You are on page 1of 789

Project :

Employer :
Engineer :
Contractor :
DEDUCTION FOR FILLING IMPORTED SOIL ( GRADE SLAB INCLUDING HARD CORE)

GRAD SLAB
SI NO DRW NO REV LOCATION DESCRIPTION NO LENGTH WIDTH DEPTH PERIMETER HOR. AREA QUERY ANSWER
CONC.

(m) (m) (m) (m) (m²) (m³)

A DEDUCTION FOR FILLING IMPORTED SOIL ( GRADE SLAB INCLUDING HARD CORE) - - 68.00
GRID A1-D1-D4-B'4-
1 S-BN-11.1-1111 A 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 0.02 73.35 269.84 5.40
B'4'-A4'
2 -do- GRID C4-B'5 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 1.80 7.70 0.02 19.00 13.86 0.28
GRID D4-D6-A6-A4'-
3 -do- 200mm THK GRADE SLAB FROM -0.770 TO -0.450 (AT -0.370 LVL) 1.00 0.32 77.25 193.75 62.00
B'4'-B'5-C5-C4
4 -do- ENTRANCE FRONT 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 2.56 1.51 0.02 5.57 3.85 0.08

5 -do- ENTRANCE REAR 200mm THK GRADE SLAB FROM -0.470 TO -0.450 (AT -0.070) 1.00 2.31 1.21 0.02 4.72 2.78 0.06

6 -do- DCT COLUMN - C4 (4.00) 0.75 0.20 0.02 7.60 (0.60) (0.01)

TOTAL CARRIED TO IMPORTED SOIL DEDUCTION 67.79


Project :
Employer :
Engineer :
Contractor :
DEDUCTION FOR FILLING IMPORTED SOIL ( BLINDING)

50mm thk
SI NO DRW NO REV LOCATION DESCRIPTION NO LENGTH WIDTH DEPTH HOR. AREA CONC. ADD/DEDUCTION FOR FORMWORK QUERY ANSWER
BLINDING
(m) (m) (m) (m²) (m³) DESCRIPTION NO L W H QTY QTY

A DEDUCTION FOR FILLING IMPORTED SOIL ( BLINDING) 4.00 - 4.00

A.2 BELOW GROUND BEAMS


1 -do- EXTERNAL GB1 1.00 6.00 0.54 0.05 3.24 0.16 ADD GRID-A1 1.00 0.49 0.29 0.05 0.01 0.17
2 -do- EXTERNAL GB2 1.00 4.00 0.54 0.05 2.16 0.11 ADD GRID-A2 & A3 2.00 0.20 0.29 0.05 0.01 0.11

3 -do- EXTERNAL GB2 1.00 5.45 0.54 0.05 2.94 0.15 ADD GRID-A4 1.00 0.75 0.29 0.05 0.01 0.16

4 -do- EXTERNAL GB2 1.00 2.30 0.54 0.05 1.24 0.06 ADD GRID-A4' 1.00 0.20 0.19 0.05 0.00 0.06

5 -do- EXTERNAL GB2 1.00 5.20 0.54 0.05 2.81 0.14 ADD GRID-A5 1.00 0.20 0.29 0.05 0.00 0.14

6 -do- EXTERNAL GB2 1.00 7.00 0.54 0.05 3.78 0.19 ADD GRID-A6 1.00 0.49 0.29 0.05 0.01 0.20

7 -do- EXTERNAL GB2 1.00 5.28 0.54 0.05 2.85 0.14 ADD GRID-A6 1.00 0.75 0.29 0.05 0.01 0.15

8 -do- EXTERNAL GB2 1.00 2.53 0.54 0.05 1.36 0.07 ADD GRID-B6 & C6 2.00 0.75 0.29 0.05 0.02 0.09

9 -do- EXTERNAL GB1 1.00 5.00 0.54 0.05 2.70 0.14 ADD GRID-D6 1.00 0.75 0.29 0.05 0.01 0.15

10 -do- EXTERNAL GB2 1.00 5.28 0.54 0.05 2.85 0.14 ADD GRID-A1 1.00 0.75 0.29 0.05 0.01 0.15

11 -do- EXTERNAL GB2 1.00 2.53 0.54 0.05 1.36 0.07 ADD GRID-B1 & C1 2.00 0.75 0.29 0.05 0.02 0.09

12 -do- EXTERNAL GB1 1.00 5.00 0.54 0.05 2.70 0.14 ADD GRID-D1 1.00 0.75 0.29 0.05 0.01 0.15

13 -do- EXTERNAL GB1 1.00 5.73 0.54 0.05 3.09 0.15 ADD GRID-D1 1.00 0.49 0.29 0.05 0.01 0.16

14 -do- EXTERNAL GB2 1.00 3.45 0.54 0.05 1.86 0.09 ADD GRID-D2 & D3 2.00 0.75 0.29 0.05 0.02 0.11

15 -do- EXTERNAL GB2 1.00 2.98 0.54 0.05 1.61 0.08 ADD GRID-D3' 1.00 0.20 0.29 0.05 0.00 0.08

16 -do- EXTERNAL GB2 1.00 2.55 0.54 0.05 1.38 0.07 ADD GRID-D4 1.00 0.20 0.29 0.05 0.00 0.07

17 -do- EXTERNAL GB2 1.00 7.70 0.54 0.05 4.16 0.21 ADD GRID-D5 1.00 0.20 0.29 0.05 0.00 0.21

18 -do- EXTERNAL GB2 1.00 7.00 0.54 0.05 3.78 0.19 ADD GRID-D6 1.00 0.49 0.29 0.05 0.01 0.20

19 -do- INTERNAL GB4 1.00 2.53 0.30 0.05 0.76 0.04 0.04

20 -do- INTERNAL GB3 1.00 5.00 0.30 0.05 1.50 0.08 0.08

21 -do- INTERNAL GB3 1.00 7.10 0.30 0.05 2.13 0.11 0.11

22 -do- INTERNAL GB3 1.00 2.53 0.30 0.05 0.76 0.04 0.04

23 -do- INTERNAL GB3 1.00 7.70 0.30 0.05 2.31 0.12 0.12

24 -do- INTERNAL GB3 1.00 7.70 0.30 0.05 2.31 0.12 0.12

25 -do- EXTERNAL DDT RECESS (23.00) 0.80 0.10 0.05 (0.09) (0.09)

26 -do- EXTERNAL DDT RECESS (5.00) 0.50 0.10 0.05 (0.01) (0.01)

A.4 BELOW STEPS

27 S-BN-11.1-1111 A SECTION 3-3 STEPS-FRONT 1.00 2.56 1.00 0.05 2.56 0.13 0.13

28 -do- SECTION 3-3 STEPS-REAR 1.00 2.31 1.00 0.05 2.31 0.12 0.12

A.5 BELOW RAMP

29 S-BN-11.1-1111 A SECTION 4-4 RAMP 1.00 6.90 1.61 0.05 11.07 0.55 0.55

A.6 BELOW BLOCK WORK

30 S-BN-11.1-1111 A SECTION 4-4 BW AT ENTRANCE FRONT 2.00 2.61 0.54 0.05 2.81 0.14 DDT C3 (2.00) 0.45 0.25 0.05 (0.01) 0.13

31 -do- SECTION 4-4 BW AT ENTRANCE REAR 1.00 2.41 0.54 0.05 1.30 0.06 DDT C3 (1.00) 0.45 0.25 0.05 (0.01) 0.06

32 -do- SECTION 4-4 BW AT ENTRANCE REAR 1.00 2.41 0.54 0.05 1.30 0.06 DDT C3 (1.00) 0.45 0.25 0.05 (0.01) 0.06

33 -do- SECTION 4-4 DDT RAMP (1.00) 1.61 0.05 0.05 (0.00) (0.00)

TOTAL CARRIED TO IMPORTED SOIL DEDUCTION 3.85 0.04 3.89


Project :
Employer :
Engineer :
Contractor :
ANTI TERMITE TREATMENT

TOTAL
SI NO DRW NO REV LOCATION DESCRIPTION NO LENGTH WIDTH DEPTH HOR. AREA ADD/DEDUCTION QUERY ANSWER
AREA
(m) (m) (m) (m²) DESCRIPTION NO L W H QTY (m²)

A ANTI TERMITE TREATMENT 680.00 1.00 680.00

A.1 BELOW FOOTINGS

1 S-BN-11.1-1001 A F1 7.00 2.40 2.40 40.32 40.32

2 -do- F2 6.00 2.20 2.20 29.04 29.04

3 -do- F3 8.00 2.00 2.00 32.00 32.00

4 -do- F4 3.00 1.80 1.80 9.72 9.72

5 -do- F5 6.00 1.20 1.20 8.64 8.64

A.2 BELOW GROUND BEAMS -


6 -do- EXTERNAL GB1 1.00 6.00 0.54 3.24 ADD GRID-A1 1.00 0.49 0.29 0.14 3.38
ADD GRID-A2 &
7 -do- EXTERNAL GB2 1.00 4.00 0.54 2.16 2.00 0.20 0.29 0.12 2.28
A3
8 -do- EXTERNAL GB2 1.00 5.45 0.54 2.94 ADD GRID-A4 1.00 0.75 0.29 0.22 3.16

9 -do- EXTERNAL GB2 1.00 2.30 0.54 1.24 ADD GRID-A4' 1.00 0.20 0.19 0.04 1.28

10 -do- EXTERNAL GB2 1.00 5.20 0.54 2.81 ADD GRID-A5 1.00 0.20 0.29 0.06 2.87

11 -do- EXTERNAL GB2 1.00 7.00 0.54 3.78 ADD GRID-A6 1.00 0.49 0.29 0.14 3.92

12 -do- EXTERNAL GB2 1.00 5.28 0.54 2.85 ADD GRID-A6 1.00 0.75 0.29 0.22 3.07
ADD GRID-B6 &
13 -do- EXTERNAL GB2 1.00 2.53 0.54 1.36 2.00 0.75 0.29 0.43 1.80
C6
14 -do- EXTERNAL GB1 1.00 5.00 0.54 2.70 ADD GRID-D6 1.00 0.75 0.29 0.22 2.92

15 -do- EXTERNAL GB2 1.00 5.28 0.54 2.85 ADD GRID-A1 1.00 0.75 0.29 0.22 3.07
ADD GRID-B1 &
16 -do- EXTERNAL GB2 1.00 2.53 0.54 1.36 2.00 0.75 0.29 0.43 1.80
C1
17 -do- EXTERNAL GB1 1.00 5.00 0.54 2.70 ADD GRID-D1 1.00 0.75 0.29 0.22 2.92

18 -do- EXTERNAL GB1 1.00 5.73 0.54 3.09 ADD GRID-D1 1.00 0.49 0.29 0.14 3.23
ADD GRID-D2 &
19 -do- EXTERNAL GB2 1.00 3.45 0.54 1.86 2.00 0.75 0.29 0.43 2.30
D3
20 -do- EXTERNAL GB2 1.00 2.98 0.54 1.61 ADD GRID-D3' 1.00 0.20 0.29 0.06 1.66

21 -do- EXTERNAL GB2 1.00 2.55 0.54 1.38 ADD GRID-D4 1.00 0.20 0.29 0.06 1.44

22 -do- EXTERNAL GB2 1.00 7.70 0.54 4.16 ADD GRID-D5 1.00 0.20 0.29 0.06 4.22

23 -do- EXTERNAL GB2 1.00 7.00 0.54 3.78 ADD GRID-D6 1.00 0.49 0.29 0.14 3.92

24 -do- INTERNAL GB4 1.00 2.53 0.30 0.76 - 0.76

25 -do- INTERNAL GB3 1.00 5.00 0.30 1.50 - 1.50

26 -do- INTERNAL GB3 1.00 7.10 0.30 2.13 - 2.13

27 -do- INTERNAL GB3 1.00 2.53 0.30 0.76 - 0.76

28 -do- INTERNAL GB3 1.00 7.70 0.30 2.31 - 2.31

29 -do- INTERNAL GB3 1.00 7.70 0.30 2.31 - 2.31

30 -do- EXTERNAL DDT RECESS (23.00) 0.80 0.10 (1.84) (1.84)

31 -do- EXTERNAL DDT RECESS (5.00) 0.50 0.10 (0.25) (0.25)

A.3 BELOW GRAD SLAB -

32 S-BN-11.1-1111 A AREA OF GRADE SLAB 1.00 483.00 483.00

A.4 BELOW STEPS


33 S-BN-11.1-1111 A SECTION 3-3 STEPS-FRONT 1.00 2.56 1.00 2.56 2.56

34 -do- SECTION 3-3 STEPS-REAR 1.00 2.31 1.00 2.31 2.31

A.5 BELOW RAMP -

35 S-BN-11.1-1111 A SECTION 4-4 RAMP 1.00 6.90 1.61 11.07 11.07

A.6 BELOW BLOCK WORK -

36 S-BN-11.1-1111 A SECTION 4-4 BLOCK WORK AT ENTRANCE FRONT 2.00 2.61 0.54 2.81 DDT C3 (2.00) 0.45 0.25 (0.23) 2.59

37 -do- SECTION 4-4 BLOCK WORK AT ENTRANCE REAR 1.00 2.41 0.54 1.30 DDT C3 (1.00) 0.45 0.25 (0.11) 1.19

38 -do- SECTION 4-4 BLOCK WORK AT ENTRANCE REAR 1.00 2.41 0.54 1.30 DDT C3 (1.00) 0.45 0.25 (0.11) 1.19

39 -do- SECTION 4-4 DDT RAMP (1.00) 1.61 0.05 (0.08) (0.08)

TOTAL 679.71 0.73 680.44


Project :
Employer :
Engineer :
Contractor :
EXCAVATION

AFTER
SITE FORMATIO EXCAVATIO
SI NO DRW NO REV LOCATION DESCRIPTION SSL OGL NO LENGTH WIDTH DEPTH AREA QUERY ANSWER
CLEARANC N LVL N
E
(m) (m) (m) (m²) (m³)

A EXCAVATION 613.00 675.00

S-BN-11.1-1001 ASSUMED ORIGINAL GROUND LEVEL IS


1 A MASS EXCAVATION (0.07) (0.87) (1.02) (2.12) 1.00 1.10 613.36 674.69 ORIGINAL GROUND LEVEL NOT GIVEN
SITE CLEARNCE BELOW GROUND BEAM BLINDING -0.870

=SSL-GROUND BEAM HEIGHT-50mm


(FORMATION LVL=OGL-1.2m FOOTING- 50mm THK BLINDING)
THICK BLINDING
=-0.070-0.750-0.050

=-0.870

TOTAL 613.36 674.69


Project :
Employer :
Engineer :
Contractor :
SITE CLEARANCE

SI NO DRW NO REV LOCATION DESCRIPTION SSL OGL FORMATION LVL NO LENGTH WIDTH DEPTH AREA VOLUME QUERY ANSWER

(m) (m) (m) (m²) (m³)

A SITE CLEARANCE 613.000 92.000

S-BN-11.1-1001 ASSUMED ORIGINAL GROUND LEVEL IS


1 A 150mm THK SITE CLEARANCE (0.07) (0.87) (2.12) 1.00 35.00 17.50 0.15 612.50 91.88 ORIGINAL GROUND LEVEL NOT GIVEN
SITE CLEARNCE BELOW GROUND BEAM BLINDING -0.870

=SSL-GROUND BEAM HEIGHT-50mm


THICK BLINDING
=-0.070-0.750-0.050
=-0.870

TOTAL 612.50 91.88


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


DEMOLITION
DEMOLITION AND ALTERATION WORKS

(i) Demolition of precast reinforced concrete elements, stone pitched


embarkments, stainless steel elements, gate house and some plastic
elements etc

All demolished item(s) are to remain property of Employer; except


where instructed to be carted away

A Carefully demolished the existing shanties and cart away the debris away items 350,000.00
from site

B Carefully demolished existing retaining wall 300mm thick x 162 meter items 3,000,000.00
long x 6meter high.(292cu.m Approx.) and cart away the debris

C Ditto retaining wall base assume 500mm thick x 4000mm wide x items 3,500,000.00
162meter long (324cu.m Approx.) and cart away the debris

D Allow for cutting the existing reinforcement items 200,000.00

Bill Nr.2: Main building Page 2/7


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

Demolition to summary 7,050,000.00


BILL NR.2: MAIN BUILDING
SUBSTRUCTURE
GROUNDWORK
INFORMATION [All Provisional]
Nature and location of the work
The work in this section comprises:

(i) Excavations, trenches, pits and the likes, concrete work,


waterproofing, earth filling, and all other ancillary works associated with
strip/pad foundation up to and including ground floor slab. (ii)
All concrete works are provisional quantities in this section
D20: EXCAVATING AND FILLING
Excavating
Top soil for preservation

A average 150mm deep 7,491 m2 115.00 861,465.00

Pit excavation
Excavate pit for basement from ground level maximum depth not
B exceeding 10metres deep . 14,137 m3 1,083.00 15,310,371.00

C Ditto working space ditto 7,068 m3 1,083.00 7,654,644.00

Disposal of excavated material


D off site 14,137 m3 354.00 5,004,498.00

Excavated material arising from excavation


Filling to excavation
E average thickness exceeding 0.25m 7,068 m3 410.00 2,897,880.00

Selected excavated laterite material obtained from offsite borrow pits


Filling to excavation; depositing in layers 150mm maximum thickness
F average thickness 1400mm 6,792 m3 5,000.00 33,960,000.00

G Extra over for filling ramp base in basement level 01 467 m3 5,000.00 2,335,000.00

Hardcore to be obtained from off-site;

Filling to make up levels; depositing in layers 150mm maximum thickness


H average thickness 200mm 970 m3 6,279.00 6,090,630.00

Termite treatmment

J dieldrex 20" or other equal and approved anti-termite solution to sides 6,772 m2 142.00 961,624.00
and bottom of excavtions

K Keeping excavation free from general and ground water item 450,000.00

Bill Nr.2: Main building Page 2/8


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

L Extra for cut and chase on pile cap (600mm & 700mm diamter) to
accomodate pile cap 800mm deep 821 nr. 7,500.00 6,157,500.00

To collection : 81,683,612.00

E IN - SITU CONCRETE

E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Plain in-situ concrete; mix 1:10, 20 aggregate; blinding


Pile cap
A not exceeding 150mm thick; poured on 100mm PCC 364 m3 29,395.00 10,699,780.00

B Diito in lift shaft base 7 m3 29,395.00 205,765.00

Under ground slabs


C 100mm thick PCC; poured before pile cap/earth surfaces 485 m3 29,395.00 14,256,575.00

Reinforced in-situ concrete; B.S.5328, designed mix C25, 20 aggregate,


minimum cement content 395 kg/m3; vibrated (Ready mixed Concrete -
RMC)

Pile cap
D generally; 800 - 1600mm thick 1,672 m3 48,100.00 80,423,200.00

Columns stud
E generally (rectangular/square) 42 m3 48,100.00 2,020,200.00

F Diito circular 31 m3 48,100.00 1,491,100.00

Beds
G Level 01 basement slabs thickness 150-450mm thick 728 m3 48,100.00 35,016,800.00

Column (basement level 01 -level 02)


H generally (rectangular/square) 80 m3 48,100.00 3,848,000.00

J Diito circular 60 m3 48,100.00 2,886,000.00

Column (basement level 02 - ground floor (level 03)


K generally (rectangular/square) 80 m3 48,100.00 3,848,000.00

L Diito circular 60 m3 48,100.00 2,886,000.00

Level 01 (basement waffle floor)


M Solid slab 150mm thick 45 m3 48,100.00 2,164,500.00

N Cantilever 150mm thick 25 m3 48,100.00 1,202,500.00

Bill Nr.2: Main building Page 2/9


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

150mm Topping
P Basememt floor slab (level 01) 633 m3 48,100.00 30,447,300.00

Q Lift shaft base & wall starter 81 m3 48,100.00 3,896,100.00

To collection : 195,291,820.00

Level 02 (basement waffle floor)


A Solid slab 45 m3 48,100.00 2,164,500.00

B Cantilever 25 m3 48,100.00 1,202,500.00

150mm Topping
C Basememt floor slab (level 02) 633 m3 48,100.00 30,447,300.00

Beam
D Level 01 (basement ) 271 m3 48,100.00 13,035,100.00

E Level 02 (basement ) 205 m3 48,100.00 9,860,500.00

Lift wall shaft


F level 01 -level 02 57 cu.m 48,100.00 2,741,700.00

G level 02 -level 03 57 cu.m 48,100.00 2,741,700.00

Ramp
Ramp (4nr)
Slopping ramp
H Level 01-Level 02 47 cu.m 48,100.00 2,260,700.00

J Level 02-Level 03 47 cu.m 48,100.00 2,260,700.00

Ramp Beam
K Level 01-Level 02 15 cu.m 48,100.00 721,500.00

L Level 02-Level 03 15 cu.m 48,100.00 721,500.00

Driveway ramp/bridge
Slopping ramp
M Level 01-Level 02 62 cu.m 48,100.00 2,982,200.00

N Level 02-Level 03 38 cu.m 48,100.00 1,827,800.00

Ramp/bridge Beam
P Level 01-Level 02 20 cu.m 48,100.00 962,000.00

Q Level 02-Level 03 12 cu.m 48,100.00 577,200.00

Bill Nr.2: Main building Page 2/10


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Retaining wall (345lm)
R Retaining wall base (Size 3000mm x 500mm thick) 518 cu.m 48,100.00 24,915,800.00

S Retaining wall 300mm thick (6000mm x 300mm thick) 621 cu.m 48,100.00 29,870,100.00

To collection : 129,292,800.00

Staircase in basement
Landing
A generally in landing (level 01-level 02) 1 cu.m 48,100.00 48,100.00

B generally in landing (level 02-level 03) 1 cu.m 48,100.00 48,100.00

Slopping soffit of stairs (Strings)


C generally (level 01-level 02) 4 cu.m 48,100.00 192,400.00

D generally (level 02-level 03) 4 cu.m 48,100.00 192,400.00

Steps
E generally (Level 01- Level 02) 1 cu.m 48,100.00 48,100.00

F generally (Level 02- Level 03) 1 cu.m 48,100.00 48,100.00

Landing beams
G generally (Level 01- Level 02) 1 cu.m 48,100.00 48,100.00

H generally (Level 02- Level 03) 1 cu.m 48,100.00 48,100.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to produce plain surface:

Sides of foundations : plain vertical.

J Pile cap height 800 - 1600mm high 2,171 m2 4,000.00 8,684,000.00

Columns stud
K Vertical sides of column stud(rectangular/Square) 350 m2 4,000.00 1,400,000.00

L Ditto circular 202 m2 4,400.00 888,800.00

Column (basement level 01 -level 02)


M Vertical sides of column stud(rectangular/Square) 675 m2 4,000.00 2,700,000.00

N Ditto circular 390 m2 4,400.00 1,716,000.00

Bill Nr.2: Main building Page 2/11


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Column (basement level 02 - ground floor (level 03)
P Vertical sides of column stud(rectangular/Square) 675 m2 4,000.00 2,700,000.00

Q Ditto circular 390 m2 4,400.00 1,716,000.00

Level 01 (basement floor)


R Soffit of slab 4,685 m2 4,000.00 18,740,000.00

T Ditto edges not exceeding 250mm wide 4,072 m 1,000.00 4,072,000.00

To collection : 43,290,200.00

Level 02 (basement floor)


A Soffit of slab 4,685 m2 4,000.00 18,740,000.00

B Ditto edges not exceeding 250mm wide 4,072 m 1,000.00 4,072,000.00

Beam
C Sides and soffit of beam (level 01) 1,974 m2 4,000.00 7,896,000.00

D Sides and soffit of beam (level 02) 1,834 m2 4,000.00 7,336,000.00

lift wall base


E Vertical sides of lift wall starter 268 m2 4,000.00 1,072,000.00

F Edges of lift base not exceeding not exceeding 95 m 1,200.00 114,000.00

G Vertical sides of lift wall (level 01 -Level 02) 350 m2 4,000.00 1,400,000.00

H Vertical sides of lift wall (level 02 -Level 03) 350 m2 4,000.00 1,400,000.00

Ramp
J Sides and soffit of ramp (level 01-level 02) 253 m2 4,000.00 1,012,000.00

K Sides and soffit of ramp (level 02-level 03) 253 m2 4,000.00 1,012,000.00

Ramp beam
L Sides and soffit of ramp (level 01-level 02) 161 m2 4,000.00 644,000.00

M Sides and soffit of ramp (level 02-level 03) 161 m2 4,000.00 644,000.00

Driveway ramp/bridge
Slopping ramp

N Sides and Soffit of slopping ramp (Level 01 - Level 02) 372 m2 4,000.00 1,488,000.00

P Sides and Soffit of slopping ramp (Level 01 - Level 02) 217 m2 4,000.00 868,000.00

Ramp beam

Bill Nr.2: Main building Page 2/12


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Q Sides and soffit of ramp (level 01-level 02) 238 m2 4,000.00 952,000.00

R Sides and soffit of ramp (level 02-level 03) 139 m2 4,000.00 556,000.00

Retaining wall (345lm)


S Vertical sides of wall base 345 m2 4,000.00 1,380,000.00

T Vertical sides of wall 4,140 m2 4,000.00 16,560,000.00

To collection : 67,146,000.00

Staircase

Horizontal soffit of landing

A 4,000.00 36,000.00
slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m 9 m2

Sides and soffit of landing beams


B slope exceeding 15 degrees 5 m2 4,000.00 20,000.00

Slopping soffit of stairs


C slope exceeding 15 degrees 21 m2 4,000.00 84,000.00

Edges of suspended landing; plain vertical


D height not exceeding 250mm 12 m 1,000.00 12,000.00

Steps; edges of risers, plain vertical


E average height 250mm 60 m 1,000.00 60,000.00

Raking string of steps


F width not exceeding 250mm 17 m 1,000.00 17,000.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel


(TMT-TIGER)

Straight and bent

Pile Cap
G H12 0.87 t 710,000.00 617,700.00

H H16 37.07 t 710,000.00 26,319,700.00

J H20 71.00 t 710,000.00 50,410,000.00

K H25 95.00 t 710,000.00 67,450,000.00

Bill Nr.2: Main building Page 2/13


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

Columns

L H10 (stirrups) 0.92 t 710,000.00 653,200.00

M H16 0.21 t 710,000.00 149,100.00

N H20 0.15 t 710,000.00 106,500.00

P H25 13.20 t 710,000.00 9,372,000.00

To collection : 155,307,200.00

Column stud
A H10 4.15 t 710,000.00 2,946,500.00

B H16 0.23 t 710,000.00 163,300.00

C H20 0.44 t 710,000.00 312,400.00

D H25 25.30 t 710,000.00 17,963,000.00

Column (basement level 01 -level 02)


E H10 8.30 t 710,000.00 5,893,000.00

F H16 0.32 t 710,000.00 227,200.00

G H20 0.62 t 710,000.00 440,200.00

H H25 35.43 t 710,000.00 25,155,300.00

Column (basement level 02 - ground floor (level 03)


J H10 8.30 t 710,000.00 5,893,000.00

K H16 0.32 t 710,000.00 227,200.00

L H20 0.62 t 710,000.00 440,200.00

M H25 35.43 t 710,000.00 25,155,300.00

Slab/waffle (level 01)


N H8 11.21 t 710,000.00 7,959,100.00

P H10 0.13 t 710,000.00 92,300.00

Q H12 31.68 t 710,000.00 22,492,800.00

Bill Nr.2: Main building Page 2/14


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

R H16 56.67 t 710,000.00 40,235,700.00

Slab/waffle (level 02)


S H8 11.21 t 710,000.00 7,959,100.00

T H10 0.13 t 710,000.00 92,300.00

U H12 31.68 t 710,000.00 22,492,800.00

V H16 56.67 t 710,000.00 40,235,700.00

To collection : 226,376,400.00

Beam (level 01)


A H10 15.98 t 710,000.00 11,345,800.00

B H12 0.33 t 710,000.00 234,300.00

C H16 3.89 t 710,000.00 2,761,900.00

D H20 26.17 t 710,000.00 18,580,700.00

E H25 17.10 t 710,000.00 12,141,000.00

Beam (level 02)


F H10 15.98 t 710,000.00 11,345,800.00

G H12 0.33 t 710,000.00 234,300.00

H H16 3.89 t 710,000.00 2,761,900.00

J H20 26.17 t 710,000.00 18,580,700.00

K H25 17.10 t 710,000.00 12,141,000.00

Lift starter wall


L H12 0.92 t 710,000.00 653,200.00

M H16 4.60 t 710,000.00 3,266,000.00

Lift base(Provisional)
N H12 6.30 t 710,000.00 4,473,000.00

Lift wall (level 01-level 02)

Bill Nr.2: Main building Page 2/15


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


P H12 2.12 t 710,000.00 1,505,200.00

Q H16 3.52 t 710,000.00 2,499,200.00

Lift wall (level 02-level 03)


R H12 2.12 t 710,000.00 1,505,200.00

S H16 3.52 t 710,000.00 2,499,200.00

Ramp (level 01)


T H12 1.62 t 710,000.00 1,150,200.00

U H16 4.59 t 710,000.00 3,258,900.00

To collection : 110,937,500.00

Ramp (level 02)


A H12 1.62 t 710,000.00 1,150,200.00

B H16 4.59 t 710,000.00 3,258,900.00

Ramp beam (level 01)


C H10 0.52 t 710,000.00 369,200.00

D H12 4.84 t 710,000.00 3,436,400.00

E H16 1.36 t 710,000.00 965,600.00

F H20 0.96 t 710,000.00 681,600.00

Ramp beam (level 02)


G H10 0.52 t 710,000.00 369,200.00

H H12 4.84 t 710,000.00 3,436,400.00

J H16 1.36 t 710,000.00 965,600.00

K H20 0.96 t 710,000.00 681,600.00

Driveway ramp/bridge
Level 01-Level 02
L H12 2.13 t 710,000.00 1,512,300.00

M H16 6.05 t 710,000.00 4,295,500.00

Bill Nr.2: Main building Page 2/16


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Level 02-Level 03
N H12 1.30 t 710,000.00 923,000.00

P H16 3.72 t 710,000.00 2,641,200.00

Ramp/bridge Beam (level 01)


Q H10 0.72 t 710,000.00 511,200.00

R H12 6.45 t 710,000.00 4,579,500.00

S H16 1.82 t 710,000.00 1,292,200.00

T H20 1.28 t 710,000.00 908,800.00

To collection : 31,978,400.00
Ramp/bridge Beam (level 02)
A H10 0.52 t 710,000.00 369,200.00

B H12 4.84 t 710,000.00 3,436,400.00

C H16 1.36 t 710,000.00 965,600.00

D H20 0.96 t 710,000.00 681,600.00

Retaining wall base(Provisional)


E H12 62.40 t 710,000.00 44,304,000.00

F H16 93.00 t 710,000.00 66,030,000.00

Retaining wall (Provisional)


G H12 74.00 t 710,000.00 52,540,000.00

H H16 112.00 t 710,000.00 79,520,000.00

Staircase (level 01-Level 02)


J 16mm diameter 0.04 t 710,000.00 28,400.00

K 12mm diameter 0.36 t 710,000.00 255,600.00

L 10mm diameter (stirrups) 0.18 t 710,000.00 127,800.00

M 8mm 0.14 t 710,000.00 99,400.00

Bill Nr.2: Main building Page 2/17


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Staircase (level 02-Level 03)
N 16mm diameter 0.04 t 710,000.00 28,400.00

P 12mm diameter 0.36 t 710,000.00 255,600.00

Q 10mm diameter (stirrups) 0.18 t 710,000.00 127,800.00

R 8mm 0.14 t 710,000.00 99,400.00

Reinforcement fabric; B.S.4483, hard drawn plain round steel; welded


8mm thick Reference A252, weight 3.95kg/m2 measured net with
minimum 300mm side laps; 300mm end laps

S 1 layer; laid on top generally (Level 01) 5,458 m2 1,575.00 8,596,350.00

T 1 layer; laid on top generally (Level 02) 4,925 m2 1,575.00 7,756,875.00

Expansion Joint
U Expansion joint 20mm thick ploystrene naked panel 614 m2 761.00 467,254.00

To collection : 265,689,679.00

BUILDING FABRIC SUNDRIES


P10: SUNDRY INSULATION/ PROOFING WORK/ FIRE STOPS
Polythene sheeting, Visqueen 1000 gauge; 250 micron
Plain areas
A horizontal; laid loose 5,458 m2 700.00 3,820,600.00

ADDITIONAL WORK IN SUBSTRUCTURE

Allow a provisional sum of N10,000,000.00 (Ten million Naira Only) for


B unforseeing additional work in substructure to be expended as may be sum 10,000,000.00
directed by the Architect

To collection : 13,820,600.00

Collection

SUBSTRUCTURE.

Page 2/2 81,683,612.00

Page 2/3 195,291,820.00

Page 2/4 129,292,800.00

Page 2/5 43,290,200.00

Bill Nr.2: Main building Page 2/18


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Page 2/6 67,146,000.00

Page 2/7 155,307,200.00

Page 2/8 226,376,400.00

Page 2/9 110,937,500.00

Page 2/10 31,978,400.00

Page 2/11 265,689,679.00

Page 2/12 13,820,600.00

To MALL Summary : 1,320,814,211.00


FRAMES AND UPPER FLOORS
INFORMATION
Nature and location of the work
The work in this section comprises

(i.) Reinforced concrete columns, beams, suspended floor slabs and


associated works.
(ii.) The Contractor is however referred to Structural Engineer's drawings
for details and scope of the Works.
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced in-situ concrete; B.S.5328, designed mix C25, 20 aggregate,


minimum cement content 395 kg/m3; vibrated (Ready mixed Concrete -
RMC)
Solid Slabs; suspended floor 150mm thick
A 1st floor slab (level 03) 45 cu.m 48,100.00 2,164,500.00

B 2nd floor slab (level 04) 45 cu.m 48,100.00 2,164,500.00

C 3rd floor slab (level 05) 45 cu.m 48,100.00 2,164,500.00

D 4th floor slab (level 06) 45 cu.m 48,100.00 2,164,500.00

E 5th floor slab (level 07) 45 cu.m 48,100.00 2,164,500.00

F 6th floor slab (level 08) 45 cu.m 48,100.00 2,164,500.00

Bill Nr.2: Main building Page 2/19


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

G 7th floor slab (level 09) 45 cu.m 48,100.00 2,164,500.00

150mm Topping

H 1st floor slab (level 03) 514 cu.m 48,100.00 24,723,400.00

J 2nd floor slab (level 04) 514 cu.m 48,100.00 24,723,400.00

K 3rd floor slab (level 05) 514 cu.m 48,100.00 24,723,400.00

L 4th floor slab (level 06) 514 cu.m 48,100.00 24,723,400.00

M 5th floor slab (level 07) 514 cu.m 48,100.00 24,723,400.00

N 6th floor slab (level 08) 394 cu.m 48,100.00 18,951,400.00

P 7th floor slab (level 09) 506 cu.m 48,100.00 24,338,600.00

Waffle Ribs
Q 1st floor slab (level 03) 473 cu.m 48,100.00 22,751,300.00

R 2nd floor slab (level 04) 473 cu.m 48,100.00 22,751,300.00

S 3rd floor slab (level 05) 473 cu.m 48,100.00 22,751,300.00

To collection : 250,312,400.00

A 4th floor slab (level 06) 473 cu.m 48,100.00 22,751,300.00

B 5th floor slab (level 07) 473 cu.m 48,100.00 22,751,300.00

C 6th floor slab (level 08) 501 cu.m 48,100.00 24,098,100.00

D 7th floor slab (level 09) 165 cu.m 48,100.00 7,936,500.00

Beams
E 1st floor beam (level 03) 305 cu.m 48,100.00 14,670,500.00

F 2nd floor beam (level 04) 305 cu.m 48,100.00 14,670,500.00

G 3rd floor beam (level 05) 330 cu.m 48,100.00 15,873,000.00

H 4th floor beam (level 06) 330 cu.m 48,100.00 15,873,000.00

J 5th floor beam (level 07) 330 cu.m 48,100.00 15,873,000.00

K 6th floor beam (level 08) 309 cu.m 48,100.00 14,862,900.00

Lift Shaft Wall

Bill Nr.2: Main building Page 2/20


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


J Ground floor (level 02) -1st floor (level 03) 57 cu.m 48,100.00 2,741,700.00

K 1st floor (level 03) -2nd floor (level 04) 57 cu.m 48,100.00 2,741,700.00

L 2nd floor (level 04) - 3rd floor (level 05) 57 cu.m 48,100.00 2,741,700.00

M 3rd floor (level 05) -4th floor(level 06) 57 cu.m 48,100.00 2,741,700.00

N 4th floor (level 06) -5th floor( level 07) 57 cu.m 48,100.00 2,741,700.00

P 5th floor(level 08) -6th floor (level 09) 57 cu.m 48,100.00 2,741,700.00

Q 6th floor(level 09) -roof level floor 77 cu.m 48,100.00 3,703,700.00

Column
Square column type
A Ground floor (level 03) -1st floor (level 04) 68 cu.m 48,100.00 3,270,800.00

B 1st floor (level 04) -2nd floor (level 05) 68 cu.m 48,100.00 3,270,800.00

C 2nd floor (level 05) - 3rd floor (level 06) 67 cu.m 48,100.00 3,222,700.00

D 3rd floor (level 06) -4th floor(level 07) 65 cu.m 48,100.00 3,126,500.00

To collection : 202,404,800.00

A 4th floor (level 06) -5th floor( level 07) 65 cu.m 48,100.00 3,126,500.00

B 5th floor(level 07) -6th floor (level 08) 65 cu.m 48,100.00 3,126,500.00

C 6th floor(level 08) -Lower roof level (level 09) 65 cu.m 48,100.00 3,126,500.00

D Lower roof level (level 09)- Upper roof level 33 cu.m 48,100.00 1,587,300.00

Circular Column
E Ground floor (level 03) -1st floor (level 04) 45 cu.m 48,100.00 2,164,500.00

F 1st floor (level 04) -2nd floor (level 05) 30 cu.m 48,100.00 1,443,000.00

G 2nd floor (level 05) - 3rd floor (level 06) 29 cu.m 48,100.00 1,394,900.00

H 3rd floor (level 06) -4th floor(level 07) 29 cu.m 48,100.00 1,394,900.00

J 4th floor (level 06) -5th floor( level 07) 29 cu.m 48,100.00 1,394,900.00

Bill Nr.2: Main building Page 2/21


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


K 5th floor(level 07) -6th floor (level 08) 29 cu.m 48,100.00 1,394,900.00

L 6th floor(level 08) -Lower roof level (level 09) 20 cu.m 48,100.00 962,000.00

M Lower roof level (level 09)- Upper roof level 14 cu.m 48,100.00 673,400.00

Swimming pool
N Base 200mm thick 23 cu.m 48,100.00 1,106,300.00

P Beam 21 cu.m 48,100.00 1,010,100.00

R Wall 200 22 cu.m 48,100.00 1,058,200.00

Gallery
S Slab 200mm thick 90 cu.m 48,100.00 4,329,000.00

T Beam 31 cu.m 48,100.00 1,491,100.00

U Tread 1250mm wide 34 cu.m 48,100.00 1,635,400.00

To collection : 32,419,400.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to produce plain surface:


Horizontal soffit of suspended solid slab
A 1st floor slab (level 03) 300 m2 4,000.00 1,200,000.00

B 2nd floor slab (level 04) 300 m2 4,000.00 1,200,000.00

C 3rd floor slab (level 05) 300 m2 4,000.00 1,200,000.00

D 4th floor slab (level 06) 300 m2 4,000.00 1,200,000.00

E 5th floor slab (level 07) 300 m2 4,000.00 1,200,000.00

F 6th floor slab (level 08) 300 m2 4,000.00 1,200,000.00

G Pent floor (level 09) 300 m2 4,000.00 1,200,000.00

Bill Nr.2: Main building Page 2/22


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

Horizontal soffit of Topping


H 1st floor slab (level 03) 2,374 m2 4,000.00 9,496,000.00

J 2nd floor slab (level 04) 2,374 m2 4,000.00 9,496,000.00

K 3rd floor slab (level 05) 2,374 m2 4,000.00 9,496,000.00

L 4th floor slab (level 06) 2,374 m2 4,000.00 9,496,000.00

M 5th floor slab (level 07) 2,374 m2 4,000.00 9,496,000.00

N 6th floor slab (level 08) 1,255 m2 4,000.00 5,020,000.00

P Pent floor (level 09) 2,003 m2 4,000.00 8,012,000.00

Sides of Waffle ribs


Q 1st floor slab (level 03) 4,726 m2 4,000.00 18,904,000.00

R 2nd floor slab (level 04) 4,726 m2 4,000.00 18,904,000.00

S 3rd floor slab (level 05) 4,726 m2 4,000.00 18,904,000.00

T 4th floor slab (level 06) 4,726 m2 4,000.00 18,904,000.00

U 5th floor slab (level 07) 4,726 m2 4,000.00 18,904,000.00

V 6th floor slab (level 08) 5,011 m2 4,000.00 20,044,000.00

W Pent floor (level 09) 1,645 m2 4,000.00 6,580,000.00

To collection : 190,056,000.00

Sides and soffit of beam


regular shaped; height to soffit exceeding 3000mm (sides)
A 1st floor beam (level 03) 2,948 m2 4,000.00 11,792,000.00

B 2nd floor beam (level 04) 2,948 m2 4,000.00 11,792,000.00

C 3rd floor beam (level 05) 2,948 m2 4,000.00 11,792,000.00

D 4th floor beam (level 06) 2,948 m2 4,000.00 11,792,000.00

E 5th floor beam (level 07) 2,948 m2 4,000.00 11,792,000.00

F 6th floor beam (level 08) 2,726 m2 4,000.00 10,904,000.00

Vertical sides of lift wall

Bill Nr.2: Main building Page 2/23


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


G Ground floor (level 02) -1st floor (level 03) 351 m2 4,000.00 1,404,000.00

H 1st floor (level 03) -2nd floor (level 04) 351 m2 4,000.00 1,404,000.00

J 2nd floor (level 04) - 3rd floor (level 05) 351 m2 4,000.00 1,404,000.00

K 3rd floor (level 05) -4th floor(level 06) 351 m2 4,000.00 1,404,000.00

L 4th floor (level 06) -5th floor( level 07) 351 m2 4,000.00 1,404,000.00

M 5th floor(level 08) -6th floor (level 09) 351 m2 4,000.00 1,404,000.00

N 6th floor(level 09) -roof level floor 488 m2 4,000.00 1,952,000.00

Column square
Vertical sides of column
P Ground floor (level 03) -1st floor (level 04) 659 m2 4,000.00 2,636,000.00

Q 1st floor (level 04) -2nd floor (level 05) 659 m2 4,000.00 2,636,000.00

R 2nd floor (level 05) - 3rd floor (level 06) 652 m2 4,000.00 2,608,000.00

S 3rd floor (level 06) -4th floor(level 07) 645 m2 4,000.00 2,580,000.00

T 4th floor (level 06) -5th floor( level 07) 644 m2 4,000.00 2,576,000.00

U 5th floor(level 07) -6th floor (level 08) 644 m2 4,000.00 2,576,000.00

V 6th floor(level 08) -Lower roof level (level 09) 644 m2 4,000.00 2,576,000.00

W Lower roof level (level 09)- Upper roof level 374 m2 4,000.00 1,496,000.00

To collection : 99,924,000.00
Circular column
A Ground floor (level 03) -1st floor (level 04) 295 m2 4,000.00 1,180,000.00

B 1st floor (level 04) -2nd floor (level 05) 239 m2 4,000.00 956,000.00

C 2nd floor (level 05) - 3rd floor (level 06) 234 m2 4,000.00 936,000.00

D 3rd floor (level 06) -4th floor(level 07) 234 m2 4,000.00 936,000.00

E 4th floor (level 06) -5th floor( level 07) 234 m2 4,000.00 936,000.00

F 5th floor(level 07) -6th floor (level 08) 234 m2 4,000.00 936,000.00

G 6th floor(level 08) -Lower roof level (level 09) 191 m2 4,000.00 764,000.00

Bill Nr.2: Main building Page 2/24


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

H Lower roof level (level 09)- Upper roof level 147 m2 4,000.00 588,000.00

Edges of the slab not exceeding 250mm wide


J 1st floor slab (level 03) 2,212 m 1,000.00 2,212,000.00

K 2nd floor slab (level 04) 2,212 m 1,000.00 2,212,000.00

L 3rd floor slab (level 05) 2,212 m 1,000.00 2,212,000.00

M 4th floor slab (level 06) 2,212 m 1,000.00 2,212,000.00

N 5th floor slab (level 07) 2,212 m 1,000.00 2,212,000.00

P 6th floor slab (level 08) 1,468 m 1,000.00 1,468,000.00

Q Pent floor (level 09) 1,802 m 1,000.00 1,802,000.00


Swimming pool
R Swimming pool beam sides and soffit 175 m2 4,000.00 700,000.00

S Soffit of swimming pool base 160 m2 4,000.00 640,000.00

T m 1,000.00 51,000.00
Ditto edges of swimming pool base not exceeding 250mm wide 51

U Vertical sides of wall 217 m2 4,000.00 868,000.00

Gallery formwork
V Soffit of the gallery slab 450 m2 4,000.00 1,800,000.00

W Sides and soffit of gallery beam 295 m2 4,000.00 1,180,000.00

X Edges of gallery slab not exceeding 250mm wide 95 m 1,000.00 95,000.00

Y Riser to gallery tread 200mm wide 270 m 1,000.00 270,000.00

Z String not exceeding 300mm 70 m 1,200.00 84,000.00


To collection : 27,250,000.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE


Reinforcement bars; B.S.4449, hot rolled deformed high yield steel
(TMT-TIGER)
Straight and bent
Suspended slabs/cantilever
1st floor slab (level 03)
A H8 7.61 t 710,000.00 5,403,100.00

B H10 0.13 t 710,000.00 92,300.00

C H12 7.50 t 710,000.00 5,325,000.00

Bill Nr.2: Main building Page 2/25


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

D H16 28.70 t 710,000.00 20,377,000.00

E H12(hunch bench) Provisional 4.40 t 710,000.00 3,124,000.00

2nd floor slab (level 04)


F H8 7.61 t 710,000.00 5,403,100.00

G H10 0.13 t 710,000.00 92,300.00

H H12 7.50 t 710,000.00 5,325,000.00

J H16 28.70 t 710,000.00 20,377,000.00

K H12(hunch bench) Provisional 4.40 t 710,000.00 3,124,000.00

3rd floor slab (level 05)


L H8 7.61 t 710,000.00 5,403,100.00

M H10 0.13 t 710,000.00 92,300.00

N H12 7.50 t 710,000.00 5,325,000.00

P H16 28.70 t 710,000.00 20,377,000.00

Q H12(hunch bench) Provisional 4.40 t 710,000.00 3,124,000.00

4th floor slab (level 06)


R H8 7.61 t 710,000.00 5,403,100.00

S H10 0.13 t 710,000.00 92,300.00

T H12 7.50 t 710,000.00 5,325,000.00

U H16 28.70 t 710,000.00 20,377,000.00

V H12(hunch bench) Provisional 4.40 t 710,000.00 3,124,000.00


To collection : 137,285,600.00

5th floor slab (level 07)


A H8 7.11 t 710,000.00 5,048,100.00

B H10 0.13 t 710,000.00 92,300.00

C H12 6.70 t 710,000.00 4,757,000.00

D H16 23.93 t 710,000.00 16,990,300.00

E H12(hunch bench) Provisional 4.00 t 710,000.00 2,840,000.00

Bill Nr.2: Main building Page 2/26


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

6th floor slab (level 08)


F H8 7.11 t 710,000.00 5,048,100.00

G H10 0.13 t 710,000.00 92,300.00

H H12 6.70 t 710,000.00 4,757,000.00

J H16 23.93 t 710,000.00 16,990,300.00

K H12(hunch bench) Provisional 4.00 t 710,000.00 2,840,000.00

7th floor slab (level 09)


L H8 3.64 t 710,000.00 2,584,400.00

M H10 0.13 t 710,000.00 92,300.00

N H12 11.50 t 710,000.00 8,165,000.00

P H16 12.60 t 710,000.00 8,946,000.00

Q H12(hunch bench) Provisional 3.00 t 710,000.00 2,130,000.00

Beam
1st floor beam (Level 03)
J H10 13.06 t 710,000.00 9,272,600.00

K H12 0.95 t 710,000.00 674,500.00

L H16 11.85 t 710,000.00 8,413,500.00

M H20 16.14 t 710,000.00 11,459,400.00

N H25 13.91 t 710,000.00 9,876,100.00

To collection : 121,069,200.00

2nd floor beam (Level 04)


A H10 13.06 t 710,000.00 9,272,600.00

B H12 0.95 t 710,000.00 674,500.00

C H16 11.85 t 710,000.00 8,413,500.00

D H20 16.14 t 710,000.00 11,459,400.00

Bill Nr.2: Main building Page 2/27


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

E H25 13.91 t 710,000.00 9,876,100.00

3rd floor beam (Level 05)


A H10 13.06 t 710,000.00 9,272,600.00

B H12 0.95 t 710,000.00 674,500.00

C H16 11.85 t 710,000.00 8,413,500.00

D H20 16.14 t 710,000.00 11,459,400.00

E H25 13.91 t 710,000.00 9,876,100.00

4th floor beam (Level 06)


F H10 13.06 t 710,000.00 9,272,600.00

G H12 0.95 t 710,000.00 674,500.00

H H16 11.85 t 710,000.00 8,413,500.00

J H20 16.14 t 710,000.00 11,459,400.00

K H25 13.91 t 710,000.00 9,876,100.00

5th floor beam (Level 07)


L H10 13.06 t 710,000.00 9,272,600.00

M H12 0.95 t 710,000.00 674,500.00

N H16 11.85 t 710,000.00 8,413,500.00

P H20 16.14 t 710,000.00 11,459,400.00

Q H25 13.91 t 710,000.00 9,876,100.00

To collection : 158,784,400.00

6th floor beam (Level 07)


A H10 13.06 t 710,000.00 9,272,600.00

B H12 1.15 t 710,000.00 816,500.00

C H16 13.11 t 710,000.00 9,308,100.00

Bill Nr.2: Main building Page 2/28


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

D H20 16.14 t 710,000.00 11,459,400.00

E H25 13.91 t 710,000.00 9,876,100.00

Column
Ground floor (level 03) -1st floor (level 04)
F H10 8.54 t 710,000.00 6,063,400.00

G H16 0.34 t 710,000.00 241,400.00

H H20 1.73 t 710,000.00 1,228,300.00

J H25 31.00 t 710,000.00 22,010,000.00

1st floor (level 04) -2nd floor (level 05)


K H10 8.40 t 710,000.00 5,964,000.00

L H16 0.34 t 710,000.00 241,400.00

M H20 12.43 t 710,000.00 8,825,300.00

N H25 10.27 t 710,000.00 7,291,700.00

2nd floor (level 05) - 3rd floor (level 06)


P H10 8.40 t 710,000.00 5,964,000.00

Q H16 0.63 t 710,000.00 447,300.00

R H20 16.00 t 710,000.00 11,360,000.00

S H25 4.03 t 710,000.00 2,861,300.00

3rd floor (level 06) -4th floor(level 07)


T H10 8.15 t 710,000.00 5,786,500.00

U H16 0.63 t 710,000.00 447,300.00

V H20 17.00 t 710,000.00 12,070,000.00

To collection : 131,534,600.00

4th floor (level 06) -5th floor( level 07)


A H10 8.15 t 710,000.00 5,786,500.00

B H16 8.10 t 710,000.00 5,751,000.00

Bill Nr.2: Main building Page 2/29


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

C H20 5.00 t 710,000.00 3,550,000.00

5th floor (level 07) -6th floor( level 08)


D H10 8.15 t 710,000.00 5,786,500.00

E H16 9.80 t 710,000.00 6,958,000.00

F H20 2.31 t 710,000.00 1,640,100.00

6th floor(level 08) -Lower roof level (level 09)


G H10 8.00 t 710,000.00 5,680,000.00

H H16 9.08 t 710,000.00 6,446,800.00

J H20 2.31 t 710,000.00 1,640,100.00

Lower roof level (level 09)- Upper roof level


K H10 4.00 t 710,000.00 2,840,000.00

L H16 6.00 t 710,000.00 4,260,000.00

M H20 0.53 t 710,000.00 376,300.00

Lift shaft
Ground floor (level 03) -1st floor (level 04)
N H12 2.13 t 710,000.00 1,512,300.00

P H16 3.52 t 710,000.00 2,499,200.00


1st floor (level 04) -2nd floor (level 05)
Q H12 2.13 t 710,000.00 1,512,300.00

R H16 3.52 t 710,000.00 2,499,200.00


2nd floor (level 05) - 3rd floor (level 06)
S H12 2.13 t 710,000.00 1,512,300.00

T H16 3.52 t 710,000.00 2,499,200.00


3rd floor (level 06) -4th floor(level 07)
U H12 2.13 t 710,000.00 1,512,300.00

V H16 3.52 t 710,000.00 2,499,200.00


4th floor (level 06) -5th floor( level 07)
W H12 2.13 t 710,000.00 1,512,300.00

X H16 3.52 t 710,000.00 2,499,200.00


To collection : 70,772,800.00
5th floor (level 07) -6th floor( level 08)
A H12 2.13 t 710,000.00 1,512,300.00

Bill Nr.2: Main building Page 2/30


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


B H16 3.52 t 710,000.00 2,499,200.00
6th floor(level 08) -upper roof level
C H12 4.97 t 710,000.00 3,528,700.00

D H16 1.14 t 710,000.00 809,400.00

Swimming pool
In Swimming pool wall
E H12 0.73 t 710,000.00 518,300.00

F H16 3.81 t 710,000.00 2,705,100.00

In Swimming pool base


G H12 3.14 t 710,000.00 2,229,400.00

H H12 (Provisional haunch bench) 0.31 t 710,000.00 220,100.00

In Swimming pool beam (Provisional)


J H10 1.58 t 710,000.00 1,121,800.00

K H16 3.68 t 710,000.00 2,612,800.00

Gallery
In gallery slab
L H12 8.23 t 710,000.00 5,843,300.00

In gallery beam
M H10 1.36 t 710,000.00 965,600.00

N H16 1.46 t 710,000.00 1,036,600.00

P H20 0.32 t 710,000.00 227,200.00

Q H25 4.23 t 710,000.00 3,003,300.00

Reinforcement fabric; B.S.4483, hard drawn plain round steel; welded


7mm thick Reference A193, weight 3.02kg/m2 measured net with
minimum 300mm side laps; 300mm end laps

R 1 layer; laid on top generally (Level 03) 2,374 m2 1,575.00 3,739,050.00

S Ditto (level 04) 2,374 m2 1,575.00 3,739,050.00

T Ditto (level 05) 2,374 m2 1,575.00 3,739,050.00

U Ditto (level 06) 2,374 m2 1,575.00 3,739,050.00

To collection : 43,789,300.00
Brc cont'd

Bill Nr.2: Main building Page 2/31


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


A Ditto (level 07) 2,374 m2 1,575.00 3,739,050.00

B Ditto( level 08) 1,255 m2 1,575.00 1,976,625.00

C Ditto (level 09) 2,003 m2 1,575.00 3,154,725.00

400mm x 225mm Polystrene pod


D Polystrene 400mm x 225mm in level (Level 03) 1,396 m2 9,400.00 13,122,400.00

E Ditto (level 04) 1,396 m2 9,400.00 13,122,400.00

F Ditto (level 05) 1,396 m2 9,400.00 13,122,400.00

G Ditto (level 06) 1,396 m2 9,400.00 13,122,400.00

H Ditto (level 07) 1,396 m2 9,400.00 13,122,400.00

J Ditto (level 08) 1,459 m2 9,400.00 13,714,600.00

K Ditto (level 09) 462 m2 9,400.00 4,342,800.00


Sundries
Swimming pool
R Supply and install 2 layers of bituminous felt 270 m2 8,500.00 2,295,000.00
To collection : 182,413,400.00
Collection
FRAME & UPPER FLOOR
Page 2/6 250,312,400.00

Page 2/7 202,404,800.00

Page 2/8 32,419,400.00

Page 2/9 190,056,000.00

Page 2/10 99,924,000.00

Page 2/11 27,250,000.00

Page 2/12 137,285,600.00

Page 2/13 121,069,200.00

Page 2/14 158,784,400.00

Page 2/15 131,534,600.00

Page 2/16 70,772,800.00

Page 2/17 182,413,400.00

Bill Nr.2: Main building Page 2/32


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


To MALL Summary : 1,604,226,600.00
STAIRCASES
INFORMATION
Nature and location of the work

The work in this section comprises

(i.) Reinforced concrete staircases and associated works.


(ii.) The Contractor is however referred to Structural Engineer's drawings
for details and scope of the Works.

E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced in-situ concrete; B.S.5328, designed mix C25, 20 aggregate,


minimum cement content 395 kg/m3; vibrated (Ready mixed Concrete -
RMC)
Landing

A Level 03 - Level 04 2 m3 48,100.00 96,200.00

B Level 04 - Level 05 2 m3 48,100.00 96,200.00

C Level 05 - Level 06 2 m3 48,100.00 96,200.00

D Level 06 - Level 07 1 m3 48,100.00 48,100.00

E Level 07 - Level 08 1 m3 48,100.00 48,100.00

F Level 08 - Level 09 1 m3 48,100.00 48,100.00

G Level 09 - Level 10 1 m3 48,100.00 48,100.00

Slopping soffit of stairs


H Level 03 - Level 04 13 m3 48,100.00 625,300.00

J Level 04 - Level 05 13 m3 48,100.00 625,300.00

K Level 05 - Level 06 13 m3 48,100.00 625,300.00

L Level 06 - Level 07 13 m3 48,100.00 625,300.00

M Level 07 - Level 08 13 m3 48,100.00 625,300.00

N Level 08 - Level 09 13 m3 48,100.00 625,300.00

P Level 09 - Level 10 13 m3 48,100.00 625,300.00

Bill Nr.2: Main building Page 2/33


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To collection : 4,858,100.00
Steps
A Level 03 - Level 04 5 m3 48,100.00 240,500.00

B Level 04 - Level 05 5 m3 48,100.00 240,500.00

C Level 05 - Level 06 5 m3 48,100.00 240,500.00

D Level 06 - Level 07 5 m3 48,100.00 240,500.00

E Level 07 - Level 08 5 m3 48,100.00 240,500.00

F Level 08 - Level 09 5 m3 48,100.00 240,500.00

G Level 09 - Level 10 5 m3 48,100.00 240,500.00

E20: FORMWORK FOR IN-SITU CONCRETE


Sawn formwork to produce plain surface:
Horizontal soffit of landing
Slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m
H Level 03 - Level 04 5 m2 4,000.00 20,000.00

J Level 04 - Level 05 5 m2 4,000.00 20,000.00

K Level 05 - Level 06 5 m2 4,000.00 20,000.00

L Level 06 - Level 07 5 m2 4,000.00 20,000.00

M Level 07 - Level 08 5 m2 4,000.00 20,000.00

N Level 08 - Level 09 5 m2 4,000.00 20,000.00

P Level 09 - Level 10 5 m2 4,000.00 20,000.00

Slopping soffit of stairs


slope exceeding 15 degrees
Q Level 03 - Level 04 71 m2 4,000.00 284,000.00

R Level 04 - Level 05 71 m2 4,000.00 284,000.00

S Level 05 - Level 06 71 m2 4,000.00 284,000.00

T Level 06 - Level 07 71 m2 4,000.00 284,000.00

U Level 07 - Level 08 71 m2 4,000.00 284,000.00

W Level 08 - Level 09 71 m2 4,000.00 284,000.00

Bill Nr.2: Main building Page 2/34


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

X Level 09 - Level 10 71 m2 4,000.00 284,000.00

To collection : 3,811,500.00
Edges of landing
not exceeding 250mm wide
A Level 03 - Level 04 33 m 1,000.00 33,000.00

B Level 04 - Level 05 33 m 1,000.00 33,000.00

C Level 05 - Level 06 33 m 1,000.00 33,000.00

D Level 06 - Level 07 33 m 1,000.00 33,000.00

E Level 07 - Level 08 33 m 1,000.00 33,000.00

F Level 08 - Level 09 33 m 1,000.00 33,000.00

G Level 09 - Level 10 33 m 1,000.00 33,000.00

Steps; edges of risers, plain vertical


not exceeding 150mm wide
H Level 03 - Level 04 198 m 600.00 118,800.00

J Level 04 - Level 05 198 m 600.00 118,800.00

K Level 05 - Level 06 198 m 600.00 118,800.00

L Level 06 - Level 07 198 m 600.00 118,800.00

M Level 07 - Level 08 198 m 600.00 118,800.00

N Level 08 - Level 09 198 m 600.00 118,800.00

P Level 09 - Level 10 198 m 600.00 118,800.00

Raking string of steps


width not exceeding 375mm
Q Level 03 - Level 04 40 m 1,500.00 60,000.00

R Level 04 - Level 05 40 m 1,500.00 60,000.00

S Level 05 - Level 06 40 m 1,500.00 60,000.00

T Level 06 - Level 07 40 m 1,500.00 60,000.00

U Level 07 - Level 08 40 m 1,500.00 60,000.00

Bill Nr.2: Main building Page 2/35


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


V Level 08 - Level 09 40 m 1,500.00 60,000.00

W Level 09 - Level 10 40 m 1,500.00 60,000.00

To collection : 1,482,600.00
E30: REINFORCEMENT FOR IN-SITU CONCRETE
Reinforcement bars; B.S.4449, hot rolled deformed high yield steel
(TMT-TIGER)
Straight and bent
Stairs
Level 03 - Level 04
A H12 1.80 t 710,000.00 1,278,000.00

B H10 0.32 t 710,000.00 227,200.00

Level 04 - Level 05
C H12 1.80 t 710,000.00 1,278,000.00

D H10 0.32 t 710,000.00 227,200.00

Level 06 - Level 07
E H12 1.80 t 710,000.00 1,278,000.00

F H10 0.32 t 710,000.00 227,200.00

Level 07 - Level 08
G H12 1.10 t 710,000.00 781,000.00

H H10 0.20 t 710,000.00 142,000.00

Level 08 - Level 09
J H12 1.10 t 710,000.00 781,000.00

K H10 0.20 t 710,000.00 142,000.00

Level 09 - Level 10
L H12 1.10 t 710,000.00 781,000.00

M H10 0.20 t 710,000.00 142,000.00

L31 METAL BALUSTRADES

Approved Balustrade comprising of 50mm Diameter galvanished hollow


steel pipe epoxy painted verticals balustrade and 65mm Diameter
galvanished hollow steel epoxy painted horizontal handrail spaced at
150mm c/c with 25mm Diameter Galvanished epoxy painted handrail.
G Level 03 - Level 04 47 m 75,000.00 3,525,000.00

Bill Nr.2: Main building Page 2/36


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


H Level 04 - Level 05 47 m 75,000.00 3,525,000.00

J Level 06 - Level 07 47 m 75,000.00 3,525,000.00

K Level 07 - Level 08 28 m 75,000.00 2,100,000.00

L Level 08 - Level 09 28 m 75,000.00 2,100,000.00

M Level 09 - Level 10 28 m 75,000.00 2,100,000.00


To collection : 24,159,600.00
SURFACE FINISHES
M10: SAND CEMENT/ CONCRETE/ SCREEDS/TOPPINGS
Mortar, cement and sand (1:4) beds and backings
30mm work to floor on concrete base
Landing
A Level 03 - Level 04 14 m2 2,040.00 28,560.00

B Level 04 - Level 05 14 m2 2,040.00 28,560.00

C Level 06 - Level 07 14 m2 2,040.00 28,560.00

D Level 07 - Level 08 14 m2 2,040.00 28,560.00

E Level 08 - Level 09 14 m2 2,040.00 28,560.00

F Level 09 - Level 10 14 m2 2,040.00 28,560.00

25mm work to treads on concrete base


width 300mm
G Level 03 - Level 04 198 m 401.00 79,398.00

J Level 04 - Level 05 198 m 401.00 79,398.00

K Level 06 - Level 07 198 m 401.00 79,398.00

L Level 07 - Level 08 198 m 401.00 79,398.00

M Level 08 - Level 09 198 m 401.00 79,398.00

N Level 09 - Level 10 198 m 401.00 79,398.00

12mm work to plain risers on concrete base


height 150mm
P Level 03 - Level 04 198 m 120.00 23,760.00

Q Level 04 - Level 05 198 m 120.00 23,760.00

R Level 06 - Level 07 198 m 120.00 23,760.00

Bill Nr.2: Main building Page 2/37


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


S Level 07 - Level 08 198 m 120.00 23,760.00

T Level 08 - Level 09 198 m 120.00 23,760.00

U Level 09 - Level 10 198 m 120.00 23,760.00

To collection : 790,308.00

12mm work to skirting on wall


height 100mm
A Level 03 - Level 04 198 m 80.00 15,840.00

B Level 04 - Level 05 198 m 80.00 15,840.00

C Level 06 - Level 07 198 m 80.00 15,840.00

D Level 07 - Level 08 198 m 80.00 15,840.00

E Level 08 - Level 09 198 m 80.00 15,840.00

F Level 09 - Level 10 198 m 80.00 15,840.00

M40: STONE/ CONCRETE/ QUARRY/ CERAMIC TILING/MOSAIC

Supply and install


Nigeria Granite floor tiles;(Kamazo grey) 3 joints systematic layout,
bedding in 10 cement mortar (1:4); including pointing.

800mm x 400mm x 15mm thick to floors on cement and sand base;


level to falls only not exceeding 15 degrees from horizontal

Landing
A Level 03 - Level 04 14 m2 15,036.00 210,504.00

B Level 04 - Level 05 14 m2 15,036.00 210,504.00

C Level 06 - Level 07 14 m2 15,036.00 210,504.00

D Level 07 - Level 08 14 m2 15,036.00 210,504.00

E Level 08 - Level 09 14 m2 15,036.00 210,504.00

F Level 09 - Level 10 14 m2 15,036.00 210,504.00

Bill Nr.2: Main building Page 2/38


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Staircase treads slab
width 300mm
F Level 03 - Level 04 198 m 10,024.00 1,984,752.00

J Level 04 - Level 05 198 m 10,024.00 1,984,752.00

K Level 06 - Level 07 198 m 10,024.00 1,984,752.00

L Level 07 - Level 08 198 m 10,024.00 1,984,752.00

M Level 08 - Level 09 198 m 10,024.00 1,984,752.00

N Level 09 - Level 10 198 m 10,024.00 1,984,752.00


To collection : 13,266,576.00
Staircase risers
height 150mm
A Level 03 - Level 04 198 m 5,012.00 992,376.00

B Level 04 - Level 05 198 m 5,012.00 992,376.00

C Level 06 - Level 07 198 m 5,012.00 992,376.00

D Level 07 - Level 08 198 m 5,012.00 992,376.00

E Level 08 - Level 09 198 m 5,012.00 992,376.00

F Level 09 - Level 10 198 m 5,012.00 992,376.00

Skirting on wall
height 100mm
G Level 03 - Level 04 198 m 1,503.60 297,712.80

H Level 04 - Level 05 198 m 1,503.60 297,712.80

J Level 06 - Level 07 198 m 1,503.60 297,712.80

K Level 07 - Level 08 198 m 1,503.60 297,712.80

L Level 08 - Level 09 198 m 1,503.60 297,712.80

M Level 09 - Level 10 198 m 1,503.60 297,712.80

M20: PLASTERED/RENDERED

Mortar, cement and sand (1:4); steel trowelled


12mm work to walls on concrete base or blockwork
Horizontal soffit of landing
regular shaped; rectangular; height to soffit 1.50 - 3.00m
L Level 03 - Level 04 14 m2 1,500.00 21,000.00

Bill Nr.2: Main building Page 2/39


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

M Level 04 - Level 05 14 m2 1,500.00 21,000.00

N Level 06 - Level 07 14 m2 1,500.00 21,000.00

P Level 07 - Level 08 14 m2 1,500.00 21,000.00

Q Level 08 - Level 09 14 m2 1,500.00 21,000.00

Level 09 - Level 10 14 m2 1,500.00 21,000.00

To collection : 7,866,532.80
Slopping soffit of stairs
slope exceeding 15 degrees
A Level 03 - Level 04 71 m2 1,500.00 106,500.00

B Level 04 - Level 05 71 m2 1,500.00 106,500.00

C Level 05 - Level 06 71 m2 1,500.00 106,500.00

D Level 06 - Level 07 71 m2 1,500.00 106,500.00

E Level 07 - Level 08 71 m2 1,500.00 106,500.00

F Level 08 - Level 09 71 m2 1,500.00 106,500.00

G Level 09 - Level 10 71 m2 1,500.00 106,500.00


Raking string of staircase
width not exceeding 375mm
F Level 03 - Level 04 40 m 562.50 22,500.00

G Level 04 - Level 05 40 m 562.50 22,500.00

H Level 05 - Level 06 40 m 562.50 22,500.00

J Level 06 - Level 07 40 m 562.50 22,500.00

K Level 07 - Level 08 40 m 562.50 22,500.00

L Level 08 - Level 09 40 m 562.50 22,500.00

M Level 09 - Level 10 40 m 562.50 22,500.00


M60: PAINTING/CLEAR FINISHING
Wall screeding (I-nox)
floating of landing soffits
over 300mm wide; internal; as architectural details

Bill Nr.2: Main building Page 2/40


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Slopping soffit of stairs
slope exceeding 15 degrees
L Level 03 - Level 04 71 m2 625.00 44,375.00

M Level 04 - Level 05 71 m2 625.00 44,375.00

N Level 05 - Level 06 71 m2 625.00 44,375.00

P Level 06 - Level 07 71 m2 625.00 44,375.00

Q Level 07 - Level 08 71 m2 625.00 44,375.00

R Level 08 - Level 09 71 m2 625.00 44,375.00

S Level 09 - Level 10 71 m2 625.00 44,375.00

To collection : 1,213,625.00
Raking string of staircase
width not exceeding 375mm
A Level 03 - Level 04 40 m 234.38 9,375.00

B Level 04 - Level 05 40 m 234.38 9,375.00

C Level 05 - Level 06 40 m 234.38 9,375.00

D Level 06 - Level 07 40 m 234.38 9,375.00

E Level 07 - Level 08 40 m 234.38 9,375.00

F Level 08 - Level 09 40 m 234.38 9,375.00

G Level 09 - Level 10 40 m 234.38 9,375.00

Horizontal soffit of landing


regular shaped; rectangular; height to soffit 1.50 - 3.00m
H Level 03 - Level 04 5 m2 625.00 3,125.00

J Level 04 - Level 05 5 m2 625.00 3,125.00

K Level 05 - Level 06 5 m2 625.00 3,125.00

L Level 06 - Level 07 5 m2 625.00 3,125.00

M Level 07 - Level 08 5 m2 625.00 3,125.00

N Level 08 - Level 09 5 m2 625.00 3,125.00

P Level 09 - Level 10 5 m2 625.00 3,125.00

Bill Nr.2: Main building Page 2/41


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


One mist coat and two full coats of "dulux" emulsion paint
Cement rendered general surfaces
Horizontal soffit of landing
regular shaped; rectangular; height to soffit 1.50 - 3.00m
L Level 03 - Level 04 5 m2 1,312.50 6,562.50

M Level 04 - Level 05 5 m2 1,312.50 6,562.50

N Level 05 - Level 06 5 m2 1,312.50 6,562.50

P Level 06 - Level 07 5 m2 1,312.50 6,562.50

To collection : 113,750.00

A Level 07 - Level 08 5 m2 1,312.50 6,562.50

B Level 08 - Level 09 5 m2 1,312.50 6,562.50

C Level 09 - Level 10 5 m2 1,312.50 6,562.50

Slopping soffit of stairs


slope exceeding 15 degrees
D Level 03 - Level 04 71 m2 1,312.50 93,187.50

E Level 04 - Level 05 71 m2 1,312.50 93,187.50

F Level 05 - Level 06 71 m2 1,312.50 93,187.50

G Level 06 - Level 07 71 m2 1,312.50 93,187.50

H Level 07 - Level 08 71 m2 1,312.50 93,187.50

J Level 08 - Level 09 71 m2 1,312.50 93,187.50

K Level 09 - Level 10 71 m2 1,312.50 93,187.50

Raking string of staircase


width not exceeding 375mm

Bill Nr.2: Main building Page 2/42


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


L Level 03 - Level 04 40 m 492.19 19,687.50

M Level 04 - Level 05 40 m 492.19 19,687.50

N Level 05 - Level 06 40 m 492.19 19,687.50

P Level 06 - Level 07 40 m 492.19 19,687.50

Q Level 07 - Level 08 40 m 492.19 19,687.50

R Level 08 - Level 09 40 m 492.19 19,687.50

S Level 09 - Level 10 40 m 492.19 19,687.50

To collection : 809,812.50

Collection
STAIRCASE.
Page 2/26 4,858,100.00

Page 2/27 3,811,500.00

Page 2/28 1,482,600.00

Page 2/29 24,159,600.00

Page 2/30 790,308.00

Page 2/31 13,266,576.00

Page 2/32 7,866,532.80

Page 2/33 1,213,625.00

Page 2/34 113,750.00

Page 2/35 809,812.50

Bill Nr.2: Main building Page 2/43


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To MALL Summary : 58,372,404.30


ROOF AND ROOF COVERING
INFORMATION
Nature and location of the work
The work in this section comprises

(i.) Reinforced concrete roof beams, structural timber works, roof


covering and associated works.
(ii.) The Contractor is however referred to Architect's and Structural
Engineer's drawing for the scope of work.

E IN - SITU CONCRETE

E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced in-situ concrete; B.S.5328, designed mix C25, 20 aggregate,


minimum cement content 395 kg/m3; vibrated (Ready mixed Concrete -
RMC)

Beams; roof beams

A lower roof beam not exceeding 600mm deep 203 m3 48,100.00 9,764,300.00

B Upper roof beam not exceeding 600mm deep 102 m3 48,100.00 4,906,200.00

Roof gutter slab 150mm thick

C Solid slab area generally 134 m3 48,100.00 6,445,400.00

D Ditto topping 506 m3 48,100.00 24,338,600.00

Bill Nr.2: Main building Page 2/44


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


E Ditto waffle ribs 165 m3 48,100.00 7,936,500.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to produce plain surface:

Beam; plain vertical and soffit


F Lower roof beams 1,995 m2 4,000.00 7,980,000.00

G Upper roof beams 1,088 m2 4,000.00 4,352,000.00

Horizontal soffit of suspended roof gutter slab;


H regular shaped; rectangular; 2,302 m2 4,000.00 9,208,000.00

Edges of suspended roof gutter slab; plain vertical


J height not exceeding 250mm 1,802 m 1,000.00 1,802,000.00

To collection : 76,733,000.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel


(TMT-TIGER)

Straight and bent

Roof Beams (lower roof )


A H10 10.32 t 710,000.00 7,327,200.00

B H12 0.36 t 710,000.00 255,600.00

C H16 13.35 t 710,000.00 9,478,500.00

D H20 10.04 t 710,000.00 7,128,400.00

E H25 5.22 t 710,000.00 3,706,200.00

Upper roof beam


F H8 1.28 t 710,000.00 908,800.00

G H10 3.66 t 710,000.00 2,598,600.00

H H16 9.61 t 710,000.00 6,823,100.00

Roof gutter and slab


J H8 3.64 t 710,000.00 2,584,400.00

Bill Nr.2: Main building Page 2/45


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

K H10 0.13 t 710,000.00 92,300.00

L H12 11.47 t 710,000.00 8,143,700.00

M H16 12.59 t 710,000.00 8,938,900.00

Parapet wall

D m2 5,731.00 8,298,488.00
225mm blockwall filled with concrete (1: 4:8-20mm aggregate) 1,448

K 12mm plastering 1,448 m2 1,500.00 2,172,000.00

L Wall screeding ( x-nox exterior) 1,448 m2 1,000.00 1,448,000.00

M Precast concrete copping 300mm wide x 50mm thick 180 m 1,500.00 270,000.00

70,174,188.00

STRUCTURAL STEEL WORK (LOWER ROOF TRUSSES)

Supply,Fabricate and Install the following existing structural steel roof


members weldable steel: to B.S4360 ‘ hot rolled sections; site fabricated
and bolted site connection Install at roof level over 4.00m above ground
floor levtel, with and including angle cleats, hoisting and erection,
painting with red oxide primer on surfaces, including plates,anti sag rods,
nuts, bolts and other accessories and surface treatment on site after
installation

Rafters
A 65 x 65 x 6mm thick (Top and bottom members) 585 m 10,500.00 6,142,500.00

Zed Purlins
B 150 x 50 x 2mm thick Zed purlins @ 909 ctrs 1441 m 7,850.00 11,311,850.00

Internal Members
C 65 x 65 x 6mm thick (Internal members) 506 m 6,800.00 3,440,800.00

Bracing
D 70 x 70 x 6mm L bracing 462 m 2,550.00 1,178,100.00

Antisag Rods
E 12mmØ Antisag rods 252 m 500.00 126,000.00

Bill Nr.2: Main building Page 2/46


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Angle Cleats
F 125 x 75 x 8mm thick angle cleat on purlins 330 nr 6,800.00 2,244,000.00

Connecting Plates
G 450 x 300 x 20mm thick mild steel plate on end trusses 30 nr 6,800.00 204,000.00

Bolts and Nuts


H 20mmØ Bolts 690 nr 6,800.00 4,692,000.00

J Nuts ditto 690 nr 6,800.00 4,692,000.00

H72: DESIGN ROOFING SHEET COVERINGS/ FLASHINGS


Aluminium roof covering
'Queensway''Gauge 0.7mm coloured Aluminium roof covering 900mm
corruagtion [as approved by Architect]: roof coverings; fixing to
hardwood purlins with fixing screws; 200mm end laps and one or two
corrugation side laps.

K pitch not exceeding 15 degrees 1258 m2 8,500.00 10,693,000.00

Cappings; ridge; barge board

L 600mm girth 66 m 5,100.00 336,600.00

Cappings; flashings; eaves angle

M 250mm girth 171 m 2,125.00 363,375.00

45,424,225.00
STRUCTURAL STEEL WORK (UPPER ROOF TRUSSES)

Supply,Fabricate and Install the following existing structural steel roof


members weldable steel: to B.S4360 ‘ hot rolled sections; site fabricated
and bolted site connection Install at roof level over 4.00m above ground
floor levtel, with and including angle cleats, hoisting and erection,
painting with red oxide primer on surfaces, including plates,anti sag rods,
nuts, bolts and other accessories and surface treatment on site after
installation

Zed Purlins

A 150 x 50 x 2mm thick Zed purlins @ 909 ctrs 2160 m 7,850.00 16,956,000.00

Antisag Rods
B 12mmØ Antisag rods 384 m 500.00 192,000.00

Angle cleat
C 125 x 75 x 8mm thick angle cleat on purlins 504 nr 6,800.00 3,427,200.00

Bolts and Nuts


D 20mmØ Bolts 1008 nr 1,500.00 1,512,000.00

Bill Nr.2: Main building Page 2/47


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

E Nuts ditto 1008 nr 1,500.00 1,512,000.00

H72: DESIGN ROOFING SHEET COVERINGS/ FLASHINGS


Aluminium roof covering
'Queensway''Gauge 0.7mm coloured Aluminium roof covering 900mm
corruagtion [as approved by Architect]: roof coverings; fixing to
hardwood purlins with fixing screws; 200mm end laps and one or two
corrugation side laps.

F pitch not exceeding 15 degrees 2000 m2 8,500.00 17,000,000.00

Cappings; flashings; eaves angle


G 250mm girth 546 m 2,125.00 1,160,250.00

30mm work to roofs on concrete base; one coat; screeded

H to falls and crossfalls and to slopes not exceeding 15 degrees from 2,302 m2 3,500.00 8,057,000.00
horizontal

49,816,450.00
Collection

ROOF AND ROOF COVERING

Page 2/37 76,733,000.00

Page 2/38 70,174,188.00

Page 2/39 45,424,225.00

Page 2/40 49,816,450.00

Bill Nr.2: Main building Page 2/48


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To MALL Summary : 242,147,863.00


EXTERNAL AND INTERNAL WALLS
INFORMATION
Nature and location of the work
The work in this section comprises

(i) The erection of hollow sandcrete block walls, reinforced concrete


lintels. (ii)
The Contractor is however referred to Architect's and Structural
Engineer's drawings for details and scope of the scope of work

E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced in-situ concrete; B.S.5328, designed mix C25, 20 aggregate,


minimum cement content 395 kg/m3; vibrated (Ready mixed Concrete -
RMC)

Lintel

Bill Nr.2: Main building Page 2/49


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


A generally in basement floor (level 01) 5 m3 48,100.00 240,500.00

B generally in basement floor (level 02) 5 m3 48,100.00 240,500.00

C generally in ground floor (Level 03) 32 m3 48,100.00 1,539,200.00

D generally in 1st floor (Level 04) 39 m3 48,100.00 1,875,900.00

E generally in 2nd floor (Level 05) 39 m3 48,100.00 1,875,900.00

F generally in 3rd floor (Level 06) 47 m3 48,100.00 2,260,700.00

G generally in 4th floor (Level 07) 47 m3 48,100.00 2,260,700.00

H generally in 5th floor (Level 08) 36 m3 48,100.00 1,731,600.00

J generally in 6th floor (Level 09) 38 m3 48,100.00 1,827,800.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to produce plain surface:

Lintel: sides and soffit.


regular shaped rectangle

K generally in basement floor (level 01) 68 m2 4,000.00 272,000.00

L generally in basement floor (level 02) 68 m2 4,000.00 272,000.00

M generally in ground floor (Level 03) 411 m2 4,000.00 1,644,000.00

N generally in 1st floor (Level 04) 508 m2 4,000.00 2,032,000.00

P generally in 2nd floor (Level 05) 508 m2 4,000.00 2,032,000.00


To collection : 20,104,800.00

A generally in 3rd floor (Level 06) 615 m2 4,000.00 2,460,000.00

B generally in 4th floor (Level 07) 615 m2 4,000.00 2,460,000.00

C generally in 5th floor (Level 08) 463 m2 4,000.00 1,852,000.00

D generally in 6th floor (Level 09) 498 m2 4,000.00 1,992,000.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel


(TMT-TIGER)

Bill Nr.2: Main building Page 2/50


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Straight and bent

Lintel
generally in basement floor (level 01)
A H16 0.70 t 710,000.00 497,000.00

B H10 in links 0.30 t 710,000.00 213,000.00

generally in basement floor (level 02)


C H16 0.70 t 710,000.00 497,000.00

D H10 in links 0.30 t 710,000.00 213,000.00

generally in ground floor (Level 03)


G H16 3.80 t 710,000.00 2,698,000.00

H H10 in links 1.80 t 710,000.00 1,278,000.00

generally in 1st floor (Level 04)


J H16 4.65 t 710,000.00 3,301,500.00

K H10 in links 2.19 t 710,000.00 1,554,900.00

generally in 2nd floor (Level 05)


L H16 4.65 t 710,000.00 3,301,500.00

M H10 in links 2.19 t 710,000.00 1,554,900.00

generally in 3rd floor (Level 06)


N H16 5.63 t 710,000.00 3,997,300.00

P H10 in links 2.65 t 710,000.00 1,881,500.00

To collection : 29,751,600.00

generally in 4th floor (Level 07)


A H16 5.63 t 710,000.00 3,997,300.00

B H10 in links 2.65 t 710,000.00 1,881,500.00

generally in 5th floor (Level 08)


C H16 4.24 t 710,000.00 3,010,400.00

D H10 in links 2.00 t 710,000.00 1,420,000.00

generally in 6th floor (Level 09)


E H16 4.60 t 710,000.00 3,266,000.00

Bill Nr.2: Main building Page 2/51


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

F H10 in links 2.15 t 710,000.00 1,526,500.00

MASONRY
F10: BLOCK WALLING
Stone dust hollow blockwork, bedded and jointed in cement and sand
mortar
230mm Walls
230mm thick; stretcher bond; regular
G generally in basement floor (level 01) 577 m2 5,000.00 2,885,000.00

H generally in basement floor (level 02) 577 m2 5,000.00 2,885,000.00

J generally in ground floor (Level 03) 2,221 m2 5,000.00 11,105,000.00

K generally in 1st floor (Level 04) 2,864 m2 5,000.00 14,320,000.00

L generally in 2nd floor (Level 05) 2,864 m2 5,000.00 14,320,000.00

M generally in 3rd floor (Level 06) 2,706 m2 5,000.00 13,530,000.00

N generally in 4th floor (Level 07) 2,709 m2 5,000.00 13,545,000.00

P generally in 5th floor (Level 08) 2,122 m2 5,000.00 10,610,000.00

Q generally in 6th floor (Level 09) 1,867 m2 5,000.00 9,335,000.00

Gable ends
R 230mm thick; stretcher bond; regular in gable 263 m2 5,000.00 1,315,000.00

150mm wall
150mm thick; stretcher bond; regular
S generally in basement floor (level 01) 601 m2 4,250.00 2,554,250.00

T generally in basement floor (level 02) 624 m2 4,250.00 2,652,000.00

To collection : 114,157,950.00

A generally in ground floor (Level 03) 1,779 m2 4,250.00 7,560,750.00

B generally in 1st floor (Level 04) 2,124 m2 4,250.00 9,027,000.00

C generally in 2nd floor (Level 05) 2,124 m2 4,250.00 9,027,000.00

D generally in 3rd floor (Level 06) 2,827 m2 4,250.00 12,014,750.00

E generally in 4th floor (Level 07) 2,827 m2 4,250.00 12,014,750.00

Bill Nr.2: Main building Page 2/52


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


F generally in 5th floor (Level 08) 2,130 m2 4,250.00 9,052,500.00

G generally in 6th floor (Level 09) 2,127 m2 4,250.00 9,039,750.00

Expansion Joint
H Expansion joint 20mm thick ploystrene naked panel 2,046 m2 761.00 1,557,006.00
To collection : 69,293,506.00
Collection

EXTERNAL AND INTERNAL WALLS

Page 2/42 20,104,800.00

Page 2/43 29,751,600.00

Page 2/44 114,157,950.00

Page 2/45 69,293,506.00

To MALL Summary : 233,307,856.00


L WINDOWS, CURTAIN WALLS AND DOORS
INFORMATION
Nature and location of the work
The work in this section comprises

(i) Timber flush door and steel frames, anodised aluminium doors and
windows.
(ii) The contractor is however referred to the Architectural doors and
windows schedule for details and scope of work.
L10: WINDOWS

Bill Nr.2: Main building Page 2/53


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


L11 ALUMINIUM WINDOWS AND DOORS/CURTAIN WALL

SUPPLY AND FIX the following aluminium or approved equal best quality
purpose made. EBM system on sliding window . EBM curtain wall with
6mm/10mm clear glass glazed . including cutting and pinning lugs to
blockwork or concrete and pointing in mastic.

ALUMINIUM WINDOW 6mm thick


Level 01
A Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00

Level 02
B Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00

Level 03
C Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00

D Ditto size 450mm x 600mm high 51 nr 70,000.00 3,570,000.00

Level 04
E Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00

F Ditto size 450mm x 600mm high 59 nr 70,000.00 4,130,000.00

Level 05
G Aluminium sliding window 900mm x 1500mm high 12 nr 164,062.00 1,968,744.00

H Ditto size 450mm x 600mm high 59 nr 70,000.00 4,130,000.00

Level 06
J Aluminium sliding window 900mm x 1500mm high 27 nr 164,062.00 4,429,674.00

K Ditto size 600mm x 600mm high 49 nr 70,000.00 3,430,000.00

Level 07
L Aluminium sliding window 900mm x 1500mm high 27 nr 164,062.00 4,429,674.00

M Size 2700mm x 1500mm high 44 nr 492,184.35 21,656,111.40

N Size 1500mm x 1500mm high 12 nr 273,435.75 3,281,229.00

To collection : 58,900,408.40

A Size 1800mm x 1500mm high 10 nr 328,122.90 3,281,229.00

B Size 2400mm x 1500mm high 10 nr 437,497.20 4,374,972.00

C Ditto size 600mm x 600mm high 49 nr 70,000.00 3,430,000.00

Bill Nr.2: Main building Page 2/54


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

Level 08
D Aluminium sliding window 900mm x 1500mm high 27 nr 164,062.00 4,429,674.00

E Size 2700mm x 1500mm high 33 nr 492,184.35 16,242,083.55

F Size 1500mm x 1500mm high 8 nr 273,435.75 2,187,486.00

G Size 1800mm x 1500mm high 2 nr 328,122.90 656,245.80

H Size 2400mm x 1500mm high 2 nr 437,497.20 874,994.40

J Ditto size 600mm x 600mm high 37 nr 70,000.00 2,590,000.00

Level 09
K Aluminium sliding window 900mm x 1500mm high 19 nr 164,062.00 3,117,178.00

L Size 2700mm x 1500mm high 28 nr 492,184.35 13,781,161.80

M Size 1500mm x 1500mm high 7 nr 273,435.75 1,914,050.25

N Size 1800mm x 1500mm high 2 nr 328,122.90 656,245.80

P Size 2400mm x 1500mm high 5 nr 437,497.20 2,187,486.00

Q Ditto size 600mm x 600mm high 36 nr 70,000.00 2,520,000.00

Fixed light (6mm thick glass)


Level 03
R 2700mm x 1500mm high 42 nr 961,875.00 40,398,750.00

Level 04
S 2700mm x 1500mm high 50 nr 961,875.00 48,093,750.00

Level 05
T 2700mm x 1500mm high 50 nr 961,875.00 48,093,750.00

Level 06
U 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00

Level 07
V 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00

To collection : 264,236,556.60

Level 08
A 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00

Bill Nr.2: Main building Page 2/55


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


B Ditto 2000mm x 1500mm high 4 nr 712,500.00 2,850,000.00

Level 09
C 2700mm x 1500mm high 34 nr 961,875.00 32,703,750.00

D Ditto 2000mm x 1500mm high 4 nr 712,500.00 2,850,000.00

Shop front (10mm thick glass)


Level 03
E Front shop glass façade size 2700mm x 1500mm high 38 nr 639,900.00 24,316,200.00

Level 04
F Front shop glass façade size 2700mm x 1500mm high 54 nr 639,900.00 34,554,600.00

Level 05
G Front shop glass façade size 2700mm x 1500mm high 54 nr 639,900.00 34,554,600.00

Aluminium Curtain wall


EBM Profile with 5mm thick glass

Front side Elevation


H Size 2400mm x 12000mm high overrall 2 nr 2,448,000.00 4,896,000.00

J Ditto 7500mm x 12000mm high 2 nr 7,650,000.00 15,300,000.00

K Ditto 2000mm x 21000mm high 2 nr 3,570,000.00 7,140,000.00

L Ditto 6400mm x 21000mm high 1 nr 11,424,000.00 11,424,000.00

Right Side Elevation


M Size 6400mm x 21000mm high 5 nr 11,424,000.00 57,120,000.00

Back Elevation
N Size 6400mm x 16000mm high 3 nr 8,704,000.00 26,112,000.00

Left side elevation


P Size 6400mm x 21000mm high 5 nr 11,424,000.00 57,120,000.00

Subframe(window only)
Q 40mm x 20mm aluminium subframe 6,478 m 1,600.00 10,364,800.00

R Ditto on curtain wall 964 m 1,600.00 1,542,400.00

To collection : 355,552,100.00

Burglar Proofing

Bill Nr.2: Main building Page 2/56


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Burglar proofing comprising of hollow section steel pipes
Composite steel burglar bar fixed screen panel units fixed to
structural window opening; vertical members comprising 25x25mm
hollow section pipes fixed per design and fixed to 38 x 38mm
comprising hollow section framing with and including priming with
red oxide paint and finished in appropriate gloss paint.

Level 01
A Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00

Level 02
B Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00

Level 03
C Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00

D Ditto size 450mm x 600mm high 51 nr 2,500.00 127,500.00

Level 04
E Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00

F Ditto size 450mm x 600mm high 59 nr 2,500.00 147,500.00

Level 05
G Size 900mm x 1500mm high 12 nr 11,475.00 137,700.00

H Ditto size 450mm x 600mm high 59 nr 2,500.00 147,500.00

Level 06
J Size 900mm x 1500mm high 27 nr 11,475.00 309,825.00

K Ditto size 600mm x 600mm high 49 nr 3,060.00 149,940.00

Level 07
L Size 900mm x 1500mm high 27 nr 11,475.00 309,825.00

M Size 2700mm x 1500mm high 44 nr 34,425.00 1,514,700.00

N Size 1500mm x 1500mm high 12 nr 19,125.00 229,500.00

A Size 1800mm x 1500mm high 10 nr 22,950.00 229,500.00

B Size 2400mm x 1500mm high 10 nr 30,600.00 306,000.00

C Ditto size 600mm x 600mm high 49 nr 3,060.00 149,940.00

Bill Nr.2: Main building Page 2/57


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


To collection : 4,310,230.00

Level 08
A Size 900mm x 1500mm high 27 nr 11,475.00 309,825.00

B Size 2700mm x 1500mm high 33 nr 34,425.00 1,136,025.00

C Size 1500mm x 1500mm high 8 nr 19,125.00 153,000.00

D Size 1800mm x 1500mm high 2 nr 22,950.00 45,900.00

E Size 2400mm x 1500mm high 2 nr 30,600.00 61,200.00

F Ditto size 600mm x 600mm high 37 nr 3,060.00 113,220.00

Level 09
G Size 900mm x 1500mm high 19 nr 11,475.00 218,025.00

H Size 2700mm x 1500mm high 28 nr 34,425.00 963,900.00

J Size 1500mm x 1500mm high 7 nr 19,125.00 133,875.00

K Size 1800mm x 1500mm high 2 nr 22,950.00 45,900.00

L Size 2400mm x 1500mm high 5 nr 30,600.00 153,000.00

M Ditto size 600mm x 600mm high 36 nr 3,060.00 110,160.00

Fixed light (6mm thick glass)


Level 03
N 2700mm x 1500mm high 42 nr 34,425.00 1,445,850.00

Level 04
P 2700mm x 1500mm high 50 nr 34,425.00 1,721,250.00

Level 05
Q 2700mm x 1500mm high 50 nr 34,425.00 1,721,250.00

Level 06
R 2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00

Level 07
T 2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00

Level 08
2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00

Ditto 2000mm x 1500mm high 4 nr 25,500.00 102,000.00

Bill Nr.2: Main building Page 2/58


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To collection : 11,945,730.00

Level 09
A 2700mm x 1500mm high 34 nr 34,425.00 1,170,450.00

B Ditto 2000mm x 1500mm high 4 nr 25,500.00 102,000.00

Shop front
Level 03
C Size 2700mm x 1500mm high 38 nr 34,425.00 1,308,150.00

Level 04
D Size 2700mm x 1500mm high 54 nr 34,425.00 1,858,950.00

Level 05
E Size 2700mm x 1500mm high 54 nr 34,425.00 1,858,950.00

Burglary Proofing Curtain wall


Front side Elevation
F Size 2400mm x 12000mm high overrall 2 nr 244,800.00 489,600.00

G Ditto 7500mm x 12000mm high 2 nr 765,000.00 1,530,000.00

H Ditto 2000mm x 21000mm high 2 nr 357,000.00 714,000.00

J Ditto 6400mm x 21000mm high 1 nr 1,142,400.00 1,142,400.00

Right Side Elevation


K Size 6400mm x 21000mm high 5 nr 1,142,400.00 5,712,000.00

Back Elevation
L Size 6400mm x 16000mm high 3 nr 870,400.00 2,611,200.00

Left side elevation


M Size 6400mm x 21000mm high 5 nr 1,142,400.00 5,712,000.00

L20 TIMBER DOORS/SHUTTERS/HATCHES


Supply and install
Doors in hardwood; selected for transparent finishings
High quality panel doors

Ready made door complete with lock ,frame & architrave and stopper
Solid core, single leaf; single swing; solid door, factory finish with
hardwood lipping all edges and polished door frames and all sprayed with
approved quality varnish paint

Level 01

Bill Nr.2: Main building Page 2/59


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


N Size 750mm x 2100mm high 20 nr 175,000.00 3,500,000.00

P 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

To collection : 29,109,700.00

Level 02
A Size 750mm x 2100mm high 20 nr 175,000.00 3,500,000.00

B 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

Level 03
C Size 750mm x 2100mm high 66 nr 175,000.00 11,550,000.00

D 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

Level 04
E Size 750mm x 2100mm high 74 nr 175,000.00 12,950,000.00

F 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

Level 05
G Size 750mm x 2100mm high 74 nr 175,000.00 12,950,000.00

H 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

Level 06
J Size 750mm x 2100mm high 48 nr 175,000.00 8,400,000.00

K 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

L 900 X 2100mm high overall 88 nr 175,000.00 15,400,000.00

Level 07
M Size 750mm x 2100mm high 48 nr 175,000.00 8,400,000.00

N 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

P 900 X 2100mm high overall 88 nr 175,000.00 15,400,000.00

Level 08
Q Size 750mm x 2100mm high 48 nr 175,000.00 8,400,000.00

R 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

S 900 X 2100mm high overall 88 nr 175,000.00 15,400,000.00

Level 09

Bill Nr.2: Main building Page 2/60


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


T Size 750mm x 2100mm high 53 nr 175,000.00 9,275,000.00

U 900 X 2100mm high overall with glass panes 300mm x 400mm 8 nr 175,000.00 1,400,000.00

V 900 X 2100mm high overall 57 nr 175,000.00 9,975,000.00

To collection : 142,800,000.00

L21 METAL DOORS/SHUTTERS/HATCHES

Aluminium Swing Door (EBM profile system with 10mm clear glass)
Level 03
A Size 900mm x 2100mm high 34 nr 156,000.00 5,304,000.00

Level 04
B Size 900mm x 2100mm high 50 nr 156,000.00 7,800,000.00

Level 05
C Size 900mm x 2100mm high 50 nr 156,000.00 7,800,000.00

Aluminium sliding door (EBM syytem with 10mm glazed clear glass)

Level 03
D Size 2700mm x 2100mm high 20 nr 239,318.16 4,786,363.20

Level 04
E Size 2700mm x 2100mm high 20 nr 239,318.16 4,786,363.20

Level 05
F Size 2700mm x 2100mm high 20 nr 239,318.16 4,786,363.20

Level 06
G Size 1350mm x 2100mm high 33 nr 119,659.08 3,948,749.64

Level 07
H Size 1350mm x 2100mm high 33 nr 120,000.00 3,960,000.00

Level 08
J Size 1350mm x 2100mm high 29 nr 120,000.00 3,480,000.00

Level 09
K Size 1350mm x 2100mm high 14 nr 120,000.00 1,680,000.00

P BUILDING FABRIC SUNDRIES


P21 IRONMONGERY

Name plates
' TOILET' sign engraved on stainless steel plate size 350 x 100; Ref IRXX;
L finish: SS 523 nr 9,000.00 4,707,000.00

Bill Nr.2: Main building Page 2/61


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


M Room Numbers and other spaces sign engraved on stainless plate 321 nr 9,000.00 2,889,000.00

N Shop Numbers and other spaces sign engraved on stainless plate 134 nr 9,000.00 1,206,000.00

To collection : 57,133,839.24
Collection

WINDOWS AND DOORS

Page 2/46 58,900,408.40

Page 2/47 264,236,556.60

Page 2/48 355,552,100.00

Page 2/49 4,310,230.00

Page 2/50 11,945,730.00

Page 2/51 29,109,700.00

Page 2/52 142,800,000.00

Page 2/53 57,133,839.24

Bill Nr.2: Main building Page 2/62


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To MALL Summary : 923,988,564.24


FITTING AND FIXTURES
FURNITURE/EQUIPMENT
INFORMATION
Nature and location of the work

The work in this section comprises


(i.) joinery and associated works
(ii.) Metal balcony railings and wall grilles
(iii.) The Contractor is however referred to Architect's details and scope
of work

Wardrobe
Fitted wardrobe cabinet comprising 18mm thick laminated door 2mm
thick edging complete with matching screws,glues and necessary
accessories

Level 06
A 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00

B 1600mm Long x 600mm wide x 2500mm high 22 nr 1,120,000.00 24,640,000.00

C 3100mm Long x 600mm wide x 2500mm high 12 nr 2,170,000.00 26,040,000.00

D 2500mm Long x 600mm wide x 2500mm high 10 nr 1,750,000.00 17,500,000.00

Level 07
E 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00

F 1600mm Long x 600mm wide x 2500mm high 22 nr 1,120,000.00 24,640,000.00

G 3100mm Long x 600mm wide x 2500mm high 12 nr 2,170,000.00 26,040,000.00

H 2500mm Long x 600mm wide x 2500mm high 10 nr 1,750,000.00 17,500,000.00

Level 08
J 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00

K 1600mm Long x 600mm wide x 2500mm high 22 nr 1,120,000.00 24,640,000.00

Bill Nr.2: Main building Page 2/63


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

L 3100mm Long x 600mm wide x 2500mm high 3 nr 2,170,000.00 6,510,000.00

M 2500mm Long x 600mm wide x 2500mm high 2 nr 1,750,000.00 3,500,000.00

level 09
N 2400mm Long x 600mm wide x 2500mm high 22 nr 1,680,000.00 36,960,000.00

P 1600mm Long x 600mm wide x 2500mm high 22 nr 1,120,000.00 24,640,000.00

Q 1700mm Long x 600mm wide x 2500mm high 2 nr 1,190,000.00 2,380,000.00

R 2500mm Long x 600mm wide x 2500mm high 2 nr 1,750,000.00 3,500,000.00

To collection : 349,370,000.00

Store shelves
Level 06
A 1600mm Long x 600mm wide x 2500mm high (3 steps) 5 nr 200,000.00 1,000,000.00

Level 07
B 1600mm Long x 600mm wide x 2500mm high (3 steps) 5 nr 200,000.00 1,000,000.00

Level 08
C 1600mm Long x 600mm wide x 2500mm high (3 steps) 1 nr 200,000.00 200,000.00

Level 09
D 1600mm Long x 600mm wide x 2500mm high (3 steps) 1 nr 200,000.00 200,000.00

Kitchen cabinet
Level 06
E L-Shaped 5600mm Long x 600mm wide x 900mm high 5 nr 1,411,200.00 7,056,000.00

Level 07
F L-Shaped 5600mm Long x 600mm wide x 900mm high 5 nr 1,411,200.00 7,056,000.00

Level 08
G L-Shaped 5600mm Long x 600mm wide x 900mm high 1 nr 1,411,200.00 1,411,200.00

Level 09
H L-Shaped 5600mm Long x 600mm wide x 900mm high 1 nr 1,411,200.00 1,411,200.00

Living Room Shelve


Level 06
J 2100mm Long x 600mm wide x 1500mm high 22 nr 630,000.00 13,860,000.00

K 3100mm Long x 600mm wide x 1500mm high 12 nr 930,000.00 11,160,000.00

Level 07

Bill Nr.2: Main building Page 2/64


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


L 2100mm Long x 600mm wide x 1500mm high 22 nr 630,000.00 13,860,000.00

M 3100mm Long x 600mm wide x 1500mm high 8 nr 930,000.00 7,440,000.00

Level 08
N 2100mm Long x 600mm wide x 1500mm high 22 nr 630,000.00 13,860,000.00

P 3100mm Long x 600mm wide x 1500mm high 8 nr 930,000.00 7,440,000.00

Level 09
Q 2100mm Long x 600mm wide x 1500mm high 22 nr 630,000.00 13,860,000.00

To collection : 100,814,400.00
Aluminium duct cover grille
Level 01
A Size 450mm x 3200mm high 4 nr 50,400.00 201,600.00

Level 02
B Size 450mm x 3200mm high 4 nr 50,400.00 201,600.00

Level 03
C Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00

D Size 600mm x 3450mm high 46 nr 72,450.00 3,332,700.00

Level 04
E Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00

F Size 600mm x 3450mm high 58 nr 72,450.00 4,202,100.00

Level 05
G Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00

H Size 600mm x 3450mm high 58 nr 72,450.00 4,202,100.00

Level 06
J Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00

K Size 600mm x 3450mm high 58 nr 72,450.00 4,202,100.00

Level 07
L Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00

M Size 600mm x 3450mm high 58 nr 72,450.00 4,202,100.00

Bill Nr.2: Main building Page 2/65


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Level 08
N Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00

P Size 600mm x 3450mm high 54 nr 72,450.00 3,912,300.00

Level 09
Q Size 450mm x 3450mm high 4 nr 54,337.50 217,350.00

R Size 600mm x 3450mm high 56 nr 72,450.00 4,057,200.00

To collection : 29,833,650.00

Balcony handrailings
Frameless glass railing with 10mm tampered glass fixed with leg spider,
glass connector and all necessary accessories

A Level 03 246 m 75,000.00 18,450,000.00

B Level 04 262 m 75,000.00 19,650,000.00

C Level 05 294 m 75,000.00 22,050,000.00

D Level 06 294 m 75,000.00 22,050,000.00

E Level 07 294 m 75,000.00 22,050,000.00

F Level 08 294 m 75,000.00 22,050,000.00

G Level 09 343 m 75,000.00 25,725,000.00

Alucobond cladding
Aluminium Composite Material consisting of two aluminium
H cover sheets with fireretardant or non combustible mineral filled 9,244 m2 35,000.00 323,540,000.00
core

To collection : 475,565,000.00

COLLECTION

Bill Nr.2: Main building Page 2/66


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

Page/55 349,370,000.00

Page/56 100,814,400.00

Page/57 29,833,650.00

Page/58 475,565,000.00

To MALL Summary : 955,583,050.00


FLOOR FINISHING

SURFACE FINISHES

INFORMATION

Nature and location of the work

The work in this section comprises


(i) Floor finishings with and other associated works
(ii) The Contractor is hereby referred to the various
Architect's location drawings and schedule of finishing in relation to this
section for the nature and content of the work to be executed.

