the Engineer
CONTRACTOR'S FACILITIES
A Allow for O&M manuals for MEP and other works as per specifications item
The Contractor shall not be entitled for any extra payment or extension of time for
B the correction, preparation and supplying of the above mentioned drawings and item
information.
Training on Completion
Allow for trainings of Employer's staff related to all system on completion of the
C item
project
Provide for carefully covering up and protecting all of the Works by whatever means
D item
necessary as required during construction and on completion until handover
Disposal of debris
Keep the site free from debris arresting from the works during the construction
E period and leave the site free from debris on completion to the satisfaction of the item
Engineer.
Allow for maintenance of public and private roads used by the Contractor around
F item
the site
The Contractor shall take all necessary precautions in reducing noise caused by
A plant by means of mufflers, silencers, screens and the like in line with HSE item
requirements.
Watering of roads, fill granular materials as required at exit points, clean dirt carried
B item
beyond exit point on daily basis.
Provide for removing all rubbish from the site both as it accumulates from time to
C item
time and at completion.
Provide for cleaning the buildings inside and out, removing stains and touching up
D paint work and polish work and leaving the whole of the works clean, ready for item
occupation and to the satisfaction of the Engineer on completion.
The Contractor shall provide dedicated workmen to observe and clear designated
E item
areas of Foreign Object Debris as it occurs.
The Contractor shall be responsible for cleaning the site and work area completely
of all his temporary installation on completion of the Works shall be required to
grade or rake the area he has occupied to remove all traces of his occupation and
F item
leave the site as close to its original condition as possible. The Contractor shall
provide constantly available labour transport and materials to maintain the
cleanliness and tidiness of the Site.
The Contractor shall make every effort to comply with local authorities rulles and
G item
requirements
The Contractor shall provide guarantee/warrantee for the items as required in the
specification. Guarantee/warrantee are to be taken in the name of the Employer
A item
and forward the originals to the Engineer prior to the issue of the certified of
completion. All Guarantee/Warrantee should be started from the date of completion.
Submittals
Prepare and submit to the Engineer all submittals, materials, working drawings,
B item
record drawings, procurement schedule etc. as required by the Specification.
Samples
The Contractor shall allow for submitting samples of all materials and goods as
required to the Engineer/specification for obtaining his approval, and for paying all
C item
fees and charges etc., in connection therewith. (after approval sample may be used
in construction of the project)
Technical Literature
The Contractor shall obtain copies of the latest editions of standard manuals
D specified in the specification to be kept on site for the use of the Engineer. Upon item
completion of the project they are to be handed over to the Employer.
Statutory Obligations
Allow for all costs for permission, licenses, inspection compliance to regulation and
E item
no objection certificates.
Shop Drawings
F Prepare and submit to the Engineer all shop drawings required by the specification. item
The Contractor shall note that the Employer may appoint other contractors to
carryout certain items of specialist, ancillary or other works. The contractor shall
afford any such other contractors, Employers own workmen or any other duly
A item
constituted authorities all reasonable opportunity to resource and execute their
works. The Contractor shall include for liaising with all such other contractors, direct
workmen or other authorities and for co-coordinating his works with
A preliminary outline programme for carrying out the works shall be prepared by the
Contractor and submitted with the tender. Within 14 days upon receipt of Engineer's
B order to commence the work, the Contractor shall prepare a detailed programme in item
the manner as detailed in the specification for carrying out the works and shall
submit copies of the programme to the Engineer for his approval
This shall be accompanied by labour force monthly loading for each trade, including
C item
sub-contractors, supervisory staff, cash flow and details of materials procurement.
The programme shall be updated and expanded at such times as stated in the
specification and shall be submitted to the Engineer in monthly intervals. Two week
D look ahead programmes shall be Look ahead program shall contains with details of item
Plan and method he propose to employ. No works based on such proposals shall
proceed without the approval of Engineer
In addition to the above, the Contractor shall submit in a Monthly Progress Report
E item
showing all the details in accordance as specified in the
Photographs
Each month during the progress of the works, the Contractor shall arrange at his
own expense the taking of progress photographs from viewpoints selected by the
Engineer sufficient to record progress at the appropriate stage of the work. Six
copies comprising 36 No. 100x75 mm and 6 No. 300 x 250 mm colour photographs
presented in a proper manner approved by the Engineer, together with negatives
D and electronic copy shall be handed to the Engineer for his retention. The item
photographs shall be properly documented with dates, details of the viewpoint and
location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written
permission. The Contractor shall provide suitable albums for the correct storage of
the above photographs as specified in the Specification.
Site Meetings
The Contractor will attend with adequate responsible representation to Site Meeting
A item
and all other meetings to which the Engineer has given instructions to attend.
The Contractor will further undertake to inform and present to attend meeting(s) any
B representative(s) for those sub-contractors, suppliers, etc., under his direct control, item
if so requested by the Engineer.
The Contractor will ensure that all meetings with sub-contractors are held just prior
C item
to the site meetings to ensure accurate reporting on progress, information, etc.
Climatic Condition
Daily maximum and minimum air temperature (including overnight) shall be included
D item
in the Daily Report
Number of hours per day in which works are prevented by inclement weather (flood,
E item
etc.).
Other Costs
Allow for all costs, expenses etc. details of which must be set out below & extended
separately by the contractor incurred in carrying out the requirements of the
G Contract and not otherwise included in this bill. All costs & expenses not entered item
hereinafter will be deemed to be included in the prices inserted elsewhere in this
Bill.
COLLECTION
A NVR 32 Channel with 2TB HDD Capacity and Wireless Mouse 4 No. 550,000.00 2,200,000.00
Page/227
SURVEILLANCE CAMERA SYSTEM(IP CAMERA) 13,990,000.00
G Panasonic Telephone with Screen Single Line Corded with Caller Id display 20 No. 18,500.00 370,000.00
J External Line Dailer (MTN, GLO, AIRTEL, 9MOBILE) 5 No. 40,000.00 200,000.00
Page/228
PABX INTERCOM TELEPHONE SYSTEM 10,495,000.00
D Electronic Magnetic Lock & ZL Bracket For Access Control 48 No. 40,000.00 1,920,000.00
Page/229
IP -BASED ACCESS CONTROL SYSTEM 8,680,000.00
IP-TV SYSTEM
C LCM Web Base Management System software license 1 No. 1,570,000.00 1,570,000.00
G SFP+ 10GE module, 20 km, 2 fiber, 1310 nm, LC, DDM, pc 6 No. 135,000.00 810,000.00
Supply, install, test and commission Satellite dish with LNB; VHF/UHF
antenna and accessories including all items necessary for complete
2 installation as per specification.
L Supply and install free to air dish + MultiSwitch 1 LOT 750,000.00 750,000.00
Supply and install DSTV satellite dish complete with one year subscription for
M basic channels + 16 outgoing Multi Switch 140 LOT 65,750.00 9,205,000.00
3 Others
Page/230
IP-TV SYSTEM 53,833,473.38
Page/231
TV- SATELLITE SYSTEM 5,078,250.00
B Energy Saver (Room power Control) used with Mifare Card 140 No. 25,650.00 3,591,000.00
Page/232
HOTEL LOCKS AND ENERGY SAVER. 13,129,500.00
Page/233
ADDRESSABLE FIRE DETECTION-ALARM SYSTEM 10,995,000.00
A Mikrotik Router and Wireless with 600MBPS Speed(Dual WAN) 1 No. 385,000.00 385,000.00
K SFP+ 10GE module, 20 km, 2 fiber, 1310 nm, LC, DDM, pc 6 No. 95,650.00 573,900.00
Page/234
HOTEL- NETWORKING (INTERNET AND INTRANET) 10,710,400.00
D 6 Zone Multizone, 6 Sources Amplifier & Emergency/Evacuation Console 1 No. 1,200,000.00 1,200,000.00
Page/235
MULTIZONE SOUND SYSTEM PUBLIC ADDRESS AND VOICE EVACUATION 15,085,000.00
Page/236
S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL
1-RN2dT1 RMU
cooling:ONAN
Vector group:Dyn11
Conductor:cu/cu
Make:ABB Turkey
Coupler:
outgoing:
1-1800A 3P MCCB
1-400A 3P MCCB
1-200A 3P MCCB
1-160A 3P MCCB
Load monitor
Page/237
Phase Monitoring relay +CT+MCB
set of MCB
Emergency pushbuttons
Page/11 59,710,000.00
On site
Outgoing
1-400A 3P MCCB
1-200A 3P MCCB
1-100A 3P MCCB
12-63A 3P MCCB
5-32A 3P MCCB
2-UNIVERSAL Enclosure
Outgoing
Cooling (KW)&Power(KW)
cooling: 3-168kw
power:14.1kw,14.1kw,14.1kw
VRV 0.1
cooling: 1-124kw
power:8.9KW,8.9kw,12.9kw
Page/238
VRV 0.2 & 1.1
cooling: 2-112kw
power:8.9KW,8.9kw,12.9kw
VRV 1.2
cooling: 1-106kw
power:5.13KW,8.9kw,12.9kw
cooling: 5-95kw
power:5.13KW,8.9kw,12.9kw
Page/12 8,988,000.00
cooling: 5-85kw
power:10.8KW,12.9kw
VRV 6.1
cooling: 1-45kw
power:10.8KW,
In details
1-64a 2p MCP
Outgoing
1-60A 3P MCCB
1-38A 3P Contacto
1-ON/OFF Pushbuttons
2-universal Enclosure
set of terminals
Incomer
Page/239
Outgoing
3-10A 1P MCB
1-6MODULE ENCLOSURE
7 BASEMENT FLOOR PUMP ROOM PUMP:400A LV PANEL Comprising: 1 nr. 1,169,000.00 1,169,000.00
Incomer
1-400A 3P MCCB
Outgoing
2-200A 3P MCCB
4-63A 3P MCCB
1-UNIVERSAL Enclosure
Page/13 1,466,360.00
1-200A 3P MCCB
Outgoing
1-UNIVERSAL Enclosure
1-100A 3P MCCB
Outgoing
1-UNIVERSAL Enclosure
Page/240
1-20KA surge Arrestor +MCB
Outgoing
11-32A 3P MCB
1-36MODULE Enclosure
Outgoing
19-10A 1P MCB+spare
1-24MODULE Enclosure
Outgoing
15-16A 1P MCB
3-10A 1P MCB
1-18MODULE Enclosure
Page/14 2,935,870.00
Outgoing
5-20A 1P MCB
14-16A 1P MCB
5-10A 1P MCB
1-24MODULE Enclosure
Outgoing
3-25A 3P MCB
3-20A 1P MCB
10-16A 1P MCB
2-10A 1P MCB
1-24MODULE Enclosure
Outgoing
3-25A 3P MCB
2-16A 1P MCB+spare
1-10A 1P MCB
1-12MODULE Enclosure
Page/241
16 GROUND FLOOR POWER AUDITORIUM DB-AUD:6WAYTPNDB comprising:
Outgoing
7-16A 1P MCB
11-10A 1P MCB
1-12MODULE Enclosure
Outgoing
10-16A 1P MCB+spare
15-10A 1P MCB+spare
1-36MODULE Enclosure
Page/15 662,410.00
Outgoing
12-16A 1P MCB+spare
7-10A 1P MCB+spare
1-36MODULE Enclosure
Outgoing
6-16A 1P MCB+spare
6-10A 1P MCB+spare
1-12MODULE Enclosure
Incomer
Outgoing
3-16A 1P MCB+spare
3-10A 1P MCB
1-6MODULE Enclosure
Incomer
Page/242
1-125A 3P ISOLATOR SWITCH
6-16A 1P MCB+spare
1-10A 1P MCB
1-18MODULE Enclosure
Incomer
Outgoing
1-25A 1P MCB+spare
6-16A 1P MCB+spare
1-36MODULE Enclosure
Outgoing
3-16A 1P MCB+spare
3-10A 1P MCB
1-6MODULE Enclosure
Page/16 3,593,240.00
Incomer
Outgoing
4-16A 1P MCB+spare
8-10A 1P MCB+spare
1-12MODULE Enclosure
Outgoing
2-25A 1P MCB
3-16A 1P MCB+spare
7-10A 1P MCB
1-12MODULE Enclosure
Page/243
TESCOM-EUROPEAN STANDARD
Page/17 17,434,340.00
Page/11 59,710,000.00
Page/12 8,988,000.00
Page/13 1,466,360.00
Page/14 2,935,870.00
Page/15 662,410.00
Page/16 3,593,240.00
Page/17 17,434,340.00
Page/244
TRANSFORMER SUB STATION, SYNCHRO PANEL. 94,790,220.00
EXCAVATION
A Trench 1m maximum depth; from 150 below existing level 73 cu.m 1,850.00 135,050.00
Reinforcement
Page/245
J 45,000 litres under groung tank with associated accessories and works 1 NR 6,500,000.00 6,500,000.00
Formwork
M 10,000 litres ground day tank with associated accessories and works 1 Nr. 1,872,486.00 1,872,486.00
T Allow for the fabrication and installation of 1 meter high steel stand sum 75,000.00
Generator sets
U 500kVA 400V 50Hz, 1500RPM JMG FG Wilson cummings engine 2 Nr 45,390,100.00 90,780,200.00
100,517,391.00
GENERAL SUMMARY
Page/246
GRAND TOTAL 337,304,234.38
Page/247
PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION
STATION BUILDING
A1 20mm dia Flexible/Didnity PVC Pipe 355 length 260.00 48.00 109,340.00
A2 25mm dia Flexible/Dignity PVC Pipe 290 length 300.00 58.00 103,820.00
OUTDOOR CABLE
2 5 pair underground armoured telephone cable 80 m 1,650.00 400.00 164,000.00
INDOOR CABLE
3 CAT 6 Cable 450 m 850.00 220.00 481,500.00
6 COMMUNICATION EQUIPMENT
i PABX Equipmentequipped with:
3 trunk lines,
36 extension
operator hands free console, voice mail.
Make/Type ……PANASONIC 1 No. 155,000.00 30,500.00 185,500.00
ii Telephone handsets.
Make/Type Panasonic with Display 7 No. 8,245.00 2,125.00 72,590.00
RJ 45 system dual face plate with modules & shutter
iii
for Data/Telephone
Make/Type 7 No. 2,800.00 500.00 23,100.00
Allow for termination for Telephone points in floor
iv Lot 20,000.00
boxes 1
Cables complete with jack for connection between
v Lot 25,000.00
PABX and MDF 1
Allow for 1No. 1.5KVA APC UPS/ support and all
vi other necessary item for complete installation of UPS Lot 25,000.00
supply to voice/data systems 1
STATION BUILDING
STATION BUILDING
HEAD END
12GHZ 140mm Electronic coated steel offset Dish with
1 polyester pain stand poly propylene metal support in No. 62,000.00 16,250.00 78,250.00
galvanized plate 1
DISTRIBUTION SYSTEM
4 8way- RF splitter Televes 1 No. 18,360.00 4,590.00 22,950.00
5 Tv outlet (TV + SAT)- TELEVES REF 5246 7 No. 2,400.00 600.00 21,000.00
D EARTHING
Supply, install, test & commission
the earthing of the electrical
installation works and equipment
complete with W.J. Furse & Co.
earth rods, earth tape, teat clamps
equipotential earth bar of the
main switch board, all to achieve
earth resistance of 0.2ohms and all
other necessary items for a complete
earthing systems as per specification
STATION BUILDING
E CABLES
1 1.5mm2 Single Core PVC Cable (100m/roll) 21 rolls 8,900.00 1,600.00 220,500.00
3 4mm2 Single Core PVC Cable (100m/roll) 6 rolls 21,220.00 3,800.00 150,120.00
4 16mm2 x 4Core PVC/PVC Copper Cable (100m/roll) 150 rolls 4,880.00 800.00 852,000.00
From main panel to DB-A, DB-B, DB-C, DB-D, DB-E, DB-
F, DB-G, DB-GH
5 10mm2 x 2Core PVC/PVC Copper Cable (100m/roll) 130 m 2,850.00 500.00 435,500.00
From main panel to CU-H
STATION BUILDING
G3 13A twin socket outlet on Raw power 41 No. 2,800.00 700.00 143,500.00
G6 15A Switch Socket Outlet for water heater 1 No. 2,650.00 550.00 3,200.00
G7 20A DP Switch with indicator light for A?C 14 No. 2,650.00 550.00 44,800.00
H LIGHTING FITTINGS
STATION BUILDING
SUMMARY
E CABLES 1,437,620.00
EXTERNAL WORKS
In-commer
1No.800A 4-pole ACB
Out-going
5No. 45A 4pole MCCB
2No. 60A 3pole MCCB
10No. 10A 2pole MCCB
2No. 45A 2pole MCCB
2No.32A 3pole MCCB as spare
- Control Switch single pole
- Voltage monitoring relay
- Phase failure relay 380 - 415V
- Reverse Power Relay
- Emergency (mushroom) stop switch
- Digital Multimeter
- Time Relay
- Control relay,
- Signal lamp red, green, or yellow lens
- Single pole mcb for controls
- Surge Suppressor FURSE
1 Make/Type----- 1 no 1,590,000.00 150,000.00 1,740,000.00
2
LIGHTING KIOSK complete with contactor and photocell
Busbars fully assembled
and wired in
Dimension :
consisting of:
Enclosure : Metal Clad
Busbar Rating : 1000A
Rated Voltage: 690V, 50-60Hz
Short circuit rating:
In-commer
1No.16A 3-pole MCB
Out-going
20No. 10A 2pole MCB 1 no 635,350.00 65,000.00 700,350.00
4
Allow cost for 400A change-over switch 1 no 15,000.00 275,000.00
260,000.00
B POWER CABLES
(Coleman cable/Nigerchin/Kabelmetal)
21 Allow for all other items necessary for complete installation and
1 Lot
commissioning of transformer 100,000.00
D LIGHTNING PREVENTION/PROTECTION
Supply, install, test and commission
(Furse) lightning spikes linked
together with copper tapes on top of
the building complete with 23x3mm
copper tape, clamps, earthing rods,
test points and rod couplers.
