METHOD STATEMENT FOR PILING WORK
PAGE 1 of 28
Issue for
01 Oct. 18.2023
Approval
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 2 of 28
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 3 of 28
Table of Contents
1.0 PURPOSE............................................................................................................................................ 4
2.0 SCOPE................................................................................................................................................ 4
3.0 REFERENCES....................................................................................................................................... 4
4.0 DEFINITIONS....................................................................................................................................... 4
5.0 GENERAL AND SAFETY REQUIREMENTS.............................................................................................. 5
6.0 RESPONSIBILITIES............................................................................................................................... 5
6.1 PROJECT MANAGER.....................................................................................................................................6
9.2 SURVEY,MARKING.....................................................................................................................................14
9.5 ROPING...................................................................................................................................................16
9.9 TOLERANCES............................................................................................................................................ 20
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 4 of 28
10.0 INSPECTION-QA/QC.......................................................................................................................... 24
11.0 HSE MEASURES................................................................................................................................. 27
12.0 ATTACHMENT................................................................................................................................... 29
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 5 of 28
1.0 PURPOSE
This project is for a large scale Solar PV Plant to generate electricity through a
renewable energy source.
The purpose of this document is to describe and define what and how to do
the piling works
Responsibility and authority to carry out the works in strict compliance with
HSE and QA/QC departments as well as legal and contractual regulations
of the Project.
2.0 SCOPE
The scope of this document is to explain the procedure and method of Piling
works at Al Shuaibah PV Project to perform the piling works. Piling can be
performed by 3 methods that will be explained in this document.
Direct Ramming
3.0 REFERENCES
4.0 DEFINITIONS
PM Project Manager
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 6 of 28
CM Construction Manager
SE Site Engineer
IC Inspection Checklist
MS Method Statement
PV Photovoltaic
Before commencing any work, all permits shall be checked and ensured
that they are valid until completion of activity.
All staff and workmen shall wear Personnel Protective Equipment (PPE).
All personnel shall be cautioned while working near live lines and other
services.
6.0 RESPONSIBILITIES
Piling Works includes ramming, pre-drilled ramming and drilling and concreting
of metal profile needed for the erection of the PV Structure. Piling works team
will be the responsible for the unloading of metal posts, transportation and
SEPCO Electric Power Construction Corporation
DOCUMENT NAME SEP-WAD-CO-MS-0009
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 7 of 28
distribution within the area of work, correct installation in line with the
assembly and installation manual submitted by the posts manufacturer. Piling
works will be involved in the concrete for the execution of the piling.
Responsibility will be to guarantee that the material will arrive on site in good
condition and that all quality test and inspection tests will be strictly carried in
line with standard.
Implement the company's quality policy and follow the overall policy, and
take full responsibility for the realization of the project quality objectives,
safety objectives, and environmental protection objectives;
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 8 of 28
Plan, organize, coordinate, and control the entire process of the project
according to project management methods;
Responsible for preparing material plans, including monthly plans and fund
use plans; Preparation of construction schedule;
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 9 of 28
Responsible for the blanking review and verification of the entire project;
Prepares reviews and updates, the Project Health Safety & Environment
related documents.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 10 of 28
Supports & provides guidance to Site HSE Officers on all HSE matters.
Prepares reviews and updates, the project Health safety & Environment
documents in coordination with the Project Manager & HSE Manager,
Manages work of Project safety Representatives / Committees.
Oversees preparation of all HSE documentation for the project e.g. Safety
Plans, Risk assessments.
Recommends safety targets for the project in association with the HSE
Manager and calculates accident frequency.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 11 of 28
Execute daily survey field tasks according to the procedures of the Survey
Department.
Prepare survey data and sketches in the proper format for transfer/
handover of information.
Ensure that the workers under his command fully understand the
procedures and hazards involved in the job.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 12 of 28
To be familiar with the Health and safety Policy and to co-operate in its
implementation at all times.
To take reasonable care for the safety and health of themselves, their
colleagues and anyone else who may be affected by their acts or
omissions.
To report all accidents (whether persons are injured or not) and any
damage to their immediate supervisor.
To ensure security directives during the execution of earth works, all activities
shall be monitored in compliance with relevant standards, codes and
procedures described in the HSE manual and project specification as
minimum as follows:
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 13 of 28
All equipment shall be inspected by the authority prior to start of the work.