M10: SAND CEMENT/ CONCRETE/ SCREEDS/TOPPINGS

Mortar, cement and sand (1:4)


50mm work to floors on concrete base; one coat; screeded

level 01

A level and to falls only not exceeding 15 degrees from horizontal with anti 4,472 m2 5,000.00 22,360,000.00
dust additives

level 02

B level and to falls only not exceeding 15 degrees from horizontal with anti 4,472 m2 5,000.00 22,360,000.00
dust additives

42mm work to floors on concrete base; one coat; screeded


level 01

Bill Nr.2: Main building Page 2/67


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

C level and to falls only not exceeding 15 degrees from horizontal to 201 m2 3,000.00 603,000.00
received tiles

level 02

D level and to falls only not exceeding 15 degrees from horizontal to 201 m2 3,000.00 603,000.00
received tiles

level 03

E level and to falls only not exceeding 15 degrees from horizontal to 2,294 m2 3,000.00 6,882,000.00
received tiles

level 04

F level and to falls only not exceeding 15 degrees from horizontal to 3,056 m2 3,000.00 9,168,000.00
received tiles

level 05

G level and to falls only not exceeding 15 degrees from horizontal to 3,079 m2 3,000.00 9,237,000.00
received tiles

level 06

H level and to falls only not exceeding 15 degrees from horizontal to 3,050 m2 3,000.00 9,150,000.00
received tiles

To collection : 80,363,000.00

level 07

A level and to falls only not exceeding 15 degrees from horizontal to 3,001 m2 3,000.00 9,003,000.00
received tiles

level 08

B level and to falls only not exceeding 15 degrees from horizontal to 2,997 m2 3,000.00 8,991,000.00
received tiles

level 09

C level and to falls only not exceeding 15 degrees from horizontal to 3,125 m2 3,000.00 9,375,000.00
received tiles

12mm cement backing to skirting on wall

level 01
D height 100mm 402 m 150.00 60,300.00

level 02
E height 100mm 402 m 150.00 60,300.00

Bill Nr.2: Main building Page 2/68


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To collection : 188,215,600.00
M40: TILING
Unglazed vitrified floor tiles; 3 joints systematic layout, bedding in
10mm cement mortar (1:3); including pointing.

450mm x 450mm x 8mm thick to floors on cement and sand base; level
to falls only not exceeding 15 degrees from horizontal

A Ground floor patterned; over 300mm wide 1,642.00 m2 7,750.00 12,725,500.00

B First floor patterned; over 300mm wide 1,653.00 m2 7,750.00 12,810,750.00

C Second floor patterned; over 300mm wide 1,653.00 m2 7,750.00 12,810,750.00

D Third floor patterned; over 300mm wide 1,270.00 m2 7,750.00 9,842,500.00

D Pent floor patterned; over 300mm wide 508.00 m2 7,750.00 3,937,000.00


6,726.00
100mm skirting Tiles
E Ground floor patterned; over 300mm wide 388.00 m 775.00 300,700.00

F First floor patterned; over 300mm wide 401.00 m 775.00 310,775.00

G Second floor patterned; over 300mm wide 401.00 m 775.00 310,775.00

H Third floor patterned; over 300mm wide 1,097.00 m 775.00 850,175.00

Nigeria Granite floor tiles;(Kamazo grey) 3 joints systematic layout,


bedding in 10 cement mortar (1:4); including pointing.

800mm x 400mm x 15mm thick to floors on cement and sand base;


level to falls only not exceeding 15 degrees from horizontal
L Ground floor patterned; over 300mm wide 259.00 m2 15,036.00 3,894,324.00

M First floor patterned; over 300mm wide 508.00 m2 15,036.00 7,638,288.00

N Second floor patterned; over 300mm wide 508.00 m2 15,036.00 7,638,288.00

P Third floor patterned; over 300mm wide 508.00 m2 15,036.00 7,638,288.00

Q Pent floor patterned; over 300mm wide 367.00 m2 15,036.00 5,518,212.00


2,150.00
Entrance Steps

Bill Nr.2: Main building Page 2/69


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


N Tread 300mm wide #REF! m 10,024.00 #REF!

P Risers 150mm wide #REF! m 5,012.00 #REF!

100mm skirting granite


Q Ground floor patterned; over 300mm wide 165.00 m 1,503.60 248,094.00

R First floor patterned; over 300mm wide 171.00 m 1,503.60 257,115.60


To collection : #REF!
A Second floor patterned; over 300mm wide 171.00 m 1,503.60 257,115.60

B Third floor patterned; over 300mm wide 470.00 m 1,503.60 706,692.00

C Pent floor patterned; over 300mm wide 203.00 m 1,503.60 305,230.80

To collection : 1,269,038.40

Collection

Floor Finishing

Page 2/35 188,215,600.00

Page 2/36 #REF!

Page 2/37 1,269,038.40

Bill Nr.2: Main building Page 2/70


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To MALL Summary : #REF!


WALL FINISHING
SURFACE FINISHES
INFORMATION
Nature and location of the work

The work in this section comprises

(i) Walls finishings with and including other associated works but
excluding painting which is measured in a separate element.
(ii) The Contractor is hereby referred to
the various Architect's location drawings in relation to this section for the
nature and content of the work to be executed.

M20: PLASTERED/RENDERED

Mortar, cement and sand (1:4); steel trowelled

12mm work to walls on concrete base or blockwork


Ground floor wall
A Ground floor wall width exceeding 300mm 1,642.00 m2 1,500.00 2,463,000.00

B Ditto lift wall externally 46.00 m2 1,500.00 69,000.00

C width not exceeding 300mm 775.00 m 450.00 348,750.00

D width not exceeding 300mm; isolated columns square 83.00 m2 1,500.00 124,500.00

First and second floor


F First floor wall width exceeding 300mm 2,964.00 m2 1,500.00 4,446,000.00

G Ditto lift wall externally 92.00 m2 1,500.00 138,000.00

H width not exceeding 300mm 1,142.00 m 450.00 513,900.00

J width not exceeding 300mm; isolated columns square 166.00 m2 1,500.00 249,000.00

3rd floor

Bill Nr.2: Main building Page 2/71


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


K 3rd floor wall width exceeding 300mm 4,779.00 m2 1,500.00 7,168,500.00

L Ditto lift wall externally 46.00 m2 1,500.00 69,000.00

M width not exceeding 300mm 775.00 m 450.00 348,750.00

To collection : 15,938,400.00
Pent floor
A Pent floor wall width exceeding 300mm 679.00 m2 1,500.00 1,018,500.00

B Ditto lift wall externally 46.00 m2 1,500.00 69,000.00

C width not exceeding 300mm 192.00 m 450.00 86,400.00

D width not exceeding 300mm; isolated columns 33.00 m2 1,500.00 49,500.00

M40: CERAMIC TILING


Glazed Ceramic tiles, B.S.6431, glazed; 2 joints, symmetrical layout;
fixing with adhesive or cement mortar, grouting with matching cement
grout

250mm x 450mm x 6mm thick to walls on sand and cement base


Ground floor
E patterned, width exceeding 300mm 249.00 m2 7,750.00 1,929,750.00

1st floor
F patterned, width exceeding 300mm 176.00 m2 7,750.00 1,364,000.00

2nd floor
G patterned, width exceeding 300mm 176.00 m2 7,750.00 1,364,000.00

3rd floor
H Patterned, width exceeding 300mm 1,200.00 m2 7,750.00 9,300,000.00

EXTERNAL WORK
12mm work to walls on concrete base or blockwork
Ground Floor
M width exceeding 300mm 741.00 m2 1,500.00 1,111,500.00

N width not exceeding 300mm 245.00 m 450.00 110,250.00


1st floor & 2nd floor
P width exceeding 300mm 1,167.00 m2 1,500.00 1,750,500.00

Bill Nr.2: Main building Page 2/72


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


Q width not exceeding 300mm 1,050.00 m 450.00 472,500.00
3rd floor
R width exceeding 300mm 654.00 m2 1,500.00 981,000.00

S width not exceeding 300mm 613.00 m 450.00 275,850.00

Pent floor
T width exceeding 300mm 589.00 m2 1,500.00 883,500.00

U width not exceeding 300mm 16.00 m 450.00 7,200.00

To collection : 20,773,450.00
Lift wall entrance façade
A 15mm thick granite wall fixed to entrance of lift wall façade 230.00 m2 15,036.00 3,458,280.00

B Aluco bond 397.00 m2 31,250.00 12,406,250.00

C laser cut metal façade 94.00 m2 36,111.00 3,394,434.00

D 50mm x 2mm thick hollow steel pipe decoration on façade painted with m 1,700.00 132,600.00
gloss paint 78.00

To collection : 19,391,564.00

Collection

WALL FINISHING

Page 2/50 15,938,400.00

Page 2/51 20,773,450.00

Page 2/52 19,391,564.00

Bill Nr.2: Main building Page 2/73


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To MALL Summary : 56,103,414.00


CEILING FINISHING

INFORMATION

Nature and location of the work

The work in this section comprises

(i) Ceiling finishings with and including other associated works but
excluding painting which is measured in a separate Element
(ii) The Contractor is hereby referred to the various Architect's location
drawings in relation to this section for the nature and content of the work
to be executed.
SURFACE FINISHES

K13 RIGID SHEET LINNING/COVERING


High quality plaster of paris; 12.5mm thick secrete fixing with screws or
other approved method; filling fixing holes and joints with plaster;
including all necessary screeding

Plaster of paris ceiling with cornices


A over 300mm wide; internal; as architectural details 3rd floor 1,579.00 m2 5,250.00 8,289,750.00

B over 300mm wide; internal; as architectural details Pent floor 877.00 m2 5,250.00 4,604,250.00

Owa accoustic suspended ceilings

Suspended linings; Owa accoustic ceiling type size 600mm x 600mm x


15mm thick clip-in/Aluminum Micro perforated in concealed grid or
other approved in a normal grid.
C over 300mm wide; internal; as architectural details ground floor 1,861.00 m2 8,562.00 15,933,882.00

D over 300mm wide; internal; as architectural details 1st floor 2,275.00 m2 8,562.00 19,478,550.00

E over 300mm wide; internal; as architectural details 2nd floor 2,275.00 m2 8,562.00 19,478,550.00

Mortar, cement and sand (1:4); steel trowelled

Bill Nr.2: Main building Page 2/74


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


12mm work to walls on concrete base or blockwork

F width exceeding 300mm in ground floor 1,861.00 m2 1,500.00 2,791,500.00

G width exceeding 300mm in 1st floor 2,275.00 m2 1,500.00 3,412,500.00

H width exceeding 300mm in 2nd floor 2,275.00 m2 1,500.00 3,412,500.00

J width exceeding 300mm in 3rd floor 1,579.00 m2 1,500.00 2,368,500.00

To MALL Summary : 79,769,982.00


PAINTING AND DECORATONS
SURFACE FINISHES
INFORMATION
Nature and location of the work
The work in this section comprises
(i.) Painting and decorations on new works.
(ii.) The Contractor is however referred to Architect's details and location
drawings for the details and scope of the works to be executed in this
section.

M60: PAINTING/CLEAR FINISHING


Wall screeding (I-nox)
Cement rendered general surfaces
Ground floor
A Ground; girth exceeding 300mm; wall internally 1,393.00 m2 625.00 870,625.00

B width not exceeding 300mm 775.00 m 187.50 145,312.50

C width not exceeding 300mm; isolated columns square 83.00 m2 625.00 51,875.00

1st and 2nd floor


F First & second floor wall width exceeding 300mm 2,612.00 m2 625.00 1,632,500.00

H width not exceeding 300mm 1,142.00 m 187.50 214,125.00

J width not exceeding 300mm; isolated columns 166.00 m2 625.00 103,750.00

3rd floor
K Third floor wall width exceeding 300mm 3,579.00 m2 625.00 2,236,875.00

M width not exceeding 300mm 775.00 m 187.50 145,312.50

Pent floor

Bill Nr.2: Main building Page 2/75


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


P Pent floor wall width exceeding 300mm 679.00 m2 625.00 424,375.00

R width not exceeding 300mm 16.00 m 187.50 3,000.00

S width not exceeding 300mm; isolated columns 33.00 m2 625.00 20,625.00

Ceiling screeding
Wall screeding (I-nox)
T over 300mm wide; internal; as architectural details 3rd floor 1,579.00 m2 625.00 986,875.00

U over 300mm wide; internal; as architectural details Pent floor 877.00 m2 625.00 548,125.00

To collection : 7,383,375.00

Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.

Cement rendered general surfaces


A Ground; girth exceeding 300mm; wall internally 1,393.00 m2 1,312.50 1,828,312.50

B width not exceeding 300mm 775.00 m 393.75 305,156.25

C width not exceeding 300mm; isolated columns square 83.00 m2 1,312.50 108,937.50

First and second floor


D Ground floor wall width exceeding 300mm 2,612.00 m2 1,312.50 3,428,250.00

E width not exceeding 300mm 1,142.00 m 393.75 449,662.50

J width not exceeding 300mm; isolated columns 166.00 m2 1,312.50 217,875.00

3rd floor
K 1st floor-5th floor wall width exceeding 300mm 3,579.00 m2 1,312.50 4,697,437.50

M width not exceeding 300mm 775.00 m 393.75 305,156.25

Pent floor
P Pent floor wall width exceeding 300mm 679.00 m2 1,312.50 891,187.50

R width not exceeding 300mm 16.00 m 393.75 6,300.00

S width not exceeding 300mm; isolated columns round 33.00 m2 1,312.50 43,312.50

Ceilings painting

Bill Nr.2: Main building Page 2/76


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


T over 300mm wide; internal; as architectural details 3rd floor 1,579.00 m2 1,312.50 2,072,437.50

U over 300mm wide; internal; as architectural details Pent floor 877.00 m2 1,312.50 1,151,062.50

To collection : 15,505,087.50
Externally
Wall screeding ( x-nox exterior)
Ground Floor
A width exceeding 300mm 741.00 m2 1,000.00 741,000.00

B width not exceeding 300mm 245.00 m 300.00 73,500.00

1st & 2nd floor


C width exceeding 300mm 1,167.00 m2 1,000.00 1,167,000.00

D width not exceeding 300mm 1,050.00 m 300.00 315,000.00

3rd floor
E width exceeding 300mm 654.00 m2 1,000.00 654,000.00

F width not exceeding 300mm 613.00 m 300.00 183,900.00

Pent floor
G width exceeding 300mm 589.00 m2 1,000.00 589,000.00

H width not exceeding 300mm 16.00 m 300.00 4,800.00

J Gable ends 56.00 m2 1,000.00 56,000.00

Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.

Ground Floor

Bill Nr.2: Main building Page 2/77


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


G width exceeding 300mm 741.00 m2 1,312.50 972,562.50

H width not exceeding 300mm 245.00 m 393.75 96,468.75

1st floor & 2nd floor


J width exceeding 300mm 1,167.00 m2 1,312.50 1,531,687.50

K width not exceeding 300mm 1,050.00 m 393.75 413,437.50

3rd floor
L width exceeding 300mm 654.00 m2 1,312.50 858,375.00

M width not exceeding 300mm 613.00 m 393.75 241,368.75

Pent floor
N width exceeding 300mm 589.00 m2 1,312.50 773,062.50

P width not exceeding 300mm 16.00 m 393.75 6,300.00

Q Parapet wall 1,448.00 m2 1,312.50 1,900,500.00

R Gable ends 56.00 m2 1,312.50 73,500.00


To collection : 10,651,462.50

Collection

PAINTING AND DECORATION

Page 2/42 7,383,375.00

Page 2/43 15,505,087.50

Page 2/44 10,651,462.50

Bill Nr.2: Main building Page 2/78


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount

To MALL Summary : 33,539,925.00

MOTEL BUILDING COLLECTION AMOUNT

DEMOLITION #REF!

SUBSTRUCTURE 1,320,814,211.00

FRAMES AND UPPER FLOORS 1,604,226,600.00

STAIRCASES 58,372,404.30

ROOF CONSTRUCTION AND ROOF COVERING 242,147,863.00

EXTERNAL AND INTERNAL WALLS 233,307,856.00

WINDOWS, CURTAIN WALL AND DOORS 923,988,564.24

Bill Nr.2: Main building Page 2/79


PROPOSED MIXED DEVELOPMENT

No Item Description Qty Unit Rate Amount


FITTINGS AND FIXTURES 955,583,050.00

FLOOR FINISHING #REF!

WALL FINISHING 56,103,414.00

CEILING FINISHING 79,769,982.00

PAINTING AND DECORATONS 33,539,925.00

To GENERAL SUMMARY #REF!

Bill Nr.2: Main building Page 2/80


Page №:(81)

Type your name of company here.


MAITAM
Name of Project A JAVA

Name of Structure BASEMENT SLAB 1

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 0 0 136879 0 0 0 0 136879

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(82)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

BASEMENT SLAB 1 T12 1 8 8№ 2600 18.470

Bottom Rfct- X-Direction T12 1 4 4№ 4450 15.806

T12 1 4 4№ 5250 18.648

T12 1 4 4№ 10350 36.763

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 10600 37.651

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 10350 36.763

T12 1 4 4№ 5450 19.358

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 10600 37.651

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 5500 19.536

T12 1 4 4№ 4450 15.806

T12 1 33 33 № 6400 187.546

T12 1 24 24 № 6400 136.397

T12 1 21 21 № 5250 97.902

T12 1 21 21 № 5500 102.564

T12 1 3 3№ 3850 10.256

T12 1 23 23 № 6200 126.629

T12 1 30 30 № 6900 183.816

T12 1 156 156 № 10350 1433.765

T12 1 156 156 № 10600 1468.397

T12 1 156 156 № 10350 1433.765

T12 1 156 156 № 10350 1433.765

T12 1 156 156 № 10600 1468.397

T12 1 30 30 № 7250 193.140

T12 1 3 3№ 3750 9.990

T12 1 23 23 № 6200 126.629

T12 1 17 17 № 5500 83.028

T12 1 295 295 № 10350 2711.286

T12 1 18 18 № 10600 169.430

T12 1 18 18 № 5450 87.113

T12 1 24 24 № 11300 240.826

T12 1 10 10 № 10450 92.796

T12 1 156 156 № 10350 1433.765

T12 1 105 105 № 11300 1053.612

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(83)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 58 58 № 11300 581.995

T12 1 10 10 № 10450 92.796

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 9700 34.454

T12 1 58 58 № 11300 581.995

T12 1 101 101 № 10350 928.271

T12 1 101 101 № 10600 950.693

T12 1 101 101 № 10350 928.271

T12 1 101 101 № 10350 928.271

T12 1 13 13 № 10600 122.366

T12 1 10 10 № 7200 63.936

T12 1 10 10 № 2950 26.196

T12 1 10 10 № 10450 92.796

T12 1 58 58 № 10600 545.942

T12 1 10 10 № 10450 92.796

T12 1 58 58 № 11300 581.995

T12 1 10 10 № 7200 63.936

T12 1 13 13 № 10600 122.366

T12 1 10 10 № 2950 26.196

T12 1 58 58 № 11300 581.995

T12 1 10 10 № 10450 92.796

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 9700 34.454

T12 1 10 10 № 10450 92.796

T12 1 30 30 № 11300 301.032

T12 1 145 145 № 10350 1332.666

T12 1 156 156 № 10600 1468.397

T12 1 156 156 № 10350 1433.765

T12 1 156 156 № 10350 1433.765

T12 1 107 107 № 10600 1007.170

T12 1 106 106 № 11300 1063.646

T12 1 17 17 № 5500 83.028

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(84)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 23 23 № 6200 126.629

T12 1 30 30 № 6900 183.816

T12 1 3 3№ 3850 10.256

T12 1 24 24 № 6400 136.397

T12 1 21 21 № 5250 97.902

T12 1 17 17 № 5500 83.028

T12 1 28 28 № 7200 179.021

T12 1 23 23 № 6200 126.629

T12 1 3 3№ 3750 9.990

T12 1 22 22 № 5500 107.448

T12 1 30 30 № 6400 170.496

T12 1 4 4№ 4550 16.162

T12 1 2 2№ 5500 9.768

T12 1 32 32 № 10600 301.210

T12 1 36 36 № 5500 175.824

T12 1 13 13 № 12000 138.528

T12 1 4 4№ 4400 15.629

T12 1 4 4№ 4700 16.694

T12 1 7 7№ 8500 52.836

T12 1 4 4№ 8750 31.080

T12 1 11 11 № 7000 68.376

T12 1 4 4№ 8750 31.080

T12 1 11 11 № 10400 101.587

T12 1 13 13 № 12000 138.528

T12 1 4 4№ 8750 31.080

T12 1 29 29 № 10350 266.533

Top Rfct- X-Direction T12 1 8 8№ 2600 18.470

T12 1 4 4№ 5250 18.648

T12 1 4 4№ 4450 15.806

T12 1 4 4№ 5450 19.358

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 10400 36.941

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 10700 38.006

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 5400 19.181

T12 1 4 4№ 5450 19.358

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(85)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 10700 38.006

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 10300 36.586

T12 1 4 4№ 4450 15.806

T12 1 33 33 № 6400 187.546

T12 1 24 24 № 6400 136.397

T12 1 21 21 № 5250 97.902

T12 1 21 21 № 10300 192.074

T12 1 3 3№ 3850 10.256

T12 1 23 23 № 6200 126.629

T12 1 30 30 № 6900 183.816

T12 1 156 156 № 5450 754.978

T12 1 156 156 № 10400 1440.691

T12 1 156 156 № 10700 1482.250

T12 1 156 156 № 5400 748.051

T12 1 156 156 № 5450 754.978

T12 1 261 261 № 10700 2479.918

T12 1 30 30 № 12000 319.680

T12 1 3 3№ 3750 9.990

T12 1 23 23 № 6400 130.714

T12 1 17 17 № 10400 156.998

T12 1 295 295 № 5400 1414.584

T12 1 156 156 № 5450 754.978

T12 1 123 123 № 10400 1135.930

T12 1 18 18 № 10500 167.832

T12 1 24 24 № 6300 134.266

T12 1 10 10 № 5450 48.396

T12 1 262 262 № 10500 2442.888

T12 1 156 156 № 5450 754.978

T12 1 105 105 № 6300 587.412

T12 1 58 58 № 6300 324.475

T12 1 10 10 № 5450 48.396

T12 1 20 20 № 8750 155.400

T12 1 58 58 № 6300 324.475

T12 1 101 101 № 5450 488.800

T12 1 101 101 № 10400 932.755

T12 1 101 101 № 10700 959.662

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(86)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 101 101 № 5400 484.315

T12 1 101 101 № 5450 488.800

T12 1 13 13 № 10700 123.521

T12 1 10 10 № 12000 106.560

T12 1 10 10 № 7950 70.596

T12 1 10 10 № 5450 48.396

T12 1 58 58 № 6300 324.475

T12 1 101 101 № 5450 488.800

T12 1 101 101 № 10400 932.755

T12 1 101 101 № 10700 959.662

T12 1 101 101 № 5400 484.315

T12 1 101 101 № 5450 488.800

T12 1 58 58 № 10700 551.093

T12 1 10 10 № 5450 48.396

T12 1 10 10 № 12000 106.560

T12 1 10 10 № 7950 70.596

T12 1 10 10 № 5450 48.396

T12 1 58 58 № 6300 324.475

T12 1 16 16 № 8750 124.320

T12 1 4 4№ 4850 17.227

T12 1 10 10 № 5450 48.396

T12 1 30 30 № 6300 167.832

T12 1 145 145 № 5450 701.742

T12 1 145 145 № 10400 1339.104

T12 1 156 156 № 10700 1482.250

T12 1 156 156 № 5400 748.051

T12 1 156 156 № 5450 754.978

T12 1 107 107 № 10700 1016.671

T12 1 106 106 № 10400 978.931

T12 1 106 106 № 6300 593.006

T12 1 17 17 № 10400 156.998

T12 1 23 23 № 6200 126.629

T12 1 30 30 № 6900 183.816

T12 1 3 3№ 3850 10.256

T12 1 24 24 № 6400 136.397

T12 1 21 21 № 5250 97.902

T12 1 17 17 № 10300 155.489

T12 1 28 28 № 12000 298.368

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(87)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 23 23 № 6400 130.714

T12 1 3 3№ 3750 9.990

T12 1 22 22 № 10400 203.174

T12 1 4 4№ 4400 15.629

T12 1 4 4№ 9600 34.099

T12 1 7 7№ 12000 74.592

T12 1 12 12 № 8750 93.240

T12 1 2 2№ 10400 18.470

T12 1 4 4№ 4550 16.162

T12 1 2 2№ 10400 18.470

T12 1 11 11 № 5400 52.747

T12 1 11 11 № 12000 117.216

T12 1 13 13 № 12000 138.528

T12 1 29 29 № 5450 140.348

T12 1 32 32 № 10700 304.051

T12 1 36 36 № 10500 335.664

T12 1 13 13 № 12000 138.528

Bottom Rfct Layout-Y-


T12 1 60 60 № 650 34.632
directn

T12 1 14 14 № 4850 60.295

T12 1 12 12 № 10450 111.355

T12 1 13 13 № 11600 133.910

T12 1 58 58 № 11600 597.446

T12 1 10 10 № 10450 92.796

T12 1 58 58 № 11600 597.446

T12 1 10 10 № 10450 92.796

T12 1 232 232 № 11600 2389.786

T12 1 40 40 № 10450 371.184

T12 1 29 29 № 11600 298.723

T12 1 12 12 № 11600 123.610

T12 1 12 12 № 11700 124.675

T12 1 17 17 № 4850 73.216

T12 1 17 17 № 6500 98.124

T12 1 14 14 № 6450 80.186

T12 1 12 12 № 7400 78.854

T12 1 4 4№ 3550 12.610

T12 1 33 33 № 9500 278.388

T12 1 507 507 № 9600 4322.074

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(88)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 4 4№ 8750 31.080

T12 1 129 129 № 5600 641.491

T12 1 9 9№ 4700 37.562

T12 1 58 58 № 5600 288.422

T12 1 9 9№ 4700 37.562

T12 1 58 58 № 5600 288.422

T12 1 9 9№ 4700 37.562

T12 1 58 58 № 5600 288.422

T12 1 9 9№ 4700 37.562

T12 1 58 58 № 5600 288.422

T12 1 9 9№ 4700 37.562

T12 1 41 41 № 5600 203.885

T12 1 5 5№ 7200 31.968

T12 1 84 84 № 5600 417.715

T12 1 4 4№ 8750 31.080

T12 1 129 129 № 8100 927.871

T12 1 10 10 № 7950 70.596

T12 1 58 58 № 8100 417.182

T12 1 40 40 № 7950 282.384

T12 1 174 174 № 8100 1251.547

T12 1 41 41 № 8100 294.905

T12 1 10 10 № 8750 77.700

T12 1 84 84 № 8100 604.195

T12 1 4 4№ 7200 25.574

T12 1 4 4№ 8750 31.080

T12 1 129 129 № 12000 1374.624

T12 1 10 10 № 7950 70.596

T12 1 10 10 № 3650 32.412

T12 1 232 232 № 12000 2472.192

T12 1 40 40 № 7950 282.384

T12 1 40 40 № 3650 129.648

T12 1 41 41 № 12000 436.896

T12 1 5 5№ 6100 27.084

T12 1 84 84 № 12000 895.104

T12 1 4 4№ 6100 21.667

T12 1 4 4№ 4550 16.162

T12 1 33 33 № 6500 190.476

T12 1 41 41 № 6700 243.934

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(89)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 15 15 № 9100 121.212

T12 1 414 414 № 10700 3933.662

T12 1 39 39 № 10150 351.515

T12 1 14 14 № 6400 79.565

T12 1 10 10 № 10500 93.240

T12 1 17 17 № 11600 175.114

T12 1 14 14 № 3800 47.242

T12 1 12 12 № 3400 36.230

T12 1 30 30 № 6500 173.160

T12 1 101 101 № 12000 1076.256

T12 1 205 205 № 10600 1929.624

T12 1 12 12 № 7400 78.854

T12 1 15 15 № 3000 39.960

T12 1 24 24 № 10600 225.907

T12 1 15 15 № 6400 85.248

T12 1 15 15 № 11850 157.842

T12 1 205 205 № 6350 1155.954

T12 1 25 25 № 6350 140.970

T12 1 25 25 № 8100 179.820

TOP RFCT LAYOUT- 1ST


T12 1 60 60 № 650 34.632
BASEMENT

T12 1 14 14 № 4850 60.295

T12 1 12 12 № 5500 58.608

T12 1 13 13 № 6600 76.190

T12 1 28 28 № 6600 164.102

T12 1 60 60 № 5450 290.376

T12 1 290 290 № 6600 1699.632

T12 1 29 29 № 6600 169.963

T12 1 12 12 № 6600 70.330

T12 1 12 12 № 11700 124.675

T12 1 17 17 № 4850 73.216

T12 1 17 17 № 6500 98.124

T12 1 4 4№ 3550 12.610

T12 1 33 33 № 12000 351.648

T12 1 14 14 № 10800 134.266

T12 1 24 24 № 10000 213.120

T12 1 15 15 № 7400 98.568

T12 1 13 13 № 11800 136.219

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(90)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 400 400 № 10000 3552.000

T12 1 13 13 № 11800 136.219

T12 1 15 15 № 7400 98.568

T12 1 10 10 № 10000 88.800

T12 1 96 96 № 7700 656.410

T12 1 232 232 № 7700 1586.323

T12 1 144 144 № 7700 984.614

T12 1 4 4№ 8750 31.080

T12 1 129 129 № 6850 784.681

T12 1 45 45 № 9300 371.628

T12 1 232 232 № 6850 1411.210

T12 1 41 41 № 6850 249.395

T12 1 5 5№ 4700 20.868

T12 1 84 84 № 6850 510.955

T12 1 4 4№ 4700 16.694

T12 1 4 4№ 8750 31.080

T12 1 129 129 № 8000 916.416

T12 1 10 10 № 11600 103.008

T12 1 58 58 № 8000 412.032

T12 1 40 40 № 11600 412.032

T12 1 174 174 № 8000 1236.096

T12 1 41 41 № 8000 291.264

T12 1 5 5№ 8750 38.850

T12 1 84 84 № 8000 596.736

T12 1 4 4№ 8750 31.080

T12 1 4 4№ 8750 31.080

T12 1 129 129 № 12000 1374.624

T12 1 50 50 № 7550 335.220

T12 1 232 232 № 12000 2472.192

T12 1 41 41 № 12000 436.896

T12 1 5 5№ 9750 43.290

T12 1 84 84 № 12000 895.104

T12 1 4 4№ 9750 34.632

T12 1 4 4№ 4550 16.162

T12 1 33 33 № 2950 86.447

T12 1 15 15 № 5450 72.594

T12 1 12 12 № 9850 104.962

T12 1 15 15 № 9450 125.874

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(91)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 39 39 № 7000 242.424

T12 1 14 14 № 8900 110.645

T12 1 14 14 № 3800 47.242

T12 1 24 24 № 12000 255.744

T12 1 10 10 № 1550 13.764

T12 1 17 17 № 2650 40.004

T12 1 30 30 № 2600 69.264

T12 1 345 345 № 12000 3676.320

T12 1 12 12 № 2450 26.107

T12 1 41 41 № 12000 436.896

T12 1 15 15 № 1550 20.646

T12 1 24 24 № 9000 191.808

T12 1 15 15 № 11850 157.842

T12 1 304 304 № 12000 3239.424

T12 1 25 25 № 6350 140.970

T12 1 25 25 № 4750 105.450

136879.422

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(92)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(93)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(94)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(95)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(96)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(97)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(98)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(99)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(100)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(101)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(102)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(103)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(104)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(105)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(106)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(107)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(108)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(109)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(110)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(111)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(112)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(113)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(114)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(115)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(116)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(117)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(118)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(119)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(120)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(121)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(122)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(123)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(124)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(125)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(126)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(127)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(128)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(129)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(130)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(131)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(132)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(133)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(134)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(135)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(136)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(137)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(138)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(139)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(140)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(141)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(142)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(143)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(144)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(145)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(146)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(147)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(148)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(149)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(150)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(151)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(152)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(153)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(154)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(155)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(156)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(157)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(158)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(159)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(160)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(161)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(162)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(163)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(164)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(165)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(166)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(167)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BNL
Project : MARAYUS PLAZA
CONCRETE COLUMN BASE MEASUREMENT
Project Manager :
Prepared by
Date 04-Aug-20 FIRST BASEMENT LEVEL CONCRETE AND FORMWORK

QTY L W H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
1st Basement floor Beams 6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222
BM 60 X 50 H04-17 1.00 40 40 0.60 0.50 12.00 64.00
BM 60 X 50 H17-21 1.00 11 11 0.60 0.50 3.30 17.60
BM 60X50 H1-22 1.00 62 62 0.60 0.50 18.60 99.20
BM60 X 50 H17-20 1.00 7 7 0.60 0.50 2.10 11.20
BM 60 X 50 H01-5 1.00 15 15 0.60 0.50 4.50 24.00
BM 60 X50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H1-4 1.00 11 11 0.60 0.50 3.30 17.60
BM 60 X 50 H07-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H7-15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50H7-H15 1.00 21 21 0.60 0.50 6.30 33.60
BM 60 X 50 H17-23 1.00 13 13 0.60 0.50 3.90 20.80
BM 60 X 50 H19-23 1.00 10 10 0.60 0.50 3.00 16.00
BM 60 X 50 H19-25 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60 X 50 H19-23 1.00 12 12 0.60 0.50 3.60 19.20
BM 60X50 V04-17 1.00 61 61 0.60 0.50 18.30 97.60
BM60X50V01-18 1.00 86 86 0.60 0.50 25.80 137.60
BM 60X50V01-4 1.00 16 16 0.60 0.50 4.80 25.60
BM 60X50V01-17 1.00 82 82 0.60 0.50 24.60 131.20
BM60X50 V01-17 1.00 82 82 0.60 0.50 24.60 131.20
BM 60X50 V01-17 1.00 82 82 0.60 0.50 24.60 131.20
BM 60 X50 V01-4 1.00 16 16 0.60 0.50 4.80 25.60
BM 60X50 V01-4 1.00 16 16 0.60 0.50 4.80 25.60
BM60X50 V04-17 1.00 61 61 0.60 0.50 18.30 97.60
BM60X50 V4-5 1.00 6 6 0.60 0.50 1.80 9.60
BM60 X50 V07-14 1.00 36 36 0.60 0.50 10.80 57.60
BM 2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM 2 20X50 1.00 4 4 0.20 0.50 0.40 4.80
BM 2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM2 20X50 1.00 4 4 0.20 0.50 0.40 4.80
BM 2 20 X50 1.00 4 4 0.20 0.50 0.40 4.80
BM 2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM2 20 X50 1.00 6 6 0.20 0.50 0.60 7.20
BM2 20 X50 1.00 4 4 0.20 0.50 0.40 4.80

Cu.m Sq.m

GRAND TOTAL 1,114.00 326.20 1,766.40 #REF!

#REF!
B1 60 X50 1.00 62 62 0.60 0.50 18.60 99.20
BM 1 60 X 50 1.00 11 11 0.60 0.50 3.30 17.60
BM 1 60 X 50 1.00 40 40 0.60 0.50 12.00 64.00
BM 150 X60 1.00 11 11 0.60 0.50 3.30 17.60
BM 1 50 X 60 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 50 X60 1.00 16 16 0.60 0.50 4.80 25.60
BM 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 50 X 60 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 60 X 50 1.00 20 20 0.60 0.50 6.00 32.00
BM 60 X 50 1.00 20 20 0.60 0.50 6.00 32.00
BM 50 X 60 1.00 20 20 0.60 0.50 6.00 32.00
BM 1 60 X 50 1.00 16 16 0.60 0.50 4.80 25.60
BM 60 X50 1.00 16 16 0.60 0.50 4.80 25.60
BM 1 50 X 60 1.00 16 16 0.60 0.50 4.80 25.60
B2 20 X 50 1 5.58 5.58 0.2 0.5 0.56 6.70
B2 20 X 50 1 4 4 0.2 0.5 0.40 4.80
B2 20 X 50 1 4 4 0.2 0.5 0.40 4.80
B2 20 X 50 1 5.58 5.58 0.2 0.5 0.56 6.70
363.16 105.12 573.39
ITEM DESCRIPTION UNIT QTY RATE DEL RATE
TO SITE FIXED
A AIR-CONDITIONING SYSTEM INSTALLATION

Air-conditioning and Ventilaton Units Installation

Split Units
1 Wall mounted split air-conditioing unit complete with installation
bracket, electrical cable and other installation accessories
Capacity: 9000 BTU Nr 165 FIX ONLY 12,000.00

2 Wall mounted split air-conditioing unit complete with installation


bracket, electrical cable and other installation accessories
Capacity: 12000 BTU Nr 76 FIX ONLY 12,000.00

3 Wall mounted split air-conditioing unit complete with installation


bracket, electrical cable and other installation accessories Nr 214 FIX ONLY 12,000.00
Cooling capacity:- 18000 BTU

4 Floor Standing Air-conditioing


Floor Standing Air-conditioing unit complete with electrical cable and
other installation accessories
Capacity: 24000 BTU Nr 7 FIX ONLY 25,000.00

B Refrigent Pipework Installation

Pipes
Light gauge annealed copper tubes in coils and rigid pipes to BS 2871.
Table Y for connection by means of autogenous welding.

1 15.90mm Internal Diameter m 70 2,928.00 585.60 3,513.60

2 12.70mm Internal Diameter m 3391 2,340.00 468.00 2,808.00

3 9.52mm Internal Diameter m 2150 1,640.00 328.00 1,968.00

4 6.35mm Internal Diameter m 5541 1,240.00 248.00 1,488.00

Accessories
5 19mm Internal Diameter Insulation Tube (15mmThick) m 5541 477.00 95.40 572.40

6 16mm Internal Diameter Insulation Tube (19mmThick) m 5541 405.00 81.00 486.00

7 2.5mmsq. 3-Core PVC/PVC Cable m 5541 1,865.00 373.00 2,238.00

8 65mm Diammeter non-kink PVC Pipe Sleeve m 5076 1,035.00 207.00 1,242.00

Condensate Pipework
9 50mm m 1,460 981 196.2 1,177.20

10 50 x 50 x 50mmTee Nr 484 780 156 936.00

11 50mm Bend Nr 210 695 139 834.00

12 25mm Dia pipe (upvc) m 5200 270.00 54.00 324.00

13 25mmBend(900) Nr 1994 225.00 45.00 270.00

14 25 x 25x 25mm Equal Tee Nr 400 252.00 50.40 302.40

CCP748M.BOQ Page 170


15 25mm Internal Diameter Insulation Tube for condensate with 19mm m 5300 1,200.00 240.00 1,440.00
Armaflex insulation tube

16 Installation material such as insulation tapes, Tangit gum, Plugs and


clips etc LOT 1

TOTAL TO SUMMARY

CCP748M.BOQ Page 171


SUMMARY OF COST FOR MAIN BUILDING

A Airconditioning pipe works Installation =N=


TOTAL TO PHASE 1 =N=

SUBTOTAL

7.5% VAT

TOTAL

CCP748M.BOQ Page 172


1,980,000.00

912,000.00

2,568,000.00

175,000.00

245,952.00

9,521,928.00

4,231,200.00

8,245,008.00

3,171,668.40

2,692,926.00

12,400,758.00

6,304,392.00

1,718,712

453,024

175,140

1,684,800.00

538,380.00

120,960.00

CCP748M.BOQ Page 173


7,632,000.00

3,000,000.00

62,136,848.40

CCP748M.BOQ Page 174


62,136,848.40
62,136,848.4

62,136,848.40

4,660,263.63

66,797,112.03

CCP748M.BOQ Page 175


Prepared by Nazedees Borner Nig Ltd

PROJECT: COMMERCIAL DEVELOPMENT AT WUSE, ABUJA


BILL OF QUANTITY: PLUMBING INSTALLATION

176
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT QTY RATE RATE TOTAL COST


DEL TO FIXED
SITE
A WATER SUPPLY PIPEWORK INSTALLATION
50mm-20mm Aquatherm PP-R Pipe

PIPES
1 25mm m 2 1,196 239 2,870

2 20mm m 5 800 160 4,800

Fittings
Elbow
3 25mm Dia Nr 4 420 84 2,016

4 20mm Dia Nr 2 350 70 840

Wallplate
5 20mm x 1/2" Nr 3 1,200 240 4,320

Equal Tee
6 25 x 25 x 25mm Nr 1 450 90 540

7 20 x 20 x 20mm Nr 1 400 80 480

Reducing Tee
8 25 x 20 x 25mm Nr 1 450 90 540

Nipple
9 25mm X 1/2" male Nr 1 1,800 360 2,160

Sockets
10 25mm Nr 1 420 84 504

11 20mm Nr 1 350 70 420

Valves
12 25mm Gate Valve Nr 1 9,000 1800 10,800

13 15mm Angle Valve with chrome cover plate Nr 3 3,500 700 12,600

14 15mm Copper Flexible connector Nr 3 2,000 400 7,200

MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot

All installation Acessories e.g pipe clip-single


16 and double, bushing and cap plugs etc. Lot

TOTAL TO COLLECTION 50,090

177
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT RATE RATE TOTAL COST


DEL TO FIXED
SITE
A SOIL AND WASTE PIPEWORK INSTALLATION
PVC and Polythene pipes and fittings to BS-EN
1329 and 1401
OSTENDORF
PIPES
1 100mm m 2 2,800 560 6,720

2 50mm m 3 981 196.2 3,532

FITTINGS
Bends (90 Degree)
3 100mm Nr 1 1,385 277 1,662

4 50mm Nr 2 695 139 1,668

Bends (45 Degree)


5 100mm Nr 4 1,385 277 6,648

6 50mm Nr 10 695 139 8,340

TEES
7 100 x 100 x 100mm Nr 1 1,680 336 2,016

8 100 x 50 x 100mm Nr 1 1,681 336.2 2,017

9 50 x 50 x 50mm Nr 1 780 156 936

TRAPS
10 100mm Pan Connector Nr 1 2,000 400 2,400

11 50mm Stainless Steel Floor Drain Nr 1 22,000 2200 24,200

Socket
12 100mm Nr 1 1,385 277 1,662

13 50mm Nr 1 695 139 834

Installation accessories e.g. Tangit Gum,


14 Brackets Clips etc. LOT
TOTAL TO COLLECTION 62,635

178
Prepared by Nazedees Borner Nig Ltd

COST COLLECTION

A Water Supply Pipework Installation =N= 50,090

B Soil and Wast Water Pipework


Installation =N= 62,635

SUB-TOTAL =N= 112,725

Total to Main Summary =N= 112,725

179
Prepared by Nazedees Borner Nig Ltd

PROJECT: COMMERCIAL DEVELOPMENT AT WUSE, ABUJA


BILL OF QUANTITY: PLUMBING INSTALLATION

180
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT QTY RATE RATE TOTAL COST


DEL TO FIXED
SITE
A WATER SUPPLY PIPEWORK INSTALLATION
50mm-20mm Aquatherm PP-R Pipe

PIPES
1 25mm m 948 1,196 239 1,360,570

2 20mm m 2,370 800 160 2,275,200

Fittings
Elbow
3 25mm Dia Nr 1,896 420 84 955,584

4 20mm Dia Nr 948 350 70 398,160

Wallplate
5 20mm x 1/2" Nr 1,422 1,200 240 2,047,680

Equal Tee
6 25 x 25 x 25mm Nr 474 450 90 255,960

7 20 x 20 x 20mm Nr 474 400 80 227,520

Reducing Tee
8 25 x 20 x 25mm Nr 474 450 90 255,960

Nipple
9 25mm X 1/2" male Nr 474 1,800 360 1,023,840

Sockets
10 25mm Nr 474 420 84 238,896

11 20mm Nr 474 350 70 199,080

Valves
12 25mm Gate Valve Nr 474 9,000 1800 5,119,200

13 15mm Angle Valve with chrome cover plate Nr 1,422 3,500 700 5,972,400

14 15mm Copper Flexible connector Nr 1,422 2,000 400 3,412,800

MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot

All installation Acessories e.g pipe clip-single


16 and double, bushing and cap plugs etc. Lot

TOTAL TO COLLECTION 23,742,850

181
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT RATE RATE TOTAL COST


DEL TO FIXED
SITE
A SOIL AND WASTE PIPEWORK INSTALLATION
PVC and Polythene pipes and fittings to BS-EN
1329 and 1401
OSTENDORF
PIPES
1 100mm m 948 2,800 560 3,185,280

2 50mm m 1,422 981 196.2 1,673,978

FITTINGS
Bends (90 Degree)
3 100mm Nr 474 1,385 277 787,788

4 50mm Nr 948 695 139 790,632

Bends (45 Degree)


5 100mm Nr 1,896 1,385 277 3,151,152

6 50mm Nr 4,740 695 139 3,953,160

TEES
7 100 x 100 x 100mm Nr 474 1,680 336 955,584

8 100 x 50 x 100mm Nr 474 1,681 336.2 956,153

9 50 x 50 x 50mm Nr 474 780 156 443,664

TRAPS
10 100mm Pan Connector Nr 474 2,000 400 1,137,600

11 50mm Stainless Steel Floor Drain Nr 474 22,000 2200 11,470,800

Socket
12 100mm Nr 474 1,385 277 787,788

13 50mm Nr 474 695 139 395,316

Installation accessories e.g. Tangit Gum,


14 Brackets Clips etc. LOT
TOTAL TO COLLECTION 29,688,895

182
Prepared by Nazedees Borner Nig Ltd

COST COLLECTION

A Water Supply Pipework Installation =N= 23,742,850

B Soil and Wast Water Pipework


Installation =N= 29,688,895

SUB-TOTAL =N= 53,431,745

Total to Main Summary =N= 53,431,745

183
BILL NR 6

- EXTERNAL PLUMBING

COMMERCIAL DEVELOPMENT. PLUMBING. PL./1


DESCRIPTION UNIT QTY UNIT RATE AMOUNT
SUPPLY

BILL #6

FRP/GRP Raw Water storage tank


6.1 water Tank to structural Engineer's details
Capacity 129,600 liters (6.1m X 6.1m X 3.66m),
Comprising of:
The tank shall be constructed with
drain sump,completely leakproof
into the subsoil and suction to fire pump, water
treatment plant,water intake into the tank, vent etc.
must be provided. the tank shall be partitoned. Nr 1 27,000,000.00 27,000,000.00

FRP/GRP Potable Water storage tank


6.3 water Tank to structural Engineer's details
Capacity 82,944 liters (4.88m X 4.88m X 3.66m),
Comprising of:
The tank shall be constructed with
drain sump,completely leakproof
into the subsoil and suction to fire pump, water
treatment plant,water intake into the tank, vent etc.
must be provided. the tank shall be partitoned. Nr 1 21,600,000.00 21,600,000.00

Water Pressure Booster Pumps set for sanitary wares


6.4 2 x 2.2kw Electric Water booster/transfer set (duty/standby)
on stainless steel skid 6m3/hr,60m head
all necessary accessories, panels, complete with
pressure vessel etc for automatic operation.
complete with the appropriate BMS gateway Set 1 6,075,000.00 6,075,000.00

6.5 Drill max 300mm diameter borehole for the


installation of 150mm diameter UPVC casing to
a depth of 100m. (actual depth to be based on
geophysical survey report) Anticipated borehole
yield shall not be less than 5m3/hr Nr 2 750,000.00 1,500,000.00

6.6 Supply and install 15kW submersible pump type


Grundfos 1phase 220V 50Hz cap 10m3/hr
against120m head, together with power and control
cables dry running protection electrode, starter,
relays and pilot lamp Nr 2 350,000.00 700,000.00

6.7 Automatic Fire fighting Pump set complete with


Diesel Petrol and Jockey pumps
Flow rate 50l/sec
Head 45mH SET 1 16,200,000.00 16,200,000.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./2


DESCRIPTION UNIT QTY UNIT RATE AMOUNT
SUPPLY

6.8 Supply install and put to work Reverse Osmosis


packaged Water Treatment Plant, capacity more
than 5m3/hr to treat raw water from borehole to
W.H.O standard. The plant shall incorporate
product portable water tank, aeration plant,
chemical dozing units etc. Treated water to be
delivered directly to the potable surface water tank.
water quality to determine system components.
NAFDAC guideline for portable water treatment to
be strictly followed. complete with the appropriate
BMS gateway.

Nr 1 15,000,000.00 15,000,000.00

6.9 Extra for supply of chemicals, filters, membrane etc.


for twelve months operation of the plant (contractor
to provide detail list.) other installation accessories.
Lot 1 5,550,000.00 5,550,000.00

6.10 Allow for training of in-house operator (contractor


provide details)
Lot 1 800,000.00 800,000.00

6.1 Associated pipe works with fittings an acessories PS 1 5,000,000.00

6.1 Swimming pool equipment and filters PS 1 25,000,000.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./3


SUBTOTAL '6' CARRIED TO SUMMARY 124,425,000.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./4


BILL NR 2

- SANITARY FIXTURE

COMMERCIAL DEVELOPMENT. PLUMBING. PL./5


PROPOSED COMMERCIAL DEVELOPMENT
MECHANICAL SERVICES BILL OF ENGINEERING MEASUREMENT AND EVALUATION
PLUMBING AND FIRE FIGHTING SYSTEM
ITEM DESCRIPTION UNIT QTY UNIT RATE
SUPPLY ERECT

BILL #2
SANITARY FIXTURE: All sanitary fixtures
shall be: AMITAGE SHANK or approved equal.

B.1 Wall mounted dual fluch WC Bowl made of


Vitreous China Dual Flush Water Consumption
6.0-3.0 Lpf Includes plastic slow-close seat and cover
with concealed seat ring In-wall high-density
polyethylene (HDPE) tank, insulated to prevent
condensation16 gauge, powder coated,
structural steel tubing in-wall carrier unit rated to
400 kg without damage to finished wall or carrier Nr 490 148,500.00 8,625.00

B.2 Lavatory Wash Basin, Wall Hung, complete with


mixer tap, pop up waste, 32mm bottle trap. Armitage
shank or approved equal. Nr 490 121,500.00 12,150.00

B.3 Wall hung urinal,with concealed cisten and piping with


sensor auto-flush
piping with system.
automatic sensor flush system. Nr 72 155,250.00 15,525.00

B.4 Stainless steel kitchen sinks, single bowl


double drain complete with mounting brackets. Nr 52 81,000.00 8,100.00

B.5 Hand Driers. Slieber Eltron or approved equal. Nr 252 27,000.00 2,700.00

B.6 Soap Dispensers, Brightwell or equal. Nr 252 14,040.00 1,404.00

B.7 6mm plate glass mirror 450 x 600mm fixed to wall


with chromium plated dome headed screws
Armitage shank or approved equal. Nr 490 5,400.00 540.00

B.9 Reinforced fiber glass shower tray with mixer


taps and telephone shower, traps complete with
non-slip base. Armitage shank or approved
equal. Nr 135 202,500.00 20,250.00

B.10 15 liters Thermostatic Electric water Heater.


ARISTON or approved equal. Complete with
installation fittings, viz. non-return valves etc. Nr 135 87,750.00 8,775.00

B.11 Set of Bathroom accessories consisting of,


but not limited to the following items:
toilet roll holder, towel rail, soap dish etc. set 490 33,750.00 3,375.00

B.12 Sundry installation materials Lot 1 200,000.00 20,000.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./6


SUB-TOTAL FOR ITEM "B"

BILL NR 3

- COLD AND HOT WATER SUPPLY SERVICES PIPES

COMMERCIAL DEVELOPMENT. PLUMBING. PL./7


ITEM DESCRIPTION UNIT QTY UNIT RATE
SUPPLY ERECT

C COLD AND HOT WATER SUPPLY SERVICES


PIPES
Install, test and commission pressure water
supply pipe, make; multi layer pipe or approved
equal with minimum working pressure of 10bar.
Installation cost to include for pressure testing
as indicated in the specification.

C1 50mm diameter (INTERNAL DIAMETER) m 450 3,780.00 378.00

C.2 32mm diameter (INTERNAL DIAMETER) m 1,000 3,468.15 346.82

C.3 25mm diameter (INTERNAL DIAMETER) m 800 2,381.40 238.14

C.4 19mm diameter (INTERNAL DIAMETER) m 600 1,539.00 153.90

C.5 13mm diameter (INTERNAL DIAMETER) m 1,500 1,015.20 101.52

Elbows
C.6 50mm diameter Nr 20 2,175.00 217.50

C.7 32mm diameter Nr 50 2,105.40 210.54

C.8 25mm diameter Nr 220 1,618.20 161.82

C.9 19mm diameter Nr 300 984.55 98.46

C.10 13mm diameter Nr 500 697.45 69.74

Gate valves

C.10 50mm diameter Nr 4 8,265.00 826.50

C.11 32mm diameter Nr 10 4,640.00 464.00

C.12 25mm diameter Nr 10 3,770.00 377.00

C.13 19mm diameter Nr 4 2,900.00 290.00

C.14 13mm diameter Nr 10 2,900.00 290.00

Tees

COMMERCIAL DEVELOPMENT. PLUMBING. PL./8


C.15 50 x 50 x 32mm diameter Nr 10 1,450.00 145.00

C.16 32 x 32 x 25mm diameter Nr 100 1,450.00 145.00

C.17 25 x 25 x 19mm diameter Nr 300 1,740.00 174.00

C.18 19 x 19 x 13mm diameter Nr 350 1,015.00 101.50

C.19 32mm diameter Nr 50 1,740.00 174.00

C.20 25mm diameter Nr 70 1,740.00 174.00

ITEM DESCRIPTION UNIT QTY UNIT RATE


SUPPLY ERECT

COLD AND HOT WATER SUPPLY SERVICES


PIPES CONT'D

C.21 19mm diameter Nr 60 1,450.00 145.00

C.22 13mm diameter Nr 80 1,160.00 116.00

Sockets

C.23 50mm diameter Nr 10 1,450.00 145.00

C.24 32mm diameter Nr 50 580.00 58.00

C.25 25mm diameter Nr 80 507.50 50.75

C.26 19mm diameter Nr 100 362.50 36.25

C.27 13mm diameter Nr 150 362.50 36.25

Union
C.28 50mm diameter Nr 4 8,700.00 870.00

C.29 32mm diameter Nr 50 5,075.00 507.50

C.30 25mm diameter Nr 80 4,060.00 406.00

C.31 19mm diameter Nr 150 3,625.00 362.50

C.32 13mm diameter Nr 100 3,625.00 362.50

Nipple

C.33 50mm diameter Nr 4 7,540.00 754.00

C.34 32mm diameter Nr 5 3,190.00 319.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./9


C.35 25mm diameter Nr 8 2,175.00 217.50

C.36 19mm diameter Nr 216 1,450.00 145.00

C.37 13mm diameter Nr 1,200 1,015.00 101.50

Reducers

C.38 32/25 reducers Nr 6 2,900.00 290.00

C.39 25/19 reducers Nr 100 2,610.00 261.00

C.40 19/13 reducers Nr 120 2,610.00 261.00

Non-return valves
C.41 50mm diameter Nr 2 8,700.00 870.00

C.42 32mm diameter Nr 6 7,250.00 725.00


ITEM DESCRIPTION UNIT QTY UNIT RATE
SUPPLY ERECT

COLD AND HOT WATER SUPPLY SERVICES


PIPES CONT'D

C.43 25mm diameter Nr 2 3,625.00 362.50

Bib taps

C.44 19mm diameter Nr 8 5,075.00 507.50

Angle valves

C.45 16mm diameter Nr 1100 3,375.00 337.50

Bathroom isolation valves

C.46 19mm diameter Nr 250 7,250.00 725.00

C.43 25mm diameter Nr 2 3,625.00 362.50

Bib taps

C.44 19mm diameter Nr 6 5,075.00 507.50

Angle valves

C.45 16mm diameter Nr 1200 3,375.00 337.50

Bathroom isolation valves

C.46 19mm diameter Nr 216 7,250.00 725.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./10


SUB-TOTAL FOR ITEM "C"
ITEM DESCRIPTION UNIT QTY UNIT RATE
SUPPLY ERECT

D WASTE AND SOIL WATER DRAINAGE PIPE


Drainage piping in UPVC U/G drain pipe to
B.S 4660;1973 .Pipe shall be Mutinchi and fittings
shall be Wavin,Redi or approved equal

Piping

D.1 150mm diameter m 150 3,770.00 377.00

D.2 100mm diameter m 2,000 3,190.00 319.00

D.3 50mm diameter m 1,500 1,450.00 145.00

Sockets

D.4 150mm diameter Nr 20 3,915.00 391.50

D.5 100mm diameter Nr 200 3,625.00 362.50

D.6 50mm diameter Nr 150 2,175.00 217.50

UPVC Y - Tees

D.7 100mm diameter Nr 300 4,596.50 459.65

D.8 50mm diameter Nr 220 1,740.00 174.00

D.9 100mm diameter pan-connectors Nr 216 3,625.00 362.50

Floor drain with trap

COMMERCIAL DEVELOPMENT. PLUMBING. PL./11


D.10 50mm diameter Nr 216 4,640.00 464.00

Elbow

D.11 50mm diameter 90° Nr 50 2,175.00 217.50

D.12 100mm diameter 45° Nr 150 3,645.00 364.50

D.13 50mm diameter 45° Nr 100 2,025.00 202.50

End plug

D.14 100mm diameter Nr 50 2,465.00 246.50

D.15 50mm diameter Nr 60 1,450.00 145.00

Bottle trap

D.16 32mm diameter Nr 75 5,365.00 536.50

D.17 Civil works w.r.t setting out and laying of drainage


piping Lot 1 -

E.18 100mm diameter fubura Nr 10 15,000.00 1,500.00

S/N DESCRIPTION UNIT QTY UNIT RATE


SUPPLY ERECT
WASTE AND SOIL WATER DRAINAGE
PIPES CONT'D

SEPTIC TANK AND MANHOLE

D.19 600 x 600mm Nr 10

D.20 450 x 450mm Nr 8

D.21 Allow for the construction of septic tank and


soak away pit Lot 1

D.22 Allow a provisional sum of N500,000.00 for


other special fixture as may be required and
specified by the engineers. PS 1

COMMERCIAL DEVELOPMENT. PLUMBING. PL./12


SUB-TOTAL FOR ITEM "D"

BILL NR 5

COMMERCIAL DEVELOPMENT. PLUMBING. PL./13


- FIRE PROTECTION SYSTEM

DESCRIPTION UNIT QTY UNIT RATE


SUPPLY ERECT

E FIRE PROTECTION SYSTEM

E.1 5Kg CO2 Extinguisher complete with signage.


Angus or approved equal Nr 90 27,000.00 2,700.00

E.2 9Kg ABC dry powder Extinguisher complete with


signage. Angus or approved equal Nr 90 20,250.00 2,025.00

E.3 Fire Hosereel Cabinet consisting of


a recessed swing type hosereel with
19mm internal diameter X 30m length,
reinforced rubber hose pipe wound on
metal reel complete with signage and
Fire extinguisher
Angus or approved equal(must be in
cabinet) Nr 90 222,750.00 22,275.00

Pipes

COMMERCIAL DEVELOPMENT. PLUMBING. PL./14


All pipes must be pressured tested to a minimum
of 10 bar. External underground pipes to be wrapped
with denso tape. Internal pipes shall be Black
steel pipe.

E.4 100mm diameter m 250 13,500.00 1,350.00

E.5 75mm diameter m 50 10,800.00 1,080.00

E.6 65mm diameter m 50 12,825.00 1,282.50

E.7 50mm diameter m 350 3,510.00 351.00

E.8 25mm diameter m 100 3,105.00 310.50

E.9 19mm diameter m 100 2,430.00 243.00

Tees

E.10 100mm diameter Nr 10 8,700.00 870.00

E.11 100/100/75mm diameter Nr 5 7,975.00 797.50

E.12 100/100/65mm diameter Nr 10 7,975.00 797.50

Elbow

E.13 100mm diameter Nr 8 5,075.00 507.50

E.14 65mm diameter Nr 8 4,350.00 435.00

E.15 19mm diameter Nr 50 2,175.00 217.50

DESCRIPTION UNIT QTY UNIT RATE


SUPPLY ERECT

FIRE PROTECTION SYSTEM CONT'D

Socket

E.16 100mm diameter Nr 12 7,250.00 725.00

E.17 75mm diameter Nr 10 6,525.00 652.50

E.18 65mm diameter Nr 8 6,380.00 638.00

E.19 19mm diameter Nr 6 4,205.00 420.50

Nipples
E.20 100mm diameter Nr 10 5,800.00 580.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./15


E.21 19mm diameter Nr 90 4,350.00 435.00

Gate valve

E.22 100mm diameter Nr 4 116,000.00 11,600.00

E.23 19mm diameter Nr 90 7,250.00 725.00

Non- Return valve

E.24 100mm diameter Nr 6 65,250.00 6,525.00

E.25 65mm diameter Nr 8 40,500.00 4,050.00

Union

E.26 100mm diameter Nr 6 8,700.00 870.00

E.27 19mm diameter Nr 8 2,900.00 290.00

Reducers

E.28 100mm x 75mm diameter Nr 8 8,700.00 870.00

E.29 100mm x 65mm diameter Nr 10 7,250.00 725.00

E.30 50mm x 25mm diameter Nr 8 5,800.00 580.00

E.31 25mm x 20mm diameter Nr 8 33,750.00 3,375.00

Air release valve

E.32 25mm diameter Nr 10 47,250.00 4,725.00

Landing valve

E.33 65mm diameter Nr 4 121,500.00 12,150.00

DESCRIPTION UNIT QTY UNIT RATE


SUPPLY ERECT

FIRE PROTECTION SYSTEM CONT'D

Fireman breech inlet

E.34 100mm diameter Nr 1 391,500.00 39,150.00

Hydrant

E.35 100mm diameter Nr 4 391,500.00 39,150.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./16


E.36 Allow a provision of N300,000.00 for
other special fittings as may be
required and specified by the engineers PS 1

SUBTOTAL '5' CARRIED TO SUMMARY

COMMERCIAL DEVELOPMENT. PLUMBING. PL./17


COMMERCIAL DEVELOPMENT. PLUMBING. PL./18
ALUATION

AMOUNT

157,125.00 76,991,250.00

133,650.00 65,488,500.00

170,775.00 12,295,800.00

89,100.00 4,633,200.00

29,700.00 7,484,400.00

15,444.00 3,891,888.00

5,940.00 2,910,600.00

222,750.00 30,071,250.00

96,525.00 13,030,875.00

37,125.00 18,191,250.00

220,000.00 220,000.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./19


235,209,013.00

S PIPES

COMMERCIAL DEVELOPMENT. PLUMBING. PL./20


AMOUNT

1,871,100.00

3,814,965.00

2,095,632.00

1,015,740.00

1,675,080.00

47,850.00

115,797.00

391,604.40

324,901.50

383,597.50

36,366.00

51,040.00

41,470.00

12,760.00

31,900.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./21


15,950.00

159,500.00

574,200.00

390,775.00

95,700.00

133,980.00

AMOUNT

95,700.00

102,080.00

15,950.00

31,900.00

44,660.00

39,875.00

59,812.50

38,280.00

279,125.00

357,280.00

598,125.00

398,750.00

33,176.00

17,545.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./22


19,140.00

344,520.00

1,339,800.00

19,140.00

287,100.00

344,520.00

19,140.00

47,850.00
AMOUNT

7,975.00

44,660.00

4,083,750.00

1,993,750.00

7,975.00

33,495.00

4,455,000.00

1,722,600.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./23


30,162,581.90
AMOUNT

622,050.00

7,018,000.00

2,392,500.00

86,130.00

797,500.00

358,875.00

1,516,845.00

421,080.00

861,300.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./24


1,102,464.00

119,625.00

601,425.00

222,750.00

135,575.00

95,700.00

442,612.50

by builder

165,000.00

AMOUNT

by builder

by builder

by builder

500,000.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./25


17,459,431.50

COMMERCIAL DEVELOPMENT. PLUMBING. PL./26


AMOUNT

29,700.00 2,673,000.00

22,275.00 2,004,750.00

22,052,250.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./27


3,712,500.00

594,000.00

705,375.00

1,351,350.00

341,550.00

267,300.00

95,700.00

43,862.50

87,725.00

44,660.00

38,280.00

119,625.00

AMOUNT

95,700.00

71,775.00

56,144.00

27,753.00

63,800.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./28


430,650.00

510,400.00

717,750.00

430,650.00

356,400.00

57,420.00

25,520.00

76,560.00

79,750.00

51,040.00

297,000.00

519,750.00

534,600.00

AMOUNT

430,650.00

1,722,600.00

COMMERCIAL DEVELOPMENT. PLUMBING. PL./29


300,000.00

40,987,839.50

COMMERCIAL DEVELOPMENT. PLUMBING. PL./30


Prepared by Nazedees Borner Nig Ltd

PROJECT: COMMERCIAL DEVELOPMENT AT WUSE, ABUJA


BILL OF QUANTITY: PLUMBING INSTALLATION

31
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT QTY RATE RATE TOTAL COST


DEL TO FIXED
SITE
A WATER SUPPLY PIPEWORK INSTALLATION
50mm-20mm Aquatherm PP-R Pipe

PIPES
1 25mm m 2 1,196 239 2,870

2 20mm m 5 800 160 4,800

Fittings
Elbow
3 25mm Dia Nr 4 420 84 2,016

4 20mm Dia Nr 2 350 70 840

Wallplate
5 20mm x 1/2" Nr 3 1,200 240 4,320

Equal Tee
6 25 x 25 x 25mm Nr 1 450 90 540

7 20 x 20 x 20mm Nr 1 400 80 480

Reducing Tee
8 25 x 20 x 25mm Nr 1 450 90 540

Nipple
9 25mm X 1/2" male Nr 1 1,800 360 2,160

Sockets
10 25mm Nr 1 420 84 504

11 20mm Nr 1 350 70 420

Valves
12 25mm Gate Valve Nr 1 9,000 1800 10,800

13 15mm Angle Valve with chrome cover plate Nr 3 3,500 700 12,600

14 15mm Copper Flexible connector Nr 3 2,000 400 7,200

MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot

All installation Acessories e.g pipe clip-single


16 and double, bushing and cap plugs etc. Lot

TOTAL TO COLLECTION 50,090

32
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT RATE RATE TOTAL COST


DEL TO FIXED
SITE
A SOIL AND WASTE PIPEWORK INSTALLATION
PVC and Polythene pipes and fittings to BS-EN
1329 and 1401
OSTENDORF
PIPES
1 100mm m 2 2,800 560 6,720

2 50mm m 3 981 196.2 3,532

FITTINGS
Bends (90 Degree)
3 100mm Nr 1 1,385 277 1,662

4 50mm Nr 2 695 139 1,668

Bends (45 Degree)


5 100mm Nr 4 1,385 277 6,648

6 50mm Nr 10 695 139 8,340

TEES
7 100 x 100 x 100mm Nr 1 1,680 336 2,016

8 100 x 50 x 100mm Nr 1 1,681 336.2 2,017

9 50 x 50 x 50mm Nr 1 780 156 936

TRAPS
10 100mm Pan Connector Nr 1 2,000 400 2,400

11 50mm Stainless Steel Floor Drain Nr 1 22,000 2200 24,200

Socket
12 100mm Nr 1 1,385 277 1,662

13 50mm Nr 1 695 139 834

Installation accessories e.g. Tangit Gum,


14 Brackets Clips etc. LOT
TOTAL TO COLLECTION 62,635

33
Prepared by Nazedees Borner Nig Ltd

COST COLLECTION

A Water Supply Pipework Installation =N= 50,090

B Soil and Wast Water Pipework


Installation =N= 62,635

SUB-TOTAL =N= 112,725

Total to Main Summary =N= 112,725

34
Prepared by Nazedees Borner Nig Ltd

PROJECT: COMMERCIAL DEVELOPMENT AT WUSE, ABUJA


BILL OF QUANTITY: PLUMBING INSTALLATION

35
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT QTY RATE RATE TOTAL COST


DEL TO FIXED
SITE
A WATER SUPPLY PIPEWORK INSTALLATION
50mm-20mm Aquatherm PP-R Pipe

PIPES
1 25mm m 2 1,196 239 2,870

2 20mm m 5 800 160 4,800

Fittings
Elbow
3 25mm Dia Nr 4 420 84 2,016

4 20mm Dia Nr 2 350 70 840

Wallplate
5 20mm x 1/2" Nr 3 1,200 240 4,320

Equal Tee
6 25 x 25 x 25mm Nr 1 450 90 540

7 20 x 20 x 20mm Nr 1 400 80 480

Reducing Tee
8 25 x 20 x 25mm Nr 1 450 90 540

Nipple
9 25mm X 1/2" male Nr 1 1,800 360 2,160

Sockets
10 25mm Nr 1 420 84 504

11 20mm Nr 1 350 70 420

Valves
12 25mm Gate Valve Nr 1 9,000 1800 10,800

13 15mm Angle Valve with chrome cover plate Nr 3 3,500 700 12,600

14 15mm Copper Flexible connector Nr 3 2,000 400 7,200

MISCELLANEOUS ACCESSORIES
15 Pressure Testing of Supply Pipes Lot

All installation Acessories e.g pipe clip-single


16 and double, bushing and cap plugs etc. Lot

TOTAL TO COLLECTION 50,090

36
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT RATE RATE TOTAL COST


DEL TO FIXED
SITE
A SOIL AND WASTE PIPEWORK INSTALLATION
PVC and Polythene pipes and fittings to BS-EN
1329 and 1401
OSTENDORF
PIPES
1 100mm m 2 2,800 560 6,720

2 50mm m 3 981 196.2 3,532

FITTINGS
Bends (90 Degree)
3 100mm Nr 1 1,385 277 1,662

4 50mm Nr 2 695 139 1,668

Bends (45 Degree)


5 100mm Nr 4 1,385 277 6,648

6 50mm Nr 10 695 139 8,340

TEES
7 100 x 100 x 100mm Nr 1 1,680 336 2,016

8 100 x 50 x 100mm Nr 1 1,681 336.2 2,017

9 50 x 50 x 50mm Nr 1 780 156 936

TRAPS
10 100mm Pan Connector Nr 1 2,000 400 2,400

11 50mm Stainless Steel Floor Drain Nr 1 22,000 2200 24,200

Socket
12 100mm Nr 1 1,385 277 1,662

13 50mm Nr 1 695 139 834

Installation accessories e.g. Tangit Gum,


14 Brackets Clips etc. LOT
TOTAL TO COLLECTION 62,635

37
Prepared by Nazedees Borner Nig Ltd

COST COLLECTION

A Water Supply Pipework Installation =N= 50,090

B Soil and Wast Water Pipework


Installation =N= 62,635

SUB-TOTAL =N= 112,725

Total to Main Summary =N= 112,725

38
ITEM DESCRIPTION UNIT QTY RATE DEL RATE
TO SITE FIXED
A AIR-CONDITIONING SYSTEM INSTALLATION

Air-conditioning and Ventilaton Units Installation

Split Units
1 Wall mounted split air-conditioing unit complete with installation
bracket, electrical cable and other installation accessories
Capacity: 9000 BTU Nr 2 FIX ONLY 12,000.00

2 Wall mounted split air-conditioing unit complete with installation


bracket, electrical cable and other installation accessories
Capacity: 12000 BTU Nr 6 FIX ONLY 12,000.00

3 Wall mounted split air-conditioing unit complete with installation


bracket, electrical cable and other installation accessories Nr 272 FIX ONLY 12,000.00
Cooling capacity:- 18000 BTU 280

SUB TOTAL C/F

CCP748M.BOQ Page 39
ITEM DESCRIPTION UNIT QTY RATE DEL RATE
TO SITE FIXED
SUB TOTAL C/B

B Refrigent Pipework Installation

Pipes
Light gauge annealed copper tubes in coils and rigid pipes to BS 2871.
Table Y for connection by means of autogenous welding.

1 12.70mm Internal Diameter m 3877 2,340.00 468.00

2 9.52mm Internal Diameter m 40 1,640.00 328.00

3 6.35mm Internal Diameter m 3900 1,240.00 248.00

Accessories
4 19mm Internal Diameter Insulation Tube (15mmThick) m 3400 477.00 95.40
ARMAFLEX

5 16mm Internal Diameter Insulation Tube (19mmThick) m 40 405.00 81.00

6 2.5mmsq. 3-Core PVC/PVC Cable m 3400 1,865.00 373.00


RABIEMETAL

7 65mm Diammeter non-kink PVC Pipe Sleeve m 3200 1,035.00 207.00

Condensate Pipework
8 32mm m 810 600.00 120

9 32mmTee Nr 200 320.00 64

10 32mm Bend Nr 210 320.00 64

11 25mm Dia pipe (upvc) m 1826 270.00 54.00

12 25mmBend(900) Nr 1800 225.00 45.00

13 25 x 25x 25mm Equal Tee Nr 200 252.00 50.40

14 25mm Internal Diameter Insulation Tube for condensate with 19 m 1900 1,200.00 240.00
Armaflex insulation tube

15 Installation material such as insulation tapes, Tangit gum, Plugs and


clips etc LOT 1

TOTAL TO SUMMARY

CCP748M.BOQ Page 40
SUMMARY OF COST FOR MAIN BUILDING

A Airconditioning pipe works Installation =N=


TOTAL =N=

SUBTOTAL

7.5% VAT

TOTAL

CCP748M.BOQ Page 41
24,000.00

72,000.00

3,264,000.00

3,360,000.00

CCP748M.BOQ Page 42
3,360,000.00

10,886,616.00

78,720.00

5,803,200.00

1,946,160.00

19,440.00

7,609,200.00

3,974,400.00

583,200

76,800

80,640

591,624.00

486,000.00

60,480.00

2,736,000.00

3,000,000.00

41,292,480.00

CCP748M.BOQ Page 43
41,292,480.00
41,292,480.0

41,292,480.00

3,096,936.00

44,389,416.00

CCP748M.BOQ Page 44
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT (N)

CONDITIONS OF CONTRACT

The Contractor will be deemed to have read each of the clauses in the
Conditions Of Contract And Contract Forms of which only the marginal
heading is stated below and he is to allow opposite to the number and title of
each clause carring a monetary value for carrying out the clause in its
entirety.
For convenience, only those provisions considered to have an obvious
financial effect are set out below and against each provision, the price shall
be inserted for

A Performance Bond item

B Advance payment bond item

Insurance specific to the Contract

C Loss/damage to property item

D Workmen Compensation Policy item

E Third Party Liability item

F Contractors All Risk Policy item ₦10,500,000.00

Cost Related to other Clauses in the Condition of Contract

The Contractor shall include/ allow for complying in all respects with the Conditions
of Contract Clauses 1 to 20 as per FIDIC 99 Condition of Contract for Construction
G item
for building and engineering works designed by the Employer. JCT 80;1994 revision
standard conditions

Mobilization and demobilization

Mobilization of all supervisions, labours, plants, materials and equipments


H item ₦5,000,000.00
necessary for the proper execution of the Works.

De-mobilization of all supervisions, labours, plants, materials and equipments


J item ₦7,500,000.00
necessary for the proper execution of the Works

Access to site

Construct access to the site and obtain by prior arrangement with the Engineer.
K Alter, shift and adopt from time to time as necessary in order to access the site or item
building

Use of the site

L The site shall not be used for any purpose other than the execution of the Contract item

Limitations of working space

The Contractor will allocate the site as indicated on the Engineer's site plans and he
must allow for setting out of temporary office accommodation and for storage of
M materials etc. Either within the site areas or at such other location that the item
Contractor may provide himself and at his own cost as per the Municipality
Regulations.

The Contractor shall take all reasonable precautions to prevent work people
N including those employed by the Sub-contractors from trespassing on adjoining
owner's property.
item
Limitations of working hours

Working hours shall be as per the labour law of Nigeria (Nigeria or Governing Law).
P Contractor shall allow for any additional working hours in order to achieve item
construction programme in coordination with Engineer

Existing services

The Contractor shall ascertain for himself the location of existing services on, under
or over the site. He shall take precautions to protect all such services within the
Q item
confines of the site and immediately make good any damage at his own expenses
in coordination with service authorities

BILL NO-01/ 45
CARRIED TO COLLECTION PAGE N

BILL NO-01/ 46
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S ADMINISTRATIVE ARRANGEMENTS

Site Administration.

The Contractor shall allow for providing all that is required for the proper
A administration of the contract at site level and in particular for complying in all item
respects with the relevant clauses in the Standard Conditions of Contract.

Supervision

Contractor shall allow for supervision and the site agent shall be replaced with
B item
appropriate person within reasonable time as approved by the Engineer

Security

The Contractor shall be responsible for and shall allow for providing 24 hours
C item
security through-out construction period

Safety, Health and Welfare of Workpeople

Provide for all costs and charges incurred by complying with all safety, health and
D welfare regulations, pertaining to staff and work people employed on the site item
including those employed by all sub-contractors

The Contractor shall be responsible for and shall allow for providing medical
E facilities including emergency medical facilities for his staff and shall made these item
available to Engineer's staff

Transport of Workpeople

Allow for the cost of all transport to and from site on the work people engaged on
F item
the site

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 47
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONSTRUCTION PLANTS

Small Plant and Tools

Provide for all necessary small plants and tools for the proper execution and
A item
completion of the Works

Scaffolding

Provide all necessary temporary scaffolding for the proper execution and
completion of the Works. Alter, relocate and adapt from time to time as necessary.
B The Contractor is to ascertain whether any scaffolding is required by any sub- item
contractor before striking. If the Contractor should strike any of his scaffolding and
is so required it shall be re-erected at his own expense.

Cranes and Lifting Plant

Provide all necessary mobile/ tower cranes and lifting plant for the proper execution
C and completion of the contract. (Note: The tower crane should not be installed in
permanent structure)

Site Transport

D Contractor shall allow for transportation of plant and equipment. item

Plants Required for Specific Trades

Provide all necessary plants required for specific trades for the proper execution
E item
and completion of the contract.

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 48
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Sign Boards

The Contractor shall allow for the provision, erection and maintenance of necessary
site notice board as required by the Engineer to display image of the project, project
A nr
name, the Employer's name and names of all Consultants associated with the
Project

The sign boards shall be complete weather durable with all necessary foundations,
supports, framing, painting and sign writing in English denoting the title of the
project and name of the Employer, Consultants and contractors with their
B item
respective addresses and building permit details. The Contractor shall provide all
details of the sign board to the Engineer for his approval before any work is put in
hand and to enable erection to commence in the early stages of the contract.

The Contractor shall provide sufficient lighting to sign boards which includes power
C item
supply and lighting fixture.

The Contractor shall clean, maintain and at the completion of the Contract remove
D item
the sign board, supports and foundations.

E Any authority payments item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 49
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

ENGINEER'S FACILITIES

Site Offices, Stores and other Facilities

Office construction shall be light airy manner with air-conditioned for Employer,
Engineer and Clerk of works/ General office (but not limited to three office) shall be
constructed comprising of Meeting room, toilets, pantry facilities & sample room,
etc. all as per specification

The Contractor shall construct sub-structure to place porta-cabins as per Engineer's


A item
instruction

The Contractor shall supply and place Port-a- cabins, comprising of carpet floors
B item
and all other finishes as stated in the specification

The Contractor shall Supply and install all electromechanical works including fire
C alarm and fire fighting system in accordance with ROP standard and approval of item
works as per engineer's

The Contractor shall obtain power, water, drainage and telephone to meet office
D item
requirement (separate for Employer's and Engineer's office)

The Contractor shall supply minimum of following new furniture and other items for
each office (Contractor shall provide warranty card or slip for all Electronic items)

E Desk complete with twin pedestal lockable drawers nr

F Tables nr

G Lockable filing (two drawer in each office) cabinets nr

H Storage cupboard/ book case nr

Drawing hangers complete with drawing suspension clamps or one chest of drawer
J nr
specifically designed for drawing storage

K Drafting table with adjustable stool nr

L Swivel based/ sprung back desk chair nr

M Conference table nr

N Conference chairs nr

P Visit Chairs nr

Q Fixed shelving required for storage/ display of samples and other materials nr

R Electric kettle nr

S 350 liter refrigerator nr

T Microwave oven nr

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 50
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

ENGINEER'S FACILITIES

Site Offices, Stores and other Facilities

The Contractor shall supply, install and maintain following equipment with
necessary cabling, wiring and power connection.

Telephone instruments, one in Employer's office, one in Engineer's office with


A nr
extension to general office

B Fax machine in general office nr

Colour printer photocopier and scanner on high speed (A3/A4 format, reduction/
C nr
enlargement facility, 2 sides coping, cassette feeds and sorting facility), scanner

Laptop with network facility and internet, minimum configuration; Intel Core i7,
2GHz processor, 1 TB SSD hard disk, 16 GB RAM, DVD super multi DL Rewriter,
15.4" LED monitor, in built card reader, in built web cam & mic, Wi-Fi, Bluetooth,
D nr
complete with wireless mouse, flash memory stick (8GB), printer, Anti virus, Micro
soft Office - all programs with single user license agreement, with latest softwares
(return to Employer after completion of the project)

E The Contractor shall replace any defected item during the course of Construction. item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 51
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities

Maintenance of project office and office equipment includes cleaning on daily basis
A and to provide consumable items for the use of Employer and consultant such as month
toilet soaps, towels, pantry items like clean drinking water, milk, coffee, sugar, etc.,

The Contractor shall supply of stationaries and other sundry items (copy papers, fax
papers, pens, pencils, leads, erasers, pins, staplers, pin boards, binder, paper
B month
cutter, heavy duty punching machine, mirror, waste bins, desk paper trays, clocks,
etc.).

C The Contractor shall supply of toners, special colour printing paper, CDs, DVDs, etc. month

The Contractor shall maintain site office and floor and window cleaning and removal
D month
of rubbish

The Contractor shall pay the cost of utilities. (Water, Electricity, Telephone, Internet,
E month
etc.)

The Contractor shall provide high speed ADSL internet connection with Wi-Fi for
F month
exclusive use of Employer & Engineer

The Contractor shall supply PPE for sole use of the Employer, Engineer and their
G staff visiting the site, safety helmets, safety shoes, protective eye glass, ear muffs, item
reflective jackets, etc., as requested by the Engineer

The Contractor shall maintain and provide necessary security to the Engineer's
H item
facilities after issuing of completion certificate until the Employer take over security.

J Remove Port-a-cabin, clean the area as instructed by Engineer. item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 52
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

The Contractor shall provide, erect, maintain and remove on completion all
necessary site offices, stores, mess rooms, sanitary accommodation and other
A facilities as may be required by the contractor for his own and his sub-contractors item
use, together with all associated water, drainage, electrical lighting and power, air
conditioning, telephone/ equipment and attendance.

The position of all site office stores etc. shall be to the approval of the Engineer,
and the contractor must allow for any 'off site' facilities he may require additional to
B item
the area allocated to him. Contractor shall submit the Facilities Plan for Engineer’s
approval.

Temporary Roads

Provide, maintain and alter as necessary temporary roads, paths, hard standings,
C pavement crossings and the like to and within the site. Remove and reinstate all item
ground and work disturbed when required.

Temporary Works

Supply, install, remove and handover all temporary fencing to Employer at the
D item
completion of the Works

Water for the Works

Provide all water required for the works and provide and remove on completion all
requisite temporary pipe work, pumps, storage tanks etc. The Contractor must
E item
include for obtaining water from an independent source up to the issuance of
Taking Over Certificate.

Lighting and Power for the Works

Provide all electric light and power required for the Works and remove all temporary
F item
installations on completion up to the issuance of Completion Certificate.

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 53
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

Foul Discharge

Provide necessary sewage connecting to Engineer's site office, Contractor's office


A item
and discharge as requested

Testing of Materials

The Contractor shall carry out tests by an independent third party laboratory
B approved by the Engineer as per specification and shall report all test results item
promptly to the Engineer

The Contractor shall be responsible for sending Engineer’s representatives to the


source of supply or manufacturer's works to test the materials or supervise their
C item
production whenever considered necessary and shall bear all necessary costs
related to the same.

Copies of Orders

The Contractor shall provide the Engineer with a copy of all orders for the supply of
D such materials or goods required in connection with the Works as the Engineer may item
specify.

Testing of the Works

Allow for all tests required by the specification to be carried out including all
E necessary equipment, materials and reports as per scope of Works and item
specification.

Provide water, fuel and electricity necessary for the plumbing and engineering
F item
installations.

As-built Drawings

As-built' drawings shall be six sets hard copies and one set of electronic copy in CD
in latest AutoCAD format as specified in the specification. Each set of hard copy of
G item
drawings shall be properly bound and presented in a suitable manner acceptable to
the Engineer

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 54
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

Operation and Maintenance Manuals

A Allow for O&M manuals for MEP and other works as per specifications item

The Contractor shall not be entitled for any extra payment or extension of time for
B the correction, preparation and supplying of the above mentioned drawings and item
information.

Training on Completion

Allow for trainings of Employer's staff related to all system on completion of the
C item
project

Protecting the Works

Provide for carefully covering up and protecting all of the Works by whatever means
D item
necessary as required during construction and on completion until handover

Disposal of debris

Keep the site free from debris arresting from the works during the construction
E period and leave the site free from debris on completion to the satisfaction of the item
Engineer.

Maintenance of Public and Private Roads

Allow for maintenance of public and private roads used by the Contractor around
F item
the site

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 55
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Control of Noise, Dust and Pollution

The Contractor shall take all necessary precautions in reducing noise caused by
A plant by means of mufflers, silencers, screens and the like in line with HSE item
requirements.

Watering of roads, fill granular materials as required at exit points, clean dirt carried
B item
beyond exit point on daily basis.

Provide for removing all rubbish from the site both as it accumulates from time to
C item
time and at completion.

Provide for cleaning the buildings inside and out, removing stains and touching up
D paint work and polish work and leaving the whole of the works clean, ready for item
occupation and to the satisfaction of the Engineer on completion.

The Contractor shall provide dedicated workmen to observe and clear designated
E item
areas of Foreign Object Debris as it occurs.

The Contractor shall be responsible for cleaning the site and work area completely
of all his temporary installation on completion of the Works shall be required to
grade or rake the area he has occupied to remove all traces of his occupation and
F item
leave the site as close to its original condition as possible. The Contractor shall
provide constantly available labour transport and materials to maintain the
cleanliness and tidiness of the Site.

All Statutory Obligations

The Contractor shall make every effort to comply with local authorities rulles and
G item
requirements

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 56
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Guarantee and Warrantee

The Contractor shall provide guarantee/warrantee for the items as required in the
specification. Guarantee/warrantee are to be taken in the name of the Employer
A item
and forward the originals to the Engineer prior to the issue of the certified of
completion. All Guarantee/Warrantee should be started from the date of completion.

Submittals

Prepare and submit to the Engineer all submittals, materials, working drawings,
B item
record drawings, procurement schedule etc. as required by the Specification.

Samples

The Contractor shall allow for submitting samples of all materials and goods as
required to the Engineer/specification for obtaining his approval, and for paying all
C item
fees and charges etc., in connection therewith. (after approval sample may be used
in construction of the project)

Technical Literature

The Contractor shall obtain copies of the latest editions of standard manuals
D specified in the specification to be kept on site for the use of the Engineer. Upon item
completion of the project they are to be handed over to the Employer.

Statutory Obligations

Allow for all costs for permission, licenses, inspection compliance to regulation and
E item
no objection certificates.

Shop Drawings

F Prepare and submit to the Engineer all shop drawings required by the specification. item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 57
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Employer's Tradesmen, Direct Contractors and other Authorities

The Contractor shall note that the Employer may appoint other contractors to
carryout certain items of specialist, ancillary or other works. The contractor shall
afford any such other contractors, Employers own workmen or any other duly
A item
constituted authorities all reasonable opportunity to resource and execute their
works. The Contractor shall include for liaising with all such other contractors, direct
workmen or other authorities and for co-coordinating his works with

Special Requirements for Programmes of Progress Charts

A preliminary outline programme for carrying out the works shall be prepared by the
Contractor and submitted with the tender. Within 14 days upon receipt of Engineer's
B order to commence the work, the Contractor shall prepare a detailed programme in item
the manner as detailed in the specification for carrying out the works and shall
submit copies of the programme to the Engineer for his approval

This shall be accompanied by labour force monthly loading for each trade, including
C item
sub-contractors, supervisory staff, cash flow and details of materials procurement.

The programme shall be updated and expanded at such times as stated in the
specification and shall be submitted to the Engineer in monthly intervals. Two week
D look ahead programmes shall be Look ahead program shall contains with details of item
Plan and method he propose to employ. No works based on such proposals shall
proceed without the approval of Engineer

In addition to the above, the Contractor shall submit in a Monthly Progress Report
E item
showing all the details in accordance as specified in the

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 58
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Photographs

Each month during the progress of the works, the Contractor shall arrange at his
own expense the taking of progress photographs from viewpoints selected by the
Engineer sufficient to record progress at the appropriate stage of the work. Six
copies comprising 36 No. 100x75 mm and 6 No. 300 x 250 mm colour photographs
presented in a proper manner approved by the Engineer, together with negatives
D and electronic copy shall be handed to the Engineer for his retention. The item
photographs shall be properly documented with dates, details of the viewpoint and
location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written
permission. The Contractor shall provide suitable albums for the correct storage of
the above photographs as specified in the Specification.

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 59
BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Site Meetings

The Contractor will attend with adequate responsible representation to Site Meeting
A item
and all other meetings to which the Engineer has given instructions to attend.

The Contractor will further undertake to inform and present to attend meeting(s) any
B representative(s) for those sub-contractors, suppliers, etc., under his direct control, item
if so requested by the Engineer.

The Contractor will ensure that all meetings with sub-contractors are held just prior
C item
to the site meetings to ensure accurate reporting on progress, information, etc.

Climatic Condition

Daily maximum and minimum air temperature (including overnight) shall be included
D item
in the Daily Report

Number of hours per day in which works are prevented by inclement weather (flood,
E item
etc.).

Site Survey and Grid Levels

Before commencing excavation or site leveling operations, the Contractor shall


conduct a site survey, witnessed by the Engineer, related to a benchmark. Levels
F shall be taken at 5m intervals in both directions across the entire site which must be item
agreed with Engineer prior to commencing excavations or filling operations, all as
specified in the specification

Other Costs

Allow for all costs, expenses etc. details of which must be set out below & extended
separately by the contractor incurred in carrying out the requirements of the
G Contract and not otherwise included in this bill. All costs & expenses not entered item
hereinafter will be deemed to be included in the prices inserted elsewhere in this
Bill.

CARRIED TO COLLECTION PAGE N


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES

BILL NO-01/ 60
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

COLLECTION

BILL NO. 1 PRELIMINARIES

Page No. 1/1 ₦0.00

Page No. 1/2 ₦0.00

Page No. 1/3 ₦0.00

Page No. 1/4 ₦0.00

Page No. 1/5

Page No. 1/6

Page No. 1/7

Page No. 1/8

Page No. 1/9

Page No. 1/10

Page No. 1/11

Page No. 1/12

Page No. 1/13

Page No. 1/14

Page No. 1/15

Bill No.1 Preliminaries Carried to General Summary Page N

BILL NO-01/ 61
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

BILL No. 1

PRELIMINARIES

A10: PROJECT PARTICULARS


Name, nature and location
A
The work comprises four floor shopping complex with parking spaces and additional
three floor parking spaces . The overrall lenght of the building is 61.0m long x 58.8m
wide. The suspended slabs are constructred of reinforced concrete slab. 1 item
Floor finishes are generally vitrified ceramic tiles in lettable areas, Public area is granite
while the car park area is asphaltic concrete. Plaster of paris suspended ceiling and pop
screeded and painted suspended slabs.
Services consists mechanical and Electrical services to be carried out by nominated sub
contractors

External works consists of Hard & soft landscaping. The entire paved hardstanding. 1 item

Nature: Shopping complex


Location: Wuse district
Abuja.

B Name and addresses of Employer and Consultants

ARCHITECTS (hereinunder referred to as CA)


Twinlight Architects Limited
13 Morenikeji Avenue, Orogun, Ibadan

STRUCTURAL ENGINEER
PTL Project Ttowers Limited
26 christmas Street phase 4 Kubwa, Abuja

MECHANICAL & ELECTRICAL ENGINEERS


HDWAKS Engineering Services Limited
No.3 Mekambo Close, off Durban Street, off Ademola Adetokunbo Crescent, Wuse 2
Abuja

QUANTITY SURVEYORS
BILLSTEC ASSOCIATES .
SUITE 6, Develyn Place
60 Nouarchott Street, wuse zone 1, Abuja

BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES

Prelims Page 1 / 62
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)


THE PRINCIPAL CONTRACTOR: "The Contractor" 1 item

A PROJECT MANAGER: Billstec Associates 1 item

B "CONTRACT ADMINISTRATOR (hereinunder referred to as 'CA):


The Architect" 1 item

C "PLANNING SUPERVISOR:
The Architect" 1 item

D A20: THE CONTRACT /SUB-CONTRACT

E Form of contract

F JCT 80;1994 revision standard conditions

under seal 1 item

G Performance guarantee bond/collateral warranties/Advance payment bond

this shall be from approved Bank.


Only on special consideration shall an insurance bond or other types of bonds be
acceptable.

H Mobilization and demobilization

Mobilization of all supervisions, labours, plants, materials and equipments necessary for the
proper execution of the Works. 1 item

De-mobilization of all supervisions, labours, plants, materials and equipments necessary for the
proper execution of the Works 1 item

J EMPLOYER'S REQUIREMENTS: PROVISION, CONTENT AND USE OF DOCUMENTS

Employer's requirements or limitations

No part of the tender document shall be copied or use for any other purposes than for this
project without the written consent of the consultant (s) concerned

Fixed charge 1 item

K A32: EMPLOYER'S REQUIREMENTS: MANAGEMENT OF THE WORKS

Employer's requirements or limitations

the contractor shall be required to carry out test for all concrete work including an not
limited to cube tests (for 7, 14 and 28 days) after casting and re-bar test to determine
strength of each supplies to site.

L Testing of Materials

Include the following Provisional Sum of N500,000.00 500,000.00


for Testing of Materials

M Statutory charges
Include the Provisional Sum of N15,000,000.00 15,000,000.00
for Statutory/Stacking/Community Charges (Council) to be
expended directly by the client

CARRIED TO COLLECTION PAGE N 15,500,000.00

Prelims Page 1 / 63
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
Photographs
A

The contractor shall submit progress photograph in 5 sets on monthly basis with site
progress report on the basis approved by the Project Manager. The Contractor shall
arrange at his own expense the taking of progress photographs from viewpoints selected
by the Project Manager sufficient to record progress at the appropriate stage of the
work.The photographs shall be properly documented with dates, details of the viewpoint
and location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written permission.
The Contractor shall provide suitable albums for the correct storage of the above
photographs as specified in the Specification.

Time related charge 1 item 3,000,000.00 3,000,000.00

B Supervision of the works.

