Professional Documents
Culture Documents
260
0 Outline
1. Background
2. Framework on Risk Based Slope Designs
a. Slope Impact Categories
b. Two different approaches: Deemed to Satisfy Approach vs. Engineering Approach
c. Subsoil drains
d. Robustness requirements for proposed building located at the crest of slope
e. Annex A – Framework
261
26
1 Background
262
26
1 Rainfall Events Leading to Landslides in Singapore
Source: Latsis Symposium by CCES at ETH-Z, Zurich, Switzerland, 17-19 Sep 2007
263
26
1 Case Study: Slope Failure at Kent Ridge Crescent
• Continuous heavy rainfall during the
period of Dec 2005 to January 2006
had caused a massive landslide
adjacent to a building at Kent Ridge
Crescent on 11 January 2006.
264
26
1 Case Study: Slope Failure at Kent Ridge Crescent
Transient Infiltration Analysis
0.000 20.000 40.000 60.000 80.000
140.000 m
127.000
124.000
Building – No influx 123.000
122.000
120.000
Unsaturated Zone 121.000
Input flux = 20mm/day 120.000
119.000
Raised GWT 118.000
117.000
116.000
115.000
100.000 Estimated Slip Surface
114.000
113.000
112.000
111.000
110.000
80.000 108.000
• Likely cause is combination of rainfall induced saturation leading to
loss of suction and rising GWT
Active groundwater head
Phase number: 6 Phase time: 5 day, Extreme groundwater head 126.01 m
265
26
1 Impact of Climate Change
Extreme Rainfall Incident at Zheng Zhou Flooding Incident at Dunearn Road
Zhengzhou city flooded after a heavy downpour Flooded canal along Bt Timah Rd and Dunearn Rd on 24 Aug 2021
• Worst Rainfall with return period of 1000 years • Top 0.5% of max. daily rainfall records since 1981.
• Zhengzhou recorded 209.1mm of heavy rains in an hour. • Highest daily total rainfall 239.8mm
• Rainfall amount of 552.5mm within 24 hours from 19 July, • 3 hours rainfall of 159.8mm
8pm to 20 July, 8pm.
Clause 4.3.5.6
Long-term changes in groundwater that are likely to occur during the design working life of the structure
(including those due to climate change and rising groundwater) should be taken into account.
267
26
2
Framework on Risk Based
Slope Designs
268
26
2 Engagement with Industry
Working Committee Members Date Events
Subsoil drains
270
27
2 Slope Impact Categories
Impact Categories Definition of Impact Categories Type of Adjacent Buildings / Structures Close proximity to adjacent buildings /
structures
High impact High consequence for loss of human life, or • Densely populated residential area (4- Crest : Buildings located within 0.7 H
economic, social or environmental consequences storey and above) Toe : Buildings located within 1 H
very great • office building
• shopping mall
• major infrastructure (e.g. MRT)
Impact
Medium impact Medium consequence for loss of human life, • Landed house, shophouse (up to 3-storey) Crest : Buildings located within 0.7 H
economic, social or environmental consequences Toe : Buildings located within 1 H
considerable
Low impact Low consequence for loss of human life, and • Non-habitable single storey structures Green Field
economic, social or environmental consequences
small or negligible
or Landed House
or (≤ 3 Storeys)
Landed House
0.7H
0.7H Landed House 0.7H (≤ 3 Storeys)
Shopping Mall
H (≤ 3 Storeys) H
H
H H
H
Note: The potential failure zone, defined as 0.7H at the crest or 1H at the toe is derived from local case studies of slope failure. 271
27
2 Design Requirements
Design Requirements Site Investigation Design Approach Long-Term Monitoring Regime to Robustness
be Specified on Plans Requirements of
Foundation for
Option 1: Option 2: Soil Nails/ Subsoil Drains
Proposed Buildings
Deemed to Satisfy Approach Engineering Approach Ground System
Located at the
(Prescribed Onerous Design (Design GWT Derived from Seepage Anchors System (Engineering
Slope Impact Crest of Slope
GWT) Analysis Incorporating Climate Change) Approach)
Categories
High Impact • Min 2 BHs per • Ultimate Limit State • Ultimate Limit State Yes Yes Required
design section • Accidental Load Case • Accidental Load Case with design GWT
• Closer borehole with design GWT at 1.0H incorporating extreme daily rainfall
interval • Subsoil drains with • Subsoil drains designed for specified
closer spacing closer spacing with overdesign factor
of 3.
Medium Impact • Min 1 BH per • Ultimate Limit State • Ultimate Limit State QP to decide Yes QP to decide
design section • Accidental Load Case • Accidental Load Case with design
• Medium with design GWT at 0.9H GWT incorporating extreme daily
borehole interval • Subsoil drains with rainfall
medium spacing • Subsoil drains designed for specified
medium spacing with overdesign factor
of 3.