Ramming machine helper will lift pile with hand and place in ramming
machine head dye and will go away, operator will wait for helper to stay
away on safe distance and then start the ramming procedure, with every
machine there will be 2 helpers, one will be used to give flag signal for
safe practice.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 14 of 28
Labor 8 Pakistani
Piling works can be done by 3 ways, Direct Ramming, Pre-Drilled Ramming (if
required) and Concrete Poured Piling (if required).
Survey,
Ropin
Machine In
Direct
Pre- Drilling–
Rammin Pouring
(I Required Work
(If )
Inspectio Adjus
QA/ N
Ye
SEPCO Electric Power Construction Corporation
NexPil
DOCUMENT NAME SEP-WAD-CO-MS-0009
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 15 of 28
9.2 Survey,Marking
The sub-contractor will send to EPC and Engineering Department all the
points of the surveyor and Engineering department will submit officially the pile
height and slope for confirmation prior to execution of work.
The surveyor will use a GPS to set the piles, since the tolerance established is
+-2cm (in coordinate XY) which are acceptable for this device, once the post is
set on its place (coordinates XY) the level whose tolerance is also +-2cm shall
be calculate by laser level which accuracy is more than acceptable taking into
consideration the acceptance criteria.
Piling Subcontractor Surveyor will take in account during the marking and the
setting out works that its important take also 1 meter of perimeter of the
tracker to send in .txt or excel format (all points of the tracker) to send to the
Engineering department for the calculations of the pile height, tolerances, and
slope. The progress of the setting out works will be submitted in weekly basis
with the production template provided by EPC. Piling subcontractors will notify
to EPC any anomaly or possible problem in the final height between trackers
in order to avoid big differences of height in 2 different trackers W-E with
enough advance time.
The survey engineer will take northing-easting by using the GPS data and will
give the elevation for first and last pile in tracker and the pile heights will be
maintained using this data to keep the tracker pile ramming according to the
tolerance given for slope.
Slope can be verified after ramming during inspection by using the laser.
Piles are distributed using Tele-handler, workers and flagman for direct
SEPCO Electric Power Construction Corporation
DOCUMENT NAME SEP-WAD-CO-MS-0009
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 16 of 28
ramming. Piles are distributed after the survey points are installed on the
marked points of piling coordinates and piles are then distributed on ground as
per sections and color coding of piles
Pile distribution is very important, the dedicated pile distribution supervisor will
ensure to distribute the certain type of piles (C,H,I) to be distributed at correct
location for each zone. Flag man will be deputed with every machine to carry
out safe work practice.
9.5 Roping
Roping is done after pile distribution from north to south for pile alignment and
to check the depth of pile in ground after putting marked line on pile with a
marker. Roping will done to align the pile from pile A of one tracker to the pile
A of next tracker below. The height of rope from ground will be kept 200-
300mm and the rebar rod offset from piles will be 150- 300 mm.
For roping the steel rod will be used to put the Fish Wire rope (1mm) thick and
there will be 3 steel rods for each tracker, start end and middle of tracker to
avoid any sag in fish wire.
Steel rebar will be protected by putting yellow colored rebar cap on top of steel
for visibility and safety purposes.
roping will be used to kept the piles aligned, for maintaining the height of piles
and to check the north/south twist of piles.
Safety tape will also be installed in middle of fish wire rope after pile ramming
to increase the visibility and avoid any slip or trip from wire.
Roping will intact in place until the inspection with owner is completed.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 17 of 28
The ramming process must ensure to comply with the dimensions required for
the pile regarding especially for depth (pile design), and ramming machine
hammer heads will be designed as per pile designs and will be ensured there
is no play inside that can damage pile top surface. If any of those parameters
are not properly addressed, final result will not be as designed. To accomplish
with those parameters.Ramming machine must be driven by specialized
operators, if possible, with previous experience in solar projects.
The operator should always monitor the impact force of the pile, the versatility
SEPCO Electric Power Construction Corporation
DOCUMENT NAME SEP-WAD-CO-MS-0009
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 18 of 28
of the steel pile and the diving depth of the pile; When the steel pile is driven
up to the design elevation, the operator needs to adjust the impact power of
the pile driver, and slowly impact until it reaches the design embedding
elevation. In the process, a helper is required to assist the operator to
complete it together. Avoid steel pile ramming depth exceeding design depth.