Earthing basis are to be less than
0.2ohms and all other necessary items
for a complete installation of the
lightning prevention/protection (Furse)
E LIGHTING FITTING
Supply, install and test, commissioning AFROLUX LED STREET
LIGHT lighting fittings complete with lamps and all items
necessary for a complete installation and as recommended by
the manufacturers:
All Lighting fittings should complete with lamps
G SOLAR POWER
Allow a Prime cost sum of N5,000,000.00 (Five Million Naira
Only ) to provide 80 Pcs of 300W Solar Panel to be connected
to multi-power off line inverter to power security lights, canopy
lights and minor office equipment etc. (Cost of Inverter not
inclusive)
5,000,000.00
H CAMERA
Allow a Prime cost sum of N3,000,000.00 (Three Million Naira
Only ) for IP camera in Admin building offices, and entire
forecourt area. 3,000,000.00
SUMMARY
H CAMERA 3,000,000.00
SWITCHES
EXTRACTOR FAN 88
POWER POINT
1 Mixed MCB/DB 155
2 AC socket point 95
3 10A 2gang 1 way switch 311
4 13A twin switch socket 6
5 Mixed MCCB main low voltage Distribution panel 4
6 CCU 3
FIRE DETECTOR
1 Heat Detector 80
2 Smoke Detector 182
3 Fire Alarm 33
4 4-Loop Analogue fire alarm control panel 4
CCTV LAYOUT
1 IP ceiling mounted fixed Dome Camera 8
2 Wall mounted fixed Bullet Vandal resistance Night-time
vision Camera 24
3 Wall mounted 3mp 60fp Vandal Resistance camera 12
SANITARY FITTINGS
1 Toilets 179
2 WH B 201
3 Urinals 22
4 Kitchen sink 4
Item Description Qty Unit Reference Unit Price Amount
3 Marble floor Finishing 20mm thick cut sqm 390 120,000.00 46,800,000.00
to size Botticino Design
Sub-total 116,750,000.00
Lighting & Fittings
Sub-total 15,219,000.00
Fire Alarm System
Sub-total 5,500,000.00
7 Sub-total 22,645,000.00
Sanitaries, Doors & Wall finsih
Sub-total 31,568,000.00
Air-Conditioning
9 units of 12 Horsepower
9
Sub-total 26,000,000.00
Furnishing & Electronics
2 Guest Seats 2
Sub-total 66,695,000.00
Summary
2 Lighting 15,219,000.00
6 Air-Condition 26,000,000.00
SUBSTRUCTURE
GROUNDWORK
Excavating
B maximum depth not exceeding 2500mm; commencing surface 3616 m3 1,850.00 6,689,600.00
150mm below existing ground level
Excavate pit for basement from ground level maximum depth not
exceeding 4.0metres deep and cart away spoil to temporary spoil
C 2872 m3 1,850.00 5,313,200.00
heap 150metres within the site
D Keeping excavation free from general and ground water item 1,500,000.00
Termite treatmment
D dieldrex 20" or other equal and approved anti-termite solution to 2108 m2 250.00 527,000.00
sides and bottom of excavtions
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE
Ground beam;
Raft foundation
To collection : 69,477,550.00
Columns (below basement to ground floor level 2)
Retaining wall
Staircase in basement
Landing
Steps
Landing beams
175mm Ground
Entrance steps
Ramp
To collection : 32,805,500.00
Toes steps
Columns; isolated
Retaining Wall
Bed
K slab thickness not exceeding 200mm; height to soffit 3.0 - 4.5m 328 m2 4,850.00 1,590,800.00
L slab thickness not exceeding 200mm; height to soffit 3.0 - 4.5m 1169 m2 4,850.00 5,669,650.00
To collection : 26,044,887.50
Ground slab
Staircase
D slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m 17 m2 4,850.00 82,450.00
Sides of Ramp
To collection : 5,041,575.00
E30: REINFORCEMENT FOR IN-SITU CONCRETE
Reinforcement bars; B.S.4449, hot rolled deformed high yield
steel
Straight and bent
Raft Foundation
Ground beam
Columns
Retaining Wall
To collection : 75,544,675.00
Staircase
Beam (Provisional)
MASONRY
To collection : 18,100,700.00
BUILDING FABRIC SUNDRIES
Plain areas
Tanking
B Tanking to surfaces of retaining walls 388 m2 4,500.00 1,746,000.00
Water bar
C 300 x 3mm rubberized water bar Type AR 24 set in concrete 313 m 6,750.00 2,112,750.00
Expansion Joint
D Expansion joint 25mm thick flexcell board 29 m2 4,200.00 121,800.00
INFORMATION
E IN - SITU CONCRETE
Beams
Columns
To collection : 121,314,175.00
Beam
A regular shaped; rectangular; height to soffit exceeding 3000mm 3868 m2 4,850.00 18,759,800.00
Columns
Suspended slabs/cantilever
Columns (Provisional)
Beams
To collection : 163,089,570.00
Lift Shaft wall
To collection : 15,691,975.00
Collection
INFORMATION
E IN - SITU CONCRETE
Landing
Steps
Landing beams
E slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m 100 m2 4,850.00 485,000.00
To Collection : 3,306,000.00
Sides and soffit of landing beams
Stairs
F 16mm diameter 8.34 t 455,500.00 3,798,870.00
Landing beams
H 20mm diameter 0.73 t 455,500.00 332,515.00
K Stainless steel handrailing complete with balusters vertical and 188 m 75,000.00 14,100,000.00
horizontal member
To Collection : 20,700,692.50
SURFACE FINISHES
Landing
E patterned 117 m2 7,850.00 918,450.00
Staircase treads
Staircase risers
G height 175mm 704 m 1,373.75 967,120.00
Skirting on wall
H height 100mm 200 m 785.00 157,000.00
To Collection : 4,608,090.00
M20: PLASTERED/RENDERED
A regular shaped; rectangular; height to soffit 1.50 - 3.00m 117 m2 1,800.00 210,600.00
To Collection : 1,377,900.00
One mist coat and two full coats of "dulux" emulsion paint
A regular shaped; rectangular; height to soffit 1.50 - 3.00m 117 m2 1,650.00 193,050.00
To Collection : 631,537.50
No Item Description Qty Unit Rate Amount
Collection
STAIRCASE.
Page 2/12 3,306,000.00
INFORMATION
E IN - SITU CONCRETE
To collection : 3,029,500.00
Horinzontal soffit of suspended roof slab;
Roof Beams
C 16mm diameter 1.26 t 455,500.00 573,930.00
Roof slabs
E 12mm diameter 1.7 t 455,500.00 774,350.00
CLADDING/COVERING
K Extra for dishing out around medium pipes 8 nr. 10,000.00 80,000.00
To collection : 67,204,355.00
SURFACE FINISHES
A to falls and crossfalls and to slopes not exceeding 15 degrees from 1772 m2 2,000.00 3,544,000.00
horizontal
M20: PLASTERED/RENDERED
To collection : 7,892,400.00
No Item Description Qty Unit Rate Amount
Collection
INFORMATION
E IN - SITU CONCRETE
Lintel
Lintel
To collection : 17,144,620.00
MASONRY
Walls
B 230mm thick; ditto in dwarf wall single toilet area 1500mm high 77 m2 6,550.00 504,350.00
100mm x 190mm x 190mm Glass block wall with 10mm joints with
D and including joint spacers and grouting in matching grout 36 m2 52,000.00 1,872,000.00
Expansion Joint
E Expansion joint 25mm thick flexcell board 459 m2 4,200.00 1,927,800.00
To collection : 52,253,425.00
No Item Description Qty Unit Rate Amount
Collection
(i) Timber flush door and steel frames, anodised aluminium doors
and windows.
(ii) The contractor is however referred to the Architectural doors
and windows schedule for details and scope of work.
L10: WINDOWS
Basement
P4000 section obtainable from NIGALEX comprising of 1 nr single
A projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall 38 nr 173,500.00 6,593,000.00
900mm x 1200mm high
Ground Floor
P4000 section obtainable from NIGALEX comprising of 3nr center
projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall
B 2250mm x 2100mm high 3 nr 945,000.00 2,835,000.00
C Extra over for sun shade using 50mm louver blades 3 nr 177,000.00 531,000.00
E Extra over for sun shade using 50mm louver blades 13 nr 201,500.00 2,619,500.00
G Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00
To collection : 28,022,400.00
A Extra over for sun shade using 50mm louver blades 1 nr 143,100.00 143,100.00
C Extra over for sun shade using 50mm louver blades 1 nr 177,000.00 177,000.00
G Extra over for sun shade using 50mm louver blades 2 nr 542,400.00 1,084,800.00
J Extra over for sun shade using 50mm louver blades 1 nr 403,200.00 403,200.00
First floor
M Extra over for sun shade using 50mm louver blades 17 nr 126,000.00 2,142,000.00
To collection : 34,956,800.00
A Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00
D Extra over for sun shade using 50mm louver blades 1 nr 177,000.00 177,000.00
F Extra over for sun shade using 50mm louver blades 1 nr 143,100.00 143,100.00
J Extra over for sun shade using 50mm louver blades 2 nr 403,250.00 806,500.00
Second floor
M Extra over for sun shade using 50mm louver blades 2 nr 177,000.00 354,000.00
To collection : 42,042,100.00
A Extra over for sun shade using 50mm louver blades 16 nr 201,500.00 3,224,000.00
C Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00
G Extra over for sun shade using 50mm louver blades 1 nr 177,000.00 177,000.00
J Extra over for sun shade using 50mm louver blades 1 nr 143,100.00 143,100.00
Third floor
N Extra over for sun shade using 50mm louver blades 4 nr 177,000.00 708,000.00
To collection : 58,713,500.00
A Extra over for sun shade using 50mm louver blades 29 nr 201,500.00 5,843,500.00
C Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00
F Extra over for sun shade using 50mm louver blades 3 nr 177,000.00 531,000.00
J Extra over for sun shade using 50mm louver blades 2 nr 440,500.00 881,000.00
Fourth Floor
P4000 section obtainable from NIGALEX comprising of 3nr center
projected panel, 3nr top fixed panels, 2nr bottom fixed panels
L glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 4 nr 945,000.00 3,780,000.00
2100mm high
M Extra over for sun shade using 50mm louver blades 4 nr 177,000.00 708,000.00
K Extra over for sun shade using 50mm louver blades 29 nr 201,500.00 5,843,500.00
B Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00
E Extra over for sun shade using 50mm louver blades 3 nr 177,000.00 531,000.00
H Extra over for sun shade using 50mm louver blades 2 nr 403,250.00 806,500.00
Fifth Floor
Pent floor
To collection : 25,239,800.00
A Extra over for sun shade using 50mm louver blades 1 nr 201,500.00 201,500.00
C Extra over for sun shade using 50mm louver blades 1 nr 397,000.00 397,000.00
CURTAIN WALL
Ground floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Pent Floor
Aluminium Doors
Ground Floors
First Floor
Second Floor
To collection : 89,264,500.00
Fourth Floor
Fifth Floor
P4000 section obtainable from NIGALEX comprising of 1nr Double
B hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 908,000.00 1,816,000.00
1600mm x 2400mm high (Normal door)
Security doors
Supply and install israeli security door size 900mm x 2400mm high
E 2 nr 568,700.00 1,137,400.00
Subframe
F Allow a provisional sum of N2,500,000.00 for Sub frame sum 2,500,000.00
To collection : 87,667,900.00
To collection : 2,425,000.00
No Item Description Qty Unit Rate Amount
Collection
FURNITURE/EQUIPMENT
INFORMATION
A Aluminium luxalon grille duct cover grilles vertical 195 m2 67,500.00 13,162,500.00
Kitchen cabinets
Base Unit
C Overrall size 6160mm long x 720mm wide x 600mm depth 6 m2 830,300.00 4,981,800.00
Upper Unit
D Overrall size 4300mm long x 720mm wide x 300mm depth 4 m2 745,350.00 2,981,400.00
E Granite top size 6160mm long x 720mmwide x 20mm thick 6 m2 731,800.00 4,390,800.00
Base Unit
A Overrall size 1750mm long x 720mm wide x 600mm depth 2 m2 255,150.00 510,300.00
Upper Unit
B Overrall size 1750mm long x 720mm wide x 300mm depth 2 m2 303,350.00 606,700.00
C Granite top size 6160mm long x 720mmwide x 20mm thick 2 m2 732,000.00 1,464,000.00
Wall panelling
F High quality timber wall panelling 326 m2 76,000.00 24,776,000.00
Door partitions
K
900mm x 2100mm high complete with lock,frame and door stopper 25 nr 45,000.00 1,125,000.00
To collection : 79,158,000.00
No Item Description Qty Unit Rate Amount
Collection
SURFACE FINISHES
INFORMATION
B level and to falls only not exceeding 15 degrees from horizontal to 532 m2 1,500.00 798,000.00
receive unglazed vitrified tiles (Toilet and kitchen only)
C level and to falls only not exceeding 15 degrees from horizontal to 3759 m2 1,500.00 5,638,500.00
receive unglazed vitrified tiles (offices and lobby)
D level and to falls only not exceeding 15 degrees from horizontal to 654 m2 2,000.00 1,308,000.00
receive granite tiles and epoxy flooring
To collection : 14,841,300.00
M40: TILING
Spanish Unglazed vitrified floor tiles; 3 joints systematic
layout, bedding in 10mm cement mortar (1:3); including
pointing.
Entrance Steps
E Tread 300mm wide 71 m 10,000.00 710,000.00
To collection : 99,714,850.00
WALL FINISHING
SURFACE FINISHES
INFORMATION
(i) Walls finishings with and including other associated works but
excluding painting which is measured in a separate element.
(ii) The Contractor is
hereby referred to the various Architect's location drawings in
relation to this section for the nature and content of the work to be
executed.
M20: PLASTERED/RENDERED
To collection : 47,515,075.00
EXTERNAL WORK
Aluco bond
Collection
WALL FINISHING
INFORMATION
(i) Ceiling finishings with and including other associated works but
excluding painting which is measured in a separate Element
(ii) The Contractor is hereby referred to the various Architect's
location drawings in relation to this section for the nature and
content of the work to be executed.
SURFACE FINISHES
One mist coat and two full coats of "dulux" emulsion paint
over 300mm wide; internal; as architectural details (basement only)
E 1430 m2 1,650.00 2,359,500.00
SURFACE FINISHES
INFORMATION
Prepare and apply one layer sealer and one layer undercoat
"dulux" silk emulsion paint.
SUBSTRUCTURE 264,376,827.50
STAIRCASES 30,624,220.00
Name of Structure
4650.003
9300.006
Name of Structure
T8 22 33 726 № 0.000
T8 24 33 792 № 0.000
C8 T20 1 18 18 № 0.000
T8 1 33 33 № 0.000
C5 T16 1 20 20 № 0.000
T8 1 33 33 № 0.000
C4 T20 2 16 32 № 0.000
T8 2 33 66 № 0.000
C3 T16 1 18 18 № 0.000
T8 1 33 33 № 0.000
1556.040
3112.080
Name of Structure
T8 24 33 792 № 0.000
T8 1 33 33 № 6600 86.031
T8 1 33 33 № 9720 126.700
T8 2 33 66 № 6200 161.634
T8 1 33 33 № 7960 103.759
7138.358
14276.716
Name of Structure
T8 1 33 33 № 6600 86.031
T8 1 33 33 № 9720 126.700
T8 2 33 66 № 6200 161.634
T8 1 33 33 № 7960 103.759
11806.478
23612.956
Name of Structure
46297.434
Name of Structure
57350.370
Name of Structure
850.460
1700.920
Name of Structure
61645.609
123291.218
Name of Structure
T8 1 40 40 № 8080 127.664
26509.274
53018.548
Name of Structure
4183.809
8367.618
Name of Structure
4809.269
PRELIMINARIES
Preliminaries
Clause
Defects Liability Period 15,16
& 30 6 months from the day named in the
certificate of Practical Completion of
the Works or at the end of a rainy
season, whichever is later.
Period of Delay:
S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
Bill Nr 1;PRELIMINARIES Page 1/384
PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06
Condition of Contract
Clause Nr.
1 Contractor's Obligations
2 Architect's/S.O Instructions
3 Contract Documents
8 Foreman-in-charge
10 Clerk of Works
12 Contract Bills
13 Contract Sum
16 Sectional completion
17 Assignment or sub-letting
To Collection
Clause Nr.
18
Injury to persons and property and Employer's indemnity
23 Extension of time
25 Determination by Employer
26 Determination by Contractor
27 Nominated sub-contractor
28 Nominated suppliers
31 Fluctuations
32 Outbreaks of hostilities
33 War damage
34 Antiquities
35 Arbitration
External works consists of the entire paved hardstanding and lawn 1 item
area.
STRUCTURAL ENGINEER
JAVA DESIGN CONCEPTS LTD
Plot No 559, Jahi-Katampe Road, Jahi District Abuja.
QUANTITY SURVEYORS
BILLSTEC ASSOCIATES
SUITE 6,Develyn Place
No 6, Nouakchott street,Wuse zone 1
FCT, Abuja.
E-mail: Billstecassociates@gmail.com
F Form of contract
the contractor shall be required to carry out test for all concrete
K work including an not limited to cube tests (for 7, 14 and 28 days)
after casting and re-bar test to determine strength of each supplies
to site.
Testing of Materials
L Include the following Provisional Sum of N1,500,000.00 1 item ₦500,000.00 ₦1,000,000.00 ₦1,500,000.00
for Testing of Materials
Statutory charges
Include the Provisional Sum of N4,000,000.00
M for Statutory/Stacking/EIA 1 item ₦4,000,000.00 ₦4,000,000.00
charges to be expended directly by the client
Q An English speaking qualified full time supervisor shall be required 1 item ₦30,000,000.00 ₦30,000,000.00
for the duration of the contract period
B Design constraints; Contractors are advised to view the designs 1 item ₦0.00
(Architectural, Structural and Services) and allow here for
complying with any constrain imposed on the work due to the
nature of the design, component materials and specifications.
D Access: This shall include maintaining of the existing road adjoining 1 item ₦0.00
the site for the duration of the work.
E Use of the site; It is expected that the site will be used only for the 1 item ₦0.00
purpose of the work.
The site shall not be for any other unrelated activities except with
the express and written permission of the Architect.
B Swivel based/ sprung back desk chair (2nr) 1 item ₦200,000.00 ₦200,000.00
Site records
R Operation and maintenance manuals. 1 item ₦800,000.00 ₦800,000.00
A General management staff including site supervisors, site clerk and 1 item ₦50,000,000.00 ₦50,000,000.00
other site management staff.
Site accommodation
B shall include site offices and sanitary rooms for consultants (2nr 1 item ₦10,000,000.00 ₦4,000,000.00 ₦2,500,000.00 ₦16,500,000.00
offices) complete with air-conditioning, office desk and drawers
and drawing tables.
