Professional Documents
Culture Documents
Development Project
Introduction
Background
Dhaka Urban Transport Network Development Study (DHUTS) Phase II (Feasibility Study
of Mass Rapid Transit (MRT) Line 6 is a continuation work of Preparatory Survey of
DHUTS. In this regards, GOB, JICA and relevant agencies discussed and agreed Preparatory
Survey on Dhaka Urban Transport Network Development Study (hereinafter referred to as
Phase I) in December 4, 2008. In addition, Dhaka Urban Transport Network Development
Study Phase I study prioritized MRT Line 6 (total length of 21.5 km) as the first project.
Afterwards, GOB, JICA and other relevant agencies signed Minutes of Discussion (MOD) in
2010 on Preparatory Survey for Dhaka Urban Transport Network Development Study
(DHUTS) Phase II (Feasibility Study of Mass Rapid Transit (MRT) Line 6 (hereinafter referred
to as Phase II Study) with a broader objective.
Scope
The report we prepared is based on the resettlement action plan prepared by JICA in
cooperation of the implementing agency, GOB. This study reflects on the socio-economic
impacts that could be inflicted upon by the land acquisition & resettlement work of the project.
Though detailed data collection & survey procedure which involved impactful public
consultations, this study managed to address every minute details of the socio-economic
survey. This Resettlement Action Plan (RAP) has been prepared incorporating some mitigating
measures to encounter the negative social and economic impacts so that the affected households
could maintain their economic and social standards during and after the project
implementation at least to pre-project level.
The study will also propose a thorough compensation plan for the socio-economic losses,
mostly related to households and commercial enterprises, as well as employees/vendors, etc.,
so that the affected people can at least retain their pre-project socio-economic standard or life.
Study Framework of the Project
Policy and Legal Framework
MRT Line 6 is a “Red Category” project under the Schedule 1 of Environmental Conservation
Law 1997. The cost of engineering works is above one million BDT and it is an elevated
viaduct of 16.8km. That is why this project falls under “Red Category”. The construction is
done using the median of the existing road along the built up areas of the city. MRT structure
is an elevated structure so no land acquisition is needed for constructing tracks. But land
acquisition was done for constructing depot, route alignment on sharp curves, station building
etc. Planners made an extensive effort to keep the land requirement minimum. It was estimated
that 0.28 ha land is required. From this estimation RAP and EIA were prepared. For preparing
EIA some of the laws and policies of Bangladesh are followed. Such as: National
Environmental Policy 1992, The Environmental Policy of 1992, National Environmental
Action Plan (NEMAP) 1995, The Environmental Conservation Act 1995, Environmental
Conservation Rules 1997. There some national policies which are also followed during
preparation of EIA. These policies are: Environmental Court Act, 2000 and subsequent
amendments in 2002, National Transport Policy, 2004, The National Water Policy, 1999, The
Vehicle Act, 1927, Motor Vehicle Ordinance, 1983, Water Supply and Sanitation Act, 1996,
The Acquisition and Requisition of Immovable Property Ordinance 1982 and subsequent
amendments 1994, 1995 and 2004, National Land use Policy, 2001, Draft Wetland Policy,
1998.
Data Collection
Data Collection of the Project Affected Persons (PAPs) from the proposed Corridor of Impact
(COI) was done by trained investigators with guidance and under the supervision of the Data
Analyst of Resettlement specialist of the project during October-November 2010. The data
collection survey included
1. Full census of households, shops etc.
2. Socio-economic surveys of 20% of the households
3. Assessing the value of lands and other assets.
4. Ward and community-based group discussion, focusing on wide range of data e.g., age &
sap distribution, education, occupation, poverty data, demography.
5. Types of ownership of the affected structures and other assets, choice of relocation, etc.
through questionnaire and schedule.
The Project Area
MRT Line 6 is 215 km including 18 stations starting from Utara North and ending at Saidabad
passing through Pallabi - Mirpur to Begum Rokeya Sharani - Bijoy Sarani - farmgate –
Sonargaon - Kamaruzzaman Sharani and Hatkhola Road. Land acquisition will be required for
Constructing all the 18 stations at the selected places of Uttara, Pallabi, IMT, Mirpur, Kazipara,
Agargaon, Chandrima Udaan, farmgate, Sonargaon, Shahbag, BUET Shahidullah Hall, Kaptan
Bazar, Banga Bhaban and Saidabad.