Erect the post to be installed manually and move pile driver to correct position.
Operate pile driver inserting the post into ground until to the designed
elevation. If there is any play in pile hammer head during ramming the pile
head die installed in machine will be immediately replaced in order to avoid
any damages in pile top surface.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 19 of 28
When start driving pile, each pile shall be continuously pressed and
continuously checked by digital spirit level meter the alignment of pile into the
ground until reaching design depth. By using the digital spirit level, the
supervisor will be able to ensure that he is installing the pile within the height
tolerance values mentioned in the installation manual.
The post ramming sequence will be A to A, roping will be done for each
tracker and reference will be from first pile of one tracker and first pile of the
next tracker below.
Ramming machine operator will ram the piles from north to south of one
tracker and then will move to south to north of next tracker.
North
South
9.9 Tolerances
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 20 of 28
This option will be used in case soil formation is hard to drive and steel pile
can't be driven into the ground any more and doesn't reach the design depth
and ramming time exceed 3-6 minutes. If the operation continues then post
head may damage or machines will break down.
In such a case the pre-drilling option will be used and if any steel pile is
deformed or damaged due to hard soil and failed ramming then this pile will be
pulled out and if the pile head is fixable then it will be fixed using special
rectification tool and will be galvanized using approved galvanization paint
otherwise this pile will be placed in damaged piles area. Once pre-drilling is
completed the diameter of the hole will be less than the dimension of post, the
hole will be back filled again with the soil removed during drilling and then
ramming of the post will be done as per design depths continually executing
the post installation work.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 21 of 28
Pre-drilling is required in hard areas and depends where the designer assign
the areas for pre-drilling, the hole is drilled using drilling machine with
compressor or drilling machine with Auger to make a hole less in diameter
than the cross sectional area of the pile, after drilling the hole is back filled with
natural sand and compaction is done and the last step is to perform the
ramming according to the design depth.
The micro piling machines and trained operators will only be used for this
work. In case of hard strata machines will be provided by air compressor of 25
bar to guarantee that sand will be completely flashed from the bore hole and
that the drilling tool is cooled due to high-speed rotation. Down to hall
hammers will be used to carry the drilling in hard strata. In case of soft strata,
the machine will be provided with auger plus concentric, and water pump will
be used to guarantee the execution of the drilling. After mixing water with soil,
mud will form to protect the inner wall of the hole, preventing soil from
collapsing into the hole.Once all functions of machines are checked, these will
be placed in the area of work and each of them will operate in the same
tracker area. Boreholes will be carried strictly in line with the drawing provide
following blue and red flags placed by the survey team. Each team is
composed of two workers: one machine operator and one helper. While the
operator is driving the machine to the required location, the helper will indicate
the exact point of drilling. The bit of the drilling rig shall, hence, be placed with
its own central axis in correspondence of the flag. On completion, the operator
will place the drilling tool on the ground and vertical of the column will be
guaranteed by means of digital level. Depth of the borehole will be checked
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 22 of 28
with a tape meter or with a graduated bar (in wood or metal material). Until the
pile is located in its place, all the holes will be barricaded, with cones, warning
tape or similar in order to warn about their presence. No workers related with
the task will be permitted to stay in the work area. It will be tried as far as
possible not to change the workers in each section. In case sand is not flashed
or in case sand collapse within the boreholes a cleaning procedure need to be
put in place. Cleaning will be carried by means of air compressor. Place the
hose of air compressor inside the borehole, fix the hose on the ground and set
the pressure at 5 bar. On competition, the compressor needs to be switched
off and the hose removed from the hole. It will be tried as far as possible not to
change the workers in each section. In case of the collapsing the bore hole will
be re-flashed.
Alignment
The installation should be carried in way to guarantee that all posts being part
of the same row should have same slope in N-S direction and should be
aligned in W-E direction. Professional rotating laser will be using for this
scope. Max slope allowed in direction N-S and max slope allowed in direction
W-E will be according to specifications in the Installation Manual. The
configuration of the laser will be done using the elevation data provided by the
surveyor. For each tracker, the survey team will take the elevation of at least 6
points. On competition, the data will be processed, and results uploaded on
the rotating laser. This method will guarantee that the tracker will have same
slope along the 2 axes.