The Contractor shall maintain site office and floor and window
G 1 item ₦4,000,000.00 ₦4,000,000.00
cleaning and removal of rubbish
The Contractor shall supply PPE for sole use of the Employer,
Engineer and their staff visiting the site, safety helmets, safety
L 1 item ₦4,000,000.00 ₦5,000,000.00 ₦9,000,000.00
shoes, protective eye glass, ear muffs, reflective jackets, etc., as
requested by the Engineer
N Temporary Power including standby generator for general use by 1 item ₦10,000,000.00 ₦15,000,000.00 ₦500,000.00 ₦25,500,000.00
main contractor and subcontractors for the duration of the
contract. That has the capacity to power Crane
Provide all electric light and power required for the Works and
P remove all temporary installations on completion up to the 1 item ₦2,500,000.00 ₦3,500,000.00 ₦6,000,000.00
issuance of Completion Certificate.
Q Temporary Water for the works including for general use by main 1 item ₦2,500,000.00 ₦1,000,000.00 ₦3,500,000.00
contractor and sub - contractors for the duration of the contract.
R Storage of materials including lock-up spaces for specialist sub- 1 item ₦3,500,000.00 ₦500,000.00 ₦500,000.00 ₦4,500,000.00
contractors
M Site Security including day and night security staff. 1 item ₦12,000,000.00 ₦12,000,000.00
Mechanical plant
Dimensions in descriptions
A A55: DAYWORKS
Include the following provisional sums
LABOUR: include the provisional sum for skilled labour (insert all-
in rate against provisional hours shown and extend to cash
column)
CONDITIONS OF CONTRACT
The Contractor shall include/ allow for complying in all respects with the Conditions
G of Contract Clauses 1 to 20 as per FIDIC 99 Condition of Contract for Construction item
for building and engineering works designed by the Employer.
Access to site
Construct access to the site and obtain by prior arrangement with the Engineer.
K Alter, shift and adopt from time to time as necessary in order to access the site or item
building
L The site shall not be used for any purpose other than the execution of the Contract item
The Contractor will allocate the site as indicated on the Engineer's site plans and he
must allow for setting out of temporary office accommodation and for storage of
M materials etc. Either within the site areas or at such other location that the item
Contractor may provide himself and at his own cost as per the Municipality
Regulations.
The Contractor shall take all reasonable precautions to prevent work people
N including those employed by the Sub-contractors from trespassing on adjoining
owner's property.
item
Limitations of working hours
Working hours shall be as per the labour law of xxxx (Include the Country name or
P Governing Law). Contractor shall allow for any additional working hours in order to item
achieve construction programme in coordination with Engineer
Existing services
The Contractor shall ascertain for himself the location of existing services on, under
or over the site. He shall take precautions to protect all such services within the
Q item
confines of the site and immediately make good any damage at his own expenses
in coordination with service authorities
Site Administration.
The Contractor shall allow for providing all that is required for the proper
A administration of the contract at site level and in particular for complying in all item
respects with the relevant clauses in the Standard Conditions of Contract.
Supervision
Contractor shall allow for supervision and the site agent shall be replaced with
B item
appropriate person within reasonable time as approved by the Engineer
Security
The Contractor shall be responsible for and shall allow for providing 24 hours
C item
security through-out construction period
Provide for all costs and charges incurred by complying with all safety, health and
D welfare regulations, pertaining to staff and work people employed on the site item
including those employed by all sub-contractors
The Contractor shall be responsible for and shall allow for providing medical
E facilities including emergency medical facilities for his staff and shall made these item
available to Engineer's staff
Transport of Workpeople
Allow for the cost of all transport to and from site on the work people engaged on
F item
the site
CONSTRUCTION PLANTS
Provide for all necessary small plants and tools for the proper execution and
A item
completion of the Works
Scaffolding
Provide all necessary temporary scaffolding for the proper execution and
completion of the Works. Alter, relocate and adapt from time to time as necessary.
B The Contractor is to ascertain whether any scaffolding is required by any sub- item
contractor before striking. If the Contractor should strike any of his scaffolding and
is so required it shall be re-erected at his own expense.
Provide all necessary mobile/ tower cranes and lifting plant for the proper execution
C and completion of the contract. (Note: The tower crane should not be installed in
permanent structure)
Site Transport
Provide all necessary plants required for specific trades for the proper execution
E item
and completion of the contract.
Sign Boards
The Contractor shall allow for the provision, erection and maintenance of necessary
site notice board as required by the Engineer to display image of the project, project
A nr
name, the Employer's name and names of all Consultants associated with the
Project
The sign boards shall be complete weather durable with all necessary foundations,
supports, framing, painting and sign writing in Arabic (Optional for any languages)
and English denoting the title of the project and name of the Employer, Consultants
B and contractors with their respective addresses and building permit details. The item
Contractor shall provide all details of the sign board to the Engineer for his approval
before any work is put in hand and to enable erection to commence in the early
stages of the contract.
The Contractor shall provide sufficient lighting to sign boards which includes power
C item
supply and lighting fixture.
The Contractor shall clean, maintain and at the completion of the Contract remove
D item
the sign board, supports and foundations.
ENGINEER'S FACILITIES
Office construction shall be light airy manner with air-conditioned for Employer,
Engineer and Clerk of works/ General office (but not limited to three office) shall be
constructed comprising of conference hall, toilets, pantry facilities & sample room,
etc. all as per specification
The Contractor shall supply and place Port-a- cabins, comprising of carpet floors
B item
and all other finishes as stated in the specification
The Contractor shall Supply and install all electromechanical works including fire
C alarm and fire fighting system in accordance with ROP standard and approval of item
works as per engineer's
The Contractor shall obtain power, water, drainage and telephone to meet office
D item
requirement (separate for Employer's and Engineer's office)
The Contractor shall supply minimum of following new furniture and other items for
each office (Contractor shall provide warranty card or slip for all Electronic items)
F Tables nr
Drawing hangers complete with drawing suspension clamps or one chest of drawer
J nr
specifically designed for drawing storage
M Conference table nr
N Conference chairs nr
P Visit Chairs nr
Q Fixed shelving required for storage/ display of samples and other materials nr
R Electric kettle nr
T Microwave oven nr
ENGINEER'S FACILITIES
The Contractor shall supply, install and maintain following equipment with
necessary cabling, wiring and power connection.
Colour printer photocopier and scanner on high speed (A3/A4 format, reduction/
C nr
enlargement facility, 2 sides coping, cassette feeds and sorting facility), scanner
Laptop with network facility and internet, minimum configuration; Intel Core i7,
2GHz processor, 1 TB SSD hard disk, 16 GB RAM, DVD super multi DL Rewriter,
15.4" LED monitor, in built card reader, in built web cam & mic, Wi-Fi, Bluetooth,
D nr
complete with wireless mouse, flash memory stick (8GB), printer, Anti virus, Micro
soft Office - all programs with single user license agreement, with latest softwares
(return to Employer after completion of the project)
E The Contractor shall replace any defected item during the course of Construction. item
CONTRACTOR'S FACILITIES
Maintenance of project office and office equipment includes cleaning on daily basis
A and to provide consumable items for the use of Employer and consultant such as month
toilet soaps, towels, pantry items like clean drinking water, milk, coffee, sugar, etc.,
The Contractor shall supply of stationaries and other sundry items (copy papers, fax
papers, pens, pencils, leads, erasers, pins, staplers, pin boards, binder, paper
B month
cutter, heavy duty punching machine, mirror, waste bins, desk paper trays, clocks,
etc.).
C The Contractor shall supply of toners, special colour printing paper, CDs, DVDs, etc. month
The Contractor shall maintain site office and floor and window cleaning and removal
D month
of rubbish
The Contractor shall pay the cost of utilities. (Water, Electricity, Telephone, Internet,
E month
etc.)
The Contractor shall provide high speed ADSL internet connection with Wi-Fi for
F month
exclusive use of Employer & Engineer
The Contractor shall supply PPE for sole use of the Employer, Engineer and their
G staff visiting the site, safety helmets, safety shoes, protective eye glass, ear muffs, item
reflective jackets, etc., as requested by the Engineer
The Contractor shall maintain and provide necessary security to the Engineer's
H item
facilities after issuing of completion certificate until the Employer take over security.
CONTRACTOR'S FACILITIES
The Contractor shall provide, erect, maintain and remove on completion all
necessary site offices, stores, mess rooms, sanitary accommodation and other
A facilities as may be required by the contractor for his own and his sub-contractors item
use, together with all associated water, drainage, electrical lighting and power, air
conditioning, telephone/ equipment and attendance.
The position of all site office stores etc. shall be to the approval of the Engineer,
and the contractor must allow for any 'off site' facilities he may require additional to
B item
the area allocated to him. Contractor shall submit the Facilities Plan for Engineer’s
approval.
Temporary Roads
Provide, maintain and alter as necessary temporary roads, paths, hard standings,
C pavement crossings and the like to and within the site. Remove and reinstate all item
ground and work disturbed when required.
Temporary Works
Supply, install, remove and handover all temporary fencing to Employer at the
D item
completion of the Works
Provide all water required for the works and provide and remove on completion all
requisite temporary pipe work, pumps, storage tanks etc. The Contractor must
E item
include for obtaining water from an independent source up to the issuance of
Taking Over Certificate.
Provide all electric light and power required for the Works and remove all temporary
F item
installations on completion up to the issuance of Completion Certificate.
CONTRACTOR'S FACILITIES
Foul Discharge
Testing of Materials
The Contractor shall carry out tests by an independent third party laboratory
B approved by the Engineer as per specification and shall report all test results item
promptly to the Engineer
Copies of Orders
The Contractor shall provide the Engineer with a copy of all orders for the supply of
D such materials or goods required in connection with the Works as the Engineer may item
specify.
Allow for all tests required by the specification to be carried out including all
E necessary equipment, materials and reports as per scope of Works and item
specification.
Provide water, fuel and electricity necessary for the plumbing and engineering
F item
installations.
As-built Drawings
As-built' drawings shall be six sets hard copies and one set of electronic copy in CD
in latest AutoCAD format as specified in the specification. Each set of hard copy of
G item
drawings shall be properly bound and presented in a suitable manner acceptable to
the Engineer
CONTRACTOR'S FACILITIES
A Allow for O&M manuals for MEP and other works as per specifications item
The Contractor shall not be entitled for any extra payment or extension of time for
B the correction, preparation and supplying of the above mentioned drawings and item
information.
Training on Completion
Allow for trainings of Employer's staff related to all system on completion of the
C item
project
Provide for carefully covering up and protecting all of the Works by whatever means
D item
necessary as required during construction and on completion until handover
Disposal of debris
Keep the site free from debris arresting from the works during the construction
E period and leave the site free from debris on completion to the satisfaction of the item
Engineer.
Allow for maintenance of public and private roads used by the Contractor around
F item
the site
The Contractor shall take all necessary precautions in reducing noise caused by
A plant by means of mufflers, silencers, screens and the like in line with HSE item
requirements.
Watering of roads, fill granular materials as required at exit points, clean dirt carried
B item
beyond exit point on daily basis.
Provide for removing all rubbish from the site both as it accumulates from time to
C item
time and at completion.
Provide for cleaning the buildings inside and out, removing stains and touching up
D paint work and polish work and leaving the whole of the works clean, ready for item
occupation and to the satisfaction of the Engineer on completion.
The Contractor shall provide dedicated workmen to observe and clear designated
E item
areas of Foreign Object Debris as it occurs.
The Contractor shall be responsible for cleaning the site and work area completely
of all his temporary installation on completion of the Works shall be required to
grade or rake the area he has occupied to remove all traces of his occupation and
F item
leave the site as close to its original condition as possible. The Contractor shall
provide constantly available labour transport and materials to maintain the
cleanliness and tidiness of the Site.
The Contractor shall make every effort to comply with local authorities rulles and
G item
requirements
The Contractor shall provide guarantee/warrantee for the items as required in the
specification. Guarantee/warrantee are to be taken in the name of the Employer
A item
and forward the originals to the Engineer prior to the issue of the certified of
completion. All Guarantee/Warrantee should be started from the date of completion.
Submittals
Prepare and submit to the Engineer all submittals, materials, working drawings,
B item
record drawings, procurement schedule etc. as required by the Specification.
Samples
The Contractor shall allow for submitting samples of all materials and goods as
required to the Engineer/specification for obtaining his approval, and for paying all
C item
fees and charges etc., in connection therewith. (after approval sample may be used
in construction of the project)
Technical Literature
The Contractor shall obtain copies of the latest editions of standard manuals
D specified in the specification to be kept on site for the use of the Engineer. Upon item
completion of the project they are to be handed over to the Employer.
Statutory Obligations
Allow for all costs for permission, licenses, inspection compliance to regulation and
E item
no objection certificates.
Shop Drawings
F Prepare and submit to the Engineer all shop drawings required by the specification. item
The Contractor shall note that the Employer may appoint other contractors to
carryout certain items of specialist, ancillary or other works. The contractor shall
afford any such other contractors, Employers own workmen or any other duly
A item
constituted authorities all reasonable opportunity to resource and execute their
works. The Contractor shall include for liaising with all such other contractors, direct
workmen or other authorities and for co-coordinating his works with
A preliminary outline programme for carrying out the works shall be prepared by the
Contractor and submitted with the tender. Within 14 days upon receipt of Engineer's
B order to commence the work, the Contractor shall prepare a detailed programme in item
the manner as detailed in the specification for carrying out the works and shall
submit copies of the programme to the Engineer for his approval
This shall be accompanied by labour force monthly loading for each trade, including
C item
sub-contractors, supervisory staff, cash flow and details of materials procurement.
The programme shall be updated and expanded at such times as stated in the
specification and shall be submitted to the Engineer in monthly intervals. Two week
D look ahead programmes shall be Look ahead program shall contains with details of item
Plan and method he propose to employ. No works based on such proposals shall
proceed without the approval of Engineer
In addition to the above, the Contractor shall submit in a Monthly Progress Report
E item
showing all the details in accordance as specified in the
Photographs
Each month during the progress of the works, the Contractor shall arrange at his
own expense the taking of progress photographs from viewpoints selected by the
Engineer sufficient to record progress at the appropriate stage of the work. Six
copies comprising 36 No. 100x75 mm and 6 No. 300 x 250 mm colour photographs
presented in a proper manner approved by the Engineer, together with negatives
D and electronic copy shall be handed to the Engineer for his retention. The item
photographs shall be properly documented with dates, details of the viewpoint and
location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written
permission. The Contractor shall provide suitable albums for the correct storage of
the above photographs as specified in the Specification.
Site Meetings
The Contractor will attend with adequate responsible representation to Site Meeting
A item
and all other meetings to which the Engineer has given instructions to attend.
The Contractor will further undertake to inform and present to attend meeting(s) any
B representative(s) for those sub-contractors, suppliers, etc., under his direct control, item
if so requested by the Engineer.
The Contractor will ensure that all meetings with sub-contractors are held just prior
C item
to the site meetings to ensure accurate reporting on progress, information, etc.
Climatic Condition
Daily maximum and minimum air temperature (including overnight) shall be included
D item
in the Daily Report
Number of hours per day in which works are prevented by inclement weather (flood,
E item
etc.).
Other Costs
Allow for all costs, expenses etc. details of which must be set out below & extended
separately by the contractor incurred in carrying out the requirements of the
G Contract and not otherwise included in this bill. All costs & expenses not entered item
hereinafter will be deemed to be included in the prices inserted elsewhere in this
Bill.
COLLECTION
120
MAINTAIN, alter, adapt and move temporary works and services as necessary. Clear
away when no longer required and make good
vehicle) and fueling
for the duration of
130 RESIDENCY SUPERVISION: Provide for Residency as follows: this Contract
Architect 12-months
Architect x 12-months
Quantity Surveyor x 12-months
M&E + Structural Engineer x 12-months
210
ROOM FOR MEETINGS: Provide suitable temporary accommodation for site
meetings, adequately air conditioned and lit, with table and chairs for [24nr.] twenty
four people. The room may be part of the Contractor's own site offices.