An English speaking qualified full time supervisor shall be required for the duration of the
contract period.Contractor shall allow for supervision and the site agent shall be replaced
with appropriate person within reasonable time as approved by the Project Manager

Fixed charge 1 item 7,000,000.00 7,000,000.00

C A34: EMPLOYER'S REQUIREMENTS: SECURITY /SAFETY /PROTECTION

Employer's requirements or limitations, details stated

D Maintain public and private roads

Time related charge 1 item 500,000.00 500,000.00

E Protection of work in all sections

Time related charge 1 item 500,000.00 500,000.00

G Maintain live services

Time related charge 1 item 653,859.95 653,859.95

H A35: EMPLOYER'S REQUIREMENTS: SPECIFIC LIMITATIONS ON METHOD


/SEQUENCE /TIMING/USE OF SITE

Employer's requirements or limitations, details stated

J
Design constraints; Contractors are advised to view the designs (Architectural, Structural
and Services) and allow here for complying with any constrain imposed on the work due
to the nature of the design, component materials and specifications.

Fixed charge 1 item -

K Method and sequence of work: Tenderers are advised to read through the "instruction to
persons tendering" and allow herein for any special obligation imposed on the
contractors on method and work sequence

L Access: This shall include maintaining of the existing road adjoining the site for the
duration of the work.

Time related charge 1 item -

CARRIED TO COLLECTION PAGE N 11,653,859.95

Prelims Page 1 / 64
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A
Use of the site; It is expected that the site will be used only for the purpose of the work.
The site shall not be for any other unrelated activities except with the express and written
permission of the Architect.

Fixed charge 1 item -

Working hours: This shall be between the hours of 7am to 5pm (Monday to Saturday).
Any additional working hour may be employed by the contractor for the purpose of
meeting work schedule and targets as laid down in the work program.
Any additional cost of fulfilling the contractors obligation in term of meeting program
targets should be allowed here.

Time related charge 1 item -

Overtime/Labour Fluctuation : Overtime claim will only be entertained where specifically


requested and ordered by the Architect to cover delays under clause 26.2.1 to 26.2.6 of
the contract conditions.
Fluctuation claim on labour shall NOT Entertained. The contractor is to make allowance
herein for claim to cover off-site work force partially employed on the work.

Fixed charge 1 item 2,000,000.00 2,000,000.00

D
EMPLOYER'S REQUIREMENTS: FACILITIES /TEMPORARY WORKS /SERVICES

E Employer's requirements or limitations, details stated

F Offices - site offices for use by the contractor for the project duration

Fixed charge 1 item 5,000,000.00 5,000,000.00

Time related charge 1 item 2,500,000.00 2,500,000.00

G Sanitary accommodation

Fixed charge 1 item 1,000,000.00 1,000,000.00

Time related charge 1 item 500,000.00 500,000.00

H Temporary fences, hoardings, screens and roofs


Provision of 6mm painted plywood hoarding 2.40m high with and including hardwood
timber support members approximately 280m
Fixed charge 1 item 2,000,000.00 2,000,000.00

Time related charge 1 item 500,000.00 500,000.00

CARRIED TO COLLECTION PAGE N 13,500,000.00

Prelims Page 1 / 65
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A Name boards (1 nr.)

The Contractor shall allow for the provision, erection and maintenance of necessary site
notice board as required by the Engineer to display image of the project, project name,
the Employer's name and names of all Consultants associated with the Project.The sign
boards shall be complete weather durable with all necessary foundations, supports,
framing, painting and sign writing in English denoting the title of the project and name of
the Employer, Consultants and contractors with their respective addresses and building
permit details. The Contractor shall provide all details of the sign board to the Engineer
for his approval before any work is put in hand and to enable erection to commence in the
early stages of the contract.The Contractor shall provide sufficient lighting to sign boards
which includes power supply and lighting fixture.The Contractor shall clean, maintain and
at the completion of the Contract remove the sign board, supports and foundations.Any
authority payments
Fixed charge 1 item 500,000.00 500,000.00

Time related charge 1 item 400,000.00 400,000.00

B A37: EMPLOYER'S REQUIREMENTS: OPERATION /MAINTENANCE OF THE


FINISHED BUILDING

C Employer's requirements or limitations

The contractor shall be expected to maintain and keep the building free of defect for six
months duration of defect liability period.

Fixed charge 1 item 1,500,000.00 1,500,000.00

D A40: CONTRACTOR'S GENERAL COST ITEMS: MANAGEMENT AND STAFF

Management and staff

General management staff including site supervisors, site clerk and other site
management staff.

Fixed charge 1 item 10,000,000.00 10,000,000.00

E A41: CONTRACTOR'S GENERAL COST ITEMS: SITE ACCOMMODATION

Site accommodation

shall include site office and sanitary rooms for consultants (2nr offices) The Contractor
shall supply and place Port-a- cabins, comprising of carpet floors and all other finishes as
stated in the specification.The Contractor shall obtain power, water, drainage.The
Contractor shall supply minimum of following new furniture and other items for each office
(Contractor shall provide warranty card or slip for all Electronic items)complete with air-
conditioning, office desk and drawers and drawing tables, Photocopy machine

Fixed charge 1 item 3,500,000.00 3,500,000.00

Time related charge 1 item 1,500,000.00 1,500,000.00

one air-conditioned large meeting room to contain a minimum of 15 persons within the
existing structure complete with comfortable meeting table and chairs and the contractor
shall provide for one wireless fixed digital telephone for use by consultants and provide
for refreshments (finger meals and drinks) for every site meetings (ONCE monthly)

Fixed charge 1 item 5,000,000.00 5,000,000.00

Time related charge 1 item 2,500,000.00 2,500,000.00

CARRIED TO COLLECTION PAGE N 24,900,000.00

Prelims Page 1 / 66
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
CONTRACTOR'S GENERAL COST ITEMS: SERVICES AND FACILITIES

Services and facilities

A Temporary Power including standby generator for general use by main contractor and
subcontractors for the duration of the contract.

Fixed charge 1 item 3,000,000.00 3,000,000.00

Time related charge 1 item 4,000,000.00 4,000,000.00

B Temporary Water for the works including for general use by main contractor and sub -
contractors for the duration of the contract.

Fixed charge 1 item 2,000,000.00 2,000,000.00

Time related charge 1 item 500,000.00 500,000.00

C Telephone and administration

Fixed charge 1 item 200,000.00 200,000.00

Time related charge 1 item 500,000.00 500,000.00

D Safety, health and welfare

Fixed charge 1 item 2,500,000.00 2,500,000.00

Time related charge 1 item 500,000.00 500,000.00

F Storage of materials including lock-up spaces for specialist sub-contractors

Fixed charge 1 item 2,000,000.00 2,000,000.00

Time related charge 1 item 500,000.00 500,000.00

G Rubbish disposal

Time related charge 1 item 3,500,000.00 3,500,000.00

H Cleaning

Time related charge 1 item 5,000,000.00 5,000,000.00

J Protection of work in all sections

Time related charge 1 item 500,000.00 500,000.00

CARRIED TO COLLECTION PAGE N 24,700,000.00

Prelims Page 1 / 67
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A Site Security including day and night security staff.

Time related charge 1 item 7,000,000.00 7,000,000.00

B Small plant and tools


Provide for all necessary small plants and tools for the proper execution and completion of the
Works and also Provide all necessary plants required for specific trades for the proper execution
and completion of the contract.

Fixed charge 1 item 1,000,000.00 1,000,000.00

Time related charge 1 item 500,000.00 500,000.00

C A43: CONTRACTOR'S GENERAL COST ITEMS: MECHANICAL PLANT

Mechanical plant

All plant required for effective executive and completion of the project .This shall include
but not limited to mobile and fixed cranes , excavators, earthmoving equipment, concrete
mixers (mobile and fixed ), standing and mobile scaffolds and other equipment and plant
that the contractor shall allow necessary for keeping ground excavation free of general
water for the entire period of substructure works as described in the description of works .
(Note: The tower crane should not be installed in permanent structure)

Fixed charge 1 item 40,000,000.00 40,000,000.00

Time related charge 1 item 5,000,000.00 5,000,000.00

Dimensions in descriptions
All dimensions in the descriptions are in millimeters unless otherwise indicated (i.e. 100
girth means 100mm girth)

D Materials supplied by the client

The client may be supplying some of the materials for which P. C. rates are indicated in
the bills of quantities and some materials listed in the basic price list and are to be
incorporated into the works.
The contractor is implored to allow herein for receiving and storing such materials before
incorporation into the works.

The amount allow herein or somewhere else in this bill shall be deemed to cover all
incidental expenses in connection with receiving and keeping in secured store up to
incorporation into the works including insurance of such materials and goods

The amount allowed within the description in the bills of quantities as 'PC supply' are the
basic rates of such materials delivered to site. The client reserves the right to supply such
materials and where-ever such is the case these rates shall be the basis of adjustment of
the measured work executed by the contractor.
No claim for loss of profit or incidental expenses whatsoever shall be entertained on such
adjustment.

E Project Supervision Expenses


500,000.00
Include the Provisional Sum of N500.000.00 for - Reimbursable, Printing, Communication,
Correspondence delivery etc to be expended as directed by the Architect.

CARRIED TO COLLECTION PAGE N 54,000,000.00

Prelims Page 1 / 68
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)
A A55: DAYWORKS
Include the following provisional sums

For work ordered to be paid for on a daywork basis in accordance with JCT'80 Clause
13.5.4.1 and 13.5.4.2

(the Provisional hours, sums and percentage additions are to be considered as part of the
overall contingency sum)

SECTION A: the following schedule of Dayworks shall be as defined in "Definition of


prime cost of daywork carried out under a building contract" last before issued by the
Federation of Building and Civil Engineering Contractors. (percentages are to be
extended in the cash column)

LABOUR: (as defined in Section 3) - (percentages are to be extended in the cash


column)

add for incidental costs, overheads and profit as defined in section 6

MATERIALS AND GOODS: (as defined in Section 4) - (percentages are to be extended


in the cash column)

add for incidental costs, overheads and profit as defined in section 6

PLANT: (as defined in Section 5) - (percentages are to be extended in the cash column)
(plant shall be charged at the market rates current at the time the work is executed)

SECTION B: (daywork ordered to be carried out after the date of commencement of the
defects liability period) - the following schedule of Dayworks shall be as defined in section
1 except that sub-clause 1:2 referring to the defects liability period shall be deemed to be
deleted (percentages are to be extended in the cash column)

LABOUR: (as defined in Section 3) - include the provisional sum for skilled labour (insert
all-in rate against provisional hours shown and extend to cash column)

add for incidental costs, overheads and profit as defined in section 6

LABOUR: (as defined in Section 3) - include the provisional sum for un-skilled labour
(insert all-in rate against provisional hours shown and extend to cash column)

add for incidental costs, overheads and profit as defined in section 6

CARRIED TO COLLECTION PAGE N -

Prelims Page 1 / 69
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

Preliminaries 1/1 -

Preliminaries 1/2 15,500,000.00

Preliminaries 1/3 11,653,859.95

Preliminaries 1/4 13,500,000.00

Preliminaries 1/5 24,900,000.00

Preliminaries 1/6 24,700,000.00

Preliminaries 1/7 54,000,000.00

Preliminaries 1/8

Preliminaries
Carried to summary 144,253,859.95

Prelims Page 1 / 70
PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount

BILL NR.2: MAIN BUILDING


SUBSTRUCTURE

GROUNDWORK

INFORMATION [All Provisional]

Nature and location of the work

The work in this section comprises:

(i) Excavations, trenches, pits and the likes, concrete work,


waterproofing, earth filling, and all other ancillary works associated with
strip/pad foundation up to and including ground floor slab. (ii)
All concrete works are provisional quantities in this section
D20: EXCAVATING AND FILLING
Excavating

Top soil for preservation

A average 150mm deep 3916 m2 138.00 540,408.00

Trenches width exceeding 300mm

B maximum depth not exceeding 1500mm; commencing surface 150mm 656 m3 2,048.00 1,343,029.25
below existing ground level

Pits; for isolated concrete foundation; 110nr.

C maximum depth not exceeding 2000mm; commencing surface 150mm 2475 m3 2,048.00 5,068,247.04
below existing ground level

D Ditto lift shaft not exceeding 2000mm deep 87 m3 2,048.00 178,560.00

Working space allowance to excavation; including additional earthwork


support, disposal and backfilling with selected excavated material

E pits 1916 m3 2,048.00 3,923,968.00

F Pits in lift shaft 67 m3 2,048.00 137,216.00


5201
Disposal of excavated material

G off site 2874 m3 425.00 1,221,321.40

To collection : 12,412,749.68

BILL NR.2: MAIN BUILDING PAGE 2/71


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Excavated material arising from excavation

Filling to excavation

A average thickness exceeding 0.25m 2327 m3 492.00 1,144,882.08

Selected excavated laterite material obtained from offsite borrow pits

Filling to excavation; depositing in layers 150mm maximum thickness

B average thickness 350mm 1254 m3 5,236.00 6,568,038.40

Hardcore to be obtained from off-site;

Filling to make up levels; depositing in layers 150mm maximum thickness

C average thickness 300mm 1075 m3 10,500.00 11,289,600.00

Termite treatmment

D dieldrex 20" or other equal and approved anti-termite solution to sides 6552 m2 173.00 1,133,482.16
and bottom of excavtions

E Keeping excavation free from general and ground water item 250,000.00

F Allow for breaking rock /existing concrete foundation item 350,000.00

E IN - SITU CONCRETE

E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Plain in-situ concrete; mix 1:10, 20 aggregate;50mm blinding


Column bases
G not exceeding 150mm thick; poured on earth surfaces 80 m3 68,750.00 5,488,312.50

H Ditto in strip foundation 27 m3 68,750.00 1,878,525.00

J Diito in lift shaft base 3 m3 68,750.00 193,359.38

Under ground slabs

K Sand blinding not exceeding 150mm thick; poured on consolidated 538 m3 4,577.00 2,460,595.20
hardcore surfaces

To collection : 30,756,794.72

BILL NR.2: MAIN BUILDING PAGE 2/72


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Plain in-situ concrete; B.S.5328, designed mix C20, 20 aggregate,


minimum cement content 310 kg/m3; vibrated

Isolated foundations; poured on blinding

A generally; 150 - 450mm thick 126 m3 85,625.00 10,762,240.50

Reinforced in-situ concrete; B.S.5328, designed mix C25, 20 aggregate,


minimum cement content 302.5 kg/m3; vibrated

Isolated foundations; column bases

B generally; 250 - 500mm thick 1564 m3 85,625.00 133,948,068.13

Reinforced in-situ concrete; B.S.5328, designed mix C25, 20 aggregate,


minimum cement content 302.5 kg/m3; vibrated

Columns
C generally 45 m3 85,625.00 3,812,667.19

Beds
D ground slabs thickness 150-450mm thick 538 m3 85,625.00 46,032,000.00

E Steps 32 m3 85,625.00 2,774,250.00

Lift Shaft Wall


F in foundation 6 m3 85,625.00 491,457.53

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to produce plain surface:


Sides of foundations : plain vertical.

G column bases; height 500 - 1200mm high 1330 m2 5,000.00 6,648,400.00

Sides and edges of beds : plain vertical.

H ground slabs; height not exceeding 250mm 240 m 1,250.00 300,000.00

J Ditto in riser 150mm 960 m 750.00 720,000.00

Columns; isolated
K regular shaped; rectangular 374 m2 5,000.00 1,870,650.00

Lift Shaft Wall


L in foundation 50 m2 5,000.00 249,550.00

To collection : 207,609,283.34

BILL NR.2: MAIN BUILDING PAGE 2/73


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel


(TMT)
Straight and bent

Column bases
A H16 44.89 t 800,000.00 35,913,703.10

B H20 69.11 t 800,000.00 55,291,841.92

Columns

C H10 (stirrups) 2.91 t 800,000.00 2,326,883.10

D H16 0.34 t 800,000.00 272,808.35

E H20 4.95 t 800,000.00 3,962,667.52

F H25 11.22 t 800,000.00 8,979,152.00

Lift base
G H16 4.59 t 800,000.00 3,675,334.66

Lift shaft
Ground floor -1st floor
H H16 1.48 t 800,000.00 1,182,169.50

J H10 0.18 t 800,000.00 146,527.92

Reinforcement fabric; B.S.4483, hard drawn plain round steel; welded


6mm thick Reference A142, weight 2.22kg/m2 measured net with
minimum 300mm side laps; 300mm end laps

K 1 layer; laid on top generally 3584 m2 1,212.00 4,343,808.00

MASONRY
F10: BLOCK WALLING

Stone dust hollow blockwork, bedded and jointed in cement and sand
mortar (1:6)

Walls; filled solid with concrete grade 15

L 230mm thick; stretcher bond 2137 m2 7,621.00 16,287,601.20

Expansion Joint
M Expansion joint 20mm thick ploystrene naked panel 180 m2 676.00 121,680.00

To collection : 132,504,177.26

BILL NR.2: MAIN BUILDING PAGE 2/74


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

BUILDING FABRIC SUNDRIES

P10: SUNDRY INSULATION/ PROOFING WORK/ FIRE STOPS

Polythene sheeting, Visqueen 1000 gauge; 250 micron

Plain areas

A horizontal; laid loose 3584 m2 180.00 645,120.00

ADDITIONAL WORK IN SUBSTRUCTURE

Allow a provisional sum of N5,000,000.00 (Five million Naira Only) for


B unforseen additional work in substructure to be expended as may be sum 5,000,000.00
directed by the Architect
To collection : 5,645,120.00

Collection

SUBSTRUCTURE.

Page 2/1 12,412,749.68

Page 2/2 30,756,794.72

Page 2/3 207,609,283.34

Page 2/4 132,504,177.26

Page 2/5 5,645,120.00

To Main Building Collection : 388,928,125.00

BILL NR.2: MAIN BUILDING PAGE 2/75


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
FRAMES AND UPPER FLOORS
INFORMATION
Nature and location of the work
The work in this section comprises

(i.) Reinforced concrete columns, beams, suspended floor slabs and


associated works.
(ii.) The Contractor is however referred to Structural Engineer's drawings
for details and scope of the Works.
E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE
Reinforced in-situ concrete; B.S.5328, 40Kn/mm2 designed Mix 35
(35Mpa), 20 aggregate, minimum cement content 375 kg/m3; vibrated
and maximum water cement ratio of 0.43 (Ready mixed Concrete -RMC)

Slabs; suspended floor n.e 175mm thick


A 1st floor slab 561 cu.m 85,625.00 48,050,609.37

B 2nd floor slab 561 cu.m 85,625.00 48,050,609.37

C 3rd floor slab 561 cu.m 85,625.00 48,050,609.37

D 4th floor slab 393 cu.m 85,625.00 33,667,750.00

E 5th floor slab 367 cu.m 85,625.00 31,407,250.00

F 6th floor slab 367 cu.m 85,625.00 31,407,250.00

Beams
G 1st floor beam 229 cu.m 85,625.00 19,635,043.36

H 2nd floor beam 229 cu.m 85,625.00 19,635,043.36

J 3rd floor beam 229 cu.m 85,625.00 19,635,043.36

K 4th floor beam 211 cu.m 85,625.00 18,058,066.33

L 5th floor beam 147 cu.m 85,625.00 12,575,326.33

M 6th floor beam 147 cu.m 85,625.00 12,575,326.33

Lift Shaft Wall


N Ground floor -1st floor 10 cu.m 85,625.00 839,296.42

P 1st floor -2nd floor 10 cu.m 85,625.00 839,296.42

Q 2nd floor - 3rd floor 10 cu.m 85,625.00 839,296.42

R 3rd floor - 4th floor 10 cu.m 85,625.00 839,296.42

S 4th floor - 5th floor 10 cu.m 85,625.00 839,296.42

T 5th floor - 6th floor 10 cu.m 85,625.00 839,296.42

U 6th floor -roof level 12 cu.m 85,625.00 1,031,952.67

To collection : 348,815,658.39

BILL NR.2: MAIN BUILDING PAGE 2/76


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Column
A Ground floor -1st floor 76 cu.m 85,625.00 6,481,534.22

B 1st floor -2nd floor 76 cu.m 85,625.00 6,481,534.22

C 2nd floor - 3rd floor 66 cu.m 85,625.00 5,654,557.27

D 3rd floor - 4th floor 52 cu.m 85,625.00 4,456,832.63

E 4th floor - 5th floor 37 cu.m 85,625.00 3,190,657.22

F 5th floor - 6th floor 37 cu.m 85,625.00 3,190,657.22

G 6th floor -roof level 37 cu.m 85,625.00 3,190,657.22


4455
E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to produce plain surface:


Horizontal soffit of suspended slab/Cantilever;
H 1st floor slab 3381 m2 5,000.00 16,905,000.00

J 2nd floor slab 3381 m2 5,000.00 16,905,000.00

K 3rd floor slab 3381 m2 5,000.00 16,905,000.00

L 4th floor slab 2272 m2 5,000.00 11,360,000.00

M 5th floor slab 2096 m2 5,000.00 10,480,000.00

N 6th floor slab 2096 m2 5,000.00 10,480,000.00


16607
Edges of suspended slab; plain vertical
height not exceeding 250mm
P 1st floor slab 398 m 1,250.00 497,500.00

Q 2nd floor slab 398 m 1,250.00 497,500.00

R 3rd floor slab 398 m 1,250.00 497,500.00

S 4th floor slab 322 m 1,250.00 402,500.00

T 5th floor slab 317 m 1,250.00 396,250.00

U 6th floor slab 317 m 1,250.00 396,250.00


2150

To collection : 118,368,929.98

BILL NR.2: MAIN BUILDING PAGE 2/77


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Beam

regular shaped; height to soffit exceeding 3000mm (sides)


A 1st floor beam 2036 m2 5,000.00 10,180,825.00

B 2nd floor beam 2036 m2 5,000.00 10,180,825.00

C 3rd floor beam 2036 m2 5,000.00 10,180,825.00

D 4th floor beam 1845 m2 5,000.00 9,223,675.00

E 5th floor beam 1135 m2 5,000.00 5,676,075.00

F 6th floor beam 1135 m2 5,000.00 5,676,075.00

10224
Columns
regular shaped; rectangular

G Ground floor -1st floor 623 m2 5,000.00 3,112,530.00

H 1st floor -2nd floor 623 m2 5,000.00 3,112,530.00

J 2nd floor - 3rd floor 602 m2 5,000.00 3,007,980.00

K 3rd floor - 4th floor 492 m2 5,000.00 2,458,455.00

L 4th floor - 5th floor 294 m2 5,000.00 1,470,712.50

M 5th floor - 6th floor 294 m2 5,000.00 1,470,712.50

N 6th floor -roof level 294 m2 5,000.00 1,470,712.50


3221
Lift Shaft Wall
P Ground floor -1st floor 85 m2 5,000.00 426,174.00

Q 1st floor -2nd floor 85 m2 5,000.00 426,174.00

R 2nd floor - 3rd floor 85 m2 5,000.00 426,174.00

S 3rd floor - 4th floor 85 m2 5,000.00 426,174.00

T 4th floor - 5th floor 85 m2 5,000.00 426,174.00

U 5th floor - 6th floor 85 m2 5,000.00 426,174.00

V 6th floor -roof level 100 m2 5,000.00 501,174.00

To collection : 70,280,150.50

BILL NR.2: MAIN BUILDING PAGE 2/78


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
E30: REINFORCEMENT FOR IN-SITU CONCRETE
Reinforcement bars; B.S.4449, hot rolled deformed high yield steel
(TMT)
Straight and bent
Suspended slabs/cantilever
1st floor slab
A H12 49.51 t 800,000.00 39,609,214.20

B H12 (haunch bench) 4.95 t 800,000.00 3,960,921.42

C H10 6.92 t 800,000.00 5,535,514.00

2nd floor slab


D H12 49.51 t 800,000.00 39,609,214.20

E H12 (haunch bench) 4.95 t 800,000.00 3,960,921.42

F H10 6.92 t 800,000.00 5,535,514.00

3rd floor slab


G H12 49.51 t 800,000.00 39,609,214.20

H H12 (haunch bench) 4.95 t 800,000.00 3,960,921.42

J H10 6.92 t 800,000.00 5,535,514.00

4th floor slab


K H12 31.95 t 800,000.00 25,560,223.80

L H12 (haunch bench) 3.20 t 800,000.00 2,556,022.38

M H10 5.31 t 800,000.00 4,245,870.96

5th floor slab


N H12 31.95 t 800,000.00 25,560,223.80

P H12 (haunch bench) 3.20 t 800,000.00 2,556,022.38

Q H10 3.67 t 800,000.00 2,934,618.75

6th floor slab


R H12 31.95 t 800,000.00 25,560,223.80

S H12 (haunch bench) 3.20 t 800,000.00 2,556,022.38

T H10 3.67 t 800,000.00 2,934,618.75


302.23
Beam
1st floor beam
U H25 27.93 t 800,000.00 22,340,265.85

V H20 7.30 t 800,000.00 5,841,579.74

W H16 10.56 t 800,000.00 8,448,722.90

X H10 9.23 t 800,000.00 7,383,023.86

To collection : 285,794,388.23

BILL NR.2: MAIN BUILDING PAGE 2/79


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

2nd floor beam


A H25 27.93 t 800,000.00 22,340,265.85

B H20 7.30 t 800,000.00 5,841,579.74

C H16 10.56 t 800,000.00 8,448,722.90

D H10 9.23 t 800,000.00 7,383,023.86

3rd floor beam


E H25 27.93 t 800,000.00 22,340,265.85

F H20 7.30 t 800,000.00 5,841,579.74

G H16 10.56 t 800,000.00 8,448,722.90

H H10 9.23 t 800,000.00 7,383,023.86

4th floor beam


J H25 29.04 t 800,000.00 23,231,089.00

K H20 6.39 t 800,000.00 5,115,945.86

L H16 8.04 t 800,000.00 6,428,299.24

M H10 9.34 t 800,000.00 7,471,739.86

5th floor beam


N H25 27.95 t 800,000.00 22,360,616.95

P H20 3.97 t 800,000.00 3,178,422.46

Q H16 3.43 t 800,000.00 2,743,113.18

R H10 5.90 t 800,000.00 4,716,866.95

6th floor beam


S H25 27.95 t 800,000.00 22,360,616.95

T H20 3.97 t 800,000.00 3,178,422.46

U H16 3.43 t 800,000.00 2,743,113.18

V H10 5.90 t 800,000.00 4,716,866.95


300.36
Column
Ground floor -1st floor
W H25 11.22 t 800,000.00 8,979,152.00

X H20 4.95 t 800,000.00 3,962,667.52

Y H16 0.34 t 800,000.00 272,808.35

Z H10 3.78 t 800,000.00 3,024,948.04

To collection : 212,511,873.65

BILL NR.2: MAIN BUILDING PAGE 2/80


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

1st floor -2nd floor


A H25 8.70 t 800,000.00 6,956,376.00

B H20 4.24 t 800,000.00 3,394,316.80

C H16 1.50 t 800,000.00 1,202,377.52

D H10 3.77 t 800,000.00 3,019,175.72

2nd floor - 3rd floor


E H25 8.02 t 800,000.00 6,413,680.00

F H20 2.80 t 800,000.00 2,241,827.84

G H16 2.31 t 800,000.00 1,849,034.34

H H10 3.69 t 800,000.00 2,954,076.87

3rd floor - 4th floor


J H25 7.71 t 800,000.00 6,167,000.00

K H20 2.31 t 800,000.00 1,847,139.84

L H16 1.48 t 800,000.00 1,182,169.50

M H10 3.67 t 800,000.00 2,933,873.78

4th floor - 5th floor


N H25 1.48 t 800,000.00 1,184,064.00

P H20 1.34 t 800,000.00 1,073,551.36

Q H16 2.45 t 800,000.00 1,960,178.48

R H10 3.67 t 800,000.00 2,933,873.78

5th floor - 6th floor


S H25 0.86 t 800,000.00 690,704.00

T H20 1.34 t 800,000.00 1,073,551.36

U H16 2.70 t 800,000.00 2,162,258.74

V H10 3.67 t 800,000.00 2,933,873.78

6th floor - roof level


W H25 0.86 t 800,000.00 690,704.00

X H20 1.34 t 800,000.00 1,073,551.36

Y H16 2.70 t 800,000.00 2,162,258.74

Z H10 3.67 t 800,000.00 2,933,873.78


96.59
To collection : 61,033,491.60

BILL NR.2: MAIN BUILDING PAGE 2/81


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Lift shaft
Ground floor -1st floor
A H16 1.31 t 800,000.00 1,047,786.13

B H10 0.29 t 800,000.00 230,103.10


1st floor -2nd floor
C H16 1.31 t 800,000.00 1,047,786.13

D H10 0.29 t 800,000.00 230,103.10


2nd floor -3rdfloor
E H16 1.31 t 800,000.00 1,047,786.13

F H10 0.29 t 800,000.00 230,103.10


3rd floor - 4th floor
G H16 1.31 t 800,000.00 1,047,786.13

H H10 0.29 t 800,000.00 230,103.10


4th floor - 5th floor
J H16 1.31 t 800,000.00 1,047,786.13

K H10 0.29 t 800,000.00 230,103.10


5th floor - 6th floor
L H16 1.23 t 800,000.00 984,636.05

M H10 0.29 t 800,000.00 230,103.10


6th floor - roof level
N H16 1.32 t 800,000.00 1,057,890.14

P H10 0.29 t 800,000.00 230,103.10

Lift slab
R H12 0.24 t 800,000.00 192,000.00
11.36
To collection : 9,084,178.55
Collection
FRAME & UPPER FLOOR
Page 2/6 348,815,658.39

Page 2/7 118,368,929.98

Page 2/8 70,280,150.50

Page 2/9 285,794,388.23

Page 2/10 212,511,873.65

Page 2/11 61,033,491.60

Page 2/12 9,084,178.55

To Main Building Collection : 1,105,888,670.91

BILL NR.2: MAIN BUILDING PAGE 2/82


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
STAIRCASES
INFORMATION
Nature and location of the work
The work in this section comprises

(i.) Reinforced concrete staircases and associated works.


(ii.) The Contractor is however referred to Structural Engineer's drawings
for details and scope of the Works.

E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced in-situ concrete; B.S.5328, 40Kn/mm2 designed Mix 35


(35Mpa), 20 aggregate, minimum cement content 375 kg/m3; vibrated
and maximum water cement ratio of 0.43 (Ready mixed Concrete -RMC)
Landing

A Ground floor - 1st floor 1.3 m3 85,625.00 110,970.00

B 1st floor - 2nd floor 1.3 m3 85,625.00 110,970.00

C 2nd Floor - 3rd floor 1.3 m3 85,625.00 110,970.00

D 3rd floor - 4th floor 0.4 m3 85,625.00 36,990.00

E 4th floor - 5th floor 0.4 m3 85,625.00 36,990.00

F 5th floor - 6th floor 0.4 m3 85,625.00 36,990.00

Slopping soffit of stairs


G Ground floor - 1st floor 3.8 m3 85,625.00 323,662.50

H 1st floor - 2nd floor 3.8 m3 85,625.00 323,662.50

J 2nd Floor - 3rd floor 3.8 m3 85,625.00 323,662.50

K 3rd floor - 4th floor 1.3 m3 85,625.00 107,887.50

L 4th floor - 5th floor 1.3 m3 85,625.00 107,887.50

M 5th floor - 6th floor 1.3 m3 85,625.00 107,887.50

Beams
N Ground floor - 1st floor 3.7 m3 85,625.00 320,734.13

P 1st floor - 2nd floor 2.8 m3 85,625.00 237,506.63

Q 2nd Floor - 3rd floor 2.8 m3 85,625.00 237,506.63

R 3rd floor - 4th floor 1.4 m3 85,625.00 116,158.88

S 4th floor - 5th floor 1.4 m3 85,625.00 116,158.88

T 5th floor - 6th floor 1.4 m3 85,625.00 116,158.88

To collection : 2,882,754.00

BILL NR.2: MAIN BUILDING PAGE 2/83


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Steps
A Ground floor - 1st floor 1.7 m3 85,625.00 145,648.13

B 1st floor - 2nd floor 1.7 m3 85,625.00 145,648.13

C 2nd Floor - 3rd floor 1.7 m3 85,625.00 145,648.13

D 3rd floor - 4th floor 0.6 m3 85,625.00 48,549.37

E 4th floor - 5th floor 0.6 m3 85,625.00 48,549.37

F 5th floor - 6th floor 0.6 m3 85,625.00 48,549.37


40.47
E20: FORMWORK FOR IN-SITU CONCRETE
Sawn formwork to produce plain surface to
Horizontal soffit of landing
Slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m
G Ground floor - 1st floor 9 m2 5,000.00 43,200.00

H 1st floor - 2nd floor 9 m2 5,000.00 43,200.00

J 2nd Floor - 3rd floor 9 m2 5,000.00 43,200.00

K 3rd floor - 4th floor 3 m2 5,000.00 14,400.00

L 4th floor - 5th floor 3 m2 5,000.00 14,400.00

M 5th floor - 6th floor 3 m2 5,000.00 14,400.00


25.92
Slopping soffit of stairs
slope exceeding 15 degrees
N Ground floor - 1st floor 25 m2 5,000.00 126,000.00

P 1st floor - 2nd floor 25 m2 5,000.00 126,000.00

Q 2nd Floor - 3rd floor 25 m2 5,000.00 126,000.00

R 3rd floor - 4th floor 8 m2 5,000.00 42,000.00

S 4th floor - 5th floor 8 m2 5,000.00 42,000.00

T 5th floor - 6th floor 8 m2 5,000.00 42,000.00


101
Stair beams
slope exceeding 15 degrees
U Ground floor - 1st floor 32 m2 5,000.00 161,985.00

V 1st floor - 2nd floor 29 m2 5,000.00 145,785.00

W 2nd Floor - 3rd floor 29 m2 5,000.00 145,785.00

X 3rd floor - 4th floor 10 m2 5,000.00 48,595.00

Y 4th floor - 5th floor 10 m2 5,000.00 48,595.00

Z 5th floor - 6th floor 10 m2 5,000.00 48,595.00

To collection : 1,858,732.50

BILL NR.2: MAIN BUILDING PAGE 2/84


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Edges of landing
not exceeding 250mm wide
A Ground floor - 1st floor 22 m 1,250.00 27,000.00

B 1st floor - 2nd floor 22 m 1,250.00 27,000.00

C 2nd Floor - 3rd floor 22 m 1,250.00 27,000.00

D 3rd floor - 4th floor 7 m 1,250.00 9,000.00

E 4th floor - 5th floor 7 m 1,250.00 9,000.00

F 5th floor - 6th floor 7 m 1,250.00 9,000.00


64.8
Steps; edges of risers, plain vertical
not exceeding 150mm wide
G Ground floor - 1st floor 76 m 1,250.00 94,500.00

H 1st floor - 2nd floor 76 m 1,250.00 94,500.00

J 2nd Floor - 3rd floor 76 m 1,250.00 94,500.00

K 3rd floor - 4th floor 25 m 1,250.00 31,500.00

L 4th floor - 5th floor 25 m 1,250.00 31,500.00

M 5th floor - 6th floor 25 m 1,250.00 31,500.00


302
Raking string of steps
width not exceeding 300mm
N Ground floor - 1st floor 21 m 1,500.00 31,500.00

P 1st floor - 2nd floor 21 m 1,500.00 31,500.00

Q 2nd Floor - 3rd floor 21 m 1,500.00 31,500.00

R 3rd floor - 4th floor 7 m 1,500.00 10,500.00

S 4th floor - 5th floor 7 m 1,500.00 10,500.00

T 5th floor - 6th floor 7 m 1,500.00 10,500.00


63

To collection : 612,000.00
No Item Description Qty Unit Rate Amount

BILL NR.2: MAIN BUILDING PAGE 2/85


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


E30: REINFORCEMENT FOR IN-SITU CONCRETE
Reinforcement bars; B.S.4449, hot rolled deformed high yield steel
(TMT-TIGER)
Straight and bent
Stairs
Ground floor - 1st floor
D H20 0.16 t 800,000.00 125,510.78

E H16 2.18 t 800,000.00 1,745,215.61


1st floor - 2nd floor
F H20 0.16 t 800,000.00 125,510.78

G H16 2.18 t 800,000.00 1,745,215.61


2nd Floor - 3rd floor
H H20 0.16 t 800,000.00 125,510.78

J H16 2.18 t 800,000.00 1,745,215.61


3rd floor - 4th floor
K H20 0.16 t 800,000.00 125,510.78

L H16 2.18 t 800,000.00 1,745,215.61


4th floor - 5th floor
M H20 0.16 t 800,000.00 125,510.78

N H16 2.18 t 800,000.00 1,745,215.61


5th - 6th floor
P H20 0.16 t 800,000.00 125,510.78

Q H16 2.18 t 800,000.00 1,745,215.61


14.03

To collection : 11,224,358.37

BILL NR.2: MAIN BUILDING PAGE 2/86


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
L31 METAL BALUSTRADES
Stainless steel handrailing bolted, with connector and all necessary
accessories
A Ground floor - 1st floor 21 m 85,250.00 1,790,250.00

B 1st floor - 2nd floor 27 m 85,250.00 2,301,750.00

C 2nd Floor - 3rd floor 27 m 85,250.00 2,301,750.00

D 3rd floor - 4th floor 9 m 85,250.00 767,250.00

E 4th floor - 5th floor 9 m 85,250.00 767,250.00

F 5th floor - 6th floor 9 m 85,250.00 767,250.00

SURFACE FINISHES 102


M10: SAND CEMENT/ CONCRETE/ SCREEDS/TOPPINGS
Mortar, cement and sand (1:4) beds and backings
30mm work to floor on concrete base
Landing

G Ground floor - 1st floor 9 m2 2,365.00 20,433.60

H 1st floor - 2nd floor 9 m2 2,365.00 20,433.60

J 2nd Floor - 3rd floor 9 m2 2,365.00 20,433.60

K 3rd floor - 4th floor 3 m2 2,365.00 6,811.20

L 4th floor - 5th floor 3 m2 2,365.00 6,811.20

M 5th floor - 6th floor 3 m2 2,365.00 6,811.20

To collection : 8,777,234.40

BILL NR.2: MAIN BUILDING PAGE 2/87


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
25mm work to treads on concrete base
width 300mm
A Ground floor - 1st floor 72 m 605.00 43,560.00

B 1st floor - 2nd floor 72 m 605.00 43,560.00

C 2nd Floor - 3rd floor 72 m 605.00 43,560.00

D 3rd floor - 4th floor 24 m 605.00 14,520.00

E 4th floor - 5th floor 24 m 605.00 14,520.00

F 5th floor - 6th floor 24 m 605.00 14,520.00

12mm work to plain risers on concrete base


height 150mm
L Ground floor - 1st floor 76 m 156.00 11,793.60

M 1st floor - 2nd floor 76 m 156.00 11,793.60

N 2nd Floor - 3rd floor 76 m 156.00 11,793.60

P 3rd floor - 4th floor 25 m 156.00 3,931.20

Q 4th floor - 5th floor 25 m 156.00 3,931.20

R 5th floor - 6th floor 25 m 156.00 3,931.20

To collection : 221,414.40

BILL NR.2: MAIN BUILDING PAGE 2/88


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
12mm work to skirting on wall
height 100mm
A Ground floor - 1st floor 43 m 104.00 4,446.00

B 1st floor - 2nd floor 43 m 104.00 4,446.00

C 2nd Floor - 3rd floor 43 m 104.00 4,446.00

D 3rd floor - 4th floor 14 m 104.00 1,482.00

E 4th floor - 5th floor 14 m 104.00 1,482.00

F 5th floor - 6th floor 14 m 104.00 1,482.00

M40: STONE/ CONCRETE/ QUARRY/ CERAMIC TILING/MOSAIC


Supply and install
Nigeria Granite floor tiles;(Champne silver) 3 joints systematic layout,
bedding in 10 cement mortar (1:4); including pointing.

600mm x 600mm x 15mm thick to floors on cement and sand base;


level to falls only not exceeding 15 degrees from horizontal
Landing
L Ground floor - 1st floor 9 m2 16,500.00 142,560.00

M 1st floor - 2nd floor 9 m2 16,500.00 142,560.00

N 2nd Floor - 3rd floor 9 m2 16,500.00 142,560.00

P 3rd floor - 4th floor 3 m2 16,500.00 47,520.00

Q 4th floor - 5th floor 3 m2 16,500.00 47,520.00

R 5th floor - 6th floor 3 m2 16,500.00 47,520.00


35

To collection : 588,024.00
No Item Description Qty Unit Rate Amount

BILL NR.2: MAIN BUILDING PAGE 2/89


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


Staircase treads slab
width 300mm
A Ground floor - 1st floor 72 m 6,600.00 475,200.00

B 1st floor - 2nd floor 72 m 6,600.00 475,200.00

C 2nd Floor - 3rd floor 72 m 6,600.00 475,200.00

D 3rd floor - 4th floor 24 m 6,600.00 158,400.00

E 4th floor - 5th floor 24 m 6,600.00 158,400.00

F 5th floor - 6th floor 24 m 6,600.00 158,400.00


288
Staircase risers
height 150mm
G Ground floor - 1st floor 76 m 3,300.00 249,480.00

H 1st floor - 2nd floor 76 m 3,300.00 249,480.00

J 2nd Floor - 3rd floor 76 m 3,300.00 249,480.00

K 3rd floor - 4th floor 25 m 3,300.00 83,160.00

L 4th floor - 5th floor 25 m 3,300.00 83,160.00

M 5th floor - 6th floor 25 m 3,300.00 83,160.00


302
Sand blast Anti slips strip
N Ground floor - 1st floor 76 m 4,000.00 302,400.00

P 1st floor - 2nd floor 76 m 4,000.00 302,400.00

Q 2nd Floor - 3rd floor 76 m 4,000.00 302,400.00

R 3rd floor - 4th floor 25 m 4,000.00 100,800.00

S 4th floor - 5th floor 25 m 4,000.00 100,800.00

T 5th floor - 6th floor 25 m 4,000.00 100,800.00


302

To collection : 4,108,320.00

BILL NR.2: MAIN BUILDING PAGE 2/90


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Skirting on wall
height 100mm
A Ground floor - 1st floor 43 m 2,500.00 106,875.00

B 1st floor - 2nd floor 43 m 2,500.00 106,875.00

C 2nd Floor - 3rd floor 43 m 2,500.00 106,875.00

D 3rd floor - 4th floor 14 m 2,500.00 35,625.00

E 4th floor - 5th floor 14 m 2,500.00 35,625.00

F 5th floor - 6th floor 14 m 2,500.00 35,625.00


171
M20: PLASTERED/RENDERED
Mortar, cement and sand (1:4); steel trowelled
12mm work to walls on concrete base or blockwork
Horizontal soffit of landing
regular shaped; rectangular; height to soffit 1.50 - 3.00m

G Ground floor - 1st floor 9 m2 1,650.00 14,256.00

H 1st floor - 2nd floor 9 m2 1,650.00 14,256.00

J 2nd Floor - 3rd floor 9 m2 1,650.00 14,256.00

K 3rd floor - 4th floor 3 m2 1,650.00 4,752.00

L 4th floor - 5th floor 3 m2 1,650.00 4,752.00

M 5th floor - 6th floor 3 m2 1,650.00 4,752.00

To collection : 484,524.00

BILL NR.2: MAIN BUILDING PAGE 2/91


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Slopping soffit of stairs

slope exceeding 15 degrees


A Ground floor - 1st floor 25 m2 1,650.00 41,580.00

B 1st floor - 2nd floor 25 m2 1,650.00 41,580.00

C 2nd Floor - 3rd floor 25 m2 1,650.00 41,580.00

D 3rd floor - 4th floor 8 m2 1,650.00 13,860.00

E 4th floor - 5th floor 8 m2 1,650.00 13,860.00

F 5th floor - 6th floor 8 m2 1,650.00 13,860.00

Sides of stair beams

regular shaped; rectangular


G Ground floor - 1st floor 32 m2 1,650.00 53,455.05

H 1st floor - 2nd floor 29 m2 1,650.00 48,109.05

J 2nd Floor - 3rd floor 29 m2 1,650.00 48,109.05

K 3rd floor - 4th floor 10 m2 1,650.00 16,036.35

L 4th floor - 5th floor 10 m2 1,650.00 16,036.35

M 5th floor - 6th floor 10 m2 1,650.00 16,036.35

Raking string of staircase


width not exceeding 375mm
N Ground floor - 1st floor 21 m 618.75 12,993.75

P 1st floor - 2nd floor 21 m 618.75 12,993.75

Q 2nd Floor - 3rd floor 21 m 618.75 12,993.75

R 3rd floor - 4th floor 7 m 618.75 4,331.25

S 4th floor - 5th floor 7 m 618.75 4,331.25

T 5th floor - 6th floor 7 m 618.75 4,331.25

To collection : 416,077.20

BILL NR.2: MAIN BUILDING PAGE 2/92


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
M60: PAINTING/CLEAR FINISHING
Wall screeding (I-nox)
floating of landing soffits
over 300mm wide; internal; as architectural details
Slopping soffit of stairs
slope exceeding 15 degrees

A Ground floor - 1st floor 25 m2 1,000.00 25,200.00

B 1st floor - 2nd floor 25 m2 1,000.00 25,200.00

C 2nd Floor - 3rd floor 25 m2 1,000.00 25,200.00

D 3rd floor - 4th floor 8 m2 1,000.00 8,400.00

E 4th floor - 5th floor 8 m2 1,000.00 8,400.00

F 5th floor - 6th floor 8 m2 1,000.00 8,400.00

Sides of stair beams


regular shaped; rectangular

G Ground floor - 1st floor 32 m2 1,000.00 32,397.00

H 1st floor - 2nd floor 29 m2 1,000.00 29,157.00

J 2nd Floor - 3rd floor 29 m2 1,000.00 29,157.00

K 3rd floor - 4th floor 10 m2 1,000.00 9,719.00

L 4th floor - 5th floor 10 m2 1,000.00 9,719.00

M 5th floor - 6th floor 10 m2 1,000.00 9,719.00

Raking string of staircase


width not exceeding 375mm
N Ground floor - 1st floor 21 m 375.00 7,875.00

P 1st floor - 2nd floor 21 m 375.00 7,875.00

Q 2nd Floor - 3rd floor 21 m 375.00 7,875.00

R 3rd floor - 4th floor 7 m 375.00 2,625.00

S 4th floor - 5th floor 7 m 375.00 2,625.00

T 5th floor - 6th floor 7 m 375.00 2,625.00

To collection : 252,168.00

BILL NR.2: MAIN BUILDING PAGE 2/93


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Horizontal soffit of landing
regular shaped; rectangular; height to soffit 1.50 - 3.00m
A Ground floor - 1st floor 9 m2 1,000.00 8,640.00

B 1st floor - 2nd floor 9 m2 1,000.00 8,640.00

C 2nd Floor - 3rd floor 9 m2 1,000.00 8,640.00

D 3rd floor - 4th floor 3 m2 1,000.00 2,880.00

E 4th floor - 5th floor 3 m2 1,000.00 2,880.00

F 5th floor - 6th floor 3 m2 1,000.00 2,880.00

One mist coat and two full coats of "dulux" emulsion paint
Cement rendered general surfaces
Horizontal soffit of landing
regular shaped; rectangular; height to soffit 1.50 - 3.00m
G Ground floor - 1st floor 9 m2 1,654.00 14,290.56

H 1st floor - 2nd floor 9 m2 1,654.00 14,290.56

J 2nd Floor - 3rd floor 9 m2 1,654.00 14,290.56

K 3rd floor - 4th floor 3 m2 1,654.00 4,763.52

L 4th floor - 5th floor 3 m2 1,654.00 4,763.52

M 5th floor - 6th floor 3 m2 1,654.00 4,763.52

Sides of stair beams


regular shaped; rectangular

N Ground floor - 1st floor 32 m2 1,654.00 53,584.64

P 1st floor - 2nd floor 29 m2 1,654.00 48,225.68

Q 2nd Floor - 3rd floor 29 m2 1,654.00 48,225.68

R 3rd floor - 4th floor 10 m2 1,654.00 16,075.23

S 4th floor - 5th floor 10 m2 1,654.00 16,075.23

T 5th floor - 6th floor 10 m2 1,654.00 16,075.23

To collection : 289,983.91

BILL NR.2: MAIN BUILDING PAGE 2/94


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Slopping soffit of stairs


slope exceeding 15 degrees

A Ground floor - 1st floor 25 m2 1,654.00 41,680.80

B 1st floor - 2nd floor 25 m2 1,654.00 41,680.80

C 2nd Floor - 3rd floor 25 m2 1,654.00 41,680.80

D 3rd floor - 4th floor 8 m2 1,654.00 13,893.60

E 4th floor - 5th floor 8 m2 1,654.00 13,893.60

F 5th floor - 6th floor 8 m2 1,654.00 13,893.60

Raking string of staircase


width not exceeding 300mm
M Ground floor - 1st floor 21 m 620.25 13,025.25

N 1st floor - 2nd floor 21 m 620.25 13,025.25

P 2nd Floor - 3rd floor 21 m 620.25 13,025.25

Q 3rd floor - 4th floor 7 m 620.25 4,341.75

R 4th floor - 5th floor 7 m 620.25 4,341.75

S 5th floor - 6th floor 7 m 620.25 4,341.75

To collection : 218,824.20

BILL NR.2: MAIN BUILDING PAGE 2/95


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Collection
STAIRCASE.
Page 2/13 2,882,754.00

Page 2/14 1,858,732.50

Page 2/15 612,000.00

Page 2/16 11,224,358.37

Page 2/17 8,777,234.40

Page 2/18 221,414.40

Page 2/19 588,024.00

Page 2/20 4,108,320.00

Page 2/21 484,524.00

Page 2/22 416,077.20

Page 2/23 252,168.00

Page 2/24 289,983.91

Page 2/25 218,824.20

To Main Building Collection : 31,934,414.98

BILL NR.2: MAIN BUILDING PAGE 2/96


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
RAMPS
INFORMATION
Nature and location of the work

The work in this section comprises

(i.) Reinforced concrete Ramps and associated works.


(ii.) The Contractor is however referred to Structural Engineer's drawings
for details and scope of the Works.

E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced in-situ concrete; B.S.5328, 40Kn/mm2 designed Mix 35


(35Mpa), 20 aggregate, minimum cement content 375 kg/m3; vibrated
and maximum water cement ratio of 0.43 (Ready mixed Concrete -RMC)

Slopping soffit of Ramp


A Ground floor - 1st floor 44 m3 85,625.00 3,758,458.00

B 1st -2nd floor 44 m3 85,625.00 3,758,458.00

C 2nd -3rd floor 44 m3 85,625.00 3,758,458.00

D 3rd - 4th floor 44 m3 85,625.00 3,758,458.00

E 4th - 5th floor 44 m3 85,625.00 3,758,458.00

F 5th - 6th floor 44 m3 85,625.00 3,758,458.00

Ramp Beams
G Ground floor - 1st floor 5 m3 85,625.00 437,406.75

H 1st -2nd floor 5 m3 85,625.00 437,406.75

J 2nd -3rd floor 5 m3 85,625.00 437,406.75

K 3rd - 4th floor 5 m3 85,625.00 437,406.75

L 4th - 5th floor 5 m3 85,625.00 437,406.75

M 5th - 6th floor 5 m3 85,625.00 437,406.75


294.02
To collection : 25,175,188.50

BILL NR.2: MAIN BUILDING PAGE 2/97


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

E20: FORMWORK FOR IN-SITU CONCRETE


Sawn formwork to produce plain surface:
Horizontal soffit of landing

Slopping soffit of Ramp


slope exceeding 15 degrees
A Ground floor - 1st floor 170 m2 5,000.00 851,400.00

B 1st -2nd floor 170 m2 5,000.00 851,400.00

C 2nd -3rd floor 170 m2 5,000.00 851,400.00

D 3rd - 4th floor 170 m2 5,000.00 851,400.00

E 4th - 5th floor 170 m2 5,000.00 851,400.00

F 5th - 6th floor 170 m2 5,000.00 851,400.00


1022
Ramp Beams
slope exceeding 15 degrees
G Ground floor - 1st floor 31 m2 5,000.00 156,090.00

H 1st -2nd floor 31 m2 5,000.00 156,090.00

J 2nd -3rd floor 31 m2 5,000.00 156,090.00

K 3rd - 4th floor 31 m2 5,000.00 156,090.00

L 4th - 5th floor 31 m2 5,000.00 156,090.00

M 5th - 6th floor 31 m2 5,000.00 156,090.00


187
Raking string of Ramps
not exceeding 250mm wide
N Ground floor - 1st floor 72 m 1,250.00 90,000.00

P 1st -2nd floor 72 m 1,250.00 90,000.00

Q 2nd -3rd floor 72 m 1,250.00 90,000.00

R 3rd - 4th floor 72 m 1,250.00 90,000.00

S 4th - 5th floor 72 m 1,250.00 90,000.00

T 5th - 6th floor 72 m 1,250.00 90,000.00


216

To collection : 6,584,940.00

BILL NR.2: MAIN BUILDING PAGE 2/98


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel


(TMT)

Straight and bent


Ramps
Ground floor - 1st floor
A H20 0.64 t 800,000.00 508,673.89

B H16 4.88 t 800,000.00 3,905,200.95

C H12 1.43 t 800,000.00 1,147,358.02

D H10 0.32 t 800,000.00 253,488.37

1st -2nd floor


E H20 0.64 t 800,000.00 508,673.89

F H16 4.88 t 800,000.00 3,905,200.95

G H12 1.43 t 800,000.00 1,147,358.02

H H10 0.32 t 800,000.00 253,488.37

2nd -3rd floor


J H20 0.64 t 800,000.00 508,673.89

K H16 4.88 t 800,000.00 3,905,200.95

L H12 1.43 t 800,000.00 1,147,358.02

K H10 0.32 t 800,000.00 253,488.37

3rd - 4th floor


M H20 0.64 t 800,000.00 508,673.89

N H16 4.88 t 800,000.00 3,905,200.95

P H12 1.43 t 800,000.00 1,147,358.02

Q H10 0.32 t 800,000.00 253,488.37

4th - 5th floor


R H20 0.64 t 800,000.00 508,673.89

S H16 4.88 t 800,000.00 3,905,200.95

T H12 1.43 t 800,000.00 1,147,358.02

U H10 0.32 t 800,000.00 253,488.37

To collection : 29,073,606.13

BILL NR.2: MAIN BUILDING PAGE 2/99


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

5th - 6th floor

A H20 0.64 t 800,000.00 508,673.89

B H16 4.88 t 800,000.00 3,905,200.95

C H12 1.43 t 800,000.00 1,147,358.02

D H10 0.32 t 800,000.00 253,488.37


43.61
L31 METAL BALUSTRADES
Stainless steel handrailing bolted, with connector and all necessary
accessories (300mm high)
E Ground floor - 1st floor 24 m 45,250.00 1,086,000.00

F 1st floor - 2nd floor 20 m 45,250.00 905,000.00

G 2nd Floor - 3rd floor 20 m 45,250.00 905,000.00

H 3rd floor - 4th floor 20 m 45,250.00 905,000.00

J 4th floor - 5th floor 20 m 45,250.00 905,000.00

K 5th floor - 6th floor 20 m 45,250.00 905,000.00

L 5th floor - 6th floor 20 m 45,250.00 905,000.00


144
SURFACE FINISHES
M20: PLASTERED/RENDERED
Mortar, cement and sand (1:4); steel trowelled
12mm work to walls on concrete base or blockwork
Slopping soffit of Ramp
slope exceeding 15 degrees

M Ground floor - 1st floor 170 m2 1,484.00 252,695.52

N 1st floor - 2nd floor 170 m2 1,484.00 252,695.52

P 2nd Floor - 3rd floor 170 m2 1,484.00 252,695.52

Q 3rd floor - 4th floor 170 m2 1,484.00 252,695.52

R 4th floor - 5th floor 170 m2 1,484.00 252,695.52

S 5th floor - 6th floor 170 m2 1,484.00 252,695.52

To collection : 13,846,894.35

BILL NR.2: MAIN BUILDING PAGE 2/100


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Ramp Beams
slope exceeding 15 degrees
A Ground floor - 1st floor 31 m2 1,484.00 46,327.51

B 1st floor - 2nd floor 31 m2 1,484.00 46,327.51

C 2nd Floor - 3rd floor 31 m2 1,484.00 46,327.51

D 3rd floor - 4th floor 31 m2 1,484.00 46,327.51

E 4th floor - 5th floor 31 m2 1,484.00 46,327.51

F 5th floor - 6th floor 31 m2 1,484.00 46,327.51

Raking string of Ramps


not exceeding 250mm wide
G Ground floor - 1st floor 72 m 556.50 40,068.00

H 1st floor - 2nd floor 72 m 556.50 40,068.00

J 2nd Floor - 3rd floor 72 m 556.50 40,068.00

K 3rd floor - 4th floor 72 m 556.50 40,068.00

L 4th floor - 5th floor 72 m 556.50 40,068.00

M 5th floor - 6th floor 72 m 556.50 40,068.00

To collection : 518,373.07

BILL NR.2: MAIN BUILDING PAGE 2/101


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
M60: PAINTING/CLEAR FINISHING
Wall screeding (I-nox)
floating of landing soffits
over 300mm wide; internal; as architectural details
Slopping soffit of Ramp
slope exceeding 15 degrees

A Ground floor - 1st floor 170 m2 1,000.00 170,280.00

B 1st floor - 2nd floor 170 m2 1,000.00 170,280.00

C 2nd Floor - 3rd floor 170 m2 1,000.00 170,280.00

D 3rd floor - 4th floor 170 m2 1,000.00 170,280.00

E 4th floor - 5th floor 170 m2 1,000.00 170,280.00

F 5th floor - 6th floor 170 m2 1,000.00 170,280.00

Ramp beams
regular shaped; rectangular

G Ground floor - 1st floor 31 m2 1,000.00 31,218.00

H 1st floor - 2nd floor 31 m2 1,000.00 31,218.00

J 2nd Floor - 3rd floor 31 m2 1,000.00 31,218.00

K 3rd floor - 4th floor 31 m2 1,000.00 31,218.00

L 4th floor - 5th floor 31 m2 1,000.00 31,218.00

M 5th floor - 6th floor 31 m2 1,000.00 31,218.00

Raking string of Ramps


not exceeding 250mm wide
N Ground floor - 1st floor 72 m 375.00 27,000.00

P 1st floor - 2nd floor 72 m 375.00 27,000.00

Q 2nd Floor - 3rd floor 72 m 375.00 27,000.00

R 3rd floor - 4th floor 72 m 375.00 27,000.00

S 4th floor - 5th floor 72 m 375.00 27,000.00

T 5th floor - 6th floor 72 m 375.00 27,000.00

To collection : 1,370,988.00

BILL NR.2: MAIN BUILDING PAGE 2/102


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

One mist coat and two full coats of "dulux" emulsion paint
Cement rendered general surfaces
Slopping soffit of Ramp
slope exceeding 15 degrees
A Ground floor - 1st floor 170 m2 1,654.00 281,643.12

B 1st floor - 2nd floor 170 m2 1,654.00 281,643.12

C 2nd Floor - 3rd floor 170 m2 1,654.00 281,643.12

D 3rd floor - 4th floor 170 m2 1,654.00 281,643.12

E 4th floor - 5th floor 170 m2 1,654.00 281,643.12

F 5th floor - 6th floor 170 m2 1,654.00 281,643.12

Ramp beams
regular shaped; rectangular

G Ground floor - 1st floor 31 m2 1,654.00 51,634.57

H 1st floor - 2nd floor 31 m2 1,654.00 51,634.57

J 2nd Floor - 3rd floor 31 m2 1,654.00 51,634.57

K 3rd floor - 4th floor 31 m2 1,654.00 51,634.57

L 4th floor - 5th floor 31 m2 1,654.00 51,634.57

M 5th floor - 6th floor 31 m2 1,654.00 51,634.57

Raking string of Ramps


not exceeding 250mm wide

N Ground floor - 1st floor 72 m2 1,654.00 119,088.00

P 1st floor - 2nd floor 72 m2 1,654.00 119,088.00

Q 2nd Floor - 3rd floor 72 m2 1,654.00 119,088.00

R 3rd floor - 4th floor 72 m2 1,654.00 119,088.00

S 4th floor - 5th floor 72 m2 1,654.00 119,088.00

T 5th floor - 6th floor 72 m2 1,654.00 119,088.00

To collection : 2,714,194.15

BILL NR.2: MAIN BUILDING PAGE 2/103


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

RAMPS.
Page 2/27 25,175,188.50

Page 2/28 6,584,940.00

Page 2/29 29,073,606.13

Page 2/30 13,846,894.35

Page 2/31 518,373.07

Page 2/32 1,370,988.00

Page 2/33 2,714,194.15

To Main Building Collection : 79,284,184.20

BILL NR.2: MAIN BUILDING PAGE 2/104


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
ROOF AND ROOF COVERING
INFORMATION
Nature and location of the work
The work in this section comprises

(i.) Bituminious felt, structural steel works, roof covering and associated
works.
(ii.) The Contractor is however referred to Architect's and Structural
Engineer's drawing for the scope of work.

(iii.) Reinforced concrete roof slab and beam and associated works.
(iv.) The Contractor is however referred to Structural Engineer's
drawings for details and scope of the Works.

Reinforced in-situ concrete; B.S.5328, 40Kn/mm2 designed Mix 35


(35Mpa), 20 aggregate, minimum cement content 375 kg/m3; vibrated
and maximum water cement ratio of 0.43 (Ready mixed Concrete -RMC)

A Roof slab 340 m3 85,625.00 29,129,625.00

B Roof beam 153 m3 85,625.00 13,059,203.91

Sawn marine board formwork to produce plain surface:


Horizontal soffit of suspended solid slab

C Soffit of slab 2268 m2 5,000.00 11,340,000.00

D Ditto edges of the roof slab not exceeding 250mm wide 212 m 1,250.00 265,000.00

E Sides and soffit of beam 1185 m2 5,000.00 5,924,800.00

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel


(TMT-TIGER)
Straight and bent
Roof slab
F H12 35.24 t 800,000.00 28,192,255.98

G H12(hunch bench) Provisional 3.5 t 800,000.00 2,819,225.60

H H10 3.7 t 800,000.00 2,979,006.35

Roof beam
J H25 17.77 t 800,000.00 14,213,701.60

K H20 4.24 t 800,000.00 3,391,356.64

L H16 4.07 t 800,000.00 3,258,417.83

M H10 5.67 t 800,000.00 4,537,500.99

Parapet wall
N 225mm blockwall filled solid with lean concrete 504 m2 8,500.00 4,287,400.00

To collection : 123,397,493.90

BILL NR.2: MAIN BUILDING PAGE 2/105


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Copping
A 200mm wide x 50mm precast concrete copping 317 m 2,000.00 634,000.00

Prepare and apply 3mm thick one layer of bituminious felt or equal and
approved to concrete below ground level
B Horizontal surfaces 2268 m2 8,500.00 19,278,000.00

C Vertical surfaces 504 m2 8,500.00 4,287,400.00

Backing
D 42mm cement and sand backing horizontally 2268 m2 3,175.00 7,200,900.00

E 12mm cement and sand backing vertically 504 m2 1,650.00 832,260.00

F 12mm plastering 504 m2 1,650.00 832,260.00

G Ditto copping not exceeding 300mm wide 317 m 495.00 156,915.00

H Wall screeding ( e-nox exterior) 504 m2 1,000.00 504,400.00

J Ditto copping not exceeding 300mm wide 317 m 300.00 95,100.00

To collection : 33,821,235.00

BILL NR.2: MAIN BUILDING PAGE 2/106


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

STRUCTURAL/CARCASSING METAL/TIMBER
G20: CARPENTRY/ TIMBER FRAMING/ FIRST FIXING

All hardwood are to be treated with Solignum or approved anti termite


solution.
Hardwood, wrot

50 x 150mm

A Tie beam 988 m 858.00 847,704.00

B Rafters 1166 m 858.00 1,000,428.00

75mm x 100mm

C Wall plates 854 m 788.00 672,952.00

50 x 100mm

D Strutts / braces 2340 m 632.00 1,478,880.00

50 x 75mm

E purlins @ 900mm centres 1342 m 519.00 696,498.00

25 x 225mm

F Fascial board 62 m 1,532.00 94,984.00

50 x 50mm
E noggins; internally 9226 m 445.00 4,105,570.00

To collection : 8,897,016.00

BILL NR.2: MAIN BUILDING PAGE 2/107


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
CLADDING/COVERING

H72: DESIGN ROOFING SHEET COVERINGS/ FLASHINGS

Aluminium roof covering

Longspan [as approved by Architect]: roof coverings; fixing to hardwood


purlins with fixing screws; 200mm end laps and one or two corrugation
side laps.

A pitch not exceeding 15 degrees 1165 m2 6,425.00 7,485,767.50

Cappings; flashings; eaves angle

B 150mm girth 62 m 963.75 59,752.50

To collection : 7,545,520.00
Collection

ROOF AND ROOF COVERING

Page 2/35 123,397,493.90

Page 2/36 33,821,235.00

Page 2/37 8,897,016.00

Page 2/38 7,545,520.00

To Main Building Collection : 173,661,264.90

BILL NR.2: MAIN BUILDING PAGE 2/108


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
EXTERNAL AND INTERNAL WALLS
INFORMATION
Nature and location of the work
The work in this section comprises

(i) The erection of hollow sandcrete block walls, reinforced concrete


lintels. (ii)
The Contractor is however referred to Architect's and Structural
Engineer's drawings for details and scope of the scope of work

E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced in-situ concrete; B.S.5328, 40Kn/mm2 designed Mix 35


(35Mpa), 20 aggregate, minimum cement content 375 kg/m3; vibrated
and maximum water cement ratio of 0.43 (Ready mixed Concrete -RMC)

Lintel
A generally in ground floor 7 m3 85,625.00 570,724.88

B generally in 1st floor 8 m3 85,625.00 715,670.88

C generally in 2nd floor 8 m3 85,625.00 715,670.88

D generally in 3rd floor 8 m3 85,625.00 715,670.88

E generally in 4th floor 1 m3 85,625.00 49,825.19

F generally in 5th floor 1 m3 85,625.00 49,825.19

G generally in 6th floor 1 m3 85,625.00 49,825.19

E20: FORMWORK FOR IN-SITU CONCRETE


Sawn formwork to produce plain surface to
Lintel: sides and soffit.
regular shaped rectangle
H generally in ground floor 87 m2 5,000.00 434,700.00

J generally in 1st floor 109 m2 5,000.00 545,100.00

K generally in 2nd floor 109 m2 5,000.00 545,100.00

L generally in 3rd floor 109 m2 5,000.00 545,100.00

M generally in 4th floor 8 m2 5,000.00 37,950.00

N generally in 5th floor 8 m2 5,000.00 37,950.00

P generally in 6th floor 8 m2 5,000.00 37,950.00

To collection : 5,051,063.06

BILL NR.2: MAIN BUILDING PAGE 2/109


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel


(TMT-TIGER)

Straight and bent

Lintel
Ground floor
A H12 0.45 t 800,000.00 358,060.95

B H10 in links 0.36 t 800,000.00 286,405.35

1st floor
C H12 0.56 t 800,000.00 448,997.07

D H10 in links 0.45 t 800,000.00 359,027.94

2nd floor
E H12 0.56 t 800,000.00 448,997.07

F H10 in links 0.45 t 800,000.00 359,027.94

3rd floor
G 12mm diameter 0.56 t 800,000.00 448,997.07

H 10mm diameter (stirrups) 0.45 t 800,000.00 359,027.94

4th floor
J H12 0.04 t 800,000.00 31,259.29

K H10 in links 0.03 t 800,000.00 25,417.91

5th floor
L H12 0.04 t 800,000.00 31,259.29

M H10 in links 0.03 t 800,000.00 25,417.91

6th floor
N 12mm diameter 0.04 t 800,000.00 31,259.29

P 10mm diameter (stirrups) 0.03 t 800,000.00 25,417.91

To collection : 3,238,572.92

BILL NR.2: MAIN BUILDING PAGE 2/110


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
MASONRY
F10: BLOCK WALLING
Stone dust hollow blockwork, bedded and jointed in cement and sand
mortar
230mm Walls
230mm thick; stretcher bond; regular
A 230mm thick; stretcher bond; regular in Ground floor 1197 m2 5,432.00 6,504,059.52

B 230mm thick; stretcher bond; regular in 1st floor 1360 m2 5,432.00 7,385,999.04

C 230mm thick; stretcher bond; regular in 2nd floor 1360 m2 5,432.00 7,385,999.04

D 230mm thick; stretcher bond; regular in 3rd floor 1164 m2 5,432.00 6,324,803.52

E 230mm thick; stretcher bond; regular in 4th floor 344 m2 5,432.00 1,867,847.52

F 230mm thick; stretcher bond; regular in 5th floor 344 m2 5,432.00 1,867,847.52

G 230mm thick; stretcher bond; regular in 6th floor 344 m2 5,432.00 1,867,847.52
6113
150mm wall
H 150mm thick; stretcher bond; regular in Ground floor 39 m2 3,728.00 145,671.60

J 150mm thick; stretcher bond; regular in 1st floor 39 m2 3,728.00 145,671.60

K 150mm thick; stretcher bond; regular in 2nd floor 39 m2 3,728.00 145,671.60

L 150mm thick; stretcher bond; regular in 3rd floor 39 m2 3,728.00 145,671.60


156

Expansion Joint
M Expansion joint 20mm thick ploystrene naked panel 455 m2 761.00 345,933.86

To collection : 34,133,023.94
Collection

EXTERNAL AND INTERNAL WALLS

Page 2/39 5,051,063.06

Page 2/40 3,238,572.92

Page 241 34,133,023.94

To Main Building Collection : 42,422,659.92

BILL NR.2: MAIN BUILDING PAGE 2/111


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
L WINDOWS, CURTAIN WALLS AND DOORS
INFORMATION
Nature and location of the work
The work in this section comprises

(i) Timber flush door and steel frames, anodised aluminium doors and
windows.
(ii) The contractor is however referred to the Architectural doors and
windows schedule for details and scope of work.
L10: WINDOWS
L11 ALUMINIUM WINDOWS AND DOORS/CURTAIN WALL
Ground floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall

A Size 3600mm x 2850mm high with aluminium swing door 1800mm x 155 m2 120,000.00 18,576,000.00
2100mm high (measured seperately)

Projected Window 6mm laminated clear glass single glazing EBM with
nett
B Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00

1st floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall

C Size 3600mm x 2850mm high with aluminium swing door 1800mm x 206 m2 120,000.00 24,768,000.00
2100mm high (measured seperately)

Projected Window 6mm laminated clear glass single glazing EBM with
nett
D Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00

2nd floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall

E Size 3600mm x 2850mm high with aluminium swing door 1800mm x 206 m2 120,000.00 24,768,000.00
2100mm high (measured seperately)

Projected Window 6mm laminated clear glass single glazing EBM with
nett
F Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00

3rd floor
Shop front (Curtain wall)
10mm thick Tempered glass frameless glazing glass wall

G Size 3600mm x 2850mm high with aluminium swing door 1800mm x 155 m2 657,600.00 101,796,480.00
2100mm high (measured seperately)

Projected Window 6mm laminated clear glass single glazing EBM with
nett
H Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00

To collection : 170,657,280.00

BILL NR.2: MAIN BUILDING PAGE 2/112


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

4th floor
Projected Window 6mm laminated clear glass single glazing EBM with
nett
A Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00

5th floor
Projected Window 6mm laminated clear glass single glazing EBM with
nett
B Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00

6th floor
Projected Window 6mm laminated clear glass single glazing EBM with
nett
C Size 1300mm x 1200mm high 1 nr 187,200.00 187,200.00

Subframe
D 40mm x 20mm aluminium subframe on window 35 m 1,903.00 66,605.00

L20 TIMBER DOORS/SHUTTERS/HATCHES


Supply and install
High quality panel doors

Ready made door complete with lock ,frame & architrave and stopper
Solid core, single leaf; single swing; solid door, factory finish with
hardwood lipping all edges and polished door frames and all sprayed with
approved quality varnish paint

Ground floor
E Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00

F 900 X 2100mm high overall 4 nr 100,000.00 400,000.00

1st floor
G Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00

H 900 X 2100mm high overall 4 nr 100,000.00 400,000.00

2nd floor
J Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00

K 900 X 2100mm high overall 4 nr 100,000.00 400,000.00

3rd floor
L Size 750mm x 2100mm high 7 nr 100,000.00 700,000.00

M 900 X 2100mm high overall 4 nr 100,000.00 400,000.00

4th floor
N 900 X 2100mm high overall 2 nr 100,000.00 200,000.00

5th floor
P 900 X 2100mm high overall 2 nr 100,000.00 200,000.00

5th floor
Q 900 X 2100mm high overall 2 nr 100,000.00 200,000.00

BILL NR.2: MAIN BUILDING PAGE 2/113


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount

To collection : 5,628,205.00

BILL NR.2: MAIN BUILDING PAGE 2/114


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

L21 METAL DOORS/SHUTTERS/HATCHES


Aluminium Door EBM profile (K2000) with 10mm clear glass
Ground floor
A Aluminium Swing Door size 1800mm x 2100mm high 24 nr 321,300.00 7,711,200.00

1st Floor
B Aluminium Swing Door size 1800mm x 2100mm high 32 nr 321,300.00 10,281,600.00

2nd floor
C Aluminium Swing Door size 1800mm x 2100mm high 32 nr 321,300.00 10,281,600.00

3rd Floor
D Aluminium Swing Door size 1800mm x 2100mm high 24 nr 321,300.00 7,711,200.00

ROLLER SHUTTER DOORS


Ground floor
E Door size 3600mm x 2850mm high 24 nr 415,800.00 9,979,200.00

1st Floor
F Door size 3600mm x 2850mm high 32 nr 415,800.00 13,305,600.00

2nd floor
G Door size 3600mm x 2850mm high 32 nr 415,800.00 13,305,600.00

3rd Floor
H Door size 3600mm x 2850mm high 24 nr 415,800.00 9,979,200.00

P BUILDING FABRIC SUNDRIES


P21 IRONMONGERY

Name plates
' TOILET' sign engraved on stainless steel plate size 350 x 100; Ref IRXX;
J finish: SS 28 nr 7,000.00 196,000.00

K Room Numbers and other spaces sign engraved on stainless plate 20 nr 7,000.00 140,000.00

L Shop Numbers and other spaces sign engraved on stainless plate 112 nr 7,000.00 784,000.00

To collection : 83,675,200.00
Collection

WINDOWS AND DOORS

Page 2/42 170,657,280.00

Page 2/43 5,628,205.00

Page 2/44 83,675,200.00

To Main Building Collection : 259,960,685.00

BILL NR.2: MAIN BUILDING PAGE 2/115


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
FITTING AND FIXTURES
FURNITURE/EQUIPMENT
INFORMATION
Nature and location of the work
The work in this section comprises
(i.) joinery and associated works
(ii.) Metal balcony railings and wall grilles
(iii.) The Contractor is however referred to Architect's details and scope
of work

Balcony handrailings
Laser-cut steel handrailing bolted, with connector and all necessary
accessories
A 1st floor 120 m2 95,500.00 11,460,000.00

B 2nd floor 120 m2 95,500.00 11,460,000.00

C 3rd floor 120 m2 95,500.00 11,460,000.00


360

STRUCTURAL STEEL WORKS ON EXTERNAL FACADE

D Allow a provisional sum of N150,000,000.00 for the fabrication of steel sum 150,000,000.00
work and Alucobond covering on external facade as may be instructed by
the Architect (2385m2)

To Main Building Collection : 184,380,000.00

BILL NR.2: MAIN BUILDING PAGE 2/116


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
FLOOR FINISHING

SURFACE FINISHES

INFORMATION

Nature and location of the work

The work in this section comprises


(i) Floor finishings with and other associated works
(ii) The Contractor is hereby referred to the various
Architect's location drawings and schedule of finishing in relation to this
section for the nature and content of the work to be executed.

M10: SAND CEMENT/ CONCRETE/ SCREEDS/TOPPINGS

Mortar, cement and sand (1:4)

Ground floor

42mm work to floors on concrete base; one coat; screeded

A level and to falls only not exceeding 15 degrees from horizontal (To 503 m2 3,174.00 1,596,522.00
receive Light grey ceramic tiles)

B Ditto(To receive unglazed Light grey ceramic tiles) 26 m2 3,174.00 82,524.00

30mm work to floors on concrete base; one coat; screeded

C level and to falls only not exceeding 15 degrees from horizontal (To 389 m2 2,365.00 919,985.00
receive Granite)

First Floor
42mm work to floors on concrete base; one coat; screeded

D level and to falls only not exceeding 15 degrees from horizontal (To 663 m2 3,174.00 2,104,362.00
receive Light grey ceramic tiles)

E Ditto(To receive unglazed Light grey ceramic tiles) 26 m2 3,174.00 82,524.00

30mm work to floors on concrete base; one coat; screeded

F level and to falls only not exceeding 15 degrees from horizontal (To 460 m2 2,365.00 1,087,900.00
receive Granite)

Second Floor
42mm work to floors on concrete base; one coat; screeded

G level and to falls only not exceeding 15 degrees from horizontal (To 663 m2 3,174.00 2,104,362.00
receive Light grey ceramic tiles)

H Ditto(To receive unglazed Light grey ceramic tiles) 26 m2 3,174.00 82,524.00

30mm work to floors on concrete base; one coat; screeded

J level and to falls only not exceeding 15 degrees from horizontal (To 460 m2 2,365.00 1,087,900.00
receive Granite)

To collection 9,148,603.00
No Item Description Qty Unit Rate Amount

BILL NR.2: MAIN BUILDING PAGE 2/117


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


Third floor
42mm work to floors on concrete base; one coat; screeded

A level and to falls only not exceeding 15 degrees from horizontal (To 663 m2 3,174.00 2,104,362.00
receive Light grey ceramic tiles)

B Ditto(To receive unglazed Light grey ceramic tiles) 26 m2 3,174.00 82,524.00

30mm work to floors on concrete base; one coat; screeded

C level and to falls only not exceeding 15 degrees from horizontal (To 430 m2 2,365.00 1,016,950.00
receive Granite)

Fourth floor
30mm work to floors on concrete base; one coat; screeded

D level and to falls only not exceeding 15 degrees from horizontal (To 33 m2 2,365.00 78,045.00
receive Granite)

Fifth floor
30mm work to floors on concrete base; one coat; screeded

E level and to falls only not exceeding 15 degrees from horizontal (To 33 m2 2,365.00 78,045.00
receive Granite)

Sixth floor
30mm work to floors on concrete base; one coat; screeded

F level and to falls only not exceeding 15 degrees from horizontal (To 45 m2 2,365.00 106,425.00
receive Granite)

12mm cement backing to skirting on wall


Ground floor
G height 100mm 460 m 165.00 75,853.80

First floor
H height 100mm 604 m 165.00 99,613.80

2nd floor
J height 100mm 604 m 165.00 99,613.80

3rd floor
K height 100mm 424 m 165.00 69,913.80

4th floor
L height 100mm 28 m 165.00 4,573.80

5th floor
M height 100mm 28 m 165.00 4,573.80

6th floor
N height 100mm 28 m 165.00 4,573.80

To collection : 3,825,067.60

BILL NR.2: MAIN BUILDING PAGE 2/118


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
M40: TILING
Grey ceramic tiles; 3 joints systematic layout, bedding in 10mm cement
mortar (1:3); including pointing.

400mm x 400mm x 12mm thick to floors on cement and sand base;


level to falls only not exceeding 15 degrees from horizontal

Ground floor
A Ground floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00

First Floor
B First floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00

Second floor
C Second floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00

Third floor
D Third floor patterned; over 300mm wide 26 m2 15,000.00 390,000.00
104
Water proofing to wet Area
E Bituminious felt double layer 104 m2 8,500.00 884,000.00

Asphalt flooring in Ground floor


F Supply and install epoxy flooring 2480 m2 8,000.00 19,840,000.00

Asphalt flooring in First Floor


G Supply and install epoxy flooring 2175 m2 8,000.00 17,400,000.00

Asphalt flooring in Second floor


H Supply and install epoxy flooring 2175 m2 8,000.00 17,400,000.00

Asphalt flooring in Third floor


J Supply and install epoxy flooring 2175 m2 8,000.00 17,400,000.00

Asphalt flooring in fourth floor


K Supply and install epoxy flooring 2175 m2 8,000.00 17,400,000.00

Asphalt flooring in Fifth floor


L Supply and install epoxy flooring 2175 m2 8,000.00 17,400,000.00

Asphalt flooring in Sixth floor


M Supply and install epoxy flooring 2175 m2 8,000.00 17,400,000.00
15530
To collection : 126,684,000.00

BILL NR.2: MAIN BUILDING PAGE 2/119


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Ceramic floor tiles;(Light grey) 3 joints systematic layout, bedding in 10
cement mortar (1:4); including pointing.

800mm x 800mm x 12mm thick to floors on cement and sand base;


level to falls only not exceeding 15 degrees from horizontal
Ground floor
A Ground floor patterned; over 300mm wide 503 m2 15,000.00 7,545,000.00

1st floor
B First floor patterned; over 300mm wide 663 m2 15,000.00 9,945,000.00

2nd floor
C Second floor patterned; over 300mm wide 663 m2 15,000.00 9,945,000.00

3rd floor
D Third floor patterned; over 300mm wide 663 m2 15,000.00 9,945,000.00

4th floor
E Fourth floor patterned; over 300mm wide 33 m2 15,000.00 495,000.00

5th floor
F Fifth floor patterned; over 300mm wide 33 m2 15,000.00 495,000.00

6th floor
G Sixth floor patterned; over 300mm wide 45 m2 15,000.00 675,000.00
2603
100mm skirting
Ground floor
H height 100mm 460 m 1,500.00 689,580.00

1st floor
J height 100mm 604 m 1,500.00 905,580.00

2nd floor
K height 100mm 604 m 1,500.00 905,580.00

3rd floor
L height 100mm 424 m 1,500.00 635,580.00

4th floor
M height 100mm 28 m 1,500.00 41,580.00

5th floor
N height 100mm 28 m 1,500.00 41,580.00

6th floor
P height 100mm 28 m 1,500.00 41,580.00
2174

To collection : 42,306,060.00

BILL NR.2: MAIN BUILDING PAGE 2/120


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Nigeria Granite floor tiles;(Champne silver) 3 joints systematic layout,
bedding in 10 cement mortar (1:4); including pointing.

600mm x 600mm x 15mm thick to floors on cement and sand base;


level to falls only not exceeding 15 degrees from horizontal
Ground floor
A Ground floor patterned; over 300mm wide 389 m2 16,500.00 6,418,500.00

1st floor
B First floor patterned; over 300mm wide 460 m2 16,500.00 7,590,000.00

2nd floor
C Second floor patterned; over 300mm wide 460 m2 16,500.00 7,590,000.00

3rd floor
D Third floor patterned; over 300mm wide 430 m2 16,500.00 7,095,000.00

4th floor
E Fourth floor patterned; over 300mm wide 33 m2 16,500.00 544,500.00

5th floor
F Fifth floor patterned; over 300mm wide 33 m2 16,500.00 544,500.00

6th floor
G Sixth floor patterned; over 300mm wide 45 m2 16,500.00 742,500.00
1850
100mm skirting
Ground floor
H Ground floor patterned; over 300mm wide 245 m 2,500.00 612,500.00

1st floor
J First floor patterned; over 300mm wide 310 m 2,500.00 775,000.00

2nd floor
K Second floor patterned; over 300mm wide 310 m 2,500.00 775,000.00

3rd floor
L Third floor patterned; over 300mm wide 310 m 2,500.00 775,000.00

4th floor
M Fourth floor patterned; over 300mm wide 10 m 2,500.00 24,000.00

5th floor
N Fifth floor patterned; over 300mm wide 10 m 2,500.00 24,000.00

6th floor
P Sixth floor patterned; over 300mm wide 10 m 2,500.00 24,000.00
1204

To collection : 33,534,500.00

BILL NR.2: MAIN BUILDING PAGE 2/121


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


Collection
Floor Finishing
Page 2/46 9,148,603.00

Page 2/47 3,825,067.60

Page 2/48 126,684,000.00

Page 2/49 42,306,060.00

Page 2/50 33,534,500.00

To Main Building Collection : 215,498,230.60

BILL NR.2: MAIN BUILDING PAGE 2/122


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
WALL FINISHING
SURFACE FINISHES
INFORMATION
Nature and location of the work
The work in this section comprises

(i) Walls finishings with and including other associated works but
excluding painting which is measured in a separate element.
(ii) The Contractor is hereby referred to
the various Architect's location drawings in relation to this section for the
nature and content of the work to be executed.
M20: PLASTERED/RENDERED

Mortar, cement and sand (1:4); steel trowelled


12mm work to walls on concrete base or blockwork
Ground floor
A Ground floor wall width exceeding 300mm 1414 m2 1,650.00 2,332,489.50

B Ditto Lift wall/shear wall 24 m2 1,650.00 39,699.00

C Ditto isolated column 623 m2 1,897.50 1,181,205.14

D width not exceeding 300mm 249 m 569.25 141,743.25

First floor
E First floor wall width exceeding 300mm 1657 m2 1,650.00 2,734,363.50

F Ditto lift wall externally 24 m2 1,650.00 39,699.00

G Ditto isolated column 623 m2 1,650.00 1,027,134.90

H width not exceeding 300mm 323 m 495.00 159,885.00

2nd floor
J second floor wall width exceeding 300mm 1621 m2 1,650.00 2,674,963.50

K Ditto lift wall externally 24 m2 1,650.00 39,699.00

L Ditto isolated column 602 m2 1,650.00 992,633.40

M width not exceeding 300mm 323 m 495.00 159,885.00

3rd floor
N Third floor wall width exceeding 300mm 1209 m2 1,650.00 1,994,239.50

P Ditto lift wall externally 24 m2 1,650.00 39,699.00

Q Ditto isolated column 492 m2 1,650.00 811,290.15

R width not exceeding 300mm 249 m 495.00 123,255.00

To collection : 14,491,883.84

BILL NR.2: MAIN BUILDING PAGE 2/123


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

4th floor
A Fourth floor wall width exceeding 300mm 73 m2 1,650.00 120,037.50

B Ditto lift wall externally 24 m2 1,650.00 39,699.00

C Ditto isolated column 294 m2 1,650.00 485,335.13

D width not exceeding 300mm 16 m 495.00 7,920.00

5th floor
E Fifth floor wall width exceeding 300mm 73 m2 1,650.00 120,037.50

F Ditto lift wall externally 24 m2 1,650.00 39,699.00

G Ditto isolated column 294 m2 1,650.00 485,335.13

H width not exceeding 300mm 16 m 495.00 7,920.00

6th floor
J Sixth floor wall width exceeding 300mm 73 m2 1,650.00 120,037.50

K Ditto lift wall externally 24 m2 1,650.00 39,699.00

L Ditto isolated column 294 m2 1,650.00 485,335.13

M width not exceeding 300mm 16 m 495.00 7,920.00

To collection : 1,958,974.88

BILL NR.2: MAIN BUILDING PAGE 2/124


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

EXTERNAL WORK
12mm work to walls on concrete base or blockwork
Ground floor
A width exceeding 300mm 1059 m2 1,650.00 1,747,746.00

B width not exceeding 300mm 479 m 495.00 237,105.00

1st floor
C width exceeding 300mm 1140 m2 1,650.00 1,881,660.00

D width not exceeding 300mm 608 m 495.00 300,960.00

2nd floor
E width exceeding 300mm 1176 m2 1,650.00 1,941,060.00

F width not exceeding 300mm 590 m 495.00 292,050.00

3rd floor
G width exceeding 300mm 1198 m2 1,650.00 1,977,096.00

H width not exceeding 300mm 534 m 495.00 264,330.00

To collection : 8,642,007.00

BILL NR.2: MAIN BUILDING PAGE 2/125


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
4th floor
A width exceeding 300mm 615 m2 1,650.00 1,014,700.50

B width not exceeding 300mm 242 m 495.00 119,790.00

5th floor
C width exceeding 300mm 615 m2 1,650.00 1,014,700.50

D width not exceeding 300mm 242 m 495.00 119,790.00

6th floor
E width exceeding 300mm 615 m2 1,650.00 1,014,700.50

F width not exceeding 300mm 242 m 495.00 119,790.00

Roof floor
G width exceeding 300mm 504 m2 1,650.00 832,260.00

Brown Brick wall finish


H Brown Brick wall finish 105 m2 22,500.00 2,362,500.00

To collection : 6,598,231.50
Collection

WALL FINISHING

Page 2/52 14,491,883.84

Page 2/53 1,958,974.88

Page 2/54 8,642,007.00

Page 2/55 6,598,231.50

To Main Building Collection : 31,691,097.21

BILL NR.2: MAIN BUILDING PAGE 2/126


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
CEILING FINISHING

INFORMATION

Nature and location of the work


The work in this section comprises

(i) Ceiling finishings with and including other associated works but
excluding painting which is measured in a separate Element
(ii) The Contractor is hereby referred to the various Architect's location
drawings in relation to this section for the nature and content of the work
to be executed.
SURFACE FINISHES

Mortar, cement and sand (1:4); steel trowelled


12mm work to walls on concrete base or blockwork
Ground floor
A over 300mm wide; internal; 529 m2 1,650.00 872,850.00

B Ditto sides and soffit of drop beam 1225 m2 1,650.00 2,021,985.24

First floor
C over 300mm wide; internal; 689 m2 1,650.00 1,136,850.00

D Ditto sides and soffit of drop beam 1225 m2 1,650.00 2,021,985.24

Second floor
E over 300mm wide; internal; 689 m2 1,650.00 1,136,850.00

F Ditto sides and soffit of drop beam 1225 m2 1,650.00 2,021,985.24

Third floor
K13 RIGID SHEET LINNING/COVERING
High quality plaster of paris; 12.5mm thick secrete fixing with screws or
other approved method; filling fixing holes and joints with plaster;
including all necessary screeding

G over 300mm wide; internal; 1140 m2 9,500.00 10,830,000.00


Mortar, cement and sand (1:4); steel trowelled
12mm work to walls on concrete base or blockwork

H Ditto sides and soffit of drop beam 389 m2 1,650.00 642,255.24

Fourth floor
J over 300mm wide; internal; 211 m2 1,650.00 348,150.00

K Ditto sides and soffit of drop beam 23 m2 1,650.00 38,157.24

Fifth floor
L over 300mm wide; internal; 33 m2 1,650.00 54,450.00

M Ditto sides and soffit of drop beam 19 m2 1,650.00 31,333.50

Sixth floor
N over 300mm wide; internal; 45 m2 1,650.00 74,250.00

P Ditto sides and soffit of drop beam 19 m2 1,650.00 31,333.50

BILL NR.2: MAIN BUILDING PAGE 2/127


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount

To Main Building Collection : 21,262,435.20

BILL NR.2: MAIN BUILDING PAGE 2/128


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate
PAINTING AND DECORATONS
SURFACE FINISHES
INFORMATION
Nature and location of the work
The work in this section comprises
(i.) Painting and decorations on new works.
(ii.) The Contractor is however referred to Architect's details and location
drawings for the details and scope of the works to be executed in this
section.

M60: PAINTING/CLEAR FINISHING


Wall screeding (I-nox)
Cement rendered general surfaces
Ground floor
A Ground floor wall width exceeding 300mm 1414 m2 1,000.00 1,413,630.00

B Ditto lift wall externally 24 m2 1,000.00 24,060.00

C Ditto isolated column 623 m2 1,000.00 622,506.00

D width not exceeding 300mm 249 m 300.00 74,700.00

First floor
E First floor wall width exceeding 300mm 1657 m2 1,000.00 1,657,190.00

F Ditto lift wall externally 24 m2 1,000.00 24,060.00

G Ditto isolated column 623 m2 1,000.00 622,506.00

H width not exceeding 300mm 323 m 300.00 96,900.00

To collection : 4,535,552.00

BILL NR.2: MAIN BUILDING PAGE 2/129


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
2nd floor
A second floor wall width exceeding 300mm 1621 m2 1,000.00 1,621,190.00

B Ditto lift wall externally 24 m2 1,000.00 24,060.00

C Ditto isolated column 602 m2 1,000.00 601,596.00

E width not exceeding 300mm 323 m 300.00 96,900.00

3rd floor
F Third floor wall width exceeding 300mm 1209 m2 1,000.00 1,208,630.00

G Ditto lift wall externally 24 m2 1,000.00 24,060.00

H Ditto isolated column 492 m2 1,000.00 491,691.00

K width not exceeding 300mm 249 m 300.00 74,700.00

4th floor
L Fourth floor wall width exceeding 300mm 73 m2 1,000.00 72,750.00

M Ditto lift wall externally 24 m2 1,000.00 24,060.00

N Ditto isolated column 294 m2 1,000.00 294,142.50

Q width not exceeding 300mm 16 m 300.00 4,800.00

5th floor
R Fifth floor wall width exceeding 300mm 73 m2 1,000.00 72,750.00

S Ditto lift wall externally 24 m2 1,000.00 24,060.00

T Ditto isolated column 294 m2 1,000.00 294,142.50

V width not exceeding 300mm 16 m 300.00 4,800.00

6th floor
A Six floor wall width exceeding 300mm 73 m2 1,000.00 72,750.00

B Ditto lift wall externally 24 m2 1,000.00 24,060.00

C Ditto isolated column 294 m2 1,000.00 294,142.50

D width not exceeding 300mm 16 m 300.00 4,800.00

To collection : 5,330,084.50

BILL NR.2: MAIN BUILDING PAGE 2/130


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Ceiling screeding I -nox


Ground floor
A over 300mm wide; internal; 529 m2 1,000.00 529,000.00

B Ditto sides and soffit of drop beam 1225 m2 1,000.00 1,225,445.60

1st floor
C over 300mm wide; internal; 689 m2 1,000.00 689,000.00

D Ditto sides and soffit of drop beam 1225 m2 1,000.00 1,225,445.60

2nd floor
E over 300mm wide; internal; 689 m2 1,000.00 689,000.00

F Ditto sides and soffit of drop beam 1225 m2 1,000.00 1,225,445.60

3rd floor
G over 300mm wide; internal; 1140 m2 1,000.00 1,140,000.00

H Ditto sides and soffit of drop beam 389 m2 1,000.00 389,245.60

4th floor
J over 300mm wide; internal; 211 m2 1,000.00 211,000.00

K Ditto sides and soffit of drop beam 23 m2 1,000.00 23,125.60

5th floor
L over 300mm wide; internal; 33 m2 1,000.00 33,000.00

M Ditto sides and soffit of drop beam 19 m2 1,000.00 18,990.00

6th floor
N over 300mm wide; internal; 45 m2 1,000.00 45,000.00

P Ditto sides and soffit of drop beam 19 m2 1,000.00 18,990.00

7463

To collection : 7,462,688.00

BILL NR.2: MAIN BUILDING PAGE 2/131


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
On wall
Ground floor
A Ground floor wall width exceeding 300mm 1414 m2 1,654.00 2,338,144.02

B Ditto lift wall externally 24 m2 1,654.00 39,795.24

C Ditto isolated column 623 m2 1,654.00 1,029,624.92

D width not exceeding 300mm 249 m 496.20 123,553.80

First floor
E First floor wall width exceeding 300mm 1657 m2 1,654.00 2,740,992.26

F Ditto lift wall externally 24 m2 1,654.00 39,795.24

G Ditto isolated column 623 m2 1,654.00 1,029,624.92

H width not exceeding 300mm 323 m 496.20 160,272.60

2nd floor
J second floor wall width exceeding 300mm 1621 m2 1,654.00 2,681,448.26

K Ditto lift wall externally 24 m2 1,654.00 39,795.24

L Ditto isolated column 602 m2 1,654.00 995,039.78

M width not exceeding 300mm 323 m 496.20 160,272.60

3rd floor
N Third floor wall width exceeding 300mm 1209 m2 1,654.00 1,999,074.02

P Ditto lift wall externally 24 m2 1,654.00 39,795.24

Q Ditto isolated column 492 m2 1,654.00 813,256.91

R width not exceeding 300mm 249 m 496.20 123,553.80

4th floor
S Fourth floor wall width exceeding 300mm 73 m2 1,654.00 120,328.50

T Ditto lift wall externally 24 m2 1,654.00 39,795.24

U Ditto isolated column 294 m2 1,654.00 486,511.69

V width not exceeding 300mm 16 m 496.20 7,939.20

5th floor
W Fifth floor wall width exceeding 300mm 73 m2 1,654.00 120,328.50

X Ditto lift wall externally 24 m2 1,654.00 39,795.24

Y Ditto isolated column 294 m2 1,654.00 486,511.69

Z width not exceeding 300mm 16 m 496.20 7,939.20

BILL NR.2: MAIN BUILDING PAGE 2/132


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount

To collection : 15,663,188.14

BILL NR.2: MAIN BUILDING PAGE 2/133


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
6th floor
A Sixth floor wall width exceeding 300mm 73 m2 1,654.00 120,328.50

B Ditto lift wall externally 24 m2 1,654.00 39,795.24

C Ditto isolated column 294 m2 1,654.00 486,511.69

D width not exceeding 300mm 16 m 496.20 7,939.20

Ceilings painting
Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
Ground floor
E over 300mm wide; internal; 529 m2 1,654.00 874,966.00

F Ditto sides and soffit of drop beam 1225 m2 1,654.00 2,026,887.02

1st floor
G over 300mm wide; internal; 689 m2 1,654.00 1,139,606.00

H Ditto sides and soffit of drop beam 1225 m2 1,654.00 2,026,887.02

2nd floor
J over 300mm wide; internal; 689 m2 1,654.00 1,139,606.00

K Ditto sides and soffit of drop beam 1225 m2 1,654.00 2,026,887.02

3rd floor
L over 300mm wide; internal; 1140 m2 1,654.00 1,885,560.00

M Ditto sides and soffit of drop beam 389 m2 1,654.00 643,812.22

4th floor
N over 300mm wide; internal; 211 m2 1,654.00 348,994.00

P Ditto sides and soffit of drop beam 23 m2 1,654.00 38,249.74

5th floor
Q over 300mm wide; internal; 33 m2 1,654.00 54,582.00

R Ditto sides and soffit of drop beam 19 m2 1,654.00 31,409.46

6th floor
S over 300mm wide; internal; 45 m2 1,654.00 74,430.00

T Ditto sides and soffit of drop beam 19 m2 1,654.00 31,409.46


7463

To collection : 12,997,860.59

BILL NR.2: MAIN BUILDING PAGE 2/134


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount
Externally
Wall screeding ( E-nox exterior)
Ground floor
A over 300mm wide; external. 1059 m2 950.00 1,006,278.00

B width not exceeding 300mm 620 m 285.00 176,700.00

1st floor
C over 300mm wide; external. 1140 m2 950.00 1,083,380.00

D width not exceeding 300mm 608 m 285.00 173,280.00

2nd floor
E over 300mm wide; external. 1176 m2 950.00 1,117,580.00

F width not exceeding 300mm 620 m 285.00 176,700.00

3rd floor
G over 300mm wide; external. 1176 m2 950.00 1,117,580.00

H width not exceeding 300mm 620 m 285.00 176,700.00

4th floor
J over 300mm wide; external. 615 m2 950.00 584,221.50

K width not exceeding 300mm 242 m 285.00 68,970.00

5th floor
L over 300mm wide; external. 615 m2 950.00 584,221.50

M width not exceeding 300mm 242 m 285.00 68,970.00

6th floor
N over 300mm wide; external. 615 m2 950.00 584,221.50

P width not exceeding 300mm 242 m 285.00 68,970.00

6th floor
Q over 300mm wide; external. 504 m2 950.00 479,180.00

To collection : 7,466,952.50

BILL NR.2: MAIN BUILDING PAGE 2/135


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


No Item Description Qty Unit Rate Amount

Prepare and apply one layer sealer and one layer undercoat "dulux" silk
emulsion paint.
Ground floor
A over 300mm wide; external. 1059 m2 1,654.00 1,751,982.96

B width not exceeding 300mm 620 m 496.20 307,644.00


1st floor
C over 300mm wide; external. 1140 m2 1,654.00 1,886,221.60

D width not exceeding 300mm 620 m 496.20 307,644.00

2nd floor
E over 300mm wide; external. 859 m2 1,654.00 1,420,786.00

F width not exceeding 300mm 620 m 496.20 307,644.00

3rd floor
G over 300mm wide; external. 859 m2 1,654.00 1,420,786.00

H width not exceeding 300mm 620 m 496.20 307,644.00

4th floor
J over 300mm wide; external. 615 m2 1,654.00 1,017,160.38

K width not exceeding 300mm 242 m 496.20 120,080.40

5th floor
L over 300mm wide; external. 615 m2 1,654.00 1,017,160.38

M width not exceeding 300mm 242 m 496.20 120,080.40

6th floor
N over 300mm wide; external. 615 m2 1,654.00 1,017,160.38

P width not exceeding 300mm 242 m 496.20 120,080.40

Parapet wall
Q over 300mm wide; external. 504 m2 1,654.00 834,277.60
To collection : 11,956,352.50
Collection
PAINTING AND DECORATION

Page 2/57 4,535,552.00

Page 2/58 5,330,084.50

Page 2/59 7,462,688.00

Page 2/60 15,663,188.14

Page 2/61 12,997,860.59

Page 2/62 7,466,952.50

BILL NR.2: MAIN BUILDING PAGE 2/136


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount


Page 2/63 11,956,352.50
To Main Building Collection : 65,412,678.22

BILL NR.2: MAIN BUILDING PAGE 2/137


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

No Item Description Qty Unit Rate Amount

MALL BUILDING COLLECTION AMOUNT

SUBSTRUCTURE 388,928,125.00

FRAMES AND UPPER FLOORS 1,105,888,670.91

STAIRCASES 31,934,414.98

RAMPS 79,284,184.20

ROOF CONSTRUCTION AND ROOF COVERING 173,661,264.90

EXTERNAL AND INTERNAL WALLS 42,422,659.92

WINDOWS, CURTAIN WALL AND DOORS 259,960,685.00

FITTINGS AND FIXTURES 184,380,000.00

FLOOR FINISHING 215,498,230.60

WALL FINISHING 31,691,097.21

CEILING FINISHING 21,262,435.20

PAINTING AND DECORATONS 65,412,678.22

To GENERAL SUMMARY 2,600,324,446.13

BILL NR.2: MAIN BUILDING PAGE 2/138


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

MECHANICAL SERVICES INSTALLATION

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/139


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


BILL NO. M1: - SANITARY FITTINGS
Supply, install, test and commission the following
sanitary wares as specified in the drawings &
Specifications

Wash hand Basin half pedestal, complete with Mixer


A tap bottle trap, pop-up waste and all installation 24 Nos 164,000.00
kits( Guravit, Hangsgrohe Tap) Guravit pan or approved
equal.