Concrete Pouring
Once the alignment is performed, the concrete will be poured until the required
depth. A concrete funnel will facilitate the pouring of concrete and will
guarantee that the same does not come in contact with the surrounding sand
while ensuring that the concrete will not lose its properties and the sand does
not collapse within the borehole. In order to give the fresh conglomerate,
during its installation, compactness, homogeneity and density, such as to
guarantee the resistance required in the design the concrete will be vibrated.
In case of availability of ground water, while concreting, the ground water, mud
etc. will raise and flow out through top. Concrete will be poured till clean
concrete reaches top. Mix design of concrete provided by the Piling works
must comply with the characteristics required by the drawing. The concrete
bucket will be third party approved bucket and bucket will be locked with
SEPCO Electric Power Construction Corporation
DOCUMENT NAME SEP-WAD-CO-MS-0009
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 23 of 28
Telehandler forks using third party approved D-shackles and safety will be
ensured while pouring concrete that no worker is below the concrete bucket
and flag man should be provided with telehandler
10.0 INSPECTION-QA/QC
Materials should be reported to the owner after entering the site, and can shift
them into storage area only confirmation of owner. The pile foundation
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 24 of 28
In order to avoid influencing the project quality due to the lack of deep
understanding of drawings, the joint check-up shall be organized according to
the drawing design procedure before each activity starts.
All construction work and project management shall carry out quality education
before commencement, and make technical disclosure to all construction
worker, so as to improve quality awareness, implement the company's quality
policy and ensure the smooth realization of quality objectives.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 25 of 28
Strictly carry out the inspection and recheck during construction, and
consciously accept the technical guidance and quality supervision of the
owner and supervision engineer during construction. Measuring
instruments such as theodolite, level gauge and steel ruler used for
measuring and positioning shall be sent to the meteorological inspection
department to check their accuracy, and they can be used only after they
are qualified.
The fixed point of pile location, reference axis and leveling points in pile
foundation construction must be inspected and reviewed by the
construction unit or supervision unit before being used. No supervision unit
review records, shall not carry out any construction.
The technical department of the project intends to take charge of the unified
division of labor and assign special people to take charge of each working
procedure, formulate standardized management, strictly enforce the handover
system between working procedures, and ensure the working procedure
quality. During the construction, the self-inspection and mutual inspection
between working procedures should be perfected, and the next working
procedure should be checked to see if the previous working procedure is
qualified.
Final inspection shall be done using for each operation included document,
drawing.There are spaces in the required inspection points for Piling works to
reflect the acceptance of each transaction by signature and date. This IPP
works also as a registry and provides evidence of the various visual
inspections performed. Visual and dimensional checks listed in the ICL shall
be carried out.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 26 of 28
During the pile ramming, there might be some damages due to hammer
pressure and the pile heads need to be rectified.
Special tools recommended by PVH will be used to rectify the pile heads and
pile twists as shown below in figures.
After pile head is rectified for any bend or damage, approved zinc paint will be
applied on pile heads for galvanization and zinc paint can also be applied on
pile flange if there is any scratch while rectifying the twist in any pile as per
PVH Galvanization Repair Manual.
Pile paint coating should not be damaged, if coating is effected then apply
zinc paint approved by owner.
Pile head should not deform during ramming, if damaged then repair and
fix.
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 27 of 28
Electricity for on-site construction shall strictly comply with "one machine
and one gate". It is strictly forbidden to mix and match cables and wires,
drag them on the surface at will, and lay them buried or overhead in strict
accordance with the requirements. Set up warning signs on the surface of
buried wires.
On-site generator room and distribution box shall set up protective railings
in strict accordance with the requirements.
The on-site machinery and equipment shall promptly provide the relevant
responsible departments of the project department with the entry report
instructions, and clarify the identity information and operation certificates of
the equipment operators.
On-site materials are arranged neatly by division, name and type, and
warehouses will be temporarily set up for materials with special storage
requirements.
When the operator ascends the work platform more than 2m away from
the reference surface, he/she should wear the seat belt according to the
REV 00
METHOD STATEMENT FOR PILING WORK
PAGE 28 of 28
After the completion of the project, the construction waste shall be cleaned
up and disposed of in the designated waste yard according to the
classification, and on-site incineration is strictly prohibited.