220
CONSULTANTS' SITE OFFICE: Provide and obtain approval of suitable lockable
temporary accommodation and facilities as follows:
Intel Pentium iv 3.0Ghz, 120GB HDD, DVDRW, 1GBEDO RAM, 17” TFT VDU,
Internet ready (3nr.) + HP Laserjet 3 in 1 (printer, scanner and colour copier) (3nr)
Tee
5 90 x 90 x 90mm Nos 2 15,892 3,178 19,070
Reducing Tee
7 100 x 90 x 100mm Nos 4 22,040 4,408 26,448
Bend
11 100mm Nos 10 20,300 4,060 24,360
SUB-TOTAL C/F
MECHANICAL
ITEM UNIT QTY RATE DEL RATE
DESCRIPTION TO SITE FIXED
ITEM DESCRIPTION UNIT RATE DEL RATE
TO SITE FIXED
SUB-TOTAL (C/B)
Socket
15 100mm Nos 50 10,440 2,088 12,528
Reducing Socket
19 100mm x 90mm Nos 2 10,440 2,088 12,528
Nipple
23 100mm Nos 4 48,000 9,600 57,600
FLANGES(PAIRS)
26 100mm Nos 6 24,393 4,879 29,272
Gate Valve
28 100mm Nos 3 208,626 41,725 250,351
Union Connector
31 100mm Nos 3 68,260 13,652 81,912
37
All installation Acessories e.g bushing and cap plugs etc. Lot
MECHANICAL
TOTAL COST
4,742,400.0
6,264,000.0
5,812,992.0
436,800.0
38,140.8
27,144.0
105,792.0
211,584.0
114,422.4
1,538,160.0
243,600.0
305,126.4
183,744.0
167,040.0
20,190,945.6
MECHANICAL
TOTAL COST
TOTAL COST
20,190,945.6
626,400.0
606,720.0
584,640.0
67,680.0
25,056.0
15,168.0
365,400.0
13,932.0
230,400.0
47,328.0
175,392.0
175,629.6
560,400.0
751,053.6
441,840.0
107,520.0
245,736.0
64,368.0
1,002,240.0
MECHANICAL
TOTAL COST
8,100,400.0
200,000.0
1,500,000
3,000,000
39,098,248.8
MECHANICAL
Prepared by Nazedees Borner Nig Ltd
PIPES
1 90mm m 550 7,830 1,566 9,396
Fittings
Elbow
4 90mm Dia Nr 36 5,684 1,137 6,821
Equal Tee
7 90 x 90 x 90mm Nr 2 8,323 1,665 9,988
Reducing Tee
9 90 x 50 x 90mm Nr 60 8,323 1,665 9,988
Nipple
11 90mm Nr 4 28,239 5,648 33,887
Sockets
13 90mm Nr 138 5,684 1,137 6,821
Valves
15 90mm Nr 4 94,029 18,806 112,835
Union Connector
18 90mm Nr 4 38,280 7,656 45,936
418
Prepared by Nazedees Borner Nig Ltd
MISCELLANEOUS ACCESSORIES
TOTAL TO COLLECTION
419
Prepared by Nazedees Borner Nig Ltd
FITTINGS
Bends (45 Degree)
4 200mm Nr 10 7,800 1560 9,360
Socket
7 200mm Nr 25 6,730 1346 8,076
420
Prepared by Nazedees Borner Nig Ltd
COST COLLECTION
SUB-TOTAL =N=
421
Prepared by Nazedees Borner Nig Ltd
AZA, ABUJA
ATION
TOTAL COST
5,167,800
1,263,600
83,592
245,549
119,851
15,600
19,975
7,134
599,256
249,690
135,547
84,634
941,270
92,742
451,339
857,880
350,328
183,744
641,880
422
Prepared by Nazedees Borner Nig Ltd
500,000
12,011,412
423
Prepared by Nazedees Borner Nig Ltd
TOTAL COST
1,040,400
2,924,712
1,075,200
93,600
86,304
515,220
201,900
275,400
132,960
300,000
6,645,696
424
Prepared by Nazedees Borner Nig Ltd
12,011,412
6,645,696
18,657,108
18,657,108
425
Prepared by Nazedees Borner Nig Ltd
1 WATER CLOSET
Water closet suite complete, with pan, cistern,
flush mechanism, seat cover and other
installation accessories. Nr 484 FIX ONLY 6,000
3 SHOWER
Shower complete with shower mixer control,
spout, and other accessories. Nr 117 FIX ONLY 10,000
4 URINAL
Urinal complete with mixer tap,
waste and other accessories. Nr 74 FIX ONLY 5,500
5 Hand Dryer
Hand dryer complete with other installation
accessories Nr 72 FIX ONLY 2,500
6 Soap Dispenser
Soap Dispenser complete with other installation
accessories Nr 72 FIX ONLY 2,000
7 BATHROOM ACCESSORIES
i Soap Dish Nr 117 FIX ONLY 2,000
ii Towel Rail Nr 117 FIX ONLY 2,000
iii Toilet Roll Holder Nr 484 FIX ONLY 2,000
iv Toilet Brush Holder Nr 484 FIX ONLY 2,000
v Wall Mirror Nr 484 FIX ONLY 4,500
v Soap Dispenser Nr 72 FIX ONLY 4,501
8 KITCHEN SINK
i) Stainless Steel kitchen sink complete with
single bowl, single drainer,
swivel bridge mixer tap, chain waste plug and
other installation accessories. Nr 50 FIX ONLY 6,000
TOTAL TO COLLECTION
426
Prepared by Nazedees Borner Nig Ltd
PIPES
1 50mm m 2,217 4,050 810 4,860
Fittings
Elbow
7 50mm Dia Nr 200 1,189 238 1,427
Wallplate
12 20mm Nr 622 4,002 800 4,802
Equal Tee
14 50 x 50 x 50mm Nr 20 1,189 238 1,427
Reducing Tee
19 50 x 25 x 50mm Nr 490 1,189 238 1,427
427
Prepared by Nazedees Borner Nig Ltd
SUB-TOTAL C/F
428
Prepared by Nazedees Borner Nig Ltd
Nipple
24 25mm X 3/4" male Nr 117 1,800 360 2,160
Sockets
28 50mm Nr 550 1,189 238 1,427
Valves
33 50mm Nr 55 11,915 2,383 14,298
36 15mm Angle Valve with chrome cover plate Nr 1,300 3,500 700 4,200
MISCELLANEOUS ACCESSORIES
38 Pressure Testing of Supply Pipes Lot
TOTAL TO COLLECTION
429
Prepared by Nazedees Borner Nig Ltd
FITTINGS
Bends (90 Degree)
3 100mm Nr 686 1,385 277 1,662
TEES
7 100 x 100 x 100mm Nr 532 1,680 336 2,016
TRAPS
10 100mm Vent Cowl Nr 70 6,000 1200 7,200
Socket
13 100mm Nr 1,500 1,385 277 1,662
430
Prepared by Nazedees Borner Nig Ltd
COST COLLECTION
SUB-TOTAL =N=
431
Prepared by Nazedees Borner Nig Ltd
AZA, ABUJA
LATION
TOTAL COST
2,904,000
2,662,000
1,170,000
407,000
180,000
144,000
234,000
234,000
968,000
968,000
2,178,000
324,072
300,000
585,000
13,258,072
432
Prepared by Nazedees Borner Nig Ltd
TOTAL COST
10,774,620
2,713,954
401,856
10,025,137
3,416,724
285,360
62,400
487,872
3,650,942
2,149,963
2,987,093
6,806,429
28,536
9,000
259,200
3,325,476
1,485,091
699,132
180,000
1,050,960
433
Prepared by Nazedees Borner Nig Ltd
1,674,288
2,101,920
54,575,953
434
Prepared by Nazedees Borner Nig Ltd
TOTAL COST
54,575,953
252,720
987,120
594,173
2,046,080
784,740
195,000
20,160
2,680,973
1,069,253
786,390
350,328
6,307,200
5,460,000
3,120,000
3,500,000
3,500,000
86,230,090
435
Prepared by Nazedees Borner Nig Ltd
TOTAL COST
24,709,440
2,342,628
1,140,132
663,864
3,540,060
4,030,722
1,072,512
1,210,320
1,034,280
504,000
1,161,600
15,754,200
2,493,000
333,600
2,000,000
61,990,358
436
Prepared by Nazedees Borner Nig Ltd
13,258,072
86,230,090
61,990,358
161,478,520
161,478,520
437
MAITAM COMPLEX SANITARY WARES
SANITARY WARES BILL OF QUATITIES
ITE DESCRIPTION PRODUCT TYPE PRODUCT QTY BASIC RATE TOTAL AMOUNT
M CODE
1 WC
i Wall mounted dual fluch GURALVIT 485 132,800.00 64,408,000.00
WC Bowl made of VIEGA
Vitreous China Dual
Flush Water
Consumption 6.0-3.0 Lpf
Includes plastic slow-
close seat, structural
steel tubing in-wall
carrier unit rated
2 WHB
i Wash Basin, Wall Hung, GURALVIT 485 109,500.00 53,107,500.00
complete with mixer tap,
pop up waste, 32mm
bottle trap. Armitage
shank or approved
equal.
SUBTOTAL 208,426,020.00
TOTAL 224,057,971.50
S/NO DESCRIPTION QTY UNIT RATE AMOUNT
Split Units
Pipes
Light gauge annealed copper tubes in coils and rigid pipes to BS 2871.
Table Y for connection by means of autogenous welding.
Accessories
J 19mm Internal Diameter Insulation Tube (15mmThick) ARMAFLEX 5541 m 572.40 3,171,668.40
Condensate Pipework
N 50mm 1,460 m 1,177.20 1,718,712.00
2A GENERAL ITEMS
2A1.0 Information Required
2A1.0.1 Location Drawings as defined in General Rule 5.1 item 0.00
Page 1
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS
Page 2
Nigeri2An Institute of Qu2Antity Surveyors To Collection N 0.00
Page 3
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS
Page 4
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS
Page 5
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS
Collection
Page 6
BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION
2B GROUND INVESTIGATION
2B1.1 Trial pits and trenches
2B1.1.1 Number in material other than rock
2B1.1.1.1 Maximum depth not exceeding 1m 0 nr 0.00
2B1.1.1.2 Maximum depth 1-2m 0 nr 0.00
2B1.1.1.3 Maximum depth 2-3m 0 nr 0.00
2B1.1.1.4 Maximum depth 3-5m 0 nr 0.00
2B1.1.1.5 Maximum depth 5-10m 0 nr 0.00
2B1.1.1.6 Maximum depth 10-15m 0 nr 0.00
2B1.1.1.7 Maximum depth 15-20m 0 nr 0.00
2B1.1.1.8 Maximum depth stated exceeding 20m 0 nr 0.00
2B1.1.2 Number in material which includes rock
2B1.1.2.1 Maximum depth not exceeding 1m 0 nr 0.00
2B1.1.2.2 Maximum depth 1-2m 0 nr 0.00
2B1.1.2.3 Maximum depth 2-3m 0 nr 0.00
2B1.1.2.4 Maximum depth 3-5m 0 nr 0.00
2B1.1.2.5 Maximum depth 5-10m 0 nr 0.00
2B1.1.2.6 Maximum depth 10-15m 0 nr 0.00
2B1.1.2.7 Maximum depth 15-20m 0 nr 0.00
2B1.1.2.8 Maximum depth stated exceeding 20m 0 nr 0.00
2B1.1.3 Depth in material other than rock 0m 0.00
2B1.1.4 Depth in rock 0m 0.00
2B1.1.5 Depth supported 0m 0.00
2B1.1.6 Depth backfilled, material stated 0m 0.00
2B1.1.7 Removal of obstructions 0h 0.00
2B1.1.8 Pumping at a stated minimum extraction rate 0h 0.00
2B1.2 Light cable percussion boreholes
2B1.2.1 Number 0 nr 0.00
2B1.2.2 Depth
2B1.2.2.1 In holes of maximum depth not exceeding 5m 0m 0.00
2B1.2.2.2 In holes of maximum depth 5-10m 0m 0.00
2B1.2.2.3 In holes of maximum depth 10-20m 0m 0.00
2B1.2.2.4 In holes of maximum depth 20-30m 0m 0.00
2B1.2.2.5 In holes of maximum depth 30-40m 0m 0.00
2B1.2.2.6 In holes of maximum depth stated exceeding 40m 0m 0.00
2B1.2.3 Depth backfilled, material stated 0m 0.00
2B1.2.4 Chiselling to prove rock or to penetrate obstructions 0h 0.00
Page 7
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION
Page 8
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION
Page 9
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION
Page 10
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION
Page 11
BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION
Collection
Page 12
BESMM4 CIVIL WORK SECTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS
Page 13
BESMM4 2CIVIL WORK SE2CTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS
Page 14
BESMM4 2CIVIL WORK SE2CTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS
Page 15
BESMM4 CIVIL WORK SECTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS
Collection
Page 16
BESMM4 CIVIL WORK SECTIONS DEMOLITION & SITE CLEARANCE
Page 17
BESMM4 CIVIL WORK SECTIONS DEMOLITION & SITE CLEARANCE
Page 18
BESMM4 CIVIL WORK SECTIONS DEMOLITION & SITE CLEARANCE
Collection
Page 19
BESMM4 CIVIL WORK SECTIONS EARTHWORKS
2E EARTHWORKS
2E1.1 Excavation by dredging
2E1.2 Excavation for cuttings
2E1.2.1 Topsoil 0 m3 0.00
Material other than topsoil, rock or artificial hard
2E1.2.2 material 0 m3 0.00
2E1.2.3 Rock 0 m3 0.00
Stated artificial hard material exposed at the
2E1.2.4 Commencing Surface 0 m3 0.00
Stated artificial hard material not exposed at the
2E1.2.5 Commencing Surface 0 m3 0.00
2E1.3 Excavation for foundations
2E1.3.1 Topsoil
Material other than topsoil, rock or artificial hard
2E1.3.2 material
2E1.3.3 Rock
Stated artificial hard material exposed at the
2E1.3.4 Commencing Surface
Stated artificial hard material not exposed at the
2E1.3.5 Commencing Surface
Controlled and hazardous material exposed at the
2E1.3.6 commencing surface
Controlled and hazardous material not exposed at the
2E1.3.7 commencing surface
2E1.3.7.1 Maximum depth not exceeding 0.25m 0 m3 0.00
2E1.3.7.2 Maximum depth 0.25-0.5m 0 m3 0.00
2E1.3.7.3 Maximum depth 0.5-1m 0 m3 0.00
2E1.3.7.4 Maximum depth 1-2m 0 m3 0.00
2E1.3.7.5 Maximum depth 2-5m 0 m3 0.00
2E1.3.7.6 Maximum depth 5-10m 0 m3 0.00
2E1.3.7.7 Maximum depth 10-15m 0 m3 0.00
2E1.3.7.8 Maximum depth stated exceeding 15m 0 m3 0.00
2E1.4 General excavation
2E1.4.1 Topsoil
Material other than topsoil, rock or artificial hard
2E1.4.2 material
2E1.4.3 Rock
Stated artificial hard material exposed at the
2E1.4.4 Commencing Surface
Stated artificial hard material not exposed at the
2E1.4.5 Commencing Surface
2E1.4.5.1 Maximum depth not exceeding 0.25m 0 m3 0.00
2E1.4.5.2 Maximum depth 0.25-0.5m 0 m3 0.00
2E1.4.5.3 Maximum depth 0.5-1m 0 m3 0.00
2E1.4.5.4 Maximum depth 1-2m 0 m3 0.00
Page 20
B2ESMM4 CIVIL WORK S2ECTIONS EARTHWORKS
Page 21
B2ESMM4 CIVIL WORK S2ECTIONS EARTHWORKS
Page 22
BESMM4 CIVIL WORK SECTIONS EARTHWORKS
Collection
Page 23
BESMM4 CIVIL WORK SECTIONS IN SITU CONCRETE
2F IN SITU CONCRETE
Provision of concrete, designed Concrete: Cement to
2F1.1 BS12 or BS146 20mm aggregate
2F1.1.1 Strength C8/10 0 m3 0.00
2F1.1.2 Strength C12/15 m3
2F1.1.3 Strength C16/20 m3
2F1.1.4 Strength C20/25 m3
2F1.1.5 Strength C25/30 m3
2F1.1.6 Strength C28/35 m3
2F1.1.7 Strength C30/37 m3
2F1.1.8 Strength C32/40 m3
Provision of concrete, designated Concrete: Cement
2F1.2 to BS12 or BS146 20mm aggregate
2F1.2.1 Strength RC20/25 0 m3 0.00
2F1.2.2 Strength RC 25/30 m3
2F1.2.3 Strength RC28/35 m3
2F1.2.4 Strength RC30/37 m3
2F1.2.5 Strength RC32/40 m3
2F1.2.6 Strength RC35/45 m3
2F1.2.7 Strength RC40/50 0 m3 0.00
Page 24
BESMM4 CIVIL WORK SECTIONS IN SITU CONCRETE
Page 25
BESMM4 CIVIL WORK SECTIONS IN SITU CONCRETE
Collection
Page 26
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES
2G CONCRETE ANCILLARIES
2G1.1 Formwork: rough finish
2G1.2 Formwork: fair finish
2G1.3 Formwork: other stated finish
2G1.4 Formwork: stated surface features
2G1.1.1 Plane horizontal
2G1.1.2 Plane sloping
2G1.1.3 Plane battered
2G1.1.4 Plane vertical
2G1.1.5 Curved to one radius in one plane
2G1.1.1.1 Width not exceeding 0.1m 0m 0.00
2G1.1.1.2 Width 0.1-0.2m 0m 0.00
2G1.1.1.3 Width 0.2-0.4m 0 m2 0.00
2G1.1.1.4 Width 0.4-1.22m 0 m2 0.00
2G1.1.1.5 Width exceeding 1.22m 0 m2 0.00
2G1.1.6 Other curved 0 m2 0.00
2G1.1.7 For voids
2G1.1.7.1 Small void depth not exceeding 0.5m 0 nr 0.00
2G1.1.7.2 Small void depth 0.5-1m 0 nr 0.00
2G1.1.7.3 Small void depth 1-2m 0 nr 0.00
2G1.1.7.4 Small void depth stated exceeding 2m 0 nr 0.00
2G1.1.7.5 Large void depth not exceeding 0.5m 0 nr 0.00
2G1.1.7.6 Large void depth 0.5-1m 0 nr 0.00
2G1.1.7.7 Large void depth 1-2m 0 nr 0.00
2G1.1.7.8 Large void depth stated exceeding 2m 0 nr 0.00
2G1.1.8 For concrete components of constant cross-section
2G1.1.8.1 Beams 0m 0.00
2G1.1.8.2 Columns 0m 0.00
2G1.1.8.3 Walls 0m 0.00
2G1.1.8.4 Other members 0m 0.00
2G1.1.8.5 Projections 0m 0.00
2G1.1.8.6 Intrusions 0m 0.00
2G1.5 Reinforcement
2G1.5.1 Plain round steel bars to BS 4449
2G1.5.2 Deformed steel bars to BS 4449
2G1.5.3 Stainless steel bars of stated quality
2G1.5.4 Reinforcing bars of other stated material
2G1.5.1.1 Nominal size 6mm 0.00 t 0.00
2G1.5.1.2 Nominal size 8mm 0.00 t 0.00
Page 27
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES
Page 28
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES
2G1.8.3 Inserts
2G1.8.3.1 Linear inserts 0m 0.00
2G1.8.3.2 Other inserts 0 nr 0.00
2G1.8.4 Grouting under plates
2G1.8.4.1 Area not exceeding 0.1m2 0 nr 0.00
2G1.8.4.2 Area 0.1-0.5m2 0 nr 0.00
2G1.8.4.3 Area 0.5-1m2 0 nr 0.00
2G1.8.4.4 Area stated exceeding 1m2 0 nr 0.00
Page 29
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES
Collection
Page 30
BESMM4 CIVIL WORK SECTIONS PRECAST CONCRETE
2H PRECAST CONCRETE
2H1.1 Beams
2H1.2 Prestressed pre-tensioned beams
2H1.3 Prestressed post-tensioned beams
2H1.4 Columns
2H1.1.1 Length not exceeding 5m
2H1.1.2 Length 5-7m
2H1.1.3 Length 7-10m
2H1.1.4 Length 10-15m
2H1.1.5 Length 15-20m
2H1.1.6 Length 20-30m
2H1.1.7 Length exceeding 30m
2H1.1.1.1 Mass not exceeding 250kg 0 nr 0.00
2H1.1.1.2 Mass 250-500kg 0 nr 0.00
2H1.1.1.3 Mass 500kg-1t 0 nr 0.00
2H1.1.1.4 Mass 1-2t 0 nr 0.00
2H1.1.1.5 Mass 2-5t 0 nr 0.00
2H1.1.1.6 Mass 5-10t 0 nr 0.00
2H1.1.1.7 Mass 10-20t 0 nr 0.00
2H1.1.1.8 Mass stated exceeding 20t 0 nr 0.00
2H1.5 Slabs
2H1.5.1 Area not exceeding 1m2
2H1.5.2 Area 1-4m2
2H1.5.3 Area 4-15m2
2H1.5.4 Area 15-50m2
2H1.5.5 Area exceeding 50m2
2H1.5.1.1 Mass not exceeding 250kg 0 nr 0.00
2H1.5.1.2 Mass 250-500kg 0 nr 0.00
2H1.5.1.3 Mass 500kg-1t 0 nr 0.00
2H1.5.1.4 Mass 1-2t 0 nr 0.00
2H1.5.1.5 Mass 2-5t 0 nr 0.00
2H1.5.1.6 Mass 5-10t 0 nr 0.00
2H1.5.1.7 Mass 10-20t 0 nr 0.00
2H1.5.1.8 Mass stated exceeding 20t 0 nr 0.00
2H1.6 Segmental units
2H1.6.1 Generally
2H1.6.1.1 Mass not exceeding 250kg 0 nr 0.00
2H1.6.1.2 Mass 250-500kg 0 nr 0.00
2H1.6.1.3 Mass 500kg-1t 0 nr 0.00
Page 31
BESMM4 CIVIL WORK SECTIONS PRECAST CONCRETE
Page 32
BESMM4 CIVIL WORK SECTIONS PRECAST CONCRETE
Collection
Page 33
BESMM4 CIVIL WORK SECTIONS PIPEWORK - PIPES
2J PIPEWORK - PIPES
2J1.1 Clay pipes
2J1.2 Concrete pipes
2J1.3 Iron pipes
2J1.4 Steel pipes
2J1.5 Polyvinyl chloride pipes
2J1.6 Glass reinforced plastic pipes
2J1.7 High density polyethylene pipes
2J1.8 Medium density polyethylene pipes
2J1.2.1 Nominal bore not exceeding 200mm
2J1.2.2 Nominal bore 200-300mm
2J1.2.3 Nominal bore 300-600mm
2J1.2.4 Nominal bore 600-900mm
2J1.2.5 Nominal bore 900-1200mm
2J1.2.6 Nominal bore 1200-1500mm
2J1.2.7 Nominal bore 1500-1800mm
2J1.2.8 Nominal bore exceeding 1800mm
2J1.2.1.1 Not in trenches 0m 0.00
2J1.2.1.2 In trenches, depth not exceeding 1.5m 0m 0.00
2J1.2.1.3 In trenches, depth 1.5-2m 0m 0.00
2J1.2.1.4 In trenches, depth 2-2.5m 0m 0.00
2J1.2.1.5 In trenches, depth 2.5-3m 0m 0.00
2J1.2.1.6 In trenches, depth 3-3.5m 0m 0.00
2J1.2.1.7 In trenches, depth 3.5-4m 0m 0.00
2J1.2.1.8 In trenches, depth exceeding 4m 0m 0.00
Page 34
BESMM4 CIVIL WORK SECTIONS PIPEWORK - PIPES
Collection
Page 35
BESMM4 CIVIL WORK SECTIONS PIPEWORK - FITTINGS & VALVES
Page 36
BESMM4 CIVIL WOR2K SECTIONS PIPEWORK - FITTINGS & VALVES
Page 37
BESMM4 CIVIL WORK SECTIONS PIPEWORK - FITTINGS & VALVES
Collection
Page 38
BESMM4 CIVIL WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S
Page 39
BESMM4 CIVI2L WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S
Page 40
BESMM4 CIVI2L WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S
Page 41
BESMM4 CIVI2L WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S
Page 42
BESMM4 CIVIL WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S
Collection
Page 43
BESMM4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...