Wall mounted dual flush WC Bowl made of Vitreous


B China Dual Flush Water Consumption 6.0-3.0 Lpf 28 Nos 145,600.00
Includes soft close seat,

Wall Hung (Concealed Cistern) water closet c/w soft


C 28 Nos 115,000.00
seat cover, fittings and all installation kits Guravit

Toilet roll holder


Stainless toilet roll holders with installation
D 28 Nos 30,000.00
accessories. Take (Code: TEPKPHODVC)

Floor Drain

E 10cm X 10cm Square drain with installation accessories 28 Nos 17,400.00

Urinal complete with the rinal bowl, conceal element,


F 8 Nos 507,000.00
flush button and other installation accessories

G Urinary Divider 4 Nos 101,500.00

H Hand held bidet 28 Nos 15,000.00

Mirror
600 x 700mm Top Basin wall fitted mirror c/w all
J 24 Nos 20,000.00
installation accessories.

SANITARY FITTING

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/140


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


BILL NO: M2 - COLD WATER SUPPLY AND
Internal Water Supply and Distribution
DISTRIBUTION
Supply, and deliver the following 75mm-20mm
Aquatherm PP-R Pipe and 20mm-15mmViega Multilayer
Composite Pipe PE-Xc/AL/PE-Xc
Pipeworks

A 50mm 121 m 5,886.00

B 32mm 282 m 2,664.00

C 25mm 382 m 1,675.00

D 20mm 1,141 m 1,340.00

Fittings
Elbow
E 50mm Dia 22 Nr 500.00

F 32mm Dia 33 Nr 250.00

G 25mm Dia 96 Nr 200.00

H 20mm Dia 148 Nr 100.00

Reducing Elbow
J 32 x 20mm 7 Nr 450.00

Wallplate
K 20mm 83 Nr 4,200.00

Equal Tee
L 50 x 50 x 50mm 3 Nr 1,380.00

M 32 x 32 x 32mm 18 Nr 650.00

N 25 x 25 x 25mm 94 Nr 576.00

P 20 x 20 x 20mm 32 Nr 450.00

Reducing Tee
Q 50 x 32 x 50mm 2 Nr 1,380.00

R 32 x 25 x 25mm 8 Nr 650.00

S 32 x 20 x 32mm 7 Nr 650.00

T 32 x 32 x 20mm 7 Nr 650.00

U 20 x 25 x 20mm 7 Nr 576.00

V 25 x 20 x 20mm 7 Nr 576.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/141


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/142


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


Nipple
A 50m 2 Nr 13,416.00

B 25mm X 1/2" male 72 Nr 3,104.40

C 20mm 91 Nr 2,485.00

Sockets
D 50mm 12 Nr 1,140.00

E 32mm 8 Nr 780.00

F 25mm 72 Nr 504.00

Valves
G 50mm 8 Nr 18,321.60

H 25mm Gate Valve 48 Nr 12,636.00

J 15mm Angle Valve with chrome cover plate 60 Nr 6,000.00

K 15mm Copper Flexible connector 60 Nr 4,200.00

L 50mm Non-Return Valve 2 Nr 26,640.00

M 20mm tap 83 Nr 5,500.00

Union Connector
N 50mm 28 Nr 2,500.00

Tank Connector
P 50mm 4 Nr 3,000.00

MISCELLANEOUS ACCESSORIES
Q Pressure Testing of Supply Pipes Lot

All installation Acessories e.g pipe clip-single and


R Lot
double, bushing and cap plugs etc.

Allow a provisional sum of N5,000,000:00 for payment


S of connection to FCT Water Board Mains to be 1 Lot 5,000,000.00
executed by Abuja Water Board
Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/143


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

Commissioning:
Preparation of shop and as built drawings to be
A 1 lot 250,000.00
approved by the Engineer.

Carried to collection;

COLLECTION

Page/ 3

Page/4

Page/5

COLD WATER SUPPLY AND DISTRIBUTION

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/144


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


BILL NO. : M3 -SOIL AND WASTE PIPEWORK
INSTALLATION
PVC and Polythene pipes and fittings to BS-EN 1329 and
1401
OSTENDORF
PIPES
A 200mm 100 m 16,620.00

B 110mm 62 m 5,110.80

C 75mm 13 m 3,550.00

D 50mm 88 m 2,050.80

FITTINGS
Bends (90 Degree)
E 110mm 12 Nr 1,782.00

F 75mm 2 Nr 1,215.00

G 50mm 48 Nr 840.00

Y TEES
H 110 x 110 x 110mm 36 Nr 3,062.40

J 75 x 50 x 75mm 4 Nr 2,300.00

K 50 x 50 x 50mm 44 Nr 936.00

TRAPS
L 110mm Vent Cowl 28 Nr 4,800.00

M 110mm Pan Connector 28 Nr 2,400.00

N 50mm Stainless Steel Floor Drain 28 Nr 10,750.00

P Installation accessories e.g. Brackets, Clips etc. LOT

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/145


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

Manhole 40mm plastic chamber base cover finishing


A with cast iron and 400mm extension pipe, rubber seal 2 nr 330,000.00
and other accessories

Allow a provisional sum of N15,000,000:00 for


B payment of connection to AEPB line to be executed by 1 Lot 15,000,000.00
AEPB

Carried to collection;

COLLECTION

Page/ 6

Page/7

SOIL AND WASTE PIPEWORK INSTALLATION

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/146


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


BILL NO. M4- RAINWATER
PVC and Polythene pipes and fittings to BS-EN 1329 and
1401
OSTENDORF
PIPES
A 200mm 160 m 16,620.00

B 110mm 439 m 5,110.80

FITTINGS
Bends (90 Degree)
C 110mm 72 Nr 1,782.00

Equal Tee
D 200 x 200 x 200mm 3 Nr 2,673.00

Reducing Elbow
E 200 x 110mm 2 Nr 1,782.00

Reducing Tee
F 200 x 110 x 200mm 9 Nr 2,673.00

other fittings

G 100mm Floor Drain 66 Nr 10,750.00

H 100mm Roof Drain Fullbore 17 Nr 26,400.00

Installation accessories e.g. Tangit Gum, Brackets Clips


J LOT
etc.

K 400mm width drain channel with metal grate cover LOT

RAINWATER PIPING WORKS

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/147


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


FIRE FIGHTING PIPES INSTALLATION
EQUIPMENTS FOR SPRINKLER SYSTEM

The pricing is based on the supply and installation of and


PP-R Red Fire Pipe with fusion fittings. Pipes shall be
able to withstand pressure testing to 15 bar
100mm-25mm PP-R Fire Pipe
PIPE
A 100mm dia 85 m 31,000.00

B 80mm dia 249 m 23,100.00

C 65mm dia 98 m 16,600.00

D 50mm dia 1466 m 5,440.00

E 40mm dia 510 m 3,760.00

F 32mm dia 498 m 2,160.00

G 25mm dia 1950 m 1,400.00

Tee
H 100 x 100 x 100mm 4 Nos 19,538.00

J 80 x 100 x 80mm 7 Nos 18,450.00

K 80 x 80 x 80mm 3 Nos 18,450.00

L 80 x 65 x 80mm 1 Nos 17,584.00

M 80 x 50 x 80mm 43 Nos 9,768.00

N 80 x 40 x 80mm 4 Nos 20,040.00

P 80 x 50 x 65mm 8 Nos 20,040.00

Q 80 x 25 x 80mm 31 Nos 7,765.00

R 65 x 65 x 65mm 1 Nos 18,960.00

S 65 x 50 x 65mm 11 Nos 6,862.80

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/148


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

A 65 x 25 x 65mm 3 Nos 6,862.80

B 65 x 25 x 50mm 4 Nos 6,862.80

C 50 x 50 x 50mm 6 Nos 5,224.80

D 25 x 50 x 50mm 6 Nos 5,224.80

E 40 x 25 x 40mm 1 Nos 1,600.00

F 32 x 25 x 32mm 4 Nos 1,104.00

G 25 x 32 x 25mm 2 Nos 862.50

H 25 x 25 x 25mm 18 Nos 660.00

Cross Tee

J 50 x 25 x 50 x 25mm 10 Nos 6,862.80

K 25 x 25 x 40 x 25mm 7 Nos 5,224.80

L 40 x 25 x 50 x 25mm 7 Nos 5,224.80

M 32 x 25 x 50 x 25mm 2 Nos 5,224.80

N 50 x 25 x 65 x 25mm 2 Nos 6,965.00

P 25 x 50 x 50 x 65mm 6 Nos 6,965.00

Q 25 x 50 x 50 x 50mm 3 Nos 6,965.00

R 25 x 80 x 50 x 65mm 6 Nos 15,926.40

S 25 x 80 x 50 x 80mm 15 Nos 15,926.40

T 25 x 65 x 50 x 65mm 3 Nos 10,152.00

Bend
U 100x100mm 5 Nos 16,640.00

V 80x80mm 3 Nos 13,312.00

W 65 x 50mm 4 Nos 4,776.00

X 50 x 50mm 12 Nos 2,720.00

Y 25 x 25mm 14 Nos 576.00

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/149


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

Socket
A 80mm 50 Nos 10,255.20

B 65mm 3 Nos 6,994.80

C 50mm 227 Nos 2,112.00

D 25mm 174 Nos 480.00

Reducing Socket

E 50mm x 40mm 106 Nos 2,112.00

F 50mm x 25mm 104 Nos 2,112.00

G 40mm x 32mm 111 Nos 1,260.00

H 32mm x 25mm 114 Nos 676.80

Nipple
J 80mm 7 Nos 97,200.00

K 25mm 1122 Nos 3,247.20

Union Connector (Flange)


L 80mm 14 Nos 62,880.00

Air Release Valve


M 50mm 2 Nos 56,040.00

Gate Valve
N 100mm 8 Nos 154,351.20

P 80mm 7 Nos 123,480.00

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/150


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

A Sprinkler head 1122 Nos 5,292.00

B Automatic zone control valve 7 Nos 516,000.00

C Drain valve 7 Nos 23,640.00

D Clips and hangers Lot

E Pressure Testing of Sprinkler Pipes Lot

F Lot
All installation Acessories e.g bushingand cap plugs etc.

Fire hosereel pump,FHP-1, Packaged fire pump


set,mounted on a common base frame,comprising of 1
Diesel/1 Electric/jockey self priming pumps with
G pressure vessel ,switches and gauges and all other 1 Nos 25,000,000.00
accessories for a functional installation to Mechanical
Engineer consultant specifications (137m3/hr, 112m
head) complete with butterfly valves and other
installation accessories

FIRE FIGHTING PIPES INSTALLATION


EQUIPMENTS FOR HOSE REEL & DRY RISER

The pricing is based on the supply and installation of and


PP-R Red Fire Pipe with fusion fittings. Pipes shall be
able to withstand pressure testing to 15 bar
100mm-25mm Aquatherm PP-R Fire Pipe
PIPE
H 100mm dia 96 m 31,000.00

J 50mm dia 97 m 8,320.00

K 32mm dia 79 m 2,160.00

Tee
L 100 x 100 x 100mm 2 Nos 19,538.00

M 50 x 50 x 50mm 2 Nos 9,769.00

N 32 x 32 x 32mm 4 Nos 1,250.00

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/151


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

Bend
A 100mm 7 Nos 16,640.00

B 50mm 7 Nos 2,720.00

C 32mm 16 Nos 768.00

Socket
D 100mm 10 Nos 19,840.00

E 50mm 6 Nos 6,994.80

F 32mm 6 Nos 676.80

Nipple
G 100mm 15 Nos 97,200.00

H 50mm 15 Nos 36,120.00

J 32mm 15 Nos 5,846.40

Union Connector (Flange)


K 100mm 6 Nos 62,880.00

L 50mm 15 Nos 31,560.00

M 32mm 15 Nos 14,760.00

Air Release Valve


N 50mm 2 Nos 56,040.00

Gate Valve
P 100mm 4 Nos 123,480.00

Q 50mm 16 Nos 36,360.00

R 32mm 16 Nos 15,960.00

Landing Valve
S 100mm 15 Nos 312,480.00

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/152


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

Breaching Inlet
A Twin breaching inlet with enclosure 1 Nos 269,514.00

Fire hosereel cabinet

B Double compartment fire hosereel cabinet complete 15 Nos 384,000.00


30m long flexible hose, extinguisher and spray nozzle

C 9Kg ABC Fire Extinguisher 42 Nr 50,011.50

D 5Kg Co2 Fire Extinguisher 42 Nr 60,060.00

E Clips and hangers Lot

F All installation Acessories e.g bushingand cap plugs etc. Lot

Fire hosereel pump,FHP-1, Packaged fire pump


set,mounted on a common base frame,comprising of 1
Diesel/1 Electric/jockey self priming pumps with
G pressure vessel ,switches and gauges and all other 1 Nos 300,000.00
accessories for a functional installation to Mechanical
Engineer consultant specifications (137m3/hr, 112m
head) complete with butterfly valves and other
installation accessories

Carried to collection;

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/153


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

COLLECTION

Page/9

Page/10

Page/11

Page/12

Page/13

Page/14

FIRE FIGHTING PIPES INSTALLATION


EQUIPMENTS FOR SPRINKLER SYSTEM TO
SUMMARY

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/154


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


BILL NO. M6-WATER STORAGE, TREATMENT AND
PUMPS

Water Storage tank of capacity 128,000 litres (128m3)


A 8 x 8 x 2m deep complete with all accessories such as 1 nr. 57,600,000.00
ladder, level indicator, manhole , cover sockets etc as
Raw water tank

Concrete underground treated waste tank of capacity


B 67,500 litres (67.5m3) 9 x 3 2.5m deep complete with 1 nr. 27,500,000.00
all accessories such as ladder, level indicator, manhole ,
cover sockets etc as treated water tank

Reinforced fibre Roof tank(Treated water tank) of


capacity 25,000 litres (25.0m3) size: 5.0 x 5.0 x 1.0mm
C complete with all accessories such as ladder, level 1 nr. 24,357,942.00
indicator, manhole , cover sockets etc as Clear water
tank

Steel underground Diesel tank of capacity 45,000


D litres (45m3) complete with all accessories such as vent 1 nr. 24,947,247.00
pipe, level indicator, manhole , cover sockets etc as
diesel storage tank

Steel Diesel Day tank of capacity 10,000 litres (10m3)


E complete with all accessories such as ladder, level 1 nr. 6,875,226.00
indicator, manhole , cover sockets, fuel filters etc as
diesel storage tank
Water Treatment Plant
Package water treatment unit Brackish RO Systems RO-
F 200 Series Model 'TW-4.5K-340' as manfactured by 1 nr. 43,785,546.26
Pure Aqua Inc.
Booster pumps

ELECTRIC BOOSTER PUMPS WITH NON-RETURN


VALVE ON DISCHARGE SIDE. I duty, 1 standby: head
G - 53m; flow rate - 3.5l/s; motor rating - 3kw; motor 2 nr. 4,800,000.00
speed - 2900rpm; power supply - 415-3-50 (V-Ph-Hz)
Pressure vessel 100l

DUPLICATE WATER TRANSFER PUMPS WITH NON-


RETURN VALVE ON DISCHARGE SIDE. I duty, 1
H standby: head - 20m; flow rate - 5l/s; motor rating - 2 nr. 1,200,000.00
1.2kw; motor speed - 2900rpm; power supply - 415-3-50
(V-Ph-Hz) Pressure vessel 50l

Diesel Transfer Pumps

Flow rate 3.0L/s.


Head at 15 m., motor rating;746W
J power supply 220-1-50 (V-Ph-Hz) 2 nr. 2,400,000.00
motor speed 1500rpm.Make; Lowara or equall approved
with the panells and some accessories

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/155


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/156


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


Testing :
A Allow for the testing of all the above 1 Lot 500,000.00
Commissioning:
Training of 2nr Client's personnel on Operation and
B 1 Item 145,000.00
Maintenance.

Preparation of shop and as built drawings to be


C 1 Item 245,000.00
approved by the Engineer.

COLLECTION
Page/ 14

Page/15

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/157


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


BILL NO: M7 BOREHOLES

MOBILIZATION
Mobilization of drilling equipment, materials and
A 1 sum 46,950.00
personnel to site.

Geophysical investigation to determine the most


B 1 Nos 93,900.00
suitable location for the boreholes.

DRILLING
C Construction of mud-pit for drilling process. 1 sum 18,780.00

Drilling of soft and hard rock to accommodate 150mm


D pvc casings and screens ( Provisional depth borehole) 100 m 70.45

Supply and installation of 150mm pvc casing and screens


E 100 m 53.35
including all fittings and accessories

Full development of the borehole till water is clean and


F 1 sum 70,425.00
initial chlorination.

Pumping test of the borehole to determine its maximum


G 1 sum 46,950.00
yield

H Laboratory Water Analysis. 1 sum 14,085.00

J Borehole Logging. 1 sum 46,950.00

PUMP, PIPES AND FITTINGS INSTALLATION


Supply and installation of 3HP three phase grundfos SQ
submersible pump, complete with installation of 1.25"
K dia. UPVC pipes as riser mains, Electrical wiring using 1 Nos 2,300,460.00
4x2.5mm2 copper cable, Pump Panel and all accessories
to make a complete system.

PLUMBING WORK
Allow a provisional sum of N250,000.00 for plumbing
L pipe work from the bore hole to the Raw water tank 1 Lot 250,000.00
( Provisional depth 1000m)

TESTING AND COMMISSIONING


Allow for the testing and commissioning of all the
M 1 Lot 46,950.00
installation above.

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/158


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


AIR CONDITIONING SLEEVE (SPLIT)
REFRIGERANT PIPING
REFRIGERANT PIPES (m)
A 9.5mm dia, 995 m 4,200.00

B 15.9mm dia, 995 m 5,600.00

Pipe Insulation Armaflex (m)


C 9.5mm dia, 995 m 1,033.33

D 15.9mm dia, 995 m 1,477.78

PIPE AUXILIARIES

Other materials not mentioned but required for


E installation to be complete, i.e. unions 'brackets, Lot
hangers, couplings, insulators, sleeves insulation,
armaflex tapes, glue, refrigerant gas etc

F 75mm sleeves for split units 995 m 2,850.00

CONDENSATE DRAINAGE
Supply and install pvc condensate drain pipe work as
G shown on the contract drawing. Pipes shall be insulated 995 m 4,850.00
with Armaflex insulation.

ELECTRICAL WIRING
H 4C X 4.0mm2 Flexible (Nocaco) 995 m 4,850.00

Outsdoor steel hanger


J Steel hanger 125 nr 10,500.00

Interpretation Procedures, Mobilisation and Site


K 1 items
Organisation

L Construction Documents 1 items

Commissioning and Testing of entire installation and


M 1 items
provision of Test Certificates

N 1 items
Record drawings, Operation and Maintenance Manuals

P 1 items
Mobilization and Demobilization of Tools and Equipment

AIR CONDITIONING SLEEVE (SPLIT)

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/159


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


LIFT INSTALLATIONS
X TRANSPORT SYSTEMS
X10 LIFTS

675kg (9 persons) Passenger Lift


Supply and install 'schindler' or 'KONE' 675kg (9 persons)
passenger lift as specified:
General Data
Rated load - 675kg
Number of persons - 9
Speed - 1.0m/s;
Travel - 29,400mm
Drive type -Traction gearless elevator
Drive power - 4.6kw
Control-3ks
Stop/entrance - 7/7 all in line;
Car-1
Type - steel car
No of opening - 1No
Size - width x depth x height - 1100mm x 1400mm x 2300mm
Wall - stainless steel
Ceiling - flat in white skin steel
Lighting fittings - halogen spot lighting with dimmers
Handrail - tube type handrail of stainless steel on
rear wall
Car clear height - 2300mm
Mirror - Full height on opposite car operating panel
Floor finish -Granite
Physical challenged person enabled, such sounder, brail for the blind and
entrance ramp. Compliance to BCA
Car door
Door size - 900mm
Type - one automatic centre opening door
Door finish - brushed stainless steel
Safety devices - electronic safety edge , photocell
device,pressure switch
Options include - micro movement car button, overload
safety
devices light door ray protection device (photocell), alarm bell
emergency trap door
Control System - Miconic Microprocessor car button, overload, full load
by pass, car fan/light automatic of, Lift alarm, Door final timer,
Anti-nuisance, Fireman`s control, Fireman`s switch, Emergency power
control, Digital indicator at all fall, Direction Arrow & Gongs at all floors
Intercom 3 ways (Car & Motor room) and Automatic Rescue System

TO COLLECTION

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/160


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


Lift installations (cont'd)
Landing doors
Type - One automatic Centre opening door
Door finish - brushed stainless steel
Clear width x height - 900mm x 2100mm
Safety devices - electronicmechanical locks and
contacts
Signalization
Car operation panel - one with vandal resistant button, door

Landing signalization - Micro movement call buttons/vandal resistant


call buttons, position indicator at main floor, direction arrows at others
Drive system/machinery
Drive type - general variable frequency drive
Power supply - 415V +/ –10% 50Hz 3Ph, 4 wire 3PE/5
WIRE 3PNE, 230V 50Hz 1ph (2 wire + earth)

Power input - 15KW


Location - machine roomless
Shaft
Material - reinforced concrete
Size - width x depth 2470mm x 2470mm
Pit - 1600mm
Headroom - 3150mm
Other features required - digital position indicator and hall
lanterns at ground floor, vandal resistant landing buttons
and door still angles intercommunication between car
A and lobby fire proof door (Regulation EN 81) 2 nr 50,000,000.00

UPS and Stabilizer


20KVa UPS for 15 Minutes back up power supply,
B 2 nr 4,000,000.00
Electrical Control Panel

Testing and Commisioning

Commissioning and Testing of completed installation; as


C specified and in accordance to manufacturers 1 Item 1,500,000.00
reccommendation and relevant standards

Records and Documentation


Installation generally; Allow for the following
Shop Drawings
4 Sets each; A1 paper prints, binding into sets;
D 1 Item 350,000.00
electronic copies in CD roms

Installation Drawings
4 Sets each; A1 paper prints, binding into sets;
E 1 Item 250,000.00
electronic copies in CD roms

" As fitted" or " As Built" Drawings


4 Sets each; A1 paper prints, binding into sets;
F 1 Item 200,000.00
electronic copies in CD roms
TO COLLECTION

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/161


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE


Training and Maintenace
Installation generally; Allow for
manufacturers reccomended spare parts for at least one year operation
A list with coded manufacturer's part number, qualified
and submitted along with tender 1 Item 3,500,000.00

Operating and maintenance manuals


4 Set each; in A4 paper prints, binding into copies;
B 1 Item 150,000.00
electronic copies on CD Rom

Training and Maintenance generally; Allow for the following


as detailed in sub-contractors submission and to engineers satisfaction
Training and Operation of Install facility
C 2 no. Client Personel 1 Item 150,000.00

Routine Maintenance
D Warranty Period 1 Item 300,000.00

Testing of the entire system and equipment installation


E at the expiration of Warranty period to the satisfaction 1 Item 350,000.00
of the Consultants
TO COLLECTION

COLLECTION

Page 20

Page 21

Page 22

Lift Installation carried to Summary

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/162


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

S/N DESCRIPTION QTY UNIT RATE

GRAND SUMMARY PAGE

1 SANITARY FITTINGS

2 COLD WATER SUPPLY AND DISTRIBUTION

3 SOIL AND WASTE PIPEWORK INSTALLATION

4 RAINWATER

FIRE FIGHTING PIPES INSTALLATION


5
EQUIPMENTS FOR SPRINKLER SYSTEM

6 WATER STORAGE, TREATMENT AND PUMPS

7 BOREHOLES

8 AIR CONDITIONING AND VENTILATION

9 LIFT INSTALLATION

MECHANICAL INSTALLATION CARRIED TO


SUMMARY

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/163


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/164


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

3,936,000.00

4,076,800.00

3,220,000.00

840,000.00

487,200.00

4,056,000.00

406,000.00

420,000.00

480,000.00

17,922,000.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/165


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

712,206.00

750,182.40

639,347.50

1,528,538.00

11,000.00

8,250.00

19,200.00

14,800.00

3,150.00

348,600.00

4,140.00

11,700.00

54,144.00

14,400.00

2,760.00

5,200.00

4,550.00

4,550.00

4,032.00

4,032.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/166


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

4,144,781.90

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/167


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

26,832.00

223,516.80

226,135.00

13,680.00

6,240.00

36,288.00

146,572.80

606,528.00

360,000.00

252,000.00

53,280.00

456,500.00

70,000.00

12,000.00

2,000,000.00

2,000,000.00

5,000,000.00

11,489,572.60

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/168


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

250,000.00

250,000.00

4,144,781.90

11,489,572.60

250,000.00

15,884,354.50

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/169


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

1,662,000.00

316,869.60

46,150.00

180,470.40

21,384.00

2,430.00

40,320.00

110,246.40

9,200.00

41,184.00

134,400.00

67,200.00

301,000.00

3,000,000.00

5,932,854.40

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/170


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

660,000.00

15,000,000.00

15,660,000.00

5,932,854.40

15,660,000.00

21,592,854.40

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/171


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

2,659,200.00

2,243,641.20

128,304.00

8,019.00

3,564.00

24,057.00

709,500.00

448,800.00

500,000.00

2,000,000.00

8,725,085.20

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/172


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

2,635,000.00

5,751,900.00

1,626,800.00

7,975,040.00

1,917,600.00

1,075,680.00

2,730,000.00

78,152.00

129,150.00

55,350.00

17,584.00

420,024.00

80,160.00

160,320.00

240,715.00

18,960.00

75,490.80

24,987,925.80

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/173


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

20,588.40

27,451.20

31,348.80

31,348.80

1,600.00

4,416.00

1,725.00

11,880.00

68,628.00

36,573.60

36,573.60

10,449.60

13,930.00

41,790.00

20,895.00

95,558.40

238,896.00

30,456.00

83,200.00

39,936.00

19,104.00

32,640.00

8,064.00

907,052.40

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/174


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

512,760.00

20,984.40

479,424.00

83,520.00

223,872.00

219,648.00

139,860.00

77,155.20

680,400.00

3,643,358.40

880,320.00

112,080.00

1,234,809.60

864,360.00

9,172,551.60

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/175


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

5,937,624.00

3,612,000.00

165,480.00

2,000,000.00

1,000,000.00

1,000,000.00

25,000,000.00

2,976,000.00

807,040.00

170,640.00

39,076.00

19,538.00

5,000.00

42,732,398.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/176


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

116,480.00

19,040.00

12,288.00

198,400.00

41,968.80

4,060.80

1,458,000.00

541,800.00

87,696.00

377,280.00

473,400.00

221,400.00

112,080.00

493,920.00

581,760.00

255,360.00

4,687,200.00

9,682,133.60

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/177


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

269,514.00

5,760,000.00

2,100,483.00

2,522,520.00

1,000,000.00

2,000,000.00

300,000.00

13,952,517.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/178


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

24,987,925.80

907,052.40

9,172,551.60

42,732,398.00

9,682,133.60

13,952,517.00

101,434,578.40

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/179


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

57,600,000.00

27,500,000.00

24,357,942.00

24,947,247.00

6,875,226.00

43,785,546.26

9,600,000.00

2,400,000.00

4,800,000.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/180


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

201,865,961.26

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/181


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

500,000.00

145,000.00

245,000.00

890,000.00

201,865,961.26

890,000.00

202,755,961.26

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/182


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

46,950.00

93,900.00

18,780.00

7,045.00

5,335.00

70,425.00

46,950.00

14,085.00

46,950.00

2,300,460.00

250,000.00

46,950.00

2,947,830.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/183


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

4,179,000.00

5,572,000.00

1,028,163.35

1,470,391.10

5,600,000.00

2,835,750.00

4,825,750.00

4,825,750.00

1,312,500.00

1,500,000.00

1,500,000.00

1,500,000.00

1,500,000.00

4,000,000.00

41,649,304.45

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/184


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

0.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/185


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

100,000,000.00

8,000,000.00

1,500,000.00

350,000.00

250,000.00

200,000.00

110,300,000.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/186


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

3,500,000.00

150,000.00

150,000.00

300,000.00

350,000.00

4,450,000.00

0.00

110,300,000.00

4,450,000.00

114,750,000.00

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/187


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Mechanical Installations

AMOUNT

17,922,000.00

15,884,354.50

21,592,854.40

8,725,085.20

101,434,578.40

202,755,961.26

2,947,830.00

41,649,304.45

114,750,000.00

527,661,968.21

BILL NR. 3: MECHANICAL INSTALLATION PAGE 3/188


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


INTERNAL LIGHTING FITTINGS AND
SWITCHES.
Supply and deliver to site, the following items
complete with all the necessary operational
accessories or approved equal:-

Supply, deliver to site, and install the following:-

A 12W led ceiling recessed spotlight (toilets) 52 nr. 12,500.00 650,000.00

B 15W led wall mounted stairways & passage fitting 15 nr. 11,520.00 172,800.00

C 22W led ceiling recessed fitting (shop area) 692 nr. 11,520.00 7,971,840.00

D 18W led surface light (car park area) 818 nr. 5,760.00 4,711,680.00

18W led surface light (lobby area, ticketing, power


E 285 nr. 5,760.00 1,641,600.00
room)

F 1 x 10W wall mounted mirror light 24 nr 35,000.00 840,000.00

G 75w 6'' extractor fan 36 nr. 40,000.00 1,440,000.00

H Hand dryer 8 nr. 35,000.00 280,000.00

INTERNAL LIGHTING FITTINGS AND


SWITCHES. 17,707,920.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/189


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/NO DESCRIPTION QTY UNIT RATE AMOUNT


SWITCHES AND SOCKET
Supply, deliver to site, and install the following:-
(Legrand or Approved Equal)

SWITCHES
A 10A, 1 Gang, 1 Way Switch 'LEGRAND' 175 No. 1,800.00 315,000.00

B 10A, 2 Gang, 1 Way Switch 'LEGRAND' 59 No. 2,200.00 129,800.00

C 10A, 3 Gang, 1 Way Switch 'LEGRAND' 7 No. 4,650.00 32,550.00

SOCKET AND POWER OUTLET


D 13A, single switched socket outlets 308 No. 3,168.00 975,744.00

E 13A, Double switched socket outlets 356 No. 4,608.00 1,640,448.00

20A Air condition switch with neons 'LEGRAND' (Ac)


F 119 No. 5,830.00 693,770.00

CONDUITING AND WIRING (using conductor from


NOCACO,Nigerchin or Cable metal)

Allow for conduiting complete with fittings -knock out


boxes, bushing etc (25mm PVC) of all 13A, 15A, 20A,
G 783 Pts 2,990.00 2,341,170.00
Cooker Control Units and TV outlets in concealed
system. (Niger pipe or approved equal).

Allow for wiring of all 15A & 20A socket outlets,


cooker and Ac outlet in concealed PVC conduits using
H 119 Pts 9,717.00 1,156,323.00
3 nos x 4mm2 PVC single core copper cables
(Nigerchine, Kablemetal or Nocaco).

Allow for wiring of all 13A socket outlets point using


J 3 nos 2.5mm2 single core PVC insulated copper cable 664 Pts 2,990.00 1,985,360.00
(Nigerchine, Kablemetal or Nocaco).

Allow for wiring of all lighting points and switches


K using 3 nos x 1.5mm2 single core copper cable with 2,171 Pts 2,691.00 5,842,161.00
different colour (Nigerchine or Nocaco).

SWITCHES AND SOCKET 15,112,326.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/190


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT

Supply and deliver to site, the following complete with


all the necessary installation accessories :-

100A, SP&N,4ways Consumer unit complete with 32A


A MCB , RCCB, rated sub circuit MCBs and blank off 1 No. 35,000.00 35,000.00
spare way for future use, ABB.

100A, SP&N,6ways Consumer unit complete with 32A


B MCB , RCCB, rated sub circuit MCBs and blank off 104 No. 55,208.00 5,741,632.00
spare way for future use, ABB.

100A, SP&N, 8ways Consumer unit complete with 32A


C MCB , RCCB, rated sub circuit MCBs and blank off 3 No. 75,800.00 227,400.00
spare way for furture use, ABB.

100A, TP&N, 8ways Distribution board complete with


D 63A MCB , RCCB, rated sub circuit MCBs and blank 18 No. 250,800.00 4,514,400.00
off spare way for furture use, ABB.

100A, TP&N,4ways Consumer unit complete with 32A


E MCB , RCCB, rated sub circuit MCBs and blank off 2 No. 128,250.00 256,500.00
spare way for future use, ABB.

Sub-Total C/F to Summary 10,774,932.00


S/N DESCRIPTION QTY UNIT RATE AMOUNT
SUMMARY LIGHTING & POWER

A LIGHTING FITTINGS & ACCESSORIES 17,707,920.00

B SWITCHES AND SOCKET 15,112,326.00

C DISTRIBUTION BOARD 10,774,932.00

SUMMARY LIGHTING & POWER 43,595,178.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/191


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


PANELS & CABLING/LIGHTING
PROTECTION/EARTHING/CABLE TRAY
CABLE

Supply, deliver to site, and install and connect the


following cables, complete with glands, lug etc.
(Nigerchin, Nocaco or approved equal)
A 1c X 8 X 500mm2 pvc/pvc copper cable 50 Lm 475,200.00 23,760,000.00

B 1c X 4 X 500mm2 pvc/pvc copper cable 50 Lm 237,600.00 11,880,000.00

C 4c X 240mm2 pvc/pvc copper cable 60 Lm 156,653.00 9,399,180.00

D 3 X 1c X 95mm copper/xlpe/pvc cable 60 Lm 43,470.00 2,608,200.00

E 4c X 70mm2 Pvc/Pvc cu 373 Lm 45,550.00 16,990,150.00

F 4C X 35mm2 pvc/pvc cu 321 Lm 31,083.00 9,977,643.00

G 5c x 16mm2 Pvc/Pvc cu 442 Lm 18,506.25 8,179,762.50

H 4c x 16mm2 Pvc/Pvc cu 398 Lm 15,000.00 5,970,000.00

J 4c x 6mm2 Pvc/Pvc cu 50 Lm 6,700.00 335,000.00

K 3c x 10mm2 Pvc/Pvc copper cable 2976 Lm 7,950.00 23,659,200.00

L 3 x 6mm2 Pvc/Pvc copper cable 763 Lm 5,022.00 3,831,786.00

INSTALLATION AND CONNECTION


Allow for installation and connection of copper cables
M using cable trays, conduits, cable clips,lugs etc. 1 Lot 1,000,000.00 1,000,000.00

CABLE 117,590,921.50

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/192


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


PANEL
Equipment: Medium Voltage Panel 'SCHNIEDER,
ABB OR MERLIN GERIN'. All MV Panels shall
come with all necessary components for connection
to the building management system.

L.V. Switch panel comprising of the followings:


800A TP Busbar
- A set of ammeters, voltmeters, supply ‘ON’ indicator
A
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
2 No. 800A TPN Incomer MCCB 1 nr 6,550,000.00 6,550,000.00
- Set of 800A TPN Busbars
- 1Nr 800A 4P Motorized MCCB Incomers
- 4Nr 200A 3P MCCB outgoing
- 3Nr 100A 3P MCCB outgoings
- 5Nr 63A 3P MCCB outgoings
- 2Nr 100A 3P MCCB spare
- 2 Nr (class 1 & class 2) Surge Arrestor protected
with
Blanked off spaces for future addition of outgoing
circuits.

Ground Floor L.V. Switch panel comprising of the


followings:
200A TP Busbar
B - A set of ammeters, voltmeters, supply ‘ON’ indicator
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
1 No. 200A TPN Incomer MCCB 1 nr. 850,000.00 850,000.00
3No. 63A TPN Outgoing MCCB
25No. 32A SPN Outgoing MCCB
1No. 63A TPN Outgoing MCCB spare
2No. 32A SPN Outgoing MCCB spare
- 1 Nr 200A Surge protector with
Blanked off spaces for future addition of outgoing
circuits.

First Floor L.V. Switch panel comprising of the


followings:
200A TP Busbar
C - A set of ammeters, voltmeters, supply ‘ON’ indicator
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
1 No. 200A TPN Incomer MCCB 1 nr. 850,000.00 850,000.00
3No. 63A TPN Outgoing MCCB
33No. 32A SPN Outgoing MCCB
1No. 63A TPN Outgoing MCCB spare
2No. 32A SPN Outgoing MCCB spare
- 1 Nr 200A Surge protector with
Blanked off spaces for future addition of outgoing
circuits.

TO COLLECTION 8,250,000.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/193


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT

Second Floor L.V. Switch panel comprising of the


followings:
200A TP Busbar
A - A set of ammeters, voltmeters, supply ‘ON’ indicator
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
1 No. 200A TPN Incomer MCCB 1 nr. 850,000.00 850,000.00
3No. 63A TPN Outgoing MCCB
33No. 32A SPN Outgoing MCCB
1No. 63A TPN Outgoing MCCB spare
2No. 32A SPN Outgoing MCCB spare
- 1 Nr 200A Surge protector with
Blanked off spaces for future addition of outgoing
circuits.

Third Floor L.V. Switch panel comprising of the


followings:
200A TP Busbar
B - A set of ammeters, voltmeters, supply ‘ON’ indicator
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
1 No. 200A TPN Incomer MCCB 1 nr. 850,000.00 850,000.00
5No. 63A TPN Outgoing MCCB
31No. 32A SPN Outgoing MCCB
1No. 63A TPN Outgoing MCCB spare
2No. 32A SPN Outgoing MCCB spare
- 1 Nr 200A Surge protector with
Blanked off spaces for future addition of outgoing
circuits.

Fourth Floor L.V. Switch panel comprising of the


followings:
100A TP Busbar
C - A set of ammeters, voltmeters, supply ‘ON’ indicator
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
1 No. 100A TPN Incomer MCCB 1 nr. 450,000.00 450,000.00
2No. 63A TPN Outgoing MCCB
1No. 32A SPN Outgoing MCCB
1No. 63A TPN Outgoing MCCB spare
1No. 32A SPN Outgoing MCCB spare
- 1 Nr 250A Surge protector with
Blanked off spaces for future addition of outgoing
circuits.

TO COLLECTION 2,150,000.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/194


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT

Fifth Floor L.V. Switch panel comprising of the


followings:
100A TP Busbar
A - A set of ammeters, voltmeters, supply ‘ON’ indicator
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
1 No. 100A TPN Incomer MCCB 1 nr. 450,000.00 450,000.00
2No. 63A TPN Outgoing MCCB
1No. 32A SPN Outgoing MCCB
1No. 63A TPN Outgoing MCCB spare
1No. 32A SPN Outgoing MCCB spare
- 1 Nr 250A Surge protector with
Blanked off spaces for future addition of outgoing
circuits.

Sixth Floor L.V. Switch panel comprising of the


followings:
100A TP Busbar
B - A set of ammeters, voltmeters, supply ‘ON’ indicator
lamps, kilowatt/hour meter, frequency meter and
power factor meter.
- Over current, earth fault, and over voltage
protection relays.
1 No. 100A TPN Incomer MCCB 1 nr. 450,000.00 450,000.00
2No. 63A TPN Outgoing MCCB
1No. 32A SPN Outgoing MCCB
1No. 63A TPN Outgoing MCCB spare
1No. 32A SPN Outgoing MCCB spare
- 1 Nr 250A Surge protector with
Blanked off spaces for future addition of outgoing
circuits.

TO COLLECTION 900,000.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/195


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

COLLECTION

Page/5 8,250,000.00

Page/6 2,150,000.00

Page/7 900,000.00

PANEL 11,300,000.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/196


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


LIGHTNING PROTECTION AND STRUCTURAL EARTHING
Supply the following with all the associated
Installation accessories
A Prevectron 2 S6.60 air Terminal (INDELEC) 1 Nr 800,000.00 800,000.00

B 25mmx 3mm Bare copper tape 400 m 5,500.00 2,200,000.00

C 70mm x 3mm bare copper condutor 133 m 8,500.00 1,130,500.00

900x900mm lattice copper Earth plate FURSE PE110


D 12 Nr 7,600.00 91,200.00

E Concrete Inspection pit FURSE PT005 12 Nr 8,000.00 96,000.00

F 16mmx1800mm Copper Earth rods FURSE RB 005 96 Nr 22,000.00 2,112,000.00

G Screw Down Test Clamp 12 Nr 8,100.00 97,200.00

Allow for all associated saddles clips,bolts and nuts


H and soil conditioning agents to achieve acceptable 1 Lot 500,000.00 500,000.00
earthing resistance

5m galvanised iron pole to serve mast for mounting


J 1 Nr 18,800.00 18,800.00
Prevectron 2 S6.60 air Terminal

K Allow for earth resistance test 1 lot 500,000.00 500,000.00

L Allow for the earthing of all equipment metal works 1 lot 1,000,000.00 1,000,000.00
within the building to the reinforcement and steel
works at all floors and sub-structure levels

LIGHTNING PROTECTION AND STRUCTURAL EARTHING 8,545,700.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/197


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


CABLE TRAY
Hot dip galvanized perforated cable tray with
returned flange 5cm deep for LV cables. Make Ardic
or approve equal
A Cable trays, 500 x 50 mm wide. 945 Lm 24,160.00 22,831,200.00

B Cable trays, 200 x 50mm wide. 945 Lm 12,906.00 12,196,170.00

Equipment Sundries 'SCHNEIDER ELECTRIC'


C Service Meters (+/- 5no) 118 No 110,000.00 12,980,000.00

CABLE TRAY 48,007,370.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/198


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT

SUMMARY
PANELS & CABLING/LIGHTING
PROTECTION/EARTHING/CABLE TRAY
CABLE 117,590,921.50

PANEL 11,300,000.00

LIGHTING PROTECTION AND STRUCTURAL


8,545,700.00
EARTHING

CABLE TRAY 48,007,370.00

PANELS & CABLING/LIGHTING 185,443,991.50


PROTECTION/EARTHING/CABLE TRAY

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/199


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


SMOKE DETECTION & FIRE ALARM SYSTEM
Conduiting works

Allow for provision of PVC conduiting for all Smoke


detector, heat detector, Break glass and Bell point
A 496 Nos 10,000.00 4,960,000.00
connected to main panel and Mimic panel (Niger pipes,
Diginty or approved equal)

Wiring works

Allow for wiring of all Smoke detector, heat detector,


Break glass and Bell point connected to main panel and
B 496 Nos 12,000.00 5,952,000.00
Mimic panel using 2 x 1.5mm fire retendant cable.
(Approved by the consultant)

Fittings
Addressable Ceiling mounted smoke detectors with
C 174 Nos 35,000.00 6,090,000.00
intergral sounder and LED indicator (Gent/Zeta))

addressable ceiling mounted Heat detector with


D 184 No. 28,000.00 5,152,000.00
intergral sounder and LED indicator (Gent or Zeta)

E Addressable Manual break glass call point 34 Nos 45,000.00 1,530,000.00

F Electronic sounder 34 Nos 42,000.00 1,428,000.00

G 4 Loop Vigilon fire alarm control panel 1 Nos 3,500,000.00 3,500,000.00

H Sounder 34 Nos 45,000.00 1,530,000.00

J Alarm flasher 34 Nos 60,000.00 2,040,000.00

K Repeater Panel 1 Nos 750,000.00 750,000.00

SMOKE DETECTION & FIRE ALARM SYSTEM 32,932,000.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/200


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


TELECOMMUNICATIONS
Telephone outlets of TENBY or other equal and
approved manufacturer including fixing and all
A necessary connections and fixing accessories in 113 Nos 5,000.00 565,000.00
accordance with the manufacturer's instructions in:

Cables and conduits


PVC Sheathed twisted pair copper cables as of
ALKATEL, KABEL METAL or other approved drawn
into 20 diameter concealed UPVC conduits; rates to
include for all cables, conduits and other accessories
neccessary for complete installation all in accordance
with the manufacturer's instructions in:

B 0.5Ω Cable for telephone outlet points 113 Nos 18,400.00 2,079,200.00

TELECOMMUNICATIONS 2,644,200.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/201


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


CCTV INSTALLATION
The CCTV Surveillance system shall be the BOSCH
Video System

Day/Night Vario-focus IP camera (fixed,


A 41 Nr 92,225.00 3,781,225.00
indoor/outdoor)

B PTZ Dome IP camera (outdoor) 4 Nr 230,000.00 920,000.00

C IP Ceiling mounted fixed dome camera 2MP 56 Nr 80,600.00 4,513,600.00

D U-Rack for CCTV Control equipment (22 U RACK) 1 Nr 350,000.00 350,000.00

E Turbo 120 Channel 1080P NVR 1 Nr 8,500,000.00 8,500,000.00

F 18 Way CCTV Power Supply Box 1 Nr 46,000.00 46,000.00

G Samsung 42'' smart Full HD 1 Nr 280,000.00 280,000.00

H 1 TB HDD 1 Nr 67,500.00 67,500.00

J Winpossee RG 59 CCTV Video & Signal Cable 1 Lot 500,000.00 500,000.00

K Cat 6e Unshielded twisted pair cable: Systimax 1 Lot 500,000.00 500,000.00

L Cat 6e shielded twisted pair cable: Systimax 1 Lot 500,000.00 500,000.00

Installation accessories such as fibre optics


M 1 Lot 2,000,000.00 2,000,000.00
connectors, termination accessories, screws, etc

CCTV INSTALLATION 21,958,325.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/202


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


PUBLIC ADDRESS SYSTEM

A Ceiling Public address speaker 60 Nr 45,000.00 2,700,000.00

B High level wall mounted public address speaker 70 Nr 120,000.00 8,400,000.00

C Mixer amplifier 1 Nr 542,500.00 542,500.00

D Easy line SD, tuner source 1 Nr 80,600.00 80,600.00

E U-Rack for PAS Control equipment (42 ELV RACK) 1 Nr 437,500.00 437,500.00

Installation accessories such as, cables and


F 1 Lot 3,500,000.00 3,500,000.00
termination accessories, screws, etc

PUBLIC ADDRESS SYSTEM 15,660,600.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/203


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


CABLE TRAY
Hot dip galvanized perforated cable tray with
returned flange 5cm deep for LV cables. Make
Ardic or approve equal

A Cable trays, 200 x 60mm wide. 1215 Lm 12,906.00 15,680,790.00

CABLE TRAY 15,680,790.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/204


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


SUMMARY FOR ELV

A SMOKE DETECTION & FIRE ALARM SYSTEM 32,932,000.00

B COMMUNICATIONS INSTALLATIONS 2,644,200.00

C CCTV INSTALLATION 21,958,325.00

D PUBLIC ADDRESS SYSTEM 15,660,600.00

E CABLE TRAY INSTALLATION 15,680,790.00

EXTRA LOW VOLTAGE (ELV) 88,875,915.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/205


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT


IN POWER SUPPLY
Transformer

Supply, install and commission 500KVA, 11/0.415-KV,


3-phase, 50-Hz, Delta-Delta, step-down, double
wound, oil-immersed windings, oil-natural, air-natural
(ONAN) cooled, outdoor type Transformer complete
A with off-Load tap changer as well as all other 1 Nos 11,000,000.00 11,000,000.00
standard fittings and accessories applicable to the
type, capacity, Temperature and Tropical weather
conditions inclusive of all necessary installation
accessories. (Schneider or approved equal)

Generator

500KVA 415V 1500RPM 50Hz Starting Prime Gen.


Set, Brushless Revolving Field Type, 4-Pole self
B regulating automatic voltage regulator, solid state, 1 Nos 74,550,000.00 74,550,000.00
class 'H' insulation and Tropical Impregnation with
the following:

200KVA 415V 1500RPM 50Hz Starting Prime Gen.


Set, Brushless Revolving Field Type, 4-Pole self
C regulating automatic voltage regulator, solid state, 1 Nos 35,450,000.00 35,450,000.00
class 'H' insulation and Tropical Impregnation with
the following:

D 32A TPN SLK 2 Nos 60,000.00 120,000.00

E Allow for earthing of all equipment 2 Lot 1,000,000.00 2,000,000.00

Reinforced insitu concrete grade 25.5; sawn form


F work; reinforcement; excavation and backfilling and 2 No 1,500,000.00 3,000,000.00
disposal of surplus material 800x800mm thick
Transformer Plinth

Allow for the Construction of Gantry within the


G 2 No 1,000,000.00 2,000,000.00
switch yard

11KV 630A 50Hz SF-6 , 2-Way Extensible (Ring


H Master Range) Ring Main Unit - RMU 1 suitable for 1 No 6,300,000.00 6,300,000.00
outdoor use (IP54 enclosure), and complete with all
installation accessories, comprising: CE - 2 200A
Extensible Circuit Breakers; Ref: Schineder/ABB

TO COLLECTION 134,420,000.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/206


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

11kV AEDC METERING UNIT


Supply and Installation of AEDC 11kV Metering
A 1 No 4,000,000.00 4,000,000.00
Unit/Panel

Isolator/Synchronizing panel

800A TPN Isolator complete with metering and


B 1 No 1,975,000.00 1,975,000.00
instrumentation

800A TPN 415V 50Hz AMF/ATS Switching Panel


C with motorised breakers and manual bypass with 1 No 6,525,000.00 6,525,000.00
metering and instrumentation

800A TPN 415V 50Hz Automatic Synchronizing Panel


complete with auto load sensing, load sharing devices
with associated controls, and the following: 1 Set of
D 1 No 13,525,000.00 13,525,000.00
hard drawn high conductivity 800A TPN, 50Hz, 415V
copper Busbars; 1No 800A TPN MCCBs Incomers; 1No
800A TPN ACBS outgoings; Metering and
instrumentation

TO COLLECTION 26,025,000.00
S/N DESCRIPTION QTY UNIT RATE AMOUNT
COLLECTION FOR POWER

A Page/18 134,420,000.00

B Page/19 26,025,000.00

POWER SUPPLY 160,445,000.00

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/207


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA Electrical Installations

S/N DESCRIPTION QTY UNIT RATE AMOUNT

SUMMARY

A LIGHTING & POWER 43,595,178.00

PANELS & CABLING/LIGHTING


185,443,991.50
B PROTECTION/EARTHING/CABLE TRAY

C EXTRA LOW VOLTAGE 88,875,915.00

D POWER SUPPLY 160,445,000.00

ELECTRICAL INSTALLATIONS 478,360,084.50

BILL NR. 4: ELECTRICAL INSTALLATIONS PAGE 4/208


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

GENERAL SUMMARY
S/N DESCRIPTION QTY UNIT RATE AMOUNT

1 BILL NR 1 : PRELIMINARIES AND GENERAL ITEMS 1 Nr 144,253,859.95 144,253,859.95

2 BILL NR 2: MAIN BUILDING 1 Nr 2,600,324,446.13 2,600,324,446.13

3 BILL NR 3 : MECHANICAL INSTALLATION 1 Nr 527,661,968.21 527,661,968.21

4 BILL NR 4 : ELECTRICAL INSTALLATION 1 Nr 478,360,084.50 478,360,084.50

SUB-TOTAL 1 3,750,600,358.80

GENERAL CONTINGENCIES

Allow the sum of N80,000,000.00 ( EIGHTY Million


Naira Only) for unforeseen additional works in respect
5 of the Entire Works to be expended as directed 80,000,000.00

SUB-TOTAL 11 3,830,600,358.80

ADD
6 VAT @ 7.5% 7.50% 287,295,026.91

TOTAL ESTIMATED PROJECT COST 4,117,895,385.71

COMPLETION PERIOD: Within _______ Weeks of officially taking possession of Site

SIGNED BY THE SAID ____________________ _____________________


Name Signature

____________________
Designation

FOR AND ON BEHALF OF __________________________________________________


Name of Company

General Summary GS/209


PROPOSED COMMERCIAL DEVELOPMENT AT WUSE MARKET : ABUJA

GENERAL SUMMARY
S/N DESCRIPTION QTY UNIT RATE AMOUNT

1 BILL NR 1 : PRELIMINARIES AND GENERAL ITEMS 1 Nr 13,928,792.91 13,928,792.91

2 BILL NR 2: MAIN BUILDING 1 Nr 257,615,250.00 257,615,250.00

3 BILL NR 3 : MECHANICAL INSTALLATION 1 Nr 20,960,608.25 20,960,608.25

4 BILL NR 4 : ELECTRICAL INSTALLATION 1 Nr 0.00 -

SUB-TOTAL 1 292,504,651.16

GENERAL CONTINGENCIES

Allow the sum of N80,000,000.00 ( EIGHTY Million


Naira Only) for unforeseen additional works in respect
5 of the Entire Works to be expended as directed 500,000.00

SUB-TOTAL 11 293,004,651.16

ADD
6 VAT @ 7.5% 7.50% 21,975,348.84

TOTAL ESTIMATED PROJECT COST 314,980,000.00

COMPLETION PERIOD: Within _______ Weeks of officially taking possession of Site

SIGNED BY THE SAID ____________________ _____________________


Name Signature

____________________
Designation

FOR AND ON BEHALF OF __________________________________________________


Name of Company

General Summary GS/210


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT (N)

CONDITIONS OF CONTRACT

Conditions of Contract shall be the FIDIC 99 Condition of Contract for Construction


for building and engineering works designed by the Employer. For convenience,
only those provisions considered to have an obvious financial effect are set out
below and against each provision, the price shall be inserted for

A Performance Bond item

B Advance payment bond item

Insurance specific to the Contract

C Loss/damage to property item

D Workmen Compensation Policy item

E Third Party Liability item

F Contractors All Risk Policy item ₦10,500,000.00

Cost Related to other Clauses in the Condition of Contract

The Contractor shall include/ allow for complying in all respects with the Conditions
G of Contract Clauses 1 to 20 as per FIDIC 99 Condition of Contract for Construction item
for building and engineering works designed by the Employer.

Mobilization and demobilization

Mobilization of all supervisions, labours, plants, materials and equipments


H item ₦5,000,000.00
necessary for the proper execution of the Works.

De-mobilization of all supervisions, labours, plants, materials and equipments


J item ₦7,500,000.00
necessary for the proper execution of the Works

Access to site

Construct access to the site and obtain by prior arrangement with the Engineer.
K Alter, shift and adopt from time to time as necessary in order to access the site or item
building

Use of the site

L The site shall not be used for any purpose other than the execution of the Contract item

Limitations of working space

The Contractor will allocate the site as indicated on the Engineer's site plans and he
must allow for setting out of temporary office accommodation and for storage of
M materials etc. Either within the site areas or at such other location that the item
Contractor may provide himself and at his own cost as per the Municipality
Regulations.

The Contractor shall take all reasonable precautions to prevent work people
N including those employed by the Sub-contractors from trespassing on adjoining
owner's property.
item
Limitations of working hours

Working hours shall be as per the labour law of Nigeria (Nigeria or Governing Law).
P Contractor shall allow for any additional working hours in order to achieve item
construction programme in coordination with Engineer

Existing services

The Contractor shall ascertain for himself the location of existing services on, under
or over the site. He shall take precautions to protect all such services within the
Q item
confines of the site and immediately make good any damage at his own expenses
in coordination with service authorities

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 211


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S ADMINISTRATIVE ARRANGEMENTS

Site Administration.

The Contractor shall allow for providing all that is required for the proper
A administration of the contract at site level and in particular for complying in all item
respects with the relevant clauses in the Standard Conditions of Contract.

Supervision

Contractor shall allow for supervision and the site agent shall be replaced with
B item
appropriate person within reasonable time as approved by the Engineer

Security

The Contractor shall be responsible for and shall allow for providing 24 hours
C item
security through-out construction period

Safety, Health and Welfare of Workpeople

Provide for all costs and charges incurred by complying with all safety, health and
D welfare regulations, pertaining to staff and work people employed on the site item
including those employed by all sub-contractors

The Contractor shall be responsible for and shall allow for providing medical
E facilities including emergency medical facilities for his staff and shall made these item
available to Engineer's staff

Transport of Workpeople

Allow for the cost of all transport to and from site on the work people engaged on
F item
the site

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 212


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONSTRUCTION PLANTS

Small Plant and Tools

Provide for all necessary small plants and tools for the proper execution and
A item
completion of the Works

Scaffolding

Provide all necessary temporary scaffolding for the proper execution and
completion of the Works. Alter, relocate and adapt from time to time as necessary.
B The Contractor is to ascertain whether any scaffolding is required by any sub- item
contractor before striking. If the Contractor should strike any of his scaffolding and
is so required it shall be re-erected at his own expense.

Cranes and Lifting Plant

Provide all necessary mobile/ tower cranes and lifting plant for the proper execution
C and completion of the contract. (Note: The tower crane should not be installed in
permanent structure)

Site Transport

D Contractor shall allow for transportation of plant and equipment. item

Plants Required for Specific Trades

Provide all necessary plants required for specific trades for the proper execution
E item
and completion of the contract.

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 213


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Sign Boards

The Contractor shall allow for the provision, erection and maintenance of necessary
site notice board as required by the Engineer to display image of the project, project
A nr
name, the Employer's name and names of all Consultants associated with the
Project

The sign boards shall be complete weather durable with all necessary foundations,
supports, framing, painting and sign writing in English denoting the title of the
project and name of the Employer, Consultants and contractors with their
B item
respective addresses and building permit details. The Contractor shall provide all
details of the sign board to the Engineer for his approval before any work is put in
hand and to enable erection to commence in the early stages of the contract.

The Contractor shall provide sufficient lighting to sign boards which includes power
C item
supply and lighting fixture.

The Contractor shall clean, maintain and at the completion of the Contract remove
D item
the sign board, supports and foundations.

E Any authority payments item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 214


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

ENGINEER'S FACILITIES

Site Offices, Stores and other Facilities

Office construction shall be light airy manner with air-conditioned for Employer,
Engineer and Clerk of works/ General office (but not limited to three office) shall be
constructed comprising of Meeting room, toilets, pantry facilities & sample room,
etc. all as per specification

The Contractor shall construct sub-structure to place porta-cabins as per Engineer's


A item
instruction

The Contractor shall supply and place Port-a- cabins, comprising of carpet floors
B item
and all other finishes as stated in the specification

The Contractor shall Supply and install all electromechanical works including fire
C alarm and fire fighting system in accordance with ROP standard and approval of item
works as per engineer's

The Contractor shall obtain power, water, drainage and telephone to meet office
D item
requirement (separate for Employer's and Engineer's office)

The Contractor shall supply minimum of following new furniture and other items for
each office (Contractor shall provide warranty card or slip for all Electronic items)

E Desk complete with twin pedestal lockable drawers nr

F Tables nr

G Lockable filing (two drawer in each office) cabinets nr

H Storage cupboard/ book case nr

Drawing hangers complete with drawing suspension clamps or one chest of drawer
J nr
specifically designed for drawing storage

K Drafting table with adjustable stool nr

L Swivel based/ sprung back desk chair nr

M Conference table nr

N Conference chairs nr

P Visit Chairs nr

Q Fixed shelving required for storage/ display of samples and other materials nr

R Electric kettle nr

S 350 liter refrigerator nr

T Microwave oven nr

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 215


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

ENGINEER'S FACILITIES

Site Offices, Stores and other Facilities

The Contractor shall supply, install and maintain following equipment with
necessary cabling, wiring and power connection.

Telephone instruments, one in Employer's office, one in Engineer's office with


A nr
extension to general office

B Fax machine in general office nr

Colour printer photocopier and scanner on high speed (A3/A4 format, reduction/
C nr
enlargement facility, 2 sides coping, cassette feeds and sorting facility), scanner

Laptop with network facility and internet, minimum configuration; Intel Core i7,
2GHz processor, 1 TB SSD hard disk, 16 GB RAM, DVD super multi DL Rewriter,
15.4" LED monitor, in built card reader, in built web cam & mic, Wi-Fi, Bluetooth,
D nr
complete with wireless mouse, flash memory stick (8GB), printer, Anti virus, Micro
soft Office - all programs with single user license agreement, with latest softwares
(return to Employer after completion of the project)

E The Contractor shall replace any defected item during the course of Construction. item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 216


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities

Maintenance of project office and office equipment includes cleaning on daily basis
A and to provide consumable items for the use of Employer and consultant such as month
toilet soaps, towels, pantry items like clean drinking water, milk, coffee, sugar, etc.,

The Contractor shall supply of stationaries and other sundry items (copy papers, fax
papers, pens, pencils, leads, erasers, pins, staplers, pin boards, binder, paper
B month
cutter, heavy duty punching machine, mirror, waste bins, desk paper trays, clocks,
etc.).

C The Contractor shall supply of toners, special colour printing paper, CDs, DVDs, etc. month

The Contractor shall maintain site office and floor and window cleaning and removal
D month
of rubbish

The Contractor shall pay the cost of utilities. (Water, Electricity, Telephone, Internet,
E month
etc.)

The Contractor shall provide high speed ADSL internet connection with Wi-Fi for
F month
exclusive use of Employer & Engineer

The Contractor shall supply PPE for sole use of the Employer, Engineer and their
G staff visiting the site, safety helmets, safety shoes, protective eye glass, ear muffs, item
reflective jackets, etc., as requested by the Engineer

The Contractor shall maintain and provide necessary security to the Engineer's
H item
facilities after issuing of completion certificate until the Employer take over security.

J Remove Port-a-cabin, clean the area as instructed by Engineer. item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 217


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

The Contractor shall provide, erect, maintain and remove on completion all
necessary site offices, stores, mess rooms, sanitary accommodation and other
A facilities as may be required by the contractor for his own and his sub-contractors item
use, together with all associated water, drainage, electrical lighting and power, air
conditioning, telephone/ equipment and attendance.

The position of all site office stores etc. shall be to the approval of the Engineer,
and the contractor must allow for any 'off site' facilities he may require additional to
B item
the area allocated to him. Contractor shall submit the Facilities Plan for Engineer’s
approval.

Temporary Roads

Provide, maintain and alter as necessary temporary roads, paths, hard standings,
C pavement crossings and the like to and within the site. Remove and reinstate all item
ground and work disturbed when required.

Temporary Works

Supply, install, remove and handover all temporary fencing to Employer at the
D item
completion of the Works

Water for the Works

Provide all water required for the works and provide and remove on completion all
requisite temporary pipe work, pumps, storage tanks etc. The Contractor must
E item
include for obtaining water from an independent source up to the issuance of
Taking Over Certificate.

Lighting and Power for the Works

Provide all electric light and power required for the Works and remove all temporary
F item
installations on completion up to the issuance of Completion Certificate.

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 218


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

Foul Discharge

Provide necessary sewage connecting to Engineer's site office, Contractor's office


A item
and discharge as requested

Testing of Materials

The Contractor shall carry out tests by an independent third party laboratory
B approved by the Engineer as per specification and shall report all test results item
promptly to the Engineer

The Contractor shall be responsible for sending Engineer’s representatives to the


source of supply or manufacturer's works to test the materials or supervise their
C item
production whenever considered necessary and shall bear all necessary costs
related to the same.

Copies of Orders

The Contractor shall provide the Engineer with a copy of all orders for the supply of
D such materials or goods required in connection with the Works as the Engineer may item
specify.

Testing of the Works

Allow for all tests required by the specification to be carried out including all
E necessary equipment, materials and reports as per scope of Works and item
specification.

Provide water, fuel and electricity necessary for the plumbing and engineering
F item
installations.

As-built Drawings

As-built' drawings shall be six sets hard copies and one set of electronic copy in CD
in latest AutoCAD format as specified in the specification. Each set of hard copy of
G item
drawings shall be properly bound and presented in a suitable manner acceptable to
the Engineer

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 219


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

Operation and Maintenance Manuals

A Allow for O&M manuals for MEP and other works as per specifications item

The Contractor shall not be entitled for any extra payment or extension of time for
B the correction, preparation and supplying of the above mentioned drawings and item
information.

Training on Completion

Allow for trainings of Employer's staff related to all system on completion of the
C item
project

Protecting the Works

Provide for carefully covering up and protecting all of the Works by whatever means
D item
necessary as required during construction and on completion until handover

Disposal of debris

Keep the site free from debris arresting from the works during the construction
E period and leave the site free from debris on completion to the satisfaction of the item
Engineer.

Maintenance of Public and Private Roads

Allow for maintenance of public and private roads used by the Contractor around
F item
the site

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 220


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Control of Noise, Dust and Pollution

The Contractor shall take all necessary precautions in reducing noise caused by
A plant by means of mufflers, silencers, screens and the like in line with HSE item
requirements.

Watering of roads, fill granular materials as required at exit points, clean dirt carried
B item
beyond exit point on daily basis.

Provide for removing all rubbish from the site both as it accumulates from time to
C item
time and at completion.

Provide for cleaning the buildings inside and out, removing stains and touching up
D paint work and polish work and leaving the whole of the works clean, ready for item
occupation and to the satisfaction of the Engineer on completion.

The Contractor shall provide dedicated workmen to observe and clear designated
E item
areas of Foreign Object Debris as it occurs.

The Contractor shall be responsible for cleaning the site and work area completely
of all his temporary installation on completion of the Works shall be required to
grade or rake the area he has occupied to remove all traces of his occupation and
F item
leave the site as close to its original condition as possible. The Contractor shall
provide constantly available labour transport and materials to maintain the
cleanliness and tidiness of the Site.

All Statutory Obligations

The Contractor shall make every effort to comply with local authorities rulles and
G item
requirements

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 221


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Guarantee and Warrantee

The Contractor shall provide guarantee/warrantee for the items as required in the
specification. Guarantee/warrantee are to be taken in the name of the Employer
A item
and forward the originals to the Engineer prior to the issue of the certified of
completion. All Guarantee/Warrantee should be started from the date of completion.

Submittals

Prepare and submit to the Engineer all submittals, materials, working drawings,
B item
record drawings, procurement schedule etc. as required by the Specification.

Samples

The Contractor shall allow for submitting samples of all materials and goods as
required to the Engineer/specification for obtaining his approval, and for paying all
C item
fees and charges etc., in connection therewith. (after approval sample may be used
in construction of the project)

Technical Literature

The Contractor shall obtain copies of the latest editions of standard manuals
D specified in the specification to be kept on site for the use of the Engineer. Upon item
completion of the project they are to be handed over to the Employer.

Statutory Obligations

Allow for all costs for permission, licenses, inspection compliance to regulation and
E item
no objection certificates.

Shop Drawings

F Prepare and submit to the Engineer all shop drawings required by the specification. item

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 222


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Employer's Tradesmen, Direct Contractors and other Authorities

The Contractor shall note that the Employer may appoint other contractors to
carryout certain items of specialist, ancillary or other works. The contractor shall
afford any such other contractors, Employers own workmen or any other duly
A item
constituted authorities all reasonable opportunity to resource and execute their
works. The Contractor shall include for liaising with all such other contractors, direct
workmen or other authorities and for co-coordinating his works with

Special Requirements for Programmes of Progress Charts

A preliminary outline programme for carrying out the works shall be prepared by the
Contractor and submitted with the tender. Within 14 days upon receipt of Engineer's
B order to commence the work, the Contractor shall prepare a detailed programme in item
the manner as detailed in the specification for carrying out the works and shall
submit copies of the programme to the Engineer for his approval

This shall be accompanied by labour force monthly loading for each trade, including
C item
sub-contractors, supervisory staff, cash flow and details of materials procurement.

The programme shall be updated and expanded at such times as stated in the
specification and shall be submitted to the Engineer in monthly intervals. Two week
D look ahead programmes shall be Look ahead program shall contains with details of item
Plan and method he propose to employ. No works based on such proposals shall
proceed without the approval of Engineer

In addition to the above, the Contractor shall submit in a Monthly Progress Report
E item
showing all the details in accordance as specified in the

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 223


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Photographs

Each month during the progress of the works, the Contractor shall arrange at his
own expense the taking of progress photographs from viewpoints selected by the
Engineer sufficient to record progress at the appropriate stage of the work. Six
copies comprising 36 No. 100x75 mm and 6 No. 300 x 250 mm colour photographs
presented in a proper manner approved by the Engineer, together with negatives
D and electronic copy shall be handed to the Engineer for his retention. The item
photographs shall be properly documented with dates, details of the viewpoint and
location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written
permission. The Contractor shall provide suitable albums for the correct storage of
the above photographs as specified in the Specification.

CARRIED TO COLLECTION PAGE N

BILL NO-01/ 224


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

Site Meetings

The Contractor will attend with adequate responsible representation to Site Meeting
A item
and all other meetings to which the Engineer has given instructions to attend.

The Contractor will further undertake to inform and present to attend meeting(s) any
B representative(s) for those sub-contractors, suppliers, etc., under his direct control, item
if so requested by the Engineer.

The Contractor will ensure that all meetings with sub-contractors are held just prior
C item
to the site meetings to ensure accurate reporting on progress, information, etc.

Climatic Condition

Daily maximum and minimum air temperature (including overnight) shall be included
D item
in the Daily Report

Number of hours per day in which works are prevented by inclement weather (flood,
E item
etc.).

Site Survey and Grid Levels

Before commencing excavation or site leveling operations, the Contractor shall


conduct a site survey, witnessed by the Engineer, related to a benchmark. Levels
F shall be taken at 5m intervals in both directions across the entire site which must be item
agreed with Engineer prior to commencing excavations or filling operations, all as
specified in the specification

Other Costs

Allow for all costs, expenses etc. details of which must be set out below & extended
separately by the contractor incurred in carrying out the requirements of the
G Contract and not otherwise included in this bill. All costs & expenses not entered item
hereinafter will be deemed to be included in the prices inserted elsewhere in this
Bill.

CARRIED TO COLLECTION PAGE N


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES

BILL NO-01/ 225


ITEM DESCRIPTION QTY UNIT RATE AMOUNT (N)

COLLECTION

BILL NO. 1 PRELIMINARIES

Page No. 1/1 ₦0.00

Page No. 1/2 ₦0.00

Page No. 1/3 ₦0.00

Page No. 1/4 ₦0.00

Page No. 1/5

Page No. 1/6

Page No. 1/7

Page No. 1/8

Page No. 1/9

Page No. 1/10

Page No. 1/11

Page No. 1/12

Page No. 1/13

Page No. 1/14

Page No. 1/15

Bill No.1 Preliminaries Carried to General Summary Page N

BILL NO-01/ 226


S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

SURVEILLANCE CAMERA SYSTEM(IP CAMERA)

A NVR 32 Channel with 2TB HDD Capacity and Wireless Mouse 4 No. 550,000.00 2,200,000.00

B Indoor Dome IP Camera 4MP 82 No. 40,000.00 3,280,000.00

C Indoor Bullet IP Camera 4MP 15 No. 45,000.00 675,000.00

D Outdoor Bullet IP Camera 4MP 10 No. 45,000.00 450,000.00

E Motorized Outdoor Bullet IP Camera 4MP (PTZ) 3 No. 250,000.00 750,000.00

F 24 ports POE network switch 6 No. 250,000.00 1,500,000.00

G 24 ports switch 6 No. 95,000.00 570,000.00

H Desktop - All in one PC (to work as server) 1 No. 450,000.00 450,000.00

J Gigabit Router 1 No. 150,000.00 150,000.00

K 2TB Surveillance HDD for Storage 8 No. 45,000.00 360,000.00

L 50 inch LED TV used as Monitor 4 No. 350,000.00 1,400,000.00

M Cat6+ Network Cable (UTP 100% Copper) 12 Roll 65,000.00 780,000.00

N Cat6+ Network Cable ( (STP, 100% Copper) 7 Roll 75,000.00 525,000.00

P Installation Accessories 1 LOT 450,000.00 350,000.00

Q Design, Labour & Configuration 1 LOT 750,000.00 550,000.00

Page/227
SURVEILLANCE CAMERA SYSTEM(IP CAMERA) 13,990,000.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

PABX INTERCOM TELEPHONE SYSTEM


Panasonic Intercom Pabx Equipment 200 Extension Configuration - KX-TD 600
A Hybrid IP-PBX 1 No. 1,800,000.00 1,800,000.00

B Power Pack 1 No. 350,000.00 350,000.00

C Extension Card (24 extension) 7 No. 350,000.00 2,450,000.00

D Console Card 1 No. 250,000.00 250,000.00

E Console Phone 5 No. 75,000.00 375,000.00

F External Line Card 2 No. 250,000.00 500,000.00

G Panasonic Telephone with Screen Single Line Corded with Caller Id display 20 No. 18,500.00 370,000.00

H Panasonic Telephone without screen 126 No. 10,000.00 1,260,000.00

J External Line Dailer (MTN, GLO, AIRTEL, 9MOBILE) 5 No. 40,000.00 200,000.00

K 100pair 1 Roll 250,000.00 250,000.00

L 50pair 4 Roll 125,000.00 500,000.00

M 10pair 3 Roll 40,000.00 120,000.00

N 2 Pair PVC Cable 100% Pure Copper 12 Roll 35,000.00 420,000.00

P RJ 11 FacePlate/socket 140 No. 2,500.00 350,000.00

Q Installation Accessories 1 LOT 550,000.00 550,000.00

R Design, Labour and Configuration 1 LOT 750,000.00 750,000.00

Page/228
PABX INTERCOM TELEPHONE SYSTEM 10,495,000.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

IP -BASED ACCESS CONTROL SYSTEM

A Access Control Master Controller 1 No. 450,000.00 450,000.00

B Access Control Slave Controller 12 No. 150,000.00 1,800,000.00

C Access Control Software Management 1 No. 250,000.00 250,000.00

D Electronic Magnetic Lock & ZL Bracket For Access Control 48 No. 40,000.00 1,920,000.00

E No Touch Exit Button 48 No. 20,000.00 960,000.00

F Door Closer (40-60Kg) 48 No. 50,000.00 2,400,000.00

G Installation Accessories 1 LOT 350,000.00 350,000.00

H Design, Labour and Configuration 1 LOT 550,000.00 550,000.00

Page/229
IP -BASED ACCESS CONTROL SYSTEM 8,680,000.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

IP-TV SYSTEM

Supply, install, test and commission headend equipment consisting of


1 IPTV server, setup box switches, satellite dish, local antenna, cables and
accessories. Including all other items necessary for complete installation
as per specification and drawings.

DVB to IP Gateway for TV providers to receive, up to 16 satellite transponders


or multiplexes and IPTV channels (more than 200 TV channels) with redundant
A power supply and hot-swap storage 1 No. 18,785,350.00 18,785,350.00

B IPTV set up box 140 No. 65,000.00 9,100,000.00

C LCM Web Base Management System software license 1 No. 1,570,000.00 1,570,000.00

Ethernet-switch MES2348P 24 ports 10/100/1000BASE-T (PoE/PoE+) and 4


D ports 10GBASE-X (SFP+)/1000BASE-X (SFP) 6 No. 550,000.00 3,300,000.00

Ethernet-switch MES3308F, 4 ports 1000Base- X (SFP), 4 combo-ports,


E 10/100/1000BaseT/1000Base/X (SFP), 4 ports 10GBase-X (SFP+), L2+ 1 No. 2,350,000.00 2,350,000.00

F Power module PM160-220/12, 220V AC, 160W 1 No. 125,000.00 125,000.00

G SFP+ 10GE module, 20 km, 2 fiber, 1310 nm, LC, DDM, pc 6 No. 135,000.00 810,000.00

H Systimax/Lucent/Avaya Gigaspeed 24-port patch panel 6 No. 55,000.00 330,000.00

J Modular Patch Cord (2m) 140 No. 2,500.00 350,000.00

K Shipping and clearing 1 LOT 1,250,000.00 1,250,000.00

Supply, install, test and commission Satellite dish with LNB; VHF/UHF
antenna and accessories including all items necessary for complete
2 installation as per specification.

L Supply and install free to air dish + MultiSwitch 1 LOT 750,000.00 750,000.00

Supply and install DSTV satellite dish complete with one year subscription for
M basic channels + 16 outgoing Multi Switch 140 LOT 65,750.00 9,205,000.00

N Systimax/Lucent/Avaya Cat6e Cable (305m/roll) 15 Roll 75,350.00 1,130,250.00

P Coaxial Cable 150 Mtrs 550.00 82,500.00

3 Others

Q 6 month support 1 LOT 650,000.00 650,000.00

R Installation accessories 1 LOT 178,000.00 178,000.00

S Testing and Comissioning 1 LOT 305,000.00 305,000.00

T Design, Configuration & Installation 1 LOT 3,562,373.38 3,562,373.38

Page/230
IP-TV SYSTEM 53,833,473.38

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

TV- SATELLITE SYSTEM

A DSTV HD Decoder 7 No. 45,000.00 315,000.00

B TSTV HD Decoder with accessories 3 No. 38,500.00 115,500.00

C Free to Air with Dish and LNB 3 No. 85,000.00 255,000.00

D Startimes Sat 3 No. 45,000.00 135,000.00

E Industrial HD TV signal Modulator (HDMI/AV to RF) 1 No. 650,000.00 650,000.00

F TV faceplate 150 No. 2,500.00 375,000.00

G RG 6 Signal Cable ASTEL 15 No. 35,850.00 537,750.00

H Signal Amplifer/Booster (Televees 50db) 6 No. 145,000.00 870,000.00

J 16 way Splitter and Combiner 10 No. 45,000.00 450,000.00

K wireless Remote Controller 5 No. 35,000.00 175,000.00

L Installation Accessories 1 LOT 450,000.00 450,000.00

M Design, Labour, Configuration and Training 1 LOT 750,000.00 750,000.00

Page/231
TV- SATELLITE SYSTEM 5,078,250.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

HOTEL LOCKS AND ENERGY SAVER.


Mifare Card Hotel Lock Brushed Stainless Steel finishing(sus 304) Different Key
A cylinders with 3 mechanical keys 140 No. 45,000.00 6,300,000.00

B Energy Saver (Room power Control) used with Mifare Card 140 No. 25,650.00 3,591,000.00

C Handset for Mifare Door Lock 10 No. 35,000.00 350,000.00

D Mifare Card Encoder with USB Port. 5 No. 22,500.00 112,500.00

E T5557 Card 250 No. 2,500.00 625,000.00

F Programming Software FOC Free charge

G 2.5mm pure Copper cable (100% Copper) 12 Rolls 18,500.00 222,000.00

H MCB Controller 140 No. 4,500.00 630,000.00

J Door mortiser 140 No. 2,850.00 399,000.00

K Installation Accessories 1 lots 350,000.00 350,000.00

L Design, Labour, Configuration and Training 1 lots 550,000.00 550,000.00

Page/232
HOTEL LOCKS AND ENERGY SAVER. 13,129,500.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

ADDRESSABLE FIRE DETECTION-ALARM SYSTEM

A 4 Loop Fire Alarm Addressable Panel 1 No. 1,650,000.00 1,650,000.00

B Optical Smoke Detector 250 No. 19,500.00 4,875,000.00

C Ionized Heat Detector 45 No. 22,500.00 1,012,500.00

D Manual CallPoint 40 No. 19,500.00 780,000.00

E Sounder Flasher 35 No. 19,500.00 682,500.00

F Fire Retardant Cable 5 Rolls 135,000.00 675,000.00

G Strobe Light 3 No. 45,000.00 135,000.00

H Master Blaster Siren 3 No. 45,000.00 135,000.00

J Installation Accessories 1 lot 400,000.00 400,000.00

K Design, Labour, Configuration and Training 1 lot 650,000.00 650,000.00

Page/233
ADDRESSABLE FIRE DETECTION-ALARM SYSTEM 10,995,000.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

HOTEL- NETWORKING (INTERNET AND INTRANET)

A Mikrotik Router and Wireless with 600MBPS Speed(Dual WAN) 1 No. 385,000.00 385,000.00

B LAN Ethernet RJ45 Port Faceplate 40 No. 2,500.00 100,000.00

Ethernet-switch MES2348P 24 ports 10/100/1000BASE-T (PoE/PoE+) and 4


C ports 10GBASE-X (SFP+)/1000BASE-X (SFP) 6 No. 450,000.00 2,700,000.00

D Long Range Access Point(Wifi) 21 No. 95,000.00 1,995,000.00

E Outdoor Access Point(wifi) 5 No. 85,000.00 425,000.00

F Wifi Network Extender 5 No. 75,000.00 375,000.00

G 19U Network Rack 2 No. 135,000.00 270,000.00

H 9U Network Rack 7 No. 85,000.00 595,000.00

J 6U Network Rack 7 No. 75,000.00 525,000.00

K SFP+ 10GE module, 20 km, 2 fiber, 1310 nm, LC, DDM, pc 6 No. 95,650.00 573,900.00

L Cat6 Cable (UTP, 100% Copper) 10 Rolls 65,000.00 650,000.00

M Cat6 Cable (STP, 100% Copper) 8 Rolls 75,000.00 600,000.00

N Lightening Arrestor and EarthRod 3 No. 40,500.00 121,500.00

P Industrial Surge protector 6 No. 32,500.00 195,000.00

Q Installation Accessories 1 lots 450,000.00 450,000.00

R Design, Labour, Configuration and Training 1 lots 750,000.00 750,000.00

Page/234
HOTEL- NETWORKING (INTERNET AND INTRANET) 10,710,400.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

MULTIZONE SOUND SYSTEM PUBLIC ADDRESS AND VOICE EVACUATION

A Ceiling Recessed Speakers (Speech & Music) 70 No. 45,000.00 3,150,000.00

B Ceiling Recessed Speakers (Speech) 200 No. 35,000.00 7,000,000.00

C Wall Mount Speakers 6 No. 65,000.00 390,000.00

D 6 Zone Multizone, 6 Sources Amplifier & Emergency/Evacuation Console 1 No. 1,200,000.00 1,200,000.00

E High Gain wired Microphone 2 No. 75,000.00 150,000.00

F Wall Mount Volume Controller 2 Rolls 45,000.00 90,000.00

G Media player sources 3 No. 35,000.00 105,000.00

H Audio Signal Cables 25 Rolls 25,000.00 625,000.00

J Cat6 UTP Cable 10 No. 65,000.00 650,000.00

K Flex power cable 15 Rolls 35,000.00 525,000.00

L Installation Accessories 1 LOT 450,000.00 450,000.00

M Design, Labour & Configuration. 1 LOT 750,000.00 750,000.00

Page/235
MULTIZONE SOUND SYSTEM PUBLIC ADDRESS AND VOICE EVACUATION 15,085,000.00

S/N DEVICE/EQUIPMENT DESCRIPTION QTY UNIT UNIT PRICE TOTAL

SUMMARY EXTRA LOW VOLTAGE

1 SURVEILLANCE CAMERA SYSTEM(IP CAMERA) 13,990,000.00

2 PABX INTERCOM TELEPHONE SYSTEM 10,495,000.00

3 IP -BASED ACCESS CONTROL SYSTEM 8,680,000.00

4 IP-TV SYSTEM 53,833,473.38

5 TV- SATELLITE SYSTEM 5,078,250.00

6 HOTEL LOCKS AND ENERGY SAVER 13,129,500.00

7 ADDRESSABLE FIRE DETECTION-ALARM SYSTEM 10,995,000.00

8 HOTEL- NETWORKING (INTERNET AND INTRANET) 10,710,400.00

9 MULTIZONE SOUND SYSTEM PUBLIC ADDRESS AND VOICE EVACUATION 15,085,000.00

EXTRA LOW VOLTAGE TOTAL 141,996,623.38

Page/236
S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

TRANSFORMER SUB STATION, SYNCHRO PANEL.

1 11KV RINGMASTER RMU Comprising:

1-RN2dT1 RMU

TFL Protection upto 1.5MVA 1 nr. 5,950,000.00 5,950,000.00

2 1500KVA 11/0.415KVTRANSFORMER 1 nr. 20,790,000.00 20,790,000.00

Type:oil immersed,step down

cooling:ONAN

Vector group:Dyn11

Conductor:cu/cu

Make:ABB Turkey

3 BASEMENT:1600A SYNCHRONIZATION/MAIN LV PANEL comprising:

incomer 1 nr. 32,970,000.00 32,970,000.00

1-1600A 4P motorized MVS ACB 1500KVA Mains

3-1800A 4P Motorised MVS ACB 500KVA Gen1,2&3

1-65KA Surge arrestor+MCB

1-PM500 Multimeter + CT+MCB

Coupler:

1-2500 4P motorized MVS ACB

(to be interlocked with mains)

outgoing:

1-1800A 3P MCCB

1-400A 3P MCCB

1-200A 3P MCCB

1-160A 3P MCCB

1-100A 3P MCCB + Spare

3-63A 3P MCCB + Spare

3-32A 3P MCCB + Spare

AMF/SYNCH Control section

set of Deepsa Modules for:

Load monitor

Load matching relays for autostart up & shut down

mains sensing unit with overload protection

Automatic synchronizing unit

Automatic load sharing bus system

Automatic duty selector switch

Page/237
Phase Monitoring relay +CT+MCB

set of H/O/A selector switch

set of MCB

Set of control relays(AC & DC)

Emergency pushbuttons

set of ON/OFF/TRIP Pilot lamps

Set of timing relays

set of universal enclosure

set of 2500A RYBN+E bushbars

Page/11 59,710,000.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

On site

Programming & interfacing

control cables between panel & GEN

Test & commisioning


GROUND FLOOR ELECTRICAL ROOM:800A MAIN DISTRIBUTION
4 PANELcomprising:

Incomer 1 nr. 3,395,000.00 3,395,000.00

1-800A 33P MCCB

1-Ammeter + selector switch+CT

1-Voltmeter + selector switch + MCB

1-40KA surge Arrestor+MCB

3-Power ON pilot lamps

Outgoing

1-400A 3P MCCB

1-200A 3P MCCB

1-100A 3P MCCB

12-63A 3P MCCB

5-32A 3P MCCB

2-UNIVERSAL Enclosure

set of 800A RYBN+E bushbars

5 AC PANEL:600A MOTOR CONTROL CENTRE comprising:

Incomer section 1 nr. 5,593,000.00 5,593,000.00

Outgoing

1-60A 3P MCCB spare

2-30A 3P MCCB spare

OUTDOOR UNITS:VARIABLE REFRIGERANT FLOW SYSTEM VRV

Cooling (KW)&Power(KW)

VRV 0.3,6.2 & 6.3

cooling: 3-168kw

power:14.1kw,14.1kw,14.1kw

VRV 0.1

cooling: 1-124kw

power:8.9KW,8.9kw,12.9kw

Page/238
VRV 0.2 & 1.1

cooling: 2-112kw

power:8.9KW,8.9kw,12.9kw

VRV 1.2

cooling: 1-106kw

power:5.13KW,8.9kw,12.9kw

VRV 1.1,2.1,3.1,4.1& 5.1

cooling: 5-95kw

power:5.13KW,8.9kw,12.9kw

Page/12 8,988,000.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

VRV 1.2,2.2,3.2,4.2 & 5.2

cooling: 5-85kw

power:10.8KW,12.9kw

VRV 6.1

cooling: 1-45kw

power:10.8KW,

In details

Main Incomer section

1-600A 3P Incoming MCCB

1-40KA Surge Arrestor + MCB

1-Ammeter + selector switch+CT

1-Voltmeter + selector switch + MCB

1-Phase monitoring Relay (UV,OV,PF & FR) +MCB

3-Supply Available indicator lamp

1-Unhealthy supply indicator lamp

1-64a 2p MCP

Outgoing

2-60A 3P MCCB spare

2-30A 3P MCCB spare

18-VRV:(14.1KW max) Each comprising:

1-60A 3P MCCB

1-38A 3P Contacto

1-ON/OFF Pushbuttons

2-RUN/OFF Indicator lamp

2-universal Enclosure

set of terminals

set of 600A RBN+E bushbars

6 AC INDOOR VRV:6WAY SPN CONSUMER UNIT comprising: 8 nr. 37,170.00 297,360.00

Incomer

1-32A 2P ISOLATOR SWITCH

Page/239
Outgoing

3-16A 1P MCB +spare

3-10A 1P MCB

1-6MODULE ENCLOSURE

7 BASEMENT FLOOR PUMP ROOM PUMP:400A LV PANEL Comprising: 1 nr. 1,169,000.00 1,169,000.00

Incomer

1-400A 3P MCCB

1-Ammeter + selector switch+CT

1-Voltmeter + selector switch + MCB

1-40KA Surge Arrestor + MCB

3-power ON pilot lamps

Outgoing

2-200A 3P MCCB

4-63A 3P MCCB

5-32A 3P MCCB +spare

1-UNIVERSAL Enclosure

set of 400A RYBN+E Bushbars

Page/13 1,466,360.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

8 BASEMENT FLOOR ROOM BOILER:200A LV PANEL comprising:

Incomer 1 nr. 651,000.00 651,000.00

1-200A 3P MCCB

1-Ammeter + selector switch+CT

1-Voltmeter + selector switch + MCB

1-40KA Surge Arrestor + MCB

3-power ON pilot lamps

Outgoing

1-63A 3P MCCB Spare

1-40A 3P MCCB Spare

6-32A 3P MCCB +spare

1-UNIVERSAL Enclosure

set of 400A RYBN+E Bushbars

9 PENT FLOOR LIFT:100A LV PANEL comprising:

Incomer 1 nr. 595,000.00 595,000.00

1-100A 3P MCCB

1-Ammeter + selector switch+CT

1-Voltmeter + selector switch + MCB

1-40KA Surge Arrestor + MCB

3-power ON pilot lamps

Outgoing

3-63A 3P MCCB +Spare

5-32A 3P MCCB +Spare

1-UNIVERSAL Enclosure

set of 400A RYBN+E Bushbars

10 UPS PANEL:200A LV Panel comprising:

Incomer 5 nr. 273,000.00 1,365,000.00

1-200A 3P ISOLATOR SWITCH

Page/240
1-20KA surge Arrestor +MCB

3-power ON pilot lamps

Outgoing

11-32A 3P MCB

1-36MODULE Enclosure

11 BASEMENT FLOOR LIGHTING DB-B:10WAY TPNDB comprising:

Incomer 1 nr. 233,100.00 233,100.00

1-63A 3P ISOLATOR SWITCH

Outgoing

19-10A 1P MCB+spare

5-10A 2P 300mA RCCB

1-24MODULE Enclosure

12 BASEMENT FLOOR POER DB.B1:6WAY TPN Db comprisng:

Incomer 1 nr. 91,770.00 91,770.00

1-63A 3P ISOLATOR SWITCH

Outgoing

15-16A 1P MCB

3-10A 1P MCB

1-18MODULE Enclosure

Page/14 2,935,870.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

13 BASEMENT FLOOR KITCHEN DB-KIT:8WAY TPN DB Comprising:

Incomer 1 nr. 118,650.00 118,650.00

1-200A 3P ISOLATOR SWITCH

Outgoing

5-20A 1P MCB

14-16A 1P MCB

5-10A 1P MCB

1-24MODULE Enclosure

14 BASEMENT FLOOR LAUNDRY ROOM DB-LUA:8WAY TPN DB Comprising:

Incomer 1 nr. 121,100.00 121,100.00

1-200A 3P ISOLATOR SWITCH

Outgoing

3-25A 3P MCB

3-20A 1P MCB

10-16A 1P MCB

2-10A 1P MCB

1-24MODULE Enclosure

15 BASEMENT FLOOR MAINTENACE OFFICE DB-M 4WAY TPN DB comprisng:

Incomer 1 nr. 80,500.00 80,500.00

1-63A 3P ISOLATOR SWITCH

Outgoing

3-25A 3P MCB

4-20A 1P MCB + spare

2-16A 1P MCB+spare

1-10A 1P MCB

1-12MODULE Enclosure

Page/241
16 GROUND FLOOR POWER AUDITORIUM DB-AUD:6WAYTPNDB comprising:

Incomer 1 nr. 91,770.00 91,770.00

1-63A 3P ISOLATOR SWITCH

Outgoing

7-16A 1P MCB

11-10A 1P MCB

1-12MODULE Enclosure

17 GROUND FLOOR DB-G:10WAY TPN DB comprising:

Incomer 1 nr. 250,390.00 250,390.00

1-63A 3P ISOLATOR SWITCH

Outgoing

10-16A 1P MCB+spare

15-10A 1P MCB+spare

5-10A 2P 300mA RCCB

1-36MODULE Enclosure

Page/15 662,410.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

18 GROUND FLOOR DB-G:8WAY TPN DB comprising:

Incomer 1 nr. 233,100.00 233,100.00

1-63A 3P ISOLATOR SWITCH

Outgoing

12-16A 1P MCB+spare

7-10A 1P MCB+spare

5-10A 2P 300mA RCCB

1-36MODULE Enclosure

19 GROUND FOOR RECEPTION DB-R:4WAY TPN DB comprising:

Incomer 1 nr. 72,170.00 72,170.00

1-63A 3P ISOLATOR SWITCH

Outgoing

6-16A 1P MCB+spare

6-10A 1P MCB+spare

1-12MODULE Enclosure

20 FIRST-FIFTH FLOOR CU-1.2:6WAY SPN CONSUMER UNIT comprising

Incomer

1-32A 3P ISOLATOR SWITCH 5 nr. 37,170.00 185,850.00

Outgoing

3-16A 1P MCB+spare

3-10A 1P MCB

1-6MODULE Enclosure

21 FIRST-FIFTH FLOOR DB-1.1:6WAY TPN DB comprising

Incomer

Page/242
1-125A 3P ISOLATOR SWITCH

Outgoing 5 nr. 371,000.00 1,855,000.00

6-16A 1P MCB+spare

1-10A 1P MCB

11-25A 2P 300mA RCCB

1-18MODULE Enclosure

22 FIRST-FIFTH FLOOR DB-1.1:10WAY TPN DB comprising

Incomer

1-125A 3P ISOLATOR SWITCH 5 nr. 241,990.00 1,209,950.00

Outgoing

1-25A 1P MCB+spare

6-16A 1P MCB+spare

23-25A 2P 300mA RCCB

1-36MODULE Enclosure

23 PENT FLOOR CU-GYM:6WAY SPN CONSUMER UNIT comprising

Incomer 1 nr. 37,170.00 37,170.00

1-32A 3P ISOLATOR SWITCH

Outgoing

3-16A 1P MCB+spare

3-10A 1P MCB

1-6MODULE Enclosure

Page/16 3,593,240.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

24 PENT FLOOR DB-SP:4WAY TPN DB comprising

Incomer

1-63A 3P ISOLATOR SWITCH 1 nr. 72,170.00 72,170.00

Outgoing

4-16A 1P MCB+spare

8-10A 1P MCB+spare

1-12MODULE Enclosure

25 PENT FLOOR DB-P:4WAY TPN DB comprising

Incomer 1 nr. 72,170.00 72,170.00

1-100A 3P ISOLATOR SWITCH

Outgoing

2-25A 1P MCB

3-16A 1P MCB+spare

7-10A 1P MCB

1-12MODULE Enclosure

26 100KVA INVERTER UPS comprising:

Incomer 1 nr. 17,290,000.00 17,290,000.00

European UPS (100KVA)

Online double conversion topology

3/3,415V,50Hz equipped with external batteries with 30 minuetes backup

Low frequency UPS(i.e transformer based,need no AVR)

Installation,test & commision

(supply & laying of cables,civil works,positioning outside our scope)

Page/243
TESCOM-EUROPEAN STANDARD

Page/17 17,434,340.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

TRANSFORMER SUB STATION, SYNCHRO PANEL.

Page/11 59,710,000.00

Page/12 8,988,000.00

Page/13 1,466,360.00

Page/14 2,935,870.00

Page/15 662,410.00

Page/16 3,593,240.00

Page/17 17,434,340.00

Page/244
TRANSFORMER SUB STATION, SYNCHRO PANEL. 94,790,220.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL


UNDERGROUND DIESEL TANK & GENERATOR SETS

Size 6000 x 3000 x 2400 (45000litres)

EXCAVATION

A Trench 1m maximum depth; from 150 below existing level 73 cu.m 1,850.00 135,050.00

B Remove surplus soil 73 cu.m 750.00 54,750.00

C Back filling with Sharp sand 43 cu.m 1,200.00 51,600.00

Plain Vibrated Concrete Grade 25.5; developing minimum 25.5N/mm2 work


1 cu.m 45,500.00 40,950.00
D strength in 28 days in base

Reinforced Insitu Vibrated Concrete Grade 25.5; developing minimum


5 cu.m 45,500.00 204,750.00
E 25.5N/mm2 work strength in 28 days in base

F Ditto,Plinth Saddle 3 cu.m 45,500.00 136,500.00

G Strapping around Saddle 2 nr 3,500.00 7,000.00

Reinforcement

Reinforcement bars; B.S.4449, hot rolled deformed high yield steel

In bases and Plinth Saddle

H 12mm 1 t 720,000.00 453,600.00

Page/245
J 45,000 litres under groung tank with associated accessories and works 1 NR 6,500,000.00 6,500,000.00

Formwork

K Vertical sides of the plinth saddle 25 sq.m 4,850.00 121,250.00

L Ditto edges of the base 18 m 485.00 8,730.00

GROUND DIESEL TANK

M 10,000 litres ground day tank with associated accessories and works 1 Nr. 1,872,486.00 1,872,486.00

Plinth base size 2400 x 2400 x 2000 (10,000litres)

N Level and compact 6 sq.m 200.00 1,200.00

BRC WIRE MESH


Fabric type A142 weight 2.22kg/m2 measured nett with minimum 300 lap at 6 sq.m 1,700.00 10,200.00
P joint

Hardcore to be obtained from off-site;

Filling to make up levels; depositing in layers 200mm maximum thickness

Q average thickness not exceeding 300mm 1 cu.m 6,500.00 6,500.00

Plain Vibrated Concrete Grade 25.5; developing minimum 25.5N/mm2 work


1 cu.m 45,500.00 45,500.00
R strength in 28 days in Plinth bases

S Formwork edges of Base Plinth 10 m 1,212.50 12,125.00

T Allow for the fabrication and installation of 1 meter high steel stand sum 75,000.00

Generator sets

U 500kVA 400V 50Hz, 1500RPM JMG FG Wilson cummings engine 2 Nr 45,390,100.00 90,780,200.00

100,517,391.00

S/N DESCRIPTION QTY UNIT UNIT PRICE TOTAL

GENERAL SUMMARY

A EXTRA LOW VOLTAGE 141,996,623.38

B TRANSFORMER SUB STATION, SYNCHRO PANEL. 94,790,220.00

C UNDERGROUND DIESEL TANK & GENERATOR SETS 100,517,391.00

Page/246
GRAND TOTAL 337,304,234.38

Page/247
PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

STATION BUILDING

DELIVERED TO SITE INSTALL INSTALLED AND


ITEM DESCRIPTION QTY UNIT AND /OR WORKING
ERECT
Unit Rate Unit Rate Total
NAIRA : K NAIRA : K NAIRA : K

A. CONDUIT AND ACCESSORIES

Make: NIG PIPE, DIGNITY, WASHALL or


APPROVED EQUAL

A1 20mm dia Flexible/Didnity PVC Pipe 355 length 260.00 48.00 109,340.00

A2 25mm dia Flexible/Dignity PVC Pipe 290 length 300.00 58.00 103,820.00

A3 50mm dia Flexible/rigid PVC Pipe 20 length 1,580.00 300.00 37,600.00

A4 50mm dia UPVC Bend 12 No 550.00 95.00 7,740.00

A5 75mm x 75mm plastic box 120 No 220.00 44.00 31,680.00

A6 75mm x 135mm plastic box 80 No 350.00 65.00 33,200.00

A7 100mm x 100mm Draw boxes 5 No 6,500.00 1,200.00 38,500.00

A8 25mm Coupler 4 Pkt 2,200.00 400.00 10,400.00

A9 20mm Coupler 5 Pkt 1,980.00 350.00 11,650.00

A10 Male/Female Bushing 4 Pkt 2,300.00 430.00 10,920.00

A11 Tangit gum (Ikg) 3 tin 4,500.00 900.00 16,200.00

A12 Conduit accessories Lot 30,000.00

A13 Miscellaneous item Lot 20,000.00

SUB-TOTAL ITEM A 461,050.00

TELEPHONE SYSTEM (No design drawing but


B
TELEPHONE points were shown)
Supply, install, test and commission Telephone PABX
system consisting telephone PABX, telephone hand
sets, connection to public line (MTN/ETISALAT/GLO),
cabling from the MDF to the junction boxes and all
other items and accessories necessary for a complete
installation.