Low Impact • Min 1 BH per • Ultimate Limit State • Ultimate Limit State QP to decide Yes Not applicable
design section • Accidental Load Case – • Accidental Load Case – Not Applicable
• Larger borehole Not Applicable • QP to decide the need for subsoil
interval • QP to decide the need drains. If provided, subsoil drains
for subsoil drains. If designed for specified larger spacing
provided may use larger with overdesign factor of 3.
spacing
272
27
2 Deemed to Satisfy Approach (DTS) vs. Engineering Approach (Eng)
Ultimate Limit State (“ULS”)
Prescribed ground water loading • Onerous Design GWT
DTS Approach
• Simple Analysis
• Safe Design
Accidental Load Case (“AL”)
Prescribed ground water loading
275
27
2 DTS Approach: Prescribed Onerous Groundwater Table
Toe of Slope
276
27
2 Eng Approach
• Eng Approach: Baseline GWT + Rainfall Loading
• Eng Approach is only applicable to GBW hill slopes. For all other
excavated slopes, the QPs are to adopt onerous design ground water
level which is normally taken to be close to full height of the slope
especially at lower ground.
277
27
2 Eng Approach: Baseline GWT + Rainfall
Eng Approach: Baseline GWT + Rainfall
Precipitation
BCA’s study concluded that by adopting
these two values, impact of climate
change deemed to be included. For slope
Infiltration with high to medium risk, additional
check is carried out with higher value of
rainfall.
Wetting front
Load Case 2:
Max 5 Days Antecedent Rainfall = 575mm
278
27
2 Eng Approach: Baseline GWT + Rainfall
Eng Approach: Baseline GWT + Rainfall
Rainfall Infiltration
Accidental Design Load Case
Crest of Slope
Max Daily Rainfall = 530mm
279
27
2 Eng Approach: Baseline GWT + Rainfall
280
28
2 Why Subsoil Drain?
Parametric Study of Influence of Subsoil Drains
Factor of Safety (FOS) 0.9 < 1
without subsoil drains
Factor of Safety (FOS) with 1.6 > 1
8m long subsoil drains
1
10
Serve as Robustness
Minimum 1 row of subsoil drain at the
bottom of the slope.
Requirements.
Objective:
To ensure the drainage system perform as per design intent in long term
QP Developer
✓ Specify on the structural plans the ✓ Undertake the monitoring and
long-term inspection and maintenance of subsoil drains
maintenance
284
28
2 Detailing for Subsoil Drains
Typical Details of Double Pipes for Subsoil Drain Example of Double Filtration Layers for
(HK Geo Publication CEDD Standard Drawing No. C2403) Subsoil Drain
Example of External Longitudinal Ribs along • 1st filtration layer: 400x400m of cut trench filled with
10-50mm coarse gravel or rock chips wrapped around
Perforated Subsoil Drain Pipe with geotextile.
• 2nd filtration layer / drainage layer: 75mm perforated
PVC pipe wrapped around with geotextile.
285
28
2 Case Study: Adoption of Eng Approach in Slope Design
Reinstatement of Existing Soil Nail Slope with 1(V):2.75(H)
Layout Plan
Section A-A
286
28
2 Case Study: Adoption of Eng Approach in Slope Design
Step 1: Obtain Soil Water Characteristic Curve (SWCC) for transient seepage analysis
Particle Size Distribution (PSD) of soil layers
• SWCC parameters can be obtained Average
Clay
S(VI)
31.8 %
Average S(V) 50<N<100
Clay 30.8 %
from tests according to ASTM ABHS007 ABHS009
Silt
Sand
31.9 %
36.0 %
Silt 33.8 %
Sand 34.5 %
D6836-16* Gravel 0.4 %
Gravel 1.0 %
ABHS008 ABHS010
• Most tests are time consuming. Average
Clay
S(V) N=100
31.7 %
However hygrometer test may give Silt
Sand
37.7 %
28.3 %
test results within minutes. Gravel 2.3 %
287
28
2 Case Study: Adoption of Eng Approach in Slope Design
Step 2: Determine Initial Design Ground Water Table
Initial Design Ground Water Table (DGWT)
Case 1 Case 2
With Water Standpipe (WSP) readings taken With frequency of Water Standpipe (WSP)
4 mbgl
min. weekly throughout November to readings taken daily to weekly and with a
March (Wet Season) minimum of 12 readings
Chart 1 GWS1158005
GWS1158014
GWS1158013
288
28
2 Case Study: Adoption of Eng Approach in Slope Design
Step 3: Initialisation to model the initial design ground water table
To achieve the initial design ground water table in the model, the designer is required to run a transient
seepage analysis with appropriate precipitation (rainfall per area) [flux] value for a period of time until the
initial design ground water table in step 1 is established.