Page 44
BES2M2M4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...
Page 45
BES2M2M4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...
Page 46
BESMM4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...
Collection
Page 47
BESMM4 CIVIL WORK SECTIONS STRUCTURAL METALWORK
2N STRUCTURAL METALWORK
2N1.1 Fabrication of main members for bridges
2N1.1.1 Rolled sections
2N1.1.2 Plates or flats
2N1.1.3 Built-up box or hollow sections
2N1.1.3.1 Straight on plan 0.00 t 0.00
2N1.1.3.2 Curved on plan 0.00 t 0.00
2N1.1.3.3 Straight on plan and cambered 0.00 t 0.00
2N1.1.3.4 Curved on plan and cambered 0.00 t 0.00
2N1.2 Fabrication of subsidiary members for bridges
2N1.2.1 Deck panels
2N1.2.1.1 Straight on plan 0.00 t 0.00
2N1.2.1.2 Curved on plan 0.00 t 0.00
2N1.2.1.3 Straight on plan and cambered 0.00 t 0.00
2N1.2.1.4 Curved on plan and cambered 0.00 t 0.00
2N1.2.2 Bracings 0.00 t 0.00
2N1.2.3 External diaphragms 0.00 t 0.00
2N1.3 Fabrication of members for frames
2N1.4 Fabrication of other members
2N1.4.1 Columns
2N1.4.2 Beams
2N1.4.3 Portal frames
2N1.4.4 Trestles, towers and built-up columns
2N1.4.5 Trusses and built-up girders
2N1.4.6 Bracings, purlins and cladding rails
2N1.4.6.1 Straight on plan 0.00 t 0.00
2N1.4.6.2 Curved on plan 0.00 t 0.00
2N1.4.6.3 Straight on plan and cambered 0.00 t 0.00
2N1.4.6.4 Curved on plan and cambered 0.00 t 0.00
2N1.4.7 Grillages 0.00 t 0.00
2N1.4.8 Anchorages and holding down bolt assemblies 0 nr 0.00
2N1.5 Erection of members for bridges
2N1.6 Erection of members for frames
2N1.7 Erection of other members
2N1.7.1 Trial erection 0.00 t 0.00
2N1.7.2 Permanent erection 0.00 t 0.00
Page 48
BESMM4 CIVIL WORK SECTIO2NS STRUCTURAL METALWORK
Page 49
BESMM4 CIVIL WORK SECTIONS STRUCTURAL METALWORK
Collection
Page 50
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS METALWORK
2P MISCELLANEOUS METALWORK
Page 51
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS METALWORK
Collection
Page 52
BESMM4 CIVIL WORK SECTIONS TIMBER
2Q TIMBER
2Q1.1 Hardwood components
2Q1.2 Softwood components
2Q1.1.1 Cross-sectional area not exceeding 0.01m2
2Q1.1.2 Cross-sectional area 0.01-0.02m2
2Q1.1.3 Cross-sectional area 0.02-0.04m2
2Q1.1.4 Cross-sectional area 0.04-0.1m2
2Q1.1.5 Cross-sectional area 0.1-0.2m2
2Q1.1.6 Cross-sectional area 0.2-0.4m2
2Q1.1.7 Cross-sectional area stated exceeding 0.4m2
2Q1.1.7.1 Length not exceeding 1.5m 0m 0.00
2Q1.1.7.2 Length 1.5-3m 0m 0.00
2Q1.1.7.3 Length 3-5m 0m 0.00
2Q1.1.7.4 Length 5-8m 0m 0.00
2Q1.1.7.5 Length 8-12m 0m 0.00
2Q1.1.7.6 Length 12-20m 0m 0.00
2Q1.1.7.7 Length stated exceeding 20m 0m 0.00
2Q1.3 Hardwood decking
2Q1.4 Softwood decking
2Q1.4.1 Thickness not exceeding 25 mm 0 m2 0.00
2Q1.4.2 Thickness 25-50 mm 0 m2 0.00
2Q1.4.3 Thickness 50-75 mm 0 m2 0.00
2Q1.4.4 Thickness 75-100 mm 0 m2 0.00
2Q1.4.5 Thickness 100-125 mm 0 m2 0.00
2Q1.4.6 Thickness 125-150 mm 0 m2 0.00
2Q1.4.7 Thickness exceeding 150 mm 0 m2 0.00
2Q1.5 Fittings and fastenings
2Q1.5.1 Straps 0 nr 0.00
2Q1.5.2 Spikes 0 nr 0.00
2Q1.5.3 Coach screws 0 nr 0.00
2Q1.5.4 Bolts 0 nr 0.00
2Q1.5.5 Plates 0 nr 0.00
Page 53
BESMM4 CIVIL WORK SECTIONS TIMBER
Collection
Page 54
BESMM4 CIVIL WORK SECTIONS PILES
2R PILES
2R1.1 Bored cast in place concrete piles
2R1.2 Driven cast in place concrete piles
2R1.1.1 Diameter 300mm or 350mm
2R1.1.2 Diameter 400mm or 450mm
2R1.1.3 Diameter 500mm or 550mm
2R1.1.4 Diameter 600mm or 750mm
2R1.1.5 Diameter 900mm or 1050mm
2R1.1.6 Diameter 1200mm or 1350mm
2R1.1.7 Diameter 1500mm
2R1.1.1.1 Number of piles 0 nr 0.00
2R1.1.1.2 Concreted length 0m 0.00
2R1.1.1.3 Depth bored or driven to stated maximum depth 0m 0.00
2R1.3 Preformed concrete piles
2R1.4 Preformed concrete sheet piles
2R1.5 Timber piles
2R1.5.1 Cross-sectional area not exceeding 0.025m2
2R1.5.2 Cross-sectional area 0.025-0.05m2
2R1.5.3 Cross-sectional area 0.05-0.1m2
2R1.5.4 Cross-sectional area 0.5-0.15m2
2R1.5.5 Cross-sectional area 0.15-0.25m2
2R1.5.6 Cross-sectional area 0.25-0.5m2
2R1.5.7 Cross-sectional area 0.5-1m2
2R1.5.8 Cross-sectional area exceeding 1m2
2R1.5.8.1 Number of piles of stated length 0 nr 0.00
2R1.5.8.2 Depth driven 0m 0.00
2R1.6 Isolated steel piles
2R1.6.1 Mass not exceeding 15kg/m
2R1.6.2 Mass 15-30kg/m
2R1.6.3 Mass 30-60kg/m
2R1.6.4 Mass 60-120kg/m
2R1.6.5 Mass 120-250kg/m
2R1.6.6 Mass 250-500kg/m
2R1.6.7 Mass 500 kg/m-1t/m
2R1.6.8 Mass exceeding 1t/m
2R1.6.8.1 Number of piles of stated length 0 nr 0.00
2R1.6.8.2 Depth driven 0m 0.00
Page 55
BESMM4 CIVIL WO2RK SECTIONS PILES
Page 56
BESMM4 CIVIL WORK SECTIONS PILES
Collection
Page 57
BESMM4 CIVIL WORK SECTIONS PILING ANCILLARIES
2S PILING ANCILLARIES
2S1.1 Cast in place concrete piles
2S1.1.1 Pre-boring
2S1.1.2 Backfilling empty bore with stated material
2S1.1.3 Permanent casings each length not exceeding 13m
2S1.1.4 Permanent casings each length exceeding 13m
2S1.1.5 Enlarged bases
2S1.1.6 Cutting off surplus lengths
2S1.1.7 Preparing heads
2S1.1.7.1 Diameter 300mm or 350mm 0m 0.00
2S1.1.7.2 Diameter 400mm or 450mm 0m 0.00
2S1.1.7.3 Diameter 500mm or 550mm 0m 0.00
2S1.1.7.4 Diameter 600mm or 750mm 0m 0.00
2S1.1.7.5 Diameter 900mm or 1050mm 0m 0.00
2S1.1.7.6 Diameter 1200mm or 1350mm 0m 0.00
2S1.1.7.7 Diameter 1500mm 0m 0.00
2S1.2 Cast in place concrete piles
2S1.2.1 Reinforcement
2S1.2.1.1 Straight bars nominal size not exceeding 25mm 0.00 t 0.00
2S1.2.1.2 Straight bars nominal size exceeding 25mm 0.00 t 0.00
2S1.2.1.3 Helical bars of stated nominal size 0.00 t 0.00
2S1.3 Preformed concrete piles
2S1.4 Timber piles
2S1.4.1 Pre-boring
2S1.4.2 Jetting
2S1.4.3 Filling hollow piles with concrete
2S1.4.4 Number of pile extensions
Length of pile extensions each length not exceeding
2S1.4.5 3m
2S1.4.6 Length of pile extensions each length exceeding 3m
2S1.4.7 Cutting off surplus lengths
2S1.4.8 Preparing heads
2S1.4.8.1 Cross-sectional area not exceeding 0.025m2 0m 0.00
2S1.4.8.2 Cross-sectional area 0.025-0.05m2 0m 0.00
2S1.4.8.3 Cross-sectional area 0.05-0.1m2 0m 0.00
2S1.4.8.4 Cross-sectional area 0.1-0.15m2 0m 0.00
2S1.4.8.5 Cross-sectional area 0.15-0.25m2 0m 0.00
2S1.4.8.6 Cross-sectional area 0.25-0.5m2 0m 0.00
2S1.4.8.7 Cross-sectional area 0.5-1m2 0m 0.00
Page 58
BE2SMM4 CIVIL WORK 2SECTION2S PILING ANCILLARIES
Page 59
BE2SMM4 CIVIL WORK 2SECTION2S PILING ANCILLARIES
Page 60
BESMM4 CIVIL WORK SECTIONS PILING ANCILLARIES
Collection
Page 61
BESMM4 CIVIL WORK SECTIONS ROADS AND PAVINGS
Page 62
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS
Page 63
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS
Page 64
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS
Page 65
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS
Page 66
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS
Page 67
BESMM4 CIVIL WORK SECTIONS ROADS AND PAVINGS
Collection
Page 68
BESMM4 CIVIL WORK SECTIONS RAIL TRACK
2U RAIL TRACK
2U1.1 Track foundations
2U1.1.1 Bottom ballast 0 m3 0.00
2U1.1.2 Top ballast 0 m3 0.00
2U1.1.3 Blinding 0 m2 0.00
2U1.1.4 Blankets 0 m2 0.00
2U1.1.5 Waterproof membranes 0 m2 0.00
2U1.1.6 Ballast cleaning 0 m3 0.00
2U1.1.7 Tamping 0m 0.00
2U1.1.8 Pneumatic ballast 0m 0.00
2U1.2 Taking up
2U1.2.1 Bullhead rails
2U1.2.2 Flat bottom rails
2U1.2.3 Dock and crane rails
2U1.2.3.1 Plain track 0m 0.00
2U1.2.3.2 Turnouts 0 nr 0.00
2U1.2.3.3 Diamond crossings 0 nr 0.00
2U1.2.4 Check and guard rails 0m 0.00
2U1.2.5 Conductor rails 0m 0.00
2U1.2.6 Sundries
2U1.2.6.1 Buffer stops 0 nr 0.00
2U1.2.6.2 Retarders 0 nr 0.00
2U1.2.6.3 Wheel stops 0 nr 0.00
2U1.2.6.4 Lubricators 0 nr 0.00
2U1.2.6.5 Switch heaters 0 nr 0.00
2U1.2.6.6 Switch levers 0 nr 0.00
2U1.2.6.7 Eutectic strip 0m 0.00
2U1.3 Lifting, packing and slewing
2U1.3.1 Bullhead rail track 0 nr 0.00
2U1.3.2 Flat bottom rail track 0 nr 0.00
2U1.3.3 Existing rail turning and fixing 0 nr 0.00
2U1.3.4 Rerailing 0 nr 0.00
2U1.3.5 Stressing rail 0 nr 0.00
Page 69
BESMM4 CIVIL WORK SECTIONS RAIL TRACK
Page 70
BESMM4 CIVIL WORK SECTIONS RAIL TRACK
Page 71
BESMM4 CIVIL WORK SECTIONS RAIL TRACK
Page 72
BESMM4 CIVIL WORK SECTIONS RAIL TRACK
Collection
Page 73
BESMM4 CIVIL WORK SECTIONS TUNNELS
2V1.1 Excavation
2V1.1.1 Tunnels in rock
2V1.1.2 Tunnels in other stated material
2V1.1.3 Shafts in rock
2V1.1.4 Shafts in other stated material
2V1.1.5 Other cavities in rock
2V1.1.6 Other cavities in other stated material
2V1.1.6.1 Stated diameter not exceeding 2m 0 m3 0.00
2V1.1.6.2 Diameter 2-3m 0 m3 0.00
2V1.1.6.3 Diameter 3-4m 0 m3 0.00
2V1.1.6.4 Diameter 4-5m 0 m3 0.00
2V1.1.6.5 Diameter 5-6m 0 m3 0.00
2V1.1.6.6 Diameter 6-7m 0 m3 0.00
2V1.1.6.7 Diameter 7-8m 0 m3 0.00
2V1.1.6.8 Diameter exceeding 8m 0 m3 0.00
2V1.1.7 Excavated surfaces in rock 0 m2 0.00
2V1.1.8 Excavated surfaces in other stated material 0 m2 0.00
2V1.2 In-situ lining to tunnels
2V1.3 In-situ lining to shafts
2V1.4 In-situ lining to other cavities
2V1.4.1 Sprayed concrete primary
2V1.4.2 Sprayed concrete secondary
2V1.4.3 Cast concrete primary
2V1.4.4 Cast concrete secondary
2V1.4.5 Formwork to stated finish
2V1.4.5.1 Stated diameter not exceeding 2m 0 m3 0.00
2V1.4.5.2 Stated diameter 2-3m 0 m2 0.00
2V1.4.5.3 Stated diameter 3-4m 0 m2 0.00
2V1.4.5.4 Stated diameter 4-5m 0 m2 0.00
2V1.4.5.5 Stated diameter 5-6m 0 m2 0.00
2V1.4.5.6 Stated diameter 6-7m 0 m2 0.00
2V1.4.5.7 Stated diameter 7-8m 0 m2 0.00
2V1.4.5.8 Stated diameter exceeding 8m 0 m2 0.00
Page 74
BESMM4 CI2VIL WORK SECTIONS TUNNELS
Qty Unit Rate N K
TUNNELS continued ...