1 Cables / Junction Boxes lot 35,000.00

OUTDOOR CABLE
2 5 pair underground armoured telephone cable 80 m 1,650.00 400.00 164,000.00

INDOOR CABLE
3 CAT 6 Cable 450 m 850.00 220.00 481,500.00

DISTRIBUTION BOXES COMPLETE WITH KRONE &


SURGE
4 64 pairs telephone junction boxes 1 No. 17,500.00 3,950.00 21,450.00

5 20 pairs telephone junction boxes 3 No. 11,650.00 3,000.00 43,950.00

6 COMMUNICATION EQUIPMENT
i PABX Equipmentequipped with:
3 trunk lines,
36 extension
operator hands free console, voice mail.
Make/Type ……PANASONIC 1 No. 155,000.00 30,500.00 185,500.00

ii Telephone handsets.
Make/Type Panasonic with Display 7 No. 8,245.00 2,125.00 72,590.00
RJ 45 system dual face plate with modules & shutter
iii
for Data/Telephone
Make/Type 7 No. 2,800.00 500.00 23,100.00
Allow for termination for Telephone points in floor
iv Lot 20,000.00
boxes 1
Cables complete with jack for connection between
v Lot 25,000.00
PABX and MDF 1
Allow for 1No. 1.5KVA APC UPS/ support and all
vi other necessary item for complete installation of UPS Lot 25,000.00
supply to voice/data systems 1

vii 75mm x 75mm plastic boxes 7 No 165.00 30.00 1,365.00


viii 20mm dia. PVC pipe 80 length 240.00 45.00 22,800.00
ix 20mm Couplers 2 pkt 2,700.00 450.00 6,300.00
x 20mm Male/Female Bushing 1 pkt 2,700.00 450.00 3,150.00
xi Tangit gum (1kg) 1 tins 5,100.00 850.00 5,950.00
xii 100mm Telephone Draw Box 2 No 4,800.00 850.00 11,300.00
xiii Accessories & Miscellaneous Lot 30,000.00

Prepared by: Royal Initiative Consult Page 4-248 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

STATION BUILDING

DELIVERED TO SITE INSTALL INSTALLED AND


ITEM DESCRIPTION QTY UNIT AND /OR WORKING
ERECT
Unit Rate Unit Rate Total
NAIRA : K NAIRA : K NAIRA : K
SUB TOTAL ITEM B. 1,177,955.00

Prepared by: Royal Initiative Consult Page 4-249 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

STATION BUILDING

DELIVERED TO SITE INSTALL INSTALLED AND


ITEM DESCRIPTION QTY UNIT AND /OR WORKING
ERECT
Unit Rate Unit Rate Total
NAIRA : K NAIRA : K NAIRA : K

TELEVISION SYSTEM (No design drawing but TV


C
points were shown)

HEAD END
12GHZ 140mm Electronic coated steel offset Dish with
1 polyester pain stand poly propylene metal support in No. 62,000.00 16,250.00 78,250.00
galvanized plate 1

MATV UHF and VHF High gain antenna DAT 45


2 No. 24,150.00 6,037.50 30,187.50
Televes 1

3 (5 - 900)MHZ, RF Amplifier Televes-5527 No. 35,000.00 10,000.00 45,000.00


1

DISTRIBUTION SYSTEM
4 8way- RF splitter Televes 1 No. 18,360.00 4,590.00 22,950.00

5 Tv outlet (TV + SAT)- TELEVES REF 5246 7 No. 2,400.00 600.00 21,000.00

Ultra low - loss RG-6, co-axial cable, with polietilene


6 physic di-electric and special anti oxidant copper-tin m 250.00 40.00 101,500.00
mesh. Beldene /Astrix/ Astel. 350

7 Cable distribution junction box 3 No 1,438.00 250.00 5,064.00


8 Television socket outlet 7 No 1,800.00 300.00 14,700.00
9 20mm dia. PVC pipe 85 length 485.00 80.00 48,025.00
10 75mm x 75mm plastic boxes 20 No 165.00 33.00 3,960.00
Conduit Accessories: (couplers, male/female bushing, Lot 30,000.00
11 tangit gum)
12 Miscellaneous Items Lot 20,000.00

SUB TOTAL ITEM C. 420,636.50

D EARTHING
Supply, install, test & commission
the earthing of the electrical
installation works and equipment
complete with W.J. Furse & Co.
earth rods, earth tape, teat clamps
equipotential earth bar of the
main switch board, all to achieve
earth resistance of 0.2ohms and all
other necessary items for a complete
earthing systems as per specification

D1 Earth Copper Rods


1.22mx15mm dia. 4 No. 6,500.00 1,350.00 31,400.00

D2 Earth Rods Couplings 3 No. 1,650.00 300.00 5,850.00

D3 Steel Driving stud 2 No. 1,200.00 200.00 2,800.00

D4 Earth rod clamps 2 No. 1,250.00 300.00 3,100.00

D5 Earth cable, 25mm2 bare copper conductor 35 M 4,450.00 750.00 182,000.00

D6 Earth Copper tape 25x3mm2 50 M 2,375.00 550.00 146,250.00

D7 Tape Clip (25x3mm2 ) 4 No. 680.00 113.00 3,172.00

D8 Test Clamp for Tape(25x3mm2 ) 2 No. 4,800.00 1,200.00 12,000.00

D9 Junction Clamp for tape(25x3mm2 ) 4 No. 3,125.00 781.00 15,624.00

D10 Earth Mat


600x600x1.5mm solid copper 2 No. 16,750.00 4,100.00 41,700.00

D11 Inspection manholes including covers 2 No. 30,000.00 6,500.00 73,000.00

D12 11.36 kg Marconite conductive aggregate 2 No. 16,000.00 2,500.00 37,000.00

Test and commissioning and all other accessories 1


D13 nessecary for complete installation of effective Lot 30,000.00
lightning and earthing system

SUB TOTAL ITEM D. 583,896.00

Prepared by: Royal Initiative Consult Page 4-250 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

STATION BUILDING

DELIVERED TO SITE INSTALL INSTALLED AND


ITEM DESCRIPTION QTY UNIT AND /OR WORKING
ERECT
Unit Rate Unit Rate Total
NAIRA : K NAIRA : K NAIRA : K

E CABLES

Bill to be read along with the electrical specification

Make: Nigerchin, Kabelmetal, or approved equal

1 1.5mm2 Single Core PVC Cable (100m/roll) 21 rolls 8,900.00 1,600.00 220,500.00

2 2.5mm Single Core PVC Cable (100m/roll)


2
12 rolls 15,500.00 2,800.00 219,600.00

3 4mm2 Single Core PVC Cable (100m/roll) 6 rolls 21,220.00 3,800.00 150,120.00

4 16mm2 x 4Core PVC/PVC Copper Cable (100m/roll) 150 rolls 4,880.00 800.00 852,000.00
From main panel to DB-A, DB-B, DB-C, DB-D, DB-E, DB-
F, DB-G, DB-GH

5 10mm2 x 2Core PVC/PVC Copper Cable (100m/roll) 130 m 2,850.00 500.00 435,500.00
From main panel to CU-H

SUB TOTAL ITEM E. 1,437,620.00

Prepared by: Royal Initiative Consult Page 4-251 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

STATION BUILDING

DELIVERED TO SITE INSTALL INSTALLED AND


ITEM DESCRIPTION QTY UNIT AND /OR WORKING
ERECT
Unit Rate Unit Rate Total
NAIRA : K NAIRA : K NAIRA : K
.
F DISTRIBUTION BOARDS (ABB)

12 way,100A, TP &N Distribution Board complete with


F1 No. - - -
mixed capacity MCBs &RCD -

8 way,63A, TP &N Distribution Board complete with


F2 No. 98,500.00 9,200.00 107,700.00
mixed capacity MCBs &RCD 1

6 way,45A, TP &N Distribution Board complete with


F3 No. 88,900.00 8,500.00 97,400.00
mixed capacity MCBs & ELCB
1

4 way,45A, TP &N Distribution Board complete with


F4 No. 78,000.00 7,500.00 85,500.00
mixed capacity MCBs &ELCB 1

F5 Allow for all other items Lot 50,000.00


1

SUB TOTAL ITEM F. 340,600.00

G. WIRING ACCESSORIES (ABB Exclusive)

G1 13A single socket outlet on Raw Power 0 No. -

G2 13A single socket outlet on UPS 10 No. 2,450.00 612.50 30,625.00

G3 13A twin socket outlet on Raw power 41 No. 2,800.00 700.00 143,500.00

G4 13A Waterproof twin socket outlet 2 No. 4,800.00 1,200.00 12,000.00

G5 13A twin socket outlet on UPS 0 No. - -

G6 15A Switch Socket Outlet for water heater 1 No. 2,650.00 550.00 3,200.00

G7 20A DP Switch with indicator light for A?C 14 No. 2,650.00 550.00 44,800.00

G8 1gang 1way switch 27 No. 1,850.00 450.00 62,100.00

G9 1gang 2way switch 2 No. 1,900.00 450.00 4,700.00

G10 2gang 1way switch 1 No. 2,100.00 525.00 2,625.00

G11 3gang 1 way switch - No. -

G12 Ceiling Rose 8 No. 400.00 100.00 4,000.00

G13 All other items 1 Lot 65,000.00

SUB TOTAL ITEM F 372,550.00

H LIGHTING FITTINGS

Supply, install and test, commissioning lighting fittings


complete with lamps and all items necessary for a
complete installation and as recommended by the
manufacturers: Thorn/Phillips

H1 2X40W fluorescent fiitings 35 No. 12,900.00 3,000.00 556,500.00

H2 40 W Incandescent ceiling fiitings light 8 No. 6,500.00 1,500.00 64,000.00

H3 25 W fitted ceiling lamp 20 No. 4,800.00 1,100.00 118,000.00

SUB-TOTAL ITEM G. 738,500.00

Prepared by: Royal Initiative Consult Page 4-252 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

STATION BUILDING

DELIVERED TO SITE INSTALL INSTALLED AND


ITEM DESCRIPTION QTY UNIT AND /OR WORKING
ERECT
Unit Rate Unit Rate Total
NAIRA : K NAIRA : K NAIRA : K

SUMMARY

A CONDUIT AND ACCESSORIES 461,050.00

B TELEPHONE SYSTEM 1,177,955.00

C TELEVISION SYSTEM 420,636.50

D EARTHING SYSTEM 583,896.00

E CABLES 1,437,620.00

F DISTRIBUTION BOARDS 340,600.00

G WIRING ACCESSORIES 372,550.00

H LIGHTING FITTINGS 738,500.00

STATION BUILDING CARRIED TO SUMMARY 5,532,807.50

Prepared by: Royal Initiative Consult Page 4-253 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

EXTERNAL WORKS

DELIVERED TO INSTALL INSTALLED AND


ITEM DESCRIPTION QTY UNIT SITE AND /OR WORKING
Unit Rate ERECT
Unit Rate Total
NAIRA : K NAIRA : K NAIRA : K

A LOW VOLTAGE DISTRIBUION PANEL


Busbars fully assembled
and wired in
Dimension :
consisting of:
Enclosure : Metal Clad
Busbar Rating : 1000A
Rated Voltage: 690V, 50-60Hz
Short circuit rating:

In-commer
1No.800A 4-pole ACB

Out-going
5No. 45A 4pole MCCB
2No. 60A 3pole MCCB
10No. 10A 2pole MCCB
2No. 45A 2pole MCCB
2No.32A 3pole MCCB as spare
- Control Switch single pole
- Voltage monitoring relay
- Phase failure relay 380 - 415V
- Reverse Power Relay
- Emergency (mushroom) stop switch
- Digital Multimeter
- Time Relay
- Control relay,
- Signal lamp red, green, or yellow lens
- Single pole mcb for controls
- Surge Suppressor FURSE
1 Make/Type----- 1 no 1,590,000.00 150,000.00 1,740,000.00

2
LIGHTING KIOSK complete with contactor and photocell
Busbars fully assembled
and wired in
Dimension :
consisting of:
Enclosure : Metal Clad
Busbar Rating : 1000A
Rated Voltage: 690V, 50-60Hz
Short circuit rating:
In-commer
1No.16A 3-pole MCB

Out-going
20No. 10A 2pole MCB 1 no 635,350.00 65,000.00 700,350.00

Allow for 400A TPN 4P MCCB Isolator in an enclosure complete


3 1 no 250,000.00 25,000.00 275,000.00
with surge suppressor and LED indicator lights- ABB/ Schneider

4
Allow cost for 400A change-over switch 1 no 15,000.00 275,000.00
260,000.00

SUB TOTAL FOR ITEM A 2,990,350.00

Prepared by: Royal Initiative Consult Page 1-254 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

B POWER CABLES

Allow a PRIME COST SUM of 10,000,000.00(Ten Million Naira


only) for the supply, installation, testing and commissioning of
power cables installed in trunking, on trays, in trench and
1 Sum
underground pipe ducts complete with saddles, cable lugs, cable
glands, cable identification labels and all other items for complete
installation as per specification and drawings.
10,000,000.00

Note: All CABLE QUANTITY ARE PROVISIONAL AND SHALL


BE SUBJECT FOR FINAL MEASUREMENT AFTER
COMPLETION OF INSTALLATION.This is sequel to no clear
cable layout design on the drawing and the drawing has no
scale. Working drawings to be produced and approved by
client before the execution of this item of work.

(Coleman cable/Nigerchin/Kabelmetal)

i 4 Core 120mm2 PVC/SWA/PVC copper cable


From Transformer to gear switch isolator - changeover switch,
generator - 400A change-over switch and change-over switch to 220 m
main panel).

ii 4 Core 25mm2 PVC/PVC copper cable


From Main panel to the Lighting kiosk 120 m

iii 2 Core 25mm2 PVC/PVC copper cable


From main panel to pump switches 65 m

iv 4 Core 10mm2 PVC/PVC copper cable


From main panel to DB-A, DB-B, DB-C, DB-D, DB-E, DB-F, DB-
400 m
G

v 2 Core 10mm2 PVC/PVC copper cable


From main panel to CU-H 130 m

vi 1 Core 10mm2 PVC/PVC earth cable 400 m

vii 1 Core 120mm2 PVC/PVC copper earth cable 220 m

viii 1 Core 25mm2 PVC/PVC copper earth cable 185 m

ix 25mm Flexible conduit pipes for external pole lights 60 m

x 100mm heavy duty pipe sleeve (upvc) 200 m

xi 50mm heavy duty pipe sleeve (upvc) 120 m

xii Allow for cable lugs 1 lot

xiii Allow for cable support 1 lot

xiv Allow for labeling of the power 1 lot

xv Allow for all other items necessary-


for complete installation
of power cables 1 lot

SUB-TOTAL FOR ITEM B 10,000,000.00

Prepared by: Royal Initiative Consult Page 1-255 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

C PHCN INSTALLATION (PROVISIONAL SUM)


TRANSFORMER
Supply, install, test and commision 300KVA, 11KV/415V step-
down transformer, earthing, Raychem Elastimoulds 11kv
1 1 No 2,980,000.00 450,000.00 3,430,000.00
terminating kits, complete with all items necessary for a complete
installation of the transformer.
Make/Type ; ABB

2 Supply, install, test and commission 3core 35mm2 underground


XLPE HT cable from Generating station to HT Pole.

Make/Type. 30 m 3,350.00 720.00 122,100.00

3 1c x 150mm2 bare aluminium conductor 60 m 580.00 130.00 42,600.00

4 11KV D fuse 1 set 52,500.00 11,800.00 64,300.00

5 11KV Gang isolator 1 set 175,000.00 38,000.00 213,000.00

6 Channel Iron 4 set 8,200.00 2,125.00 41,300.00

7 11KV Pot Insulator 6 No 3,000.00 875.00 23,250.00

8 Spindle 6 No 1,100.00 300.00 8,400.00

9 Complete Disk 6 No 4,200.00 880.00 30,480.00

10 J-Hook 6 No 2,000.00 420.00 14,520.00

11 Socket Adaptor 6 No 3,200.00 680.00 23,280.00

12 Six bolt 6 No 2,200.00 580.00 16,680.00

13 Tie-Strap 3 No 2,300.00 625.00 8,775.00

14 10.36 meter HT Concrete Pole


Make/Type. 3 No 40,000.00 8,800.00 146,400.00

15 11KV Lighting Arrester 1 set 52,000.00 12,000.00 64,000.00

16 Complete stay assembly Lot 35,000.00

17 Allow a provisional sum for the supply and installation of Phcn


charges for the supply, installation and calibration of Phcn
maximum demand meter, including Phcn charges for capital
contribution, commissioning, processing, testing inspection, 1 Lot
connection fee, stamping and all other necessary charges for the
provision of healthy power supply to site.
1,000,000.00

18 HT CABLE termination kit


Supply, install, test and commission raychem/Elastimoulds HT
termination kit for termination of HT cables to and from the HT
Overhead HT line, Transformers.
Make/Type. 1 Lot 30,000.00

19 Allow for labelling of the equipment 1 Lot 30,000.00

20 Allow for earthing of poles 1 Lot 85,000.00

21 Allow for all other items necessary for complete installation and
1 Lot
commissioning of transformer 100,000.00

The size/capacity of the power transformer was not


indicated on the drawing, hence reasonable assumption has
been made for this section. A bigger capacity would be
required assuming we are considering the aviation storage
section together with the filling station section.

SUB-TOTAL FOR ITEM C 5,529,085.00

Prepared by: Royal Initiative Consult Page 1-256 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

D LIGHTNING PREVENTION/PROTECTION
Supply, install, test and commission
(Furse) lightning spikes linked
together with copper tapes on top of
the building complete with 23x3mm
copper tape, clamps, earthing rods,
test points and rod couplers.
Earthing basis are to be less than
0.2ohms and all other necessary items
for a complete installation of the
lightning prevention/protection (Furse)

Indelec non-radioactive type on 3m high pole above the highest


D.1
point on site
S6 model 1 no 950,000.00 110,000.00 1,060,000.00

D.2 Earth Copper tape 25x3mm2(Tc 030) 50 m 6,150.00 1,551.00 385,050.00

D.3 Cable Clips(CP805) 50 no 1,200.00 213.00 70,650.00

D.4 Square clamp CS605 12 no 40,000.00 625.00 487,500.00

D.5 25x3mm Test Clamp for tape(CT110) 4 no 8,800.00 1,500.00 41,200.00

D.6 1.2 x 16mm Earth rods(RB/05) 27 no 5,350.00 1,200.00 176,850.00

D.7 16mm Earth rod coupler(CG170) 16 no 3,350.00 600.00 63,200.00

D.8 Flexible Braid bond (BN510) 4 no 7,900.00 1,400.00 37,200.00

D.9 900x900x1.5mm Earth plate lattice


copper(PE120) 2 no 61,500.00 12,300.00 147,600.00

D.10 Light weight Earth pit(PT205) 2 no 42,000.00 6,250.00 96,500.00

D.11 Rebar clamp (BN155) 8 no 6,200.00 1,100.00 58,400.00

D.12 Tee clamp (CS505) 8 no 4,500.00 1,100.00 44,800.00

D.13 Rod to cable clamp Type G 4 no 4,400.00 1,000.00 21,600.00

D.14 Allow for all other items necessary 50,000.00

SUB TOTAL ITEM D 2,740,550.00

E LIGHTING FITTING
Supply, install and test, commissioning AFROLUX LED STREET
LIGHT lighting fittings complete with lamps and all items
necessary for a complete installation and as recommended by
the manufacturers:
All Lighting fittings should complete with lamps

180W AFROLUX LED FLOOD street light Luminaire complete


with lamp on 7.5m double arm pole at 30.00M interval

1 Make Type : 8 No 240,000.00 17,000.00 2,056,000.00

2 Ditto - single arm pole at 30.00M interval 9 No 130,000.00 13,000.00 1,287,000.00

3 Allow for all other items necessary


for a complete installation of external lights 1 lot 30,000.00

SUB TOTAL FOR ITEM E 3,373,000.00

F MULTI-POWER OFFLINE INVERTER


Allow a Prime cost sum of N5,000,000.00 ( Five Million Naira
Only ) for 10KVA multi-power inverter and 20 Nr 200ah deep
cycle batteries and other accessories such as battery racks, on
load change over, cables etc to power security lights, canopy
lights and minor office equipment etc
5,000,000.00

SUB TOTAL FOR ITEM F 5,000,000.00

G SOLAR POWER
Allow a Prime cost sum of N5,000,000.00 (Five Million Naira
Only ) to provide 80 Pcs of 300W Solar Panel to be connected
to multi-power off line inverter to power security lights, canopy
lights and minor office equipment etc. (Cost of Inverter not
inclusive)
5,000,000.00

Prepared by: Royal Initiative Consult Page 1-257 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

SUB TOTAL FOR ITEM G 5,000,000.00

H CAMERA
Allow a Prime cost sum of N3,000,000.00 (Three Million Naira
Only ) for IP camera in Admin building offices, and entire
forecourt area. 3,000,000.00

SUB TOTAL FOR ITEM H 3,000,000.00

J ELECTRICAL WORKS FOR FILLING STATION FACILITY

Allow a PRIME COST SUM of N3,000,000.00 (Three Million


Naira Only) for the provision of 20 Numbers 100Watts
AFROLUX LED canopy light fittings (Marketed by Messrs.
PROJECT LABIHZAD LTD, 2/4, OLA-OLU STREET, ISOLO,
LAGOS. 08176136035, 08098244923, 08176136041) and its
4mm cables, stabilizers, UPS etc necessary for the running of
the filling station as may be approved by the engineers including
energizing the submersible pumps, signages, pylon and other
associated works. Refer to detail electrical drawings. Sum 3,000,000.00

Prepared by: Royal Initiative Consult Page 1-258 FEBRUARY, 2017


PROPOSED COMMERCIAL DEV. FOR ETERNA PLC AT AVIATION VILLAGE DISTRICT, ABUJA. ELECTRICAL INSTALLATION

SUMMARY

A LOW VOLTAGE DISTRIBUION PANEL 2,990,350.00

B POWER CABLES 10,000,000.00

C TRANSFORMER SUPPLY & INSTALLATIONS 5,529,085.00

D LIGHTENING PROTECTION/PREVENTION 2,740,550.00

E LIGHTING FITTINGS 3,373,000.00

F MULTI-POWER OFFLINE INVERTER 5,000,000.00

G SOLAR POWER 5,000,000.00

H CAMERA 3,000,000.00

J ELECTRICAL WORKS FOR FILLING STATION FACILITY 3,000,000.00

SUB-TOTAL FOR EXTERNAL WORKS 40,632,985.00

Prepared by: Royal Initiative Consult Page 1-259 FEBRUARY, 2017


ELECTRICAL FITTINGS
DESCRIPTION NUMBER
1 50w LED ceiling mounted linear flourscent 260
2 20w LED ceiling recessed round LED downlight 18
3 40w round ceiling recessed LED 190
4 80w ceiling recessed modular with side-Lit design 510
5 1x60w LED in Die-cast Alumimnum 16
6 20w LED round ceiling luminaire I die cast alumimum 424
7 28w LED ceiling surface mounted Linear flouresent 184

SWITCHES

1 One gang Two way 55


2 One gang One way 340

EXTRACTOR FAN 88

POWER POINT
1 Mixed MCB/DB 155
2 AC socket point 95
3 10A 2gang 1 way switch 311
4 13A twin switch socket 6
5 Mixed MCCB main low voltage Distribution panel 4
6 CCU 3

FIRE DETECTOR
1 Heat Detector 80
2 Smoke Detector 182
3 Fire Alarm 33
4 4-Loop Analogue fire alarm control panel 4

CCTV LAYOUT
1 IP ceiling mounted fixed Dome Camera 8
2 Wall mounted fixed Bullet Vandal resistance Night-time
vision Camera 24
3 Wall mounted 3mp 60fp Vandal Resistance camera 12

SANITARY FITTINGS
1 Toilets 179
2 WH B 201
3 Urinals 22
4 Kitchen sink 4
Item Description Qty Unit Reference Unit Price Amount

Marble, Ceiling & Painitng

1 Carrara Marble Open Book Wall sqm 120 120,000.00 14,400,000.00


Finishing for toililet including installation

2 Skirting Finishing to a hight of 150mm LNR 230 70,000.00 16,100,000.00

3 Marble floor Finishing 20mm thick cut sqm 390 120,000.00 46,800,000.00
to size Botticino Design

4 Marble Border design LM 150 180,000.00 27,000,000.00

5 Ceiling finishing High Quality Gibson sqm 390 17,500.00 6,825,000.00


Board finishing

6 Ditto Cornice Design LM 195 5,000.00 975,000.00

7 Wall Screeding Plastic of Paris sqm 750 2,200.00 1,650,000.00

8 Dulux Mat finihing Wall Painitng sqm 750 4,000.00 3,000,000.00

Sub-total 116,750,000.00
Lighting & Fittings

1 Supply and Installation Spot light warm Nr 60 12,000.00 720,000.00


White

2 Supply and Installation LED Indirect LM 195 15,000.00 2,925,000.00


Lights with full accessories

3 Supply & Install indirect LED Light for LM 45 40,000.00 1,800,000.00


Corridors and Passage way

4 Supply and Install LED Chandelier Nr 6 385,000.00 2,310,000.00

5 Supply & Install LED Wall Unit Nr 12 39,000.00 468,000.00

6 Supply & Install Twin Adjustable LED Nr 18 43,500.00 783,000.00


Lights, with Hanging chasis on Ceiling

7 Legrand Socket Mat Finishing 16 amps Nr 55 35,000.00 1,925,000.00

8 Multipurpose All in-one Socket Legrand Nr 16 140,000.00 2,240,000.00

9 Legrand Switches Nr 64 32,000.00 2,048,000.00

Sub-total 15,219,000.00
Fire Alarm System

1 Complete Smart Fire Alarm Detection Complete 1 5,500,000.00 5,500,000.00


System networked to 25 points

Sub-total 5,500,000.00

Security Alarm System

Supply of Smart Alarm System with


1 Sensor across the complete Executive Nr 1 4,200,000.00 4,200,000.00
off to 6 points

Supply & Installation of complete CCTV


2 Security System including 12 Camera's, Nr 1 5,200,000.00 5,200,000.00
Cables, Clips, 2 Terabyte DVR with
Phone application

3 Supply and Installation of Internal Phone Nr 1 3,800,000.00 3,800,000.00


Network to 15 Points

4 Complete office Netwrok system to 12 Nr 1 4,220,000.00 4,220,000.00


points

5 6 kva Inverter System with 4 Deep Cycle Nr 1 5,000,000.00 5,000,000.00


Batteries

6 Supply and Installation of Complete DStv Nr 5 45,000.00 225,000.00


to 5 Points including 1 yr Subscription

7 Sub-total 22,645,000.00
Sanitaries, Doors & Wall finsih

1 Supply & Install of WC GROHE Wall Nr 3 600,000.00 1,800,000.00


Hanging Unit Including enclosure

2 Handheld Bidet Sprayer Set, Stainless Nr 3 116,000.00 348,000.00


Steel Hand Sprayer

3 Supply & Install Wash Hand Basin Wall Nr 4 700,000.00 2,800,000.00


Hanging System

4 Supply & Install GROHE Mixer Or Nr 4 70,000.00 280,000.00


approved Quality

5 Stainless Steel Kitchen Sink Nr 2 120,000.00 240,000.00

6 Complete Kitchen, Supply & Install MDF Nr 1 3,000,000.00 3,000,000.00


Kitchen with 20mm thick marble slab

Supply & Fix Flush Doors, Including


7 frames, key & Locks. Single Door 1100 x Nr 19 400,000.00 7,600,000.00
2100mm
Supply & Fix Flush Doors, Including
8 frames, key & Locks. Single Door 2300 x Nr 4 800,000.00 3,200,000.00
2100mm

9 Automated Main Entrance Secutiry Door Nr 1 1,500,000.00 1,500,000.00

10 Marble Wall Finishing, Including wall Sqm 108 100,000.00 10,800,000.00


polished wood finishing

Sub-total 31,568,000.00

Air-Conditioning

Midea/Samsung VRF Coolong System

1 3 units of 36 Horsepower 1 26,000,000.00 26,000,000.00


3

9 units of 12 Horsepower
9
Sub-total 26,000,000.00
Furnishing & Electronics

Supply of Chairman Executive Office


1 with Executive Swivel Chair & 2 Guest Nr 1 3,000,000.00 3,000,000.00
Chairs

2 Executive Archive Side Cabinet 3mtr Nr 1 1,800,000.00 1,800,000.00


Length

3 Churchil Leather Seater 3-Seater Nr 2 3,000,000.00 6,000,000.00

4 Executive Hand sewed Carpet Nr 1 3,000,000.00 3,000,000.00

5 Light Standing Nr 1 375,000.00 375,000.00

6 4 Seater Round Table Nr 1 1,700,000.00 1,700,000.00

7 16- Seater Conference Meeting Table Nr 1 8,500,000.00 8,500,000.00


8 24- Seater Conference Meeting Table Nr 1 11,000,000.00 11,000,000.00

9 Conference Side Console Cabinet Nr 1 1,500,000.00 1,500,000.00

Junior Satff Compete Office

10 1 Manager Seat 1 1,800,000.00 1,800,000.00

2 Guest Seats 2

11 Kitchenette Nr 1 2,500,000.00 2,500,000.00

12 Automatic Window Blinds 42pcs Nr 42 410,000.00 17,220,000.00


(280Sqm Blinds) with Remote Control

13 LG 82'' Television Chairman Office Nr 1 3,750,000.00 3,750,000.00

14 LG 55'' Television Office's Nr 3 1,200,000.00 3,600,000.00

15 Electric Kettle Nr 2 45,000.00 90,000.00

16 Microwave Nr 2 150,000.00 300,000.00


17 Electric Table Top Cooker Nr 2 280,000.00 560,000.00

Sub-total 66,695,000.00
Summary

1 Floor & Ceiling 116,750,000.00

2 Lighting 15,219,000.00

3 Fire Alarm 5,500,000.00

4 Security Alarm 22,645,000.00

5 Sanitaries,Doors, Wall & Kitchen 31,568,000.00

6 Air-Condition 26,000,000.00

7 Furnishing & Electronics 66,695,000.00


Sub-total 284,377,000.00
Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

BILL NR.2: OFFICE COMPLEX

SUBSTRUCTURE

GROUNDWORK

INFORMATION [All Provisional]

Nature and location of the work

The work in this section comprises:

(i) Excavations, trenches, pits and the likes, concrete work,


waterproofing, earth filling, and all other ancillary works associated
with strip/pad foundation up to and including ground floor slab.
(ii) All concrete works are provisional quantities in this
section

D20: EXCAVATING AND FILLING

Excavating

Top soil for preservation

A average 150mm deep 2319 m2 360.00 834,840.00

Mass Excavation for raft foundation

B maximum depth not exceeding 2500mm; commencing surface 3616 m3 1,850.00 6,689,600.00
150mm below existing ground level

Excavate pit for basement from ground level maximum depth not
exceeding 4.0metres deep and cart away spoil to temporary spoil
C 2872 m3 1,850.00 5,313,200.00
heap 150metres within the site

D Keeping excavation free from general and ground water item 1,500,000.00

Working space allowance to excavation; including additional


earthwork support, disposal and backfilling with selected
excavated material

E Pits for basement 1108 m3 1,850.00 2,049,800.00

F Pits for Mass excavation 517 m3 1,850.00 956,450.00

Disposal of excavated material

G off site 6488 m3 750.00 4,866,000.00

Bill Nr.2: Office complex Page 2/270


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


To collection : 22,209,890.00
Excavated material arising from excavation
Filling to excavation

A average thickness exceeding 0.25m 1625 m3 650.00 1,056,250.00

Selected excavated laterite material obtained from offsite


borrow pits

Filling to excavation; depositing in layers 150mm maximum


thickness

B average thickness exceeding 250mm 1346 m3 5,600.00 7,537,600.00

Hardcore to be obtained from off-site;


Filling to make up levels; depositing in layers 150mm maximum
thickness

C average thickness not exceeding 300mm 367 m3 6,500.00 2,385,500.00

Termite treatmment

D dieldrex 20" or other equal and approved anti-termite solution to 2108 m2 250.00 527,000.00
sides and bottom of excavtions

E Level and compact to the bottom of excavations 1764 m2 200.00 352,800.00

E IN - SITU CONCRETE
E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Plain in-situ concrete; mix 1:10, 20 aggregate; blinding


Raft foundation slab
F not exceeding 50mm thick; poured on earth surfaces 1764 m2 1,350.00 2,381,400.00

Reinforced; Insitu Vibrated Concrete Grade 25; developing


minimum 25.5N/mm2 work strength in 28 days

Ground beam;

G generally; 300 - 765mm thick 420 m3 45,500.00 19,110,000.00

Reinforced; Insitu Vibrated Concrete Grade 25.5; developing


minimum 25.5N/mm2 work strength in 28 days

Raft foundation

H generally; 250 - 500mm thick 794 m3 45,500.00 36,127,000.00

Bill Nr.2: Office complex Page 2/271


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 69,477,550.00
Columns (below basement to ground floor level 2)

A generally; thickness 230-900mm thick 106 m3 45,500.00 4,823,000.00

Beds (Ground slab basement)

B ground slabs; thickness 150-450mm thick 220 m3 45,500.00 10,010,000.00

Retaining wall

C Thickness not exceeding 150mm-300mm 45 m3 45,500.00 2,047,500.00

Lift shaft wall (basement-ground floor level 2)

D Thickness not exceeding 250mm-400mm 38 m3 45,500.00 1,729,000.00

Staircase in basement

Landing

E generally in landing 3 m3 45,500.00 136,500.00

Slopping soffit of stairs (Strings)

F generally 8 m3 45,500.00 364,000.00

Steps

G generally 3 m3 45,500.00 136,500.00

Landing beams

H generally 2 m3 45,500.00 91,000.00

200mm Suspended floor

J generally 66 m3 45,500.00 3,003,000.00

175mm Ground

K generally 213 m3 45,500.00 9,691,500.00

Entrance steps

L generally 6 m3 45,500.00 273,000.00

Ramp

Bill Nr.2: Office complex Page 2/272


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


M generally 11 m3 45,500.00 500,500.00

To collection : 32,805,500.00
Toes steps

A generally 1 m3 45,500.00 45,500.00

Suspended beam (ground level 1)

B generally 14 m3 45,500.00 637,000.00

Suspended beam (ground level 2)

C generally 75 m3 45,500.00 3,412,500.00

E20: FORMWORK FOR IN-SITU CONCRETE


Sawn formwork to:

Sides of raft foundations : plain vertical.

D Raft; height 250 - 500mm high 168 m 2,425.00 407,400.00

Sides of Ground beam foundations : plain vertical.

E Ground beam; height not exceeding 2000mm 1375 m2 4,850.00 6,668,750.00

Columns; isolated

F regular shaped; rectangular 814 m2 4,850.00 3,947,900.00

Retaining Wall

G Vertical sides of retaining wall 388 m2 4,850.00 1,881,800.00

Lift shaft wall

H Vertical sides of lift shaft wall 329 m2 4,850.00 1,595,650.00

Bed

J Bed; height 250 mm high 155 m 1,212.50 187,937.50

200mm Suspended Ground slab

K slab thickness not exceeding 200mm; height to soffit 3.0 - 4.5m 328 m2 4,850.00 1,590,800.00

175mm Suspended Ground slab

L slab thickness not exceeding 200mm; height to soffit 3.0 - 4.5m 1169 m2 4,850.00 5,669,650.00

Bill Nr.2: Office complex Page 2/273


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 26,044,887.50
Ground slab

A Ground slab; height 250 mm high 313 m 1,212.50 379,512.50

Suspended beam (ground level 1)

B Vertical sides and soffit of beam 148 m2 4,850.00 717,800.00

Suspended beam (ground level 2)

C Vertical sides and soffit of beam 654 m2 4,850.00 3,171,900.00

Staircase

Horizontal soffit of landing

D slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m 17 m2 4,850.00 82,450.00

Sides and soffit of landing beams

E slope exceeding 15 degrees 8 m2 4,850.00 38,800.00

Slopping soffit of stairs

F slope exceeding 15 degrees 44 m2 4,850.00 213,400.00

Edges of suspended landing; plain vertical

G height not exceeding 250mm 33 m 1,212.50 40,012.50

Steps; edges of risers, plain vertical

H average height 250mm 217 m 1,212.50 263,112.50

Raking string of steps

J width not exceeding 250mm 31 m 1,212.50 37,587.50

Sides of Ramp

K generally; 500 - 1000mm wide 20 m2 4,850.00 97,000.00

Bill Nr.2: Office complex Page 2/274


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 5,041,575.00
E30: REINFORCEMENT FOR IN-SITU CONCRETE
Reinforcement bars; B.S.4449, hot rolled deformed high yield
steel
Straight and bent

Raft Foundation

A 20mm diameter 23.25 t 455,500.00 10,590,375.00

B 16mm diameter 31.33 t 455,500.00 14,270,815.00

C 12mm diameter 14.86 t 455,500.00 6,768,730.00

Ground beam

D 16mm diameter 37.18 t 455,500.00 16,935,490.00

E 10mm diameter 4.24 t 455,500.00 1,931,320.00

Columns

F 32mm diameter 5.8 t 455,500.00 2,641,900.00

G 25mm diameter 29.36 t 455,500.00 13,373,480.00

H 20mm diameter 0.11 t 455,500.00 50,105.00

J 16mm diameter 0.18 t 455,500.00 81,990.00

K 10mm diameter (stirrups) 4.14 t 455,500.00 1,885,770.00

Retaining Wall

L 16mm diameter 4.32 t 455,500.00 1,967,760.00

M 10mm diameter (stirrups) 2.06 t 455,500.00 938,330.00

Lift wall shaft

N 20mm diameter 8.15 t 455,500.00 3,712,325.00

P 16mm diameter 0.03 t 455,500.00 13,665.00

Q 16mm diameter 0.84 t 455,500.00 382,620.00

Bill Nr.2: Office complex Page 2/275


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 75,544,675.00
Staircase

A 16mm diameter 0.9 t 455,500.00 409,950.00

B 12mm diameter 0.38 t 455,500.00 173,090.00

C 10mm diameter (stirrups) 0.65 t 455,500.00 296,075.00

200mm Suspended floor

D 16mm diameter 0.52 t 455,500.00 236,860.00

E 12mm diameter 4.7 t 455,500.00 2,140,850.00

F 10mm diameter 0.43 t 455,500.00 195,865.00

175mm Suspended floor

G 20mm diameter 0.59 t 455,500.00 268,745.00

H 16mm diameter 3.56 t 455,500.00 1,621,580.00

J 12mm diameter 14.21 t 455,500.00 6,472,655.00

K 10mm diameter 2.76 t 455,500.00 1,257,180.00

Beam (Provisional)

L 20mm diameter 7.5 t 455,500.00 3,416,250.00

M 10mm diameter (stirrups) 3.2 t 455,500.00 1,457,600.00

MASONRY

F10: BLOCK WALLING

Stone dust hollow blockwork, bedded and jointed in cement


and sand mortar (1:6)

Walls; filled solid with concrete grade 15

N 230mm thick; stretcher bond 22 m2 7,000.00 154,000.00

Bill Nr.2: Office complex Page 2/276


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 18,100,700.00
BUILDING FABRIC SUNDRIES

P10: SUNDRY INSULATION/ PROOFING WORK/ FIRE STOPS

Polythene sheeting, Visqueen 1000 gauge; 50mm thick welted


lapped joints

Plain areas

A horizontal; laid loose 4686 m2 250.00 1,171,500.00

Tanking
B Tanking to surfaces of retaining walls 388 m2 4,500.00 1,746,000.00

Water bar
C 300 x 3mm rubberized water bar Type AR 24 set in concrete 313 m 6,750.00 2,112,750.00

Expansion Joint
D Expansion joint 25mm thick flexcell board 29 m2 4,200.00 121,800.00

ADDITIONAL WORK IN SUBSTRUCTURE

Allow a provisional sum of N10,000.000.00 (Ten Million Naira


E Only) for unforseeing additional work in substructure to be sum 10,000,000.00
expended as may be directed by the Architect
To collection : 15,152,050.00
No Item Description Qty Unit Rate Amount
Collection
SUBSTRUCTURE.
Page 2/1 22,209,890.00

Page 2/2 69,477,550.00

Page 2/3 32,805,500.00

Page 2/4 26,044,887.50

Page 2/5 5,041,575.00

Page 2/6 75,544,675.00

Page 2/7 18,100,700.00

Bill Nr.2: Office complex Page 2/277


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


Page 2/8 15,152,050.00

To Office Complex collection : 264,376,827.50


FRAMES AND UPPER FLOORS

INFORMATION

Nature and location of the work

The work in this section comprises

(i.) Reinforced concrete columns, beams, suspended floor slabs


and associated works.
(ii.) The Contractor is however referred to Structural Engineer's
drawings for details and scope of the Works.

E IN - SITU CONCRETE

E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced; Insitu Vibrated Concrete Grade 25.5; developing


minimum 25.5N/mm2 work strength in 28 days

Slabs; suspended floor

A thickness not exceeding 200mm 1086 m3 45,500.00 49,413,000.00

Beams

B attached 366 m3 45,500.00 16,653,000.00

Columns

C generally 372 m3 45,500.00 16,926,000.00

Lift Shaft Wall

D generally 152 m3 45,500.00 6,916,000.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to:


Horizontal soffit of suspended slab/Cantilever;

E regular shaped; rectangular; 6144 m2 4,850.00 29,798,400.00

Bill Nr.2: Office complex Page 2/278


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


Edges of suspended slab; plain vertical

F height not exceeding 250mm 1326 m 1,212.50 1,607,775.00

To collection : 121,314,175.00
Beam

A regular shaped; rectangular; height to soffit exceeding 3000mm 3868 m2 4,850.00 18,759,800.00

Columns

B regular shaped; rectangular 2857 m2 4,850.00 13,856,450.00

Lift Shaft Wall

C Vertical sides 1343 m2 4,850.00 6,513,550.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield


steel

Straight and bent

Suspended slabs/cantilever

D 20mm diameter 1.89 t 455,500.00 860,895.00

E 16mm diameter 37.66 t 455,500.00 17,154,130.00

F 12mm diameter 46.79 t 455,500.00 21,312,845.00

G 10mm diameter 16.4 t 455,500.00 7,470,200.00

Columns (Provisional)

H 25mm diameter 48 t 455,500.00 21,864,000.00

J 20mm diameter 4.33 t 455,500.00 1,972,315.00

K 16mm diameter 0.65 t 455,500.00 296,075.00

L 10mm diameter (stirrups) 31.4 t 455,500.00 14,302,700.00

Beams

Bill Nr.2: Office complex Page 2/279


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

M 25mm diameter 34.01 t 455,500.00 15,491,555.00

N 20mm diameter 25.51 t 455,500.00 11,619,805.00

P 16mm diameter 17 t 455,500.00 7,743,500.00

Q 10mm diameter in links 8.5 t 455,500.00 3,871,750.00

To collection : 163,089,570.00
Lift Shaft wall

A 20mm diameter 29.12 t 455,500.00 13,264,160.00

B 16mm diameter 1.3 t 455,500.00 592,150.00

C 10mm diameter 4.03 t 455,500.00 1,835,665.00

To collection : 15,691,975.00

Collection

FRAME & UPPER FLOOR


Page 2/9 121,314,175.00

Page 2/10 163,089,570.00

Page 2/11 15,691,975.00

Bill Nr.2: Office complex Page 2/280


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To Office Complex collection : 300,095,720.00


STAIRCASES

INFORMATION

Nature and location of the work

The work in this section comprises

(i.) Reinforced concrete staircases and associated works.


(ii.) The Contractor is however referred to Structural Engineer's
drawings for details and scope of the Works.

E IN - SITU CONCRETE

E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced; Insitu Vibrated Concrete Grade 25.5; developing


minimum 25.5N/mm2 work strength in 28 days

Landing

A generally 18 m3 45,500.00 819,000.00

Slopping soffit of stairs

B generally 27 m3 45,500.00 1,228,500.00

Steps

C generally 10 m3 45,500.00 455,000.00

Landing beams

D generally 7 m3 45,500.00 318,500.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to:

Bill Nr.2: Office complex Page 2/281


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

Horinzontal soffit of landing

E slab thickness not exceeding 200mm; height to soffit 1.50 - 3.00m 100 m2 4,850.00 485,000.00

To Collection : 3,306,000.00
Sides and soffit of landing beams

A slope exceeding 15 degrees 47 m2 4,850.00 227,950.00

Slopping soffit of stairs

B slope exceeding 15 degrees 152 m2 4,850.00 737,200.00

Edges of suspended landing; plain vertical

C height not exceeding 250mm 88 m 1,212.50 106,700.00

Steps; edges of risers, plain vertical

D average height 150mm 487 m 727.50 354,292.50

Raking string of steps

E width not exceeding 250mm 248 m 1,212.50 300,700.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield


steel

Straight and bent

Stairs
F 16mm diameter 8.34 t 455,500.00 3,798,870.00

G 10mm diameter 0.97 t 455,500.00 441,835.00

Landing beams
H 20mm diameter 0.73 t 455,500.00 332,515.00

J 16mm diameter 0.26 t 455,500.00 118,430.00

K 10mm diameter (strirrups) 0.4 t 455,500.00 182,200.00

Bill Nr.2: Office complex Page 2/282


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

L31 METAL BALUSTRADES

K Stainless steel handrailing complete with balusters vertical and 188 m 75,000.00 14,100,000.00
horizontal member

To Collection : 20,700,692.50
SURFACE FINISHES

M10: SAND CEMENT/ CONCRETE/ SCREEDS/TOPPINGS

Mortar, cement and sand (1:4) beds and backings

30mm work to floor on concrete base

A landing 117 m2 2,000.00 234,000.00

25mm work to treads on concrete base

B width 300mm 704 m 600.00 422,400.00

12mm work to plain risers on concrete base

C height 150mm 704 m 300.00 211,200.00

12mm work to skirting on wall

D height 100mm 200 m 200.00 40,000.00

M40: STONE/ CONCRETE/ QUARRY/ CERAMIC TILING/MOSAIC

Supply and install

Non-slip vitrified floor tiles; 3 joints systematic layout,


bedding in 10 cement mortar (1:4); including pointing.

450mm x 450mm x 8mm thick to floors on cement and sand


base; level to falls only not exceeding 15 degrees from
horizontal

Landing
E patterned 117 m2 7,850.00 918,450.00

Staircase treads

Bill Nr.2: Office complex Page 2/283


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


F width 300mm 704 m 2,355.00 1,657,920.00

Staircase risers
G height 175mm 704 m 1,373.75 967,120.00

Skirting on wall
H height 100mm 200 m 785.00 157,000.00

To Collection : 4,608,090.00
M20: PLASTERED/RENDERED

Mortar, cement and sand (1:4); steel trowelled

12mm work to walls on concrete base or blockwork

Horizontal soffit of landing

A regular shaped; rectangular; height to soffit 1.50 - 3.00m 117 m2 1,800.00 210,600.00

Slopping soffit of stairs

B slope exceeding 15 degrees 196 m2 1,800.00 352,800.00

Raking string of staircase

C width not exceeding 250mm 279 m 450.00 125,550.00

M60: PAINTING/CLEAR FINISHING

P.O.P floating of slab soffits

D over 300mm wide; internal; as architectural details 117 m2 1,800.00 210,600.00

Slopping soffit of stairs

E slope exceeding 15 degrees 196 m2 1,800.00 352,800.00

Raking string of staircase

F width not exceeding 250mm 279 m 450.00 125,550.00

Bill Nr.2: Office complex Page 2/284


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To Collection : 1,377,900.00

One mist coat and two full coats of "dulux" emulsion paint

Cement rendered general surfaces

Horizontal soffit of landing

A regular shaped; rectangular; height to soffit 1.50 - 3.00m 117 m2 1,650.00 193,050.00

Slopping soffit of stairs

B slope exceeding 15 degrees from horizontal 196 m2 1,650.00 323,400.00

Raking string of staircase

C width not exceeding 250mm 279 m 412.50 115,087.50

To Collection : 631,537.50
No Item Description Qty Unit Rate Amount
Collection

STAIRCASE.
Page 2/12 3,306,000.00

Page 2/13 20,700,692.50

Page 2/14 4,608,090.00

Page 2/15 1,377,900.00

Page 2/16 631,537.50

Bill Nr.2: Office complex Page 2/285


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To Office Complex collection : 30,624,220.00


ROOF AND ROOF COVERING

INFORMATION

Nature and location of the work

The work in this section comprises

(i.) Reinforced concrete roof beams, structural timber works, roof


covering and associated works.
(ii.) The Contractor is however referred to Architect's and
Structural Engineer's drawing for the scope of work.

E IN - SITU CONCRETE

E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced; Insitu Vibrated Concrete Grade 25.5; developing


minimum 25.5N/mm2 work strength in 28 days

Beams; roof beams

A not exceeding 300mm deep 15 m3 45,500.00 682,500.00

Water tank and roof slab

B generally 26 m3 45,500.00 1,183,000.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to:

Beam; plain vertical

Bill Nr.2: Office complex Page 2/286


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

D roof beams 240 m2 4,850.00 1,164,000.00

To collection : 3,029,500.00
Horinzontal soffit of suspended roof slab;

A regular shaped; rectangular; 173 m2 4,850.00 839,050.00

Edges of suspended roof slab; plain vertical

B height not exceeding 250mm 152 m 1,212.50 184,300.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield


steel

Straight and bent

Roof Beams
C 16mm diameter 1.26 t 455,500.00 573,930.00

D 10mm diameter (stirrups) 0.55 t 455,500.00 250,525.00

Roof slabs
E 12mm diameter 1.7 t 455,500.00 774,350.00

F 10mm diameter 0.4 t 455,500.00 182,200.00

CLADDING/COVERING

J41: FLEXIBLE SHEET WATER PROOFING ROOF COVERINGS

3mm Rhino lining industrial type as manufactured by Rhino Lining


Ltd, in flat covering laid in accordance with the manufacturer's
fixing instructions on slab including one coat of bituminous primer

Gutters and linings; to concrete base

Bill Nr.2: Office complex Page 2/287


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

H girth exceeding 1000mm 1772 m2 32,000.00 56,704,000.00

Wall lining on cement and sand base

J girth exceeding 1000mm 238 m2 32,000.00 7,616,000.00

K Extra for dishing out around medium pipes 8 nr. 10,000.00 80,000.00

To collection : 67,204,355.00
SURFACE FINISHES

M10: SAND CEMENT/ CONCRETE/ SCREEDS/TOPPINGS

Mortar, cement and sand (1:3)

30mm work to roofs on concrete base; one coat; screeded

A to falls and crossfalls and to slopes not exceeding 15 degrees from 1772 m2 2,000.00 3,544,000.00
horizontal

M20: PLASTERED/RENDERED

Mortar,cement and sand (1:3) floated backing.

12mm work to walls on concrete base or blockwork

B width exceeding 300mm 238 m2 1,800.00 428,400.00

Danplon Transculent roof


Translucent roof covering complete with structural steel support at
C
the Entrance Porch as manufactured by CSA 80 m2 49,000.00 3,920,000.00

To collection : 7,892,400.00
No Item Description Qty Unit Rate Amount
Collection

Bill Nr.2: Office complex Page 2/288


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


ROOF AND ROOF COVERING

Page 2/17 3,029,500.00

Page 2/18 67,204,355.00

Page 2/19 7,892,400.00

To Office Complex collection : 78,126,255.00


EXTERNAL AND INTERNAL WALLS

INFORMATION

Nature and location of the work

The work in this section comprises

(i) The erection of hollow sandcrete block walls, reinforced


concrete lintels.
(ii) The Contractor is however referred to
Architect's and Structural Engineer's drawings for details and scope
of the scope of work

E IN - SITU CONCRETE

E10: MIXING/ CASTING/ CURING/ IN-SITU CONCRETE

Reinforced; Insitu Vibrated Concrete Grade 25.5; developing


minimum 25.5N/mm2 work strength in 28 days

Lintel

A generally 95 m3 45,500.00 4,322,500.00

E20: FORMWORK FOR IN-SITU CONCRETE

Sawn formwork to:

Lintel: sides and soffit.

Bill Nr.2: Office complex Page 2/289


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


B regular shaped rectangle 1250 m2 4,850.00 6,062,500.00

E30: REINFORCEMENT FOR IN-SITU CONCRETE

Reinforcement bars; B.S.4449, hot rolled deformed high yield


steel

Straight and bent

Lintel

C 16mm diameter 4 t 455,500.00 1,822,000.00

D 12mm diameter 4.2 t 455,500.00 1,913,100.00

E 10mm diameter (stirrups) 6.64 t 455,500.00 3,024,520.00

To collection : 17,144,620.00
MASONRY

F10: BLOCK WALLING

Stone dust hollow blockwork, bedded and jointed in cement


and sand mortar

Walls

A 230mm thick; stretcher bond; regular 6821 m2 6,550.00 44,677,550.00

B 230mm thick; ditto in dwarf wall single toilet area 1500mm high 77 m2 6,550.00 504,350.00

C 150mm thick; stretcher bond; regular 555 m2 5,895.00 3,271,725.00

100mm x 190mm x 190mm Glass block wall with 10mm joints with
D and including joint spacers and grouting in matching grout 36 m2 52,000.00 1,872,000.00

Expansion Joint
E Expansion joint 25mm thick flexcell board 459 m2 4,200.00 1,927,800.00

To collection : 52,253,425.00
No Item Description Qty Unit Rate Amount
Collection

EXTERNAL AND INTERNAL WALLS

Page 2/20 17,144,620.00

Bill Nr.2: Office complex Page 2/290


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

Page 2/21 52,253,425.00

To Office Complex collection : 69,398,045.00


L WINDOWS, CURTAIN WALLS AND DOORS

Bill Nr.2: Office complex Page 2/291


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


INFORMATION

Nature and location of the work

The work in this section comprises

(i) Timber flush door and steel frames, anodised aluminium doors
and windows.
(ii) The contractor is however referred to the Architectural doors
and windows schedule for details and scope of work.

L10: WINDOWS

L11 ALUMINIUM WINDOWS AND DOORS/CURTAIN WALL


L11 ALUMINIUM WINDOWS
Aluminium powder coated double glazed windows comprising 6mm
tinted 8mm void 6mm clear P4000 section obtainable from
NIGALEX

Basement
P4000 section obtainable from NIGALEX comprising of 1 nr single
A projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall 38 nr 173,500.00 6,593,000.00
900mm x 1200mm high

Ground Floor
P4000 section obtainable from NIGALEX comprising of 3nr center
projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall
B 2250mm x 2100mm high 3 nr 945,000.00 2,835,000.00

C Extra over for sun shade using 50mm louver blades 3 nr 177,000.00 531,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
D glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 13 nr 995,000.00 12,935,000.00
2100mm high

E Extra over for sun shade using 50mm louver blades 13 nr 201,500.00 2,619,500.00

P4000 section obtainable from NIGALEX comprising of 3nr center


F projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 524,250.00 1,048,500.00
1250mm x 2100mm high

G Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
H glazing 6mm tinted 8mm void 6mm clear, overrall 2550mm x 1 nr 1,150,000.00 1,150,000.00
2100mm high

To collection : 28,022,400.00
A Extra over for sun shade using 50mm louver blades 1 nr 143,100.00 143,100.00

Bill Nr.2: Office complex Page 2/292


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
B glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 1 nr 945,000.00 945,000.00
2100mm high

Bill Nr.2: Office complex Page 2/293


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

C Extra over for sun shade using 50mm louver blades 1 nr 177,000.00 177,000.00

P4000 section obtainable from NIGALEX comprising of 1nr bottom


D projected panel, 1nr top fixed panels, glazing 6mm tinted 8mm void 8 nr 240,000.00 1,920,000.00
6mm clear, overrall 900mm x 1800mm high

P4000 section obtainable from NIGALEX comprising of 2nr bottom


E projected panel, 2nr top fixed panels, glazing 6mm tinted 8mm void 6 nr 336,700.00 2,020,200.00
6mm clear, overrall 1500mm x 1200mm high

P4000 section obtainable from NIGALEX comprising of 1nr Double


hinged door with top fixed light, 3nr center projected panels,3nr
top fixed panels, 2nr bottom fixed panels, on two side of the door ,
F glazing 6mm tinted 8mm void 6mm clear, overrall 5400mm x 2 nr 1,885,500.00 3,771,000.00
(2100/3000)mm high

G Extra over for sun shade using 50mm louver blades 2 nr 542,400.00 1,084,800.00

P4000 section obtainable from NIGALEX comprising of 1nr Double


hinged door with top fixed light, 3nr center projected panels,3nr
top fixed panels, 2nr bottom fixed panels, on one side of the door ,
H glazing 6mm tinted 8mm void 6mm clear, overrall 3400mm x 1 nr 1,552,000.00 1,552,000.00
(2100/3000)mm high

J Extra over for sun shade using 50mm louver blades 1 nr 403,200.00 403,200.00

First floor

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
K glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 3 nr 945,000.00 2,835,000.00
2100mm high

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
L glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 17 nr 995,000.00 16,915,000.00
2100mm high

M Extra over for sun shade using 50mm louver blades 17 nr 126,000.00 2,142,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


N projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 524,250.00 1,048,500.00
1250mm x 2100mm high

To collection : 34,956,800.00

A Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00

Bill Nr.2: Office complex Page 2/294


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


P4000 section obtainable from NIGALEX comprising of 1nr bottom
B projected panel, 1nr top fixed panels, glazing 6mm tinted 8mm void 8 nr 240,000.00 1,920,000.00
6mm clear, overrall 900mm x 1800mm high

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
C glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 1 nr 945,000.00 945,000.00
2100mm high

D Extra over for sun shade using 50mm louver blades 1 nr 177,000.00 177,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
E glazing 6mm tinted 8mm void 6mm clear, overrall 2550mm x 1 nr 1,150,000.00 1,150,000.00
2100mm high

F Extra over for sun shade using 50mm louver blades 1 nr 143,100.00 143,100.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
G glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 11 nr 995,000.00 10,945,000.00
2100mm high

P4000 section obtainable from NIGALEX comprising of 4nr center


projected panel, 4nr top fixed panels, 3nr bottom fixed panels
H glazing 6mm tinted 8mm void 6mm clear, overrall 3400mm x 2 nr 1,552,000.00 3,104,000.00
2100mm high

J Extra over for sun shade using 50mm louver blades 2 nr 403,250.00 806,500.00

P4000 section obtainable from NIGALEX comprising of 2nr bottom


K projected panel, 2nr top fixed panels, glazing 6mm tinted 8mm void 13 nr 336,700.00 4,377,100.00
6mm clear, overrall 1500mm x 1200mm high

Second floor

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
L glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 2 nr 945,000.00 1,890,000.00
2100mm high

M Extra over for sun shade using 50mm louver blades 2 nr 177,000.00 354,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
N glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 16 nr 995,000.00 15,920,000.00
2100mm high

To collection : 42,042,100.00

A Extra over for sun shade using 50mm louver blades 16 nr 201,500.00 3,224,000.00

Bill Nr.2: Office complex Page 2/295


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

P4000 section obtainable from NIGALEX comprising of 3nr fixed


B projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 524,250.00 1,048,500.00
1250mm x 2100mm high

C Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00

P4000 section obtainable from NIGALEX comprising of 1nr bottom


D projected panel, 1nr top fixed panels, glazing 6mm tinted 8mm void 8 nr 240,000.00 1,920,000.00
6mm clear, overrall 900mm x 1800mm high

P4000 section obtainable from NIGALEX comprising of 3nr bottom


E projected panel, 3nr top fixed panels, glazing 6mm tinted 8mm 8 nr 880,000.00 7,040,000.00
void 6mm clear, overrall 2400mm x 1500mm high

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panel
F glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 1 nr 945,000.00 945,000.00
2100mm high

G Extra over for sun shade using 50mm louver blades 1 nr 177,000.00 177,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
H glazing 6mm tinted 8mm void 6mm clear, overrall 2550mm x 1 nr 1,150,000.00 1,150,000.00
2100mm high

J Extra over for sun shade using 50mm louver blades 1 nr 143,100.00 143,100.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
K glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 1 nr 995,000.00 995,000.00
2100mm high

P4000 section obtainable from NIGALEX comprising of 2nr bottom


L projected panel, 2nr top fixed panels, glazing 6mm tinted 8mm void 25 nr 336,700.00 8,417,500.00
6mm clear, overrall 1500mm x 1200mm high

Third floor

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
M glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 4 nr 945,000.00 3,780,000.00
2100mm high

N Extra over for sun shade using 50mm louver blades 4 nr 177,000.00 708,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
P glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 29 nr 995,000.00 28,855,000.00
2100mm high

To collection : 58,713,500.00

Bill Nr.2: Office complex Page 2/296


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

A Extra over for sun shade using 50mm louver blades 29 nr 201,500.00 5,843,500.00

P4000 section obtainable from NIGALEX comprising of 3nr fixed


B projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 524,250.00 1,048,500.00
1250mm x 2100mm high

C Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00

P4000 section obtainable from NIGALEX comprising of 1nr bottom


D projected panel, 1nr top fixed panels, glazing 6mm tinted 8mm void 8 nr 240,000.00 1,920,000.00
6mm clear, overrall 900mm x 1800mm high

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
E glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 3 nr 945,000.00 2,835,000.00
2100mm high

F Extra over for sun shade using 50mm louver blades 3 nr 177,000.00 531,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
G glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 1 nr 995,000.00 995,000.00
2100mm high

P4000 section obtainable from NIGALEX comprising of 4nr center


projected panel, 4nr top fixed panels, 3nr bottom fixed panels
H glazing 6mm tinted 8mm void 6mm clear, overrall 3400mm x 2 nr 1,552,000.00 3,104,000.00
2100mm high

J Extra over for sun shade using 50mm louver blades 2 nr 440,500.00 881,000.00

P4000 section obtainable from NIGALEX comprising of 2nr bottom


K projected panel, 2nr top fixed panels, glazing 6mm tinted 8mm void 25 nr 336,700.00 8,417,500.00
6mm clear, overrall 1500mm x 1200mm high

Fourth Floor
P4000 section obtainable from NIGALEX comprising of 3nr center
projected panel, 3nr top fixed panels, 2nr bottom fixed panels
L glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 4 nr 945,000.00 3,780,000.00
2100mm high

M Extra over for sun shade using 50mm louver blades 4 nr 177,000.00 708,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
N glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 29 nr 995,000.00 28,855,000.00
2100mm high

K Extra over for sun shade using 50mm louver blades 29 nr 201,500.00 5,843,500.00

Bill Nr.2: Office complex Page 2/297


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


To collection : 65,072,400.00

P4000 section obtainable from NIGALEX comprising of 3nr fixed


A projected panel, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 524,250.00 1,048,500.00
1250mm x 2100mm high

B Extra over for sun shade using 50mm louver blades 2 nr 155,200.00 310,400.00

P4000 section obtainable from NIGALEX comprising of 1nr bottom


C projected panel, 1nr top fixed panels, glazing 6mm tinted 8mm void 8 nr 240,000.00 1,920,000.00
6mm clear, overrall 900mm x 1800mm high

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
D glazing 6mm tinted 8mm void 6mm clear, overrall 2250mm x 3 nr 945,000.00 2,835,000.00
2100mm high

E Extra over for sun shade using 50mm louver blades 3 nr 177,000.00 531,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
F glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 1 nr 995,000.00 995,000.00
2100mm high

P4000 section obtainable from NIGALEX comprising of 4nr center


projected panel, 4nr top fixed panels, 3nr bottom fixed panels
G glazing 6mm tinted 8mm void 6mm clear, overrall 3400mm x 2 nr 1,552,000.00 3,104,000.00
2100mm high

H Extra over for sun shade using 50mm louver blades 2 nr 403,250.00 806,500.00

P4000 section obtainable from NIGALEX comprising of 2nr bottom


J projected panel, 2nr top fixed panels, glazing 6mm tinted 8mm void 16 nr 336,700.00 5,387,200.00
6mm clear, overrall 1500mm x 1200mm high

Fifth Floor

P4000 section obtainable from NIGALEX comprising of 1nr bottom


K projected panel, 1nr top fixed panels, glazing 6mm tinted 8mm void 8 nr 240,000.00 1,920,000.00
6mm clear, overrall 900mm x 1800mm high

P4000 section obtainable from NIGALEX comprising of 2nr bottom


L projected panel, 2nr top fixed panels, glazing 6mm tinted 8mm void 16 nr 336,700.00 5,387,200.00
6mm clear, overrall 1500mm x 1200mm high

Pent floor

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
M glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 1 nr 995,000.00 995,000.00
2100mm high

Bill Nr.2: Office complex Page 2/298


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 25,239,800.00

A Extra over for sun shade using 50mm louver blades 1 nr 201,500.00 201,500.00

P4000 section obtainable from NIGALEX comprising of 4nr center


projected panel, 4nr top fixed panels, 3nr bottom fixed panels
B glazing 6mm tinted 8mm void 6mm clear, overrall 3250mm x 1 nr 1,701,000.00 1,701,000.00
2100mm high

C Extra over for sun shade using 50mm louver blades 1 nr 397,000.00 397,000.00

P4000 section obtainable from NIGALEX comprising of 3nr center


projected panel, 3nr top fixed panels, 2nr bottom fixed panels
D glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 1 nr 995,000.00 995,000.00
2100mm high

CURTAIN WALL

Ground floor

Semi structural curtain wall section obtainable from NIGALEX


E comprising of 16nr horizontal division & 6nr vertical division, glazing 1 nr 44,320,000.00 44,320,000.00
6mm tinted 8mm void 6mm clear glass, over all size 23745mm x
7950mm high (C-shape)

Semi structural curtain wall section obtainable from NIGALEX


F comprising of 4nr horizontal division & 6nr vertical division, glazing 1 nr 12,252,000.00 12,252,000.00
6mm tinted 8mm void 6mm clear glass, over all size 3250mm x
7950mm high (L-shape)

Semi structural curtain wall section obtainable from NIGALEX


G comprising of 12nr horizontal division & 6nr vertical division, glazing 1 nr 46,600,000.00 46,600,000.00
6mm tinted 8mm void 6mm clear glass, over all size 19025mm x
7950mm high (Z-shape)

Semi structural curtain wall section obtainable from NIGALEX


H comprising of 3nr horizontal division & 6nr vertical division, glazing 1 nr 8,146,000.00 8,146,000.00
6mm tinted 8mm void 6mm clear glass, over all size 4950mm x
7950mm high

First Floor

Semi structural curtain wall section obtainable from NIGALEX


J comprising of 4nr horizontal division & 2nr vertical division, glazing 1 nr 8,783,000.00 8,783,000.00
6mm tinted 8mm void 6mm clear glass, over all size 4270mm x
2700mm high

Second Floor

Bill Nr.2: Office complex Page 2/299


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

Semi structural curtain wall section obtainable from NIGALEX


K comprising of 13nr horizontal division & 1nr vertical division, glazing 1 nr 26,755,000.00 26,755,000.00
6mm tinted 8mm void 6mm clear glass, over all size 19760mm x
3900mm high
To collection : 150,150,500.00

Semi structural curtain wall section obtainable from NIGALEX


A comprising of 8nr horizontal division & 1nr vertical division, glazing 1 nr 18,680,000.00 18,680,000.00
6mm tinted 8mm void 6mm clear glass, over all size 10320mm x
3900mm high

Semi structural curtain wall section obtainable from NIGALEX


B comprising of 5nr horizontal division & 1nr vertical division, glazing 1 nr 13,078,500.00 13,078,500.00
6mm tinted 8mm void 6mm clear glass, over all size 7500mm x
3900mm high

Semi structural curtain wall section obtainable from NIGALEX


C comprising of 6nr horizontal division & 3nr vertical division, glazing 1 nr 8,722,500.00 8,722,500.00
6mm tinted 8mm void 6mm clear glass, over all size 8735mm x
3900mm high (L-Shaped)

Third Floor

Semi structural curtain wall section obtainable from NIGALEX


D comprising of 10nr horizontal division & 3nr vertical division, glazing 1 nr 19,280,500.00 19,280,500.00
6mm tinted 8mm void 6mm clear glass, over all size 13000mm x
3900mm high

Fourth Floor

Semi structural curtain wall section obtainable from NIGALEX


E comprising of 10nr horizontal division & 3nr vertical division, glazing 1 nr 19,280,500.00 19,280,500.00
6mm tinted 8mm void 6mm clear glass, over all size 13000mm x
3900mm high

Fifth Floor

Semi structural curtain wall section obtainable from NIGALEX


F comprising of 10nr horizontal division & 3nr vertical division, glazing 2 nr 19,280,500.00 38,561,000.00
6mm tinted 8mm void 6mm clear glass, over all size 13000mm x
3900mm high

Semi structural curtain wall section obtainable from NIGALEX


G comprising of 14nr horizontal division & 3nr vertical division, glazing 1 nr 23,950,000.00 23,950,000.00
6mm tinted 8mm void 6mm clear glass, over all size 17965mm x
3900mm high

Semi structural curtain wall section obtainable from NIGALEX


H comprising of 11nr horizontal division & 3nr vertical division, glazing 1 nr 21,250,000.00 21,250,000.00
6mm tinted 8mm void 6mm clear glass, over all size 14950mm x
3900mm high

Semi structural curtain wall section obtainable from NIGALEX


J comprising of 24nr horizontal division & 3nr vertical division, glazing 1 nr 32,500,000.00 32,500,000.00
6mm tinted 8mm void 6mm clear glass, over all size 31285mm x
3900mm high

Bill Nr.2: Office complex Page 2/300


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

Semi structural curtain wall section obtainable from NIGALEX


K comprising of 20nr horizontal division & 3nr vertical division, glazing 1 nr 32,805,000.00 32,805,000.00
6mm tinted 8mm void 6mm clear glass, over all size 26385mm x
3900mm high
To collection : 228,108,000.00

Semi structural curtain wall section obtainable from NIGALEX


A comprising of 11nr horizontal division & 3nr vertical division, glazing 1 nr 20,120,500.00 20,120,500.00
6mm tinted 8mm void 6mm clear glass, over all size 14960mm x
3900mm high

Semi structural curtain wall section obtainable from NIGALEX


B comprising of 14nr horizontal division & 3nr vertical division, glazing 1 nr 25,060,000.00 25,060,000.00
6mm tinted 8mm void 6mm clear glass, over all size 18000mm x
3900mm high

Pent Floor

Semi structural curtain wall section obtainable from NIGALEX


C comprising of 10nr horizontal division & 3nr vertical division, glazing 1 nr 19,285,000.00 19,285,000.00
6mm tinted 8mm void 6mm clear glass, over all size 13000mm x
3900mm high

Aluminium Doors

Ground Floors

P4000 section obtainable from NIGALEX comprising of 1nr Double


D hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 1,200,000.00 2,400,000.00
2400mm x 2400mm high (Normal door)

P4000 section obtainable from NIGALEX comprising of 1nr Double


E hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 7,235,000.00 14,470,000.00
2400mm x 2400mm high (Sensor door)

P4000 section obtainable from NIGALEX comprising of 1nr Double


F hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 786,500.00 1,573,000.00
1200mm x 2400mm high (Normal door)

P4000 section obtainable from NIGALEX comprising of 1nr Double


G hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 1 nr 908,000.00 908,000.00
1600mm x 2400mm high (Normal door)

First Floor

P4000 section obtainable from NIGALEX comprising of 1nr Double


H hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 1 nr 908,000.00 908,000.00
1600mm x 2400mm high (Normal door)

Second Floor

P4000 section obtainable from NIGALEX comprising of 1nr Double


J hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 3 nr 908,000.00 2,724,000.00
1600mm x 2400mm high (Normal door)

Bill Nr.2: Office complex Page 2/301


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


Third Floor

P4000 section obtainable from NIGALEX comprising of 1nr Double


K hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 908,000.00 1,816,000.00
1600mm x 2400mm high (Normal door)

To collection : 89,264,500.00
Fourth Floor

P4000 section obtainable from NIGALEX comprising of 1nr Double


A hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 3 nr 908,000.00 2,724,000.00
1600mm x 2400mm high (Normal door)

Fifth Floor
P4000 section obtainable from NIGALEX comprising of 1nr Double
B hinged pane, glazing 6mm tinted 8mm void 6mm clear, overrall 2 nr 908,000.00 1,816,000.00
1600mm x 2400mm high (Normal door)

GX section obtainable from NIGALEX comprising of 2nr sliding


C panel,glazing 6mm tinted 8mm void 6mm clear, overrall 2400mm x 2 nr 1,755,000.00 3,510,000.00
2400mm high

L21 METAL DOORS/SHUTTERS/HATCHES

Fire Escape Steel Door


D Size 1600 x 2400mm high steel fire rated door 21 nr 545,500.00 11,455,500.00

Security doors
Supply and install israeli security door size 900mm x 2400mm high
E 2 nr 568,700.00 1,137,400.00

Subframe
F Allow a provisional sum of N2,500,000.00 for Sub frame sum 2,500,000.00

L20 TIMBER DOORS/SHUTTERS/HATCHES

Doors in hardwood; selected for transparent finishings


High quality timber doors

Flush; 44 Single action flush door with extruded chipboard core in


single leaf; both faces covered with 6 external quality veneer
plywood; hardwood lipped all round including ironmongery and door
stopper frame 250mm depth complete with architrave produced by
Hit furnitures or approved type

G Size 800 x 2100 high overall 67 nr 270,000.00 18,090,000.00

H Size 950 x 2100 high overall 8 nr 270,000.00 2,160,000.00

J Size 800 x 2400 high overrall 11 nr 355,000.00 3,905,000.00

K Size 950 x 2400 high overrall 9 nr 355,000.00 3,195,000.00

L Size 1000 x 2400 high overrall 93 nr 355,000.00 33,015,000.00

Bill Nr.2: Office complex Page 2/302


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

M Size 1200 x 2400 high overrall 13 nr 320,000.00 4,160,000.00

To collection : 87,667,900.00

P BUILDING FABRIC SUNDRIES


P21 IRONMONGERY

Stainless steel; IR Security & Safety Ltd. U.K


Name plates
A Quttro female sex symbol; Ref QFS1; finish: SS 12 nr 25,000.00 300,000.00

B Quttro male sex symbol; Ref QMS1; finish: SS 12 nr 25,000.00 300,000.00


'SENIOR STAFF TOILET' sign engraved on stainless steel plate
C size 350 x 100; Ref IRXX; finish: SS 21 nr 25,000.00 525,000.00

D Biometric lock 13 nr 100,000.00 1,300,000.00

To collection : 2,425,000.00
No Item Description Qty Unit Rate Amount
Collection

WINDOWS AND DOORS

Page 2/22 28,022,400.00

Page 2/23 34,956,800.00

Page 2/24 42,042,100.00

Page 2/25 58,713,500.00

Page 2/26 65,072,400.00

Page 2/27 25,239,800.00

Page 2/28 150,150,500.00

Page 2/29 228,108,000.00

Page 2/30 89,264,500.00

Page 2/31 87,667,900.00

Page 2/32 2,425,000.00


To Office Complex collection : 811,662,900.00

Bill Nr.2: Office complex Page 2/303


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

FITTING AND FIXTURES

FURNITURE/EQUIPMENT

INFORMATION

Nature and location of the work

The work in this section comprises

(i.) joinery and associated works


(ii.) Metal balcony railings and wall grilles
(iii.) The Contractor is however referred to Architect's details and
scope of work

ALUMINIUM DUCT COVER

Natural anodize aluminium luxalon; complete including lugging,


pinning and pointing in lugs to blockwork or concretework and
pointing all round both with approved mastic

A Aluminium luxalon grille duct cover grilles vertical 195 m2 67,500.00 13,162,500.00

Steel Cat Ladder


B Construct and install steel cat ladder 600 wide x 27300mm high 1 nr 390,000.00 390,000.00

Kitchen cabinets

Fitted kitchen cabinet comprising 18mm thick laminated door 2mm


thick edging complete with matching screws,glues and necessary
accessories

Base Unit

C Overrall size 6160mm long x 720mm wide x 600mm depth 6 m2 830,300.00 4,981,800.00

Upper Unit

D Overrall size 4300mm long x 720mm wide x 300mm depth 4 m2 745,350.00 2,981,400.00

E Granite top size 6160mm long x 720mmwide x 20mm thick 6 m2 731,800.00 4,390,800.00

F Single bowl sink (Stainless Steel) 1 nr 300,000.00 300,000.00

G Hood Extractor 90cm 1 nr 245,000.00 245,000.00

Bill Nr.2: Office complex Page 2/304


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount


To collection : 26,451,500.00
KITCHENNETTE
Fitted kitchen cabinet comprising 18mm thick laminated door 2mm
thick edging complete with matching screws,glues and necessary
accessories

Base Unit

A Overrall size 1750mm long x 720mm wide x 600mm depth 2 m2 255,150.00 510,300.00

Upper Unit

B Overrall size 1750mm long x 720mm wide x 300mm depth 2 m2 303,350.00 606,700.00

C Granite top size 6160mm long x 720mmwide x 20mm thick 2 m2 732,000.00 1,464,000.00

D Single bowl sink (Stainless Steel) 1 nr 300,000.00 300,000.00

E Hood Extractor 60cm 1 nr 180,000.00 180,000.00

Wall panelling
F High quality timber wall panelling 326 m2 76,000.00 24,776,000.00

TOILET PARTITION (Female)

G 4 Ways Toilet Partition and door size 4270mm x 2085mm x


1800mm 24 Nos. 731,500.00 17,556,000.00

TOILET PARTITION (Male)

H 5 Ways Toilet Partition and door size 5620mm x 2085mm


x1800mm 30 Nos. 1,070,000.00 32,100,000.00

J Urinal Partition 600mm long x 2085mm high 18 Nos. 30,000.00 540,000.00

Door partitions

K
900mm x 2100mm high complete with lock,frame and door stopper 25 nr 45,000.00 1,125,000.00

To collection : 79,158,000.00
No Item Description Qty Unit Rate Amount
Collection

FITTINGS AND FIXTURES


Page 2/33 26,451,500.00

Page 2/34 79,158,000.00

Bill Nr.2: Office complex Page 2/305


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To Office Complex collection : 105,609,500.00


FLOOR FINISHING

SURFACE FINISHES

INFORMATION

Nature and location of the work

The work in this section comprises


(i) Floor finishings with and other associated works
(ii) The Contractor is hereby referred to
the various Architect's location drawings and schedule of finishing
in relation to this section for the nature and content of the work to
be executed.

M10: SAND CEMENT/ CONCRETE/ SCREEDS/TOPPINGS

Mortar, cement and sand (1:4)

50mm work to floors on concrete base; one coat; screeded

level and to falls only not exceeding 15 degrees from horizontal


A trowelled smooth treated with anti - dusting hardener on monolithic 1430 m2 1,500.00 2,145,000.00
concrete clear finish

42mm work to floors on concrete base; one coat; screeded

B level and to falls only not exceeding 15 degrees from horizontal to 532 m2 1,500.00 798,000.00
receive unglazed vitrified tiles (Toilet and kitchen only)

40mm work to floors on concrete base; one coat; screeded

C level and to falls only not exceeding 15 degrees from horizontal to 3759 m2 1,500.00 5,638,500.00
receive unglazed vitrified tiles (offices and lobby)

30mm work to floors on concrete base; one coat; screeded

D level and to falls only not exceeding 15 degrees from horizontal to 654 m2 2,000.00 1,308,000.00
receive granite tiles and epoxy flooring

12mm cement backing to skirting on wall

E height 100mm 2751 m 1,800.00 4,951,800.00

Bill Nr.2: Office complex Page 2/306


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 14,841,300.00
M40: TILING
Spanish Unglazed vitrified floor tiles; 3 joints systematic
layout, bedding in 10mm cement mortar (1:3); including
pointing.

300mm x 300mm x 8mm thick to floors on cement and sand


base; level to falls only not exceeding 15 degrees from
horizontal (toilet and kitchen only)

A patterned; over 300mm wide 532 m2 5,750.00 3,059,000.00

450mm x 450mm x 8mm thick to floors on cement and sand


base; level to falls only not exceeding 15 degrees from
horizontal

B patterned; over 300mm wide 3759 m2 7,850.00 29,508,150.00

Nigeria granite dark granite from rich quarries/CIBI or any


other equal qualityfloor tilling 600mm x 600mm X 30mm, on
cement and sand screeded bed ( staircase area) 3 joints
systematic layout, bedding in cement mortar (1:4); including
pointing. In floor

600mm x 600mm x 30mm thick to floors on cement and sand


base; level to falls only not exceeding 15 degrees from
horizontal
C patterned; over 300mm wide 565 m2 47,000.00 26,555,000.00

D 100mm skirting 2751 m 4,700.00 12,929,700.00

Entrance Steps
E Tread 300mm wide 71 m 10,000.00 710,000.00

F Risers 150mm wide 71 m 5,000.00 355,000.00

Raised floors; Made of Pedestrials in Galvanised steel with relevant


gasket for pedestral H 300m based 1200mm/head 200mm 'U'
section stringers 200 x 30 x 20mm in galvanised steel with relevant
gasket (wood raised floor)

Floor cavity 150 high; fixing with adhesive


G Access panels 600 x 600 with wood matt finish 452 m2 49,000.00 22,148,000.00

EPOXY RESIN MORTAR

H Water based breathable epoxy resin mortar screed flooring system


Basement applied according to manufacture specification 89 m2 50,000.00 4,450,000.00

To collection : 99,714,850.00

Page 2/35 14,841,300.00

Bill Nr.2: Office complex Page 2/307


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

Page 2/36 99,714,850.00

To Office Complex collection : 114,556,150.00

WALL FINISHING

SURFACE FINISHES

INFORMATION

Nature and location of the work

The work in this section comprises

(i) Walls finishings with and including other associated works but
excluding painting which is measured in a separate element.
(ii) The Contractor is
hereby referred to the various Architect's location drawings in
relation to this section for the nature and content of the work to be
executed.

M20: PLASTERED/RENDERED

Mortar, cement and sand (1:4); steel trowelled

12mm work to walls on concrete base or blockwork

A width exceeding 300mm 12570 m2 1,800.00 22,626,000.00

B width not exceeding 300mm 5850 m 540.00 3,159,000.00

C width not exceeding 300mm; isolated columns 2242 m2 1,800.00 4,035,600.00

M40: CERAMIC TILING

Spanish Glazed Ceramic tiles, B.S.6431, glazed; 2 joints,


symmetrical layout; fixing with adhesive or cement mortar,
grouting with matching cement grout

300mm x 450mm x 6mm thick to walls on sand and cement


base (toilet and kitchen)

D patterned, width exceeding 300mm 2783 m2 5,750.00 16,002,250.00

E width not exceeding 300mm 981 m 1,725.00 1,692,225.00

Bill Nr.2: Office complex Page 2/308


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To collection : 47,515,075.00

Spanish Unglazed wall tiles 3 joints systematic layout,


bedding in 10 cement mortar (1:3); including pointing.

600mm x 300mm x 10mm thick to walls on sand and cement


base (on retaining wall in basement)

A patterned, width exceeding 300mm 724 m2 5,750.00 4,163,000.00

B width not exceeding 300mm 306 m 1,725.00 527,850.00

Glazed Granite tiles, dark granite, glazed; 2 joints,


symmetrical layout; fixing with adhesive or cement mortar,
grouting with matching cement grout

75mm x 30mm thick to skirtings on cement and sand base; cut


to suite tiles size in toilet

C height 100mm 656 m 1,800.00 1,180,800.00

EXTERNAL WORK

Aluco bond

Supply and install 4mm thick aluminum alucobond panel cladding


D with top layer PVDF coated including Aluminium profile system 7066 m2 45,000.00 317,970,000.00
with all necessary accessories on wall in specified colour
To collection : 323,841,650.00

Collection

WALL FINISHING

Page 2/37 47,515,075.00

Page 2/38 323,841,650.00

Bill Nr.2: Office complex Page 2/309


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To Office Complex collection : 371,356,725.00


CEILING FINISHING

INFORMATION

Nature and location of the work

The work in this section comprises

(i) Ceiling finishings with and including other associated works but
excluding painting which is measured in a separate Element
(ii) The Contractor is hereby referred to the various Architect's
location drawings in relation to this section for the nature and
content of the work to be executed.
SURFACE FINISHES

K13 RIGID SHEET LINNING/COVERING

Suspended linings; Armstrong micro perforated orcal/metal flush


tegular ceiling tiles with black accoustic fleece size 600mm x
600mm x 15mm thick complete with armstrong javelin exposed T24
grid or other approved tiles
Ceilings
A Suspension 500 to 1000 deep; 15mm thick; in 600 x 600 panels 5262 m2 9,000.00 47,358,000.00

Aluminium ceilings strips


Armstrong cellio Aluminium ceilings strips rectangular shaped with
B T15 grid or other equal and approved type in basement
1430 m2 45,345.00 64,843,350.00

Aluminium framed cover filled transparent pvc sheet in entrance


C lobby in ground floor 135 m2 55,500.00 7,492,500.00

Screeding and floating of slab soffits


over 300mm wide; internal; as architectural details (basement only)
D 1430 m2 1,800.00 2,574,000.00

One mist coat and two full coats of "dulux" emulsion paint
over 300mm wide; internal; as architectural details (basement only)
E 1430 m2 1,650.00 2,359,500.00

Mortar, cement and sand (1:4); steel trowelled


12mm work to walls on concrete base or blockwork
F width exceeding 300mm 6593 m2 1,800.00 11,867,400.00

Bill Nr.2: Office complex Page 2/310


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

To Office Complex collection : 136,494,750.00


PAINTING AND DECORATONS

SURFACE FINISHES

INFORMATION

Nature and location of the work

The work in this section comprises

(i.) Painting and decorations on new works.


(ii.) The Contractor is however referred to Architect's details and
location drawings for the details and scope of the works to be
executed in this section.

M60: PAINTING/CLEAR FINISHING

Prepare and apply standard coat of plaster of paris floating to:

Cement rendered general surfaces

A girth exceeding 300mm; wall internally 9787 m2 1,800.00 17,616,600.00

B width not exceeding 250mm 4869 m 450.00 2,191,050.00

Prepare and apply one layer sealer and one layer undercoat
"dulux" silk emulsion paint.

Cement rendered general surfaces

C girth exceeding 300mm; wall externally 9787 m2 1,650.00 16,148,550.00

D girth not exceeding 300mm 4869 m 495.00 2,410,155.00

To Office Complex collection : 38,366,355.00

Bill Nr.2: Office complex Page 2/311


Proposed Head Office NPF PENSIONS LTD

No Item Description Qty Unit Rate Amount

OFFICE COMPLEX COLLECTION AMOUNT

SUBSTRUCTURE 264,376,827.50

FRAMES AND UPPER FLOORS 300,095,720.00

STAIRCASES 30,624,220.00

ROOF CONSTRUCTION AND ROOF COVERING 78,126,255.00

EXTERNAL AND INTERNAL WALLS 69,398,045.00

WINDOWS, CURTAIN WALL AND DOORS 811,662,900.00

FITTINGS AND FIXTURES 105,609,500.00

FLOOR FINISHING 114,556,150.00

WALL FINISHING 371,356,725.00

CEILING FINISHING 136,494,750.00

PAINTING AND DECORATONS 38,366,355.00

To GENERAL SUMMARY 2,320,667,447.50

Bill Nr.2: Office complex Page 2/312


Page №:(313)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 730 1309 2611 0 0 0 0 4650

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(314)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)
shear wall w1 T12 2 294 588 № 5000 2610.720

T10 2 24 48 № 44210 1309.323

T8 24 220 5280 № 350 729.960

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(315)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

4650.003

9300.006

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(316)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(317)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(318)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(319)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(320)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 647 0 0 910 0 0 0 1556

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(321)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)
C7 grd flr-1st flr T16 22 16 352 № 0.000

T8 22 33 726 № 0.000

C6 T16 8 16 128 № 4500 909.504

T8 8 33 264 № 6200 646.536

C9 T16 24 16 384 № 0.000

T8 24 33 792 № 0.000

C8 T20 1 18 18 № 0.000

T8 1 33 33 № 0.000

C5 T16 1 20 20 № 0.000

T8 1 33 33 № 0.000

C4 T20 2 16 32 № 0.000

T8 2 33 66 № 0.000

C3 T16 1 18 18 № 0.000

T8 1 33 33 № 0.000

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(322)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

1556.040

3112.080

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(323)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(324)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(325)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(326)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(327)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 2903 0 0 3681 555 0 0 7138

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(328)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)
C7 grd flr-1st flr T16 22 16 352 № 4500 2501.136

T8 22 33 726 № 6200 1777.974

C6 T16 8 16 128 № 4500 909.504

T8 8 33 264 № 6200 646.536

C9 T16 24 16 384 № 0.000

T8 24 33 792 № 0.000

C8 T20 1 18 18 № 4500 199.827

T8 1 33 33 № 6600 86.031

C5 T16 1 20 20 № 4500 142.110

T8 1 33 33 № 9720 126.700

C4 T20 2 16 32 № 4500 355.248

T8 2 33 66 № 6200 161.634

C3 T16 1 18 18 № 4500 127.899

T8 1 33 33 № 7960 103.759

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(329)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

7138.358

14276.716

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(330)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(331)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(332)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(333)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(334)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 4842 0 0 6409 555 0 0 11806

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(335)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)
C7 grd flr-1st flr T16 22 16 352 № 4500 2501.136

T8 22 33 726 № 6200 1777.974

C6 T16 8 16 128 № 4500 909.504

T8 8 33 264 № 6200 646.536

C9 T16 24 16 384 № 4500 2728.512

T8 24 33 792 № 6200 1939.608

C8 T20 1 18 18 № 4500 199.827

T8 1 33 33 № 6600 86.031

C5 T16 1 20 20 № 4500 142.110

T8 1 33 33 № 9720 126.700

C4 T20 2 16 32 № 4500 355.248

T8 2 33 66 № 6200 161.634

C3 T16 1 18 18 № 4500 127.899

T8 1 33 33 № 7960 103.759

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(336)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

11806.478

23612.956

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(337)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(338)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(339)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(340)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(341)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 0 0 46297 0 0 0 0 46297

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(342)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)
Y REINFOR. TOP T12 532 1 532 № 11750 5550.888

T12 30 1 30 № 5000 133.200

T12 30 1 30 № 6750 179.820

T12 18 1 18 № 10500 167.832

T12 56 1 56 № 4000 198.912

T12 154 1 154 № 12000 1641.024

T12 78 1 78 № 5500 380.952

T12 563 1 563 № 7250 3624.594

T12 282 1 282 № 9000 2253.744

T12 37 1 37 № 2500 82.140

T12 20 1 20 № 5500 97.680

T12 76 1 76 № 4750 320.568

T12 18 1 18 № 9500 151.848

Y REINFOR. BOTTOM T12 532 1 532 № 11750 5550.888

T12 30 1 30 № 5000 133.200

T12 30 1 30 № 6750 179.820

T12 18 1 18 № 10500 167.832

T12 56 1 56 № 4000 198.912

T12 154 1 154 № 7500 1025.640

T12 78 1 78 № 10000 692.640

T12 563 1 563 № 11500 5749.356

T12 282 1 282 № 9000 2253.744

T12 37 1 37 № 2500 82.140

T12 20 1 20 № 5500 97.680

T12 76 1 76 № 9250 624.264

T12 18 1 18 № 9500 151.848

X REINFOR. TOP T12 383 1 383 № 12000 4081.248

T12 300 1 300 № 10000 2664.000

T12 6 1 6№ 11500 61.272

T12 21 1 21 № 6500 121.212

T12 56 1 56 № 7750 385.392

T12 24 1 24 № 7500 159.840

T12 6 1 6№ 3500 18.648

T12 130 1 130 № 9000 1038.960

T12 41 1 41 № 6250 227.550

T12 39 1 39 № 6750 233.766

T12 307 1 307 № 11500 3135.084

T12 24 1 24 № 9500 202.464

T12 68 1 68 № 9500 573.648

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(343)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 82 1 82 № 10000 728.160

T12 52 1 52 № 5500 253.968

T12 16 1 16 № 11750 166.944

T12 52 1 52 № 12000 554.112

X REINFOR. BOTTOM T12 1 10750 0.000

T12 1 12000 0.000

T12 1 5000 0.000

T12 1 9750 0.000

T12 1 7000 0.000

T12 1 12000 0.000

T12 1 5250 0.000

T12 1 11500 0.000

T12 1 10000 0.000

T12 1 7250 0.000

T12 1 6000 0.000

T12 1 11500 0.000

T12 1 4750 0.000

T12 1 6250 0.000

X REINFOR. BOTTOM T12 1 7500 0.000

T12 1 7500 0.000

T12 1 7750 0.000

T12 1 10500 0.000

T12 1 5500 0.000

T12 1 9500 0.000

T12 1 9250 0.000

T12 1 10250 0.000

T12 1 11250 0.000

T12 1 11500 0.000

T12 1 3500 0.000

T12 1 9500 0.000

T12 1 10500 0.000

T12 1 7750 0.000

T12 1 5500 0.000

T12 1 10750 0.000

T12 1 10500 0.000

T12 1 5000 0.000

T12 1 9750 0.000

T12 1 10000 0.000

T12 1 12000 0.000

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(344)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 1 9000 0.000

T12 1 8500 0.000

T12 1 10000 0.000

T12 1 7250 0.000

T12 1 8000 0.000

T12 1 11500 0.000

T12 1 4750 0.000

T12 1 6250 0.000

T12 1 6500 0.000

46297.434

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(345)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(346)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 0 0 57350 0 0 0 0 57350

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(347)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Y REINFOR. TOP T12 261 1 261 № 11000 2549.448

T12 185 1 185 № 11250 1848.150

T12 42 1 42 № 9750 363.636

T12 30 1 30 № 4500 119.880

T12 30 1 30 № 6750 179.820

T12 18 1 18 № 10500 167.832

T12 56 1 56 № 4000 198.912

T12 36 1 36 № 9250 295.704

T12 147 1 147 № 12000 1566.432

T12 74 1 74 № 5500 361.416

T12 577 1 577 № 7250 3714.726

T12 287 1 287 № 9000 2293.704

T12 18 1 18 № 9500 151.848

T12 73 1 73 № 4750 307.914

Y REINFOR. BOTTOM T12 261 1 261 № 11000 2549.448

T12 185 1 185 № 11250 1848.150

T12 42 1 42 № 9750 363.636

T12 30 1 30 № 4500 119.880

T12 30 1 30 № 6750 179.820

T12 18 1 18 № 10500 167.832

T12 56 1 56 № 4000 198.912

T12 36 1 36 № 9250 295.704

T12 74 1 74 № 7500 492.840

T12 74 1 74 № 10000 657.120

T12 577 1 577 № 11500 5892.324

T12 73 1 73 № 8750 567.210

T12 18 1 18 № 9500 151.848

T12 73 1 73 № 8000 518.592

X REINFOR. TOP T12 21 1 21 № 7500 139.860

T12 96 1 96 № 12000 1022.976

T12 273 1 273 № 12000 2909.088

T12 123 1 123 № 10000 1092.240

T12 6 1 6№ 11000 58.608

T12 24 1 24 № 9500 202.464

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(348)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 14 1 14 № 9250 114.996

T12 8 1 8№ 10250 72.816

T12 48 1 48 № 7500 319.680

T12 13 1 13 № 7000 80.808

T12 6 1 6№ 3500 18.648

T12 233 1 233 № 9000 1862.136

T12 38 1 38 № 6250 210.900

T12 50 1 50 № 12000 532.800

T12 14 1 14 № 9500 118.104

T12 339 1 339 № 10750 3236.094

T12 94 1 94 № 12000 1001.664

T12 23 1 23 № 5000 102.120

T12 46 1 46 № 9750 398.268

T12 23 1 23 № 7000 142.968

T12 34 1 34 № 12000 362.304

T12 15 1 15 № 5250 69.930

T12 34 1 34 № 11500 347.208

T12 10 1 10 № 10000 88.800

T12 10 1 10 № 7250 64.380

T12 16 1 16 № 6000 85.248

T12 41 1 41 № 11500 418.692

T12 3 1 3№ 4750 12.654

T12 3 1 3№ 6250 16.650

X REINFOR. BOTTOM T12 21 1 21 № 7500 139.860

T12 96 1 96 № 7500 639.360

T12 158 1 158 № 7750 1087.356

T12 296 1 296 № 10500 2759.904

T12 6 1 6№ 5500 29.304

T12 24 1 24 № 9500 202.464

T12 14 1 14 № 9250 114.996

T12 8 1 8№ 10250 72.816

T12 48 1 48 № 11250 479.520

T12 25 1 25 № 11500 255.300

T12 6 1 6№ 3500 18.648

T12 53 1 53 № 9500 447.108

T12 38 1 38 № 10500 354.312

T12 50 1 50 № 7750 344.100

T12 14 1 14 № 5500 68.376

T12 224 1 224 № 10750 2138.304

T12 94 1 94 № 10500 876.456

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(349)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T12 23 1 23 № 5000 102.120

T12 46 1 46 № 9750 398.268

T12 23 1 23 № 10000 204.240

T12 17 1 17 № 12000 181.152

T12 145 1 145 № 9000 1158.840

T12 34 1 34 № 8500 256.632

T12 10 1 10 № 10000 88.800

T12 10 1 10 № 7250 64.380

T12 125 1 125 № 8000 888.000

T12 41 1 41 № 11500 418.692

T12 3 1 3№ 4750 12.654

T12 3 1 3№ 6250 16.650

T12 53 1 53 № 6500 305.916

57350.370

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(350)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(351)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 0 156 0 695 0 0 0 850

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(352)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)
T10 74 2 148 № 1200 109.579

T10 23 1 23 № 3250 46.121

T16 22 1 22 № 20000 694.760

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(353)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

850.460

1700.920

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(354)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(355)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(356)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(357)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(358)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 22583 0 0 35669 3393 0 0 61646

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(359)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)
T16 18 1 18 № 1110000 31548.420

T16 25 1 25 № 68590 2707.590

T20 21 1 21 № 65500 3393.359

T16 4 1 4№ 65500 413.698

T16 18 1 18 № 35170 999.602

T8 7400 1 7400 № 6700 19584.100

T8 460 1 460 № 7300 1326.410

T8 437 1 437 № 7000 1208.305

T8 235 1 235 № 5000 464.125

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(360)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

61645.609

123291.218

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(361)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(362)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(363)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(364)

Bar ø of №of №of Total Weight


Description of Elements Cutting length Code A B C D E F Shape
Mark Bars Elmts Bars № (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(365)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 9598 0 0 16911 0 0 0 26509

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(366)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

COL 1 T16 81 26 2106 № 5000 16626.870

T8 81 40 3240 № 7400 9470.520

COL 2 T16 1 36 36 № 5000 284.220

T8 1 40 40 № 8080 127.664

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(367)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

26509.274

53018.548

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(368)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(369)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(370)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(371)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(372)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 291 1521 2372 0 0 0 0 4184

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(373)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)
shear wall w1 T12 4 62 248 № 4200 924.941

T10 4 50 200 № 5050 623.170

T8 4 252 1008 № 350 139.356

W2 T12 2 44 88 № 4200 328.205

T10 2 50 100 № 4100 252.970

T8 2 80 160 № 350 22.120

W3 T12 2 62 124 № 4200 462.470

T10 2 50 100 № 5050 311.585

T8 2 252 504 № 350 69.678

W4 T12 4 44 176 № 4200 656.410

T10 4 50 200 № 2700 333.180

T8 4 108 432 № 350 59.724

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(374)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

4183.809

8367.618

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(375)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(376)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(377)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(378)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
Page №:(379)

Type your name of company here.