289
28
2 Case Study: Adoption of Eng Approach in Slope Design
Step 4: Carry out seepage analysis for ULS check
Load Case 2:
Load Case 1: Max 5 Days Antecedent Rainfall = 575mm
Max Daily Rainfall = 350mm (115mm/day for 5 days)
290
29
2 Case Study: Adoption of Eng Approach in Slope Design
Step 5: Carry out slope stability analysis for ULS check
Load Case 2:
Load Case 1: Max 5 Days Antecedent Rainfall = 575mm
Max Daily Rainfall = 350mm (115mm/day for 5 days)
291
29
2 Case Study: Adoption of Eng Approach in Slope Design
Step 6: Design for subsoil drains
Flow capacity of pipe drain, Qcap = 24.2 m3/day per pipe
292
29
2 Robustness Requirements for Proposed Building located at the Crest of Slope
293
29
3
Important Design
Consideration for
ERSS Works
294
29
Case 1:
3 Critical Aspects that MUST be Considered by QP when Designing Retaining Wall on Slope
Retaining wall and temporary ERSS Local stability check
Importance of Desk Study
including complete construction sequence
1 • Overlay of geological map to identify
potential adverse conditions (e.g. soft 7 under single submission.
soil parameters should be
verified with SI instead of with
soil deposits)
Proposed retaining wall 4 an assumed safe bearing
on existing slope pressure from boreholes
Carry out impact assessment
located far away.
on adjacent structures Identify site terrain and shows
6 including slopes in accordance
with BC Regulation 33
2 on plan and section
• For this case building retaining wall on
top of existing slope is classified as
A&A to GBW slope.
7.48m
ST02
Basement
excavation
• Proposed works involve A&A to existing slope of 7.48m height with 5 tiers of L-shape retaining wall abutting 4.9m
basement excavation.
• QP treated 5 tiers of L-shape retaining wall as individual planter box and submitted as non-AC ST. This is NOT allowed!
A&A to existing slope of 7.48m height is classified as Geotechnical Building Works (GBW) and shall submit as GBW.
• QP also split the upper A&A to existing slope (GBW) and basement excavation into two separate STs. This is NOT
Allowed!
• As both upper A&A to existing slope (GBW) and basement excavation are new construction, they shall be submitted
under the same GBW ST. 296
29
3 Case 3: Reminder: This is GBW!
Basement
Excavation
Basement
Excavation
• 2.8m high existing rubble wall along the construction boundary collapsed during basement excavation.
• Investigation revealed that:
➢ Pre-existing cracks observed, however was not included in the impact assessment. QPs are reminded to carry out
proper impact assessment in accordance with Regulation 33 with site photographs of slopes , boundary wall and
retaining structure/ wall.
➢ Daily rainfall before the day of incident was 192mm, highest recorded in previous 4 months. Heavy rain 192mm is
high but still far from max rainfall encountered in Singapore (350mm).
➢ Lack of protective measures, and appropriate instruments resulted in the incident. 298
Case 4:
3 Sensitive Existing Rubble Wall – Importance of Impact Assessment and I&M
Annex B1 – Impact Assessment Form Key Learning Points
Maintaining weepholes
during construction stage
300
3 Case 5: Preventing sinkhole due to CHI in Mixed Ground of BTG
Key Points
1. No Unauthorised 2. Monitor and Review 3. Location of 4. Correct Type of
Flushing of TBM Excavation Volume Instrumentations Instrumentations
• Flushing without shield • Continuous monitoring • RX should be placed • Extensometer (RX)
advancement could and reviewing of above TBM location to should be provided at
easily results in over- excavation volume be effective. every CHI location and
excavation, hence should be carried out • In hard ground or mixed at high-risk area.
flushing shall not be during both tunnelling ground of BTG, sinkhole • RX serves as early
carried out during and CHI. likely to form above warning system to
tunnelling and CHI. • Discharge volume tunnel within narrow detect over-excavation
should be properly range from TBM centre before voids propagate
monitored to detect line with chimney-like to surface and form
any over-excavation. mechanism. sinkhole.
RX RX
RX
30
301
4 Summary and Conclusions
30
302
42 Summary and Conclusions
✓ This framework allows risk based slope designs depending on slope
impact categories, aims to future proofing slope to cater for impact
of climate change.
✓ It allows experienced QP with adequate knowledge to adopt “Eng
Approach” that considers onerous groundwater variation and
rainfall loadings including impact of climate change to produce a
safe and efficient design.
✓ Project parties shall remember the important design consideration
for ERSS Works shared to make our ERSS and tunnelling works safe!
30
303
Annex A - Framework on Risk Based Slope
Designs
304
304
Thank You
@BCASingapore
30
305