2V1.5 Preformed segmental lining to tunnels
2V1.6 Preformed segmental lining to shafts
2V1.7 Preformed segmental lining to other cavities
2V1.7.1 Precast concrete bolted rings
2V1.7.2 Precast concrete expanded rings
2V1.7.3 Cast iron bolted rings
2V1.7.4 Cast iron expanded rings
2V1.7.5 Nodular iron rings
2V1.7.6 Fabricated steel rings
2V1.7.6.1 Stated diameter not exceeding 2m 0 m3 0.00
2V1.7.6.2 Stated diameter 2-3m 0 m2 0.00
2V1.7.6.3 Stated diameter 3-4m 0 m2 0.00
2V1.7.6.4 Stated diameter 4-5m 0 m2 0.00
2V1.7.6.5 Stated diameter 5-6m 0 m2 0.00
2V1.7.6.6 Stated diameter 6-7m 0 m2 0.00
2V1.7.6.7 Stated diameter 7-8m 0 m2 0.00
2V1.7.6.8 Stated diameter exceeding 8m 0 m2 0.00
2V1.8 Lining ancillaries
2V1.8.1 Parallel circumferential packing 0 nr 0.00
2V1.8.2 Tapered circumferential packing 0 nr 0.00
2V1.8.3 Stepped junctions 0 nr 0.00
2V1.8.4 Caulking of stated material 0m 0.00
2V1.9 Support and stablization
2V1.9.1 Rock bolts
2V1.9.1.1 Mechanical 0m 0.00
2V1.9.1.2 Pre-grouted impacted 0m 0.00
2V1.9.1.3 Chemical end anchor 0m 0.00
2V1.9.1.4 Chemical grouted 0m 0.00
2V1.9.1.5 Chemically filled 0m 0.00
2V1.9.2 Internal support
2V1.9.2.1 Steel arches supply 0.00 t 0.00
2V1.9.2.2 Steel arches erection 0.00 t 0.00
2V1.9.2.3 Timber supports supply 0 m3 0.00
2V1.9.2.4 Timber supports erection 0 m3 0.00
2V1.9.2.5 Lagging 0 m2 0.00
2V1.9.2.6 Sprayed concrete 0 m2 0.00
2V1.9.2.7 Mesh or link 0 m2 0.00
2V1.9.3 Pressure grouting
2V1.9.3.1 Sets of drilling and grouting plant 0 nr 0.00
2V1.9.3.2 Face packers 0 nr 0.00
2V1.9.3.3 Deep packers of stated size 0 nr 0.00
2V1.9.3.4 Drilling and flushing to stated diameter 0m 0.00
2V1.9.3.5 Re-drilling and flushing 0m 0.00
2V1.9.3.6 Injection of grout materials of stated composition 0.00 t 0.00
Page 75
BESMM4 CIVIL WORK SECTIONS TUNNELS
Qty Unit Rate N K
Collection
Page 76
BESMM4 CIVIL WORK SECTIONS BRICKWORK, BLOCKWORK & MASONRY
Qty Unit Rate N K
2W BRICKWORK, BLOCKWORK AND MASONRY
2W1.1 Common Brickwork
2W1.2 Facing Brickwork
2W1.3 Engineering brickwork
2W1.4 Lightweight blockwork
2W1.5 Dense concrete blockwork
2W1.6 Artificial stone blockwork
2W1.7 Ashlar masonry
2W1.8 Rubble masonry
2W1.8.1 Thickness not exceeding 150mm
2W1.8.2 Thickness 150-250mm
2W1.8.3 Thickness 250-500mm
2W1.8.4 Thickness 500mm-1m
2W1.8.5 Thickness exceeding 1m
2W1.8.5.1 Vertical straight walls 0 m2 0.00
2W1.8.5.2 Vertical curved walls 0 m2 0.00
2W1.8.5.3 Battered straight walls 0 m2 0.00
2W1.8.5.4 Battered curved walls 0 m2 0.00
2W1.8.5.5 Vertical facing to concrete 0 m2 0.00
2W1.8.5.6 Battered facing to concrete 0 m2 0.00
2W1.8.5.7 Casing to metal sections 0 m2 0.00
Columns and piers of stated cross- sectional
2W1.8.6
dimensions 0m 0.00
2W1.8.7 Surface features
2W1.8.7.1 Copings and sills, material stated 0m 0.00
2W1.8.7.2 Rebates and chases 0m 0.00
2W1.8.7.3 Cornices 0m 0.00
2W1.8.7.4 Band courses 0m 0.00
2W1.8.7.5 Corbels 0m 0.00
2W1.8.7.6 Pilasters 0m 0.00
2W1.8.7.7 Plinths 0m 0.00
2W1.8.7.8 Fair facing 0 m2 0.00
2W1.8.8 Ancillaries
2W1.8.8.1 Joint reinforcement 0m 0.00
2W1.8.8.2 Damp proof courses 0m 0.00
2W1.8.8.3 Movement joints 0m 0.00
2W1.8.8.4 Bonds to existing work 0 m2 0.00
2W1.8.8.5 Infills of stated thickness 0 m2 0.00
2W1.8.8.6 Fixings and ties 0 m2 0.00
Built-in pipes and ducts cross-sectional area not
2W1.8.8.7
exceeding0.05m2 0 nr 0.00
Built-in pipes and ducts cross- sectional area
2W1.8.8.8
stated exceeding 0.05m2 0 nr 0.00
Page 77
BESMM4 CIVIL WORK SECTIONS BRICKWORK, BLOCKWORK & MASONRY
Qty Unit Rate N K
Collection
Page 78
BESMM4 CIVIL WORK SECTIONS PAINTING
Qty Unit Rate N K
2X PAINTING
2X1.1 Lead, iron or zinc based primer paint
2X1.2 Etch primer paint
2X1.3 Oil paint
2X1.4 Alkyd gloss paint
2X1.5 Emulsion paint
2X1.6 Cement paint
2X1.7 Epoxy or polyurethane paint
2X1.8 Bituminous or coal tar paint
2X1.8.1 Metal, other than metal sections andpipework
2X1.8.2 Timber
2X1.8.3 Smooth concrete
2X1.8.4 Rough concrete
2X1.8.5 Masonry
2X1.8.6 Brickwork and blockwork
Upper surfaces inclined at an angle not exceeding
2X1.8.6.1
30 Deg to the horizontal 0 m2 0.00
2X1.8.6.2 Upper surfaces at 30-60 Deg to the horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2X1.8.6.3
the horizontal 0 m2 0.00
Upper surfaces inclined at an angle not exceeding
2X1.8.6.4
30 Deg to the horizontal 0 m2 0.00
2X1.8.6.5 Surfaces of width not exceeding 300mm 0m 0.00
2X1.8.6.6 Surfaces of width 300mm-1m 0m 0.00
2X1.8.6.7 Isolated groups of surfaces 0 nr 0.00
2X1.8.7 Metal sections 0 m2 0.00
2X1.8.8 Pipework 0 m2 0.00
Page 79
BESMM4 CIVIL WORK SECTIONS WATERPROOFING
Qty Unit Rate N K
2Y WATERPROOFING
2Y1.1 Damp proofing
2Y1.2 Tanking
2Y1.3 Roofing
2Y1.3.1 Asphalt
2Y1.3.2 Sheet metal
2Y1.3.3 Waterproof sheeting
2Y1.3.4 Waterproof coating
2Y1.3.5 Rendering in ordinary cement mortar
2Y1.3.6 Rendering in waterproof cement mortar
2Y1.3.7 Tiles
Upper surfaces inclined at an angle not exceeding 30
2Y1.3.7.1 Deg to the horizontal 0 m2 0.00
Upper surfaces inclined at 30-60 Deg to the
2Y1.3.7.2 horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2Y1.3.7.3 the horizontal 0 m2 0.00
2Y1.3.7.4 Curved surfaces 0 m2 0.00
2Y1.3.7.5 Domed surfaces 0 m2 0.00
2Y1.3.7.6 Surfaces of width not exceeding300mm 0m 0.00
2Y1.3.7.7 Surfaces of width 300mm-1m 0m 0.00
2Y1.3.7.8 Isolated groups of surfaces 0 nr 0.00
2Y1.4 Protective layers
2Y1.4.1 Sand asphalt
2Y1.4.2 Flexible sheeting
2Y1.4.3 Sand
2Y1.4.4 Sand and cement screed
2Y1.4.5 Tiles
Upper surfaces inclined at an angle not exceeding
2Y1.4.5,1 30 Deg to the horizontal 0 m2 0.00
Upper surfaces inclined at 30-60 Deg to the
2Y1.4.5,2 horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2Y1.4.5,3 the horizontal 0 m2 0.00
2Y1.4.5,4 Curved surfaces 0 m2 0.00
2Y1.4.5,5 Domed surfaces 0 m2 0.00
2Y1.4.5,6 Surfaces of width not exceeding 300mm 0m 0.00
2Y1.4.5,7 Surfaces of width 300mm-1m 0m 0.00
2Y1.4.5,8 Isolated groups of surfaces 0 nr 0.00
2Y1.5 Sprayed or brushed waterproofing 0 m2 0.00
Nigerian Institute of Quantit2Y Surve2Yors To Collection N 0.00
Page 80
BESMM4 CIVIL WORK SECTIONS WATERPROOFING
Qty Unit Rate N K
WATERPROOFING continued ...
2Y1.6 Sheet lining membrane
2Y1.6.1 Butyl rubber
2Y1.6.2 EPDM rubber
2Y1.6.3 PVC
2Y1.6.4 Polypropylene
2Y1.6.5 Polythylene
2Y1.6.6 Polyurethane
2Y1.6.7 Proprietary
Upper surfaces inclined at an angle not exceeding
2Y1.6.7.1 30 Deg to the horizontal 0 m2 0.00
Upper surfaces inclined at 30-60 Deg to the
2Y1.6.7.2 horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2Y1.6.7.3 the horizontal 0 m2 0.00
2Y1.6.7.4 Curved surfaces 0 m2 0.00
2Y1.6.7.5 Domed surfaces 0 m2 0.00
2Y1.6.7.6 Surfaces of width not exceeding 300mm 0 m2 0.00
2Y1.6.7.7 surfaces of width 300mm - 1m 0 m2 0.00
2Y1.6.7.8 Isolated groups of surfaces 0 nr 0.00
Page 81
BESMM4 CIVIL WORK SECTIONS WATERPROOFING
Qty Unit Rate N K
Collection
Page 82
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS WORK
Qty Unit Rate N K
2Z MISCELLANEOUS WORK
2Z1.1 Fences
2Z1.1.1 Timber post and rail
2Z1.1.2 Timber post and wire
2Z1.1.3 Concrete post and wire
2Z1.1.4 Metal post and wire
2Z1.1.5 Coated metal post and wire
2Z1.1.6 Timber close boarded
2Z1.1.7 Metal guard system
2Z1.1.8 Metal crash barriers
2Z1.1.8.1 Height not exceeding 1m 0m 0.00
2Z1.1.8.2 Height 1-1.25m 0m 0.00
2Z1.1.8.3 Height 1.25-1.5m 0m 0.00
2Z1.1.8.4 Height 1.5-2m 0m 0.00
2Z1.1.8.5 Height 2-2.5m 0m 0.00
2Z1.1.8.6 Height 2.5-3m 0m 0.00
2Z1.1.8.7 Height exceeding 3m 0 m3 0.00
2Z1.2 Gates and Stiles
2Z1.2.1 Timber stile gates
2Z1.2.2 Timber wicket gates
2Z1.2.3 Stiles
2Z1.2.3.1 Width not exceeding 1.5m 0 nr 0.00
2Z1.2.3.2 Width 1.5-2m 0 nr 0.00
2Z1.2.3.3 Width 2-2.5m 0 nr 0.00
2Z1.2.3.4 Width 2.5-3m 0 nr 0.00
2Z1.2.3.5 Width 3-4m 0 nr 0.00
2Z1.2.3.6 Width 4-5m 0 nr 0.00
2Z1.2.3.7 Width exceeding 5m 0 nr 0.00
2Z1.3 Drainage to structures above ground
2Z1.3.1 Mild steel
2Z1.3.2 Cast iron
2Z1.3.3 Plastics
2Z1.3.3.1 Gutters 0m 0.00
2Z1.3.3.2 Downpipes 0m 0.00
2Z1.3.3.3 Fittings to gutters 0 nr 0.00
2Z1.3.3.4 Fittings to downpipes 0 nr 0.00
2Z1.4 Rock filled gabions
2Z1.4.1 Box of stated size 0 nr 0.00
2Z1.4.2 Mattress of stated thickness 0 m2 0.00
2Z1.5 Open Cell Block System 0 nr 0.00
Page 83
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS WORK
Qty Unit Rate N K
Collection
Page 84
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
SEWER AND WATER RENOVATION AND ANCILLARY
2AA WORKS
2AA1.1 Preparation of existing sewers
2AA1.1.1 Cleaning 0m 0.00
2AA1.1.2 Removing intrusions
2AA1.1.2.1 Laterals, bore not exceeding 150mm 0 nr 0.00
Laterals, stated profile and size exceeding 150mm
2AA1.1.2.2 in one or more dimension 0 nr 0.00
2AA1.1.2.3 Other stated artifical intrusions 0 nr 0.00
2AA1.1.4 Closed-circuit television surveys 0m 0.00
2AA1.1.5 Plugging laterals, materials stated
2AA1.1.5.1 Bore not exceeding 300mm 0 nr 0.00
Page 85
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
SEWER AND WATER RENOVATION AND ANCILLARY
WORKS continued ...
Renovation of existing sewers continued ...
Segmental lining continued ...
2AA1.3.3.4 Resin concrete 0m 0.00
2AA1.3.4 Stated proprietary lining 0m 0.00
2AA1.3.5 Gunite coating of stated thickness 0m 0.00
2AA1.3.6 Annulus grouting materials stated 0 m3 0.00
2AA1.4 Laterals to renovated sewers
2AA1.4.1 Jointing
2AA1.4.1.1 Bore not exceeding 150mm 0 nr 0.00
2AA1.4.1.2 Bore 150-300mm 0 nr 0.00
Page 86
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
SEWER AND WATER RENOVATION AND ANCILLARY
WORKS continued ...
New manholes continued ...
Precast concrete with backdrop continued ...
2AA1.6.6.2 Depth 1.5-2m 0 nr 0.00
2AA1.6.6.3 Depth 2.5-3m 0 nr 0.00
2AA1.6.6.4 Depth 3-3.5m 0 nr 0.00
2AA1.6.6.5 Depth 3.5-4m 0 nr 0.00
2AA1.6.6.6 Depth stated exceeding 4m 0 nr 0.00
2AA1.7 Existing manholes
2AA1.7.1 Abandonment
2AA1.7.1.1 Depth 2-2.5m 0 nr 0.00
2AA1.7.1.2 Depth 2.5-3m 0 nr 0.00
2AA1.7.1.3 Depth 3-3.5m 0 nr 0.00
2AA1.7.1.4 Depth 3.5-4m 0 nr 0.00
2AA1.7.1.5 Depth stated exceeding 4m 0 nr 0.00
2AA1.7.2 Alteration 0 nr 0.00
2AA1.8 Interruptions
2AA1.8.1 Preparation of existing sewers
2AA1.8.2 Stabilization of existing sewers
2AA1.8.3 Renovation of existing sewers
2AA1.8.3.1 Sliplining 0h 0.00
2AA1.8.3.2 In-situ jointed pipelining 0h 0.00
2AA1.8.3.3 Segmental lining 0h 0.00
2AA1.8.3.4 Stated proprietary lining 0m 0.00
2AA1.8.3.5 Gunite coating 0m 0.00
2AA1.8.3.6 Annulus grouting 0h 0.00
2AA1.8.4 Work on laterals to renovated sewers 0h 0.00
2AA1.8.5 Work on manholes 0h 0.00
Nigerian Institute of Quantity Surveyors To Collection N 0.00
Page 87
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
Collection
Page 88
BESMM4 CIVIL WORK SECTIONS
Qty Unit Rate N K
Summary
Page 89
BESMM4 CIVIL WORK SECTIONS
Qty Unit Rate N K
Summary continued ... 0.00
Page 90
Page №:(1)
25283.998
LABOUR.
ADD
General Allowances
Statutory Contributions
NSTIF S0cial Insurance (6.5% of basic +R+T) 7,435.41 7,421.69 7,416.01 7,410.57
Include training fund (3%) 1,834.09 1,829.57 1,827.70 1,825.90
Workmen compensation 1,222.73 1,219.71 1,218.46 1,217.27
Total of 10% of annual basic 6,113.64 6,098.56 6,092.32 6,086.34
The contractor is to state below the rates of labour and market prices of materias current at the date of tender.
A list of some materials is stated below.