1sides
Name of Project only

Name of Structure

SUMMARY OF REINFORCEMENT STEEL

Size of bar T8 T10 T12 T16 T20 T25 T32 Total

Weight (Kg) 0 1093 0 1216 1813 687 0 4809

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(380)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)
FB 01 T16 2 1 2№ 2330 7.358

T16 3 1 3№ 2330 11.037

T10 9 1 9№ 1510 8.385

FB02 T16 3 2 6№ 3530 33.443

T16 3 2 6№ 3530 33.443

T10 18 2 36 № 1510 33.540

FB03 T16 3 2 6№ 3750 35.528

T20 3 2 6№ 3050 45.146

T20 3 2 6№ 6080 89.996

T10 31 2 62 № 1510 57.764

FB04 T16 3 1 3№ 6900 32.685

T16 3 1 3№ 6900 32.685

T10 34 1 34 № 1510 31.677

FB05 T16 3 1 3№ 6900 32.685

T25 5 1 5№ 6900 132.998

T10 46 1 46 № 1510 42.857

FB07 T20 4 2 8№ 2700 53.287

T16 2 2 4№ 3300 20.843

T20 4 2 8№ 3230 63.747

T16 3 2 6№ 1700 16.106

T20 4 2 8№ 4730 93.351

T16 3 2 6№ 2030 19.232

T10 41 2 82 № 1510 76.397

FB06 T16 2 1 2№ 3600 11.369

T20 3 1 3№ 3950 29.234

T16 2 1 2№ 2600 8.211

T16 3 1 3№ 1800 8.527

T16 2 1 2№ 2600 8.211

T16 3 1 3№ 1800 8.527

T16 2 1 2№ 2600 8.211

T16 3 1 3№ 1800 8.527

T16 2 1 2№ 2750 8.685

T20 3 1 3№ 3950 29.234

T16 2 1 2№ 3500 11.053

T20 3 1 3№ 4130 30.566

T16 3 1 3№ 6000 28.422

T16 3 1 3№ 7330 34.722

T16 3 1 3№ 6000 28.422

T20 3 1 3№ 4420 32.712

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(381)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T10 132 1 132 № 1510 122.980

FB08 T16 3 1 3№ 4100 19.422

T20 6 1 6№ 2400 35.525

T16 3 1 3№ 4100 19.422

T20 4 1 4№ 9600 94.733

T10 48 1 48 № 1510 44.720

FB 09 & 12 T16 3 2 6№ 5090 48.223

T20 3 2 6№ 5090 75.342

T10 25 2 50 № 1510 46.584

FB10 T16 3 2 6№ 4730 44.812

T20 5 2 10 № 4730 116.689

T10 24 2 48 № 1510 44.720

FB 11 T16 2 2 4№ 2030 12.821

T16 3 2 6№ 2030 19.232

T10 8 2 16 № 1510 14.907

FB13 T16 3 2 6№ 4500 42.633

T20 5 2 10 № 2650 65.376

T16 3 2 6№ 4500 42.633

T25 5 2 10 № 10330 398.222

FB14 T16 3 2 6№ 4560 43.201

T20 3 2 6№ 4560 67.497

T10 23 2 46 № 1510 42.857

FB15 T16 3 2 6№ 5030 47.654

T20 5 2 10 № 5030 124.090

T10 25 2 50 № 1510 46.584

FB16 T16 3 2 6№ 5330 50.496

T20 5 2 10 № 5330 131.491

T10 28 2 56 № 1510 52.174

FB17 T16 3 2 6№ 6740 63.855

T20 5 2 10 № 6740 166.276

T10 45 2 90 № 1810 100.509

FB18 T16 3 2 6№ 5630 53.339

T20 6 2 12 № 5630 166.671

T10 28 2 56 № 1510 52.174

FB 19 T16 3 2 6№ 4330 41.022

T20 4 2 8№ 1830 36.117

T20 3 2 6№ 5630 83.335

T10 29 2 58 № 1510 54.037

FB 20 T16 3 2 6№ 6740 63.855

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(382)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

T25 3 2 6№ 6740 155.896

T10 45 2 90 № 1810 100.509

FB21 T16 3 2 6№ 5590 52.960

T20 4 2 8№ 5590 110.324

T10 27 2 54 № 1510 50.310

FB22 T16 3 2 6№ 3960 37.517

T16 3 2 6№ 3960 37.517

T10 20 2 40 № 1510 37.267

FB23 T16 3 1 3№ 5830 27.617

T20 5 1 5№ 5830 71.913

T10 29 1 29 № 1810 32.386

4809.269

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(383)

Bar ø of №of №of Total Cutting Weight


Description of Elements Code A B C D E F Shape
Mark Bars Elmts Bars № length (Kg)

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06
BILL No. 1

PRELIMINARIES
Preliminaries

APPENDIX TO THE CONDITIONS

Clause
Defects Liability Period 15,16
& 30 6 months from the day named in the
certificate of Practical Completion of
the Works or at the end of a rainy
season, whichever is later.

Insurance cover for any one occurrence or series of occurrence


19(1)(a) N500,000
arising out of one event

Percentage to cover 20 ₦0.10


Professional fees

Date for possession 21 To be agreed

Date for Completion 21 To be agreed

Liquidation and Ascertained Damages 22 N 500,000 PER WEEK

Period of Delay:

by reason of loss or damage caused by any of the contingencies


26
referred to in clause 20 (if none stated is 3 months).

for any other reason


(if none stated is one month) Prime cost sums for which the
27(g)
Contractor wishes to tender

Period of Interim Certificates 30(1) Monthly 30 working Days

Percentage of Certified Value Retained


30(3)
10%

Limit of Retention Fund


30(3) 5% of the Contract Sum
5%

6 months from the day named in the


Period of Final Measurement and Valuation certificate of Practical Completion of
30(5) the Works

S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
Bill Nr 1;PRELIMINARIES Page 1/384
PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

PRELIMINARIES AND GENERAL CLAUSES


AND PREAMBLES TO THE TRADES

PRELIMINARIES AND GENERAL CLAUSES

Condition of Contract

The Articles of Agreement and Conditions of Contracts are set out


in full in previous pages of this document. .

Conditions of Contract shall be the JCT 1980 1994 Revision for


Construction for building and engineering works designed by the
Employer. For convenience, only those provisions considered to
have an obvious financial effect are set out below and against each
provision, the price shall be inserted for

Clause Nr.
1 Contractor's Obligations

2 Architect's/S.O Instructions

3 Contract Documents

4 Statutory Obligations, notices, fees and charges

5 Levels and setting out of the Works

6 Materials, goods and workmanship to conform to description,


testing and inspection.

7 Royalties and patent rights

8 Foreman-in-charge

9 Access for Architect/S.O to the Works

10 Clerk of Works

11 Variatrion, provisional and prime cost sums

12 Contract Bills

13 Contract Sum

14 Unfixed goods and materials

15 Practical completion and defects liability

16 Sectional completion

17 Assignment or sub-letting

To Collection

Bill Nr 1;PRELIMINARIES Page 1/385


PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06
S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
Preliminaries (Cont'd)

Clause Nr.

18
Injury to persons and property and Employer's indemnity

19 Insurance against injury to persons and property

20 Insurance of the Works against fire, etc.

21 Possession, completion and postponement

22 Damages for non-completion

23 Extension of time

24 Loss and expense caused by disturbance of regular programme of


the Works

25 Determination by Employer

26 Determination by Contractor

27 Nominated sub-contractor

28 Nominated suppliers

29 Artists and Tradesmen

30 Certificates and payments

31 Fluctuations

32 Outbreaks of hostilities

33 War damage

34 Antiquities

35 Arbitration

To Collection ₦0.00 ₦0.00


S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
Bill Nr 1;PRELIMINARIES Page 1/386
PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

1.1: PROJECT PARTICULARS


Name, nature and location

The work comprises demolition of existing structure and cartaway


A debris and construction of mixed development of 9 level floor 1 item
constructions. Size approximately 86.2m long x 65.0m wide x
28.5m high. The suspended floor slab is constructred of reinforced
concrete floor.

Floor finishes are generally vitrified ceramic tiles in lettable areas


and the apartment. Granite in Public area and staircase. Plaster of
paris ceiling in all the ceilings.

Services consists ducted package air conditioning; 1nr. 500kva


Generator with diesel tank 4 nr. passenger lifts, electrical
installation and plumbing installation.

External works consists of the entire paved hardstanding and lawn 1 item
area.

Nature: Mixed development


Location: Plot 2877, Maitama District, Cadastral Zone :A06
FCT, Abuja.

B Name and addresses of Employer and Consultants

ARCHITECTS (hereinunder referred to as CA)


JAVA DESIGN CONCEPTS LTD
Plot No 559, Jahi-Katampe Road, Jahi District Abuja.

STRUCTURAL ENGINEER
JAVA DESIGN CONCEPTS LTD
Plot No 559, Jahi-Katampe Road, Jahi District Abuja.

MECHANICAL & ELECTRICAL ENGINEERS


JAVA DESIGN CONCEPTS LTD
Plot No 559, Jahi-Katampe Road, Jahi District Abuja.

QUANTITY SURVEYORS
BILLSTEC ASSOCIATES
SUITE 6,Develyn Place
No 6, Nouakchott street,Wuse zone 1
FCT, Abuja.
E-mail: Billstecassociates@gmail.com

Bill Nr 1;PRELIMINARIES Page 1/387


PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

To collection ₦0.00 ₦0.00 ₦0.00 ₦0.00


S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
THE PRINCIPAL CONTRACTOR: "The Contractor" 1 item

A EMPLOYER : AFROLYKE GLOBE LIMITED 1 item

B PROJECT MANAGER: BILLSTEC ASSOCIATES 1 item

C "CONTRACT ADMINISTRATOR (hereinunder referred to as 'CA): 1 item


The Project Manager"

D "PLANNING SUPERVISOR: 1 item


The Architect"

E A20: THE CONTRACT /SUB-CONTRACT

F Form of contract

G JCT 80;1994 revision standard conditions

under seal 1 item

H Performance guarantee bond/collateral warranties/Advance


payment bond

Performance Bond 1 item

Advance payment bond 1 item

Contractors All Risk Policy 1 item

J A30 EMPLOYER'S REQUIREMENTS: PROVISION, CONTENT AND USE


OF DOCUMENTS

Employer's requirements or limitations

No part of the tender document shall be copied or use for any


other purposes than for this project without the written consent of
the consultant (s) concerned

A31 EMPLOYER'S REQUIREMENTS: MANAGEMENT OF THE WORKS

Employer's requirements or limitations

the contractor shall be required to carry out test for all concrete
K work including an not limited to cube tests (for 7, 14 and 28 days)
after casting and re-bar test to determine strength of each supplies
to site.

Testing of Materials
L Include the following Provisional Sum of N1,500,000.00 1 item ₦500,000.00 ₦1,000,000.00 ₦1,500,000.00
for Testing of Materials

Statutory charges
Include the Provisional Sum of N4,000,000.00
M for Statutory/Stacking/EIA 1 item ₦4,000,000.00 ₦4,000,000.00
charges to be expended directly by the client

Mobilization and demobilization

Mobilization of all supervisions, labours, plants, materials and


N 1 item ₦5,000,000.00 ₦5,000,000.00
equipments necessary for the proper execution of the Works.

De-mobilization of all supervisions, labours, plants, materials and


P 1 item ₦5,000,000.00 ₦5,000,000.00
equipments necessary for the proper execution of the Works

Supervision of the works.

Q An English speaking qualified full time supervisor shall be required 1 item ₦30,000,000.00 ₦30,000,000.00
for the duration of the contract period

R Maintain public and private roads 1 item ₦1,000,000.00 ₦1,000,000.00

S Maintain live services 1 item ₦1,000,000.00 ₦1,000,000.00

Bill Nr 1;PRELIMINARIES Page 1/388


PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

To collection ₦9,500,000.00 ₦33,000,000.00 ₦5,000,000.00 ₦47,500,000.00


S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
PROGRESS REPORT

The contractor shall submit progress photograph in 5 sets on


A monthly basis with site progress report on the basis approved by 1 item ₦500,000.00 ₦500,000.00
the Architects

A32: EMPLOYER'S REQUIREMENTS: SPECIFIC LIMITATIONS ON


METHOD /SEQUENCE /TIMING/USE OF SITE

Employer's requirements or limitations, details stated

B Design constraints; Contractors are advised to view the designs 1 item ₦0.00
(Architectural, Structural and Services) and allow here for
complying with any constrain imposed on the work due to the
nature of the design, component materials and specifications.

Method and sequence of work: Tenderers are advised to read


C through the "instruction to persons tendering" and allow herein 1 item ₦0.00
for any special obligation imposed on the contractors on method
and work sequence

D Access: This shall include maintaining of the existing road adjoining 1 item ₦0.00
the site for the duration of the work.

E Use of the site; It is expected that the site will be used only for the 1 item ₦0.00
purpose of the work.
The site shall not be for any other unrelated activities except with
the express and written permission of the Architect.

Working hours: This shall be between the hours of 7am to 5pm


F (Monday to Saturday). 1 item ₦0.00
Any additional working hour may be employed by the contractor
for the purpose of meeting work schedule and targets as laid down
in the work program.
Any additional cost of fulfilling the contractors obligation in term
of meeting program targets should be allowed here.

Overtime/Labour Fluctuation : Overtime claim will only be


G entertained where specifically requested and ordered by the 1 item ₦0.00
Architect to cover delays under clause 31 of the contract
conditions.
Fluctuation claim on labour shall be on the actual labour work
force on site. The contractor is to make allowance herein for claim
to cover off-site work force partially employed on the work.

A33 EMPLOYER'S REQUIREMENTS: FACILITIES /TEMPORARY


WORKS /SERVICES

Employer's requirements or limitations, details stated

Office construction shall be light airy manner with air-conditioned


for Employer, made up of Port-a-cabins shall be constructed
H comprising of conference hall accomdate 10seater, toilets, 1 item ₦5,000,000.00 ₦1,000,000.00 ₦500,000.00 ₦6,500,000.00
Waiting room, with power, water and internet facilities to meet up
with standard office requirement

The Contractor shall supply minimum of following new furniture


and other items for the employer office (Contractor shall provide
warranty card or slip for all Electronic items)

J Visitor chair (4nr) 1 item ₦240,000.00 ₦240,000.00

K Office Tables (2nr) 1 item ₦380,000.00 ₦380,000.00

L Lockable filing cabinets (2nr) 1 item ₦200,000.00 ₦200,000.00

Bill Nr 1;PRELIMINARIES Page 1/389


PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

To collection ₦5,820,000.00 ₦1,500,000.00 ₦500,000.00 ₦7,820,000.00


S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
A Storage cupboard/ book case (1nr) 1 item ₦95,000.00 ₦95,000.00

B Swivel based/ sprung back desk chair (2nr) 1 item ₦200,000.00 ₦200,000.00

C Conference table (1nr) 1 item ₦500,000.00 ₦500,000.00

D Conference chairs (10nr) 1 item ₦570,000.00 ₦570,000.00

E Electric kettle (1nr) 1 item ₦15,000.00 ₦15,000.00

F 350 liter refrigerator (1nr) 1 item ₦465,000.00 ₦465,000.00

G Microwave oven (1nr) 1 item ₦45,000.00 ₦45,000.00

H Office Sofa chair 2 seater (1nr) 1 item ₦200,000.00 ₦200,000.00

J Complete Projector equipment (1nr) 1 item ₦650,000.00 ₦100,000.00 ₦750,000.00

K Dstv (1nr) 1 item ₦45,000.00 ₦720,000.00 ₦765,000.00

L Tv 55 inches LG (1nr) 1 item ₦460,000.00 ₦460,000.00

M Photocopier (1nr) 1 item ₦750,000.00 ₦200,000.00 ₦950,000.00

N Computers (1nr) 1 item ₦400,000.00 ₦100,000.00 ₦500,000.00

P Printers (1nr) 1 item ₦50,000.00 ₦70,000.00 ₦120,000.00

Q Water dispenser (1nr) 1 item ₦65,000.00 ₦40,000.00 ₦105,000.00

Site records
R Operation and maintenance manuals. 1 item ₦800,000.00 ₦800,000.00

S Compilation of health and safety file. 1 item ₦500,000.00 ₦500,000.00

Temporary fences, hoardings, screens and roofs


T Provision of 6mm painted plywood hoarding 2.40m high with and 1 item ₦3,500,000.00 ₦500,000.00 ₦4,000,000.00
including hardwood timber support members approximately 81m

Name boards (1 nr.)

The Contractor shall allow for the provision, erection and


maintenance of necessary site notice board as required by the
U Project Manager to display image of the project, project name, the 1 item ₦500,000.00 ₦300,000.00 ₦800,000.00
Employer's name and names of all Consultants associated with the
Project and building permit detail

A34: EMPLOYER'S REQUIREMENTS: OPERATION /MAINTENANCE


OF THE FINISHED BUILDING

Employer's requirements or limitations

The contractor shall be expected to maintain and keep the building


V free of defect for six months duration of defect liability period. 1 item ₦1,500,000.00 ₦1,500,000.00
Including training of building user's staff in the operation and
maintenance

Bill Nr 1;PRELIMINARIES Page 1/390


PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

To collection ₦8,510,000.00 ₦3,330,000.00 ₦1,500,000.00 ₦13,340,000.00


S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
A40: CONTRACTOR'S GENERAL COST ITEMS: MANAGEMENT AND
STAFF

Management and staff

A General management staff including site supervisors, site clerk and 1 item ₦50,000,000.00 ₦50,000,000.00
other site management staff.

A41: CONTRACTOR'S GENERAL COST ITEMS: SITE


ACCOMMODATION

Site accommodation

B shall include site offices and sanitary rooms for consultants (2nr 1 item ₦10,000,000.00 ₦4,000,000.00 ₦2,500,000.00 ₦16,500,000.00
offices) complete with air-conditioning, office desk and drawers
and drawing tables.

One air-conditioned large meeting room to contain a minimum of


15 persons within the existing structure complete with
C comfortable meeting table and chairs and the contractor shall 1 item ₦7,500,000.00 ₦10,000,000.00 ₦1,500,000.00 ₦19,000,000.00
provide for one wireless fixed digital telephone for use by
consultants and provide for refreshments (finger meals and drinks)
for every site meetings (ONCE monthly)

Maintenance of project office and office equipment includes


cleaning on daily basis and to provide consumable items for the
D 1 item ₦9,600,000.00 ₦9,600,000.00
use of Employer and consultant such as toilet soaps, towels, pantry
items like clean drinking water, milk, coffee, sugar, etc.,

The Contractor shall supply of stationaries and other sundry items


(copy papers, pens, pencils, leads, erasers, pins, staplers, pin
E 1 item ₦9,600,000.00 ₦9,600,000.00
boards, binder, paper cutter, heavy duty punching machine,
mirror, waste bins, desk paper trays, clocks, etc.).

The Contractor shall supply of toners, special colour printing paper,


F 1 item ₦3,500,000.00 ₦3,500,000.00
CDs, DVDs, etc.

The Contractor shall maintain site office and floor and window
G 1 item ₦4,000,000.00 ₦4,000,000.00
cleaning and removal of rubbish

The Contractor shall pay the cost of utilities. (Water, Electricity,


H 1 item ₦10,000,000.00 ₦10,000,000.00
Telephone, Internet, etc.)

The Contractor shall provide high speed internet connection with


J 1 item ₦120,000.00 ₦5,760,000.00 ₦5,880,000.00
Wi-Fi for exclusive use of Employer , Consultant & Contractor

Safety, Health and Welfare of Work people


Provide for all costs and charges incurred by complying with all
safety, health and welfare regulations, pertaining to staff and work
K 1 item ₦15,000,000.00 ₦15,000,000.00
people employed on the site including those employed by all sub-
contractors

The Contractor shall supply PPE for sole use of the Employer,
Engineer and their staff visiting the site, safety helmets, safety
L 1 item ₦4,000,000.00 ₦5,000,000.00 ₦9,000,000.00
shoes, protective eye glass, ear muffs, reflective jackets, etc., as
requested by the Engineer

The Contractor shall be responsible for and shall allow for


providing medical facilities including emergency medical
M 1 item ₦1,000,000.00 ₦3,500,000.00 ₦4,500,000.00
facilities/first aid box for his staff and shall made these available to
Consultant's/client staff

Services and facilities

N Temporary Power including standby generator for general use by 1 item ₦10,000,000.00 ₦15,000,000.00 ₦500,000.00 ₦25,500,000.00
main contractor and subcontractors for the duration of the
contract. That has the capacity to power Crane

Provide all electric light and power required for the Works and
P remove all temporary installations on completion up to the 1 item ₦2,500,000.00 ₦3,500,000.00 ₦6,000,000.00
issuance of Completion Certificate.

Bill Nr 1;PRELIMINARIES Page 1/391


PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

Q Temporary Water for the works including for general use by main 1 item ₦2,500,000.00 ₦1,000,000.00 ₦3,500,000.00
contractor and sub - contractors for the duration of the contract.

R Storage of materials including lock-up spaces for specialist sub- 1 item ₦3,500,000.00 ₦500,000.00 ₦500,000.00 ₦4,500,000.00
contractors

S Rubbish disposal 1 item ₦10,000,000.00 ₦10,000,000.00

T Cleaning 1 item ₦12,000,000.00 ₦12,000,000.00

U Protection of work in all sections 1 item ₦5,000,000.00 ₦5,000,000.00

M Site Security including day and night security staff. 1 item ₦12,000,000.00 ₦12,000,000.00

To collection ₦41,120,000.00 ₦188,960,000.00 ₦5,000,000.00 ₦235,080,000.00


S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES

A43: CONTRACTOR'S GENERAL COST ITEMS: MECHANICAL PLANT

Mechanical plant

All plant required for effective executive and completion of the


A project .This shall include but not limited to mobile and fixed 1 item ₦85,000,000.00 ₦15,000,000.00 ₦3,500,000.00 ₦103,500,000.00
cranes , excavators, earthmoving equipment, concrete mixers
(mobile and fixed ), standing and mobile scaffolds and other
equipment and plant that the contractor shall allow necessary for
keeping ground excavation free of general water for the entire
period of substructure works as described in the description of
works : Please tower crane should not be installed in permanent
structure

Dimensions in descriptions

All dimensions in the descriptions are in millimeters unless


otherwise indicated (i.e. 100 girth means 100mm girth)

Project Supervision Expenses

Include the Provisional Sum of N2,000,000.00 for - Reimbursable, ₦2,000,000.00 ₦2,000,000.00


Printing, Communication, Correspondence delivery etc to be
expended as directed by the Project Manager.

A A55: DAYWORKS
Include the following provisional sums

For work ordered to be paid for on a daywork basis in accordance


with JCT'80

(the Provisional hours, sums and percentage additions are to be


considered as part of the overall contingency sum)

SECTION A: the following schedule of Dayworks shall be as defined


in "Definition of prime cost of daywork carried out under a building
contract" last before issued by the Federation of Building and Civil
Engineering Contractors. (percentages are to be extended in the
cash column)

LABOUR: percentages are to be extended in the cash column

add for incidental costs, overheads and profit as defined

MATERIALS AND GOODS: percentages are to be extended in the


cash column

add for incidental costs, overheads and profit as defined

PLANT: percentages are to be extended in the cash column (plant


shall be charged at the market rates current at the time the work is
executed)

SECTION B: daywork ordered to be carried out after the date of


commencement of the defects liability period (percentages are to
be extended in the cash column)

LABOUR: include the provisional sum for skilled labour (insert all-
in rate against provisional hours shown and extend to cash
column)

add for incidental costs, overheads and profit as defined


Bill Nr 1;PRELIMINARIES Page 1/392
PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

To collection ₦85,000,000.00 ₦17,000,000.00 ₦3,500,000.00 ₦105,500,000.00


S/NO DESCRIPTION QTY UNIT FIXED CHARGE TIME RELATED TERMINAL CHARGE TOTAL CHARGES
PRELIMINARIES

Preliminaries 1/1 ₦0.00 ₦0.00 ₦0.00 ₦0.00

Preliminaries 1/2 ₦0.00 ₦0.00 ₦0.00 ₦0.00

Preliminaries 1/3 ₦0.00 ₦0.00 ₦0.00 ₦0.00

Preliminaries 1/4 ₦9,500,000.00 ₦33,000,000.00 ₦5,000,000.00 ₦47,500,000.00

Preliminaries 1/5 ₦5,820,000.00 ₦1,500,000.00 ₦500,000.00 ₦7,820,000.00

Preliminaries 1/6 ₦8,510,000.00 ₦3,330,000.00 ₦1,500,000.00 ₦13,340,000.00

Preliminaries 1/7 ₦41,120,000.00 ₦188,960,000.00 ₦5,000,000.00 ₦235,080,000.00

Preliminaries 1/8 ₦85,000,000.00 ₦17,000,000.00 ₦3,500,000.00 ₦105,500,000.00

Bill Nr 1;PRELIMINARIES Page 1/393


PROPOSED COMMERCIAL DEVELOPMENT ON PLOT 2877 MAITAMA DISTRICT,CADATRAL ZONE:A06

Preliminaries ₦149,950,000.00 ₦243,790,000.00 ₦15,500,000.00 ₦409,240,000.00


Carried to summary

Bill Nr 1;PRELIMINARIES Page 1/394


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QUANTITY UNIT RATE AMOUNT

CONDITIONS OF CONTRACT

Conditions of Contract shall be the FIDIC 99 Condition of Contract for Construction


for building and engineering works designed by the Employer. For convenience,
only those provisions considered to have an obvious financial effect are set out
below and against each provision, the price shall be inserted for

A Performance Bond item

B Advance payment bond item

Insurance specific to the Contract

C Loss/damage to property item

D Workmen Compensation Policy item

E Third Party Liability item

F Contractors All Risk Policy item

Cost Related to other Clauses in the Condition of Contract

The Contractor shall include/ allow for complying in all respects with the Conditions
G of Contract Clauses 1 to 20 as per FIDIC 99 Condition of Contract for Construction item
for building and engineering works designed by the Employer.

Mobilization and demobilization

Mobilization of all supervisions, labours, plants, materials and equipments


H item
necessary for the proper execution of the Works.

De-mobilization of all supervisions, labours, plants, materials and equipments


J item
necessary for the proper execution of the Works

Access to site

Construct access to the site and obtain by prior arrangement with the Engineer.
K Alter, shift and adopt from time to time as necessary in order to access the site or item
building

Use of the site

L The site shall not be used for any purpose other than the execution of the Contract item

Limitations of working space

The Contractor will allocate the site as indicated on the Engineer's site plans and he
must allow for setting out of temporary office accommodation and for storage of
M materials etc. Either within the site areas or at such other location that the item
Contractor may provide himself and at his own cost as per the Municipality
Regulations.

The Contractor shall take all reasonable precautions to prevent work people
N including those employed by the Sub-contractors from trespassing on adjoining
owner's property.
item
Limitations of working hours

Working hours shall be as per the labour law of xxxx (Include the Country name or
P Governing Law). Contractor shall allow for any additional working hours in order to item
achieve construction programme in coordination with Engineer

Existing services

The Contractor shall ascertain for himself the location of existing services on, under
or over the site. He shall take precautions to protect all such services within the
Q item
confines of the site and immediately make good any damage at his own expenses
in coordination with service authorities

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 395


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

CONTRACTOR'S ADMINISTRATIVE ARRANGEMENTS

Site Administration.

The Contractor shall allow for providing all that is required for the proper
A administration of the contract at site level and in particular for complying in all item
respects with the relevant clauses in the Standard Conditions of Contract.

Supervision

Contractor shall allow for supervision and the site agent shall be replaced with
B item
appropriate person within reasonable time as approved by the Engineer

Security

The Contractor shall be responsible for and shall allow for providing 24 hours
C item
security through-out construction period

Safety, Health and Welfare of Workpeople

Provide for all costs and charges incurred by complying with all safety, health and
D welfare regulations, pertaining to staff and work people employed on the site item
including those employed by all sub-contractors

The Contractor shall be responsible for and shall allow for providing medical
E facilities including emergency medical facilities for his staff and shall made these item
available to Engineer's staff

Transport of Workpeople

Allow for the cost of all transport to and from site on the work people engaged on
F item
the site

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 396


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

CONSTRUCTION PLANTS

Small Plant and Tools

Provide for all necessary small plants and tools for the proper execution and
A item
completion of the Works

Scaffolding

Provide all necessary temporary scaffolding for the proper execution and
completion of the Works. Alter, relocate and adapt from time to time as necessary.
B The Contractor is to ascertain whether any scaffolding is required by any sub- item
contractor before striking. If the Contractor should strike any of his scaffolding and
is so required it shall be re-erected at his own expense.

Cranes and Lifting Plant

Provide all necessary mobile/ tower cranes and lifting plant for the proper execution
C and completion of the contract. (Note: The tower crane should not be installed in
permanent structure)

Site Transport

D Contractor shall allow for transportation of plant and equipment. item

Plants Required for Specific Trades

Provide all necessary plants required for specific trades for the proper execution
E item
and completion of the contract.

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 397


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

Sign Boards

The Contractor shall allow for the provision, erection and maintenance of necessary
site notice board as required by the Engineer to display image of the project, project
A nr
name, the Employer's name and names of all Consultants associated with the
Project

The sign boards shall be complete weather durable with all necessary foundations,
supports, framing, painting and sign writing in Arabic (Optional for any languages)
and English denoting the title of the project and name of the Employer, Consultants
B and contractors with their respective addresses and building permit details. The item
Contractor shall provide all details of the sign board to the Engineer for his approval
before any work is put in hand and to enable erection to commence in the early
stages of the contract.

The Contractor shall provide sufficient lighting to sign boards which includes power
C item
supply and lighting fixture.

The Contractor shall clean, maintain and at the completion of the Contract remove
D item
the sign board, supports and foundations.

E Any authority payments item

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 398


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

ENGINEER'S FACILITIES

Site Offices, Stores and other Facilities

Office construction shall be light airy manner with air-conditioned for Employer,
Engineer and Clerk of works/ General office (but not limited to three office) shall be
constructed comprising of conference hall, toilets, pantry facilities & sample room,
etc. all as per specification

The Contractor shall construct sub-structure to place porta-cabins as per Engineer's


A item
instruction

The Contractor shall supply and place Port-a- cabins, comprising of carpet floors
B item
and all other finishes as stated in the specification

The Contractor shall Supply and install all electromechanical works including fire
C alarm and fire fighting system in accordance with ROP standard and approval of item
works as per engineer's

The Contractor shall obtain power, water, drainage and telephone to meet office
D item
requirement (separate for Employer's and Engineer's office)

The Contractor shall supply minimum of following new furniture and other items for
each office (Contractor shall provide warranty card or slip for all Electronic items)

E Desk complete with twin pedestal lockable drawers nr

F Tables nr

G Lockable filing (two drawer in each office) cabinets nr

H Storage cupboard/ book case nr

Drawing hangers complete with drawing suspension clamps or one chest of drawer
J nr
specifically designed for drawing storage

K Drafting table with adjustable stool nr

L Swivel based/ sprung back desk chair nr

M Conference table nr

N Conference chairs nr

P Visit Chairs nr

Q Fixed shelving required for storage/ display of samples and other materials nr

R Electric kettle nr

S 350 liter refrigerator nr

T Microwave oven nr

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 399


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

ENGINEER'S FACILITIES

Site Offices, Stores and other Facilities

The Contractor shall supply, install and maintain following equipment with
necessary cabling, wiring and power connection.

Telephone instruments, one in Employer's office, one in Engineer's office with


A nr
extension to general office

B Fax machine in general office nr

Colour printer photocopier and scanner on high speed (A3/A4 format, reduction/
C nr
enlargement facility, 2 sides coping, cassette feeds and sorting facility), scanner

Laptop with network facility and internet, minimum configuration; Intel Core i7,
2GHz processor, 1 TB SSD hard disk, 16 GB RAM, DVD super multi DL Rewriter,
15.4" LED monitor, in built card reader, in built web cam & mic, Wi-Fi, Bluetooth,
D nr
complete with wireless mouse, flash memory stick (8GB), printer, Anti virus, Micro
soft Office - all programs with single user license agreement, with latest softwares
(return to Employer after completion of the project)

E The Contractor shall replace any defected item during the course of Construction. item

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 400


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities

Maintenance of project office and office equipment includes cleaning on daily basis
A and to provide consumable items for the use of Employer and consultant such as month
toilet soaps, towels, pantry items like clean drinking water, milk, coffee, sugar, etc.,

The Contractor shall supply of stationaries and other sundry items (copy papers, fax
papers, pens, pencils, leads, erasers, pins, staplers, pin boards, binder, paper
B month
cutter, heavy duty punching machine, mirror, waste bins, desk paper trays, clocks,
etc.).

C The Contractor shall supply of toners, special colour printing paper, CDs, DVDs, etc. month

The Contractor shall maintain site office and floor and window cleaning and removal
D month
of rubbish

The Contractor shall pay the cost of utilities. (Water, Electricity, Telephone, Internet,
E month
etc.)

The Contractor shall provide high speed ADSL internet connection with Wi-Fi for
F month
exclusive use of Employer & Engineer

The Contractor shall supply PPE for sole use of the Employer, Engineer and their
G staff visiting the site, safety helmets, safety shoes, protective eye glass, ear muffs, item
reflective jackets, etc., as requested by the Engineer

The Contractor shall maintain and provide necessary security to the Engineer's
H item
facilities after issuing of completion certificate until the Employer take over security.

J Remove Port-a-cabin, clean the area as instructed by Engineer. item

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 401


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

The Contractor shall provide, erect, maintain and remove on completion all
necessary site offices, stores, mess rooms, sanitary accommodation and other
A facilities as may be required by the contractor for his own and his sub-contractors item
use, together with all associated water, drainage, electrical lighting and power, air
conditioning, telephone/ equipment and attendance.

The position of all site office stores etc. shall be to the approval of the Engineer,
and the contractor must allow for any 'off site' facilities he may require additional to
B item
the area allocated to him. Contractor shall submit the Facilities Plan for Engineer’s
approval.

Temporary Roads

Provide, maintain and alter as necessary temporary roads, paths, hard standings,
C pavement crossings and the like to and within the site. Remove and reinstate all item
ground and work disturbed when required.

Temporary Works

Supply, install, remove and handover all temporary fencing to Employer at the
D item
completion of the Works

Water for the Works

Provide all water required for the works and provide and remove on completion all
requisite temporary pipe work, pumps, storage tanks etc. The Contractor must
E item
include for obtaining water from an independent source up to the issuance of
Taking Over Certificate.

Lighting and Power for the Works

Provide all electric light and power required for the Works and remove all temporary
F item
installations on completion up to the issuance of Completion Certificate.

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 402


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

Foul Discharge

Provide necessary sewage connecting to Engineer's site office, Contractor's office


A item
and discharge as requested

Testing of Materials

The Contractor shall carry out tests by an independent third party laboratory
B approved by the Engineer as per specification and shall report all test results item
promptly to the Engineer

The Contractor shall be responsible for sending Engineer’s representatives to the


source of supply or manufacturer's works to test the materials or supervise their
C item
production whenever considered necessary and shall bear all necessary costs
related to the same.

Copies of Orders

The Contractor shall provide the Engineer with a copy of all orders for the supply of
D such materials or goods required in connection with the Works as the Engineer may item
specify.

Testing of the Works

Allow for all tests required by the specification to be carried out including all
E necessary equipment, materials and reports as per scope of Works and item
specification.

Provide water, fuel and electricity necessary for the plumbing and engineering
F item
installations.

As-built Drawings

As-built' drawings shall be six sets hard copies and one set of electronic copy in CD
in latest AutoCAD format as specified in the specification. Each set of hard copy of
G item
drawings shall be properly bound and presented in a suitable manner acceptable to
the Engineer

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 403


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

CONTRACTOR'S FACILITIES

Site Offices, Stores and other Facilities.

Operation and Maintenance Manuals

A Allow for O&M manuals for MEP and other works as per specifications item

The Contractor shall not be entitled for any extra payment or extension of time for
B the correction, preparation and supplying of the above mentioned drawings and item
information.

Training on Completion

Allow for trainings of Employer's staff related to all system on completion of the
C item
project

Protecting the Works

Provide for carefully covering up and protecting all of the Works by whatever means
D item
necessary as required during construction and on completion until handover

Disposal of debris

Keep the site free from debris arresting from the works during the construction
E period and leave the site free from debris on completion to the satisfaction of the item
Engineer.

Maintenance of Public and Private Roads

Allow for maintenance of public and private roads used by the Contractor around
F item
the site

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 404


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

Control of Noise, Dust and Pollution

The Contractor shall take all necessary precautions in reducing noise caused by
A plant by means of mufflers, silencers, screens and the like in line with HSE item
requirements.

Watering of roads, fill granular materials as required at exit points, clean dirt carried
B item
beyond exit point on daily basis.

Provide for removing all rubbish from the site both as it accumulates from time to
C item
time and at completion.

Provide for cleaning the buildings inside and out, removing stains and touching up
D paint work and polish work and leaving the whole of the works clean, ready for item
occupation and to the satisfaction of the Engineer on completion.

The Contractor shall provide dedicated workmen to observe and clear designated
E item
areas of Foreign Object Debris as it occurs.

The Contractor shall be responsible for cleaning the site and work area completely
of all his temporary installation on completion of the Works shall be required to
grade or rake the area he has occupied to remove all traces of his occupation and
F item
leave the site as close to its original condition as possible. The Contractor shall
provide constantly available labour transport and materials to maintain the
cleanliness and tidiness of the Site.

All Statutory Obligations

The Contractor shall make every effort to comply with local authorities rulles and
G item
requirements

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 405


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

Guarantee and Warrantee

The Contractor shall provide guarantee/warrantee for the items as required in the
specification. Guarantee/warrantee are to be taken in the name of the Employer
A item
and forward the originals to the Engineer prior to the issue of the certified of
completion. All Guarantee/Warrantee should be started from the date of completion.

Submittals

Prepare and submit to the Engineer all submittals, materials, working drawings,
B item
record drawings, procurement schedule etc. as required by the Specification.

Samples

The Contractor shall allow for submitting samples of all materials and goods as
required to the Engineer/specification for obtaining his approval, and for paying all
C item
fees and charges etc., in connection therewith. (after approval sample may be used
in construction of the project)

Technical Literature

The Contractor shall obtain copies of the latest editions of standard manuals
D specified in the specification to be kept on site for the use of the Engineer. Upon item
completion of the project they are to be handed over to the Employer.

Statutory Obligations

Allow for all costs for permission, licenses, inspection compliance to regulation and
E item
no objection certificates.

Shop Drawings

F Prepare and submit to the Engineer all shop drawings required by the specification. item

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 406


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

Employer's Tradesmen, Direct Contractors and other Authorities

The Contractor shall note that the Employer may appoint other contractors to
carryout certain items of specialist, ancillary or other works. The contractor shall
afford any such other contractors, Employers own workmen or any other duly
A item
constituted authorities all reasonable opportunity to resource and execute their
works. The Contractor shall include for liaising with all such other contractors, direct
workmen or other authorities and for co-coordinating his works with

Special Requirements for Programmes of Progress Charts

A preliminary outline programme for carrying out the works shall be prepared by the
Contractor and submitted with the tender. Within 14 days upon receipt of Engineer's
B order to commence the work, the Contractor shall prepare a detailed programme in item
the manner as detailed in the specification for carrying out the works and shall
submit copies of the programme to the Engineer for his approval

This shall be accompanied by labour force monthly loading for each trade, including
C item
sub-contractors, supervisory staff, cash flow and details of materials procurement.

The programme shall be updated and expanded at such times as stated in the
specification and shall be submitted to the Engineer in monthly intervals. Two week
D look ahead programmes shall be Look ahead program shall contains with details of item
Plan and method he propose to employ. No works based on such proposals shall
proceed without the approval of Engineer

In addition to the above, the Contractor shall submit in a Monthly Progress Report
E item
showing all the details in accordance as specified in the

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 407


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

Photographs

Each month during the progress of the works, the Contractor shall arrange at his
own expense the taking of progress photographs from viewpoints selected by the
Engineer sufficient to record progress at the appropriate stage of the work. Six
copies comprising 36 No. 100x75 mm and 6 No. 300 x 250 mm colour photographs
presented in a proper manner approved by the Engineer, together with negatives
D and electronic copy shall be handed to the Engineer for his retention. The item
photographs shall be properly documented with dates, details of the viewpoint and
location etc. All photographs shall be subject to the Employer's security precautions
and shall not be used for promotional/commercial purposes without written
permission. The Contractor shall provide suitable albums for the correct storage of
the above photographs as specified in the Specification.

CARRIED TO COLLECTION PAGE USD

BILL NO-01/ 408


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES
ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

Site Meetings

The Contractor will attend with adequate responsible representation to Site Meeting
A item
and all other meetings to which the Engineer has given instructions to attend.

The Contractor will further undertake to inform and present to attend meeting(s) any
B representative(s) for those sub-contractors, suppliers, etc., under his direct control, item
if so requested by the Engineer.

The Contractor will ensure that all meetings with sub-contractors are held just prior
C item
to the site meetings to ensure accurate reporting on progress, information, etc.

Climatic Condition

Daily maximum and minimum air temperature (including overnight) shall be included
D item
in the Daily Report

Number of hours per day in which works are prevented by inclement weather (flood,
E item
etc.).

Site Survey and Grid Levels

Before commencing excavation or site leveling operations, the Contractor shall


conduct a site survey, witnessed by the Engineer, related to a benchmark. Levels
F shall be taken at 5m intervals in both directions across the entire site which must be item
agreed with Engineer prior to commencing excavations or filling operations, all as
specified in the specification

Other Costs

Allow for all costs, expenses etc. details of which must be set out below & extended
separately by the contractor incurred in carrying out the requirements of the
G Contract and not otherwise included in this bill. All costs & expenses not entered item
hereinafter will be deemed to be included in the prices inserted elsewhere in this
Bill.

CARRIED TO COLLECTION PAGE USD


BILL NO. 1
PROPOSED PROJECT NAME
PRELIMINARIES

BILL NO-01/ 409


ITEM DESCRIPTION QTY UNIT RATE AMOUNT (USD)

COLLECTION

BILL NO. 1 PRELIMINARIES

Page No. 1/1

Page No. 1/2

Page No. 1/3

Page No. 1/4

Page No. 1/5

Page No. 1/6

Page No. 1/7

Page No. 1/8

Page No. 1/9

Page No. 1/10

Page No. 1/11

Page No. 1/12

Page No. 1/13

Page No. 1/14

Page No. 1/15

Bill No.1 Preliminaries Carried to General Summary Page USD

BILL NO-01/ 410


PROPOSED ESTATE DEVELOPMENT FOR NSITF MULTI-PURPOSE COOPERATIVE LIMITED
PLOT GWARINPA, ABUJA FCT
A36 EMPLOYER'S REQUIREMENTS: FACILITIES/TEMPORARY WORK/
SERVICES GENERALLY
- Allow for periodic
110 LOCATIONS: Inform the Architect of the intended siting of all spoil heaps,
temporary works and services.

120
MAINTAIN, alter, adapt and move temporary works and services as necessary. Clear
away when no longer required and make good
vehicle) and fueling
for the duration of
130 RESIDENCY SUPERVISION: Provide for Residency as follows: this Contract
Architect 12-months
Architect x 12-months
Quantity Surveyor x 12-months
M&E + Structural Engineer x 12-months

SITE ACCOMMODATION [ROOM FOR MEETINGS]

210
ROOM FOR MEETINGS: Provide suitable temporary accommodation for site
meetings, adequately air conditioned and lit, with table and chairs for [24nr.] twenty
four people. The room may be part of the Contractor's own site offices.

220
CONSULTANTS' SITE OFFICE: Provide and obtain approval of suitable lockable
temporary accommodation and facilities as follows:

- Floor area: 40 square meters item N

- Furniture and equipment:


- 2000x1000mm Work Table complete with chair [4nr.]
- Visitors' Chairs (8nr)
- Drawings Rack [Architect + Engineer ( 2nr) item N
- Refrigerator stocked with water, softdrinks, etc (1nr)
- Hot Water Kettle, Thermos Flask, Tea Cups, etc. 2,000,000.00

Intel Pentium iv 3.0Ghz, 120GB HDD, DVDRW, 1GBEDO RAM, 17” TFT VDU,
Internet ready (3nr.) + HP Laserjet 3 in 1 (printer, scanner and colour copier) (3nr)

Sony Digital Camera DSC – F707 Cybershoot (1nr.)


Air conditioning to adequately cool the spaces.
- Lighting: 400 lux from fluorescent luminaries.
- Power supply: 4Nr 13 amp points
- Attendance: Cleaning, Tea Service, and Messenger
- Refreshments at Site Meetings
- Monthly Site Meetings - Lunch
- Other meetings - Refreshment

TRANSPORTATION FOR CLIENT'S AGENTS; Allow a sum for the


230 reimbursement of Client's agent on transportation and other incidental espences
incurred by the same throughout the duration of the contract.
9,000,000.00

Carried to Collection 11,000,000.00

Preliminaries Page 411


PROJECT: MAITAMA COMMERCIAL PLAZA, ABUJA
BILL OF QUANTITY: PLUMBING INSTALLATION
ITEM UNIT QTY RATE DEL RATE
DESCRIPTION TO SITE FIXED

FIRE FIGHTING PIPES INSTALLATION EQUIPMENTS


A FOR DRY & WET LINE

The pricing is based on the supply and installation of


and PP-R Red Fire Pipe with fusion fittings. Pipes
shall be able to withstand pressure testing to 15 bar
100mm-32mm PP-R Fire Pipe
PIPE
1 100mm dia m 190 20,800 4,160 24,960

2 90mm dia m 360 14,500 2,900 17,400

3 75mm dia m 480 10,092 2,018 12,110

4 32mm dia m 130 2,800 560 3,360

Tee
5 90 x 90 x 90mm Nos 2 15,892 3,178 19,070

6 75 x 75 x 75mm Nos 3 7,540 1,508 9,048

Reducing Tee
7 100 x 90 x 100mm Nos 4 22,040 4,408 26,448

8 100 x 75 x 100mm Nos 8 22,040 4,408 26,448

9 90 x 75 x 90mm Nos 6 15,892 3,178 19,070

10 75 x 32 x 75mm Nos 130 9,860 1,972 11,832

Bend
11 100mm Nos 10 20,300 4,060 24,360

12 90mm Nos 16 15,892 3,178 19,070

13 75mm Nos 22 6,960 1,392 8,352

14 32mm Nos 240 580 116 696

SUB-TOTAL C/F

MECHANICAL
ITEM UNIT QTY RATE DEL RATE
DESCRIPTION TO SITE FIXED
ITEM DESCRIPTION UNIT RATE DEL RATE
TO SITE FIXED
SUB-TOTAL (C/B)

Socket
15 100mm Nos 50 10,440 2,088 12,528

16 90mm Nos 80 6,320 1,264 7,584

17 75mm Nos 120 4,060 812 4,872

18 32mm Nos 100 564 113 677

Reducing Socket
19 100mm x 90mm Nos 2 10,440 2,088 12,528

20 90mm x 75mm Nos 2 6,320 1,264 7,584

21 75mm x 50mm Nos 75 4,060 812 4,872

22 50mm x 32mm Nos 10 1,161 232 1,393

Nipple
23 100mm Nos 4 48,000 9,600 57,600

24 75mm Nos 2 19,720 3,944 23,664

25 32mm Nos 30 4,872 974 5,846

FLANGES(PAIRS)
26 100mm Nos 6 24,393 4,879 29,272

Air Release Valve


27 50mm Nos 10 46,700 9,340 56,040

Gate Valve
28 100mm Nos 3 208,626 41,725 250,351

29 75mm Nos 10 36,820 7,364 44,184

30 30mm Nos 10 8,960 1,792 10,752

Union Connector
31 100mm Nos 3 68,260 13,652 81,912

32 75mm Nos 2 26,820 5,364 32,184

33 30mm Nos 120 6,960 1,392 8,352

Fire hosereel cabinet


MECHANICAL
ITEM UNIT QTY RATE DEL RATE
DESCRIPTION TO SITE FIXED

34 Double compartment fire hosereel cabinet complete 30m 289,300


long flexible hose, extinguisher and spray nozzle Nos 28 263,000 26,300
set,mounted on a common base frame,comprising of 1
35 Diesel/1 Electric/jockey self priming pumps with pressure
vessel ,switches and gauges and all other accessories
Nos 1 200,000
for a functional installation to Mechanical Engineer
consultant specifications (137m3/hr, 112m head)
complete with butterfly valves and other installation
36 Clips and hangers Lot

37
All installation Acessories e.g bushing and cap plugs etc. Lot

TOTAL FIRE FIGHTING INSTALLATIONS

MECHANICAL
TOTAL COST

4,742,400.0

6,264,000.0

5,812,992.0

436,800.0

38,140.8

27,144.0

105,792.0

211,584.0

114,422.4

1,538,160.0

243,600.0

305,126.4

183,744.0

167,040.0

20,190,945.6

MECHANICAL
TOTAL COST

TOTAL COST

20,190,945.6

626,400.0

606,720.0

584,640.0

67,680.0

25,056.0

15,168.0

365,400.0

13,932.0

230,400.0

47,328.0

175,392.0

175,629.6

560,400.0

751,053.6

441,840.0

107,520.0

245,736.0

64,368.0

1,002,240.0

MECHANICAL
TOTAL COST

8,100,400.0

200,000.0

1,500,000

3,000,000

39,098,248.8

MECHANICAL
Prepared by Nazedees Borner Nig Ltd

PROJECT: MAITAMA COMMERCIAL PLAZA, ABUJA


BILL OF QUANTITY: PLUMBING INSTALLATION
ITEM DESCRIPTION UNIT QTY RATE RATE
DEL TO FIXED
SITE
A WATER SUPPLY PIPEWORK INSTALLATION
90mm-40mm Aquatherm PP-R Pipe

PIPES
1 90mm m 550 7,830 1,566 9,396

2 50mm m 260 4,050 810 4,860

3 40mm m 30 2,322 464 2,786

Fittings
Elbow
4 90mm Dia Nr 36 5,684 1,137 6,821

5 50mm Dia Nr 84 1,189 238 1,427

6 40mm Dia Nr 20 650 130 780

Equal Tee
7 90 x 90 x 90mm Nr 2 8,323 1,665 9,988

8 50 x 50 x 50mm Nr 5 1,189 238 1,427

Reducing Tee
9 90 x 50 x 90mm Nr 60 8,323 1,665 9,988

10 90 x 40 x 90mm Nr 25 8,323 1,665 9,988

Nipple
11 90mm Nr 4 28,239 5,648 33,887

12 50mm Nr 8 8,816 1,763 10,579

Sockets
13 90mm Nr 138 5,684 1,137 6,821

14 50mm Nr 65 1,189 238 1,427

Valves
15 90mm Nr 4 94,029 18,806 112,835

16 50mm Nr 60 11,915 2,383 14,298

17 40mm Nr 22 13,270 2,654 15,924

Union Connector
18 90mm Nr 4 38,280 7,656 45,936

19 50mm Nr 60 8,915 1,783 10,698

418
Prepared by Nazedees Borner Nig Ltd

MISCELLANEOUS ACCESSORIES

All installation Acessories e.g pipe clip-single


20 and double, bushing and cap plugs etc. Lot

TOTAL TO COLLECTION

419
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT RATE RATE


DEL TO FIXED
SITE
B SOIL AND WASTE PIPEWORK INSTALLATION
PVC and Polythene pipes and fittings to BS-EN
1329 and 1401
OSTENDORF
PIPES
1 200mm m 102 8,500 1700 10,200

2 150mm m 420 5,803 1,161 6,964

3 100mm m 320 2,800 560 3,360

FITTINGS
Bends (45 Degree)
4 200mm Nr 10 7,800 1560 9,360

5 150mm Nr 20 3,596 719.2 4,315

6 100mm Nr 310 1,385 277 1,662

Socket
7 200mm Nr 25 6,730 1346 8,076

8 150mm Nr 100 2,295 459 2,754

9 100mm Nr 80 1,385 277 1,662

Installation accessories e.g. Tangit Gum,


10 Brackets Clips etc. LOT
TOTAL TO COLLECTION

420
Prepared by Nazedees Borner Nig Ltd

COST COLLECTION

A Water Supply Pipework Installation =N=

B Soil and Wast Water Pipework


Installation =N=

SUB-TOTAL =N=

Total to Main Summary =N=

421
Prepared by Nazedees Borner Nig Ltd

AZA, ABUJA
ATION
TOTAL COST

5,167,800

1,263,600

83,592

245,549

119,851

15,600

19,975

7,134

599,256

249,690

135,547

84,634

941,270

92,742

451,339

857,880

350,328

183,744

641,880

422
Prepared by Nazedees Borner Nig Ltd

500,000

12,011,412

423
Prepared by Nazedees Borner Nig Ltd

TOTAL COST

1,040,400

2,924,712

1,075,200

93,600

86,304

515,220

201,900

275,400

132,960

300,000
6,645,696

424
Prepared by Nazedees Borner Nig Ltd

12,011,412

6,645,696

18,657,108

18,657,108

425
Prepared by Nazedees Borner Nig Ltd

PROJECT: MAITAMA COMMERCIAL PLAZA, ABUJA


BILL OF QUANTITY: PLUMBING INSTALLATION
ITEM DESCRIPTION UNIT QTY RATE DEL RATE
TO SITE FIXED
A SANITARY WARES
(INSTALLATION ONLY)

1 WATER CLOSET
Water closet suite complete, with pan, cistern,
flush mechanism, seat cover and other
installation accessories. Nr 484 FIX ONLY 6,000

2 WASH HAND BASIN


Wash hand basin complete with mixer tap,
pop-up waste and other accessories. Nr 484 FIX ONLY 5,500

3 SHOWER
Shower complete with shower mixer control,
spout, and other accessories. Nr 117 FIX ONLY 10,000

4 URINAL
Urinal complete with mixer tap,
waste and other accessories. Nr 74 FIX ONLY 5,500

5 Hand Dryer
Hand dryer complete with other installation
accessories Nr 72 FIX ONLY 2,500

6 Soap Dispenser
Soap Dispenser complete with other installation
accessories Nr 72 FIX ONLY 2,000

7 BATHROOM ACCESSORIES
i Soap Dish Nr 117 FIX ONLY 2,000
ii Towel Rail Nr 117 FIX ONLY 2,000
iii Toilet Roll Holder Nr 484 FIX ONLY 2,000
iv Toilet Brush Holder Nr 484 FIX ONLY 2,000
v Wall Mirror Nr 484 FIX ONLY 4,500
v Soap Dispenser Nr 72 FIX ONLY 4,501

8 KITCHEN SINK
i) Stainless Steel kitchen sink complete with
single bowl, single drainer,
swivel bridge mixer tap, chain waste plug and
other installation accessories. Nr 50 FIX ONLY 6,000

9 ELECTRIC WATER HEATER


Electric Water Heater complete with electrical cable
mounting bracket, and other installation accessories.
1000 Litres Nr 117 FIX ONLY 5,000

TOTAL TO COLLECTION

426
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT QTY RATE RATE


DEL TO FIXED
SITE
B WATER SUPPLY PIPEWORK INSTALLATION
50mm-25mm Aquatherm PP-R Pipe and
20mm-15mmViega Multilayer Composite
Pipe PE-Xc/AL/PE-Xc

PIPES
1 50mm m 2,217 4,050 810 4,860

2 40mm m 974 2,322 464 2,786

4 25mm m 280 1,196 239 1,435

5 20mm m 4,313 1,937 387 2,324

6 15mm m 1,774 1,605 321 1,926

Fittings
Elbow
7 50mm Dia Nr 200 1,189 238 1,427

8 40mm Dia Nr 80 650 130 780

9 25mm Dia Nr 968 420 84 504

10 20mm Dia Nr 1,126 2,702 540 3,242

11 15mm Dia Nr 924 1,939 388 2,327

Wallplate
12 20mm Nr 622 4,002 800 4,802

13 15mm Nr 1,576 3,599 720 4,319

Equal Tee
14 50 x 50 x 50mm Nr 20 1,189 238 1,427

15 40 x 40 x 40mm Nr 10 750 150 900

16 25 x 25 x 25mm Nr 500 432 86 518

17 20 x 20 x 20mm Nr 770 3,599 720 4,319

18 15 x 15 x 15mm Nr 452 2,738 548 3,286

Reducing Tee
19 50 x 25 x 50mm Nr 490 1,189 238 1,427

20 40 x 25 x 40mm Nr 200 750 150 900

21 20 x 20 x 15mm Nr 290 3,020 604 3,624

427
Prepared by Nazedees Borner Nig Ltd

22 20 x 15 x 15mm Nr 462 3,020 604 3,624

23 20 x 15 x 20mm Nr 580 3,020 604 3,624

SUB-TOTAL C/F

428
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT RATE DEL RATE


TO SITE FIXED
SUB-TOTAL (C/B)

Nipple
24 25mm X 3/4" male Nr 117 1,800 360 2,160

25 25mm X 1/2" male Nr 457 1,800 360 2,160

26 20mm X 3/4" male Nr 117 4,232 846 5,078

27 20mm x 1/2" male Nr 457 3,731 746 4,477

Sockets
28 50mm Nr 550 1,189 238 1,427

29 40mm Nr 250 650 130 780

30 25mm Nr 40 420 84 504

31 20mm Nr 968 2,308 462 2,770

32 15mm Nr 484 1,841 368.2 2,209

Valves
33 50mm Nr 55 11,915 2,383 14,298

34 40mm Nr 22 13,270 2,654 15,924

35 25mm Gate Valve Nr 584 9,000 1800 10,800

36 15mm Angle Valve with chrome cover plate Nr 1,300 3,500 700 4,200

37 15mm Copper Flexible connector Nr 1,300 2,000 400 2,400

MISCELLANEOUS ACCESSORIES
38 Pressure Testing of Supply Pipes Lot

All installation Acessories e.g pipe clip-single


39 and double, bushing and cap plugs etc. Lot

TOTAL TO COLLECTION

429
Prepared by Nazedees Borner Nig Ltd

ITEM DESCRIPTION UNIT RATE RATE


DEL TO FIXED
SITE
C SOIL AND WASTE PIPEWORK INSTALLATION
PVC and Polythene pipes and fittings to BS-EN
1329 and 1401
OSTENDORF
PIPES
1 100mm m 7,354 2,800 560 3,360

2 50mm m 1,990 981 196.2 1,177

FITTINGS
Bends (90 Degree)
3 100mm Nr 686 1,385 277 1,662

4 50mm Nr 796 695 139 834

Bends (45 Degree)


5 100mm Nr 2,130 1,385 277 1,662

6 50mm Nr 4,833 695 139 834

TEES
7 100 x 100 x 100mm Nr 532 1,680 336 2,016

8 100 x 50 x 100mm Nr 600 1,681 336.2 2,017

9 50 x 50 x 50mm Nr 1,105 780 156 936

TRAPS
10 100mm Vent Cowl Nr 70 6,000 1200 7,200

11 100mm Pan Connector Nr 484 2,000 400 2,400

12 50mm Stainless Steel Floor Drain Nr 651 22,000 2200 24,200

Socket
13 100mm Nr 1,500 1,385 277 1,662

14 50mm Nr 400 695 139 834

Installation accessories e.g. Tangit Gum,


15 Brackets Clips etc. LOT
TOTAL TO COLLECTION

430
Prepared by Nazedees Borner Nig Ltd

COST COLLECTION

A Sanitary Wares =N=

B Water Supply Pipework Installation =N=

C Soil and Wast Water Pipework


Installation =N=

SUB-TOTAL =N=

Total to Main Summary =N=

431
Prepared by Nazedees Borner Nig Ltd

AZA, ABUJA
LATION
TOTAL COST

2,904,000

2,662,000

1,170,000

407,000

180,000

144,000

234,000
234,000
968,000
968,000
2,178,000
324,072

300,000

585,000

13,258,072

432
Prepared by Nazedees Borner Nig Ltd

TOTAL COST

10,774,620

2,713,954

401,856

10,025,137

3,416,724

285,360

62,400

487,872

3,650,942

2,149,963

2,987,093

6,806,429

28,536

9,000

259,200

3,325,476

1,485,091

699,132

180,000

1,050,960

433
Prepared by Nazedees Borner Nig Ltd

1,674,288

2,101,920

54,575,953

434
Prepared by Nazedees Borner Nig Ltd

TOTAL COST

54,575,953

252,720

987,120

594,173

2,046,080

784,740

195,000

20,160

2,680,973

1,069,253

786,390

350,328

6,307,200

5,460,000

3,120,000

3,500,000

3,500,000

86,230,090

435
Prepared by Nazedees Borner Nig Ltd

TOTAL COST

24,709,440

2,342,628

1,140,132

663,864

3,540,060

4,030,722

1,072,512

1,210,320

1,034,280

504,000

1,161,600

15,754,200

2,493,000

333,600

2,000,000
61,990,358

436
Prepared by Nazedees Borner Nig Ltd

13,258,072

86,230,090

61,990,358

161,478,520

161,478,520

437
MAITAM COMPLEX SANITARY WARES
SANITARY WARES BILL OF QUATITIES
ITE DESCRIPTION PRODUCT TYPE PRODUCT QTY BASIC RATE TOTAL AMOUNT
M CODE
1 WC
i Wall mounted dual fluch GURALVIT 485 132,800.00 64,408,000.00
WC Bowl made of VIEGA
Vitreous China Dual
Flush Water
Consumption 6.0-3.0 Lpf
Includes plastic slow-
close seat, structural
steel tubing in-wall
carrier unit rated

2 WHB
i Wash Basin, Wall Hung, GURALVIT 485 109,500.00 53,107,500.00
complete with mixer tap,
pop up waste, 32mm
bottle trap. Armitage
shank or approved
equal.

vi Shower with concealed HANSGROHE 120 216,400.00 25,968,000.00


mixer taps and
telephone shower, traps
complete with non-slip
base. Armitage shank or
approved equal.

vi Wall hung urinal,with GURALVIT 75 191,200.00 14,340,000.00


concealed cisten and VIEGA
sensor auto-flush
system.

SUBTOTAL C/F 157,823,500.00


SUBTOTAL C/F 157,823,500.00

vii Stainless steel kitchen 50 75,000.00 3,750,000.00


sinks, single bowl double
drain complete with
mounting brackets.

viii Hand Driers. Slieber HANSGROHE 72 35,600.00 2,563,200.00


Eltron or approved
equal.

ix Soap Dispensers, GURALVIT 1800180 72 31,000.00 2,232,000.00


Brightwell or equal.

6mm plate glass mirror TAKE 485 13,400.00 6,499,000.00


450 x 600mm fixed to
wall.

x Set of Bathroom GURALVIT 71405000 485 51,152.00 24,808,720.00


accessories consisting of,
but not limited to the
following items: toilet
roll holder, towel rail,
soap dish etc.

15 liters Thermostatic ARISTON 120 75,200.00 9,024,000.00


Electric water Heater.
ARISTON or approved
equal. Complete with
installation fittings.

xiii Towel Rail GURALVIT 40513000 120 14,380.00 1,725,600.00

SUBTOTAL 208,426,020.00

7.5% VAT 15,631,951.50

TOTAL 224,057,971.50
S/NO DESCRIPTION QTY UNIT RATE AMOUNT

AIR-CONDITIONING SYSTEM INSTALLATION

1 Air-conditioning and Ventilaton Units Installation

Split Units

Wall mounted split air-conditioing unit complete with installation


A bracket, electrical cable and other installation accessories Capacity: 165 Nr 12,000.00 1,980,000.00
9000 BTU

Wall mounted split air-conditioing unit complete with installation


B bracket, electrical cable and other installation accessories Capacity: 76 Nr 12,000.00 912,000.00
12000 BTU

Wall mounted split air-conditioing unit complete with installation


C bracket, electrical cable and other installation accessories Capacity: 214 Nr 12,000.00 2,568,000.00
18000 BTU

D Floor Standing Air-conditioing


Floor Standing Air-conditioing unit complete with electrical cable and 7 Nr 25,000.00 175,000.00
other installation accessories Capacity: 24000 BTU

2 Refrigent Pipework Installation

Pipes
Light gauge annealed copper tubes in coils and rigid pipes to BS 2871.
Table Y for connection by means of autogenous welding.

E 15.90mm Internal Diameter 70 m 3,513.60 245,952.00

F 12.70mm Internal Diameter 3391 m 2,808.00 9,521,928.00

G 9.52mm Internal Diameter 2150 m 1,968.00 4,231,200.00

H 6.35mm Internal Diameter 5541 m 1,488.00 8,245,008.00

Accessories
J 19mm Internal Diameter Insulation Tube (15mmThick) ARMAFLEX 5541 m 572.40 3,171,668.40

K 16mm Internal Diameter Insulation Tube (19mmThick) 5541 m 486.00 2,692,926.00

L 2.5mmsq. 3-Core PVC/PVC Cable RABIEMETAL/Nigerchin 5541 m 2,238.00 12,400,758.00

M 65mm Diammeter non-kink PVC Pipe Sleeve 5076 m 1,242.00 6,304,392.00

Condensate Pipework
N 50mm 1,460 m 1,177.20 1,718,712.00

P 50 x 50 x 50mmTee 484 Nr 936.00 453,024.00

Q 50mm Bend 210 Nr 834.00 175,140.00

R 25mm Dia pipe (upvc) 5200 m 324.00 1,684,800.00

S 25mmBend(900) 1994 Nr 270.00 538,380.00

T 25 x 25x 25mm Equal Tee 400 Nr 302.40 120,960.00

CCP748M.BOQ Page 440


U 25mm Internal Diameter Insulation Tube for condensate with 19mm 5300 m 1,440.00 7,632,000.00
Armaflex insulation tube

16 Installation material such as insulation tapes, Tangit gum, Plugs and


clips etc 1 LOT 3,000,000.00 3,000,000.00

TOTAL TO SUMMARY 67,771,848.40

CCP748M.BOQ Page 441


BESMM4 CIVIL WORK SECTIONS - REVIEWED VERSION GENERAL ITEMS

Qty Unit Rate N K

2A GENERAL ITEMS
2A1.0 Information Required
2A1.0.1 Location Drawings as defined in General Rule 5.1 item 0.00

Information to facilitate visiting site and addresses


where drawings or other information additional to that
required by these rules or listed information may be
2A1.0.2 inspected. item 0.00

Nigeri2An Institute of Qu2Antity Surveyors To Collection N 0.00

Page 1
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS

Qty Unit Rate N K

GENERAL ITEMS continued ...


2A1.1. Contractual requirements
2A1.1.1 Performance bond item
2A1.1.2 Insurance of the Works item
2A1.1.3 Third party insurance sum
2A1.2 Specified requirements
2A1.2.1 Accommodation for the contract administrators item
2A1.2.1.1 Offices item
2A1.2.1.2 Laboratories item
2A1.2.1.3 Cabins item
2A1.2.2 Servicesfor the contract administrators
2A1.2.2.1 Transport vehicles item
2A1.2.2.2 Telephones item
2A1.2.3 Equipment for the contract administrators item
2A1.2.3.1 Office equipment item
2A1.2.3.2 Laboratory equipment item
2A1.2.3.3 Surveying equipment item
2A1.2.4 Attendance upon the contract adminstrators
2A1.2.4.1 Drivers item
2A1.2.4.2 Chainmen item
2A1.2.4.3 Laboratory assistants item
2A1.2.5 Testing of materials item
2A1.2.6 Testing of the Works sum
2A1.2.7 Temporary works sum
2A1.2.7.1 Traffic Diversion sum
2A1.2.7.2 Traffic regulations sum
2A1.2.7.3 Access roads sum
2A1.2.7.4 Bridges sum
2A1.2.7.5 Cofferdams sum
2A1.2.7.6 Pumping sum
2A1.2.7.7 De-watering sum
2A1.2.7.8 Compressed air turnelling sum
2A1.3 Method-Related Charges
2A1.3.1 Accommodation and buildings item
2A1.3.1.1 Offices item
2A1.3.1.2 Laboratories item
2A1.3.1.3 Cabins item
2A1.3.1.4 Stores item
2A1.3.1.5 Canteens and messrooms item
2A1.3.2 Services
2A1.3.2.1 Electricity item
2A1.3.2.2 Water item
2A1.3.2.3 Security item
2A1.3.2.4 Hoardings item
2A1.3.2.5 Site transport item
2A1.3.2.6 Personnel transport item
2A1.3.2.7 Welfare item

Page 2
Nigeri2An Institute of Qu2Antity Surveyors To Collection N 0.00

Page 3
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS

Qty Unit Rate N K

GENERAL ITEMS continued ...


Method-Related Charges continued ...
2A1.3.3 Plant (A)
2A1.3.3.1 Cranes item
2A1.3.3.2 Transport item
2A1.3.3.3 Earthmoving item
2A1.3.3.4 Compaction item
2A1.3.3.5 Concrete mixing item
2A1.3.3.6 Concrete transport item
2A1.3.3.7 Pile driving item
2A1.3.3.8 Pile boring item
2A1.3.4 Plant (B)
2A1.3.4.1 Pipelaying sum
2A1.3.4.2 Paving sum
2A1.3.4.3 Tunnelling sum
2A1.3.4.4 Crushing and screening sum
2A1.3.4.5 Boring and drilling sum
2A1.3.5 Temporary Works (A)
2A1.3.5.1 Traffic diversions sum
2A1.3.5.2 Traffic regulation sum
2A1.3.5.3 Access roads sum
2A1.3.5.4 Bridges sum
2A1.3.5.5 Cofferdams sum
2A1.3.5.6 Pumping sum
2A1.3.5.7 De-watering sum
2A1.3.5.8 Compressed air for tunnelling sum
2A1.3.6 Temporary Works (B)
2A1.3.6.1 Access scaffolding sum
2A1.3.6.2 Support for scaffolding and propping sum
2A1.3.6.3 Piling sum
2A1.3.6.4 Formwork sum
2A1.3.6.5 Shafts and pits sum
2A1.3.6.6 Hardstandings sum
2A1.3.7 Supervision and labour sum
2A1.3.7.1 Supervision sum
2A1.3.7.2 Administration sum
2A1.3.7.3 Labour teams sum
2A1.4 Provisional Sums
2A1.4.1 Daywork sum

Nigeri2An Institute of Qu2Antity Surveyors To Collection N 0.00

Page 4
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS

Qty Unit Rate N K

GENERAL ITEMS continued ...


Provisional Sums continued ...
Daywork continued ...
2A1.4.1.1 Labour sum
Percentage adjustment to Provisional Sum for
2A1.4.1.2 Daywork labour sum
2A1.4.1.3 Materials sum
Percentage adjustment to Provisional Sum for
2A1.4.1.4 Daywork materials sum
2A1.4.1.5 Plant sum
Percentage adjustment to Provisional Sum for
2A1.4.1.6 Daywork plant sum
2A1.4.1.7 Supplementary charges sum
Percentage adjustment to Provisional Sum for
2A1.4.1.8 Daywork supplementary charges sum

Nominated Sub-contracts which include work on


2A1.5 the Site
2A1.5.1 Prime Cost Item sum
2A1.5.2 Labours sum
2A1.5.3 Special labours sum
2A1.5.4 Other charges and profit sum
Nominated Sub-contracts which do not include
2A1.6 work on the Site
2A1.6.1 Prime Cost Item sum
2A1.6.2 Labours sum
2A1.6.3 Special labours sum
2A1.6.4 Other charges and profit sum

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 5
BESMM4 CIVIL WORK SECTIONS GENERAL ITEMS

Qty Unit Rate N K

Collection

Total from Page 1 N 0.00

Total from Page 2 N 0.00

Total from Page 3 N 0.00

Total from Page 4 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 6
BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION

Qty Unit Rate N K

2B GROUND INVESTIGATION
2B1.1 Trial pits and trenches
2B1.1.1 Number in material other than rock
2B1.1.1.1 Maximum depth not exceeding 1m 0 nr 0.00
2B1.1.1.2 Maximum depth 1-2m 0 nr 0.00
2B1.1.1.3 Maximum depth 2-3m 0 nr 0.00
2B1.1.1.4 Maximum depth 3-5m 0 nr 0.00
2B1.1.1.5 Maximum depth 5-10m 0 nr 0.00
2B1.1.1.6 Maximum depth 10-15m 0 nr 0.00
2B1.1.1.7 Maximum depth 15-20m 0 nr 0.00
2B1.1.1.8 Maximum depth stated exceeding 20m 0 nr 0.00
2B1.1.2 Number in material which includes rock
2B1.1.2.1 Maximum depth not exceeding 1m 0 nr 0.00
2B1.1.2.2 Maximum depth 1-2m 0 nr 0.00
2B1.1.2.3 Maximum depth 2-3m 0 nr 0.00
2B1.1.2.4 Maximum depth 3-5m 0 nr 0.00
2B1.1.2.5 Maximum depth 5-10m 0 nr 0.00
2B1.1.2.6 Maximum depth 10-15m 0 nr 0.00
2B1.1.2.7 Maximum depth 15-20m 0 nr 0.00
2B1.1.2.8 Maximum depth stated exceeding 20m 0 nr 0.00
2B1.1.3 Depth in material other than rock 0m 0.00
2B1.1.4 Depth in rock 0m 0.00
2B1.1.5 Depth supported 0m 0.00
2B1.1.6 Depth backfilled, material stated 0m 0.00
2B1.1.7 Removal of obstructions 0h 0.00
2B1.1.8 Pumping at a stated minimum extraction rate 0h 0.00
2B1.2 Light cable percussion boreholes
2B1.2.1 Number 0 nr 0.00
2B1.2.2 Depth
2B1.2.2.1 In holes of maximum depth not exceeding 5m 0m 0.00
2B1.2.2.2 In holes of maximum depth 5-10m 0m 0.00
2B1.2.2.3 In holes of maximum depth 10-20m 0m 0.00
2B1.2.2.4 In holes of maximum depth 20-30m 0m 0.00
2B1.2.2.5 In holes of maximum depth 30-40m 0m 0.00
2B1.2.2.6 In holes of maximum depth stated exceeding 40m 0m 0.00
2B1.2.3 Depth backfilled, material stated 0m 0.00
2B1.2.4 Chiselling to prove rock or to penetrate obstructions 0h 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 7
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION

Qty Unit Rate N K

GROUND INVESTIGATION continued ...


2B1.3 Rotary drilled boreholes
2B1.3.1 Number 0 nr 0.00
2B1.3.2 Depth without core recovery
2B1.3.2.1 In holes of maximum depth not exceeding 5m 0m 0.00
2B1.3.2.2 In holes of maximum depth 5-10m 0m 0.00
2B1.3.2.3 In holes of maximum depth 10-20m 0m 0.00
2B1.3.2.4 In holes of maximum depth 20-30m 0m 0.00
2B1.3.2.5 In holes of maximum depth 30-40m 0m 0.00
2B1.3.2.6 In holes of maximum depth stated exceeding 40m 0m 0.00
2B1.3.3 Depth with core recovery
2B1.3.3.1 In holes of maximum depth not exceeding 5m 0m 0.00
2B1.3.3.2 In holes of maximum depth 5-10m 0m 0.00
2B1.3.3.3 In holes of maximum depth 10-20m 0m 0.00
2B1.3.3.4 In holes of maximum depth 20-30m 0m 0.00
2B1.3.3.5 In holes of maximum depth 30-40m 0m 0.00
2B1.3.3.6 In holes of maximum depth stated exceeding 40m 0m 0.00
2B1.3.4 Depth cased 0m 0.00
2B1.3.5 Depth backfilled, material stated 0m 0.00
2B1.3.6 Core boxes, length of core stated 0 nr 0.00
2B1.4 Samples
2B1.4.1 From the surface or from pits and trenches
2B1.4.1.1 Undisturbed soft material 0 nr 0.00
2B1.4.1.2 Disturbed soft material 0 nr 0.00
2B1.4.1.3 Rock 0 nr 0.00
2B1.4.1.4 Groundwater 0 nr 0.00
2B1.4.2 From boreholes
2B1.4.2.1 Open tube 0 nr 0.00
2B1.4.2.2 Disturbed 0 nr 0.00
2B1.4.2.3 Groundwater 0 nr 0.00
2B1.4.2.4 Stationary 0 nr 0.00
2B1.4.2.5 Swedish Foil 0 nr 0.00
2B1.4.2.6 Delft 0 nr 0.00
2B1.4.2.7 Bishop sand 0 nr 0.00
2B1.5 Site tests and observations
2B1.5.1 Deliberately Left Blank
2B1.5.1.1 Permeability 0h 0.00
2B1.5.1.2 Groundwater level 0 nr 0.00
2B1.5.1.3 Standard penetration 0 nr 0.00
2B1.5.1.4 Penetration vane 0 nr 0.00
2B1.5.1.5 Vane in borehole 0 nr 0.00
2B1.5.1.6 Pressure meter 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 8
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION

Qty Unit Rate N K

GROUND INVESTIGATION continued ...


Site tests and observations continued ...
2B1.5.2 Deliberately Left Blank
2B1.5.2.1 Plate bearing 0 nr 0.00
2B1.5.2.2 Self-boring pressure meter 0 nr 0.00
2B1.5.2.3 California bearing ratio 0 nr 0.00
2B1.5.2.4 Static cone sounding 0 nr 0.00
2B1.5.2.5 In situ density 0 nr 0.00
2B1.5.2.6 Mackintosh probe 0 nr 0.00
2B1.5.2.7 Hand auger borehole 0 nr 0.00
2B1.6 Instrumental observations
2B1.6.1 Pressure head
2B1.6.1.1 Standpipes 0m 0.00
2B1.6.1.2 Piezometers 0m 0.00
2B1.6.1.3 Install covers 0 nr 0.00
2B1.6.1.4 Readings 0 nr 0.00
2B1.6.2 Inclinometers
2B1.6.2.1 Installations 0 nr 0.00
2B1.6.2.2 Readings 0 nr 0.00
2B1.6.3 Settlement gauges
2B1.6.3.1 Installations 0 nr 0.00
2B1.6.3.2 Readings 0 nr 0.00
2B1.6.4 Resistivity
2B1.6.4.1 Installations 0 nr 0.00
2B1.6.4.2 Readings 0 nr 0.00
2B1.6.5 Seismic
2B1.6.5.1 Installations 0 nr 0.00
2B1.6.5.2 Readings 0 nr 0.00
2B1.6.6 Magnetometer
2B1.6.6.1 Installations 0 nr 0.00
2B1.6.6.2 Readings 0 nr 0.00
2B1.6.7 Self-potential
2B1.6.7.1 Installations 0 nr 0.00
2B1.6.7.2 Readings 0 nr 0.00
2B1.6.8 Gravimetric
2B1.6.8.1 Installations 0 nr 0.00
2B1.6.8.2 Readings 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 9
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION

Qty Unit Rate N K

GROUND INVESTIGATION continued ...


2B1.7 Laboratory tests
2B1.7.1 Classification
2B1.7.1.1 Moisture content 0 nr 0.00
2B1.7.1.2 Atterberg limits 0 nr 0.00
2B1.7.1.3 Specific gravity 0 nr 0.00
2B1.7.1.4 Particle size analysis by sieve 0 nr 0.00
2B1.7.1.5 Particle size analysis by pipette or hydrometer 0 nr 0.00
2B1.7.1.6 Frost susceptibility 0 nr 0.00
2B1.7.2 Chemical content
2B1.7.2.1 Original organic matter 0 nr 0.00
2B1.7.2.2 Sulphate 0 nr 0.00
2B1.7.2.3 pH value 0 nr 0.00
2B1.7.2.4 Contaminants 0 nr 0.00
2B1.7.3 Compaction
2B1.7.3.1 Standard 0 nr 0.00
2B1.7.3.2 Heavy 0 nr 0.00
2B1.7.3.3 Vibratory 0 nr 0.00
2B1.7.4 Consolidation
2B1.7.4.1 Oedometer cell 0 nr 0.00
2B1.7.4.2 Triaxial cell 0 nr 0.00
2B1.7.4.3 Rowe cell 0 nr 0.00
2B1.7.5 Permeability
2B1.7.5.1 Constant head 0 nr 0.00
2B1.7.5.2 Falling head 0 nr 0.00
2B1.7.6 Soil strength
2B1.7.6.1 Quick undrained triaxial 0 nr 0.00
Consolidated undrained triaxial with pore water
2B1.7.6.2 pressure measurement 0 nr 0.00
Consolidated drained triaxial with volume change
2B1.7.6.3 measurement 0 nr 0.00
2B1.7.6.4 Shearbox peak only 0 nr 0.00
2B1.7.6.5 Peak and residual 0 nr 0.00
2B1.7.6.6 Residual only 0 nr 0.00
2B1.7.6.7 Ring shear 0 nr 0.00
2B1.7.6.8 California bearing ratio 0 nr 0.00
2B1.7.7 Rock strength
2B1.7.7.1 Unconfirmed compressive strength of rock samples 0 nr 0.00
Consolidated drained triaxial with volume charge
2B1.7.7.2 measurement 0 nr 0.00
2B1.7.7.3 Brazilian 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 10
2BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION

Qty Unit Rate N K

GROUND INVESTIGATION continued ...


Laboratory tests continued ...
Rock strength continued ...
2B1.7.7.4 Ring shear 0 nr 0.00
2B1.7.7.5 Point load 0 nr 0.00
2B1.8 Professional services
2B1.8.1 Technician 0h 0.00
2B1.8.2 Technician engineer 0h 0.00
2B1.8.3 Engineer or geologist
2B1.8.3.1 Graduate 0h 0.00
2B1.8.3.2 Registered 0h 0.00
2B1.8.3.3 Principal or consultant 0h 0.00
2B1.8.3.4 Visits to the Site
2B1.8.3.5 Overnight stays in connection with visits to the Site 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 11
BESMM4 CIVIL WORK SECTIONS GROUND INVESTIGATION

Qty Unit Rate N K

Collection

Total from Page 6 N 0.00

Total from Page 7 N 0.00

Total from Page 8 N 0.00

Total from Page 9 N 0.00

Total from Page 10 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 12
BESMM4 CIVIL WORK SECTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS

Qty Unit Rate N K

GEOTECHNICAL AND OTHER SPECIALIST


2C PROCESSES
Drilling for grout holes through material other than
2C1.1 rock or artificial hard material

Vertically downwards; Downwards at an angle 0-40


2C1.1.1 Deg to the vertical; Horizontally or downwards at an
angle less than 45 Deg to the horizontal; Upwards at
an angle 0-45 Deg to the horizontal;Upwards at an
angle less than 45 Deg to the vertical
2C1.1.1.1 In holes of depth not exceeding 5m 0m 0.00
2C1.1.1.2 In holes of depth 5-10m 0m 0.00
2C1.1.1.3 In holes of depth 10-20m 0m 0.00
2C1.1.1.4 In holes of depth 20-30m 0m 0.00
2C1.1.1.5 In holes of depth 30-40m 0m 0.00
2C1.1.1.6 In holes of depth stated exceeding 40m 0m 0.00
Drilling for grout holes through rock or artificial
2C1.2 hard material

Vertically downwards; Downwards at an angle 0-45


Deg to the vertical; Horizontally or downwards at
2C1.2.1 an angle less than 45 Deg to
the horizontal; Upwards at an angle 0-45 Deg to the
horizontal; Upwards at an angle less than 45 Deg to
the vertical
2C1.2.1.1 In holes of depth not exceeding 5m 0m 0.00
2C1.2.1.2 In holes of depth 5-10m 0m 0.00
2C1.2.1.3 In holes of depth 10-20m 0m 0.00
2C1.2.1.4 In holes of depth 20-30m 0m 0.00
2C1.2.1.5 In holes of depth 30-40m 0m 0.00
2C1.2.1.6 In holes of depth stated exceeding 40m 0m 0.00
2C1.3 Driving injection pipes for grout holes

Vertically downwards; Downwards at an angle 0-45


Deg to the vertical; Horizontally or downwards at
2C1.3.1 an angle less than 45 Deg to
the horizontal; Upwards at an angle 0-45 Deg to the
horizontal; Upwards at an angle less than 45 Deg to
the vertica
2C1.3.1.1 In holes of depth not exceeding 5m 0m 0.00
2C1.3.1.2 In holes of depth 5-10m 0m 0.00
2C1.3.1.3 In holes of depth 10-20m 0m 0.00
2C1.3.1.4 In holes of depth 20-30m 0m 0.00
2C1.3.1.5 In holes of depth 30-40m 0m 0.00
2C1.3.1.6 In holes of depth stated exceeding 40m 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 13
BESMM4 2CIVIL WORK SE2CTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS

Qty Unit Rate N K

GEOTECHNICAL AND OTHER SPECIALIST


PROCESSES continued ...
2C1.4 Grout holes
2C1.4.1 Number of holes 0 nr 0.00
2C1.4.2 Number of stages 0 nr 0.00
2C1.4.3 Single water pressure tests 0 nr 0.00
2C1.4.4 Multiple water pressure tests 0 nr 0.00
2C1.4.1.1 Grout holes - Materials
2C1.4.1.1.1 Cement 0.00 t 0.00
2C1.4.1.1.2 Pulverized fuel ash 0.00 t 0.00
2C1.4.1.1.3 Sand 0.00 t 0.00
2C1.4.1.1.4 Pea gravel 0.00 t 0.00
2C1.4.1.1.5 Bentonite 0.00 t 0.00
2C1.4.1.1.6 Chemicals 0.00 t 0.00
2C1.4.5 Grout holes - Injection
2C1.4.5.1 Number of injections 0 nr 0.00
2C1.4.5.2 Neat cement grout 0.00 t 0.00
2C1.4.5.3 Cement and stated filler 0.00 t 0.00
2C1.4.5.4 Chemical grout 0.00 t 0.00
2C1.4.5.5 Other stated grout 0.00 t 0.00
2C1.4.5.6 Single packer settings 0 nr 0.00
2C1.4.5.7 Double packer settings 0 nr 0.00

2C1.5 Diaphragm walls


Excavation in material other than rock or artificial hard
2C1.5.1 material
2C1.5.2 Excavation in rock
2C1.5.3 Excavation in artificial hard material
2C1.5.3.1 Maximum depth not exceeding 5m 0 m3 0.00
2C1.5.3.2 Depth 5 - 10m 0 m3 0.00
2C1.5.4 Concrete - nominal thickness 0 m3 0.00
2C1.5.5 Plain round bar reinforcement to BS4449
2C1.5.5.1 Nominal size 6mm 0.00 t 0.00
2C1.5.5.2 Nominal size 8mm 0.00 t 0.00
2C1.5.5.3 Nominal size 10mm 0.00 t 0.00
2C1.5.5.4 Nominal size 12mm 0.00 t 0.00
2C1.5.5.5 Nominal size 16mm 0.00 t 0.00
2C1.5.5.6 Nominal size 20mm 0.00 t 0.00
2C1.5.5.7 Nominal size 25mm 0.00 t 0.00
2C1.5.5.8 Nominal size 32mm or greater 0.00 t 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 14
BESMM4 2CIVIL WORK SE2CTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS

Qty Unit Rate N K

GEOTECHNICAL AND OTHER SPECIALIST


PROCESSES continued ...
Diaphragm walls continued ...
2C1.5.6 Deformed high yield steel reinforcement to BS4449
2C1.5.6.1 Nominal size 6mm 0.00 t 0.00
2C1.5.7 Waterproofed joints sum 0.00
2C1.5.8 Guide walls 0m 0.00

2C1.6 Ground anchorages


Number in material other than rock or artificial hard
2C1.6.1 material to a stated maximum depth
Total length of tendons in material other than rock or
2C1.6.2 artifical hard material
Number in material which includes rock or artificial
2C1.6.3 hard material to a stated maximum depth
2C1.6.3.1 Temporary 0 nr 0.00
2C1.6.3.2 Temporary with single corrosion protection 0 nr 0.00
2C1.6.3.3 Temporary with double corrosion protection 0 nr 0.00
2C1.6.3.4 Permanent 0 nr 0.00
2C1.6.3.5 Permanent with single corrosion protection 0 nr 0.00
2C1.6.3.6 Permanent with double corrosion protection 0 nr 0.00
2C1.7 Sand, band and wick drains
2C1.7.1 Number of drains
2C1.7.2 Number of predrilled holes
2C1.7.3 Depth of overlying material
Depth of drains of maximum depth not exceeding
2C1.7.4 10m
2C1.7.5 Depth of drains of maximum depth 10-15m
2C1.7.6 Depth of drains of maximum depth 15-20m
2C1.7.7 Depth of drains of maximum depth 20-25m
2C1.7.8 Depth of drains stated exceeding 25m
2C1.7.8.1 Cross-sectional dimension not exceeding 100mm 0 nr 0.00
2C1.7.8.2 Cross-sectional dimension 100-200mm 0 nr 0.00
2C1.7.8.3 Cross-sectional dimension 200-300mm 0 nr 0.00
2C1.7.8.4 Cross-sectional dimension 300-400mm 0 nr 0.00
2C1.7.8.5 Cross-sectional dimension 400-500mm 0 nr 0.00
Cross-sectional dimension stated exceeding
2C1.7.8.6 500mm 0 nr 0.00
2C1.8 Vibro flotation
2C1.8.1 Number of probes
2C1.8.2 Depth of probes
2C1.8.2.1 Depth not exceeding 5m 0 nr 0.00
2C1.8.2.2 Depth 5-10m 0 nr
2C1.8.2.3 Depth 10-20m 0 nr
2C1.8.2.4 Depth 20-30m 0 nr
2C1.8.2.5 Depth 30-40m 0 nr
2C1.8.2.6 Depth stated exceeding 40m 0 nr
Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 15
BESMM4 CIVIL WORK SECTIONS GEOTECHNICAL & OTHER SPECIALIST PROCESS

Qty Unit Rate N K

Collection

Total from Page 12 N 0.00

Total from Page 13 N 0.00

Total from Page 14 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 16
BESMM4 CIVIL WORK SECTIONS DEMOLITION & SITE CLEARANCE

Qty Unit Rate N K

2D DEMOLITION AND SITE CLEARANCE


2D1.1 Site Clearance
2D1.1.1 General site clearance 0.00 ha 0.00
2D1.1.2 Invasive plant Species 0 m2 0.00
2D1.2 Trees
2D1.2.1 Girth 500mm-2m 0 nr 0.00
2D1.2.2 Girth exceeding 2m 0 nr 0.00
2D1.3 Stumps
2D1.3.1 Diameter less than 1m 0 nr 0.00
2D1.3.2 Diameter exceeding 1m 0 nr 0.00
2D1.4 Buildings
2D1.4.1 Brickwork
2D1.4.2 Concrete
2D1.4.3 Masonry
2D1.4.4 Metal
2D1.4.5 Timber
2D1.4.6 No predominant material
2D1.4.1.1 Volume not exceeding 50m3 sum 0.00
2D1.4.1.2 Volume 50-100m3 sum 0.00
2D1.4.1.3 Volume 100-250m3 sum 0.00
2D1.4.1.4 Volume 250-500m3 sum 0.00
2D1.4.1.5 Volume 500-1000m3 sum 0.00
2D1.4.1.6 Volume 1000-2500m3 sum 0.00
2D1.4.1.7 Volume 2500-5000m3 sum 0.00
2D1.4.1.8 Volume stated exceeding 5000m3 sum 0.00
2D1.5 Other structures
2D1.5.1 Brickwork
2D1.5.2 Concrete
2D1.5.3 Masonry
2D1.5.4 Metal
2D1.5.5 Timber
2D1.5.6 No predominant material
2D1.5.6.1 Volume not exceeding 50m3 sum 0.00
2D1.5.6.2 Volume 50-100m3 sum 0.00
2D1.5.6.3 Volume 100-250m3 sum 0.00
2D1.5.6.4 Volume 250-500m3 sum 0.00
2D1.5.6.5 Volume 500-1000m3 sum 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 17
BESMM4 CIVIL WORK SECTIONS DEMOLITION & SITE CLEARANCE

Qty Unit Rate N K

DEMOLITION AND SITE CLEARANCE continued ...


Other structures continued ...
No predominant material continued ...
2D1.5.6.6 Volume 1000-2500m3 sum 0.00
2D1.5.6.7 Volume 2500-5000m3 sum 0.00
2D1.5.6.8 Volume stated exceeding 5000m3 sum 0.00
2D1.6 Pipelines
2D1.6.1 Nominal bore 100-300mm 0m 0.00
2D1.6.2 Nominal bore 300-500mm 0m 0.00
2D1.6.3 Nominal bore exceeding 500mm 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 18
BESMM4 CIVIL WORK SECTIONS DEMOLITION & SITE CLEARANCE

Qty Unit Rate N K

Collection

Total from Page 16 N 0.00

Total from Page 17 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 19
BESMM4 CIVIL WORK SECTIONS EARTHWORKS

Qty Unit Rate N K

2E EARTHWORKS
2E1.1 Excavation by dredging
2E1.2 Excavation for cuttings
2E1.2.1 Topsoil 0 m3 0.00
Material other than topsoil, rock or artificial hard
2E1.2.2 material 0 m3 0.00
2E1.2.3 Rock 0 m3 0.00
Stated artificial hard material exposed at the
2E1.2.4 Commencing Surface 0 m3 0.00
Stated artificial hard material not exposed at the
2E1.2.5 Commencing Surface 0 m3 0.00
2E1.3 Excavation for foundations
2E1.3.1 Topsoil
Material other than topsoil, rock or artificial hard
2E1.3.2 material
2E1.3.3 Rock
Stated artificial hard material exposed at the
2E1.3.4 Commencing Surface
Stated artificial hard material not exposed at the
2E1.3.5 Commencing Surface
Controlled and hazardous material exposed at the
2E1.3.6 commencing surface
Controlled and hazardous material not exposed at the
2E1.3.7 commencing surface
2E1.3.7.1 Maximum depth not exceeding 0.25m 0 m3 0.00
2E1.3.7.2 Maximum depth 0.25-0.5m 0 m3 0.00
2E1.3.7.3 Maximum depth 0.5-1m 0 m3 0.00
2E1.3.7.4 Maximum depth 1-2m 0 m3 0.00
2E1.3.7.5 Maximum depth 2-5m 0 m3 0.00
2E1.3.7.6 Maximum depth 5-10m 0 m3 0.00
2E1.3.7.7 Maximum depth 10-15m 0 m3 0.00
2E1.3.7.8 Maximum depth stated exceeding 15m 0 m3 0.00
2E1.4 General excavation
2E1.4.1 Topsoil
Material other than topsoil, rock or artificial hard
2E1.4.2 material
2E1.4.3 Rock
Stated artificial hard material exposed at the
2E1.4.4 Commencing Surface
Stated artificial hard material not exposed at the
2E1.4.5 Commencing Surface
2E1.4.5.1 Maximum depth not exceeding 0.25m 0 m3 0.00
2E1.4.5.2 Maximum depth 0.25-0.5m 0 m3 0.00
2E1.4.5.3 Maximum depth 0.5-1m 0 m3 0.00
2E1.4.5.4 Maximum depth 1-2m 0 m3 0.00

Nig2Erian Institut2E of Quantity Surv2Eyors To Collection N 0.00

Page 20
B2ESMM4 CIVIL WORK S2ECTIONS EARTHWORKS

Qty Unit Rate N K


EARTHWORKS continued ...
General excavation continued ...
Stated artificial hard material not exposed at the
Commencing Surface continued ...
2E1.4.5.5 Maximum depth 2-5m 0 m3 0.00
2E1.4.5.6 Maximum depth 5-10m 0 m3 0.00
2E1.4.5.7 Maximum depth 10-15m 0 m3 0.00
2E1.4.5.8 Maximum depth stated exceeding 15m 0 m3 0.00
2E1.5 Excavation ancillaries
2E1.5.1 Trimming of excavated surfaces
2E1.5.2 Preparation of excavated surfaces
2E1.5.2.1 Topsoil 0 m3 0.00
Material other than topsoil, rock or artificial hard
2E1.5.2.2 material 0 m3 0.00
2E1.5.2.3 Rock 0 m3 0.00
2E1.5.2.4 Stated artificial hard material 0 m2 0.00
2E1.5.2.5 Controlled and hazardous material 0 m2 0.00
2E1.5.3 Disposal of excavated material
2E1.5.4 Double handling of excavated material
2E1.5.3.1 Topsoil 0 m3 0.00
Material other than topsoil, rock or artificial hard
2E1.5.3.2 material 0 m3 0.00
2E1.5.3.3 Rock 0 m3 0.00
2E1.5.3.4 Stated artificial hard material 0 m2 0.00
2E1.5.3.5 Controlled and hazardous material 0 m2 0.00
2E1.5.5 Dredging to remove silt 0 m3 0.00
Excavation of material below the Fianal Surface and
2E1.5.6 replacement with stated material 0 m3 0.00
2E1.5.7 Timber supports left in 0 m2 0.00
2E1.5.8 Metal supports left in 0 m2 0.00
2E1.6 Filling
2E1.6.1 To structures
2E1.6.2 Embankments
2E1.6.3 General
2E1.6.3.1 Excavated topsoil 0 m3 0.00
2E1.6.3.2 Imported topsoil 0 m3 0.00
Non-selected excavated material other than topsoil
2E1.6.3.3 or rock 0 m3 0.00
Selected excavated material other than topsoil or
2E1.6.3.4 rock 0 m3 0.00
2E1.6.3.5 Imported natural material other than topsoil or rock 0 m3 0.00
2E1.6.3.6 Excavated rock 0 m3 0.00

Nig2Erian Institut2E of Quantity Surv2Eyors To Collection N 0.00

Page 21
B2ESMM4 CIVIL WORK S2ECTIONS EARTHWORKS

Qty Unit Rate N K

EARTHWORKS continued ...