Miscellaneous
1. The negative impact due to ground subsidence will be reduced if the elevated structure and
station are supported by bored piles which will be driven by penetrating the stiff sand layer.
2. During construction, a proper traffic management system must be adopted to mitigate any
issue related to road network or road defect.
3. Proper protection against fire hazards must be taken in every station or depot.
Implementation Framework
The DTCB will establish, for the Project, a Project Implementation Unit (PIU) headed by a
Project Director. The PD will recruit and appoint an experienced Implementing Agency (an
NGO) as required for implementation of the resettlement activities. The PEA will
implement the RAP through setting a Resettlement Unit (RU) within the PIU. The RU will
have one Executive Engineer/Town Planner as Chief Resettlement Officer (CRO) who will
implement the plan at the field level with the assistance from Resettlement Officer (RO) and
project staff. The Project Director will ensure the land acquisition with assistance from district
administration and the CRO, i.e., the DC. The RU will coordinate land acquisition, manage
resettlement and rehabilitation of the PAPs, disburse resettlement grants, and ensure PAPs
access to development programs adequately.
The appointed Implementing Agency will open field offices, carry out information
campaign and involve affected persons including women in the implementation process
from the very beginning. The Implementing Agency will collect, collate, computerize and
process data for identification of eligible persons correctly for resettlement benefits and
assess their entitlements as per RAP policy. The CRO through the field offices, LA Office and
the Implementing Agency will execute and monitor the progress of the LA and RAP
implementation work. He/she will ensure coordination between the relevant departments,
Implementing Agency, the GRC, RAC, PVAT and the Project affected people (PAPs). Apart
from the GRC, Joint Verification Team (JVT) for quantification of affected properties and
Property Valuation Advisory Team (PVAT) will be formed by the Ministry of Housing and
Public Work (MOHW) for valuation of affected property and resolution of disputes.
Externa Monitor
Project Director
MIS Specialist
Deputy Team
Team Leader (RIA) RAC
Leader (RIA)
Area Manager (RIA)
Resettlement
GRC
Specialist
Improvements
1. Improved eligibility criteria have been followed where non titled PAPs are also
acknowledged as eligible for compensation.
2. Assessment process for compensation amount has also improved, considering the current
market price values.
3. Provision for economical & social support for effected vulnerable households has added.
4. Livelihood recovery programs, income restoration for the PAPs has also included.
5. Internal & External monitoring by a third party (legally & administratively valid) has been
carried out to ensure clarity in the whole process.
Limitations
1. Compensation payment process seems to be too complex and time consuming. There’s also
chances of corruption by the middle agents defined. Receiver PAP may also be harassed by
them.
2. There’s security question on check disbursement programme if it is carried out in public
place.
3. The loss of health deterioration due to environment pollution at the surrounding areas of
construction zone is not defined. The Air pollution in some of the zones are becoming a
serious health hazard for the surrounding population.
4. The loss of time & money due to traffic jam caused by land acquisition on roads and
construction activities is not defined. According to Accident Research Institute, Bangladesh
is losing $160 million due to traffic jam every day. And a major portion of this loss is beard
by the people facing traffic jam.
Recommendations
1. Compensation payment procedure should be simplified using smart technologies (ICTs).
2. Provision of health insurance should be established for the people affected by environment
pollution at the construction surrounding zones.
3. Traffic jam effected population due to construction activities should also be acknowledged
for compensation. This compensation can be provided by providing subsidy on transport
costs (fuel cost, Bus fare) for the routes surrounding construction zones.
4. Improved Security & Monitoring system should be enhanced for transparent activities and
to prevent robbery/extortion crimes relating to compensation payment activities.
References:
1. http://www.rthd.gov.bd/
2. https://www.jica.go.jp/bangladesh/english/activities/index.html
3. http://bba.portal.gov.bd/