Fluctuation claims: if any will be restricted to the listed materials only
a. Labourer/day 2,000.00
d. Foreman 5,000.00
Plant:
Apllication
Labour
Materials
Bags of cement deliver to site/m3 3.50 2,700.00 9,450.00
1m3 of sharp sand 0.50 3,792.00 1,896.00
1 m3 of 20mm aggs. 1.00 4,462.00 4,462.00
15,808.00
Add for water and waste 7.50% 1,185.60
Cost of materials 16,993.60 16,993.60
Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (substr.) a.b. 3,675.00 6,316.67
Cost of concrete/m3 23,310.27
Materials
Bags of cement deliver to site/m3 3.78 2,700.00 10,206.00
1m3 of sharp sand 0.40 3,792.00 1,516.80
1 m3 of 20mm aggs. 0.80 4,462.00 3,569.60
Cost of materials 15,292.40
Add for water and waste 7.50% 1,146.93
Add for:- 16,439.33
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (substr.) a.b. 3,675.00 6,316.67
Cost of concrete/m3 22,756.00
Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (superstructure.) 5,775.00
8,416.67 8,416.67
Cost of concrete/m3 28,799.35
Add GOH & profit. (30%) 25% 7,199.84
Cost/m3 35,999.19
Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (superstructure.) 5,775.00
8,416.67 8,416.67
Cost of concrete/m3 34,621.43
Add GOH & profit. (30%) 25% 8,655.36
Cost/m3 43,276.79
Labour
1No. Iron-bender/day 1.00 5,000.00 5,000.00
1No. Labourer/day 1.00 2,000.00 2,000.00
7,000.00
Add for tools 5.00% 350.00
Cost of gang/day 7,350.00
Cost of gang/10 days 10.00 73,500.00
Materials
1 tonne of reinforcement bars 260,000.00
Add for cutting and waste 5% 13,000.00
273,000.00
Add for tying wires/tonne (10kg/tonne) 50% 8,000.00 4,000.00
Cost of loading/off loading a.b. 5% 13,650.00
Labour cutting, bending and fixing a.b. 73,500.00
364,150.00
Add GOH & profit. (30%) 25% 91,037.50
Cost/tonne 455,187.50
Cost/kg (tonne/1000) 1,000.00 455.19
Materials
Cost of Mesh/m2 1,150.00
Add for tying wires, lapping at joints and waste 15% 172.50
1,322.50
Labour
Cost of gang/day 7,350.00
33.00
Output of gang/days. (33m2) 222.73
Therefore cost of labour/m2 1,545.23
Add GOH & profit. (30%) 25% 386.31
Cost/m2 1,931.53
Materials
Cost of timber for formwork/m3 146,666.67
Therefore cost of formwork plank size 25 x 300 x
3600mm 0.027 146,666.67 3,960.00
Take 10m2
Labour
Take 10m2
Materials
Sandcrete blocks/10m2 100.00 240.00 24,000.00
Add for waste 5% 1,200.00
25,200.00
M3 Cement and Sand (1:6) mortar (0.14m3) 0.14 21,435.32 3,000.95
Cost of materials 28,200.95 28,200.95
Labour
2No. Masons/day 2.00 4,000.00 8,000.00
2No. Labourers)day 2.00 2,000.00 4,000.00
12,000.00
Add for tools 5.00% 600.00
Cost of gang/day 12,600.00
Output of gang/day (10m2) 10.00
Therefore Cost of Labour/day 12,600.00
Cost of materials and labour 40,800.95
Take 10m2
Materials
100No. Sandcrete blocks/10m2 100.00 220.00 22,000.00
Add for waste 5% 1,100.00
23,100.00
M3 Cement and Sand (1:6) mortar (0.23m3) 0.23 21,435.32 4,930.12
Cost of materials 28,030.12 28,030.12
Labour
2No. Masons/day 2.00 4,000.00 8,000.00
2No. Labourers)day 2.00 2,000.00 4,000.00
12,000.00
Add for tools 5.00% 600.00
Cost of gang/day 12,600.00
Output of gang/day (9m2) 10.00
Therefore Cost of Labour/day 1,260.00
29,290.12
Take 10m2
Materials
Labour
1No. Masons/day 1.00 3,500.00 3,500.00
1No. Labourers)day 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 5.00% 250.00
Cost of gang/8hrs-day 5,250.00
Output of gang/2hrs (10m2) 10.00
Therefore Cost of Labour/10m2 (4hrs) 4.00 1,312.50
24,082.50
Add GOH & profit. (30%) 25% 6,020.63
Cost/ 10m2 30,103.13
Cost/m2 10.00 3,010.31
Take 10m2
Materials
Take 10m2
Materials
Labour
1No. Masons/day 1.00 3,500.00 3,500.00
1No. Labourers)day 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 7.50% 375.00
Cost of gang/8hrs-day 5,375.00
Output of gang/2hrs (10m2) 10.00
Therefore Cost of Labour/10m2 (4hrs) 4.00 1,343.75
14,132.90
Add GOH & profit. (30%) 25% 3,533.23
Cost/ 10m2 17,666.13
Cost/m2 10.00 1,766.61
Take 10m2
Materials
Labour
1No. Masons/day 1.00 3,500.00 3,500.00
1No. Labourers)day 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 7.50% 375.00
Cost of gang/8hrs-day 5,375.00
Output of gang/2hrs (10m2) 10.00
Therefore Cost of Labour/10m2 (4hrs) 4.00 1,343.75
12,918.50
Add GOH & profit. (30%) 25% 3,229.63
Cost/ 10m2 16,148.13
Cost/m2 10.00 1,614.81
Take 14m2
Materials
Take 14m2
Plasprufe (NT4-paralon) + labour a.b 19,999.06
Ness-bitumen applied in 2-layers @ 4m2/litre 7.00 48.82 341.74
20,340.80
Labour
Applying Ness bitumen- 2-layers @ N476.83 2.00 476.83 953.66
21,294.46
Add GOH & profit. (30%) 25% 5,323.62
Cost/ 14m2 26,618.08
Cost/m2 14.00 1,901.29
E CARPENTRY
Materials
cost per cubic meter (400m) 15,110.00
Add for nails and waste-10% 10% 1,511.00
16,621.00
Materials
cost per cubic meter (267m) 15,110.00
Add for nails and waste-10% 10% 1,511.00
16,621.00
Materials
cost per cubic meter (200m) 44,800.00
Add for nails and waste-10% 10% 4,480.00
49,280.00
Materials
cost per cubic meter (160m) 15,110.00
Add for nails and waste-10% 10% 1,511.00
16,621.00
Materials
cost per cubic meter (133m) 24,050.00
Add for nails and waste-10% 10% 2,405.00
26,455.00
METAL WORK
Materials
Bags of cement/m3 9.44 1,550.00 14,632.00
m3 of sand 1.00 3,792.00 3,792.00
18,424.00
Add for waste 10% 1,842.40
Cost of materials 20,266.40 20,266.40
Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 130.00 2,600.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 600.00 1,200.00
cost of hiring concrete mixer/day 18,800.00
Labour
1 Mason 1.00 3,500.00 3,500.00
1 Laboure 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 53,750.00
176,444.37
Add for screes 2.50% 4,411.11
180,855.48
Add GOH & profit. (30%) 25% 45,213.87
Cost/100m2 100.00 226,069.34
Cost/m2 2,260.69
Labour
1 Pavre 1.00 3,500.00 3,500.00
2 Laboures 2.00 1,500.00 3,000.00
6,500.00
Tools 7.50% 487.50
Cost of gang/day 6,987.50
Output of gang-(18m2) 1.80
Therefore cost of labour fixing frame 3,881.94
18,843.57
Labour
1 Mason 1.00 3,500.00 3,500.00
1 Laboure 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-(18m2) 2.00
Therefore cost of labour /10m2 2,687.50
28,725.42
Add for polishing and application of ebonite dividing
strips plus cement slurry 20% 5,745.08
34,470.51
Add GOH & profit. (30%) 25% 8,617.63
Cost of paving/10m2 10.00 43,088.14
Cost of paving/m2 4,308.81
50mm white insitu terrazzo paving laid in 1200 x
1200mm panels divided with and including
3 3mm ebonite dividing strips in floor paving
Labour
1 Pavre 1.00 3,500.00 3,500.00
2 Laboures 2.00 1,500.00 3,000.00
6,500.00
Tools 7.50% 487.50
Cost of gang/day 6,987.50
Output of gang-(18m2) 1.80
Therefore cost of labour fixing frame 3,881.94
20,393.20
Labour
1 Mason 1.00 3,500.00 3,500.00
1 Laboure 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-(18m2) 2.00
Therefore cost of labour /10m2 2,687.50
30,275.05
Add for polishing and application of ebonite dividing
strips plus cement slurry 20% 6,055.01
36,330.06
Add GOH & profit. (30%) 25% 9,082.51
Cost of paving/10m2 10.00 45,412.57
Cost of paving/m2 4,541.26
Labour
1 Foreman/day 1.00 3,500.00 3,500.00
1 Fitter (Laboure)/day 1.00 1,500.00 1,500.00
4 Wheeler (Labourer)/day 4.00 1,500.00 6,000.00
11,000.00
Add for tools 7.50% 825.00
Cost of gangr/day 11,825.00
Labour
1 Pavre 1.00 3,500.00 3,500.00
2 Laboures 2.00 1,500.00 3,000.00
6,500.00
Add for tools 7.50% 487.50
Cost of gang/day 6,987.50
Output of gang-(18m2) 0.90
Therefore cost of labour /10m2 7,763.89
23,073.74
Add for polishing and application of ebonite dividing
strips plus cement slurry 30% 6,922.12
29,995.86
Add GOH & profit. (30%) 45% 13,498.14
Cost of paving/10m2 10.00 43,494.00
Cost of paving/m2 4,349.40
Cost/m2 2,800.00
Take 10m2
Materials
Cost of tiles 10.00 2,800.00 28,000.00
Add for maiching coloured cement/waste 15% 4,200.00 32,200.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71
Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
41,860.71
Allow for pointing/polishing/washing surface 2% 837.21
42,697.93
Add GOH & profit. (30%) 30% 12,809.38
Cost of paving/10m2 10.00 55,507.31
Cost of paving/m2 5,550.73
Cost/m2 1,650.00
Take 10m2
Materials
Cost of tiles 10.00 1,650.00 16,500.00
Add for maiching coloured cement/waste 15% 2,475.00 18,975.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71
Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
28,635.71
Cost/m2 2,000.00
Take 10m2
Materials
Cost of tiles 10.00 2,000.00 20,000.00
Add for maiching coloured cement/waste 15% 3,000.00 23,000.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71
Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
32,660.71
Allow for pointing/polishing/washing surface 2% 653.21
33,313.93
Add GOH & profit. (30%) 30% 9,994.18
Cost of paving/10m2 10.00 43,308.11
Cost of paving/m2 4,330.81
Cost/m2 1,650.00
Take 10m2
Materials
Cost of tiles 10.00 1,650.00 16,500.00
Add for maiching coloured cement/waste 15% 2,475.00 18,975.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71
Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
28,635.71
Cost/m2 5,950.00
Take 10m2
Materials
Cost of tiles 10.00 5,950.00 59,500.00
Add for maiching coloured cement/waste 15% 8,925.00 68,425.00
Kerokoll tile adhesive-25kg bag 1.00 1,938.00 1,938.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 2,768.57
Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
76,568.57
Allow for pointing/polishing/washing surface 10% 7,656.86
84,225.43
Add GOH & profit. (30%) 45% 37,901.44
Cost of paving/10m2 10.00 122,126.87
Cost of paving/m2 12,212.69
Cost/m2 8,500.00
Take 10m2
Materials
Cost of tiles 10.00 16,000.00 160,000.00
Add for maiching coloured cement/waste 15% 24,000.00 184,000.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
201,185.71
Allow for pointing/polishing/washing surface 2% 4,023.71
205,209.43
Add GOH & profit. (30%) 25% 51,302.36
Cost of paving/10m2 10.00 256,511.79
Cost of paving/m2 25,651.18
Cost/m2 8,500.00
Take 10m2
Materials
Cost of tiles 10.00 8,500.00 85,000.00
Add for maiching coloured cement/waste 15% 12,750.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00 100,750.00
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
117,935.71
Allow for pointing/polishing/washing surface 2% 2,358.71
120,294.43
Add GOH & profit. (30%) 25% 30,073.61
Cost of paving/10m2 10.00 150,368.04
Cost of paving/m2 15,036.80
9 300 x 300 x 1.4mm pvc tiles paving
Cost/m2 450.00
Take 10m2
Materials
Cost of tiles 10.00 450.00 4,500.00
Add for waste 10% 450.00 4,950.00
1 PVC tiles adhesive 1.00 1,000.00 1,000.00
Spreead/bag (15m2) ( note. 15m2 = 1.5) ie divide
by 10m2 1.5m2 1.50
Cost of adhesive/10m2 666.67
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(1.4m2) 1.4m2 1.40
Therefore cost of labour/10m2 4,607.14
10,223.81
Take - 100m2
Quantity of mortar 100.00 0.04 4.40
Add for application waste 10% 0.44
4.84 4.84m3
Cost of mortar (1:3) 4.84 22,308.07 107,971.04
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 12m2 0.12
Therefore cost of labour/100m2 53,750.00
161,721.04
Add GOH & profit. (30%) 45% 72,774.47
Cost/100m2 100.00 234,495.51
Cost/m2 2,344.96
11 38mm Cement and sand (1:3) in screeded beds
Take - 100m2
Quantity of mortar 100.00 0.04 3.80
Add for application waste 10% 0.38
4.18
Cost of mortar (1:3) 4.18 22,308.07 93,247.72
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 14m2 0.14
Therefore cost of labour/100m2 46,071.43
139,319.15
Add GOH & profit. (30%) 45% 62,693.62
Cost/100m2 100.00 202,012.76
Cost/m2 2,020.13
Take - 100m2
Quantity of mortar 100.00 0.05 4.80
Add for application waste 10% 0.48
5.28
Cost of mortar (1:3) 5.28 22,308.07 117,786.59
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 10m2 0.10
Therefore cost of labour/100m2 64,500.00
182,286.59
Add GOH & profit. (30%) 45% 82,028.97
Cost/100m2 100.00 264,315.56
Cost/m2 2,643.16
WALL FINISHINGS
Materials
Bags of cement/m3 7.55 2,500.00 18,875.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 1,900.00
25,170.38
Add for waste 10% 2,517.04
Cost of materials 27,687.42 27,687.42
Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 265.00 5,300.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 1,000.00 2,000.00
cost of hiring concrete mixer/day 22,300.00
Output of mixer/day (20m2) (15m3) 15.00
Cost of plantr/day 1,486.67
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
96,903.71
Materials
Bags of cement/m3 7.55 2,500.00 18,875.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
23,907.88
Add for waste (10%) 10% 2,390.79
Cost of materials 26,298.67 26,298.67
Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 265.00 5,300.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 1,000.00 2,000.00
cost of hiring concrete mixer/day 22,300.00
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
101,251.31
Add for arises 2.50% 2,531.28
103,782.59
Add GOH & profit. (30%) 45% 46,702.17
Cost/100m2 100.00 150,484.76
Cost/m2 1,504.85
3 13mm Cement and sand (1:6) in paving.
Materials
Bags of cement/m3 5.40 2,500.00 13,500.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
18,846.84
Add for waste 10% 1,884.68
Cost of materials 20,731.52 20,731.52
Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 265.00 5,300.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 1,000.00 2,000.00
cost of hiring concrete mixer/day 16,800.00
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
86,432.45
Add for arises 2.50% 2,160.81
88,593.26
Add GOH & profit. (30%) 45% 39,866.97
Cost/100m2 100.00 128,460.22
Cost/m2 1,284.60
Materials
Bags of cement/m3 5.40 2,500.00 13,500.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
18,846.84
Add for waste 10% 1,884.68
Cost of materials 20,731.52 20,731.52
Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
90,756.62
Add for arises 2.50% 2,268.92
93,025.54
Add GOH & profit. (30%) 45% 41,861.49
Cost/100m2 100.00 134,887.03
Cost/m2 1,348.87
Cost/m2
Take 10m2
Materials
Cost of tiles 10.00 1,100.00 11,000.00
Add for maiching coloured cement/waste 15% 1,650.00 12,650.00
Kerokoll tile adhesive-25kg bag 1.00 1,200.00 1,200.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 1,200.00
13,850.00
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
26,750.00
Allow for pointing/polishing/washing surface 2% 535.00
27,285.00
Add GOH & profit. (30%) 45% 12,278.25
Cost of paving/10m2 10.00 39,563.25
Cost of paving/m2 3,956.33
Cost/m2
Take 10m2
Materials
Cost of tiles 10.00 1,850.00 18,500.00
Add for maiching coloured cement/waste 15% 2,775.00 21,275.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 3,000.00
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour fixing frame 12,900.00
37,175.00
Allow for pointing/polishing/washing surface 2% 743.50
37,918.50
Add GOH & profit. (30%) 45% 17,063.33
Cost of paving/10m2 10.00 54,981.83
Cost of paving/m2 5,498.18
Cost/m2 4,300.00
Take 10m2
Materials
Cost of tiles 10.00 4,300.00 43,000.00
Add for maiching coloured cement/waste 15% 6,450.00 49,450.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 3,000.00
Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour fixing frame 5,375.00
57,825.00
Allow for pointing/polishing/washing surface 2% 1,156.50
58,981.50
Add GOH & profit. (30%) 30% 17,694.45
Cost of paving/10m2 10.00 76,675.95
Cost of paving/m2 7,667.59
Cost/m2
Take 10m2
Materials
Cost of tiles 10.00 7,850.00 78,500.00
Add for maiching coloured cement/waste 15% 11,775.00 90,275.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 3,000.00
Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
106,175.00
Allow for pointing/polishing/washing surface 2% 2,123.50
108,298.50
Add GOH & profit. (30%) 45% 48,734.33
Cost of paving/10m2 10.00 157,032.83
Cost of paving/m2 15,703.28
Materials
Bags of cement/m3 9.44 2,500.00 23,600.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
28,946.84
Add for waste 10% 2,894.68
Cost of materials 31,841.52 31,841.52
Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /10m2 53,750.00
101,709.70
Add for arises 2.50% 2,542.74
104,252.45
Add GOH & profit. (30%) 45% 46,913.60
Cost/100m2 100.00 151,166.05
Cost/m2 1,511.66
CEILING FINISHINGS
Take 10m2
Materials.
Cost of particle board in 10m2 10.00 361.46 3,614.62
50 x 20mm wrought hardwood cover strips @
N15.11 76.00 15.11 1,148.36
4,762.98
Allow for nails and waste 10% 476.30
Cost of materials 5,239.28 5,239.28
Labour:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 12m2/day (note: 12m2 =1.2m2,
ie divide by 10m2) 12m2 1.20
Therefore cost labour per 10m2 5,375.00
10,614.28
Add GOH & profit. (30%) 45% 4,776.42
Cost/ 10m2 15,390.70
Cost/m2 10.00 1,539.07
Take 10m2
Materials.
Cost of particle board in 10m2 10.00 379.60 3,796.02
50 x 20mm wrought hardwood cover strips @
15.11 76.00 15.11 1,148.36
4,944.38
Allow for nails and waste 10% 494.44
Cost of materials 5,438.82 5,438.82
Labour:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 12m2/day (note: 12m2 =1.2m2,
ie divide by 10m2) 12m2 1.20
Therefore cost labour per 10m2 5,375.00
10,813.82
Add GOH & profit. (30%) 45% 4,866.22
Cost/ 10m2 15,680.04
Cost/m2 10.00 1,568.00
Take 10m2
Materials.
Cost of particle board in 10m2 10.00 154.53 1,545.28
50 x 20mm wrought hardwood cover strips 76.00 1.60 121.60
1,666.88
Allow for nails and waste 10% 166.69
Cost of materials 1,833.57 1,833.57
Labour:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 12m2/day (note: 12m2 =1.2m2,
ie divide by 10m2) 12m2 1.20
Therefore cost labour per 10m2 5,375.00
7,208.57
Add GOH & profit. (30%) 45% 3,243.86
Cost/ 10m2 10,452.43
Cost/m2 10.00 1,045.24
Materials
Bags of cement/m3 7.55 2,500.00 18,875.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
23,907.88
Add for waste 10% 2,390.79
Cost of materials 26,298.67 26,298.67
Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0 20.00 26.00 520.00
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96
Output of mixer/day (20m2) (15m3) 15.00
Cost of plantr/day 693.40
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 64,500.00
104,533.43
Add for arises 2.50% 2,613.34
107,146.76
Add GOH & profit. (30%) 45% 48,216.04
Cost/100m2 100.00 155,362.80
Cost/m2 1,553.63
Materials
Bags of cement/m3 7.55 2,000.00 15,100.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
20,132.88
Add for waste 10% 2,013.29
Cost of materials 22,146.17 22,146.17
Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0 20.00 26.00 520.00
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 64,500.00
103,840.79
Add for arises 2.50% 2,596.02
106,436.81
Add GOH & profit. (30%) 45% 47,896.56
Cost/100m2 100.00 154,333.37
Cost/m2 1,543.33
Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96
Materials
Bags of cement/m3 5.40 2,000.00 10,800.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
16,146.84
Add for waste 10% 1,614.68
Cost of materials 17,761.52 17,761.52
Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 64,500.00
96,606.12
Add for arises 2.50% 2,415.15
99,021.27
Add GOH & profit. (30%) 45% 44,559.57
Cost/100m2 100.00 143,580.85
Cost/m2 1,435.81
Take 100m2
Materials.
Covering capacity of emulsion paint/litre
1st coat-1litre/11m2 80.00 0.34 27.20 litre
2nd coat-1litre/6m2 80.00 0.34 27.20 litre
3rd coat-1litre/6m2 80.00 0.17 13.33 litre
67.73
Add for waste 10% 6.77
74.51 litre
Emulsion paint in 3 coats 74.51 332.22 24,752.82
Labour
1 painter 1.00 4,000.00 4,000.00
1 labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Take 100m2
Materials.