Filling continued ...
General continued ...
2E1.6.3.7 Imported rock 0 m3 0.00
2E1.6.3.8 Imported artificial material 0 m3 0.00
2E1.6.4 To stated depth or thickness
2E1.6.4.1 Excavated topsoil 0 m2 0.00
2E1.6.4.2 Imported topsoil 0 m2 0.00
Non-selected excavated material other than topsoil
2E1.6.4.3 or rock 0 m2 0.00
Selected excavated material other than topsoil or
2E1.6.4.4 rock 0 m2 0.00
2E1.6.4.5 Imported natural material other than topsoil or rock 0 m2 0.00
2E1.6.4.6 Excavated rock 0 m2 0.00
2E1.6.4.7 Imported rock 0 m2 0.00
2E1.6.4.8 Imported artificial material 0 m2 0.00
2E1.7 Filling ancillaries
2E1.7.1 Trimming of filled surfaces
2E1.7.2 Preparation of filled surfaces
2E1.7.2.1 Topsoil 0 m2 0.00
Material other than topsoil, rock or artificial hard
2E1.7.2.2 material 0 m2 0.00
2E1.7.2.3 Rock 0 m2 0.00
2E1.7.2.4 Stated artificial hard material 0 m2 0.00
2E1.7.3 Geotextiles 0 m2 0.00
2E1.8 Landscaping
2E1.8.1 Turfing 0 m2 0.00
2E1.8.2 Hydraulic mulch grass seeding 0 m2 0.00
2E1.8.3 Other grass seeding 0 m2 0.00
2E1.8.4 Plants, stated species and size 0 nr 0.00
2E1.8.5 Shrubs, stated species and size 0 nr 0.00
2E1.8.6 Trees, stated species and size 0 nr 0.00
2E1.8.7 Hedges, stated species, size and spacing
2E1.8.7.1 Single row 0m 0.00
2E1.8.7.2 Double row 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 22
BESMM4 CIVIL WORK SECTIONS EARTHWORKS

Qty Unit Rate N K

Collection

Total from Page 19 N 0.00

Total from Page 20 N 0.00

Total from Page 21 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 23
BESMM4 CIVIL WORK SECTIONS IN SITU CONCRETE

Qty Unit Rate N K

2F IN SITU CONCRETE
Provision of concrete, designed Concrete: Cement to
2F1.1 BS12 or BS146 20mm aggregate
2F1.1.1 Strength C8/10 0 m3 0.00
2F1.1.2 Strength C12/15 m3
2F1.1.3 Strength C16/20 m3
2F1.1.4 Strength C20/25 m3
2F1.1.5 Strength C25/30 m3
2F1.1.6 Strength C28/35 m3
2F1.1.7 Strength C30/37 m3
2F1.1.8 Strength C32/40 m3
Provision of concrete, designated Concrete: Cement
2F1.2 to BS12 or BS146 20mm aggregate
2F1.2.1 Strength RC20/25 0 m3 0.00
2F1.2.2 Strength RC 25/30 m3
2F1.2.3 Strength RC28/35 m3
2F1.2.4 Strength RC30/37 m3
2F1.2.5 Strength RC32/40 m3
2F1.2.6 Strength RC35/45 m3
2F1.2.7 Strength RC40/50 0 m3 0.00

Provision of concrete, Standardised prescribed


2F1.3 Concrete: Cement to BS12 or BS146 20mm aggregate m3
2F1.3.1 ST1 m3
2F1.3.2 ST2 m3
2F1.3.3 ST3 m3
2F1.3.4 ST4 m3
2F1.3.5 ST5 m3
Provision of concrete, Prescribed Mix: Cement to
2F1.4 BS12 or BS146 20mm aggregate
Provision of concrete, Proprietary Concrete: Cement
2F1.5 to BS12 or BS146 20mm aggregate
2F1.6 Placing of concrete, mass
2F1.7 Placing of concrete reinforced
2F1.8 Placing of concrete prestressed
2F1.6.1 Blinding m3
2F1.6.2 Bases, footings, pile caps and ground slabs 0 m3 0.00
2F1.6.3 Suspended slabs m3
2F1.6.4 Walls m3
2F1.6.4.1 Thickness not exceeding 150mm m3

Nigerian Institute o2F Quantity Surveyors To Collection N 0.00

Page 24
BESMM4 CIVIL WORK SECTIONS IN SITU CONCRETE

Qty Unit Rate N K

IN SITU CONCRETE continued ...


Placing of concrete prestressed continued ...
Walls continued ...
2F1.6.4.2 Thickness 150-300mm 0 m3 0.00
2F1.6.4.3 Thickness 300-500mm 0 m3 0.00
2F1.6.4.4 Thickness exceeding 500mm 0 m3 0.00
2F1.6.5 Columns and piers 0 m3
2F1.6.6 Beams 0 m3
2F1.6.7 Casings to metal sections
2F1.6.7.1 Cross sectional area not exceeding 0.03m2 0 m3 0.00
2F1.6.7.2 Cross sectional area 0.03-0.1m2 0 m3 0.00
2F1.6.7.3 Cross sectional area 0.1m-0.25m2 0 m3 0.00
2F1.6.7.4 Cross sectional area 0.25-1m2 0 m3 0.00
2F1.6.7.5 Cross sectional area exceeding 1m2 0 m3 0.00
2F1.6.7.6 Special beam section 0 m3 0.00
2F1.6.8 Other concrete forms

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 25
BESMM4 CIVIL WORK SECTIONS IN SITU CONCRETE

Qty Unit Rate N K

Collection

Total from Page 23 N 0.00

Total from Page 24 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 26
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES

Qty Unit Rate N K

2G CONCRETE ANCILLARIES
2G1.1 Formwork: rough finish
2G1.2 Formwork: fair finish
2G1.3 Formwork: other stated finish
2G1.4 Formwork: stated surface features
2G1.1.1 Plane horizontal
2G1.1.2 Plane sloping
2G1.1.3 Plane battered
2G1.1.4 Plane vertical
2G1.1.5 Curved to one radius in one plane
2G1.1.1.1 Width not exceeding 0.1m 0m 0.00
2G1.1.1.2 Width 0.1-0.2m 0m 0.00
2G1.1.1.3 Width 0.2-0.4m 0 m2 0.00
2G1.1.1.4 Width 0.4-1.22m 0 m2 0.00
2G1.1.1.5 Width exceeding 1.22m 0 m2 0.00
2G1.1.6 Other curved 0 m2 0.00
2G1.1.7 For voids
2G1.1.7.1 Small void depth not exceeding 0.5m 0 nr 0.00
2G1.1.7.2 Small void depth 0.5-1m 0 nr 0.00
2G1.1.7.3 Small void depth 1-2m 0 nr 0.00
2G1.1.7.4 Small void depth stated exceeding 2m 0 nr 0.00
2G1.1.7.5 Large void depth not exceeding 0.5m 0 nr 0.00
2G1.1.7.6 Large void depth 0.5-1m 0 nr 0.00
2G1.1.7.7 Large void depth 1-2m 0 nr 0.00
2G1.1.7.8 Large void depth stated exceeding 2m 0 nr 0.00
2G1.1.8 For concrete components of constant cross-section
2G1.1.8.1 Beams 0m 0.00
2G1.1.8.2 Columns 0m 0.00
2G1.1.8.3 Walls 0m 0.00
2G1.1.8.4 Other members 0m 0.00
2G1.1.8.5 Projections 0m 0.00
2G1.1.8.6 Intrusions 0m 0.00
2G1.5 Reinforcement
2G1.5.1 Plain round steel bars to BS 4449
2G1.5.2 Deformed steel bars to BS 4449
2G1.5.3 Stainless steel bars of stated quality
2G1.5.4 Reinforcing bars of other stated material
2G1.5.1.1 Nominal size 6mm 0.00 t 0.00
2G1.5.1.2 Nominal size 8mm 0.00 t 0.00

Ni2Gerian Institute of Quantity Surveyors To Collection N 0.00

Page 27
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES

Qty Unit Rate N K

CONCRETE ANCILLARIES continued ...


Reinforcement continued ...
Reinforcing bars of other stated material continued ...
2G1.5.1.3 Nominal size 10mm 0.00 t 0.00
2G1.5.1.4 Nominal size 12mm 0.00 t 0.00
2G1.5.1.5 Nominal size 16mm 0.00 t 0.00
2G1.5.1.6 Nominal size 20mm 0.00 t 0.00
2G1.5.1.7 Nominal size 25mm 0.00 t 0.00
2G1.5.1.8 Nominal size 32mm or greater 0.00 t 0.00
2G1.5.5 Special joints 0 nr 0.00
2G1.5.6 Steel fabric to BS 4483
2G1.5.7 Fabric of other stated material
2G1.5.7.1 Nominal mass not exceeding 2kg/m2 0 m2 0.00
2G1.5.7.2 Nominal mass 2-3kg/m2 0 m2 0.00
2G1.5.7.3 Nominal mass 3-4kg/m2 0 m2 0.00
2G1.5.7.4 Nominal mass 4-5kg/m2 0 m2 0.00
2G1.5.7.5 Nominal mass 5-6kg/m2 0 m2 0.00
2G1.5.7.6 Nominal mass 6-7kg/m2 0 m2 0.00
2G1.5.7.7 Nominal mass 7-8kg/m2 0 m2 0.00
2G1.5.7.8 Nominal mass stated exceeding 8kg/m2 0 m2 0.00
2G1.6 Joints
2G1.6.1 Open surface plain
2G1.6.2 Open surface with filler
2G1.6.3 Formed surface plain
2G1.6.4 Formed surface with filler
2G1.6.4.1 Width not exceeding 0.5m 0 m2 0.00
2G1.6.4.2 Width 0.5-1m 0 m2 0.00
2G1.6.4.3 Width stated exceeding 1m 0 m2 0.00
2G1.6.5 Plastics or rubber waterstops
2G1.6.6 Metal waterstops
2G1.6.6.1 Average width not exceeding 150mm 0m 0.00
2G1.6.6.2 Average width 150-200mm 0m 0.00
2G1.6.6.3 Average width 200-300mm 0m 0.00
2G1.6.6.4 Average width stated exceeding 300mm 0m 0.00
2G1.6.7 Sealed rebates or grooves 0m 0.00
2G1.6.8 Dowels
2G1.6.8.1 Plain or greased 0 nr 0.00
2G1.6.8.2 Sleeved or capped 0 nr 0.00

Ni2Gerian Institute of Quantity Surveyors To Collection N 0.00

Page 28
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES

Qty Unit Rate N K

CONCRETE ANCILLARIES continued ...


2G1.7 Post-tensioned prestressing
2G1.7.1 Horizontal internal tendons in-situ concrete
2G1.7.2 Inclined or vertical internal tendons in in situ concrete
2G1.7.3 Horizontal internal tendons in precast concrete
Inclined or vertical internal tendons in precaste
2G1.7.4 concrete
2G1.7.4.1 Length not exceeding 5m 0 nr 0.00
2G1.7.4.2 Length 5-7m 0 nr 0.00
2G1.7.4.3 Length 7-10m 0 nr 0.00
2G1.7.4.4 Length 10-15m 0 nr 0.00
2G1.7.4.5 Length 15-20m 0 nr 0.00
2G1.7.4.6 Length 20-25m 0 nr 0.00
2G1.7.4.7 Length 25-30m 0 nr 0.00
2G1.7.4.8 Length stated exceeding 30m 0 nr 0.00
2G1.7.5 External jacking operations 0 nr 0.00
2G1.8 Concrete accessories
2G1.8.1 Finishing of top surfaces
2G1.8.1.1 Wood float 0 m2 0.00
2G1.8.1.2 Steel trowel 0 m2 0.00
2G1.8.1.3 Other stated surface treatment 0 m2 0.00
2G1.8.1.4 Granolithic finish 0 m2 0.00
2G1.8.1.5 Other stated applied finish 0 m2 0.00
2G1.8.2 Finishing of formed surfaces
2G1.8.2.1 Aggregate exposure using retarder 0 m2 0.00
2G1.8.2.2 Bush hammering 0 m2 0.00
Other stated surface treatment carried out after
2G1.8.2.3 striking formwork 0 m2 0.00

2G1.8.3 Inserts
2G1.8.3.1 Linear inserts 0m 0.00
2G1.8.3.2 Other inserts 0 nr 0.00
2G1.8.4 Grouting under plates
2G1.8.4.1 Area not exceeding 0.1m2 0 nr 0.00
2G1.8.4.2 Area 0.1-0.5m2 0 nr 0.00
2G1.8.4.3 Area 0.5-1m2 0 nr 0.00
2G1.8.4.4 Area stated exceeding 1m2 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 29
BESMM4 CIVIL WORK SECTIONS CONCRETE ANCILLARIES

Qty Unit Rate N K

Collection

Total from Page 26 N 0.00

Total from Page 27 N 0.00

Total from Page 28 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 30
BESMM4 CIVIL WORK SECTIONS PRECAST CONCRETE

Qty Unit Rate N K

2H PRECAST CONCRETE
2H1.1 Beams
2H1.2 Prestressed pre-tensioned beams
2H1.3 Prestressed post-tensioned beams
2H1.4 Columns
2H1.1.1 Length not exceeding 5m
2H1.1.2 Length 5-7m
2H1.1.3 Length 7-10m
2H1.1.4 Length 10-15m
2H1.1.5 Length 15-20m
2H1.1.6 Length 20-30m
2H1.1.7 Length exceeding 30m
2H1.1.1.1 Mass not exceeding 250kg 0 nr 0.00
2H1.1.1.2 Mass 250-500kg 0 nr 0.00
2H1.1.1.3 Mass 500kg-1t 0 nr 0.00
2H1.1.1.4 Mass 1-2t 0 nr 0.00
2H1.1.1.5 Mass 2-5t 0 nr 0.00
2H1.1.1.6 Mass 5-10t 0 nr 0.00
2H1.1.1.7 Mass 10-20t 0 nr 0.00
2H1.1.1.8 Mass stated exceeding 20t 0 nr 0.00
2H1.5 Slabs
2H1.5.1 Area not exceeding 1m2
2H1.5.2 Area 1-4m2
2H1.5.3 Area 4-15m2
2H1.5.4 Area 15-50m2
2H1.5.5 Area exceeding 50m2
2H1.5.1.1 Mass not exceeding 250kg 0 nr 0.00
2H1.5.1.2 Mass 250-500kg 0 nr 0.00
2H1.5.1.3 Mass 500kg-1t 0 nr 0.00
2H1.5.1.4 Mass 1-2t 0 nr 0.00
2H1.5.1.5 Mass 2-5t 0 nr 0.00
2H1.5.1.6 Mass 5-10t 0 nr 0.00
2H1.5.1.7 Mass 10-20t 0 nr 0.00
2H1.5.1.8 Mass stated exceeding 20t 0 nr 0.00
2H1.6 Segmental units
2H1.6.1 Generally
2H1.6.1.1 Mass not exceeding 250kg 0 nr 0.00
2H1.6.1.2 Mass 250-500kg 0 nr 0.00
2H1.6.1.3 Mass 500kg-1t 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 31
BESMM4 CIVIL WORK SECTIONS PRECAST CONCRETE

Qty Unit Rate N K

PRECAST CONCRETE continued ...


Segmental units continued ...
Generally continued ...
2H1.6.1.4 Mass 1-2t 0 nr 0.00
2H1.6.1.5 Mass 2-5t 0 nr 0.00
2H1.6.1.6 Mass 5-10t 0 nr 0.00
2H1.6.1.7 Mass 10-20t 0 nr 0.00
2H1.6.1.8 Mass stated exceeding 20t 0 nr 0.00
Units for subways, culverts
2H1.7 and ducts 0m 0.00
2H1.8 Copings, sills and weir blocks
2H1.8.1 Cross-sectional area not exceeding 0.1m2 0m 0.00
2H1.8.2 Cross-sectional area 0.1m2 0m 0.00
2H1.8.3 Cross-sectional area 0.1-0.5m2 0m 0.00
2H1.8.4 Cross-sectional area 0.5-1m2 0m 0.00
2H1.8.5 Cross-sectional area exceeding 1m2 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 32
BESMM4 CIVIL WORK SECTIONS PRECAST CONCRETE

Qty Unit Rate N K

Collection

Total from Page 30 N 0.00

Total from Page 31 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 33
BESMM4 CIVIL WORK SECTIONS PIPEWORK - PIPES

Qty Unit Rate N K

2J PIPEWORK - PIPES
2J1.1 Clay pipes
2J1.2 Concrete pipes
2J1.3 Iron pipes
2J1.4 Steel pipes
2J1.5 Polyvinyl chloride pipes
2J1.6 Glass reinforced plastic pipes
2J1.7 High density polyethylene pipes
2J1.8 Medium density polyethylene pipes
2J1.2.1 Nominal bore not exceeding 200mm
2J1.2.2 Nominal bore 200-300mm
2J1.2.3 Nominal bore 300-600mm
2J1.2.4 Nominal bore 600-900mm
2J1.2.5 Nominal bore 900-1200mm
2J1.2.6 Nominal bore 1200-1500mm
2J1.2.7 Nominal bore 1500-1800mm
2J1.2.8 Nominal bore exceeding 1800mm
2J1.2.1.1 Not in trenches 0m 0.00
2J1.2.1.2 In trenches, depth not exceeding 1.5m 0m 0.00
2J1.2.1.3 In trenches, depth 1.5-2m 0m 0.00
2J1.2.1.4 In trenches, depth 2-2.5m 0m 0.00
2J1.2.1.5 In trenches, depth 2.5-3m 0m 0.00
2J1.2.1.6 In trenches, depth 3-3.5m 0m 0.00
2J1.2.1.7 In trenches, depth 3.5-4m 0m 0.00
2J1.2.1.8 In trenches, depth exceeding 4m 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 34
BESMM4 CIVIL WORK SECTIONS PIPEWORK - PIPES

Qty Unit Rate N K

Collection

Total from Page 33 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 35
BESMM4 CIVIL WORK SECTIONS PIPEWORK - FITTINGS & VALVES

Qty Unit Rate N K

2K PIPEWORK - FITTINGS AND VALVES


2K1.1 Clay pipe fittings
2K1.2 Concrete pipe fittings
2K1.3 Iron or steel pipe fittings
2K1.4 Polyvinyl chloride pipe fittings
2K1.5 Glass reinforced plastic pipe fittings
2K1.6 High density polyethylene pipe fittings
2K1.7 Medium density polyethylene pipe fittings
2K1.1.1 Bends
2K1.1.2 Junctions and branches
2K1.1.3 Tapers
2K1.1.4 Double collars
2K1.1.5 Adaptors
2K1.1.6 Glands
2K1.1.7 Bellmouths
2K1.1.8 Straight specials
2K1.1.1.1 Nominal bore not exceeding 200mm 0 nr 0.00
2K1.1.1.2 Nominal bore 200-300mm 0 nr 0.00
2K1.1.1.3 Nominal bore 300-600mm 0 nr 0.00
2K1.1.1.4 Nominal bore 600-900mm 0 nr 0.00
2K1.1.1.5 Nominal bore 900-1200mm 0 nr 0.00
2K1.1.1.6 Nominal bore 1200-1500mm 0 nr 0.00
2K1.1.1.7 Nominal bore 1500-1800mm 0 nr 0.00
2K1.1.1.8 Nominal bore exceeding 1800mm 0 nr 0.00
2K1.8 Valves and penstocks
2K1.8.1 Gate valves: hand operated
2K1.8.2 Gate valves: power operated
2K1.8.3 Non-return valves
2K1.8.4 Butterfly valves: hand operated
2K1.8.5 Butterfly valves: power operated
2K1.8.6 Air valves
2K1.8.7 Pressure reducing valves
2K1.8.8 Penstocks
2K1.8.1.1 Nominal bore not exceeding 200mm 0 nr 0.00
2K1.8.1.2 Nominal bore 200-300mm 0 nr 0.00
2K1.8.1.3 Nominal bore 300-600mm 0 nr 0.00
2K1.8.1.4 Nominal bore 600-900mm 0 nr 0.00
2K1.8.1.5 Nominal bore 900-1200mm 0 nr 0.00
2K1.8.1.6 Nominal bore 1200-1500mm 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 36
BESMM4 CIVIL WOR2K SECTIONS PIPEWORK - FITTINGS & VALVES

Qty Unit Rate N K

PIPEWORK - FITTINGS AND VALVES continued ...


Valves and penstocks continued ...
Penstocks continued ...
2K1.8.1.7 Nominal bore 1500-1800mm 0 nr 0.00
2K1.8.1.8 Nominal bore exceeding 1800mm 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 37
BESMM4 CIVIL WORK SECTIONS PIPEWORK - FITTINGS & VALVES

Qty Unit Rate N K

Collection

Total from Page 35 N 0.00

Total from Page 36 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 38
BESMM4 CIVIL WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S

Qty Unit Rate N K

PIPEWORK-MANHOLES AND PIPEWORK


2L ANCILLARIES
2L1.1 Manholes
2L1.1.1 Brick
2L1.1.2 Brick with backdrop
2L1.1.3 In-situ concrete
2L1.1.4 In-situ concrete with backdrop
2L1.1.5 Precast concrete
2L1.1.6 Precast concrete with backdrop
2L1.1.1.1 Depth not exceeding 1.5m 0 nr 0.00
2L1.1.1.2 Depth 1.5-2m 0 nr 0.00
2L1.1.1.3 Depth 2-2.5m 0 nr 0.00
2L1.1.1.4 Depth 2.5-3m 0 nr 0.00
2L1.1.1.5 Depth 3-3.5m 0 nr 0.00
2L1.1.1.6 Depth 3.5-4m 0 nr 0.00
2L1.1.1.7 Depth 3.5-4m 0 nr 0.00
2L1.2 Other stated chambers
2L1.2.1 Brick
2L1.2.2 In-situ concrete
2L1.2.3 Precast concrete
2L1.2.1.1 Depth not exceeding 1.5m 0 nr 0.00
2L1.2.1.2 Depth 1.5-2m 0 nr 0.00
2L1.2.1.3 Depth 2-2.5m 0 nr 0.00
2L1.2.1.4 Depth 2.5-3m 0 nr 0.00
2L1.2.1.5 Depth 3-3.5m 0 nr 0.00
2L1.2.1.6 Depth 3.5-4m 0 nr 0.00
2L1.2.1.7 Depth stated exceeding 4m 0 nr 0.00
2L1.3 Gullies
2L1.3.1 Clay 0 nr 0.00
2L1.3.2 Clay trapped 0 nr 0.00
2L1.3.3 In-situ concrete
2L1.3.4 In-situ concrete trapped 0 nr 0.00
2L1.3.5 Precast concrete
2L1.3.6 Precast concrete trapped 0 nr 0.00
2L1.3.7 Plastics 0 nr 0.00
2L1.3.8 Plastics trapped 0 nr 0.00
2L1.4 French drains, rubble drains, ditches and trenches
2L1.4.1 Filling French and rubble drains with graded material 0 m3 0.00
2L1.4.2 Filling French and rubble drains with rubble 0 m3 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 39
BESMM4 CIVI2L WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S

Qty Unit Rate N K

PIPEWORK-MANHOLES AND PIPEWORK


ANCILLARIES continued ...
French drains, rubble drains, ditches continued ...
2L1.4.3 Trenches for unpiped rubble drains
2L1.4.4 Rectangular section ditches: unlined
2L1.4.5 Rectangular section ditches: lined
2L1.4.6 Vee section ditches: unlined
2L1.4.7 Vee section ditches: lined

2L1.4.8 Trenches for pipes or cables not to be laid by the


Contractor
2L1.4.8.1 Cross-sectional area not exceeding 0.25m2 0m 0.00
2L1.4.8.2 Cross-sectional area 0.25-0.5m2 0m 0.00
2L1.4.8.3 Cross-sectional area 0.5-0.75m2 0m 0.00
2L1.4.8.4 Cross-sectional area 0.75-1m2 0m 0.00
2L1.4.8.5 Cross-sectional area 1-1.5m2 0m 0.00
2L1.4.8.6 Cross-sectional area 1.5-2m2 0m 0.00
2L1.4.8.7 Cross-sectional area 2-3m2 0m 0.00
2L1.4.8.8 Cross-sectional area stated exceeding 3m 0m 0.00
2L1.5 Ducts and metal culverts
2L1.5.1 Cable ducts: 1 way
2L1.5.2 Cable ducts: 2 way
2L1.5.3 Cable ducts: 3 way
2L1.5.4 Cable ducts: stated number of ways exceeding 3
Sectional corrugated metal culverts, nominal internal
2L1.5.5 diameter not exceeding 0.5m
Sectional corrugated metal culverts, nominal internal
2L1.5.6 diameter not exceeding 0.5 - 1m
Sectional corrugated metal culverts, nominal internal
2L1.5.7 diameter not exceeding 1 - 1.5m
Sectional corrugated metal culverts, nominal internal
2L1.5.8 diameter exceeding 1.5m
2L1.5.8.1 Not in trenches 0m 0.00
2L1.5.8.2 In trenches, depth not exceeding 1.5m 0m 0.00
2L1.5.8.3 In trenches, depth 1.5-2m 0m 0.00
2L1.5.8.4 In trenches, depth 2-2.5m 0m 0.00
2L1.5.8.5 In trenches, depth 2.5-3m 0m 0.00
2L1.5.8.6 In trenches, depth 3-3.5m 0m 0.00
2L1.5.8.7 In trenches, depth 3.5-4m 0m 0.00
2L1.5.8.8 In trenches, depth statedexceeding 4m 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 40
BESMM4 CIVI2L WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S

Qty Unit Rate N K

PIPEWORK-MANHOLES AND PIPEWORK


ANCILLARIES continued ...
2L1.6 Crossings
2L1.6.1 River, stream or canal width 1-3m
2L1.6.2 River, stream or canal width 3-10m
2L1.6.3 River, stream or canal stated exceeding 10m
2L1.6.4 Hedge
2L1.6.5 Wall
2L1.6.6 Fence
2L1.6.7 Sewer or drain
2L1.6.8 Other stated underground service
2L1.6.8.1 Pipe bore not exceeding 300mm 0 nr 0.00
2L1.6.8.2 Pipe bore 300-900mm 0 nr 0.00
2L1.6.8.3 Pipe bore 900-1800mm 0 nr 0.00
2L1.6.8.4 Pipe bore stated exceeding 1800mm 0 nr 0.00
2L1.7 Reinstatement
2L1.7.1 Breaking up and temporary reinstatement of roads
2L1.7.2 Breaking up and temporary reinstatement of footpaths
Breaking up, temporary and permanent reinstatement
2L1.7.3 of roads
Breaking up, temporary and permanent reinstatement
2L1.7.4 of footpaths
2L1.7.5 Reinstatement of land
2L1.7.5.1 Pipe bore not exceeding 300mm 0 nr 0.00
2L1.7.5.2 Pipe bore 300-900mm 0 nr 0.00
2L1.7.5.3 Pipe bore 900-1800mm 0 nr 0.00
2L1.7.5.4 Pipe bore stated exceeding 1800mm 0 nr 0.00
2L1.7.6 Strip topsoil from easement and reinstate 0m 0.00
2L1.8 Other pipework ancillaries
2L1.8.1 Reinstatement of field drains 0m 0.00
2L1.8.2 Marker posts 0 nr 0.00
2L1.8.3 Timber supports left in excavations 0 m2 0.00
2L1.8.4 Metal supports let in excavations 0 m2 0.00
Connections to existing manholes and other
2L1.8.5 chambers
2L1.8.6 Connections to existing pipes, ducts and culverts
2L1.8.6.1 Pipe bore not exceeding 200mm 0 nr 0.00
2L1.8.6.2 Pipe bore 200-300mm 0 nr 0.00
2L1.8.6.3 Pipe bore 300-600mm 0 nr 0.00
2L1.8.6.4 Pipe bore 600-900mm 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 41
BESMM4 CIVI2L WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S

Qty Unit Rate N K

PIPEWORK-MANHOLES AND PIPEWORK


ANCILLARIES continued ...
Other pipework ancillaries continued ...
Connections to existing pipes, ducts continued ...
2L1.8.6.5 Pipe bore 900-1200mm 0 nr 0.00
2L1.8.6.6 Pipe bore 1200-1500mm 0 nr 0.00
2L1.8.6.7 Pipe bore 1500-1800mm 0 nr 0.00
2L1.8.6.8 Pipe bore stated exceeding 1800mm 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 42
BESMM4 CIVIL WORK SECTIONS PIPEWORK - MANHOLES & PIPEWORK ANC'S

Qty Unit Rate N K

Collection

Total from Page 38 N 0.00

Total from Page 39 N 0.00

Total from Page 40 N 0.00

Total from Page 41 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 43
BESMM4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...

Qty Unit Rate N K

PIPEWORK - SUPPORTS AND PROTECTION,


2M ANCILLARIES TO LAYING AND EXCAVATION
2M1.1 Extras to excavation and backfilling
2M1.1.1 In pipe trenches
2M1.1.2 In manholes and other chambers
2M1.1.3 In headings
2M1.1.4 In thrust boring
2M1.1.5 In pipe jacking
2M1.1.1.1 Excavation of rock 0 m3 0.00
2M1.1.1.2 Excavation of mass concrete 0 m3 0.00
2M1.1.1.3 Excavation of reinforced concrete 0 m3 0.00
2M1.1.1.4 Excavation of other artifical hard material 0 m3 0.00
2M1.1.1.5 Backfilling above the Final Surface with concrete 0 m3 0.00
Backfilling above the Final Surface with stated
2M1.1.1.6 material other than concrete 0 m3 0.00
Excavation of natural material below the Final
2M1.1.1.7 Surface and backfilling with concrete 0 m3 0.00

Excavation of natural material below the Final


Surface and backfilling with stated material other
2M1.1.1.8 than concrete 0 m3 0.00
2M1.2 Special pipe laying methods
2M1.2.1 In headings
2M1.2.2 Thrust boring
2M1.2.3 Pipe jacking
2M1.2.3.1 Nominal bore not exceeding 200mm 0m 0.00
2M1.2.3.2 Nominal bore 200-300mm 0m 0.00
2M1.2.3.3 Nominal bore 300-600mm 0m 0.00
2M1.2.3.4 Nominal bore 600-900mm 0m 0.00
2M1.2.3.5 Nominal bore 900-1200mm 0m 0.00
2M1.2.3.6 Nominal bore 1200-1500mm 0m 0.00
2M1.2.3.7 Nominal bore 1500-1800mm 0m 0.00
2M1.2.3.8 Nominal bore stated exceeding1800mm 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 44
BES2M2M4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...

Qty Unit Rate N K

PIPEWORK - SUPPORTS AND PROTECTION,


ANCILLARIES TO LAYING AND continued ...
2M1.3 Beds
2M1.4 Haunches
2M1.5 Surrounds
2M1.5.1 Sand
2M1.5.2 Selected excavated granular material
2M1.5.3 Imported granular material
2M1.5.4 Mass concrete
2M1.5.5 Reinforced concrete
2M1.5.5.1 Nominal bore not exceeding 200 mm 0m 0.00
2M1.5.5.2 Nominal bore 200-300 mm 0m 0.00
2M1.5.5.3 Nominal bore 300-600 mm 0m 0.00
2M1.5.5.4 Nominal bore 600-900 mm 0m 0.00
2M1.5.5.5 Nominal bore 900-1200 mm 0m 0.00
2M1.5.5.6 Nominal bore 1200-1500 mm 0m 0.00
2M1.5.5.7 Nominal bore 1500-1800 mm 0m 0.00
2M1.5.5.8 Nominal bore stated exceeding 1800 mm 0m 0.00
2M1.6 Wrapping and lagging
2M1.6.1 Generally
2M1.6.1.1 Nominal bore not exceeding 200 mm 0m 0.00
2M1.6.1.2 Nominal bore 200-300 mm 0m 0.00
2M1.6.1.3 Nominal bore 300-600 mm 0m 0.00
2M1.6.1.4 Nominal bore 600-900 mm 0m 0.00
2M1.6.1.5 Nominal bore 900-1200 mm 0m 0.00
2M1.6.1.6 Nominal bore 1200-1500 mm 0m 0.00
2M1.6.1.7 Nominal bore 1500-1800 mm 0m 0.00
2M1.6.1.8 Nominal bore stated exceeding 1800 mm 0m 0.00
2M1.7 Concrete stools and thrust blocks
2M1.7.1 Volume not exceeding 0.1m3
2M1.7.2 Volume 0.1-0.2m3
2M1.7.3 Volume 0.2-0.5m3
2M1.7.4 Volume 0.5-1m3
2M1.7.5 Volume 1-2m3
2M1.7.6 Volume 2-4m3
2M1.7.7 Volume 4-6m3
2M1.7.8 Volume stated exceeding 6m3
2M1.7.8.1 Nominal bore not exceeding 200 mm 0m 0.00
2M1.7.8.2 Nominal bore 200-300 mm 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 45
BES2M2M4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...

Qty Unit Rate N K

PIPEWORK - SUPPORTS AND PROTECTION,


ANCILLARIES TO LAYING AND continued ...
Concrete stools and thrust blocks continued ...
Volume stated exceeding 6m3 continued ...
2M1.7.8.3 Nominal bore 300-600 mm 0m 0.00
2M1.7.8.4 Nominal bore 600-900 mm 0m 0.00
2M1.7.8.5 Nominal bore 900-1200 mm 0m 0.00
2M1.7.8.6 Nominal bore 1200-1500 mm 0m 0.00
2M1.7.8.7 Nominal bore 1500-1800 mm 0m 0.00
2M1.7.8.8 Nominal bore stated exceeding 1800 mm 0m 0.00
2M1.8 Other isolated pipe supports
2M1.8.1 Height not exceeding 1m
2M1.8.2 Height 1-1.5m
2M1.8.3 Height 1.5-2m
2M1.8.4 Height 2-3m
2M1.8.5 Height 3-4m
2M1.8.6 Height 4-5m
2M1.8.7 Height 5-6m
2M1.8.8 Height stated exceeding 6m
2M1.8.1.1 Nominal bore not exceeding 200 mm 0m 0.00
2M1.8.1.2 Nominal bore 200-300 mm 0m 0.00
2M1.8.1.3 Nominal bore 300-600 mm 0m 0.00
2M1.8.1.4 Nominal bore 900-1200 mm 0m 0.00
2M1.8.1.5 Nominal bore 1200-1500 mm 0m 0.00
2M1.8.1.6 Nominal bore 1500-1800 mm 0m 0.00
2M1.8.1.7 Nominal bore stated exceeding 1800 mm 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 46
BESMM4 CIVIL WORK SECTIONS PIPEWORK - SUPPORTS & PROTECTION, ...

Qty Unit Rate N K

Collection

Total from Page 43 N 0.00

Total from Page 44 N 0.00

Total from Page 45 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 47
BESMM4 CIVIL WORK SECTIONS STRUCTURAL METALWORK

Qty Unit Rate N K

2N STRUCTURAL METALWORK
2N1.1 Fabrication of main members for bridges
2N1.1.1 Rolled sections
2N1.1.2 Plates or flats
2N1.1.3 Built-up box or hollow sections
2N1.1.3.1 Straight on plan 0.00 t 0.00
2N1.1.3.2 Curved on plan 0.00 t 0.00
2N1.1.3.3 Straight on plan and cambered 0.00 t 0.00
2N1.1.3.4 Curved on plan and cambered 0.00 t 0.00
2N1.2 Fabrication of subsidiary members for bridges
2N1.2.1 Deck panels
2N1.2.1.1 Straight on plan 0.00 t 0.00
2N1.2.1.2 Curved on plan 0.00 t 0.00
2N1.2.1.3 Straight on plan and cambered 0.00 t 0.00
2N1.2.1.4 Curved on plan and cambered 0.00 t 0.00
2N1.2.2 Bracings 0.00 t 0.00
2N1.2.3 External diaphragms 0.00 t 0.00
2N1.3 Fabrication of members for frames
2N1.4 Fabrication of other members
2N1.4.1 Columns
2N1.4.2 Beams
2N1.4.3 Portal frames
2N1.4.4 Trestles, towers and built-up columns
2N1.4.5 Trusses and built-up girders
2N1.4.6 Bracings, purlins and cladding rails
2N1.4.6.1 Straight on plan 0.00 t 0.00
2N1.4.6.2 Curved on plan 0.00 t 0.00
2N1.4.6.3 Straight on plan and cambered 0.00 t 0.00
2N1.4.6.4 Curved on plan and cambered 0.00 t 0.00
2N1.4.7 Grillages 0.00 t 0.00
2N1.4.8 Anchorages and holding down bolt assemblies 0 nr 0.00
2N1.5 Erection of members for bridges
2N1.6 Erection of members for frames
2N1.7 Erection of other members
2N1.7.1 Trial erection 0.00 t 0.00
2N1.7.2 Permanent erection 0.00 t 0.00

2Nigeria2N I2Nstitute of Qua2Ntity Surveyors To Collection N 0.00

Page 48
BESMM4 CIVIL WORK SECTIO2NS STRUCTURAL METALWORK

Qty Unit Rate N K

STRUCTURAL METALWORK continued ...


Erection of other members continued ...
2N1.7.3 Sites bolts black
2N1.7.4 Site bolts HSFG general grade
2N1.7.5 Site bolts HSFG higher grade
Site bolts HSFG load indicating or load limit types,
2N1.7.6 general grade
Site bolts HSFG load indicating or load limit types,
2N1.7.7 higher grade
2N1.7.7.1 Diameter not exceeding 16mm 0 nr 0.00
2N1.7.7.2 Diameter 16-20 mm 0 nr 0.00
2N1.7.7.3 Diameter 20-24 mm 0 nr 0.00
2N1.7.7.4 Diameter 24-30 mm 0 nr 0.00
2N1.7.7.5 Diameter 30-36 mm 0 nr 0.00
2N1.7.7.6 Diameter 36-42 mm 0 nr 0.00
2N1.7.7.7 Diameter stated exceeding 42mm 0 nr 0.00
2N1.8 Off Site surface treatment
2N1.8.1 Blast cleaning 0 m3 0.00
2N1.8.2 Pickling 0 m3 0.00
2N1.8.3 Flame cleaning 0 m3 0.00
2N1.8.4 Wire brushing 0 m3 0.00
2N1.8.5 Metal spraying 0 m3 0.00
2N1.8.6 Galvanising 0 m3 0.00
2N1.8.7 Painting 0 m3 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 49
BESMM4 CIVIL WORK SECTIONS STRUCTURAL METALWORK

Qty Unit Rate N K

Collection

Total from Page 47 N 0.00

Total from Page 48 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 50
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS METALWORK

Qty Unit Rate N K

2P MISCELLANEOUS METALWORK

2P1.1.1 Stairways and landings 0.00 t 0.00


2P1.1.2 Walkways and platforms 0.00 t 0.00
2P1.1.3 Ladders 0m 0.00
2P1.1.4 Handrails 0m 0.00
2P1.1.5 Bridge parapets 0m 0.00
2P1.1.6 Plate flooring 0 m2 0.00
2P1.1.7 Open grid flooring 0 m2 0.00

2P1.2.1 Cladding 0 m2 0.00


2P1.2.2 Welded mesh panelling 0 m2 0.00
2P1.2.3 Duct covers 0 m2 0.00
2P1.2.4 Tie rods 0 nr 0.00
2P1.2.5 Walings 0m 0.00
2P1.2.6 Bridge bearings
2P1.2.6.1 Roller 0 nr 0.00
2P1.2.6.2 Slide 0 nr 0.00
2P1.2.6.3 Rocker 0 nr 0.00
2P1.2.6.4 Cylindrical 0 nr 0.00
2P1.2.6.5 Spherical 0 nr 0.00
2P1.2.6.6 Elastomeric 0 nr 0.00
2P1.2.6.7 Rubber pot 0 nr 0.00
2P1.2.6.8 Proprietary 0 nr 0.00
2P1.2.7 Uncovered tanks
2P1.2.8 Covered tanks
2P1.2.8.1 Volume not exceeding 1m3 0 nr 0.00
2P1.2.8.2 Volume 1-3m3 0 nr 0.00
2P1.2.8.3 Volume 3-10m3 0 nr 0.00
2P1.2.8.4 Volume 19-30m3 0 nr 0.00
2P1.2.8.5 Volume 30-100m3 0 nr 0.00
2P1.2.8.6 Volume 100-300m3 0 nr 0.00
2P1.2.8.7 Volume 300-1000m3 0 nr 0.00
2P1.2.8.8 Volume stated exceeding 1000m3 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 51
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS METALWORK

Qty Unit Rate N K

Collection

Total from Page 50 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 52
BESMM4 CIVIL WORK SECTIONS TIMBER

Qty Unit Rate N K

2Q TIMBER
2Q1.1 Hardwood components
2Q1.2 Softwood components
2Q1.1.1 Cross-sectional area not exceeding 0.01m2
2Q1.1.2 Cross-sectional area 0.01-0.02m2
2Q1.1.3 Cross-sectional area 0.02-0.04m2
2Q1.1.4 Cross-sectional area 0.04-0.1m2
2Q1.1.5 Cross-sectional area 0.1-0.2m2
2Q1.1.6 Cross-sectional area 0.2-0.4m2
2Q1.1.7 Cross-sectional area stated exceeding 0.4m2
2Q1.1.7.1 Length not exceeding 1.5m 0m 0.00
2Q1.1.7.2 Length 1.5-3m 0m 0.00
2Q1.1.7.3 Length 3-5m 0m 0.00
2Q1.1.7.4 Length 5-8m 0m 0.00
2Q1.1.7.5 Length 8-12m 0m 0.00
2Q1.1.7.6 Length 12-20m 0m 0.00
2Q1.1.7.7 Length stated exceeding 20m 0m 0.00
2Q1.3 Hardwood decking
2Q1.4 Softwood decking
2Q1.4.1 Thickness not exceeding 25 mm 0 m2 0.00
2Q1.4.2 Thickness 25-50 mm 0 m2 0.00
2Q1.4.3 Thickness 50-75 mm 0 m2 0.00
2Q1.4.4 Thickness 75-100 mm 0 m2 0.00
2Q1.4.5 Thickness 100-125 mm 0 m2 0.00
2Q1.4.6 Thickness 125-150 mm 0 m2 0.00
2Q1.4.7 Thickness exceeding 150 mm 0 m2 0.00
2Q1.5 Fittings and fastenings
2Q1.5.1 Straps 0 nr 0.00
2Q1.5.2 Spikes 0 nr 0.00
2Q1.5.3 Coach screws 0 nr 0.00
2Q1.5.4 Bolts 0 nr 0.00
2Q1.5.5 Plates 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 53
BESMM4 CIVIL WORK SECTIONS TIMBER

Qty Unit Rate N K

Collection

Total from Page 52 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 54
BESMM4 CIVIL WORK SECTIONS PILES

Qty Unit Rate N K

2R PILES
2R1.1 Bored cast in place concrete piles
2R1.2 Driven cast in place concrete piles
2R1.1.1 Diameter 300mm or 350mm
2R1.1.2 Diameter 400mm or 450mm
2R1.1.3 Diameter 500mm or 550mm
2R1.1.4 Diameter 600mm or 750mm
2R1.1.5 Diameter 900mm or 1050mm
2R1.1.6 Diameter 1200mm or 1350mm
2R1.1.7 Diameter 1500mm
2R1.1.1.1 Number of piles 0 nr 0.00
2R1.1.1.2 Concreted length 0m 0.00
2R1.1.1.3 Depth bored or driven to stated maximum depth 0m 0.00
2R1.3 Preformed concrete piles
2R1.4 Preformed concrete sheet piles
2R1.5 Timber piles
2R1.5.1 Cross-sectional area not exceeding 0.025m2
2R1.5.2 Cross-sectional area 0.025-0.05m2
2R1.5.3 Cross-sectional area 0.05-0.1m2
2R1.5.4 Cross-sectional area 0.5-0.15m2
2R1.5.5 Cross-sectional area 0.15-0.25m2
2R1.5.6 Cross-sectional area 0.25-0.5m2
2R1.5.7 Cross-sectional area 0.5-1m2
2R1.5.8 Cross-sectional area exceeding 1m2
2R1.5.8.1 Number of piles of stated length 0 nr 0.00
2R1.5.8.2 Depth driven 0m 0.00
2R1.6 Isolated steel piles
2R1.6.1 Mass not exceeding 15kg/m
2R1.6.2 Mass 15-30kg/m
2R1.6.3 Mass 30-60kg/m
2R1.6.4 Mass 60-120kg/m
2R1.6.5 Mass 120-250kg/m
2R1.6.6 Mass 250-500kg/m
2R1.6.7 Mass 500 kg/m-1t/m
2R1.6.8 Mass exceeding 1t/m
2R1.6.8.1 Number of piles of stated length 0 nr 0.00
2R1.6.8.2 Depth driven 0m 0.00

Nige2Rian Institute of Quantity Su2Rveyo2Rs To Collection N 0.00

Page 55
BESMM4 CIVIL WO2RK SECTIONS PILES

Qty Unit Rate N K

PILES continued ...


2R1.7 Interlocking steel piles
2R1.7.1 Section modulus not exceeding500cm3/m
2R1.7.2 Section modulus 500-800cm3/m
2R1.7.3 Section modulus 800-1200cm3/m
2R1.7.4 Section modulus 1200-2000cm3/m
2R1.7.5 Section modulus 2000-3000cm3/m
2R1.7.6 Section modulus 3000-4000cm3/m
2R1.7.7 Section modulus 4000-5000cm3/m
2R1.7.8 Section modulus exceeding 5000cm3/m
2R1.7.8.1 Length of special piles 0m 0.00
2R1.7.8.2 Driven area 0 m2 0.00
2R1.7.8.3 Area of piles of length notexceeding 14m 0 m2 0.00
2R1.7.8.4 Area of piles of length 14-24m 0 m2 0.00
2R1.7.8.5 Area of piles of length exceeding24m 0 m2 0.00
2R1.8 Stone Columns
2R1.8.1 Diameter: not exceeding 300mm
2R1.8.2 Diameter: 300-450mm
2R1.8.3 Diameter 450-600mm
2R1.8.4 Diameter: 600-750mm
2R1.8.5 Diameter: 750-900mm
2R1.8.6 Diameter: 900-1050mm
2R1.8.7 Diameter 1050-1200mm
2R1.8.8 Exceeding 1200mm
2R1.8.8.1 Number of columns 0 nr 0.00
2R1.8.8.2 Length of Columns 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 56
BESMM4 CIVIL WORK SECTIONS PILES

Qty Unit Rate N K

Collection

Total from Page 54 N 0.00

Total from Page 55 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 57
BESMM4 CIVIL WORK SECTIONS PILING ANCILLARIES

Qty Unit Rate N K

2S PILING ANCILLARIES
2S1.1 Cast in place concrete piles
2S1.1.1 Pre-boring
2S1.1.2 Backfilling empty bore with stated material
2S1.1.3 Permanent casings each length not exceeding 13m
2S1.1.4 Permanent casings each length exceeding 13m
2S1.1.5 Enlarged bases
2S1.1.6 Cutting off surplus lengths
2S1.1.7 Preparing heads
2S1.1.7.1 Diameter 300mm or 350mm 0m 0.00
2S1.1.7.2 Diameter 400mm or 450mm 0m 0.00
2S1.1.7.3 Diameter 500mm or 550mm 0m 0.00
2S1.1.7.4 Diameter 600mm or 750mm 0m 0.00
2S1.1.7.5 Diameter 900mm or 1050mm 0m 0.00
2S1.1.7.6 Diameter 1200mm or 1350mm 0m 0.00
2S1.1.7.7 Diameter 1500mm 0m 0.00
2S1.2 Cast in place concrete piles
2S1.2.1 Reinforcement
2S1.2.1.1 Straight bars nominal size not exceeding 25mm 0.00 t 0.00
2S1.2.1.2 Straight bars nominal size exceeding 25mm 0.00 t 0.00
2S1.2.1.3 Helical bars of stated nominal size 0.00 t 0.00
2S1.3 Preformed concrete piles
2S1.4 Timber piles
2S1.4.1 Pre-boring
2S1.4.2 Jetting
2S1.4.3 Filling hollow piles with concrete
2S1.4.4 Number of pile extensions
Length of pile extensions each length not exceeding
2S1.4.5 3m
2S1.4.6 Length of pile extensions each length exceeding 3m
2S1.4.7 Cutting off surplus lengths
2S1.4.8 Preparing heads
2S1.4.8.1 Cross-sectional area not exceeding 0.025m2 0m 0.00
2S1.4.8.2 Cross-sectional area 0.025-0.05m2 0m 0.00
2S1.4.8.3 Cross-sectional area 0.05-0.1m2 0m 0.00
2S1.4.8.4 Cross-sectional area 0.1-0.15m2 0m 0.00
2S1.4.8.5 Cross-sectional area 0.15-0.25m2 0m 0.00
2S1.4.8.6 Cross-sectional area 0.25-0.5m2 0m 0.00
2S1.4.8.7 Cross-sectional area 0.5-1m2 0m 0.00

Nigerian In2Stitute of Quantity 2Surveyor2S To Collection N 0.00

Page 58
BE2SMM4 CIVIL WORK 2SECTION2S PILING ANCILLARIES

Qty Unit Rate N K

PILING ANCILLARIES continued ...


Timber piles continued ...
Preparing heads continued ...
2S1.4.8.8 Cross-sectional area stated exceeding 1m2 0m 0.00
2S1.5 Isolated steel plates
2S1.5.1 Pre-boring
2S1.5.2 Jetting
2S1.5.3 Filling hollow piles with concrete
2S1.5.4 Number of pile extensions
Length of pile extensions eachlength not exceeding
2S1.5.5 3m
2S1.5.6 Length of pile extensions each length exceeding 3m
2S1.5.7 Cutting off surplus lengths
2S1.5.8 Preparing heads
2S1.5.8.1 Mass not exceeding 15 kg/m 0m 0.00
2S1.5.8.2 Mass 15-30 kg/m 0m 0.00
2S1.5.8.3 Mass 30-60 kg/m 0m 0.00
2S1.5.8.4 Mass 60-120 kg/m 0m 0.00
2S1.5.8.5 Mass 120-250 kg/m 0m 0.00
2S1.5.8.6 Mass 250-500 kg/m 0m 0.00
2S1.5.8.7 Mass 500 kg/m - 1 t/m 0m 0.00
2S1.5.8.8 Mass stated exceeding 1 t/m 0m 0.00
2S1.6 Interlocking steel piles
2S1.6.1 Pre-boring
2S1.6.2 Jetting
2S1.6.3 Filling hollow piles with concrete

2S1.6.4 Number of pile extensions


Length of pile extensions each length not exceeding
2S1.6.5 3m
2S1.6.6 Length of pile extensions each length exceeding 3m
2S1.6.7 Cutting off surplus lengths
2S1.6.8 Preparing heads
2S1.6.8.1 Section modulus not exceeding 500 cm3/m 0m 0.00
2S1.6.8.2 Section modulus 500-800 cm3/m 0m 0.00
2S1.6.8.3 Section modulus 800-1200 cm3/m 0m 0.00
2S1.6.8.4 Section modulus 1200-2000 cm3/m 0m 0.00
2S1.6.8.5 Section modulus 2000-3000 cm3/m 0m 0.00
2S1.6.8.6 Section modulus 3000-4000 cm3/m 0m 0.00
2S1.6.8.7 Section modulus 4000-5000 cm3/m 0 nr 0.00

Nigerian In2Stitute of Quantity 2Surveyor2S To Collection N 0.00

Page 59
BE2SMM4 CIVIL WORK 2SECTION2S PILING ANCILLARIES

Qty Unit Rate N K

PILING ANCILLARIES continued ...


Interlocking steel piles continued ...
Preparing heads continued ...
2S1.6.8.8 Section modulus stated exceeding 5000 cm3/m 0m 0.00
2S1.7 Obstructions
2S1.8 Pile tests
2S1.8.1 Maintained loading with various reactions
2S1.8.2 Constant rate of penetration
2S1.8.3 Horizontal loading
2S1.8.3.1 Test load not exceeding 100 t 0 nr 0.00
2S1.8.3.2 Test load 100-200 t 0 nr 0.00
2S1.8.3.3 Test load 200-300 t 0 nr 0.00
2S1.8.3.4 Test load 300-400 t 0 nr 0.00
2S1.8.3.5 Test load 400-600 t 0 nr 0.00
2S1.8.3.6 Test load 600-800 t 0 nr 0.00
2S1.8.3.7 Test load 800-1000 t 0 nr 0.00
2S1.8.3.8 Test load exceeding 1000 t 0 nr 0.00
2S1.8.4 Non-destructive integrity 0 nr 0.00
2S1.8.5 Inclinometer installations 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 60
BESMM4 CIVIL WORK SECTIONS PILING ANCILLARIES

Qty Unit Rate N K

Collection

Total from Page 57 N 0.00

Total from Page 58 N 0.00

Total from Page 59 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 61
BESMM4 CIVIL WORK SECTIONS ROADS AND PAVINGS

Qty Unit Rate N K

2T ROADS AND PAVINGS


Unbound Sub-bases, flexible road bases and
2T1.1 surfacing
2T1.1.1 Type 1 unbound mixture
2T1.1.2 Type 2 unbound mixtures
2T1.1.3 Type 3 (open graded) unbound
2T1.1.4 Category B (Close graded) unbound mixtures
2T1.1.4.1 Depth not exceeding 30mm 0 m2 0.00
2T1.1.4.2 Depth 30-60mm 0 m2 0.00
2T1.1.4.3 Depth 60-100mm 0 m2 0.00
2T1.1.4.4 Depth 100-150mm 0 m2 0.00
2T1.1.4.5 Depth 150-200mm 0 m2 0.00
2T1.1.4.6 Depth 200-250mm 0 m2 0.00
2T1.1.4.7 Depth 250-300mm 0 m2 0.00
2T1.1.4.8 Depth exceeding 300mm 0 m2 0.00
2T1.1.5 Type 4 (asphalt arrising) unbound mixtures
2T1.1.5.1 Depth not exceeding 30mm 0 m2 0.00
2T1.1.5.2 Depth 30-60mm 0 m2 0.00
2T1.1.5.3 Depth 60-100mm 0 m2 0.00
2T1.1.5.4 Depth 100-150mm 0 m2 0.00
2T1.1.5.5 Depth 150-200mm 0 m2 0.00
2T1.1.5.6 Depth 200-250mm 0 m2 0.00
2T1.1.5.7 Depth 250-300mm 0 m2 0.00
2T1.1.5.8 Depth exceeding 300mm 0 m2 0.00
2T1.1.6 Geotextiles 0 m2 0.00
2T1.1.7 Additional depth of stated material 0 m3 0.00
Cement and other hydraunlically bound
2T1.2 pavements
2T1.2.1 Cement bound granular mixture
Fly ash bound mixture land hydraulic road binder
2T1.2.2 bound mixture 1
Slag bound mixture B2, fly ash bound mixture 2 and
2T1.2.3 hydraulic road binder bond mixture 2
Slag bound mixture B2, fly ash bound mixture 3 and
2T1.2.4 hydraulic road binder bond mixture 3
2T1.2.5 Fly ash bound mixture 5
2T1.2.6 Slag bound mixture B1-1, B1-2, B1-3, B1-4
2T1.2.7 Soil treated by cement
2T1.2.8 Soil treated by other stated materials
2T1.2.8.1 Depth not exceeding 30mm 0 m2 0.00
2T1.2.8.2 Depth 30-60mm 0 m2 0.00
Nigerian Ins2Ti2Tu2Te of Quan2Ti2Ty Surveyors To Collection N 0.00

Page 62
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS

Qty Unit Rate N K

ROADS AND PAVINGS continued ...


Cement and other hydraunlically bound
pavements continued ...
Soil treated by other stated materials continued ...
2T1.2.8.3 Depth 60-100mm 0 m2 0.00
2T1.2.8.4 Depth 100-150mm 0 m2 0.00
2T1.2.8.5 Depth 150-200mm 0 m2 0.00
2T1.2.8.6 Depth 200-250mm 0 m2 0.00
2T1.2.8.7 Depth 250-300mm 0 m2 0.00
2T1.2.8.8 Depth exceeding 300mm 0 m2 0.00
2T1.3 Bituminous bound pavements
2T1.3.1 Hot rolled asphalt base
2T1.3.2 Hot Rolled asphalt binder
Dense base and binder course asphalt concrete
2T1.3.3 paving grade bitumen (recipe mixtures)
2T1.3.4 Dense asphalt concrete surface course
2T1.3.5 Hot rolled asphalt concrete surface
2T1.3.6 Close graded asphalt concrete surface course
2T1.3.7 Fine graded asphalt concrete surface course
2T1.3.8 Open graded asphalt concrete surface course
2T1.3.1.1 Depth not exceeding 30mm 0 m2 0.00
2T1.3.1.2 Depth 30-60mm 0 m2 0.00
2T1.3.1.3 Depth 60-100mm 0 m2 0.00
2T1.3.1.4 Depth 100-150mm 0 m2 0.00
2T1.3.1.5 Depth 150-200mm 0 m2 0.00
2T1.3.1.6 Depth 200-250mm 0 m2 0.00
2T1.3.1.7 Depth 250-300mm 0 m2 0.00
2T1.3.1.8 Depth exceeding 300mm 0 m2 0.00
2T1.4 Bituminous bound pavements
Dense base and binder course asphalt concrete
2T1.4.1 (design mixtures)
2T1.4.2 EME2 base and binder course asphalt concrete
Stone mastic asphalt binder course and regulating
2T1.4.3 course
2T1.4.4 Porous asphalt
Hot rolled asphalt concrete surface course and binder
2T1.4.5 course
2T1.4.6 Cold recycled bound maerial
2T1.4.7 Cold miling / planning
2T1.4.1.1 Depth not exceeding 30mm 0 m2 0.00

Nigerian Ins2Ti2Tu2Te of Quan2Ti2Ty Surveyors To Collection N 0.00

Page 63
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS

Qty Unit Rate N K

ROADS AND PAVINGS continued ...


Bituminous bound pavements continued ...
Cold miling / planning continued ...
2T1.4.1.2 Depth 30-60mm 0 m2 0.00
2T1.4.1.3 Depth 60-100mm 0 m2 0.00
2T1.4.1.4 Depth 100-150mm 0 m2 0.00
2T1.4.1.5 Depth 150-200mm 0 m2 0.00
2T1.4.1.6 Depth 200-250mm 0 m2 0.00
2T1.4.1.7 Depth 250-300mm 0 m2 0.00
2T1.4.1.8 Depth exceeding 300mm 0 m2 0.00
2T1.4.1.9 Regulating course of stated material 0.00 t 0.00
2T1.5 Concrete pavements
2T1.5.1 Unreinforced concrete surface slabs
2T1.5.2 Jointed reinforced concrete surface slabs
2T1.5.3 Continously reinforced concrete alab surface
2T1.5.4 Continously reinforced concrete base slabs
2T1.5.5 Wet lean concrete
2T1.5.1.1 Depth not exceeding 30mm 0 m2 0.00
2T1.5.1.2 Depth 30-60mm 0 m2 0.00
2T1.5.1.3 Depth 60-100mm 0 m2 0.00
2T1.5.1.4 Depth 100-150mm 0 m2 0.00
2T1.5.1.5 Depth 150-200mm 0 m2 0.00
2T1.5.1.6 Depth 200-250mm 0 m2 0.00
2T1.5.1.7 Depth 250-300mm 0 m2 0.00
2T1.5.1.8 Depth exceeding 300mm 0 m2 0.00
2T1.5.6 Steel fabric reinforcements to BS4483
2T1.5.7 Other Fabric reinforcement of stated material
2T1.5.7.1 Nominal mass not exceeding 2 kg/m2 0 m2 0.00
2T1.5.7.2 Nominal mass 2-3 kg/m2 0 m2 0.00
2T1.5.7.3 Nominal mass 3-4 kg/m2 0 m2 0.00
2T1.5.7.4 Nominal mass 4-5 kg/m2 0 m2 0.00
2T1.5.7.5 Nominal mass 5-6 kg/m2 0 m2 0.00
2T1.5.7.6 Nominal mass 6-7 kg/m2 0 m2 0.00
2T1.5.7.7 Nominal mass 7-8 kg/m2 0 m2 0.00
2T1.5.7.8 Nominal mass stated exceeding 8 kg/m2 0 m2 0.00

Nigerian Ins2Ti2Tu2Te of Quan2Ti2Ty Surveyors To Collection N 0.00

Page 64
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS

Qty Unit Rate N K

ROADS AND PAVINGS continued ...


Concrete pavements continued ...
2T1.5.8 Plain round steel bar reinforcement to BS4449
Deformed high yield steel bar reinforcement to
2T1.5.9 BS4449 or BS4461
2T1.5.9.1 Nominal size 6 mm 0.00 t 0.00
2T1.5.9.2 Nominal size 8 mm 0.00 t 0.00
2T1.5.9.3 Nominal size 10mm 0.00 t 0.00
2T1.5.9.4 Nominal size 12 mm 0.00 t 0.00
2T1.5.9.5 Nominal size 16 mm 0.00 t 0.00
2T1.5.9.6 Nominal size 20mm 0.00 t 0.00
2T1.5.9.7 Nominal size 25 mm 0.00 t 0.00
2T1.5.9.8 Nominal size 32 mm or greater 0.00 t 0.00
2T1.5.10 Separation and Waterproof membranes 0 m2 0.00
2T1.6 Joints in concrete pavements
2T1.6.1 Longitudinal joints
2T1.6.2 Expansion joints
2T1.6.3 Contraction joints
2T1.6.4 Warping joints
2T1.6.5 Butt joints
2T1.6.6 Construction joints
2T1.6.6.1 Depth of joint not exceeding 30mm 0m 0.00
2T1.6.6.2 Depth of joint 30-60mm 0m 0.00
2T1.6.6.3 Depth of joint 60-100mm 0m 0.00
2T1.6.6.4 Depth of joint 100-150mm 0m 0.00
2T1.6.6.5 Depth of joint 150-200mm 0m 0.00
2T1.6.6.6 Depth of joint 200-250mm 0m 0.00
2T1.6.6.7 Depth of joint 250-300mm 0m 0.00
2T1.6.6.8 Depth of joint exceeding 300mm 0m 0.00

Nigerian Ins2Ti2Tu2Te of Quan2Ti2Ty Surveyors To Collection N 0.00

Page 65
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS

Qty Unit Rate N K

ROADS AND PAVINGS continued ...


2T1.7 Kerbs, channels and edgings
Precast concrete kerbs to BS7263 Part 1, figures
2T1.7.1 reference stated
Precast concrete edgings to BS7263 Part 1, figure
2T1.7.2 reference stated
Other precast concrete kerbs, channels, edgings,
2T1.7.3 dimensioned description
In situ concrete kerbs, channels, edgings
2T1.7.4 dimensioned description
2T1.7.5 Asphalt kerbs, dimensioned description
2T1.7.6 Asphalt channels, dimensioned stated
Precast concrete natural stone , block and clay slabs
2T1.7.7 and pavers
2T1.7.8 Flexible surfacing
2T1.7.9 Insitu concrete surfacing
2T1.7.10 Grass concrete paving
2T1.7.1.1 Straight or curved to radius exceeding 12m 0m 0.00
2T1.7.1.2 Curved to radius not exceeding 12m 0m 0.00
2T1.7.1.3 Quadrants 0 nr 0.00
2T1.7.1.4 Drops 0 nr 0.00
2T1.7.1.5 Transitions 0 nr 0.00
2T1.8 Light duty pavements
2T1.8.1 Granular base
2T1.8.2 Hardcore base
2T1.8.3 Tarmacadam
2T1.8.4 Rolled asphalt
2T1.8.5 Bitumen macadam
2T1.8.6 Dense tar
2T1.8.7 In-situ concrete of stated strength
2T1.8.8 Precast concrete flags to stated specification
2T1.8.8.1 Depth of joint not exceeding 30mm 0m 0.00
2T1.8.8.2 Depth of joint 30-60mm 0m 0.00
2T1.8.8.3 Depth of joint 60-100mm 0m 0.00
2T1.8.8.4 Depth of joint 100-150mm 0m 0.00
2T1.8.8.5 Depth of joint 150-200mm 0m 0.00
2T1.8.8.6 Depth of joint 200-250mm 0m 0.00
2T1.8.8.7 Depth of joint 250-300mm 0m 0.00
2T1.8.8.8 Depth of joint exceeding 300mm 0m 0.00

Nigerian Ins2Ti2Tu2Te of Quan2Ti2Ty Surveyors To Collection N 0.00

Page 66
BESMM4 CIVIL WORK SEC2TIONS ROADS AND PAVINGS

Qty Unit Rate N K

ROADS AND PAVINGS continued ...


2T1.9 Ancillaries
2T1.9.1 Traffic signs
2T1.9.1.1 Non-illuminated 0 nr 0.00
2T1.9.1.2 Illuminated 0 nr 0.00
2T1.9.2 Surface markings
2T1.9.2.1 Non-reflecting road studs 0 nr 0.00
2T1.9.2.2 Reflecting road studs 0 nr 0.00
2T1.9.2.3 Letters and shapes 0 nr 0.00
2T1.9.2.4 Continuous lines 0m 0.00
2T1.9.2.5 Intermittent lines 0m 0.00
2T1.9.2.6 Raised rib 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 67
BESMM4 CIVIL WORK SECTIONS ROADS AND PAVINGS

Qty Unit Rate N K

Collection

Total from Page 61 N 0.00

Total from Page 62 N 0.00

Total from Page 63 N 0.00

Total from Page 64 N 0.00

Total from Page 65 N 0.00

Total from Page 66 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 68
BESMM4 CIVIL WORK SECTIONS RAIL TRACK

Qty Unit Rate N K

2U RAIL TRACK
2U1.1 Track foundations
2U1.1.1 Bottom ballast 0 m3 0.00
2U1.1.2 Top ballast 0 m3 0.00
2U1.1.3 Blinding 0 m2 0.00
2U1.1.4 Blankets 0 m2 0.00
2U1.1.5 Waterproof membranes 0 m2 0.00
2U1.1.6 Ballast cleaning 0 m3 0.00
2U1.1.7 Tamping 0m 0.00
2U1.1.8 Pneumatic ballast 0m 0.00
2U1.2 Taking up
2U1.2.1 Bullhead rails
2U1.2.2 Flat bottom rails
2U1.2.3 Dock and crane rails
2U1.2.3.1 Plain track 0m 0.00
2U1.2.3.2 Turnouts 0 nr 0.00
2U1.2.3.3 Diamond crossings 0 nr 0.00
2U1.2.4 Check and guard rails 0m 0.00
2U1.2.5 Conductor rails 0m 0.00
2U1.2.6 Sundries
2U1.2.6.1 Buffer stops 0 nr 0.00
2U1.2.6.2 Retarders 0 nr 0.00
2U1.2.6.3 Wheel stops 0 nr 0.00
2U1.2.6.4 Lubricators 0 nr 0.00
2U1.2.6.5 Switch heaters 0 nr 0.00
2U1.2.6.6 Switch levers 0 nr 0.00
2U1.2.6.7 Eutectic strip 0m 0.00
2U1.3 Lifting, packing and slewing
2U1.3.1 Bullhead rail track 0 nr 0.00
2U1.3.2 Flat bottom rail track 0 nr 0.00
2U1.3.3 Existing rail turning and fixing 0 nr 0.00
2U1.3.4 Rerailing 0 nr 0.00
2U1.3.5 Stressing rail 0 nr 0.00

Nigerian Instit2Ute of Q2Uantity S2Urveyors To Collection N 0.00

Page 69
BESMM4 CIVIL WORK SECTIONS RAIL TRACK

Qty Unit Rate N K

RAIL TRACK continued ...


2U1.4 Supplying
2U1.4.1 Bullhead rails
2U1.4.2 Flat bottom rails
2U1.4.3 Dock and crane rails
2U1.4.4 Check and guard rails
2U1.4.5 Conductor rails
2U1.4.6 Twist rails
2U1.4.6.1 Mass not exceeding 20kg/m 0.00 t 0.00
2U1.4.6.2 Mass 20-30kg/m 0.00 t 0.00
2U1.4.6.3 Mass 30-40kg/m 0.00 t 0.00
2U1.4.6.4 Mass 40-50kg/m 0.00 t 0.00
2U1.4.6.5 Mass exceeding 50kg/m 0.00 t 0.00
2U1.4.7 Sleepers
2U1.4.7.1 Timber 0 nr 0.00
2U1.4.7.2 Concrete 0 nr 0.00
2U1.4.7.3 Steel 0 nr 0.00
2U1.4.8 Fittings
2U1.4.8.1 Chairs 0 nr 0.00
2U1.4.8.2 Baseplates 0 nr 0.00
2U1.4.8.3 Pandrol rail fastenings 0 nr 0.00
2U1.4.8.4 Plain fishplates 0 nr 0.00
2U1.4.8.5 Insulated fishplates 0 nr 0.00
2U1.4.8.6 Switch heaters 0 nr 0.00
2U1.4.8.7 Switch levers 0 nr 0.00
2U1.4.8.8 Conductor rail insulators 0 nr 0.00
2U1.4.8.9 Conductor rail side ramps 0 nr 0.00
2U1.5 Supplying
2U1.5.1 Turnoutsand Crossings 0.00
2U1.5.1.1 Trap points 0 nr 0.00
2U1.5.1.2 Catch points 0 nr 0.00
2U1.5.1.3 Turnouts 0 nr 0.00
2U1.5.1.4 Diamond crossings 0 nr 0.00
2U1.5.2 Sundries
2U1.5.2.1 Buffer stops 0 nr 0.00
2U1.5.2.2 Retarders 0 nr 0.00
2U1.5.2.3 Wheel stops 0 nr 0.00
2U1.5.2.4 Lubricators 0 nr 0.00
2U1.5.2.5 Switch heaters 0 nr 0.00
2U1.5.2.6 Switch levers 0 nr 0.00
Nigerian Instit2Ute of Q2Uantity S2Urveyors To Collection N 0.00

Page 70
BESMM4 CIVIL WORK SECTIONS RAIL TRACK

Qty Unit Rate N K

RAIL TRACK continued ...


Sundries continued ...
2U1.5.2.6 Conductor rail guard boards 0m 0.00

2U1.5.3 Prefabricated track panel 18.288 long with rails


and bearers
2U1.5.3.1 Bulkhead track: timber sleepers 0m 0.00
2U1.5.3.2 Concrete sleepers 0m 0.00
2U1.5.3.3 Steel sleepers 0m 0.00
2U1.5.3.4 Flat bottom trsck: timber sleepers 0m 0.00
2U1.5.3.5 concrete sleepers 0m 0.00
2U1.5.3.6 steel sleepers 0m 0.00
2U1.5.4 Prefabricated turnouts and crossings
2U1.5.4.1 Turnouts: type stated timber bearers 0 nr 0.00
2U1.5.4.2 Turnouts: type stated concrete bearers 0 nr 0.00
2U1.5.4.3 Turnouts: type stated steel bearers 0 nr 0.00
2U1.5.4.4 Diamond crossings: type stated timber bearers 0 nr 0.00
2U1.5.4.5 Diamond crossings: type stated concrete bearers 0 nr 0.00
2U1.5.4.6 Diamond crossings: type stated steel bearers 0 nr 0.00
2UI.6 Laying with bearers on ballast
2U1.6.1 Bullhead rails
2U1.6.2 Flat bottom rails
2U1.6.3 Dock rails
2U1.6.4 Crane rails
2U1.6.4.1 Plain track 0m 0.00
Form curve in plain track radius not exceeding
2U1.6.4.2 300m 0m 0.00
2U1.6.4.3 Form curve in plain track radiusexceeding 300m 0m 0.00
2U1.6.4.4 Turnouts 0 nr 0.00
2U1.6.4.5 Diamond crossings 0 nr 0.00
2U1.6.4.6 Welded joints 0 nr 0.00
2U1.6.5 Check rails
2U1.6.6 Guard rails
2U1.6.7 Conductor rails
2U1.6.7.1 Rail 0m 0.00
2U1.6.7.2 Length ends 0 nr 0.00
2U1.6.7.3 Side ramps 0 nr 0.00
2U1.6.7.4 Welded joints 0 nr 0.00

Nigerian Instit2Ute of Q2Uantity S2Urveyors To Collection N 0.00

Page 71
BESMM4 CIVIL WORK SECTIONS RAIL TRACK

Qty Unit Rate N K

RAIL TRACK continued ...


2U1.7 Laying
2U1.7.1 Bulkhead rails slab track
2U1.7.2 Flat bottom rails: slab track
2U1.7.2.1 Plain track 0m 0.00
2U1.7.2.2 From curve in plain track not exceeding 300m 0m 0.00
2U1.7.2.3 From curve in plain track exceeding 300mm 0m 0.00
2U1.7.2.4 Turnouts 0 nr 0.00
2U1.7.2.5 Diamond crossing 0 nr 0.00
2U1.7.2.6 Welded joints 0 nr 0.00
2U1.7.2.7 spotre-sleeping 0 nr 0.00
2U1.7.3 Prefabricated track panel
2U1.7.3.1 Bulkhead rail: timber sleepers 0m 0.00
2U1.7.3.2 Bulkhead rails: concrete sleepers 0m 0.00
2U1.7.3.3 Flat bottom rails: timber 0m 0.00
2U1.7.3.4 Flat bottom rails: concrete sleepers 0m 0.00
2U1.7.3.5 Flat bottom rails: steel sleepers 0m 0.00
2U1.7.4 Prefabricated turnouts and crossings: with bearers
2U1.7.4.1 Turnouts: timber bearers 0 nr 0.00
2U1.7.4.2 Turnouts: concrete bearers 0 nr 0.00
2U1.7.4.3 Turnouts: steel bearers 0 nr 0.00
2U1.7.4.4 Diamond crossings: 0 nr 0.00
2U1.7.4.5 Diamond crossings: steel bearers 0 nr 0.00
2U1.7.5 Sundries
2U1.7.5.1 Buffer stops 0 nr 0.00
2U1.7.5.2 Retarders 0 nr 0.00
2U1.7.5.3 Wheel stops 0 nr 0.00
2U1.7.5.4 Lubricators 0 nr 0.00
2U1.7.5.5 Switch heaters 0 nr 0.00
2U1.7.5.6 Switch levers 0 nr 0.00
2U1.7.5.7 Conductor rail guard boards 0m 0.00
2U1.7.5.8 static sander 0 nr 0.00
2U1.7.5.9 Eutectic strip 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 72
BESMM4 CIVIL WORK SECTIONS RAIL TRACK

Qty Unit Rate N K

Collection

Total from Page 68 N 0.00

Total from Page 69 N 0.00

Total from Page 70 N 0.00

Total from Page 71 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 73
BESMM4 CIVIL WORK SECTIONS TUNNELS

Qty Unit Rate N K


2V TUNNELS

2V1.1 Excavation
2V1.1.1 Tunnels in rock
2V1.1.2 Tunnels in other stated material
2V1.1.3 Shafts in rock
2V1.1.4 Shafts in other stated material
2V1.1.5 Other cavities in rock
2V1.1.6 Other cavities in other stated material
2V1.1.6.1 Stated diameter not exceeding 2m 0 m3 0.00
2V1.1.6.2 Diameter 2-3m 0 m3 0.00
2V1.1.6.3 Diameter 3-4m 0 m3 0.00
2V1.1.6.4 Diameter 4-5m 0 m3 0.00
2V1.1.6.5 Diameter 5-6m 0 m3 0.00
2V1.1.6.6 Diameter 6-7m 0 m3 0.00
2V1.1.6.7 Diameter 7-8m 0 m3 0.00
2V1.1.6.8 Diameter exceeding 8m 0 m3 0.00
2V1.1.7 Excavated surfaces in rock 0 m2 0.00
2V1.1.8 Excavated surfaces in other stated material 0 m2 0.00
2V1.2 In-situ lining to tunnels
2V1.3 In-situ lining to shafts
2V1.4 In-situ lining to other cavities
2V1.4.1 Sprayed concrete primary
2V1.4.2 Sprayed concrete secondary
2V1.4.3 Cast concrete primary
2V1.4.4 Cast concrete secondary
2V1.4.5 Formwork to stated finish
2V1.4.5.1 Stated diameter not exceeding 2m 0 m3 0.00
2V1.4.5.2 Stated diameter 2-3m 0 m2 0.00
2V1.4.5.3 Stated diameter 3-4m 0 m2 0.00
2V1.4.5.4 Stated diameter 4-5m 0 m2 0.00
2V1.4.5.5 Stated diameter 5-6m 0 m2 0.00
2V1.4.5.6 Stated diameter 6-7m 0 m2 0.00
2V1.4.5.7 Stated diameter 7-8m 0 m2 0.00
2V1.4.5.8 Stated diameter exceeding 8m 0 m2 0.00

Nigerian Institute of Quantity Sur2Veyors To Collection N 0.00

Page 74
BESMM4 CI2VIL WORK SECTIONS TUNNELS
Qty Unit Rate N K
TUNNELS continued ...
2V1.5 Preformed segmental lining to tunnels
2V1.6 Preformed segmental lining to shafts
2V1.7 Preformed segmental lining to other cavities
2V1.7.1 Precast concrete bolted rings
2V1.7.2 Precast concrete expanded rings
2V1.7.3 Cast iron bolted rings
2V1.7.4 Cast iron expanded rings
2V1.7.5 Nodular iron rings
2V1.7.6 Fabricated steel rings
2V1.7.6.1 Stated diameter not exceeding 2m 0 m3 0.00
2V1.7.6.2 Stated diameter 2-3m 0 m2 0.00
2V1.7.6.3 Stated diameter 3-4m 0 m2 0.00
2V1.7.6.4 Stated diameter 4-5m 0 m2 0.00
2V1.7.6.5 Stated diameter 5-6m 0 m2 0.00
2V1.7.6.6 Stated diameter 6-7m 0 m2 0.00
2V1.7.6.7 Stated diameter 7-8m 0 m2 0.00
2V1.7.6.8 Stated diameter exceeding 8m 0 m2 0.00
2V1.8 Lining ancillaries
2V1.8.1 Parallel circumferential packing 0 nr 0.00
2V1.8.2 Tapered circumferential packing 0 nr 0.00
2V1.8.3 Stepped junctions 0 nr 0.00
2V1.8.4 Caulking of stated material 0m 0.00
2V1.9 Support and stablization
2V1.9.1 Rock bolts
2V1.9.1.1 Mechanical 0m 0.00
2V1.9.1.2 Pre-grouted impacted 0m 0.00
2V1.9.1.3 Chemical end anchor 0m 0.00
2V1.9.1.4 Chemical grouted 0m 0.00
2V1.9.1.5 Chemically filled 0m 0.00
2V1.9.2 Internal support
2V1.9.2.1 Steel arches supply 0.00 t 0.00
2V1.9.2.2 Steel arches erection 0.00 t 0.00
2V1.9.2.3 Timber supports supply 0 m3 0.00
2V1.9.2.4 Timber supports erection 0 m3 0.00
2V1.9.2.5 Lagging 0 m2 0.00
2V1.9.2.6 Sprayed concrete 0 m2 0.00
2V1.9.2.7 Mesh or link 0 m2 0.00
2V1.9.3 Pressure grouting
2V1.9.3.1 Sets of drilling and grouting plant 0 nr 0.00
2V1.9.3.2 Face packers 0 nr 0.00
2V1.9.3.3 Deep packers of stated size 0 nr 0.00
2V1.9.3.4 Drilling and flushing to stated diameter 0m 0.00
2V1.9.3.5 Re-drilling and flushing 0m 0.00
2V1.9.3.6 Injection of grout materials of stated composition 0.00 t 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 75
BESMM4 CIVIL WORK SECTIONS TUNNELS
Qty Unit Rate N K
Collection

Total from Page 73 N 0.00

Total from Page 74 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 76
BESMM4 CIVIL WORK SECTIONS BRICKWORK, BLOCKWORK & MASONRY
Qty Unit Rate N K
2W BRICKWORK, BLOCKWORK AND MASONRY
2W1.1 Common Brickwork
2W1.2 Facing Brickwork
2W1.3 Engineering brickwork
2W1.4 Lightweight blockwork
2W1.5 Dense concrete blockwork
2W1.6 Artificial stone blockwork
2W1.7 Ashlar masonry
2W1.8 Rubble masonry
2W1.8.1 Thickness not exceeding 150mm
2W1.8.2 Thickness 150-250mm
2W1.8.3 Thickness 250-500mm
2W1.8.4 Thickness 500mm-1m
2W1.8.5 Thickness exceeding 1m
2W1.8.5.1 Vertical straight walls 0 m2 0.00
2W1.8.5.2 Vertical curved walls 0 m2 0.00
2W1.8.5.3 Battered straight walls 0 m2 0.00
2W1.8.5.4 Battered curved walls 0 m2 0.00
2W1.8.5.5 Vertical facing to concrete 0 m2 0.00
2W1.8.5.6 Battered facing to concrete 0 m2 0.00
2W1.8.5.7 Casing to metal sections 0 m2 0.00
Columns and piers of stated cross- sectional
2W1.8.6
dimensions 0m 0.00
2W1.8.7 Surface features
2W1.8.7.1 Copings and sills, material stated 0m 0.00
2W1.8.7.2 Rebates and chases 0m 0.00
2W1.8.7.3 Cornices 0m 0.00
2W1.8.7.4 Band courses 0m 0.00
2W1.8.7.5 Corbels 0m 0.00
2W1.8.7.6 Pilasters 0m 0.00
2W1.8.7.7 Plinths 0m 0.00
2W1.8.7.8 Fair facing 0 m2 0.00
2W1.8.8 Ancillaries
2W1.8.8.1 Joint reinforcement 0m 0.00
2W1.8.8.2 Damp proof courses 0m 0.00
2W1.8.8.3 Movement joints 0m 0.00
2W1.8.8.4 Bonds to existing work 0 m2 0.00
2W1.8.8.5 Infills of stated thickness 0 m2 0.00
2W1.8.8.6 Fixings and ties 0 m2 0.00
Built-in pipes and ducts cross-sectional area not
2W1.8.8.7
exceeding0.05m2 0 nr 0.00
Built-in pipes and ducts cross- sectional area
2W1.8.8.8
stated exceeding 0.05m2 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 77
BESMM4 CIVIL WORK SECTIONS BRICKWORK, BLOCKWORK & MASONRY
Qty Unit Rate N K
Collection

Total from Page 76 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 78
BESMM4 CIVIL WORK SECTIONS PAINTING
Qty Unit Rate N K
2X PAINTING
2X1.1 Lead, iron or zinc based primer paint
2X1.2 Etch primer paint
2X1.3 Oil paint
2X1.4 Alkyd gloss paint
2X1.5 Emulsion paint
2X1.6 Cement paint
2X1.7 Epoxy or polyurethane paint
2X1.8 Bituminous or coal tar paint
2X1.8.1 Metal, other than metal sections andpipework
2X1.8.2 Timber
2X1.8.3 Smooth concrete
2X1.8.4 Rough concrete
2X1.8.5 Masonry
2X1.8.6 Brickwork and blockwork
Upper surfaces inclined at an angle not exceeding
2X1.8.6.1
30 Deg to the horizontal 0 m2 0.00
2X1.8.6.2 Upper surfaces at 30-60 Deg to the horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2X1.8.6.3
the horizontal 0 m2 0.00
Upper surfaces inclined at an angle not exceeding
2X1.8.6.4
30 Deg to the horizontal 0 m2 0.00
2X1.8.6.5 Surfaces of width not exceeding 300mm 0m 0.00
2X1.8.6.6 Surfaces of width 300mm-1m 0m 0.00
2X1.8.6.7 Isolated groups of surfaces 0 nr 0.00
2X1.8.7 Metal sections 0 m2 0.00
2X1.8.8 Pipework 0 m2 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 79
BESMM4 CIVIL WORK SECTIONS WATERPROOFING
Qty Unit Rate N K
2Y WATERPROOFING
2Y1.1 Damp proofing
2Y1.2 Tanking
2Y1.3 Roofing
2Y1.3.1 Asphalt
2Y1.3.2 Sheet metal
2Y1.3.3 Waterproof sheeting
2Y1.3.4 Waterproof coating
2Y1.3.5 Rendering in ordinary cement mortar
2Y1.3.6 Rendering in waterproof cement mortar
2Y1.3.7 Tiles
Upper surfaces inclined at an angle not exceeding 30
2Y1.3.7.1 Deg to the horizontal 0 m2 0.00
Upper surfaces inclined at 30-60 Deg to the
2Y1.3.7.2 horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2Y1.3.7.3 the horizontal 0 m2 0.00
2Y1.3.7.4 Curved surfaces 0 m2 0.00
2Y1.3.7.5 Domed surfaces 0 m2 0.00
2Y1.3.7.6 Surfaces of width not exceeding300mm 0m 0.00
2Y1.3.7.7 Surfaces of width 300mm-1m 0m 0.00
2Y1.3.7.8 Isolated groups of surfaces 0 nr 0.00
2Y1.4 Protective layers
2Y1.4.1 Sand asphalt
2Y1.4.2 Flexible sheeting
2Y1.4.3 Sand
2Y1.4.4 Sand and cement screed
2Y1.4.5 Tiles
Upper surfaces inclined at an angle not exceeding
2Y1.4.5,1 30 Deg to the horizontal 0 m2 0.00
Upper surfaces inclined at 30-60 Deg to the
2Y1.4.5,2 horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2Y1.4.5,3 the horizontal 0 m2 0.00
2Y1.4.5,4 Curved surfaces 0 m2 0.00
2Y1.4.5,5 Domed surfaces 0 m2 0.00
2Y1.4.5,6 Surfaces of width not exceeding 300mm 0m 0.00
2Y1.4.5,7 Surfaces of width 300mm-1m 0m 0.00
2Y1.4.5,8 Isolated groups of surfaces 0 nr 0.00
2Y1.5 Sprayed or brushed waterproofing 0 m2 0.00
Nigerian Institute of Quantit2Y Surve2Yors To Collection N 0.00

Page 80
BESMM4 CIVIL WORK SECTIONS WATERPROOFING
Qty Unit Rate N K
WATERPROOFING continued ...
2Y1.6 Sheet lining membrane
2Y1.6.1 Butyl rubber
2Y1.6.2 EPDM rubber
2Y1.6.3 PVC
2Y1.6.4 Polypropylene
2Y1.6.5 Polythylene
2Y1.6.6 Polyurethane
2Y1.6.7 Proprietary
Upper surfaces inclined at an angle not exceeding
2Y1.6.7.1 30 Deg to the horizontal 0 m2 0.00
Upper surfaces inclined at 30-60 Deg to the
2Y1.6.7.2 horizontal 0 m2 0.00
Surfaces inclined at an angle exceeding 60 Deg to
2Y1.6.7.3 the horizontal 0 m2 0.00
2Y1.6.7.4 Curved surfaces 0 m2 0.00
2Y1.6.7.5 Domed surfaces 0 m2 0.00
2Y1.6.7.6 Surfaces of width not exceeding 300mm 0 m2 0.00
2Y1.6.7.7 surfaces of width 300mm - 1m 0 m2 0.00
2Y1.6.7.8 Isolated groups of surfaces 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 81
BESMM4 CIVIL WORK SECTIONS WATERPROOFING
Qty Unit Rate N K
Collection

Total from Page 82 N 0.00

Total from Page 83 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 82
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS WORK
Qty Unit Rate N K
2Z MISCELLANEOUS WORK
2Z1.1 Fences
2Z1.1.1 Timber post and rail
2Z1.1.2 Timber post and wire
2Z1.1.3 Concrete post and wire
2Z1.1.4 Metal post and wire
2Z1.1.5 Coated metal post and wire
2Z1.1.6 Timber close boarded
2Z1.1.7 Metal guard system
2Z1.1.8 Metal crash barriers
2Z1.1.8.1 Height not exceeding 1m 0m 0.00
2Z1.1.8.2 Height 1-1.25m 0m 0.00
2Z1.1.8.3 Height 1.25-1.5m 0m 0.00
2Z1.1.8.4 Height 1.5-2m 0m 0.00
2Z1.1.8.5 Height 2-2.5m 0m 0.00
2Z1.1.8.6 Height 2.5-3m 0m 0.00
2Z1.1.8.7 Height exceeding 3m 0 m3 0.00
2Z1.2 Gates and Stiles
2Z1.2.1 Timber stile gates
2Z1.2.2 Timber wicket gates
2Z1.2.3 Stiles
2Z1.2.3.1 Width not exceeding 1.5m 0 nr 0.00
2Z1.2.3.2 Width 1.5-2m 0 nr 0.00
2Z1.2.3.3 Width 2-2.5m 0 nr 0.00
2Z1.2.3.4 Width 2.5-3m 0 nr 0.00
2Z1.2.3.5 Width 3-4m 0 nr 0.00
2Z1.2.3.6 Width 4-5m 0 nr 0.00
2Z1.2.3.7 Width exceeding 5m 0 nr 0.00
2Z1.3 Drainage to structures above ground
2Z1.3.1 Mild steel
2Z1.3.2 Cast iron
2Z1.3.3 Plastics
2Z1.3.3.1 Gutters 0m 0.00
2Z1.3.3.2 Downpipes 0m 0.00
2Z1.3.3.3 Fittings to gutters 0 nr 0.00
2Z1.3.3.4 Fittings to downpipes 0 nr 0.00
2Z1.4 Rock filled gabions
2Z1.4.1 Box of stated size 0 nr 0.00
2Z1.4.2 Mattress of stated thickness 0 m2 0.00
2Z1.5 Open Cell Block System 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 83
BESMM4 CIVIL WORK SECTIONS MISCELLANEOUS WORK
Qty Unit Rate N K
Collection

Total from Page 85 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 84
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
SEWER AND WATER RENOVATION AND ANCILLARY
2AA WORKS
2AA1.1 Preparation of existing sewers
2AA1.1.1 Cleaning 0m 0.00
2AA1.1.2 Removing intrusions
2AA1.1.2.1 Laterals, bore not exceeding 150mm 0 nr 0.00
Laterals, stated profile and size exceeding 150mm
2AA1.1.2.2 in one or more dimension 0 nr 0.00
2AA1.1.2.3 Other stated artifical intrusions 0 nr 0.00
2AA1.1.4 Closed-circuit television surveys 0m 0.00
2AA1.1.5 Plugging laterals, materials stated
2AA1.1.5.1 Bore not exceeding 300mm 0 nr 0.00

Stated profile and size exceeding 300mm in one or


2AA1.1.5.2 more dimension 0 nr 0.00
2AA1.1.6 Filling laterals and other pipes, materials stated
2AA1.1.6.1 Bore not exceeding 0.1m2 0 m3 0.00

Stated profile and size exceeding 300mm in one or


2AA1.1.6.2 more dimension 0 nr 0.00
2AA1.1.7 Local internal repairs
2AA1.1.7.1 Area not exceeding 0.1m2 0 nr 0.00
2AA1.1.7.2 Area 0.1-0.25m2 0 nr 0.00
2AA1.1.7.3 Area stated exceeding 0.25m2 0 nr 0.00
2AA1.2 Stabilization of existing sewers
2AA1.2.1 Pointing materials stated 0 m2 0.00
2AA1.2.2 Pipe joint sealing materials stated 0 nr 0.00
2AA1.2.3 External grouting
2AA1.2.3.1 Number of holes 0 nr 0.00
2AA1.2.3.2 Injection of grout materials stated 0 m3 0.00
2AA1.3 Renovation of existing sewers
2AA1.3.1 Sliplining
2AA1.3.1.1 Polyethylene 0m 0.00
2AA1.3.1.2 Polypropylene 0m 0.00
2AA1.3.2 In-situ jointed pipe lining
2AA1.3.2.1 Polyethylene 0m 0.00
2AA1.3.2.2 Polypropylene 0m 0.00
2AA1.3.2.3 Glass reinforced plastic 0m 0.00
2AA1.3.3 Segmental lining
2AA1.3.3.1 Glass reinforced plastic 0m 0.00
2AA1.3.3.2 Glass reinforced concrete 0m 0.00
2AA1.3.3.3 Cast gunite 0m 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 85
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
SEWER AND WATER RENOVATION AND ANCILLARY
WORKS continued ...
Renovation of existing sewers continued ...
Segmental lining continued ...
2AA1.3.3.4 Resin concrete 0m 0.00
2AA1.3.4 Stated proprietary lining 0m 0.00
2AA1.3.5 Gunite coating of stated thickness 0m 0.00
2AA1.3.6 Annulus grouting materials stated 0 m3 0.00
2AA1.4 Laterals to renovated sewers
2AA1.4.1 Jointing
2AA1.4.1.1 Bore not exceeding 150mm 0 nr 0.00
2AA1.4.1.2 Bore 150-300mm 0 nr 0.00

Stated profile and size exceeding 300mm in one or


2AA1.4.1.3 more dimension 0 nr 0.00
2AA1.4.2 Flap valves of stated size
2AA1.4.2.1 Remove existing 0 nr 0.00
2AA1.4.2.2 Replace existing 0 nr 0.00
2AA1.4.2.3 New flap valve of stated type 0 nr 0.00
2AA1.5 Water main renovation and ancillary works
2AA1.5.1 Cleaning
2AA1.5.2 Removing intrusions
2AA1.5.3 Pipe sample inspection
2AA1.5.4 Closed circuit television surveys
2AA1.5.5 Cement mortar lining
2AA1.5.6 Epoxy lining
2AA1.5.6.1 Nominal bore not exceeding 200mm 0m 0.00
2AA1.5.6.2 Nominal bore 200-300mm 0m 0.00
2AA1.5.6.3 Nominal bore 300-600mm 0m 0.00
2AA1.5.6.4 Nominal bore 600-900mm 0m 0.00
2AA1.5.6.5 Nominal bore 900-1200mm 0m 0.00
2AA1.5.6.6 Nominal bore stated exceeding 1200mm 0m 0.00
2AA1.6 New manholes
2AA1.6.1 Brick
2AA1.6.2 Brick with backdrop
2AA1.6.3 In situ concrete
2AA1.6.4 In situ concrete with backdrop
2AA1.6.5 Precast concrete
2AA1.6.6 Precast concrete with backdrop
2AA1.6.6.1 Depth not exceeding 1.5m 0 nr 0.00

Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 86
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
SEWER AND WATER RENOVATION AND ANCILLARY
WORKS continued ...
New manholes continued ...
Precast concrete with backdrop continued ...
2AA1.6.6.2 Depth 1.5-2m 0 nr 0.00
2AA1.6.6.3 Depth 2.5-3m 0 nr 0.00
2AA1.6.6.4 Depth 3-3.5m 0 nr 0.00
2AA1.6.6.5 Depth 3.5-4m 0 nr 0.00
2AA1.6.6.6 Depth stated exceeding 4m 0 nr 0.00
2AA1.7 Existing manholes
2AA1.7.1 Abandonment
2AA1.7.1.1 Depth 2-2.5m 0 nr 0.00
2AA1.7.1.2 Depth 2.5-3m 0 nr 0.00
2AA1.7.1.3 Depth 3-3.5m 0 nr 0.00
2AA1.7.1.4 Depth 3.5-4m 0 nr 0.00
2AA1.7.1.5 Depth stated exceeding 4m 0 nr 0.00
2AA1.7.2 Alteration 0 nr 0.00
2AA1.8 Interruptions
2AA1.8.1 Preparation of existing sewers
2AA1.8.2 Stabilization of existing sewers
2AA1.8.3 Renovation of existing sewers
2AA1.8.3.1 Sliplining 0h 0.00
2AA1.8.3.2 In-situ jointed pipelining 0h 0.00
2AA1.8.3.3 Segmental lining 0h 0.00
2AA1.8.3.4 Stated proprietary lining 0m 0.00
2AA1.8.3.5 Gunite coating 0m 0.00
2AA1.8.3.6 Annulus grouting 0h 0.00
2AA1.8.4 Work on laterals to renovated sewers 0h 0.00
2AA1.8.5 Work on manholes 0h 0.00
Nigerian Institute of Quantity Surveyors To Collection N 0.00

Page 87
BESMM4 CIVIL WORK SECTIONS SEWER AND WATER RENOVATION & ANCILLARY
Qty Unit Rate N K
Collection

Total from Page 88 N 0.00

Total from Page 89 N 0.00

Total from Page 90 N 0.00

Nigerian Institute of Quantity Surveyors To Summary N 0.00

Page 88
BESMM4 CIVIL WORK SECTIONS
Qty Unit Rate N K
Summary

GENERAL ITEMS Page 5 N 0.00

GROUND INVESTIGATION Page 11 N 0.00

GEOTECHNICAL & OTHER SPECIALIST ... Page 15 N 0.00

DEMOLITION & SITE CLEARANCE Page 18 N 0.00

EARTHWORKS Page 22 N 0.00

IN SITU CONCRETE Page 25 N 0.00

CONCRETE ANCILLARIES Page 29 N 0.00

PRECAST CONCRETE Page 32 N 0.00

PIPEWORK - PIPES Page 34 N 0.00

PIPEWORK - FITTINGS & VALVES Page 37 N 0.00

PIPEWORK - MANHOLES & PIPEWORK ... Page 42 N 0.00

PIPEWORK - SUPPORTS & ... Page 46 N 0.00

STRUCTURAL METALWORK Page 49 N 0.00

MISCELLANEOUS METALWORK Page 51 N 0.00

TIMBER Page 53 N 0.00

PILES Page 56 N 0.00

PILING ANCILLARIES Page 60 N 0.00

ROADS AND PAVINGS Page 67 N 0.00

RAIL TRACK Page 72 N 0.00

TUNNELS Page 76 N 0.00

Nigerian Institute of Quantity Surveyors Carried Forward N 0.00

Page 89
BESMM4 CIVIL WORK SECTIONS
Qty Unit Rate N K
Summary continued ... 0.00

BRICKWORK, BLOCKWORK & MASONRY Page 79 N 0.00

PAINTING Page 81 N 0.00

WATERPROOFING Page 84 N 0.00

MISCELLANEOUS WORK Page 87 N 0.00

SEWER AND WATER RENOVATION & ... Page 91 N 0.00

Nigerian Institute of Quantity Surveyors Total for Bill N 0.00

Page 90
Page №:(1)

Type your name of company here.


Name of Project
Name of Structure
SUMMARY OF REINFORCEMENT STEEL
Size of bar T8 T10 T12 T16 T20 T25 T32 Total
Weight (Kg) 7328 0 0 17956 0 0 0 25284

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(2)

Bar Description of ø of №of №of Total Cutting


Code A B C D E F Shape Weight (Kg)
Mark Elements Bars Elmts Bars № length
1st Basement BEAMS
BEAM 1 T8 1 183 183 № 6300 455.396

T16 1 6 6 № 3000 28.422


T16 1 6 6 № 4600 43.580
T16 1 6 6 № 5000 47.370
T16 1 6 6 № 12000 113.688
T16 1 6 6 № 5000 47.370
T16 1 6 6 № 9300 88.108
T16 1 6 6 № 6400 60.634
T16 1 6 6 № 3000 28.422
T16 1 6 6 № 10300 97.582
T16 1 6 6 № 5000 47.370
T16 1 6 6 № 12000 113.688
T16 1 6 6 № 5000 47.370
T16 1 6 6 № 9400 89.056
T16 1 6 6 № 5000 47.370

BEAM 1 T8 1 183 183 № 2200 159.027


T8 1 183 183 № 1800 130.113
T8 1 183 183 № 1400 101.199
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 4600 43.580
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12300 116.530
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9300 88.108
T16 1 6 6№ 6800 64.423
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 10300 97.582
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9700 91.898
T16 1 6 6№ 5000 47.370

BEAM 1 T8 1 123 123 № 2200 106.887


T8 1 123 123 № 1800 87.453
T8 1 123 123 № 1400 68.019
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 6400 60.634
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9300 88.108
T16 1 6 6№ 6400 60.634
T16 1 6 6№ 3400 32.212
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9400 89.056
SHEET 1 T16 1 6 6№ 5000 47.370

BEAM 1 T8 1 157 157 № 2200 136.433


T8 1 157 157 № 1800 111.627
T8 1 157 157 № 1400 86.821
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 4600 43.580
T16 1 6 6№ 9650 91.424
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 11200 106.109
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 1500 14.211
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 2800 26.527
T16 1 6 6№ 4800 45.475

BEAM 1 T8 1 124 124 № 2200 107.756


T8 1 124 124 № 1800 88.164

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(3)

Bar Description of ø of №of №of Total Cutting


Code A B C D E F Shape Weight (Kg)
Mark Elements Bars Elmts Bars № length
T8 1 124 124 № 1400 68.572
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 6400 60.634
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9300 88.108
T16 1 6 6№ 6400 60.634
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9400 89.056
T16 1 6 6№ 5000 47.370

BEAM 1 T8 1 91 91 № 2200 79.079


T8 1 91 91 № 1800 64.701
T8 1 91 91 № 1400 50.323
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 6400 60.634
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 9900 93.793
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 4250 40.265

BEAM 1 T8 1 91 91 № 2200 79.079


T8 1 91 91 № 1800 64.701
T8 1 91 91 № 1400 50.323
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 6400 60.634
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 4400 41.686
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
SHEET 2 T16 1 6 6№ 12000 113.688

SHEET 6 T8 1 436 436 № 2200 378.884


T8 1 436 436 № 1800 309.996
T8 1 436 436 № 1400 241.108
T16 1 6 6№ 2500 23.685
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4500 42.633
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 11000 104.214
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 7800 73.897
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 7000 66.318
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 10200 96.635
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 12000 113.688

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(4)

Bar Description of ø of №of №of Total Cutting


Code A B C D E F Shape Weight (Kg)
Mark Elements Bars Elmts Bars № length
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 11500 108.951

T8 1 439 439 № 2200 381.491


T8 1 439 439 № 1800 312.129
T8 1 439 439 № 1400 242.767
T16 1 6 6№ 2500 23.685
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 2500 23.685
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 2500 23.685
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 7800 73.897
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 6700 63.476
T16 1 6 6№ 2800 26.527
T16 1 6 6№ 2500 23.685
T16 1 6 6№ 3200 30.317
T16 1 6 6№ 10200 96.635
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 11000 104.214

SHEET 7 T8 1 392 392 № 2200 340.648


T8 1 392 392 № 1800 278.712
T8 1 392 392 № 1400 216.776
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 6400 60.634
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 11000 104.214
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 7800 73.897
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 11000 104.214
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(5)

Bar Description of ø of №of №of Total Cutting


Code A B C D E F Shape Weight (Kg)
Mark Elements Bars Elmts Bars № length
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 11500 108.951
T16 1 6 6№ 8000 75.792
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 7500 71.055
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4500 42.633

T8 1 404 404 № 2200 351.076


T8 1 404 404 № 1800 287.244
T8 1 404 404 № 1400 223.412
T16 1 6 6№ 1500 14.211
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 8700 82.424
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 11000 104.214
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 7300 69.160
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 3800 36.001
T16 1 6 6№ 1000 9.474
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 10200 96.635
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 11500 108.951
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 11500 108.951
T16 1 6 6№ 4500 42.633
T16 1 6 6№ 7500 71.055

SHEET 8 T8 1 419 419 № 2200 364.111


T8 1 419 419 № 1800 297.909
T8 1 419 419 № 1400 231.707
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 3300 31.264
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 11000 104.214
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3500 33.159

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
BBS Ref: Page №:(6)

Bar Description of ø of №of №of Total Cutting


Code A B C D E F Shape Weight (Kg)
Mark Elements Bars Elmts Bars № length
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 2500 23.685
T16 1 6 6№ 8800 83.371
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 7950 75.318
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 12000 113.688

T8 1 363 363 № 2200 315.447


T8 1 363 363 № 1800 258.093
T8 1 363 363 № 1400 200.739
T16 1 6 6№ 2500 23.685
T16 1 6 6№ 3300 31.264
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 11000 104.214
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 11000 104.214
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 10000 94.740
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 3500 33.159
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 4200 39.791
T16 1 6 6№ 7800 73.897
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 3000 28.422
T16 1 6 6№ 7950 75.318
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 4000 37.896
T16 1 6 6№ 2000 18.948
T16 1 6 6№ 12000 113.688
T16 1 6 6№ 5000 47.370
T16 1 6 6№ 9500 90.003
T16 1 6 6№ 6000 56.844
T16 1 6 6№ 11500 108.951

25283.998

Unregistered version of BBS Program Prepared by Checked by


www.BendingSchedule.com
ABTI- AMERICAN UNIVERSITY OF NIGERIA, YOLA.

BUILDER'S WORK PRICE ANALYSIS.

LABOUR.

SECTION1: NR.OF WKG DAYS/YEAR

5 working days/week x 52weeks/year 260.00 260days/yr


LESS
National Holiday 12 days
Annual leave 7 days
Incement weather 15 days
Casual leave 6 days
40 days/year
Actual working Days/year
220.00 days/year 220.00
SECTION 2: ALL IN RATES (LABOUR)

BASIC WAGES FOREMAN TT NTT LABOURER

260 days @ 235.14/day 770,000.00


260 days @ 234.56/day 770,000.00
260 days @ 234.32/day 550,000.00
260 days @ 234.09/day 440,000.00

ADD

General Allowances

Transportation (lump) 28,800.00 28,800.00 28,800.00 28,800.00


Rent subsidy (40%) 24,454.56 24,394.24 24,369.28 24,345.36
Medical (lump) 9,000.00 9,000.00 9,000.00 9,000.00
Leave (10% of annual basic) 6,113.64 6,098.56 6,092.32 6,086.34
Meal (lump) 10,560.00 10,560.00 10,560.00 10,560.00
Utility (lump) 3,600.00 3,600.00 3,600.00 3,600.00
Tools (lump) 1,056.00 1,056.00

Statutory Contributions

NSTIF S0cial Insurance (6.5% of basic +R+T) 7,435.41 7,421.69 7,416.01 7,410.57
Include training fund (3%) 1,834.09 1,829.57 1,827.70 1,825.90
Workmen compensation 1,222.73 1,219.71 1,218.46 1,217.27
Total of 10% of annual basic 6,113.64 6,098.56 6,092.32 6,086.34

TOTAL 869,134.07 870,078.33 650,032.09 538,931.78

COST/DAY 3,950.61 3,954.90 2,954.69 2,449.69


The fluctuation Clause will not apply on contract whose completion period are 12 Month and under.

SCHEDULE OF BASIC PRICES


(To be completed by Tenderer)

FLUCTUATIONS see Conditions of contract and attached

The contractor is to state below the rates of labour and market prices of materias current at the date of tender.
A list of some materials is stated below.
Fluctuation claims: if any will be restricted to the listed materials only

LABOUR BASIC PRICES (N)

Labourer 234.09 per day


Artisan (Non Trade Tested) NTT 234.32 per day
Artisan (Trade Tested) TT 234.56 per day

MATERIALS BASIC PRICES


(DELIVERED TO SITE)

1 Cement (BS 12) 20,800.00 per tonne


2 White cement 50,000.00 per tonne
3 Sand for concrete 750.00 per cub.m
4 Sand for plastering 750.00 per cub.m
5 Granite Chippings (all size) Aggregate 1,700.00 per cub.m
6 BS No. A 142 Fabric Reinforcement 15,435.00 per roll of 30.00 x 2.40 m
7 150mm Sandcrete blocks 50.00 each
8 230mm Sandcrete blocks 60.00 each
Mild steel bar reinforcement
9 10mm 104,000.00 per tonnes
High tensile bar reinforcement

10 10mm 104,000.00 per tonnes


11 12mm 104,000.00 per tonnes
12 16-25mm 104,000.00 per tonnes
13 Formwork timber 24,075.00 per cub.m
14 Carpenter/Joinery Timber 27,800.00 per cub.m
15 0.7mm Longspan Aluminium roofing sheet with alycrom finish 1,850.00 per sq.m
16 0.7mm Longspan Aluminium roofing sheet with plain finish 1,650.00 per sq.m
17 0.55mm Longspan Aluminium roofing sheet with alycrom finish 1,011.00 per sq.m
18 0.55mm Longspan Aluminium roofing sheet with plain finish 915.00 per sq.m
19 NT4 Paralon 1,292.00
20 Crittal hope door frame type DIA 27 2,500.00 each
21 Crittal hope door frame type DIA 30 2,500.00 each
22 Crittal hope door frame type DIA 33 2,500.00 each
23 Crittal hope door frame type DIA 54 2,604.00 each
Finishes
24 300 x 300 x 6mm Marazzi vitrified anti0acid
unglazed ceramic floor tiles 2,000.00 per sq.m
25 200 x 200 x 6mm Unglazed ceramic floor tiles 1,650.00 per sq.m
26 300 x 600 x 20mm royale perlato unpolished marble floor tiles 5,950.00 per sq.m
27 305 x305 x 10mm royale perlato polished calibrated
marble wall tiles 7,850.00 per sq.m
28 300 x 300 x 12mm polished CIBI Africa multi colour
granite floor tiles 7,600.00 per sq.m
29 300 x 300 x 1.4mm PVC tiles 450.00 per sq.m
30 152 x 152 x 6mm white glazed cushioned edge
ceramic wall tiles 1,000.00 per sq.m
31 153 x 152 x 6mm coloured glazed cushioned edge
ceramic wall tiles 1,750.00 per sq.m
32 12mm particle board 1,076.00 per sheet of 2.44 x 1.22m
33 12mm celotex board 1,130.00 per sheet of 2.44 x 1.22m
34 6mm Hardboard ceiling sheets 460.00 per sheet of 2.44 x 1.22m
35 Marble chips 337.00 per 20kg. Bag
36 Kerokoll tiles adhesive 1,938.00 per 25kg. Bag
37 Emulsion paint 1,300.00 per 4litre tin
38 Gloss paint 1,768.00 per 4litre tin
39 Texcote 8,156.00 per 20kg. Drum

ALL IN LABOUR RATES:

a. Labourer/day 2,000.00

b. Artisan (Non-Trade Tested)/day 3,500.00

c. Artisan (Trade Tested)/day 4,000.00

d. Foreman 5,000.00

GENERAL OVERHEADS AND PROFIT

Allowance overall costs 30%

Allowance for tools 5%

Allowance for Surpervision 5%

Allowance for waste 5%

Allowance for bulkage 20%


A EXCAVATION AND EARTHWORK

Over site excavation to remove vegetable soil


1 150mmdeep
Labour excavating 2.00 2,000.00 4,000.00
Labour loading on birrow 1.00 2,000.00 2,000.00
Labour spreading 1.00 2,000.00 2,000.00
Cost of labour 8,000.00
Allow for tools 5% 5% 400.00
Cost of gang 8,400.00

Output of gang/day 5M3 5.00


1,680.00
Cost/m3
Allow for thin layer 7.5% 0.08 126.00
1,806.00

Excavation for 150mm thick 0.15 270.90


Add GOH & profit. (30%) 30% 81.27
Cost/m3 352.17 352.17

Excavate trench/pit for foundation /column base


2 not exceeding 1.5m deep
Labourer excavating and disposing 1.00 2,000.00 2,000.00
Allow for tools 5% 5% 100.00
2,100.00
Allow for surpervision 15% 5% 105.00
Cost of gang 2,205.00

Output fo gang/day (2.00m3) 2.00


Cost/m3 1,102.50
Add GOH & profit. (30%) 30% 330.75
Cost/m3 1,433.25 1,433.25

Reture fill and ram selected excavated materials


3 around foundations:

Cost of gang as before in trench/pit excavation 2,205.00

Output fo gang/day (4.00m3) 4.00


Cost/m3 551.25
Add GOH & profit. (30%) 30% 165.38
Cost/m3 716.63 716.63
4 Remove surplus excaveted materials from site

Cost of gang as before in trench/pit excavation 2,205.00

Output fo gang/day (6.00m3) 6.00


Cost/m3 367.50
Add GOH & profit. (30%) 30% 110.25
Cost/m3 477.75 477.75

5 Rock laterite hardcore filling in bed

Cost of 3.80m3 tipper of rock laterite hardcore 3.80 12,000.00


Cost/m3 3,157.89
Allow for bulkage 20% 20% 631.58
3,789.47
Allow for waste 5% 5% 189.47
Cost of materials 3,978.95 3,978.95

Plant:

Grader hire-day 200,000.00


Output of grader/day (200m3) 200.00
Cost of grader/m3 1,000.00

Compactor/Roller hire/day 10,000.00


Output of Compactor/Roller/day (115m3) 115.00
Cost of Compactor/Roller/day 86.96
1,086.96
Cost of plant 5,065.90
Add GOH & profit. (30%) 30% 1,519.77
Cost/m3 6,585.68
6 Granite rock hardcore filling in bed:

Cost of 3.80m3 tipper of rock laterite hardcore 23,500.00

Cost/m3 3.80 23,500.00 6,184.21


Allow for bulkage 15% 0.15 927.63
7,111.84
Allow for waste 5% 5% 355.59
Cost of materials 7,467.43
Plant:
Cost of grader/m3 1,000.00
Cost of Compactor/Roller/day 86.96
Cost of plant 1,086.96
8,554.39
Add GOH & profit. (30%) 30% 2,566.32
Cost/m3 11,120.71

Dieldrex anti-termite treatment to surfaces of


7 excavations;

Cost of a gallon 4.20 litles dieldrex - 20 solution 4.20 1,450.00


Cost/litre 345.24
Add 80 litres of water 81lit

Apllication

Rate of application/m2 =10 litres


Cost of 10 litres of solution 42.62
Allow for waste 5% 5% 2.13
Cost of solution/m2 44.75

Labour

1 No. Labourer/day 1,500.00


Add for tools 5% 5% 75.00
Cost of gang/day 1,575.00

Output of gang/day (20m2) 20.00 78.75


Cost of labour/m2 application. 123.50
Add GOH & profit. (30%) 25% 30.88
Cost/m2 154.38
CONCRETE WORK
B
Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 265.00 5,300.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 1,000.00 2,000.00
cost of hiring concrete mixer/day 22,300.00

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 1,486.67
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,500.00 2,500.00
4 Wheeler (Labourer)/day 4.00 2,500.00 10,000.00
16,500.00
Allow for tools 5% 5.00% 825.00
Cost of gangr/day 17,325.00

Output of gang/day (15m3) 15.00 1,155.00

Placing concrete in substructure


1 Discharger/day (Labourer)/day 1.00 2,500.00 2,500.00
4 Wheelers (Labourer)/day 4.00 2,500.00 10,000.00
2 Placers/day (Labourer)/day 2.00 2,500.00 5,000.00
17,500.00
Allow for tools 5% 5.00% 875.00
Cost of gangr/day 18,375.00

Output of gang/day (5m3) 5.00


Cost of placing/m3 3,675.00

Placing concrete in superstructure


1 Discharger/day (Labourer)/day 1.00 2,500.00 2,500.00
6 Wheelers (Labourer)/day 6.00 2,500.00 15,000.00
4Placers/day (Labourer)/day 4.00 2,500.00 10,000.00
27,500.00
Allow for tools 5% 5.00% 1,375.00
Cost of gangr/day 28,875.00

Output of gang/day (5m3) 5.00


Cost of placing/m3 5,775.00
Plain insi concrete (1:10:20mm aggregates) in
1 50mm blinding.

Materials
Bags of cement deliver to site/m3 3.50 2,700.00 9,450.00
1m3 of sharp sand 0.50 3,792.00 1,896.00
1 m3 of 20mm aggs. 1.00 4,462.00 4,462.00
15,808.00
Add for water and waste 7.50% 1,185.60
Cost of materials 16,993.60 16,993.60

Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (substr.) a.b. 3,675.00 6,316.67
Cost of concrete/m3 23,310.27

Cost of 50mm Blinding 0.05 1,165.51


Add GOH & profit. (30%) 25% 291.38
Cost/m2 1,456.89

Plain insitu concrete (1:3:6-20mm aggregates)


2 in substructure

Materials
Bags of cement deliver to site/m3 3.78 2,700.00 10,206.00
1m3 of sharp sand 0.40 3,792.00 1,516.80
1 m3 of 20mm aggs. 0.80 4,462.00 3,569.60
Cost of materials 15,292.40
Add for water and waste 7.50% 1,146.93
Add for:- 16,439.33
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (substr.) a.b. 3,675.00 6,316.67
Cost of concrete/m3 22,756.00

Add GOH & profit. (30%) 25% 5,689.00


Cost/m3 28,445.00

Plain insitu concrete (1:3:6-20mm aggregates)


3 in superstructure
Materials, Water. & waste a.b. 16,439.33
Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (superstructure.) 5,775.00 8,416.67
Cost of concrete/m3 24,856.00
Add GOH & profit. (30%) 25% 6,214.00
Cost/m3 31,070.00

Plain insitu concrete (1:2:4-20mm aggregates)


4 in substructure
Materials
Bags of cement deliver to site/m3 5.40 2,700.00 14,580.00
1m3 of sharp sand 0.38 3,792.00 1,440.96
1 m3 of 20mm aggs. 0.76 4,462.00 3,391.12
Cost of materials 19,412.08
Add for water and waste 5.00% 970.60
20,382.68
Add for:-
Plant a.b. 2,500.00
Laboure a.b. 1,155.00
Placing (substr.) a.b. 3,397.11 7,052.11
Cost of concrete/m3 27,434.80
Add GOH & profit. (30%) 25% 6,858.70
Cost/m3 34,293.50

Plain insitu concrete (1:2:4-20mm aggregates)


5 in superstructure
Materials, Water. & waste a.b. 20,382.68

Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (superstructure.) 5,775.00
8,416.67 8,416.67
Cost of concrete/m3 28,799.35
Add GOH & profit. (30%) 25% 7,199.84
Cost/m3 35,999.19

Reinforced insitu concrete (1:2:4-20mm


6 aggregates) in substructure
Materials, Water. & waste a.b. 20,382.68
Add for Volume shrinkage for concrete vibration 12.50% 2,547.84
22,930.52
Add for:-
Plant a.b. 2,500.00
Laboure a.b. 1,155.00
Placing (substr.) a.b. 3,397.11
7,052.11 7,052.11
29,982.63
Add GOH & profit. (30%) 25% 7,495.66
Cost/m3 37,478.29

Reinforced insitu concrete (1:2:4-20mm


7 aggregates) in superstructure
Materials, Water. & waste a.b. 20,382.68
Add for Volume shrinkage for concrete vibration 12.50% 2,547.84
Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (superstructure.) 5,775.00
8,416.67 8,416.67
Cost of concrete/m3 31,347.19
Add GOH & profit. (30%) 25% 7,836.80
Cost/m3 39,183.98

Reinforced insitu concrete (1:2:3-20mm


8 aggregates) in substructure
Materials
Bags of cement 6.30 2,700.00 17,010.00
1m3 of sharp sand 0.44 3,792.00 1,668.48
1 m3 of 20mm aggs. 0.67 4,462.00 2,989.54
Cost of materials 21,668.02 21,668.02
Add for water and waste 7.50% 1,625.10
23,293.12
Add for Volume shrinkage for concrete vibration 12.50% 2,911.64
Add for:- -
Plant a.b. 2,500.00 -
Laboure a.b. 1,155.00 -
Placing (substr.) a.b. 3,397.11
7,052.11 7,052.11
33,256.88
Add GOH & profit. (30%) 25% 8,314.22
Cost/m3 41,571.09

Reinforced insitu concrete (1:2:3-20mm


9 aggregates) in superstructure
Materials, Water. & waste a.b. 23,293.12
Add for Volume shrinkage for concrete vibration 12.50% 2,911.64

Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (superstructure.) 5,775.00
8,416.67 8,416.67
Cost of concrete/m3 34,621.43
Add GOH & profit. (30%) 25% 8,655.36
Cost/m3 43,276.79

Reinforced insitu concrete (1:1:5:3-20mm


10 aggregates) in substructure
Materials
Bags of cement 6.87 655.00 4,499.85
1m3 of sharp sand 0.36 517.00 186.12
1 m3 of 20mm aggs. 0.73 1,700.00 1,241.00
Cost of materials 5,926.97
Add for water and waste 7.50% 444.52
6,371.49
Add for Volume shrinkage for concrete vibration 12.50% 796.44
Add for:- -
Plant a.b. 2,500.00 -
Laboure a.b. 1,155.00 -
Placing (substr.) a.b. 3,397.11
7,052.11 7,052.11
14,220.04
Add GOH & profit. (30%) 25% 3,555.01
Cost/m3 17,775.05

Reinforced insitu concrete (1:1:5:3-20mm


11 aggregates) in superstructure
Materials, Water. & waste a.b. 6,371.49
Add for Volume shrinkage for concrete vibration 12.50% 796.44
Add for:-
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Placing (superstructure.) 5,775.00
8,416.67 8,416.67
Cost of concrete/m3 15,584.59
Add GOH & profit. (30%) 25% 3,896.15
Cost/m3 19,480.74

12 Mild steel bar reinforcement in concrete.


Materia
1 tonne of reinforcement bars 43,659.00
Add for cutting and waste 10% 4,365.90
48,024.90
Add for tying wires/tonne (0.01t) 0.01 480.25
48,505.15
Loading/off loading:
1No. Labourer 1.00 2,500.00 2,500.00
Allow for tools 5% 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-tonnes/day (2.00t) 2.00
Therefore cost/tonne 1,343.75
49,848.90

Mild steel bar reinforcement in concrete. Cont'd 49,848.90

Labour
1No. Iron-bender/day 1.00 5,000.00 5,000.00
1No. Labourer/day 1.00 2,000.00 2,000.00
7,000.00
Add for tools 5.00% 350.00
Cost of gang/day 7,350.00
Cost of gang/10 days 10.00 73,500.00

Output of gang cutting, bending & fixing = 1 tonnes


in 8 days. Therefore cost of labour for 1 tonne 1.00 73,500.00
123,348.90
Add GOH & profit. (30%) 25% 30,837.22
Cost/tonne 154,186.12
Cost/kg (kg/tonne ie 1000) 1,000.00 154.19

High yield deformed bar reinforcement In


13 concrete.

Materials
1 tonne of reinforcement bars 260,000.00
Add for cutting and waste 5% 13,000.00
273,000.00
Add for tying wires/tonne (10kg/tonne) 50% 8,000.00 4,000.00
Cost of loading/off loading a.b. 5% 13,650.00
Labour cutting, bending and fixing a.b. 73,500.00
364,150.00
Add GOH & profit. (30%) 25% 91,037.50
Cost/tonne 455,187.50
Cost/kg (tonne/1000) 1,000.00 455.19

BRC Mesh fabric reinforcement No.A.142


14 weighing 2.22kg/m2

Materials
Cost of Mesh/m2 1,150.00
Add for tying wires, lapping at joints and waste 15% 172.50
1,322.50
Labour
Cost of gang/day 7,350.00
33.00
Output of gang/days. (33m2) 222.73
Therefore cost of labour/m2 1,545.23
Add GOH & profit. (30%) 25% 386.31
Cost/m2 1,931.53

15 Sawn formwork to concrete

Materials
Cost of timber for formwork/m3 146,666.67
Therefore cost of formwork plank size 25 x 300 x
3600mm 0.027 146,666.67 3,960.00

Take 10m2

No. of planks in 10m2 =(9.11) 6.66


Cost of sawn formwork plank 6.66 3,960.00 26,373.60
Add for bearers, props, brackets etc 50% 13,186.80
39,560.40
Add for waste 5% 1,978.02
Cost of formwork materials useable- (3 times) 8.00 41,538.42

Therefore Cost of formwork materials useable-


once/m2 8.00 41,538.42 5,192.30

Labour

Preparation of 10m2 timber for formwork:


1No. Capenter/day 1.00 4,000.00 4,000.00
1N o. Labourer/day 1.00 2,000.00 2,000.00
6,000.00
Add for tools 0.00% -
6,000.00 6,000.00
Errecting and striking timber for formwork:
1No. Capenter/day 1.00 4,000.00 4,000.00
4N o. Labourer/day 4.00 2,000.00 8,000.00
12,000.00
Add for tools 5.00% 600.00
12,600.00 12,600.00
23,792.30
Add GOH & profit. (30%) 25% 5,948.08
Cost/ 10m2 29,740.38
Cost/m2 10.00 2,974.04
C BLOCKWORK.

Cement and Sand (1:6) Mortar:


Materials
Bags of cement 5.40 2,650.00 14,310.00
1m3 of sharp sand 1.14 3,148.00 3,588.72
Cost of materials 17,898.72
Add for water and waste 5.00% 894.94
18,793.66
Mixing
Plant a.b. 1,486.67
Laboure a.b. 1,155.00
Cost of Cement and Sand (1:6) Mortar/m3 21,435.32 21,435.32

150mm Hollow Sandcrete blockwork fiiled solid


with concrete (1;3;6-20mm aggs.) in
1 substructures.

Take 10m2
Materials
Sandcrete blocks/10m2 100.00 240.00 24,000.00
Add for waste 5% 1,200.00
25,200.00
M3 Cement and Sand (1:6) mortar (0.14m3) 0.14 21,435.32 3,000.95
Cost of materials 28,200.95 28,200.95

Labour
2No. Masons/day 2.00 4,000.00 8,000.00
2No. Labourers)day 2.00 2,000.00 4,000.00
12,000.00
Add for tools 5.00% 600.00
Cost of gang/day 12,600.00
Output of gang/day (10m2) 10.00
Therefore Cost of Labour/day 12,600.00
Cost of materials and labour 40,800.95

Filling cavities with concrete


Volume of Cavities of 10m2 in 150mm blocks
(0.71m3) 0.71
Concrete (1;3:6-20mm aggs.) 0.71 22,756.00 16,156.76
56,957.70
Add GOH & profit. (30%) 25% 14,239.43
Cost/ 10m2 71,197.13
Cost/m2 10.00 7,119.71

150mm Hollow Sandcrete blockwork fiiled solid


with concrete (1;3;6-20mm aggs.) in
2 superstructures.

Bags of cement deliver to site/m3 5.40 2,650.00 14,310.00


1m3 of sharp sand 0.38 3,792.00 1,440.96
1 m3 of 20mm aggs. 0.76 4,462.00 3,391.12
Cost of materials 19,142.08
Add for water and waste 7.50% 1,435.66
20,577.74
Add for:-
Plant a.b. 2,500.00
Laboure a.b. 1,155.00
Placing (substr.) a.b. 3,397.11 7,052.11
Cost of concrete/m3 27,629.85

Materials a.b. 28,200.95


Labour a.b. 12,600.00
Filling cavities with concrete
Volume of Cavities of 10m2 in 150mm blocks
(0.71m3) 0.71
27,629.85 19,617.19
Cost of Concrete (1;3:6-20mm aggs.) 60,418.14
Add GOH & profit. (30%) 25% 15,104.53
Cost/ 10m2 75,522.67
Cost/m2 10.00 7,552.27

Ditto filled solid with concrete (1:2;4-20mm


3 aggs.) in substructure.

Take 10m2 a.b.

Materials a.b. 28,200.95


Labour a.b. 12,600.00
Total cost of materials and labour 40,800.95

Filling cavity with concrete

Volume of cavities of 10m2 in 150mm blocks.


(0.71m3) 0.71
Cost of Concrete (1:2:4-20mm aggs.) 29,982.63 21,287.67
62,088.61
Add GOH & profit. (30%) 25% 15,522.15
Cost/ 10m2 77,610.77
Cost/m2 10.00 7,761.08 7,761.08

Ditto filled solid with concrete (1:2;4-20mm


4 aggs.) in superstructure.

Take 10m2 a.b.

Materials a.b. 28,200.95


Labour a.b. 12,600.00
Total cost of materials and laboure 40,800.95

Filling cavity with concrete

Volume of cavities of 10m2 in 150mm blocks.


(0.71m3) 0.71
Concrete (1:2:4-20mm aggs.) 31,347.19 22,256.50
63,057.45
Add GOH & profit. (30%) 25% 15,764.36
Cost/ 10m2 78,821.81
Cost/m2 10.00 7,882.18 7,882.18

230mm Hollow Sandcrete blockwork fiiled solid


with concrete (1;3;6-20mm aggs.) in
5 substructures.

Take 10m2
Materials
100No. Sandcrete blocks/10m2 100.00 220.00 22,000.00
Add for waste 5% 1,100.00
23,100.00
M3 Cement and Sand (1:6) mortar (0.23m3) 0.23 21,435.32 4,930.12
Cost of materials 28,030.12 28,030.12

Labour
2No. Masons/day 2.00 4,000.00 8,000.00
2No. Labourers)day 2.00 2,000.00 4,000.00
12,000.00
Add for tools 5.00% 600.00
Cost of gang/day 12,600.00
Output of gang/day (9m2) 10.00
Therefore Cost of Labour/day 1,260.00
29,290.12

Filling cavities with concrete 2,929.01

Volume of Cavities of 10m2 in 150mm blocks


(1.0.7m3) 1.07
Concrete (1;3:6-20mm aggs.) 1.07 22,756.00 24,348.92
56,568.05
Add GOH & profit. (30%) 25% 14,142.01
Cost/ 10m2 70,710.07
Cost/m2 10.00 7,071.01

230mm Hollow Sandcrete blockwork fiiled solid


with concrete (1;3;6-20mm aggs.) in
6 superstructures.

Take 10m2 a.b.


Total cost of materials and labour 29,290.12

Filling cavity with concrete

Volume of cavities of 10m2 in 150mm blocks.


(1.07m3) 1.07
Concrete (1:2:4-20mm aggs.) 24,856.00 26,595.92
55,886.04
Add GOH & profit. (30%) 25% 13,971.51
Cost/ 10m2 69,857.55
Cost/m2 10.00 6,985.76 6,985.76

Ditto filled solid with concrete (1:2;4-20mm


7 aggs.) in substructure.

Take 10m2 a.b.


Total cost of materials and laboure 29,290.12

Filling cavity with concrete

Volume of cavities of 10m2 in 150mm blocks.


(1.07m3) 1.07
Concrete (1:2:4-20mm aggs.) 29,982.63 32,081.42
61,371.54
Add GOH & profit. (30%) 25% 15,342.89
Cost/ 10m2 76,714.43
Cost/m2 10.00 7,671.44 7,671.44
Ditto filled solid with concrete (1:2;4-20mm
8 aggs.) in superstructure.

Take 10m2 a.b.


Total cost of materials and labour 29,290.12

Filling cavity with concrete

Volume of cavities of 10m2 in 150mm blocks.


(1.07m3) 1.07
Concrete (1:2:4-20mm aggs.) 31,347.19 33,541.49
62,831.61
Add GOH & profit. (30%) 25% 15,707.90
Cost/ 10m2 78,539.52
Cost/m2 10.00 7,853.95 7,853.95

9 150mm Hollow sandcretr block.

Take 10m2 a.b.


Materials and labour a.b. 27,629.85
Add GOH & profit. (30%) 25% 6,907.46
Cost/ 10m2 34,537.31
Cost/m2 10.00 3,453.73 3,453.73

10 230mm Hollow sandcretr block.

Take 10m2 a.b.


Materials and labour a.b. 29,290.12
Add GOH & profit. (30%) 25% 7,322.53
Cost/ 10m2 36,612.66
Cost/m2 10.00 3,661.27 3,661.27
D ROOFING COVERING.

0.70 Longspan deep trough aluuminium


sheeting with alucron finish fixed to steel
1 hardwood purlins.

Take 10m2
Materials

10m2 of alucrom finish 10.00 1,800.00 18,000.00


Allow for laps 15% 2,700.00
20,700.00
Allow for screw nails and waste 10% 2,070.00
Cost of materials 22,770.00

Labour
1No. Masons/day 1.00 3,500.00 3,500.00
1No. Labourers)day 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 5.00% 250.00
Cost of gang/8hrs-day 5,250.00
Output of gang/2hrs (10m2) 10.00
Therefore Cost of Labour/10m2 (4hrs) 4.00 1,312.50
24,082.50
Add GOH & profit. (30%) 25% 6,020.63
Cost/ 10m2 30,103.13
Cost/m2 10.00 3,010.31

0.70 Longspan deep trough aluuminium


sheeting with plain finish fixed to
2 steel/hardwood purlins.

Take 10m2
Materials

10m2 of plain finish 10.00 1,900.00 19,000.00


Allow for laps 15% 2,850.00
21,850.00
Allow for screw nails and waste 10% 2,185.00
Cost of materials 24,035.00
Labour
1No. Masons/day 1.00 3,500.00 3,500.00
1No. Labourers)day 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 7.50% 375.00
Cost of gang/8hrs-day 5,375.00
Output of gang/2hrs (10m2) 10.00
Therefore Cost of Labour/10m2 (4hrs) 4.00 1,343.75
25,378.75
Add GOH & profit. (30%) 25% 6,344.69
Cost/ 10m2 31,723.44
Cost/m2 10.00 3,172.34

0.55 Longspan deep trough aluuminium


sheeting with alucrom finish fixed to
3 steel/hardwood purlins.

Take 10m2
Materials

10m2 of alucrom finish 10.00 1,011.00 10,110.00


Allow for laps 15% 1,516.50
11,626.50
Allow for screw nails and waste 10% 1,162.65
Cost of materials 12,789.15

Labour
1No. Masons/day 1.00 3,500.00 3,500.00
1No. Labourers)day 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 7.50% 375.00
Cost of gang/8hrs-day 5,375.00
Output of gang/2hrs (10m2) 10.00
Therefore Cost of Labour/10m2 (4hrs) 4.00 1,343.75
14,132.90
Add GOH & profit. (30%) 25% 3,533.23
Cost/ 10m2 17,666.13
Cost/m2 10.00 1,766.61

0.55 Longspan deep trough aluuminium


sheeting with plain finish fixed to
4 steel/hardwood purlins.

Take 10m2
Materials

10m2 of plain finish 10.00 915.00 9,150.00


Allow for laps 15% 1,372.50
10,522.50
Allow for screw nails and waste 10% 1,052.25
Cost of materials 11,574.75

Labour
1No. Masons/day 1.00 3,500.00 3,500.00
1No. Labourers)day 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 7.50% 375.00
Cost of gang/8hrs-day 5,375.00
Output of gang/2hrs (10m2) 10.00
Therefore Cost of Labour/10m2 (4hrs) 4.00 1,343.75
12,918.50
Add GOH & profit. (30%) 25% 3,229.63
Cost/ 10m2 16,148.13
Cost/m2 10.00 1,614.81

0.70/0.55 Longspan deep trough aluuminium


sheeting accessories viz: capping, flashing etc
5 600mm girth.

Take cost @ approximately 65% of cost of


sheeting.

3mm plasprufe aluminium HC roof water


6 proofing membrane to vertical surfaces

Take 14m2
Materials

Cost of NT4 paralon waterproof membrane 14.00 1,195.00 16,730.00


Add for overlap and waste 10% 1,673.00
Cost of materials 18,403.00
Labour (applying 1No. Layer)
1No. Tiler 1.00 3,500.00 3,500.00
1No. Labourer 1.00 1,500.00 1,500.00
Cost of labour 5,000.00
Add for tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang/day (12m2) 12.00 447.92
Therefore Cost of Labour/14m2 14.00 6,270.83

Ness bitumen applied in 1No. Layer


Cost of 14m2 @ 4m2/litre 3.50 48.82 170.87

Labour (applying ness bitumen


1No. Labourer 1.00 1,500.00 1,500.00
Add for tools 7.50% 112.50
Cost of gang/day 1,612.50
Output of gang/day (20m2 20.00 80.63
Therefore Cost of Labour/14m2 14.00 1,128.75
25,973.45
Add GOH & profit. (30%) 25% 6,493.36
Cost/ 14m2 32,466.82
Cost/m2 14.00 2,319.06

3mm Plasprufe aluminium HC roof water


7 proofing membrane to horizontal surfaces

Take 14m2
Plasprufe (NT4-paralon) + labour a.b 19,999.06
Ness-bitumen applied in 2-layers @ 4m2/litre 7.00 48.82 341.74
20,340.80
Labour
Applying Ness bitumen- 2-layers @ N476.83 2.00 476.83 953.66
21,294.46
Add GOH & profit. (30%) 25% 5,323.62
Cost/ 14m2 26,618.08
Cost/m2 14.00 1,901.29

E CARPENTRY

1 50 X 50mm sawn hardwood in


noggins cut and fitted

Materials
cost per cubic meter (400m) 15,110.00
Add for nails and waste-10% 10% 1,511.00
16,621.00

Allow for seasoning 10% 1,662.10


18,283.10
Treatment:
0.50 Drum of solignum per m3 hardwood 0.50 2,150.00 1,075.00
19,358.10
Labour for treament
2 Labourer 2.00 1,500.00 3,000.00

Tools 7.50% 225.00


Cost of gang/day 3,225.00
Output of gang/day (1.5m3) 1.50
Therefore cost of labour in treatment for 1m3 2,150.00
20,266.36
Labour cutting and fitting:
1 Carpenter 1.00 3,500.00 3,500.00
1 Labourer 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-say 200m/day =(0.50m3) 0.50 10,750.00
31,016.36
Add GOH & profit. (30%) 25% 7,754.09
Cost/ 400m 38,770.45
Cost/m2 400.00 96.93

50 X 75mm sawn hardwood in purlins cut and


2 fitted

Materials
cost per cubic meter (267m) 15,110.00
Add for nails and waste-10% 10% 1,511.00
16,621.00

Allow for seasoning 10% 1,662.10


18,283.10
Treatment:
0.42 Drum of solignum per m3 hardwood 0.42 2,150.00 903.00
19,186.10

50 X 75mm sawn hardwood in purlins cut and


fitted cont'd 19,186.10

Labour for treament


2 Labourer 2.00 1,500.00 3,000.00

Tools 7.50% 225.00


Cost of gang/day 3,225.00
Output of gang/day (1.8m3) 1.80
Therefore cost of labour in treatment for 1m3 1,791.67
20,977.77
Labour cutting and fitting:
1 Carpenter 1.00 3,500.00 3,500.00
1 Labourer 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-say 134m/day =(0.80m3) 0.80 6,718.75
27,696.52
Add GOH & profit. (30%) 25% 6,924.13
Cost/ 267m 34,620.65
Cost/m2 267.00 129.67

50 X 100mm sawn hardwood in struts and ties


3 etc.

Materials
cost per cubic meter (200m) 44,800.00
Add for nails and waste-10% 10% 4,480.00
49,280.00

Allow for seasoning 10% 4,928.00


54,208.00
Treatment:
0.375 Drum of solignum per m3 hardwood 0.38 5,000.00 1,900.00
56,108.00
Labour for treament
2 Labourer 2.00 5,000.00 10,000.00

Tools 7.50% 750.00


Cost of gang/day 10,750.00
Output of gang/day (2m3) 2.00
Therefore cost of labour in treatment for 1m3 5,375.00
19,942.98

50 X 100mm sawn hardwood in struts and ties


etc. cont'd 19,942.98

Labour cutting and fitting:


1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 200m/day 1.00 6,450.00
26,392.98
Add GOH & profit. (30%) 25% 6,598.25
Cost/ 200m 32,991.23
Cost/m2 200.00 164.96

4 50 X 125mm sawn hardwood in ceiling joist etc.

Materials
cost per cubic meter (160m) 15,110.00
Add for nails and waste-10% 10% 1,511.00
16,621.00

Allow for seasoning 10% 1,662.10


18,283.10
Treatment:
0.355 Drum of solignum per m3 hardwood 0.36 5,000.00 1,800.00
20,083.10
Labour for treament
2 Labourer 2.00 2,000.00 4,000.00

Tools 7.50% 300.00


Cost of gang/day 4,300.00
Output of gang/day (2.15m3) 2.15
Therefore cost of labour in treatment for 1m3 2,000.00
19,942.98
Labour cutting and fitting:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 200m/day 1.00 6,450.00
26,392.98
Add GOH & profit. (30%) 25% 6,598.25
Cost/ 160m 32,991.23
Cost/m2 160.00 206.20

50 X 150mm sawn hardwood in struts and ties


5 etc.

Materials
cost per cubic meter (133m) 24,050.00
Add for nails and waste-10% 10% 2,405.00
26,455.00

Allow for seasoning 10% 2,645.50


29,100.50
Treatment:
0.335 Drum of solignum per m3 hardwood 0.34 3,000.00 1,020.00

Labour for treament


2 Labourer 2.00 2,000.00 4,000.00

Tools 7.50% 300.00


Cost of gang/day 4,300.00
Output of gang/day (2.26m3) 2.26
Therefore cost of labour in treatment for 1m3 1,902.65
19,942.98
Labour cutting and fitting:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 200m/day 1.00 6,450.00
26,392.98
Add GOH & profit. (30%) 25% 6,598.25
Cost/ 133m 32,991.23
Cost/m2 133.00 248.05

METAL WORK

1 Crittal-Hope standard door frame type DIA-27

Cost of 1 No. Door frame 2,258.00


Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-frames/day (2No.) 2.00
Therefore cost of labour fixing frame 3,225.00
5,483.00
Add GOH & profit. (30%) 25% 1,370.75
Cost of each 6,853.75

2 Crittal-Hope standard door frame type DIA-30

Cost of 1 No. Door frame 2,291.00


Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-frames/day (2No.) 2.00
Therefore cost of labour fixing frame 3,225.00
5,516.00
Add GOH & profit. (30%) 25% 1,379.00
Cost of each 6,895.00

3 Crittal-Hope standard door frame type DIA-33

Cost of 1 No. Door frame 2,314.86


Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-frames/day (2No.) 2.00
Therefore cost of labour fixing frame 3,225.00
5,539.86
Add GOH & profit. (30%) 25% 1,384.97
Cost of each 6,924.83

4 Crittal-Hope standard door frame type DIA-54

Cost of 1 No. Door frame 2,604.02


Labour
1 Mason 1.00 638.94 638.94
1 Laboure 1.00 633.67 633.67
1,272.61
Tools 7.50% 95.45
Cost of gang/day 1,368.06
Output of gang-frames/day (2No.) 1.50
Therefore cost of labour fixing frame 912.04
3,516.06
Add GOH & profit. (30%) 25% 879.01
Cost of each 4,395.07
G FLOOR FINISHINGS

1 50mm Cement and sand (1:3) in paving.

Materials
Bags of cement/m3 9.44 1,550.00 14,632.00
m3 of sand 1.00 3,792.00 3,792.00
18,424.00
Add for waste 10% 1,842.40
Cost of materials 20,266.40 20,266.40

Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 130.00 2,600.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 600.00 1,200.00
cost of hiring concrete mixer/day 18,800.00

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 1,253.33
Labour
1 Foreman/day 1.00 3,500.00 3,500.00
1 Fitter (Laboure)/day 1.00 1,500.00 1,500.00
4 Wheeler (Labourer)/day 4.00 1,500.00 6,000.00
11,000.00
Add for tools 7.50% 825.00
Cost of gangr/day 11,825.00

Output of gang/day (15m3) 15.00 788.33


Cost of cement and sand (1:3) in mortar/m3 22,308.07

Take - 100m2 area


Quantity of mortar (1:4) 100.00 0.05 5.00
Add for application waste 10% 0.50
5.50
Cost of mortar (1:4) 5.50 22,308.07 122,694.37

Labour
1 Mason 1.00 3,500.00 3,500.00
1 Laboure 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 53,750.00
176,444.37
Add for screes 2.50% 4,411.11
180,855.48
Add GOH & profit. (30%) 25% 45,213.87
Cost/100m2 100.00 226,069.34
Cost/m2 2,260.69

50mm insitu terrazzo paving laid in 1200 x


1200mm panels divided with and including
2 3mm ebonite dividing in floor paving

Bags of cement 12.68 1,550.00 19,654.00


0.89m3 mable chips @ 2,700kg/m3 0.89 2700.00
2,403.00 16.85 40,490.55
60,144.55
Add for waste 10% 6,014.46
66,159.01
Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 15,900.96

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 1,060.06
Labour
1 Foreman/day 1.00 3,500.00 3,500.00
1 Fitter (Laboure)/day 1.00 1,500.00 1,500.00
4 Wheeler (Labourer)/day 4.00 1,500.00 6,000.00
11,000.00
Add for tools 7.50% 825.00
Cost of gangr/day 11,825.00

Output of gang/day (15m3) 15.00 788.33


Cost of cement and sand (1:3) in mortar/m3 68,007.40

Take - 10m2 area


20mm Terrazzo top
Quantity of mortar (1:4) 10.00 0.02 0.20
Add for application waste 10% 0.02
0.22
Cost of mortar (1:4) 0.22 68,007.40 14,961.63

Labour
1 Pavre 1.00 3,500.00 3,500.00
2 Laboures 2.00 1,500.00 3,000.00
6,500.00
Tools 7.50% 487.50
Cost of gang/day 6,987.50
Output of gang-(18m2) 1.80
Therefore cost of labour fixing frame 3,881.94
18,843.57

30mm cement and sand screed (1:3) 10.00 0.03 0.30


Add for application waste 8% 0.02
0.32
Cost of mortar (1:3) 0.32 22,308.07 7,194.35
26,037.92

50mm insitu terrazzo paving laid in 1200 x


1200mm panels divided with and including
3mm ebonite dividing in floor paving (cont'd) 26,037.92

Labour
1 Mason 1.00 3,500.00 3,500.00
1 Laboure 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-(18m2) 2.00
Therefore cost of labour /10m2 2,687.50
28,725.42
Add for polishing and application of ebonite dividing
strips plus cement slurry 20% 5,745.08
34,470.51
Add GOH & profit. (30%) 25% 8,617.63
Cost of paving/10m2 10.00 43,088.14
Cost of paving/m2 4,308.81
50mm white insitu terrazzo paving laid in 1200 x
1200mm panels divided with and including
3 3mm ebonite dividing strips in floor paving

Bags white cement 12.68 2,055.00 26,057.40


0.89m3 mable chips @ 2.700kg/m3 2,403.00 16.85 40,490.55
66,547.95
Add for waste 10% 6,654.80
73,202.75
Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 15,900.96

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 1,060.06
Labour
1 Foreman/day 1.00 3,500.00 3,500.00
1 Fitter (Laboure)/day 1.00 1,500.00 1,500.00
4 Wheeler (Labourer)/day 4.00 1,500.00 6,000.00
11,000.00
Add for tools 7.50% 825.00
Cost of gangr/day 11,825.00

Output of gang/day (15m3) 15.00 788.33


Cost of cement and sand (1:3) in mortar/m3 75,051.14

50mm white insitu terrazzo paving laid in 1200 x


1200mm panels divided with and including
3mm ebonite dividing strips in floor paving
cont'd 75,051.14

Take - 10m2 area

20mm Terrazzo top


Quantity of mortar (1:4) 10.00 0.02 0.20
Add for application waste 10% 0.02
0.22
Cost of mortar (1:4) 0.22 75,051.14 16,511.25

Labour
1 Pavre 1.00 3,500.00 3,500.00
2 Laboures 2.00 1,500.00 3,000.00
6,500.00
Tools 7.50% 487.50
Cost of gang/day 6,987.50
Output of gang-(18m2) 1.80
Therefore cost of labour fixing frame 3,881.94
20,393.20

30mm cement and sand screed (1:3) 10.00 0.03 0.30


Add for application waste 8% 0.02
0.32
Cost of mortar (1:3) 0.32 22,308.07 7,194.35

Labour
1 Mason 1.00 3,500.00 3,500.00
1 Laboure 1.00 1,500.00 1,500.00
5,000.00
Tools 7.50% 375.00
Cost of gang/day 5,375.00
Output of gang-(18m2) 2.00
Therefore cost of labour /10m2 2,687.50
30,275.05
Add for polishing and application of ebonite dividing
strips plus cement slurry 20% 6,055.01
36,330.06
Add GOH & profit. (30%) 25% 9,082.51
Cost of paving/10m2 10.00 45,412.57
Cost of paving/m2 4,541.26

50mm insitu granolithic paving laid in 1200 x


1200mm panels divided with and including
4 3mm ebonite dividing strips in floor paving

Bags cement 12.68 1,550.00 19,654.00


M3 of graite chips 0.89 4,462.00 3,971.18
23,625.18
Add for waste 10% 2,362.52
25,987.70
Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 15,900.96
Output of mixer/day (20m2) (15m3) 15.00
Cost of plantr/day 1,060.06

Labour
1 Foreman/day 1.00 3,500.00 3,500.00
1 Fitter (Laboure)/day 1.00 1,500.00 1,500.00
4 Wheeler (Labourer)/day 4.00 1,500.00 6,000.00
11,000.00
Add for tools 7.50% 825.00
Cost of gangr/day 11,825.00

Output of gang/day (15m3) 15.00 788.33


Cost of cement and sand (1:3) in mortar/m3 27,836.10

Take - 10m2 (50mm thick)

Quantity of mortar (1:4) 10.00 0.05 0.50


Add for application waste 10% 0.05
0.55
Cost of mortar (1:4) 0.55 27,836.10 15,309.85

Labour
1 Pavre 1.00 3,500.00 3,500.00
2 Laboures 2.00 1,500.00 3,000.00
6,500.00
Add for tools 7.50% 487.50
Cost of gang/day 6,987.50
Output of gang-(18m2) 0.90
Therefore cost of labour /10m2 7,763.89
23,073.74
Add for polishing and application of ebonite dividing
strips plus cement slurry 30% 6,922.12
29,995.86
Add GOH & profit. (30%) 45% 13,498.14
Cost of paving/10m2 10.00 43,494.00
Cost of paving/m2 4,349.40

400 x 400 x 6mm marazzi vitrified anti-acid


5 unglazed ceramic floor tiles

Cost/m2 2,800.00
Take 10m2

Materials
Cost of tiles 10.00 2,800.00 28,000.00
Add for maiching coloured cement/waste 15% 4,200.00 32,200.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71

Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
41,860.71
Allow for pointing/polishing/washing surface 2% 837.21
42,697.93
Add GOH & profit. (30%) 30% 12,809.38
Cost of paving/10m2 10.00 55,507.31
Cost of paving/m2 5,550.73

200 x 200 x 6mm unglazed ceramic floor tiles


6 paving.

Cost/m2 1,650.00
Take 10m2

Materials
Cost of tiles 10.00 1,650.00 16,500.00
Add for maiching coloured cement/waste 15% 2,475.00 18,975.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71

Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
28,635.71

300 x 300 x 6mm marazzi vitrified anti-acid


unglazed ceramic floor tiles cont'd 28,635.71

Allow for pointing/polishing/washing surface 2% 572.71


29,208.43
Add GOH & profit. (30%) 45% 13,143.79
Cost of paving/10m2 10.00 42,352.22
Cost of paving/m2 4,235.22

300 x 300 x 6mm marazzi vitrified anti-acid


5 unglazed ceramic floor tiles

Cost/m2 2,000.00
Take 10m2

Materials
Cost of tiles 10.00 2,000.00 20,000.00
Add for maiching coloured cement/waste 15% 3,000.00 23,000.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71

Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
32,660.71
Allow for pointing/polishing/washing surface 2% 653.21
33,313.93
Add GOH & profit. (30%) 30% 9,994.18
Cost of paving/10m2 10.00 43,308.11
Cost of paving/m2 4,330.81

200 x 200 x 6mm unglazed ceramic floor tiles


6 paving.

Cost/m2 1,650.00
Take 10m2

Materials
Cost of tiles 10.00 1,650.00 16,500.00
Add for maiching coloured cement/waste 15% 2,475.00 18,975.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71

Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
28,635.71

300 x 300 x 6mm marazzi vitrified anti-acid


unglazed ceramic floor tiles cont'd 28,635.71

Allow for pointing/polishing/washing surface 2% 572.71


29,208.43
Add GOH & profit. (30%) 45% 13,143.79
Cost of paving/10m2 10.00 42,352.22
Cost of paving/m2 4,235.22
300 x600 x 20mm Royale perlato unp0lised
7 marble floor tiles.

Cost/m2 5,950.00
Take 10m2

Materials
Cost of tiles 10.00 5,950.00 59,500.00
Add for maiching coloured cement/waste 15% 8,925.00 68,425.00
Kerokoll tile adhesive-25kg bag 1.00 1,938.00 1,938.00
Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide
by 10m2 7m2 0.70
Cost of adhesive/10m2 2,768.57

Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 5,375.00
76,568.57
Allow for pointing/polishing/washing surface 10% 7,656.86
84,225.43
Add GOH & profit. (30%) 45% 37,901.44
Cost of paving/10m2 10.00 122,126.87
Cost of paving/m2 12,212.69

600 x 300 x 12mm polished CIBI Africa multi-


8 coloured granite floor tiles.

Cost/m2 8,500.00
Take 10m2
Materials
Cost of tiles 10.00 16,000.00 160,000.00
Add for maiching coloured cement/waste 15% 24,000.00 184,000.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00

300 x 300 x 12mm polished CIBI Africa multi-


coloured granite floor tiles. Cont'd 184,000.00

Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide


by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
201,185.71
Allow for pointing/polishing/washing surface 2% 4,023.71
205,209.43
Add GOH & profit. (30%) 25% 51,302.36
Cost of paving/10m2 10.00 256,511.79
Cost of paving/m2 25,651.18

300 x 300 x 12mm polished CIBI Africa multi-


8 coloured granite floor tiles.

Cost/m2 8,500.00
Take 10m2
Materials
Cost of tiles 10.00 8,500.00 85,000.00
Add for maiching coloured cement/waste 15% 12,750.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00 100,750.00

300 x 300 x 12mm polished CIBI Africa multi-


coloured granite floor tiles. Cont'd 100,750.00

Spreead/bag (7m2) ( note. 7m2 = 0.70) ie divide


by 10m2 7m2 0.70
Cost of adhesive/10m2 4,285.71

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
117,935.71
Allow for pointing/polishing/washing surface 2% 2,358.71
120,294.43
Add GOH & profit. (30%) 25% 30,073.61
Cost of paving/10m2 10.00 150,368.04
Cost of paving/m2 15,036.80
9 300 x 300 x 1.4mm pvc tiles paving

Cost/m2 450.00
Take 10m2
Materials
Cost of tiles 10.00 450.00 4,500.00
Add for waste 10% 450.00 4,950.00
1 PVC tiles adhesive 1.00 1,000.00 1,000.00
Spreead/bag (15m2) ( note. 15m2 = 1.5) ie divide
by 10m2 1.5m2 1.50
Cost of adhesive/10m2 666.67

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(1.4m2) 1.4m2 1.40
Therefore cost of labour/10m2 4,607.14
10,223.81

Allow for cleaning surfaces 2% 204.48


10,428.29
Add GOH & profit. (30%) 45% 4,692.73
Cost of paving/10m2 10.00 15,121.01
Cost of paving/m2 1,512.10

10 44mm Cement and sand (1:3) in screeded beds

Take - 100m2
Quantity of mortar 100.00 0.04 4.40
Add for application waste 10% 0.44
4.84 4.84m3
Cost of mortar (1:3) 4.84 22,308.07 107,971.04

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 12m2 0.12
Therefore cost of labour/100m2 53,750.00
161,721.04
Add GOH & profit. (30%) 45% 72,774.47
Cost/100m2 100.00 234,495.51
Cost/m2 2,344.96
11 38mm Cement and sand (1:3) in screeded beds

Take - 100m2
Quantity of mortar 100.00 0.04 3.80
Add for application waste 10% 0.38
4.18
Cost of mortar (1:3) 4.18 22,308.07 93,247.72

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 14m2 0.14
Therefore cost of labour/100m2 46,071.43
139,319.15
Add GOH & profit. (30%) 45% 62,693.62
Cost/100m2 100.00 202,012.76
Cost/m2 2,020.13

12 48mm Cement and sand (1:3) in screeded beds

Take - 100m2
Quantity of mortar 100.00 0.05 4.80
Add for application waste 10% 0.48
5.28
Cost of mortar (1:3) 5.28 22,308.07 117,786.59

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 10m2 0.10
Therefore cost of labour/100m2 64,500.00
182,286.59
Add GOH & profit. (30%) 45% 82,028.97
Cost/100m2 100.00 264,315.56
Cost/m2 2,643.16
WALL FINISHINGS

1 13mm Cement and sand (1:4) rendering to wall

Materials
Bags of cement/m3 7.55 2,500.00 18,875.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 1,900.00
25,170.38
Add for waste 10% 2,517.04
Cost of materials 27,687.42 27,687.42

Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 265.00 5,300.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 1,000.00 2,000.00
cost of hiring concrete mixer/day 22,300.00
Output of mixer/day (20m2) (15m3) 15.00
Cost of plantr/day 1,486.67

Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 30,177.42

Take - 100m2 area


Quantity of mortar (1:4) 100.00 0.01 1.30
Add for application waste 10% 0.13
1.43
Cost of mortar (1:4) 1.43 30,177.42 43,153.71

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
96,903.71

13mm Cement and sand (1:4) rendering to wall


(cont'd) 96,903.71

Add for arises 2.50% 2,422.59


99,326.31
25% 24,831.58
Cost/100m2 100.00 124,157.88
Cost/m2 1,241.58

2 15mm Cement and sand (1:4) in paving.

Materials
Bags of cement/m3 7.55 2,500.00 18,875.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
23,907.88
Add for waste (10%) 10% 2,390.79
Cost of materials 26,298.67 26,298.67

Plant
Cost of hiring concrete mixer/day 1.00 15,000.00 15,000.00
20 litres diesel/day 20.00 265.00 5,300.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 1,000.00 2,000.00
cost of hiring concrete mixer/day 22,300.00

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 1,486.67
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 28,788.67

Take - 100m2 area


Quantity of mortar (1:4) 100.00 0.02 1.50
Add for application waste 10% 0.15
1.65
Cost of mortar (1:4) 1.65 28,788.67 47,501.31

15mm Cement and sand (1:4) in paving. (cont'd) 47,501.31

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
101,251.31
Add for arises 2.50% 2,531.28
103,782.59
Add GOH & profit. (30%) 45% 46,702.17
Cost/100m2 100.00 150,484.76
Cost/m2 1,504.85
3 13mm Cement and sand (1:6) in paving.

Materials
Bags of cement/m3 5.40 2,500.00 13,500.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
18,846.84
Add for waste 10% 1,884.68
Cost of materials 20,731.52 20,731.52

Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 265.00 5,300.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 1,000.00 2,000.00
cost of hiring concrete mixer/day 16,800.00

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 1,120.00
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 22,854.86

13mm Cement and sand (1:6) in paving. (cont'd) 22,854.86

Take - 100m2 area


Quantity of mortar (1:4) 100.00 0.01 1.30
Add for application waste 10% 0.13
1.43
Cost of mortar (1:6) 1.43 22,854.86 32,682.45

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
86,432.45
Add for arises 2.50% 2,160.81
88,593.26
Add GOH & profit. (30%) 45% 39,866.97
Cost/100m2 100.00 128,460.22
Cost/m2 1,284.60

4 15mm Cement and sand (1:6) in paving.

Materials
Bags of cement/m3 5.40 2,500.00 13,500.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
18,846.84
Add for waste 10% 1,884.68
Cost of materials 20,731.52 20,731.52

Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 693.40
21,424.92

15mm Cement and sand (1:6) in paving. (cont') 21,424.92

Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:6) in mortar/m3 22,428.25

Take - 100m2 area


Quantity of mortar (1:6) 100.00 0.02 1.50
Add for application waste 10% 0.15
1.65
Cost of mortar (1:4) 1.65 22,428.25 37,006.62

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /100m2 53,750.00
90,756.62
Add for arises 2.50% 2,268.92
93,025.54
Add GOH & profit. (30%) 45% 41,861.49
Cost/100m2 100.00 134,887.03
Cost/m2 1,348.87

152x 152 x 6mm whiteglazed cushion edge


5 ceramic wall tiles.

Cost/m2
Take 10m2
Materials
Cost of tiles 10.00 1,100.00 11,000.00
Add for maiching coloured cement/waste 15% 1,650.00 12,650.00
Kerokoll tile adhesive-25kg bag 1.00 1,200.00 1,200.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 1,200.00
13,850.00

152x 152 x 6mm whiteglazed cushion edge


ceramic wall tiles. (cont'd) 13,850.00

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
26,750.00
Allow for pointing/polishing/washing surface 2% 535.00
27,285.00
Add GOH & profit. (30%) 45% 12,278.25
Cost of paving/10m2 10.00 39,563.25
Cost of paving/m2 3,956.33

152x 200 x 6mm whiteglazed cushion edge


6 ceramic wall tiles.

Cost/m2
Take 10m2
Materials
Cost of tiles 10.00 1,850.00 18,500.00
Add for maiching coloured cement/waste 15% 2,775.00 21,275.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 3,000.00

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour fixing frame 12,900.00
37,175.00
Allow for pointing/polishing/washing surface 2% 743.50
37,918.50
Add GOH & profit. (30%) 45% 17,063.33
Cost of paving/10m2 10.00 54,981.83
Cost of paving/m2 5,498.18

250 400 x 6mm colureglazed cushion edge


6 ceramic wall tiles.

Cost/m2 4,300.00
Take 10m2
Materials
Cost of tiles 10.00 4,300.00 43,000.00
Add for maiching coloured cement/waste 15% 6,450.00 49,450.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 3,000.00

Labour
1 Pavre 1.00 1,500.00 1,500.00
1 Laboures 1.00 1,000.00 1,000.00
2,500.00
Add for tools 7.50% 187.50
Cost of gang/day 2,687.50
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour fixing frame 5,375.00
57,825.00
Allow for pointing/polishing/washing surface 2% 1,156.50
58,981.50
Add GOH & profit. (30%) 30% 17,694.45
Cost of paving/10m2 10.00 76,675.95
Cost of paving/m2 7,667.59

300x 600 x206mm Rorale perlato polished


7 calibrated marble wall tiles.

Cost/m2
Take 10m2
Materials
Cost of tiles 10.00 7,850.00 78,500.00
Add for maiching coloured cement/waste 15% 11,775.00 90,275.00
Kerokoll tile adhesive-25kg bag 1.00 3,000.00 3,000.00
Spreead/bag (10m2) ( note. 10m2 = 1) ie divide by
10m2 10m2 1.00
Cost of adhesive/10m2 3,000.00

Labour
1 Pavre 1.00 4,000.00 4,000.00
1 Laboures 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(5m2) 5m2 0.50
Therefore cost of labour /10m2 12,900.00
106,175.00
Allow for pointing/polishing/washing surface 2% 2,123.50
108,298.50
Add GOH & profit. (30%) 45% 48,734.33
Cost of paving/10m2 10.00 157,032.83
Cost of paving/m2 15,703.28

8 13mm Cement and sand (1:3) in paving.

Materials
Bags of cement/m3 9.44 2,500.00 23,600.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
28,946.84
Add for waste 10% 2,894.68
Cost of materials 31,841.52 31,841.52

Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 693.40
32,534.92

8 13mm Cement and sand (1:3) in paving. (cont.d) 32,534.92

Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 33,538.25

Take - 100m2 area


Quantity of mortar (1:3) 100.00 0.01 1.30
Add for application waste 10% 0.13
1.43
Cost of mortar (1:3) 1.43 33,538.25 47,959.70

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(12m2) 0.12
Therefore cost of labour /10m2 53,750.00
101,709.70
Add for arises 2.50% 2,542.74
104,252.45
Add GOH & profit. (30%) 45% 46,913.60
Cost/100m2 100.00 151,166.05
Cost/m2 1,511.66
CEILING FINISHINGS

12mm particle board or other equal and


1 approved in ceiling lining.

Cost of 1No sheet board size 2440 x 1220mm


@N1076 1,076.00 2.98 361.46

Take 10m2
Materials.
Cost of particle board in 10m2 10.00 361.46 3,614.62
50 x 20mm wrought hardwood cover strips @
N15.11 76.00 15.11 1,148.36
4,762.98
Allow for nails and waste 10% 476.30
Cost of materials 5,239.28 5,239.28

Labour:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 12m2/day (note: 12m2 =1.2m2,
ie divide by 10m2) 12m2 1.20
Therefore cost labour per 10m2 5,375.00
10,614.28
Add GOH & profit. (30%) 45% 4,776.42
Cost/ 10m2 15,390.70
Cost/m2 10.00 1,539.07

12mm celotex board or other equal and


2 approved in ceiling lining.
Cost of 1No celotex board size 2440 x 1220mm @
N1130 1,130.00 2.98 379.60

Take 10m2
Materials.
Cost of particle board in 10m2 10.00 379.60 3,796.02
50 x 20mm wrought hardwood cover strips @
15.11 76.00 15.11 1,148.36
4,944.38
Allow for nails and waste 10% 494.44
Cost of materials 5,438.82 5,438.82

12mm celotex board or other equal and


approved in ceiling lining. (cont'd) 5,438.82

Labour:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 12m2/day (note: 12m2 =1.2m2,
ie divide by 10m2) 12m2 1.20
Therefore cost labour per 10m2 5,375.00
10,813.82
Add GOH & profit. (30%) 45% 4,866.22
Cost/ 10m2 15,680.04
Cost/m2 10.00 1,568.00

6mm Hard board or other equal and approved in


3 ceiling lining.

Cost of 1No celotex board size 2440 x 1220mm @


N460 460.00 2.98 154.53

Take 10m2
Materials.
Cost of particle board in 10m2 10.00 154.53 1,545.28
50 x 20mm wrought hardwood cover strips 76.00 1.60 121.60
1,666.88
Allow for nails and waste 10% 166.69
Cost of materials 1,833.57 1,833.57

Labour:
1 Carpenter 1.00 4,000.00 4,000.00
1 Labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-say 12m2/day (note: 12m2 =1.2m2,
ie divide by 10m2) 12m2 1.20
Therefore cost labour per 10m2 5,375.00
7,208.57
Add GOH & profit. (30%) 45% 3,243.86
Cost/ 10m2 10,452.43
Cost/m2 10.00 1,045.24

4 13mm Cement and sand (1:4) rendering


to soffit

Materials
Bags of cement/m3 7.55 2,500.00 18,875.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
23,907.88
Add for waste 10% 2,390.79
Cost of materials 26,298.67 26,298.67

Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0 20.00 26.00 520.00
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96
Output of mixer/day (20m2) (15m3) 15.00
Cost of plantr/day 693.40

Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 27,995.40

Take - 100m2 area


Quantity of mortar (1:4) 100.00 0.01 1.30
Add for application waste 10% 0.13
1.43
Cost of mortar (1:4) 1.43 27,995.40 40,033.43

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 64,500.00
104,533.43
Add for arises 2.50% 2,613.34
107,146.76
Add GOH & profit. (30%) 45% 48,216.04
Cost/100m2 100.00 155,362.80
Cost/m2 1,553.63

5 15mm Cement and sand (1:4) rendering


to soffit

Materials
Bags of cement/m3 7.55 2,000.00 15,100.00
m3 of plaster sand 1.06 4,131.00 4,395.38
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
20,132.88
Add for waste 10% 2,013.29
Cost of materials 22,146.17 22,146.17

Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0 20.00 26.00 520.00
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 693.40
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 23,842.90

Take - 100m2 area


Quantity of mortar (1:4) 100.00 0.02 1.50
Add for application waste 10% 0.15
1.65
Cost of mortar (1:4) 1.65 23,842.90 39,340.79

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 64,500.00
103,840.79
Add for arises 2.50% 2,596.02
106,436.81
Add GOH & profit. (30%) 45% 47,896.56
Cost/100m2 100.00 154,333.37
Cost/m2 1,543.33

6 13mm Cement and sand (1:6) rendering


to soffit
Materials
Bags of cement/m3 5.40 2,000.00 10,800.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
16,146.84
Add for waste 10% 1,614.68
Cost of materials 17,761.52 17,761.52

Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 693.40
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 19,458.25
Take - 100m2 area
Quantity of mortar (1:4) 100.00 0.01 1.30
Add for application waste 10% 0.13
1.43
Cost of mortar (1:6) 1.43 19,458.25 27,825.30
Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 64,500.00
92,325.30
Add for arises 2.50% 2,308.13
94,633.44
Add GOH & profit. (30%) 45% 42,585.05
Cost/100m2 100.00 137,218.48
Cost/m2 1,372.18

7 13mm Cement and sand (1:6) rendering to soffit

Materials
Bags of cement/m3 5.40 2,000.00 10,800.00
m3 of plaster sand 1.14 4,131.00 4,709.34
Sika plastiment BV40 plasticiser/2000 litres/drum
@ N8500 consumption 1.5lit/m3 1.50 8,500.00 637.50
16,146.84
Add for waste 10% 1,614.68
Cost of materials 17,761.52 17,761.52

Plant
Cost of hiring concrete mixer/day 1.00 9,500.00 9,500.00
20 litres diesel/day 20.00 26.00 520.00
Lubricating oil @ N800.00/gallon(4.20 litres) @ 2.0
litres 2.00 190.48 380.96
cost of hiring concrete mixer/day 10,400.96

Output of mixer/day (20m2) (15m3) 15.00


Cost of plantr/day 693.40
Labour
1 Foreman/day 1.00 4,000.00 4,000.00
1 Fitter (Laboure)/day 1.00 2,000.00 2,000.00
4 Wheeler (Labourer)/day 4.00 2,000.00 8,000.00
14,000.00
Add for tools 7.50% 1,050.00
Cost of gangr/day 15,050.00

Output of gang/day (15m3) 15.00 1,003.33


Cost of cement and sand (1:3) in mortar/m3 19,458.25

Take - 100m2 area


Quantity of mortar (1:6) 100.00 0.02 1.50
Add for application waste 10% 0.15
1.65
Cost of mortar (1:4) 1.65 19,458.25 32,106.12

Labour
1 Mason 1.00 4,000.00 4,000.00
1 Laboure 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00
Output of gang-(10m2) 10.00
Therefore cost of labour /100m2 64,500.00
96,606.12
Add for arises 2.50% 2,415.15
99,021.27
Add GOH & profit. (30%) 45% 44,559.57
Cost/100m2 100.00 143,580.85
Cost/m2 1,435.81

PAINTING AND DECORATING

Prepare, prime and apply two coats of


1 emulsion paint to rendered surfaces

Emulsion paint-4litre tin 26,577.83


Therefore cost of emulsion paint/litre 26,577.83 80.00 332.22

Take 100m2
Materials.
Covering capacity of emulsion paint/litre
1st coat-1litre/11m2 80.00 0.34 27.20 litre
2nd coat-1litre/6m2 80.00 0.34 27.20 litre
3rd coat-1litre/6m2 80.00 0.17 13.33 litre
67.73
Add for waste 10% 6.77
74.51 litre
Emulsion paint in 3 coats 74.51 332.22 24,752.82
Labour
1 painter 1.00 4,000.00 4,000.00
1 labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00

Output of gang-(20m2)(note: 20m2 divide by


100m2=0.20 0.20
Therefore cost of labour /100m2 32,250.00
57,002.82
Add GOH & profit. (30%) 25% 14,250.70
Cost/100m2 100.00 71,253.52
Cost/m2 712.54

Prepare, touch up prime and apply two under


coats and one finishing coat gloss paint to
2 metal surfaces.

Cost of 1No. Gallon gloss paint-4litre tin 1,767.56


Therefore cost of gloss paint/litre 1,767.56 4.00 441.89

Take 100m2
Materials.
Covering capacity of gloss paint/litre
1st coat-1litre/9m2 100.00 0.111 11.11 litre
2nd coat-1litre/7m2 100.00 0.14 14.29 litre
3rd coat-1litre/7m2 100.00 0.14 14.29 litre
39.68

Prepare, touch up prime and apply two under


coats and one finishing coat gloss paint to
metal surfaces. (cont'd) 39.68

Add for waste 10% 3.97


43.65 litre
Add for touching up primer 7.50% 3.27
46.92
Gloss paint in 3 coats 46.92 441.89 20,735.51
Labour
1 painter 1.00 4,000.00 4,000.00
1 labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00

Output of gang-(18m2)(note: 18m2 divide by


100m2=0.18 0.18
Therefore cost of labour /100m2 35,833.33
56,568.85
Add GOH & profit. (30%) 45% 25,455.98
Cost/100m2 100.00 82,024.83
Cost/m2 820.25
Knot, prime, stop and apply two under coats
and one finishing coat gloss paint to wood
3 surfaces.

Cost of 1No. Gallon gloss paint-4litre tin 1,767.56


Therefore cost of gloss paint/litre 1,767.56 4.00 441.89

Take 100m2
Materials.
Covering capacity of gloss paint/litre
Knotting-1litre/50m2 100.00 0.020 2.00 litre
Priming-1litre/16m2 100.00 0.06 6.25 litre
1st, 2nd & 3rd coats a.b. 43.65 litre
51.90
Add for waste 10% 5.19
57.09 litre
Add for stopping 1.00% 0.57
57.66
Gloss paint in 3 coats 57.66 441.89 25,480.16

Knot, prime, stop and apply two under coats


and one finishing coat gloss paint to wood
surfaces. (cont'd) 25,480.16

Labour
1 painter 1.00 4,000.00 4,000.00
1 labourer 1.00 2,000.00 2,000.00
6,000.00
Add for tools 7.50% 450.00
Cost of gang/day 6,450.00

Output of gang-(16m2)(note: 16m2 divide by


100m2=0.16 0.16
Therefore cost of labour /100m2 40,312.50
65,792.66
Add GOH & profit. (30%) 45% 29,606.70
Cost/100m2 100.00 95,399.36
Cost/m2 953.99

Prepare, prime and apply one coats of texcote


4 paint to surfaces

Cost of 1No. Drum 0f 50kg-20litre texcote paint 14,200.00


Therefore cost of paint/litre 14,200.00 12.00 1,183.33
Take 100m2
Materials.
Covering capacity of paint/drum (12m2) 2.00
Amount of paint-20litre/12m2 100.00 1.670 167.00 litre
Cost of paint 167.00 1,183.33 197,616.67
Cost of paint
Labour
1 painter 1.00 3,500.00 3,500.00
1 labourer 1.00 1,500.00 1,500.00
5,000.00
Add for tools 5.00% 250.00
Cost of gang/day 5,250.00

Output of gang-(30m2)(note: 30m2 divide by


100m2=0.30 0.30
Therefore cost of labour /100m2 17,500.00
215,116.67
Add GOH & profit. (30%) 30% 64,535.00
Cost/100m2 100.00 279,651.67
Cost/m2 2,796.52
BNL
Project : BOB
CONCRETE COLUMN MEASUREMENT
Project Manager : G. AKINOLA #REF!
Prepared by CAN
Date 04-Aug-10 300.70

QTY L B H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
ZONE A 6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222
C1 19.00 0.45 0.23 2.85 5.48 73.10 26.40 16.24 981.60
C3 13.00 0.45 0.23 2.85 3.75 50.02 13.20 10.08 503.89
C19 1.00 0.45 0.30 2.85 0.38 4.28 13.20 14.00 41.18
C2 4.00 0.23 0.23 2.85 0.58 10.26 26.40 33.04 248.05
C7 6.00 0.30 0.45 2.85 2.31 25.65 26.40 16.24 309.98
ZONE B
CT 1 15.00 0.45 0.23 2.85 4.33 57.71
CT 9 2.00 0.23 0.23 2.85 0.29 5.13
CT 10 2.00 0.23 0.23 2.85 0.29 5.13
CT 11 1.00 0.30 0.23 2.85 0.19 2.99
ZONE C
C1 19.00 0.45 0.23 2.85 5.48 73.10
C3 13.00 0.45 0.23 2.85 3.83 50.39
C2 4.00 0.23 0.23 2.85 0.58 10.26
C9 5.00 0.45 0.30 2.85 1.92 21.38
C4 1.00 0.45 0.23 2.85 0.29 3.85
ZONE D
C1 15.00 0.45 0.23 2.85 4.33 57.71
C3 17.00 0.45 0.23 2.85 4.91 65.41
C2 3.00 0.23 0.23 2.85 0.43 7.70
C9 1.00 0.45 0.23 2.85 0.29 3.85
C10 7.00 0.45 0.30 2.85 2.69 29.93
ZONE E
CT 1 15.00 0.45 0.23 2.85 4.33 57.71
46.69 615.54

ZONE A
C1 0.45 0.23 2.85 0.00 0.00
C3 13.00 0.45 0.23 2.85 3.75 50.02
C19 1.00 0.45 0.30 2.85 0.38 4.28
C2 4.00 0.23 0.23 2.85 0.58 10.26
C7 6.00 0.30 0.45 2.85 2.31 25.65
ZONE B
CT 1 15.00 0.45 0.23 2.85 4.33 57.71
CT 9 2.00 0.23 0.23 2.85 0.29 5.13
CT 10 2.00 0.23 0.23 2.85 0.29 5.13
CT 11 1.00 0.30 0.23 2.85 0.19 2.99
ZONE C
C1 0.45 0.23 2.85 0.00 0.00
C3 13.00 0.45 0.23 2.85 3.83 50.39 26.40 10.08 622.29
C2 4.00 0.23 0.23 2.85 0.58 10.26
C9 5.00 0.45 0.30 2.85 1.92 21.38 2,706.98
C4 1.00 0.45 0.23 2.85 0.29 3.85
ZONE D
C1 0.45 0.23 2.85 0.00 0.00
C3 17.00 0.45 0.23 2.85 4.91 65.41
C2 3.00 0.23 0.23 2.85 0.43 7.70
C9 1.00 0.45 0.23 2.85 0.29 3.85
C10 7.00 0.45 0.30 2.85 2.69 29.93
BNL
Project : BOB
Project Manager : G. AKINOLA
Prepared by CAN CONCRETE RETAINING WALL MEASUREMENT
Date 04-Aug-10

QTY L B H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222

LIFT WALLS 0.00


ground floor to 1st floor
wall 3 1.00 2.00 0.23 2.92 1.34 11.68 4,317.12 6,812.42
wall 2 2.00 2.20 0.23 2.92 2.96 25.70
wall 1 1.00 2.00 0.23 2.92 1.34 11.68

Less doors -1.00 1.00 0.23 2.10 -0.48 -4.20


5.16 44.86 6,812.42
ground floor to 1st floor
wall 3 1.00 2.00 0.23 2.92 1.34 11.68
wall 2 2.00 2.20 0.23 2.92 2.96 25.70
wall 1 1.00 2.00 0.23 2.92 1.34 11.68

Less doors -1.00 1.00 0.23 2.10 -0.48 -4.20


5.16 44.86
ground floor to 1st floor
wall 3 1.00 2.00 0.23 2.92 1.34 11.68
wall 2 2.00 2.20 0.23 2.92 2.96 25.70
wall 1 1.00 2.00 0.23 2.92 1.34 11.68

Less doors -1.00 1.00 0.23 2.10 -0.48 -4.20


5.16 44.86 0.00 0.00 0.00 4,317.12 0.00 0.00 0.00 0.00 0.00
BNL
Project : BOB
Project Manager : G. AKINOLA
Prepared by CAN
Date GENERAL CONCRETE BEAM MEASUREMENT

QTY H B L CONC. F/WK BEAM T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL

1ST FLOOR BEAM

ZONE A
BEAM 1 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 24 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 23 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 7 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 8 1.00 0.15 0.23 17.72 0.61 9.39
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BM 10 1.00 0.30 0.23 12.03 0.83 9.98
BM 11 1.00 0.30 0.23 12.03 0.83 9.98
BM 4 1.00 0.30 0.23 4.46 0.31 3.70
BM 12 1.00 0.30 0.23 12.03 0.83 9.98
BM 13 1.00 0.30 0.23 12.03 0.83 9.98
BM 3 1.00 0.30 0.23 5.77 0.40 4.79
BM 14 1.00 0.30 0.23 30.99 2.14 25.72
BM 15 1.00 0.30 0.23 20.76 1.43 17.23
BM 16 1.00 0.30 0.23 10.23 0.71 8.49
BM 17 1.00 0.30 0.23 4.15 0.29 3.44
BM 18 1.00 0.30 0.23 6.09 0.42 5.05
BM 22 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 4.46 0.31 3.70
BM 19 1.00 0.30 0.23 30.99 2.14 25.72
BM 20 1.00 0.30 0.23 18.96 1.31 15.74
BM21 1.00 0.30 0.23 12.03 0.83 9.98

ZONE B
BM 1 1.00 0.30 0.23 18.41 1.27 15.28
BM 13 1.00 0.30 0.23 3.63 0.25 3.01
BM 2 1.00 0.30 0.23 18.41 1.27 15.28
BM5 1.00 0.30 0.23 4.21 0.29 3.49
BM3 1.00 0.30 0.23 18.41 1.27 15.28
BM4 1.00 0.30 0.23 4.30 0.30 3.57
BM6 1.00 0.30 0.23 22.01 1.52 18.27
BM 8 1.00 0.30 0.23 13.86 0.96 11.50
BM 9 1.00 0.30 0.23 3.62 0.25 3.00
BM11 1.00 0.30 0.23 13.86 0.96 11.50
BM 7 1.00 0.15 0.23 1.80 0.06 0.95
BM 14 1.00 0.30 0.23 13.86 0.96 11.50
BM 15 1.00 0.15 0.23 1.80 0.06 0.95
BM 10 1.00 0.30 0.23 10.23 0.71 8.49
BM 12 1.00 0.30 0.23 10.23 0.71 8.49

ZONE C
BM 1 1.00 0.30 0.23 27.94 1.93 23.19
BM 23 1.00 0.30 0.23 20.75 1.43 17.22
BM 3 1.00 0.30 0.23 5.77 0.40 4.79
BM 5 1.00 0.30 0.23 17.72 1.22 14.71
BM 22 1.00 0.30 0.23 10.23 0.71 8.49
BM 7 1.00 0.30 0.23 27.94 1.93 23.19
BM 8 1.00 0.15 0.23 15.92 0.55 8.44
BM 9 1.00 0.30 0.23 12.03 0.83 9.98
BM 10 1.00 0.30 0.23 12.03 0.83 9.98
BM 11 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 4.46 0.31 3.70
BM 12 1.00 0.30 0.23 12.03 0.83 9.98
BM 13 1.00 0.30 0.23 12.03 0.83 9.98
BM 6 1.00 0.30 0.23 5.77 0.40 4.79
BM 14 1.00 0.30 0.23 12.03 0.83 9.98
BM 15 1.00 0.30 0.23 12.03 0.83 9.98
BM 16 1.00 0.30 0.23 12.03 0.83 9.98
BM 17 1.00 0.30 0.23 12.03 0.83 9.98
BM 18 1.00 0.15 0.23 20.75 0.72 11.00
BM20 1.00 0.30 0.23 6.09 0.42 5.05
BM 21 1.00 0.30 0.23 4.15 0.29 3.44
BM 19 1.00 0.30 0.23 30.98 2.14 25.71
BM 24 1.00 0.30 0.23 30.98 2.14 25.71

ZONE D
BM 1 1.00 0.30 0.23 22.01 1.52 18.27
BM 2 1.00 0.30 0.23 22.01 1.52 18.27
BM 3 1.00 0.30 0.23 22.01 1.52 18.27
BM 4 1.00 0.30 0.23 22.01 1.52 18.27
BM 11 1.00 0.30 0.23 33.52 2.31 27.82
BM 5 1.00 0.30 0.23 22.01 1.52 18.27
BM 18 1.00 0.30 0.23 3.83 0.26 3.18
BM 6 1.00 0.30 0.23 22.01 1.52 18.27
BM 7 1.00 0.45 0.23 7.50 0.78 8.48
BM 8 1.00 0.30 0.23 2.40 0.17 1.99
BM 9 1.00 0.30 0.23 22.01 1.52 18.27
BM 10 1.00 0.30 0.23 22.01 1.52 18.27
BM 16 1.00 0.30 0.23 3.83 0.26 3.18
BM 14 1.00 0.30 0.23 23.65 1.63 19.63
BM 15 1.00 0.30 0.23 6.04 0.42 5.01
BM 13 1.00 0.30 0.23 33.52 2.31 27.82
BM 17 1.00 0.30 0.23 33.52 2.31 27.82
BM 19 1.00 0.30 0.23 33.52 2.31 27.82
BM 20 1.00 0.30 0.23 33.52 2.31 27.82
BM 12 1.00 0.30 0.23 33.52 2.31 27.82

ZONE E
BM 1 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 12.03 0.83 9.98
BM 3 1.00 0.30 0.23 12.03 0.83 9.98
BM 4 1.00 0.30 0.23 6.20 0.43 5.15
BM 5 1.00 0.30 0.23 12.03 0.83 9.98
BM 6 1.00 0.30 0.23 12.03 0.83 9.98
BM 8 1.00 0.30 0.23 16.34 1.13 13.56
BM 10 1.00 0.30 0.23 8.46 0.58 7.02
BM 11 1.00 0.30 0.23 4.65 0.32 3.86
BM 12 1.00 0.30 0.23 3.23 0.22 2.68
BM 13 1.00 0.30 0.23 16.34 1.13 13.56
BM 7 1.00 0.15 0.23 16.34 0.56 8.66
BM 9 1.00 0.30 0.23 3.23 0.22 2.68
94.16 1,140.28

2ND FLOOR BEAM


ZONE A
BEAM 1 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 7 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 24 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 23 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 8 1.00 0.15 0.23 17.72 0.61 9.39
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 12 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 13 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 14 1.00 0.30 0.23 30.99 2.14 25.72
BM 3 1.00 0.30 0.23 5.80 0.40 4.81
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BM 15 1.00 0.30 0.23 20.76 1.43 17.23
BM 16 1.00 0.30 0.23 10.23 0.71 8.49
BM 17 1.00 0.30 0.23 4.15 0.29 3.44
BM 18 1.00 0.30 0.23 6.09 0.42 5.05
BM 22 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 4.46 0.31 3.70
BM 19 1.00 0.30 0.23 30.99 2.14 25.72
BM 20 1.00 0.15 0.23 18.96 0.65 10.05
BM 21 1.00 0.30 0.23 12.03 0.83 9.98

ZONE B
BEAM 1 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 7 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 2 1.00 0.30 0.23 18.41 1.27 15.28
BM 5 1.00 0.30 0.23 4.21 0.29 3.49
BEAM 3 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 4 1.00 0.30 0.23 4.00 0.28 3.32
BEAM 6 1.00 0.30 0.23 22.01 1.52 18.27

BEAM 8 1.00 0.30 0.23 13.86 0.96 11.50


BEAM 9 1.00 0.30 0.23 3.63 0.25 3.01
BEAM 11 1.00 0.30 0.23 13.86 0.96 11.50
BEAM 13 1.00 0.30 0.23 3.63 0.25 3.01
BEAM 14 1.00 0.30 0.23 13.86 0.96 11.50
BEAM 15 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 10 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 12 1.00 0.30 0.23 10.23 0.71 8.49

ZONE C
BEAM 1 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 24 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 22 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 7 1.00 0.30 0.23 27.94 1.93 23.19
0.00 0.00
BEAM 8 1.00 0.15 0.23 15.92 0.55 8.44
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 12 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 13 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 2 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 14 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 15 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 21 1.00 0.30 0.23 4.15 0.29 3.44

BEAM 16 1.00 0.30 0.23 12.03 0.83 9.98


BEAM 17 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 18 1.00 0.15 0.23 20.75 0.72 11.00
BEAM 3 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 19 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 20 1.00 0.30 0.23 6.09 0.42 5.05
BEAM 23 1.00 0.30 0.23 20.75 1.43 17.22

ZONE D 0.00 0.00


BM 1 1.00 0.30 0.23 22.01 1.52 18.27
BM 15 1.00 0.30 0.23 6.04 0.42 5.01
BM 2 1.00 0.30 0.23 22.01 1.52 18.27
BM 7 1.00 0.45 0.23 7.50 0.78 8.48
BM 3 1.00 0.30 0.23 22.01 1.52 18.27
BM 18 1.00 0.30 0.23 3.83 0.26 3.18
BM 4 1.00 0.30 0.23 22.01 1.52 18.27
BM 16 1.00 0.30 0.23 3.83 0.26 3.18
BM 11 1.00 0.30 0.23 33.52 2.31 27.82

BM 5 1.00 0.30 0.23 22.01 1.52 18.27


BM 6 1.00 0.30 0.23 22.01 1.52 18.27
BM 8 1.00 0.30 0.23 2.40 0.17 1.99
BM 9 1.00 0.30 0.23 22.01 1.52 18.27
BM 10 1.00 0.30 0.23 22.01 1.52 18.27
BM 14 1.00 0.30 0.23 23.65 1.63 19.63

BM 13 1.00 0.30 0.23 33.52 2.31 27.82


BM 17 1.00 0.30 0.23 33.52 2.31 27.82
BM 19 1.00 0.30 0.23 33.52 2.31 27.82
BM 20 1.00 0.30 0.23 33.52 2.31 27.82
BM 12 1.00 0.30 0.23 33.52 2.31 27.82

ZONE E 0.00 0.00


BM 1 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 12.03 0.83 9.98
BM 3 1.00 0.30 0.23 12.03 0.83 9.98
BM 4 1.00 0.30 0.23 6.20 0.43 5.15
BM 5 1.00 0.30 0.23 12.03 0.83 9.98
BM 6 1.00 0.30 0.23 12.03 0.83 9.98
BM 8 1.00 0.30 0.23 16.34 1.13 13.56
BM 10 1.00 0.30 0.23 8.46 0.58 7.02
BM 11 1.00 0.30 0.23 4.65 0.32 3.86
BM 12 1.00 0.30 0.23 3.23 0.22 2.68
BM 13 1.00 0.30 0.23 16.34 1.13 13.56
BM 7 1.00 0.15 0.23 16.34 0.56 8.66
BM 9 1.00 0.30 0.23 3.23 0.22 2.68
93.79 1,138.08
3RD FLOOR BEAM
ZONE A
BEAM 1 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 24 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 23 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 7 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 8 1.00 0.15 0.23 17.72 0.61 9.39
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 12 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 13 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 14 1.00 0.30 0.23 30.99 2.14 25.72
BM 3 1.00 0.30 0.23 5.80 0.40 4.81
BM 2 1.00 0.30 0.23 4.46 0.31 3.70
BM 15 1.00 0.30 0.23 20.76 1.43 17.23
BM 16 1.00 0.30 0.23 10.23 0.71 8.49
BM 17 1.00 0.30 0.23 4.15 0.29 3.44
BM 18 1.00 0.30 0.23 6.09 0.42 5.05
BM 22 1.00 0.30 0.23 12.03 0.83 9.98
BM 19 1.00 0.30 0.23 30.99 2.14 25.72
BM 20 1.00 0.15 0.23 18.96 0.65 10.05
BM 21 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70

ZONE B
BEAM 1 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 7 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 2 1.00 0.30 0.23 18.41 1.27 15.28
BM 5 1.00 0.30 0.23 4.21 0.29 3.49
BEAM 3 1.00 0.30 0.23 18.41 1.27 15.28
BEAM 4 1.00 0.30 0.23 4.00 0.28 3.32
BEAM 6 1.00 0.30 0.23 22.01 1.52 18.27

BEAM 8 1.00 0.30 0.23 13.86 0.96 11.50


BEAM 9 1.00 0.30 0.23 3.63 0.25 3.01
BEAM 11 1.00 0.30 0.23 13.86 0.96 11.50
BEAM 13 1.00 0.30 0.23 3.63 0.25 3.01
BEAM 14 1.00 0.30 0.23 13.86 0.96 11.50
BEAM 15 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 10 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 12 1.00 0.30 0.23 10.23 0.71 8.49

ZONE C
BEAM 1 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 7 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 24 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 8 1.00 0.15 0.23 15.92 0.55 8.44
BEAM 9 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 12 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 13 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 14 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 15 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 23 1.00 0.30 0.23 20.75 1.43 17.22
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 16 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 17 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 18 1.00 0.15 0.23 20.75 0.72 11.00
BEAM 3 1.00 0.30 0.23 5.77 0.40 4.79
BEAM 19 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 20 1.00 0.30 0.23 6.09 0.42 5.05
BEAM 21 1.00 0.30 0.23 4.15 0.29 3.44
BEAM 22 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 2 1.00 0.30 0.23 4.46 0.31 3.70
0.00 0.00
ZONE D 0.00 0.00
BM 5 1.00 0.30 0.23 22.01 1.52 18.27
BM 6 1.00 0.30 0.23 22.01 1.52 18.27
BM 7 1.00 0.45 0.23 7.50 0.78 8.48
BM 8 1.00 0.30 0.23 2.40 0.17 1.99
BM 9 1.00 0.30 0.23 22.01 1.52 18.27
BM 10 1.00 0.30 0.23 22.01 1.52 18.27
BM 1 1.00 0.30 0.23 22.01 1.52 18.27
BM 14 1.00 0.30 0.23 23.65 1.63 19.63
BM 15 1.00 0.30 0.23 6.04 0.42 5.01
BM 16 1.00 0.30 0.23 3.83 0.26 3.18
BM 18 1.00 0.30 0.23 3.83 0.26 3.18
BM 2 1.00 0.30 0.23 22.01 1.52 18.27
BM 11 1.00 0.30 0.23 33.52 2.31 27.82
BM 12 1.00 0.30 0.23 33.52 2.31 27.82
BM 4 1.00 0.30 0.23 22.01 1.52 18.27
BM 13 1.00 0.30 0.23 33.52 2.31 27.82
BM 17 1.00 0.30 0.23 33.52 2.31 27.82
BM 19 1.00 0.30 0.23 33.52 2.31 27.82
BM 20 1.00 0.30 0.23 33.52 2.31 27.82
BM 3 1.00 0.30 0.23 22.01 1.52 18.27

ZONE E 0.00 0.00


BM 1 1.00 0.30 0.23 12.03 0.83 9.98
BM 2 1.00 0.30 0.23 12.03 0.83 9.98
BM 3 1.00 0.30 0.23 12.03 0.83 9.98
BM 4 1.00 0.30 0.23 6.20 0.43 5.15
BM 5 1.00 0.30 0.23 12.03 0.83 9.98
BM 6 1.00 0.30 0.23 12.03 0.83 9.98
BM 7 1.00 0.30 0.23 16.34 1.13 13.56
BM 8 1.00 0.30 0.23 16.34 1.13 13.56
BM 9 1.00 0.30 0.23 3.23 0.22 2.68
BM 11 1.00 0.30 0.23 4.65 0.32 3.86
BM 12 1.00 0.30 0.23 3.23 0.22 2.68
BM 10 1.00 0.30 0.23 8.46 0.58 7.02
BM 13 1.00 0.30 0.23 16.34 1.13 13.56
94.36 1,142.98

PENT FLOOR BEAM


ZONE A
BEAM 1 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 23 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 24 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.45 0.23 5.77 0.60 6.52
BEAM 7 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 8 1.00 0.30 0.23 27.95 1.93 23.20
BEAM 9 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 10 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 11 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 12 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 13 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 14 1.00 0.45 0.23 12.03 1.25 13.59
BM 3 1.00 0.45 0.23 5.80 0.60 6.55
BM 15 1.00 0.30 0.23 30.99 2.14 25.72
BM 2 1.00 0.30 0.23 4.46 0.31 3.70

BM 16 1.00 0.45 0.23 20.75 2.15 23.45


BM 17 1.00 0.30 0.23 10.23 0.71 8.49
BM 18 1.00 0.30 0.23 4.15 0.29 3.44
BM 19 1.00 0.30 0.23 6.09 0.42 5.05
BM 25 1.00 0.30 0.23 12.03 0.83 9.98
BM 20 1.00 0.30 0.23 30.99 2.14 25.72
BM 21 1.00 0.15 0.23 18.96 0.65 10.05
BM 22 1.00 0.30 0.23 18.96 1.31 15.74

ZONE C
BEAM 1 1.00 0.30 0.23 27.94 1.93 23.19
BEAM 24 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 4 1.00 0.30 0.23 4.46 0.31 3.70
BEAM 5 1.00 0.30 0.23 17.72 1.22 14.71
BEAM 6 1.00 0.45 0.23 5.77 0.60 6.52
BEAM 8 1.00 0.30 0.23 15.92 1.10 13.21
BEAM 25 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 9 1.00 0.30 0.23 15.92 1.10 13.21
BEAM 10 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 11 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 12 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 13 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 14 1.00 0.45 0.23 12.03 1.25 13.59
BEAM 15 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 16 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 17 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 18 1.00 0.30 0.23 12.03 0.83 9.98
BEAM 7 1.00 0.15 0.23 1.80 0.06 0.95
BEAM 19 1.00 0.30 0.23 20.75 1.43 17.22
BEAM 3 1.00 0.45 0.23 5.77 0.60 6.52
BEAM 20 1.00 0.30 0.23 30.98 2.14 25.71
BEAM 21 1.00 0.30 0.23 6.09 0.42 5.05
BEAM 22 1.00 0.30 0.23 4.15 0.29 3.44
BEAM 23 1.00 0.30 0.23 10.23 0.71 8.49
BEAM 2 1.00 0.30 0.23 4.46 0.31 3.70

ZONE D
BM 1 1.00 0.45 0.23 22.01 2.28 24.87
BM 2 1.00 0.45 0.23 22.01 2.28 24.87
BM 3 1.00 0.30 0.23 22.01 1.52 18.27
BM 4 1.00 0.30 0.23 2.40 0.17 1.99
BM 13 1.00 0.45 0.23 33.52 3.47 37.88
BM 5 1.00 0.30 0.23 22.09 1.52 18.33
BM 16 1.00 0.30 0.23 3.83 0.26 3.18
BM 6 1.00 0.30 0.23 22.01 1.52 18.27
BM 7 1.00 0.45 0.23 7.50 0.78 8.48
BM 8 1.00 0.30 0.23 2.40 0.17 1.99
BM 9 1.00 0.30 0.23 22.01 1.52 18.27
BM 18 1.00 0.45 0.23 3.83 0.40 4.33
BM 10 1.00 0.45 0.23 22.01 2.28 24.87
BM 22 1.00 0.45 0.23 6.04 0.63 6.83
BM 17 1.00 0.45 0.23 33.52 3.47 37.88
BM 14 1.00 0.30 0.23 23.65 1.63 19.63
BM 15 1.00 0.45 0.23 6.04 0.63 6.83
BM 11 1.00 0.30 0.23 33.52 2.31 27.82
BM 20 1.00 0.30 0.23 23.65 1.63 19.63
BM 21 1.00 0.30 0.23 3.83 0.26 3.18
BM 12 1.00 0.45 0.23 33.52 3.47 37.88
BM 19 1.00 0.45 0.23 33.52 3.47 37.88
87.54 1,013.74
ROOF BEAM
ZONE A
BNL
Project : BOB
Project Manager : G. AKINOLA
Prepared by CAN UPPER FLOOR SLABS #REF!
Date 26-Apr-10

QTY L B H(topping) H(pre-cast) CONC 1:2:4 TOPPING SQM F/WK waterproofing T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
1st floor slab 6.314 3.854 2.466 1.579 1.209 0.888 0.616 0.395 0.222

INSITU SLAB
ZONE A 0.00
1 1.00 28.17 12.26 0.150 51.80 345.36 0.00
2 1.00 12.25 19.07 0.150 35.04 233.61 0.00
0.00
Less lift -1.00 2.21 2.00 0.150 -0.66 -4.42 0.00
staircase -2.00 8.70 1.80 0.150 -4.70 -31.32
-1.00 7.50 1.50 0.150 -1.69 -11.25
-1.00 8.10 1.80 0.150 -2.19 -14.58
-1.00 6.90 1.80 0.150 -1.86 -12.42

75.75 0.00 504.98 0.00


ZONE B
1 1.00 18.64 14.09 0.150 39.40 262.64
2 2.00 2.03 2.03 0.150 1.24 8.24

40.63 0.00 270.88


ZONE C
1 1.00 28.17 12.26 0.150 51.80 345.36
2 1.00 12.25 19.07 0.150 35.04 233.61

Less lift -1.00 2.21 2.00 0.150 -0.66 -4.42

86.18 0.00 574.55

ZONE D
1 1.00 22.23 33.74 0.150 112.51 750.04
2 0.150 0.00 0.00

Less lift -1.00 2.18 1.38 0.150 -0.45 -3.01

112.05 0.00 747.03

ZONE E
1 1.00 12.25 16.56 0.150 30.43 202.86
0.150 0.00 0.00

Less lift 0.150 0.00 0.00

30.43 0.00 202.86


345.05 0.00 2,300.30
2nd floor

INSITU SLAB
ZONE A
1 1.00 28.17 12.26 0.150 51.80 345.36
2 1.00 12.25 19.07 0.150 35.04 233.61
BNL
Project : BOB
CONCRETE COLUMN MEASUREMENT
Project Manager : G. AKINOLA #REF!
Prepared by CAN
Date 04-Aug-10 300.70

QTY L B H CONC. F/WK T32 T25 T20 T16 T14 T12 T10 T8 T6 TOTAL
ZONE A 6.314 3.854 2.466 1.578 1.209 0.888 0.616 0.395 0.222
C1 18.00 0.45 0.23 1.05 1.91 25.52 26.40 16.24 929.93
C3 12.00 0.45 0.23 1.05 1.28 17.01 13.20 10.08 465.13
C19 1.00 0.45 0.30 1.05 0.14 1.58 13.20 14.00 41.18
C2 4.00 0.23 0.23 1.05 0.21 3.78 26.40 33.04 248.05
C7 6.00 0.30 0.45 1.05 0.85 9.45 26.40 16.24 309.98
ZONE B
CT 1 15.00 0.45 0.23 1.05 1.59 21.26
CT 9 2.00 0.23 0.23 1.05 0.11 1.89
CT 10 2.00 0.23 0.23 1.05 0.11 1.89
CT 11 1.00 0.30 0.23 1.05 0.07 1.10
ZONE C
C1 19.00 0.45 0.23 1.05 2.02 26.93
C3 12.00 0.45 0.23 1.05 1.30 17.14
C2 4.00 0.23 0.23 1.05 0.21 3.78
C9 5.00 0.45 0.30 1.05 0.71 7.88
C4 1.00 0.45 0.23 1.05 0.11 1.42
ZONE D
C1 15.00 0.45 0.23 1.05 1.59 21.26
C3 17.00 0.45 0.23 1.05 1.81 24.10
C2 3.00 0.23 0.23 1.05 0.16 2.84
C9 1.00 0.45 0.23 1.05 0.11 1.42
C10 7.00 0.45 0.30 1.05 0.99 11.03
ZONE E
CT 1 15.00 0.45 0.23 1.05 1.59 21.26

0.00 0.00 26.40 10.08 0.00

TOTAL 16.88 222.52 1,994.26


PROPOSED MIXED DEVELOPMENT

Prime cost and provisional sums included in this bills of quantities


Prime Costs Provisional Sums
Preliminaries
1 Testing of Materials 2,500,000.00
2 Statutory/Stacking/Community Charges (Council) 8,000,000.00
3 Project supervision expenses 250,000.00
Main building
4 Additional works in substructure #REF!
5 Steel roof member provisional sum #REF!
Plumbing installation
6 Piping and installation accessories #REF!
7 external piping accessories #REF!
Electrical installation
8 Conection to AEDC 1,200,000.00
9 Luminaries fittings 100,000.00
10 Installation of equipment Low Voltage distribution Equipment 500,000.00
11 Insulation Resistance, Electrical continuity,Earth
resistivity,Lighting Tests 500,000.00
12 Labelling of circuits in distribution boards 500,000.00
13 PBX intercom System 500,000.00
14 Central Antenna TV system 500,000.00
15 CONTINGENCY #REF!

Total - #REF!

Prov. Sums

You might also like