Covering capacity of gloss paint/litre
1st coat-1litre/9m2 100.00 0.111 11.11 litre
2nd coat-1litre/7m2 100.00 0.14 14.29 litre
3rd coat-1litre/7m2 100.00 0.14 14.29 litre
39.68
Take 100m2
Materials.
Covering capacity of gloss paint/litre
Knotting-1litre/50m2 100.00 0.020 2.00 litre
Priming-1litre/16m2 100.00 0.06 6.25 litre
1st, 2nd & 3rd coats a.b. 43.65 litre
51.90
Add for waste 10% 5.19
57.09 litre
Add for stopping 1.00% 0.57
57.66
Gloss paint in 3 coats 57.66 441.89 25,480.16
Labour
1 painter 1.00 4,000.00 4,000.00
1 labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
QTY L B H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
ZONE A 6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222
C1 19.00 0.45 0.23 2.85 5.48 73.10 26.40 16.24 981.60
C3 13.00 0.45 0.23 2.85 3.75 50.02 13.20 10.08 503.89
C19 1.00 0.45 0.30 2.85 0.38 4.28 13.20 14.00 41.18
C2 4.00 0.23 0.23 2.85 0.58 10.26 26.40 33.04 248.05
C7 6.00 0.30 0.45 2.85 2.31 25.65 26.40 16.24 309.98
ZONE B
CT 1 15.00 0.45 0.23 2.85 4.33 57.71
CT 9 2.00 0.23 0.23 2.85 0.29 5.13
CT 10 2.00 0.23 0.23 2.85 0.29 5.13
CT 11 1.00 0.30 0.23 2.85 0.19 2.99
ZONE C
C1 19.00 0.45 0.23 2.85 5.48 73.10
C3 13.00 0.45 0.23 2.85 3.83 50.39
C2 4.00 0.23 0.23 2.85 0.58 10.26
C9 5.00 0.45 0.30 2.85 1.92 21.38
C4 1.00 0.45 0.23 2.85 0.29 3.85
ZONE D
C1 15.00 0.45 0.23 2.85 4.33 57.71
C3 17.00 0.45 0.23 2.85 4.91 65.41
C2 3.00 0.23 0.23 2.85 0.43 7.70
C9 1.00 0.45 0.23 2.85 0.29 3.85
C10 7.00 0.45 0.30 2.85 2.69 29.93
ZONE E
CT 1 15.00 0.45 0.23 2.85 4.33 57.71
46.69 615.54
ZONE A
C1 0.45 0.23 2.85 0.00 0.00
C3 13.00 0.45 0.23 2.85 3.75 50.02
C19 1.00 0.45 0.30 2.85 0.38 4.28
C2 4.00 0.23 0.23 2.85 0.58 10.26
C7 6.00 0.30 0.45 2.85 2.31 25.65
ZONE B
CT 1 15.00 0.45 0.23 2.85 4.33 57.71
CT 9 2.00 0.23 0.23 2.85 0.29 5.13
CT 10 2.00 0.23 0.23 2.85 0.29 5.13
CT 11 1.00 0.30 0.23 2.85 0.19 2.99
ZONE C
C1 0.45 0.23 2.85 0.00 0.00
C3 13.00 0.45 0.23 2.85 3.83 50.39 26.40 10.08 622.29
C2 4.00 0.23 0.23 2.85 0.58 10.26
C9 5.00 0.45 0.30 2.85 1.92 21.38 2,706.98
C4 1.00 0.45 0.23 2.85 0.29 3.85
ZONE D
C1 0.45 0.23 2.85 0.00 0.00
C3 17.00 0.45 0.23 2.85 4.91 65.41
C2 3.00 0.23 0.23 2.85 0.43 7.70
C9 1.00 0.45 0.23 2.85 0.29 3.85
C10 7.00 0.45 0.30 2.85 2.69 29.93
BNL
Project : BOB
Project Manager : G. AKINOLA
Prepared by CAN CONCRETE RETAINING WALL MEASUREMENT
Date 04-Aug-10
QTY L B H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222
QTY H B L CONC. F/WK BEAM T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
ZONE A
BEAM 1 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 24 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 23 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 7 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 8 1.00 0.15 0.23 17.72 0.61 9.39
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BM 10 1.00 0.30 0.23 12.03 0.83 9.98
BM 11 1.00 0.30 0.23 12.03 0.83 9.98
BM 4 1.00 0.30 0.23 4.46 0.31 3.70
BM 12 1.00 0.30 0.23 12.03 0.83 9.98
BM 13 1.00 0.30 0.23 12.03 0.83 9.98
BM 3 1.00 0.30 0.23 5.77 0.40 4.79
BM 14 1.00 0.30 0.23 30.99 2.14 25.72
BM 15 1.00 0.30 0.23 20.76 1.43 17.23
BM 16 1.00 0.30 0.23 10.23 0.71 8.49
BM 17 1.00 0.30 0.23 4.15 0.29 3.44
BM 18 1.00 0.30 0.23 6.09 0.42 5.05
BM 22 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 4.46 0.31 3.70
BM 19 1.00 0.30 0.23 30.99 2.14 25.72
BM 20 1.00 0.30 0.23 18.96 1.31 15.74
BM21 1.00 0.30 0.23 12.03 0.83 9.98
ZONE B
BM 1 1.00 0.30 0.23 18.41 1.27 15.28
BM 13 1.00 0.30 0.23 3.63 0.25 3.01
BM 2 1.00 0.30 0.23 18.41 1.27 15.28
BM5 1.00 0.30 0.23 4.21 0.29 3.49
BM3 1.00 0.30 0.23 18.41 1.27 15.28
BM4 1.00 0.30 0.23 4.30 0.30 3.57
BM6 1.00 0.30 0.23 22.01 1.52 18.27
BM 8 1.00 0.30 0.23 13.86 0.96 11.50
BM 9 1.00 0.30 0.23 3.62 0.25 3.00
BM11 1.00 0.30 0.23 13.86 0.96 11.50
BM 7 1.00 0.15 0.23 1.80 0.06 0.95
BM 14 1.00 0.30 0.23 13.86 0.96 11.50
BM 15 1.00 0.15 0.23 1.80 0.06 0.95
BM 10 1.00 0.30 0.23 10.23 0.71 8.49
BM 12 1.00 0.30 0.23 10.23 0.71 8.49
ZONE C
BM 1 1.00 0.30 0.23 27.94 1.93 23.19
BM 23 1.00 0.30 0.23 20.75 1.43 17.22
BM 3 1.00 0.30 0.23 5.77 0.40 4.79
BM 5 1.00 0.30 0.23 17.72 1.22 14.71
BM 22 1.00 0.30 0.23 10.23 0.71 8.49
BM 7 1.00 0.30 0.23 27.94 1.93 23.19
BM 8 1.00 0.15 0.23 15.92 0.55 8.44
BM 9 1.00 0.30 0.23 12.03 0.83 9.98
BM 10 1.00 0.30 0.23 12.03 0.83 9.98
BM 11 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 4.46 0.31 3.70
BM 12 1.00 0.30 0.23 12.03 0.83 9.98
BM 13 1.00 0.30 0.23 12.03 0.83 9.98
BM 6 1.00 0.30 0.23 5.77 0.40 4.79
BM 14 1.00 0.30 0.23 12.03 0.83 9.98
BM 15 1.00 0.30 0.23 12.03 0.83 9.98
BM 16 1.00 0.30 0.23 12.03 0.83 9.98
BM 17 1.00 0.30 0.23 12.03 0.83 9.98
BM 18 1.00 0.15 0.23 20.75 0.72 11.00
BM20 1.00 0.30 0.23 6.09 0.42 5.05
BM 21 1.00 0.30 0.23 4.15 0.29 3.44
BM 19 1.00 0.30 0.23 30.98 2.14 25.71
BM 24 1.00 0.30 0.23 30.98 2.14 25.71
ZONE D
BM 1 1.00 0.30 0.23 22.01 1.52 18.27
BM 2 1.00 0.30 0.23 22.01 1.52 18.27
BM 3 1.00 0.30 0.23 22.01 1.52 18.27
BM 4 1.00 0.30 0.23 22.01 1.52 18.27
BM 11 1.00 0.30 0.23 33.52 2.31 27.82
BM 5 1.00 0.30 0.23 22.01 1.52 18.27
BM 18 1.00 0.30 0.23 3.83 0.26 3.18
BM 6 1.00 0.30 0.23 22.01 1.52 18.27
BM 7 1.00 0.45 0.23 7.50 0.78 8.48
BM 8 1.00 0.30 0.23 2.40 0.17 1.99
BM 9 1.00 0.30 0.23 22.01 1.52 18.27
BM 10 1.00 0.30 0.23 22.01 1.52 18.27
BM 16 1.00 0.30 0.23 3.83 0.26 3.18
BM 14 1.00 0.30 0.23 23.65 1.63 19.63
BM 15 1.00 0.30 0.23 6.04 0.42 5.01
BM 13 1.00 0.30 0.23 33.52 2.31 27.82
BM 17 1.00 0.30 0.23 33.52 2.31 27.82
BM 19 1.00 0.30 0.23 33.52 2.31 27.82
BM 20 1.00 0.30 0.23 33.52 2.31 27.82
BM 12 1.00 0.30 0.23 33.52 2.31 27.82
ZONE E
BM 1 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 12.03 0.83 9.98
BM 3 1.00 0.30 0.23 12.03 0.83 9.98
BM 4 1.00 0.30 0.23 6.20 0.43 5.15
BM 5 1.00 0.30 0.23 12.03 0.83 9.98
BM 6 1.00 0.30 0.23 12.03 0.83 9.98
BM 8 1.00 0.30 0.23 16.34 1.13 13.56
BM 10 1.00 0.30 0.23 8.46 0.58 7.02
BM 11 1.00 0.30 0.23 4.65 0.32 3.86
BM 12 1.00 0.30 0.23 3.23 0.22 2.68
BM 13 1.00 0.30 0.23 16.34 1.13 13.56
BM 7 1.00 0.15 0.23 16.34 0.56 8.66
BM 9 1.00 0.30 0.23 3.23 0.22 2.68
94.16 1,140.28
ZONE B
BEAM 1 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 7 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 2 1.00 0.30 0.23 18.41 1.27 15.28
BM 5 1.00 0.30 0.23 4.21 0.29 3.49
BEAM 3 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 4 1.00 0.30 0.23 4.00 0.28 3.32
BEAM 6 1.00 0.30 0.23 22.01 1.52 18.27
ZONE C
BEAM 1 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 24 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 22 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 7 1.00 0.30 0.23 27.94 1.93 23.19
0.00 0.00
BEAM 8 1.00 0.15 0.23 15.92 0.55 8.44
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 12 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 13 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 2 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 14 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 15 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 21 1.00 0.30 0.23 4.15 0.29 3.44
ZONE B
BEAM 1 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 7 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 2 1.00 0.30 0.23 18.41 1.27 15.28
BM 5 1.00 0.30 0.23 4.21 0.29 3.49
BEAM 3 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 4 1.00 0.30 0.23 4.00 0.28 3.32
BEAM 6 1.00 0.30 0.23 22.01 1.52 18.27
ZONE C
BEAM 1 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 7 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 24 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 8 1.00 0.15 0.23 15.92 0.55 8.44
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 12 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 13 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 14 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 15 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 23 1.00 0.30 0.23 20.75 1.43 17.22
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 16 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 17 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 18 1.00 0.15 0.23 20.75 0.72 11.00
BEAM 3 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 19 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 20 1.00 0.30 0.23 6.09 0.42 5.05
BEAM 21 1.00 0.30 0.23 4.15 0.29 3.44
BEAM 22 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 2 1.00 0.30 0.23 4.46 0.31 3.70
0.00 0.00
ZONE D 0.00 0.00
BM 5 1.00 0.30 0.23 22.01 1.52 18.27
BM 6 1.00 0.30 0.23 22.01 1.52 18.27
BM 7 1.00 0.45 0.23 7.50 0.78 8.48
BM 8 1.00 0.30 0.23 2.40 0.17 1.99
BM 9 1.00 0.30 0.23 22.01 1.52 18.27
BM 10 1.00 0.30 0.23 22.01 1.52 18.27
BM 1 1.00 0.30 0.23 22.01 1.52 18.27
BM 14 1.00 0.30 0.23 23.65 1.63 19.63
BM 15 1.00 0.30 0.23 6.04 0.42 5.01
BM 16 1.00 0.30 0.23 3.83 0.26 3.18
BM 18 1.00 0.30 0.23 3.83 0.26 3.18
BM 2 1.00 0.30 0.23 22.01 1.52 18.27
BM 11 1.00 0.30 0.23 33.52 2.31 27.82
BM 12 1.00 0.30 0.23 33.52 2.31 27.82
BM 4 1.00 0.30 0.23 22.01 1.52 18.27
BM 13 1.00 0.30 0.23 33.52 2.31 27.82
BM 17 1.00 0.30 0.23 33.52 2.31 27.82
BM 19 1.00 0.30 0.23 33.52 2.31 27.82
BM 20 1.00 0.30 0.23 33.52 2.31 27.82
BM 3 1.00 0.30 0.23 22.01 1.52 18.27
ZONE C
BEAM 1 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 24 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.45 0.23 5.77 0.60 6.52
BEAM 8 1.00 0.30 0.23 15.92 1.10 13.21
BEAM 25 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 9 1.00 0.30 0.23 15.92 1.10 13.21
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 12 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 13 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 14 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 15 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 16 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 17 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 18 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 7 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 19 1.00 0.30 0.23 20.75 1.43 17.22
BEAM 3 1.00 0.45 0.23 5.77 0.60 6.52
BEAM 20 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 21 1.00 0.30 0.23 6.09 0.42 5.05
BEAM 22 1.00 0.30 0.23 4.15 0.29 3.44
BEAM 23 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 2 1.00 0.30 0.23 4.46 0.31 3.70
ZONE D
BM 1 1.00 0.45 0.23 22.01 2.28 24.87
BM 2 1.00 0.45 0.23 22.01 2.28 24.87
BM 3 1.00 0.30 0.23 22.01 1.52 18.27
BM 4 1.00 0.30 0.23 2.40 0.17 1.99
BM 13 1.00 0.45 0.23 33.52 3.47 37.88
BM 5 1.00 0.30 0.23 22.09 1.52 18.33
BM 16 1.00 0.30 0.23 3.83 0.26 3.18
BM 6 1.00 0.30 0.23 22.01 1.52 18.27
BM 7 1.00 0.45 0.23 7.50 0.78 8.48
BM 8 1.00 0.30 0.23 2.40 0.17 1.99
BM 9 1.00 0.30 0.23 22.01 1.52 18.27
BM 18 1.00 0.45 0.23 3.83 0.40 4.33
BM 10 1.00 0.45 0.23 22.01 2.28 24.87
BM 22 1.00 0.45 0.23 6.04 0.63 6.83
BM 17 1.00 0.45 0.23 33.52 3.47 37.88
BM 14 1.00 0.30 0.23 23.65 1.63 19.63
BM 15 1.00 0.45 0.23 6.04 0.63 6.83
BM 11 1.00 0.30 0.23 33.52 2.31 27.82
BM 20 1.00 0.30 0.23 23.65 1.63 19.63
BM 21 1.00 0.30 0.23 3.83 0.26 3.18
BM 12 1.00 0.45 0.23 33.52 3.47 37.88
BM 19 1.00 0.45 0.23 33.52 3.47 37.88
87.54 1,013.74
ROOF BEAM
ZONE A
BNL
Project : BOB
Project Manager : G. AKINOLA
Prepared by CAN UPPER FLOOR SLABS #REF!
Date 26-Apr-10
QTY L B H(topping) H(pre-cast) CONC 1:2:4 TOPPING SQM F/WK waterproofing T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
1st floor slab 6.314 3.854 2.466 1.579 1.209 0.888 0.616 0.395 0.222
INSITU SLAB
ZONE A 0.00
1 1.00 28.17 12.26 0.150 51.80 345.36 0.00
2 1.00 12.25 19.07 0.150 35.04 233.61 0.00
0.00
Less lift -1.00 2.21 2.00 0.150 -0.66 -4.42 0.00
staircase -2.00 8.70 1.80 0.150 -4.70 -31.32
-1.00 7.50 1.50 0.150 -1.69 -11.25
-1.00 8.10 1.80 0.150 -2.19 -14.58
-1.00 6.90 1.80 0.150 -1.86 -12.42
ZONE D
1 1.00 22.23 33.74 0.150 112.51 750.04
2 0.150 0.00 0.00
ZONE E
1 1.00 12.25 16.56 0.150 30.43 202.86
0.150 0.00 0.00
INSITU SLAB
ZONE A
1 1.00 28.17 12.26 0.150 51.80 345.36
2 1.00 12.25 19.07 0.150 35.04 233.61
BNL
Project : BOB
CONCRETE COLUMN MEASUREMENT
Project Manager : G. AKINOLA #REF!
Prepared by CAN
Date 04-Aug-10 300.70
QTY L B H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
ZONE A 6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222
C1 18.00 0.45 0.23 1.05 1.91 25.52 26.40 16.24 929.93
C3 12.00 0.45 0.23 1.05 1.28 17.01 13.20 10.08 465.13
C19 1.00 0.45 0.30 1.05 0.14 1.58 13.20 14.00 41.18
C2 4.00 0.23 0.23 1.05 0.21 3.78 26.40 33.04 248.05
C7 6.00 0.30 0.45 1.05 0.85 9.45 26.40 16.24 309.98
ZONE B
CT 1 15.00 0.45 0.23 1.05 1.59 21.26
CT 9 2.00 0.23 0.23 1.05 0.11 1.89
CT 10 2.00 0.23 0.23 1.05 0.11 1.89
CT 11 1.00 0.30 0.23 1.05 0.07 1.10
ZONE C
C1 19.00 0.45 0.23 1.05 2.02 26.93
C3 12.00 0.45 0.23 1.05 1.30 17.14
C2 4.00 0.23 0.23 1.05 0.21 3.78
C9 5.00 0.45 0.30 1.05 0.71 7.88
C4 1.00 0.45 0.23 1.05 0.11 1.42
ZONE D
C1 15.00 0.45 0.23 1.05 1.59 21.26
C3 17.00 0.45 0.23 1.05 1.81 24.10
C2 3.00 0.23 0.23 1.05 0.16 2.84
C9 1.00 0.45 0.23 1.05 0.11 1.42
C10 7.00 0.45 0.30 1.05 0.99 11.03
ZONE E
CT 1 15.00 0.45 0.23 1.05 1.59 21.26
Total - #REF!
Prov. Sums